Vous êtes sur la page 1sur 6

THYRISTOR TRACTION RECTIFIERS ENGINEERING AND HYPE

Tom Young
Director of Systems 8t Engineering
IMPulse NC, Inc.

Background that DC breakers are necessary, and


controllable rectifiers introduce a host of
Thyristor rectifiers are common in problems which have had t o be
industry in the United States and the addressed (usually successfully) in
world and have been for many years. industry for over twenty years. This is
Functions have included electrolysis, not to suggest that controllable
large drives (such as rolling mills and rectifiers do not provide advantages, it
hoists), and heating. These units range is just that they are not magic bullets.
from 1OOKW t o over 1OMW and have One transit authority in the United
been employed for the past 25 years in States made the decision to build a
large DC applications which required system based on controllable rectifiers.
voltage control. There are dozens of Some of the claims and compromises
manufacturers with extensive involved in that system will be used in
experience in manufacturing controllable the evaluations which1 follow.
rectifiers, and the technology is
thoroughly established. Hundreds of The first traction supplies were rotary
technical papers have been written units, which were usually compound
based on operation of these rectifiers wound. By design of the series winding
including their characteristics and their and active control aif the shunt field,
effect on plant and utility systems. inherent regulation and operational
Suddenly, the American transit industry regulation could be controlled over a
discovered "Thyristor Rectifiers" considerable range. General operating
(typically known as controlled rectifiers experience resulted in1 the selection of a
or SCR rectifiers in the United States) negative regulation curve of typically six
and, at least in the press, traction percent. This was dlictated by current
power engineering changed completely. sharing between units and system
Claims of lower energy costs, lower stability as well as fault current
capital costs increased spacing, lower limitation. Rotary units were replaced
maintenance costs, and even elimination by mercury rectifiers, and again the
of the need for DC circuit breakers regulation was chosen as typically six
usher in this "discovery". The facts are percent negative. It: should be noted
the cost is higher, the maintenance is that mercury rectifieirs are functionally
higher, the spacing is primarily driven by equivalent to SCR rectifiers - they are
other factors, there are many reasons operated by phase delay firing with

0 1996 IEEE
0-7803-3351-9/'96/%5.00

197
complete control. The hundreds of resistance characteristic (if the voltage
papers written on these units directly goes down, the current goes up),
apply t o SCR rectifiers except that the greatly complicating analysis of system
on voltage drop in a mercury tube is stability and making active system
typically 15 volts compared t o t w o volts control very difficult. Aside from
in an SCR. These papers treat of the system gain, decisions on other system
issues of power factor, line pollution parameters are not as straight forward
and harmonics, transformer heating, as they may seem. As stated earlier,
notching, and a major range of other the rectifier can be theoretically
considerations for operation of these designed t o have flat regulation t o any
units. It is against this back drop that load; however, there are significant
the projections of advertisements, negative trade offs.
technical presentations, and simulations
need t o be evaluated. The transformer size must be increased
not only t o raise voltage t o place the
Regulation inherent regulation curve so that it
intersects the design voltage a t the
In theory, an SCR rectifier can be maximum controlled voltage load, but
designed t o produce a flat (zero also t o allow for the heating caused by
regulation) curve from no load t o five increased K factor associated with the
hundred percent load. Most units built firing phase delay. This results in
for electrolysis and plating are, in fact, increased losses at load, and also
designed t o produce a set voltage increases the no load loss, which is a
regardless of load. This is possible for a major energy use in traction units. Also
fixed or very slowly changing load the higher the load of the transition
because stability can be maintained with voltage chosen, the longer the firing
very high gain. When this type of delay at most operating conditions.
control system is applied t o varying and This results in a reduction of power
especially unpredictable loads, instability factor and an increase in harmonics
can and usually does occur. This sets a during most of the unit's operating time.
minimum regulation (maximum gain) a t This can be put in perspective by
which stable operation can be achieved, observing the operating parameters
probably 2-3 percent in a traction power during the design stages of a system.
system. This also depends on the Figure 1 shows the original (as
propulsion algorithm (almost all are now advertised) intent of the specification -
actively controlled systems). Typical the break point and inherent slope are
loads are controlled by an acceleration -
speculation but the curve shown was
driven control loop, meaning that a t a used t o demonstrate that "the 100 volt
location where distribution drop is ...
gain a t 200% full load current would
significant, they produce a negative allow a further 2/3 mile of OCS t o be

198
supplied and still achieve the same The regulation issue just discussed
voltage at the pantograph as that drives the justification for regulated
obtained with a SDR". Super imposed rectifiers. The argument is that
on this graph is the (as delivered) regulated units greatly extend the
regulation curve of the units after the distance between sulbstations. In most
design stage. The 100 volt gain at conventional systems (especially light
200% has slipped t o less than 50, and rail systems), the total voltage drop to
the 450% operating capability the pantograph is 60 t o 90%
requirement (a very significant distribution drop, ancl it would probably
requirement for contingency operation be more economical t o provide spacing
with large AC drive vehicles especially extension through improvements in that
at extended spacing) has apparently drop. Aside from drop, there are other
been lost. limitations which cannot be ignored.
With extended spaciing, fault detection
The regulation change reflects becomes a very 1imit:ing factor and we
appropriate analysis of the loss, power have a number of systems operating
factor and harmonic penalties today with no ability t o detect remote
associated with the large firing angle f auIts. Also about 1/3 of the
delays required for a large voltage distribution drop is in the rail return, and
reduction. The original curve would rail voltage (which is vehicle voltage) is
provide a power factor of about 75% a t another limiting factor.
50% load, the final curve would result
in around 85% at 50% load and almost Energy Savings
95% (the same as an unregulated
rectifier) at overloads. This makes It is not obvious that a unit that has
engineering sense, but perhaps should lower efficiency and power factor would
prompt reassessment of the advantages be justified on the basis of energy
postulated in the original system savings. The basis of this claim is
concept. As shown, the projection of savings on demand lcharges, and it is
the inherent regulation curve would true that in most traction power
result in an open circuit voltage of 900 systems the demand charge exceeds the
volts with an unregulated rectifier on energy cost. The 'theory is that by
the same transformer, very close t o "chasing the demand meter" load can
meeting the systems maximum voltage. be shifted t o underloaded stations by
Another curve appears on Figure 1 altering the voltage 01 adjacent stations.
showing the curve of a low regulation Certainly, this can be accomplished t o
rectifier. This will be discussed further some extent, but it is neither as easy
in the alternatives section of this paper. nor as predictable as it might appear.
Systems are normally carefully designed
t o provide uniform loading on average

199
and demand peaks almost always occur line pollution. These double bridge units
during rush hour, when headway's are are used in large drives and hoists in
short and loading is uniform. Also, to industry and have evolved t o be in fairly
make this system work will require a common use. They are, however,
dynamic interface with the vehicles, expensive , are generally slaved t o a
relative t o both the current voltage single load to minimize dynamic and
characteristics and scheduling. This will transient problems, and normally have a
be discussed further in the alternatives very high speed breaker in the reverse
section of this paper. bridge to prevent major damage when
an SCR mis-trigger causes a interbridge
DC Circuit Breakers fault. Although there is a lot of work t o
be done to make such a system
The claim of eliminating DC circuit workable under the dynamic conditions
breakers by using controllable rectifiers of a distributed traction power system,
deserves little discussion. Even if you regeneration reception would appear to
could detect an overload and turn off be worth the development of this or
the voltage, no operating authority some alternate system.
would turn off all outgoing circuits
because of an overload on one. Keeping Alternatives
all clear circuits alive is always critical t o
operation. This is without even Before making a decision t o use SCR
addressing the problems of remote fault rectifiers with the unknowns involved, a
detection. critical analysis should be undertaken
using achievable performance figures,
Reaeneration and alternatives should be evaluated.
Conventional diode rectifiers are well
In intracity transit systems, a large proven and well behaved. Their
percentage of the energy delivered to operation and reliability are very well
the vehicles is turned into heat in demonstrated in United States transit
braking. Efficient recovery of the systems. This is very different from
braking energy could provide a operation in many other countries where
significant reduction in energy costs. maintenance procedures and personnel
Rotary units of fifty years ago could put are vastly different and operations may
this energy back into t h e AC line, but at be by very different rules.
that time, the propulsion technology
was not available for the vehicles. As previously stated, rectifiers are
Conventional rectifiers cannot convert historically chosen t o have an inherent
this energy, but "four quadrant" regulation of six percent for system
controllable rectifiers can, albeit with stability and sharing and t o limit fault
large questions in reliability and power current. Rectifier systems can be

200
designed down t o about t w o to two and full performance with a rectifier out of
one half percent regulation with very service. By literally turning off the high
little problem. Especially in light rail, a demand unit for a short time with
coupled twelve pulse system can equipment already in place, this function
provide three percent inherent regulation could be accomplished nicely.
to over 300% load while holding fault
current well within the capabilities of If any area should be targeted for any of
light rail breakers as defined by ANSI. these functions, the most fruitful area
The curve of such a rectifier is included would have t o be the! vehicle propulsion
in Figure 1 and shows improved voltage systems. The curve! programmed into
through the meaningful range. The these systems can define the spacing,
spacing becomes limited by fault the demand, and even help considerably
detection and return voltage, not the with regeneration. This could even be
rectifier, in any case. Sizing the extended to having these systems
catenary larger would provide similar programmable by operations even by
spacing at lower cost (this has been remote control. We have already paid a
demonstrated by composite third rail) tremendous amount of money t o buy
while improving fault detection these systems which are fully
capability. There is no obvious reason electronically controllable in both
to use SCR rectifiers t o increase acceleration and braking modes, and we
spacing. could use them very much to our
advantage.
Receptivity to regeneration is a different
issue. Conceivably this capability alone
could justify SCR four quadrant References
rectifiers. Other alternatives, however,
should also be considered for this Standard Handbook: for Electrical
function. Specifically, the stored energy Engineers, Seventh Edition, 1941,
necessary t o handle the braking energy Section 9, "Rectifiers and Convertors",
from one vehicle t o the next is relatively McGraw Hill.
small, and battery storage on the DC
side should certainly be considered. Standard Handbook. for Electrical
Battery banks which would undergo Engineers, Eleventh Edition, 1978,
minimal cycling could be quite cost Section 13, "Power Electronics",
effective and could also reduce catenary McGraw Hill.
requirements rather than increase them.
"The Use of Thyristor Controlled
This brings us to chasing the demand Rectifiers for the DART System", Eric
meter. Almost all light rail systems Scotson, APTA Rapid Transit
have the capability t o operate a t almost Conference, 1995.

20 1
ADVERTISED
=-I
DELIVERED

100 200 300 400 500 AMPS


(X FULL LOAD)

FIG. I

202

Vous aimerez peut-être aussi