Vous êtes sur la page 1sur 6

WELDING GUIDELINES FOR DESIGN ENGINEERS

The following guidelines sourced from Ref 1 are provided to (2) Do not specify oversize welds
allow professional Engineers to specify the correct and
appropriate weldments for steel structures used in building The most cost effective weld is the smallest weld that
applications to not only satisfy service performance but also provides the required strength. It is good weld design
achieve cost effectiveness. practice to provide only that amount of welding which
ensures that the welded fabrication can perform its intended
ECONOMICAL DESIGN AND DETAILING function.

Usually a variety of alternative methods of achieving Specifying oversize welds may be harmful in two ways.
adequate structural performance are available and the cost Firstly, the cost is unnecessarily increased and secondly,
aspects of the alternatives must be considered. oversize welds may cause increased shrinkage which may
The principal considerations in economical detailing of lead to distortion.
weldments are:
Key Reference Standards
(a) Simplicity - details of welded attachments and details of AS 4100 – 1998, Steel Provides details on weld
end connections should be simple and consist of the fewest Structures (Ref 4) capacities, fabrication and
possible number of component parts erection tolerances etc.
(b) Weld volume - only the minimum required weld AS/NZS 1554.1 – Provides details on weld
volume, as determined by structural calculations should be 1995, Structural Steel categories, consumables,
Welding Code, Part 1: parent materials, inspection and
specified Welding of Steel process procedures etc.
(c) Accessibility - welding electrodes must be able to be Structures (Ref 5)
positioned in such a way that good quality welding can
achieved without difficulty and without undue strain on the As an example, an 8 mm fillet is only 33% stronger than a 6
operator mm fillet, yet the volume of weld metal is 78% greater.
(d) Erection - proper detailing should allow for reasonable Thus, the cost of production of a joint can be significantly
fit-up tolerances and weld preparations increased, not only due to the increased volume of weld
(e) Inspection - all welds should be located in positions so metal required but more importantly due to the increased
that visual examination and/or nondestructive testing can be time in welding the joint. Not specifying oversize welds has
carried out easily to be balanced by the need to rationalise the range of weld
sizes on a project as noted in rule (15).
Weld Categories (specified by AS/NZS 1554)
Category GP • Generally intended for use in joints (3) Use welding judiciously when using it to reduce
General which are statically loaded, and where material mass
Purpose the design load on the weld is
significantly below its ultimate capacity If welding is used to reduce the amount of material (e.g. by
(Capacity factor of 0.6 from table 3.4 of splicing to change flange plate thicknesses or to provide
AS 4100 – 1998).
stiffeners to a thin web in a three plate girder), then be sure
• Lower inspection levels and a higher
permissible level of welding defects is the cost of the welding is less than the cost saving in
permitted for GP welds when compared material cost. Weld metal costs many times more than
to SP welds. parent material (somewhere from 50 to 100 times), and it is
Category SP • Has tighter constraints on permissible often cheaper to increase component mass so as to reduce
Structural level of welding defects and higher weld metal volume.
Purpose inspection levels than GP welds.
• A higher load carrying capacity is (4) Keep the number of pieces to be welded to the
permitted by AS 4100 due to the minimum practicable
increased confidence in the weld
quality ( Capacity factors range from A simple design with the fewest number of pieces is the
0.7 to 0.9 from table 3.4 of AS 4100 -
1998). most economic and often results in a better product.
• Generally selected where the weld is
subject to dynamic loading within the (5) Remember the special effects of welding such as
limits specified in Clause 1.1 of distortion (Ref 3)
AS/NZS 1554.1 – 1995.
(6) Aim for as much fabrication to occur in the
The following rules are suggested, as basic to economical workshop as possible
weld design and detailing (see also Refs 2 and 3).
(7) Keep in mind the economics of fillet welding
(1) Design with welding in mind
Single pass fillet welds are usually limited to 8 mm leg size
This requires an appreciation of the cost components in for most processes, although with other processes, under
welding, the types of weld available, the types of processes certain conditions, a 10 mm or larger single pass fillet weld
and procedures available and their limitations. is possible. Before specifying large fillet welds, the
situation should be checked with the fabricator. Larger (9) Use fillet welds in preference to butt welds wherever
single pass fillet welds can be placed in the flat natural vee possible
position. If more than a single pass is required, the cost of
the weld increases significantly. Single run continuous fillet Butt welds usually involve edge preparation, which adds to
welds are usually more economic than intermittent fillet costs, and as a result fillet welds are cheaper than butt welds
welds of a larger size. up to about 16 mm thickness of connected plates. (Other
considerations, such as joints which may be subjected to
Weld Costs fatigue, may dictate the use of a butt weld in preference to a
less costly fillet weld).
Continuous Fillet Welds
(CFW) (10) Provide adequate access
Leg size Hours/m $/m
(t w) mm Another way the designer can significantly help productivity
6 0.3 12 is to ensure adequate access for welding. This is vital, as it
8 0.7 28 is essential to ensure always that the appropriate quality of
10 1.0 40 weld can be made. Examples of bad accessibility together
12 1.3 52 with suggested improvements are shown in Fig 1.
15 2.0 80

Butt Welds
Plate Complete Penetration Incomplete Penetration
Thickness Butt Welds (CPBW) Butt Welds (IPBW)
(t)
mm Hours/m $/m Hours/m $/m
12 1.7 68
16 2.9 116
20 3.5 140 2.9 116
25 5.6 224 3.5 140
28 7.1 284 4.4 176
32 9.2 366 5.0 198
40 13.4 536 6.5 260
45 16.0 640 7.6 304
50 19.9 796 9.1 364
Notes:
1. All welds are SP and < 250 mm in length, butt welds are
single V shape, IPBW depth of penetration is 0.5t, plate edge
preparation is included in the cost, costs are based on an hourly
rate of $40 which includes overheads, consumables and Fig 1 Some common detailing faults resulting in poor
fabricator’s margin for medium sized steel projects accessibility for welding

2. Multiplying factors to above costs, depending on access:


(11) Consider the method of fabrication
Site welding: 1.3
Overhead welding: 1.5
Vertically welding: 1.2 Allow welds to be made in the downhand position wherever
Grinding welds flush: 0.4 hrs/m = $16/m practicable. This can often be achieved by the fabricator
using special jigs and positioners.
3. The above information is sourced from Ref 6
(12) Avoid dictating the manner of making a welded
joint to allow welding to be used to maximum advantage
(8) Keep in mind the cost of butt welding
The fabricator knows the best joint preparation and welding
Complete penetration welds need only be specified when procedure for ease, economy and quality of joint using the
they are really required, and the use of partial penetration facilities available. Ensuring the method of fabrication is
welds can reduce weld metal and give other gains which add acceptable, can be achieved by calling for compliance with a
up to an improvement in productivity. If complete recognised Code or Standard (AS/NZS 1554) and requiring
penetration welds are demanded, the use of backing bars the proposed fabrication and welding procedure to be
with welds from one side which do not need back gouging submitted for concurrence on important jobs.
or turning of the work piece may lead to improvement.
(13) Be receptive to alternative proposals
If selecting joint preparations, use prequalified preparations
(AS/NZS 1554) to avoid qualification testing. Recognise the value of consultation with the fabricator and
be prepared to accept alternative welded joints/details
Select the smallest included angle consistent with achieving proposed by the fabricator which have clear advantages.
the desired penetration. Better still, specify only, say, This particularly applies to allowing the fabricator to take
‘complete penetration butt weld’ (or specify acceptable advantage of high production processes. The design of a
alternative details) on the drawing and allow the fabricator weldment can often restrict the fabricator to only the one
to select the method he can do best and most economically. process, and this may not always be the most suitable.
(14) Use a minimum number of joints by: (17) Use non-destructive testing judiciously

(a) Using the largest size of plate/section available The use of non-destructive testing of welds is very
consistent with the functional requirements disruptive to the work flow and adds considerably to the
(b) Bending or forming in place of welding (Fig 2) cost of a structure. Much of this cost will be avoided if non-
(c) Considering the use of castings, forgings in lieu of destructive testing is restricted to critical joints and carried
complex welded joints out on a random basis only after careful development of
(d) Avoiding excessive detail to reduce parent metal mass - weld procedures. Modern welding Codes encourage this
see rule (3) and Fig 3 approach.

Fig 3 Beam flange with many different plate thicknesses –


avoid when steel mass saved is less than 100 times
mass of weld metal required

Fig 2 Use of bending to reduce welding and give clean


corners (18) Test only where required

(15) Standardise joint details as much as practicable to Testing of welders and weld procedures for each job is
reduce variety expensive. Where practicable, consideration should be given
to accepting welders and procedures approved by recognised
Different sized welds at a joint will require changes in authorities for other similar work.
current and electrode size by the operator. This causes lost
time and a drop in operating efficiency. Aim to have the (19) Specify weld quality consistent with service
minimum variety of weld sizes and types on a member or at requirements
a joint.
Fitness for purpose should be the guiding rule in specifying
Key Weld Attributes weld quality. Higher quality specified unnecessarily for its
Continuous • Commonly specified by leg length – 4, 5, 6, own sake is wasteful and costly (see “Example Welding
Fillet Weld 8, and 10 mm fillets common. Specification” on page 4).
(CFW) • Design based on weld throat thickness and
length Specify tolerance limits consistent with the purpose of the
• Usually triangular profile with plate on each weld. Adequate tolerances are necessary in order to allow
side. No plate preparation necessary. for ease of fit-up.
• 6 mm fillet welds were traditional minimum
weld size for manual stick electrode welding.
Modern methods enable smaller welds to be
produced by smaller diameter wire
electrodes.
Complete • Weld penetrates the complete depth of the
Penetration plate(s) being connected
Butt Weld • Used where the full strength of the connected
(CPBW) parts is required.
• Plates are generally prepared before welding
unlike when fillet welds are used, which
leads to increased fabrication costs.
• Standard practice is not to specify the weld
geometry on the drawings – leave this for the
Fig 4 Angle seat detail – (a) preferable to (b)
fabricator in accordance with AS/NZS
1554.1
Incomplete • Weld does not penetrate the complete depth
Penetration of the plates being connected. (20) Avoid, as far as practicable, requiring turning of
Butt Weld • Used when less than the full strength of the members on to other side
(IPBW) connected parts is required, such as in low
stress areas. Examples are:
• Less costly than CPBW due to reduced plate
preparation & time. (a) Avoid putting stiffeners on both sides of a plate girder
web
(16) Use sub-assemblies to give: (b) Truss detailing which requires one side welding only
(c) Angle seat to column flange connections - a narrow seat
(a) Easier handling and positioning for downhand welding in lieu of a wide seat avoids turning the member (see Fig 4)
(b) Better access for welding
(c) Less site welding and more shop welding
(21) Avoid joints which create difficult welding is not usually necessary to depart from them unless very
procedures good reasons exist.

Joints which create difficult welding procedures. such as Where welding is specified in accordance with an Australian
two round bars side by side, acute angle intersections, etc., Standard it should be the one relevant to the service
should be avoided. Such welds prove time consuming and conditions, e.g., specifying pressure vessel standards for a
are of questionable quality (see Fig 5). Such joints also multistorey office building is poor design. Fitness for
cause difficulties with any post-weld treatments, service should be the sole criterion for the quality level
(deslagging. brushing, grinding and corrosion protection). specified and for the specification of the appropriate levels
of inspection. Any departure from normal levels is likely to
increase costs and should be called for only when really
required.

WELDING INSPECTION

Fabrication costs are very sensitive to the required weld


quality and the type and standard of inspection. It rests with
Fig 5 These joints are difficult to weld and the welds may be the design engineer to determine the critical areas of a
of questionable quality structure requiring close inspection and then to set a realistic
standard for the inspector to follow (eg Ref 7). In setting
(22) Consult Ec onomic Design of Weldments (Ref 2) for guidelines for the inspector, the best results are achieved by
further advice on ways to use welding effectively and nominating the use of the Structural Steel Welding Code,
economically AS/NZS 1554. This Standard is well understood by both
fabricators and inspection organisations and usually results
in a good job being achieved at a reasonable cost. A
WELDING SPECIFICATIONS confusing and often expensive practice sometimes adopted
is to rewrite some existing Standard clauses into the
It is essential that the drawings and specifications detail the specification in an attempt to achieve a higher standard than
functional requirements of the design clearly and concisely that provided by the Standard. This should be avoided
but avoid needless over-detailing or over specification of because it usually leads to anomalies, and contractual
items which are better left to the fabricator or erector. It is problems. Fitness for purpose should be the rule in setting
advisable to avoid generalising with such items as ‘no inspection standards and AS/NZS 1554 provides realistic
under cutting permitted’ or ‘all welds to be smooth and levels of both workmanship and inspection suited
free from defects’ or 'weld all round' as these all too often specifically for various weld quality levels required in
lead to confusion, and extra cost. structural fabrication.

Example Welding Specification REFERENCES:


(from AISC Steel Construction Journal Vol 29, No 3,
1 Economical Structural Steelwork, fourth edition, AISC, 1997
Sept 1995) appropriate for inclusion in engineering 2 Economic Design of Weldments, AWRA Technical Note 8,
drawings of structural steelwork for small to medium March 1979
sized building structures 3 Twelve Commandments to Design Engineers, Blodgett,
O.W., reprinted in AISC Steel Fabrication Journal Nos 9, 10
& 11, Nov 1973/May 1974.
“Welding to be carried out in accordance with AS/NZS 4 AS 4100 – 1998, Steel Structures
1554.1. Welding consumables to be E48XX or W50X 5 AS/NZS 1554.1 – 1995, Welding of Steel Structures
6 Costing of Steelwork from Feasibility through to
U.N.O. All welds to be 6 mm CFW SP category U.N.O.
Completion, Steel Construction Journal, AISC, Vol 30, No 2,
CPBW to be SP category U.N.O. June 1996
7 Commentary on the Structural Steel Welding Standard
Inspection to be carried out to AS/NZS 1554.1. All AS/NZS 1554, WTIA/AISC TN 11-98
GP/SP welds to be 100% visually scanned. SP welds
allow for ………… % visual examination U.N.O.” SUGGESTED FURTHER READING:

Flexibility in the approach to design is particularly 1 AS/NZS 1554.4 – 1995, Welding of High Strength Quenched
and Tempered Steels
important in considering proposals for alternative welding
2 AS/NZS 1554.5 – 1995, Welding of Steel Structures Subject
details or procedures. The fabricator or erector may have to High Levels of Fatigue Loading
alternative methods to improve productivity and reduce 3 Welding, Brazing and Cutting of Metals – Glossary of
costs and these should not necessarily be excluded by a rigid Terms, AS 2812 – 1985
specification. If tendering is involved, prices for the tender 4 Graphical Symbols for General Engineering, Part 3:
specification and for viable alternatives could be useful. Welding and Non-destructive Examination, AS 1101.3 –
1987
It is generally quite sufficient to nominate only the
functional requirements plus compliance with an appropriate AISC Head Office
welding code, such as AS/NZS 1554, for satisfactory results. Level 13, 99 Mount Street, North Sydney NSW 2060
Standards are prepared for use as reference documents and it Ph: (02) 9929 6666 Fax: (02) 9955 5406
E-mail: enquiries@aisc.com.au Web: www.aisc.com.au

Vous aimerez peut-être aussi