Project:
Nottingham Light Rail Transit system
Phase 2
Scope:
> Turnkey project management
> Integration of civil works
> Rolling stock (CITADIS™ 302)
> Power supply
> Track works
> Communication Systems
> Railway Signaling
> Depot works
THE CONTEXT
Entry into revenue service: December 2014 The Tramlink Nottingham Consortium, of which ALSTOM is a member, was awarded the
Contract start date: December 2011 Nottingham Express Transit 2 contract on 15 December 2011. It is a turnkey project,
Design and Construction: 2012-2014 providing Alstom with a new platform from which to build their infrastructure activity in
the UK. Drawing on our expertise in infrastructure and turnkey projects, a tight 36-month
design and construction programme is underway to deliver two new lines and install power
and signalling, extending the existing network by 17.5 km. Track laying will include the use
of APPITRACK™ which recently received an award in the UK for new technology. ALSTOM
will also design and install the power supply and signalling systems. Existing trams and
track will be upgraded in preparation for new signalling to be adopted, which will be
common to the two new lines, and the maintenance depot will be significantly extended in
time for the arrival of the new CITADIS™ trams before the end of 2013. Passenger services
across the whole of the expanded tram network are planned to be fully operational by the
end of 2014.
ALSTOM SOLUTIONS
> Turnkey tramway: ALSTOM’s integration of products & systems to create an
optimized tramway solution
> CITADIS™, ALSTOM’s full low-floor tram
> APPITRACK™, ALSTOM’s technology for faster track laying and reduced impact on
the environment
HIGHLIGHTS
st THE BENEFITS
1 use of CITADIS™ tram in the UK
Use of the innovative APPITRACK™ > The two new tram lines will provide access to some 1270 workplaces and
Turnkey project accommodate 55,000 commuters. The completed system will serve 20 of the 30
Short-delivery programme largest employees in Nottingham who will be within 800 metres of a tram stop.
> The scheme will encourage economic growth by providing valuable infrastructure
and will act as a catalyst to further inward investment.
Alstom Transport
48, rue Albert Dhalenne
93482 Saint-Ouen Cedex France
www.alstom.com/transport
The Customer: Nottingham City Council
The Solution: Turnkey tramway system
DETAILED SCOPE
KEY FEATURES
Line length 17.5km double track over 2 lines
Number of CITADIS™ trains 22 x 302 – 2.4m wide, 16 trams per
hour per direction
Number of passenger stations 29
Substations 9
APPITRACK™ track-laying technology Signalling Line of sight and driver route control
Power Supply 750 VDC
TRANS/CustRef/AT.TGS.NCC,NottinghamTramway/eng/07.12/FR © - ALSTOM 2012. ALSTOM, CITADIS, APPITRACK, the ALSTOM logo and any alternative version thereof are trademarks and service marks of ALSTOM.
The other names mentioned, registered or not, are the property of their respective companies. The technical and other data contained in this document is provided for information only. Neither ALSTOM, its officers and
employees accept responsibility for or should be taken as making any representation or warranty (whether express or implied) as to the accuracy or completeness of such data or the achievement of any projected performance
criteria where these are indicated. ALSTOM reserves the right to revise or change this data at any time without further notice. Photo Credits: ©ALSTOM Transport/Design & Styling.