Académique Documents
Professionnel Documents
Culture Documents
Mediation Form
1) This is a form of negotiation between the parties with the intervention
of a neutral third party, the mediator.
2) This mediator takes the parties through the process, listening to their
respective cases sometimes together, sometimes on their own with a
view to guiding them towards a settlement of their own making.
3) If one party fails to honor the terms of the settlement agreement the
only course of action open to the non-defaulting party is to sue on that
agreement,
1) Instituted a court case against Siemens Pvt, for the payment of a sum
of Birr 420,000, dated………………(420,000 which inludes interim
payment and additonal exceted works not payed under the previous
installations)
2) The court issued ruling order to Siemens on ………….. Through a three
man mediators representing each parties. The third and chair mediator
will be chosen the other two. The nominated mediators
are..................................)
Conclusion
Initial Claim by Siemens and The Contracting parties have been thorouly
investigated acording to the Contract agreement signed, technical
specification and drawings submitted to the parties.
Accordingly, both parties have agreed that, after signing of this Settlement
Agreement Wale to have no other claims out of or in connection with the
subcontrsct Agreement or any right to institute a case against Siemens Pvt in
this matter.
This Settlement Agreement shall enter into force on the date it is signed by
the duly representative of the parties to this agreement and it is signed in
three originals.
In witness thereof the parties have affixed their signatures hereinunder in the
presence of witness.
Date: Date:
__________________ ________________________
Witness
1.
2.
3.
Claims by Siemens and Wale Initial Claims Accepted Dropped WALLE'S Initial COMMENT Final Response
1
. Transformer 150W lost for APH 2,3 2,38 - OK, but handover document if Siemens can verify by the receiving
2 Mast(no1@2378.0 birr each) 87.68 7.68 where? document Wale pays
2 Rectification work for APH lights 1) Ato Getachew fixed the bulbs where beforehand WALA
. 300m barrette 07(300metres @ 9 aligned the light REH so why? 2) who finally did the job?
3 LS ) 48.45 948.45 what is this? Siemens dropped the Case d
5,97 Siemens and Wale agreed to call a meeting and get the
1 cost of additional sand and gravel 5,970.00 0.00 check letter final approval
4 Others
Share of liquidated damage if any until now EAE has not booked any claim if so
4 by EAE if any as per the sub contract agreement
-
1 273,732.3
2 Payments 1st payment 0 OK
-
400,000.0
2nd payment 0 OK