Académique Documents
Professionnel Documents
Culture Documents
Publication #420
Although great care has been taken to provide accurate and current information, neither the author(s) nor the publisher, nor anyone
else associated with this publication, shall be liable for any loss, damage or liability directly or indirectly caused or alleged to be caused
by this book. e material contained herein is not intended to provide specifi c advice or recommendations for any specifi c situation.
Any opinions expressed by the author(s) are not necessarily those of NADCA.
Trademark notice: Product or corporate names may be trademarks or registered trademarks and are used only for identifi cation and
explanation without intent to infringe nor endorse the product or corporation.
à 2006 by North American Die Casting Association, Wheeling, Illinois. All Rights Reserved.
Neither this book nor any part may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photo
copying, microfi lming, and recording, or by any information storage and retrieval system, without permission in writing form the publisher.
CHAP T E R
Preface
This text has been created by editing the original materials created by
Mr. Wayne Alofs as the course presentation and hand out materials for the
NADCA course on Process Control. The decision was made to separate the
materials in the Process Control course into two courses, Process Control
and Machine Systems. It was recognized that the two subjects are tightly
related, but the combined subject material is too much for the NADCA
course format to present as a single subject, and that the machine systems
subject matter is background information for several other branches of
study. For example, this two day Machine Systems course should be con-
sidered as prerequisite for further study in Process Control and all aspects
of Machine Maintenance (i.e. mechanical, hydraulic and electrical). The
material in this course/text is also essential information when one speci-
À es a die casting machine for purchase, evaluates various machine's for
possible purchase and/or installs a new machine. One should also have
a good understanding of the machine systems and their functions when
designing dies. This text provides one of the major cornerstones of the
NADCA Education Program.
A special thank you goes to IdraPrince for their support in the develop-
ment of this book.
iii
CHAPTER
Table of Contents
Chapter 1 -- Introduction ...................................................................... 1
v
CHAP T E R
ONE
INTRODUCTION
The die casting machine provides the energy 1. The Clamp System
and the motions required to operate the die and
2. The Ejection System
to make the castings. These functions are:
3. The Metal Injection (i.e. "Shot") System
1. Open the die so the casting can be removed
These systems are described in this text
2. Operate the ejection of the casting from the die
along with instructions for their proper adjust-
3. Interface with the controls of the ancillary equip- ments. Also included are descriptions of how
ment that removes the casting and sprays the the dies must be properly sized to the machine,
release material on the die how to measure the machine's performance
capabilities and at the end of the book is a sum-
4. Close the die
mary of preventive maintenance measures that
5. Clamp the die closed with sufÀ cient force to with- should be followed to insure continuing high
stand the pressure of the injected molten metal performance of the machine.
6. Interface with the controls of the equipment that
ladles the molten metal into the die casting machine Die casting machines are somewhat unusual
in that the metal injection (i.e. "shot") systems
7. Inject the molten metal into the die
use accumulator hydraulic circuits. Accumu-
8. Apply pressure on the molten metal as it solidiÀ es lator hydraulic circuits are hydrodynamic
systems whereas most hydraulic circuits are
The die casting machine consists of three hydrostatic systems. Therefore, some special
basic mechanical systems (plus the machine understanding of accumulator circuits is re-
controls) to accomplish these tasks. These are:
Chapte r 1 Int roduct ion
quired for understanding the dynamics of the and 1-4. The shot systems are attached to the
shot systems of die casting machines including "Front Plate" and are shown attached to the
2
the meaning of the PV and PQ 2 diagrams of right hand side of the front plate in Figures
the injection power performance curves. For 1-1- and 1-2.
that reason, a chapter is included on accumula-
tor hydraulic systems.
Clamp System
This course is designed to provide a basic
understanding of the die casting machine and The clamp system includes the three platens (i.e.
how it works to Operating Technicians, Die the front plate, traveling plate and the back plate),
Casting Technicians, Die Casting Engineers, the four tie bars, closing cylinder, toggle linkage
Tooling Engineers and Maintenance personnel. and safety bar as shown in Figures 1-1 and 1-2.
Traveling Plate
Shot Accumulator NitrogenTank
Tie Bar
machine were to be permanently submerged in Safety Bar
A-Frame
the bath of molten metal. The hot chamber ma- Back Plate
Plunger Coupler
Closing Cylinder
chines are used for casting those alloys (such as Plunger
2
Chapte r 1 Int roduct ion
4
CHAP T E R
TWO
CLAMPING SYSTEM
The die casting machine clamp system provides deÁ ect, the other components of the machine.
the following functions: The action of the linkage and the resulting
stresses imposed on the machine and die com-
1. Open and close the die ponents are illustrated in Figure 2-1 for both
2. Hydraulic power for moving cores in the die the threaded and the threadless style of tie bar
construction.
3. Hydraulic or mechanical actuation of the ejection
A threadless tie bar stretches the tie bar over
4. Hold the die closed against the opening forces
from the injected molten metal the entire length of the tie bar. That has the
advantage that the same amount of stretching
The opening and closing of the die is generates the same amount of force regardless
achieved by the closing hydraulic cylinder (see of the thickness of the die. The treaded style
À gure 1-1) actuating the [toggle] linkage to of tie bar results in the stretched part of the
move the traveling plate. tie bar changing when dies of different thick-
nesses are set in the machine. So, the same
amount of stretching will result in a different
Clamping Force stress (clamping force) for different thicknesses
of dies. However, these stretching-force differ-
The die clamping force is generated through the ences are relatively small.
mechanical advantage of the linkage multiply-
ing the force of the closing cylinder to elastically Tie bar load indicators are used to measure
stretch the tie bars and to compress, or otherwise the amount of stretch over a À xed portion of the
Chapte r 2 Clamping System
A B b
REGENERATIVE
CLOSING SHUTOFF
P T
Tensile Stress
SLOW ADJUST
A
OPEN a A B b
Compressive Stress
Locking Force
b b b b
6
Clamping System Chapte r 2
Tie bars must be oiled to protect then Figure 2-4 A manual tie bar pulling device is
from rusting and be maintained to be free of a ring that clamps to the tie bar at the traveling
scratched and dents. Detailed maintenance platen. The when the traveling platen is moved,
the tie bar moves with it.
7
Chapte r 2 Clamping System
To reinstall the tie bar the procedure is the machine) they push the back plate for-
reversed. Before reinstalling the tie bar all tie ward and reduce the die space. When rotated
bar and front plate surfaces must be clean and counterclockwise they move the back plate
lubricated with a high temperature grease. rearward and increase the die space. The nuts
must have a running clearance between the
The die height adjustment (if motorized) back plate and the back retainer to allow the
must not be operated while the tie bar is dis- nut to rotate.
connected from the front and/or back plates.
If the machine is equipped with a motorized
die height system, the tie bar nuts are driven
Die Height Adjustment by a large bull gear as shown in Figure 2-5.
Some machines use 90 degree drives at the tie
The die height adjustment system adjusts the bar nuts with drive shafts between them. The
space between the front and traveling platens bull gear or the drive shafts are powered by
to accommodate the thickness of the die. This either an electric motor or a hydraulic motor
adjustment is accomplished by moving both the through gear reducers.
traveling and back plates along with the link-
age and ejector system along the tie bars. The Some machines have the ability to adjust
same adjustment is used to set the locking ton- a single tie bar with the die height adjuster.
nage of the machine. These have a spur gear between the bull gear
and the tie bar nut. These spur gears can be
The adjustment is made by rotating the disengaged by sliding them out of contact with
tie bar nuts at the back plate on the tie bar the bull gear with a hydraulic cylinder. Then
threads (or the sleeve threads if it is a thread- when the bull gear is turned one gear tooth,
less tie bar) when the machine is open and three tie bars are adjusted, and one is not. One
the tie bars are not stressed. When the nuts such system is illustrated in Figure 2-6.
are rotated clockwise (viewed from the rear of
Figure 2-5 Shown here is one type of me- The measurement can be used to calculate
chanical die height adjustment system where the
the tonnage force to which the tie bar has been
individual tie bar nuts are rotated by a single bull
stressed. The total locking force for the ma-
gear. The bull gear is turned by an electric or hy-
draulic motor and gear reducer. Image labels: 1)
chine is the total tonnage of the four tie bars.
Rulon Bearing, 2) Bull Gear, 3) Hydraulic Motor The tie bar force is calculated by:
& Speed Reducer, and 4) Bronze Gear Nut.
8
Clamping System Chapte r 2
F = (IR x CSA x Mod.)/(LM) Dial Indicator Mounting Bracket Indicator Rod Sleeve
Where:
Figure 2-8 The installation of the dial in-
F = Force in pounds dicator on a threaded tie bar is similar to that
IR = Indicator reading in inches (to the fourth deci- shown Figure 2-7 for a treadless tie bar. The dif-
mal place) ference is that the 0.75 inch diameter hole and
CSA = Cross sectional area of the tie bar in square the indicator rod must enter the tie rod at least
Inches 10 inches deeper than the end of the threaded
Mod.= Modulus of elasticity of the tie bar material portion of the rod. Then an unstressed indica-
(30,000,000 psi for steel) tor rod sleeve is inserted into a counterbore that
LM = The length of the tie bar over which the Indi- extends to the end of the tie bar threads. Only
cator reading was measured in inches the stretching of the 10 inch length is measured
on the dial indicator.
The above force is then divided by 2000 to get
The calculation of the tie bar force requires
the force in tons. If a machine has 7.5 inch diam-
one to know the length of the tie bar that is
eter steel tie bars (CSA = 44.18 square inches)
actually being measured, LM. That length is not
and the indicator reading of one tie bar is 0.0135
a standard for the industry and may be differ-
inches over a distance of 44 inches, then:
ent for different sizes of machine. Also, for the
F = (0.0135 x 44.18 x 30,000,000)/44 threadless tie bar construction the reading is af-
fected somewhat by the complex stress-strain re-
= 406,657 pounds = 203.33 tons.
lationship around the groove in the tie bar where
the tie bar is connected to the tie bar sleeve.
9
Chapte r 2 Clamping System
To insure that the dial indicator readings 4. With the machine unlocked (no load on the tie
are accurately converted to tonnage it is neces- bar), adjust the indicator forward on the dovetail
sary to have a chart for the speciÀ c machine as slide until it reads 0.030 inches. Lock the dial
shown below to convert the dial indicator read- indicator with the lock on the dove tail slide.
ings to tie bar tonnage. 5. Turn the dial to zero and lock the dial.
0.0003 4.104
- -
- -
- -
0.0148 202.4
0.0149 203 8
0.0150 205.2
10
Clamping System Chapte r 2
Figure 2-11 Linear optical encoders are Balancing tie bar loads:
permanently installed at the end of the tie bar Manual Method
and enclosed in a rugged guard. The electrical
output is converted into tons and displayed on a
Step 1: Clamp the machine at or near its
digital read out.
rated tonnage against a Master Test
Block (MTB) placed in the die space.
(The design and details of the MTB
are in the appendix.) The MTB must
be centered between the tie bars and
cover 50% of the platen area within
the tie bar centerlines as illustrated
in Figure 2-14. The horizontal or ver-
tical distance between the tie bar cen-
Figure 2-12 When digital read out of tonnage
ters times 0.707 gives the minimum
is used, the tie bar stretch is measured with a size of the MTB in that direction.
linear optical encoder
11
Chapte r 2 Clamping System
2
= 0.4 x 5 x 150 / 7.5 =5
2
Angle of Nut Rotation = (0.1 x ¨F x L) /(P x D )
Balancing tie bar loads:
Where: Automatic Individual Tie
¨F = Desired change in force, tons Bar Adjustment Method
L = Stretched length of tie bar, in.
The machine is set with a MTB as described
P = Pitch of tie bar thread, in. above for the manual method. Then the follow-
D = Tie bar diameter, in. ing steps are followed.
A common pitch for the tie bar threads is Step 1: Adjust the die height until the total
0.25 inches in which case the equation becomes: clamping tonnage is +/- 10% of the
2
tonnage that is to be used for the bal-
= 0.4 x ¨F x L / D
ancing procedure. Full machine ton-
So for a 5 ton change to one 7.5 inch diam- nage is not necessary. For example,
an 800 ton machine can be balanced
eter tie bar 150 inches long with a 0.25 in.
at 600 tons. Then, the machine would
thread pitch,
12
Clamping System Chapte r 2
be adjusted to any tonnage between not know the reason for the high tonnage on just
540 and 660 tons with approximately one tie bar and it does not know if the machine
150 tons on each tie bar. is clamped on a MTB or a die. The high tonnage
could be caused by Á ash in the die, or uneven
Step 2: Set the "High" and "Low" load limits thermal expansion of the die from a malfunction-
ing water line. If a problem with the die or set up
with the same settings for all four tie
has caused the high tie bar tonnage, then that
bars. These limits are set on the tie problem should be À xed instead of adjusting the
bar load monitor or machine control- tie bar. The operator must select "Cancel Adjust"
ler such as that shown in Figure or "Start Adjust" on the control panel. When
2-13. For the example, a low limit of satisÀ ed that the tie bar needs to be adjusted, the
147 tons and a high limit of 153 tons operator/setter will select "Start Adjust" and the
would be ideal. adjustment procedure will proceed.
Step 3: Turn the "Auto Individual Tie Bar 2. The spur gear for the tie bar that is to be adjust-
ed will retract (i.e. disengage).
Adjust" selector switch to the "ON"
position. Figure 2-13 shows the switch 3. The remaining three tie bar nuts will adjust by
(near the center of the panel) to be in the rotation of the bull gear one gear tooth tighter.
the "OFF" position.
4. The spur gear that had been retracted will insert
(re-engage).
Step 4: Open the machine fully.
5. Then the bull gear will adjust all four tie bar
Step 5: Close and lock the machine against the nuts one gear tooth looser (i.e. back to the origi-
MTB using the "Semi-Auto" machine nal position of the three that were not to be ad-
operation mode. If the tie bars are justed), but the tie bar that was tight is now one
within the limits entered into the con- gear tooth looser.
troller, the machine will stay closed.
Two proximity switches detect the movement
The operator must open it. However,
it the tie bars are not all within the of the bull gear an insures that it will move
limits, the machine will automatically only one gear tooth for any one adjustment.
open and adjust the one tie bar that is
the farthest out of the limits.
Comparing a Die to
If the tie bar must be tightened: the Master Test Block
1. The spur gear to that tie bar nut will retract. The condition of a die or the set up can be
evaluated with the tie bar monitors once the
2. The remaining three tie bar nuts will adjust by
the rotation of the bull gear one gear tooth looser.
machine has been balanced using a MTB with
the method described in the preceding sections.
3. The spur gear that had been retracted will insert For example the machine shown in the upper
(re-engage). illustration of Figure 2-15 had the tie bars bal-
anced at 150 tons each although the machine
4. Then the bull gear will adjust all four tie bar
might have been larger than 600 tons.
nuts one gear tooth tighter (i.e. back to the
original position of the three that were not to be
adjusted), but the tie bar that was loose is now Then, the machine is clamped onto the die
one gear tooth tighter. with approximately the tonnage at which the
die should be operated. The tonnage of each
If the tie bar is to be loosened and once the tie bar is then recorded as shown in the lower
machine has opened: illustration in Figure 2-15. The total of the four
tie bar tonnages in the À gure is 600 tons. How-
1. A light on the operator's panel illuminates alert-
ever the top two tie bars are stretched to 165
ing the operator/setter to "Check the Die". The
tons while the bottom two are only stretched
machine will not loosen a tie bar without an
to 135 tons. The top tie bars are 15 tons (10%)
"OK" from the operator/setter. The machine can
13
Chapte r 2 Clamping System
over the 150 ton average and the bottom two The problem illustrated in Figure 2-15 could be:
are 15 tons (10%) below the 150 ton average.
They are 20% different from each other. The The die is not machined parallel
general rule is that each tie bar should be with- The die is not positioned correctly into the machine
in +/- 10% of the speciü ed tonnage for the die. (e.g. it could be positioned too high on the plates)
If a tie bar is out of that range the die or the set
up should be corrected. The example is at the The die is not built stiff enough and the lower
extreme limit of the rule, but in both directions. part of the die is deÁ ecting under the clamping
The die or the set up should be corrected in the force of the machine
situation shown in Figure 2-15.
Unless there is an obvious problem that must
165 Tons 165 Tons
be corrected, the die can be run, making cast-
ings, for a while. When it has reached an oper-
ating temperature equilibrium, another set of
tie bar tonnage reading is taken. The thermal
expansions of the die will change the stretching
of the tie bars. If the tie bars become adequate-
ly balanced, then no correction is required.
Die
However, any problem will usually get worse
when the die is at its operating temperatures.
Also, if † ash builds up on the parting faces of
the die, the tie bar tonnages can be affected.
14
Clamping System Chapte r 2
"ON" and let the tie bars adjust to the required When these die conditions are met, the auto tie
load. The "required" load is set by adjusting bar adjust system can do what it is intended to
the tie bar force limits to the +/- 10% values. do. It can accurately adjust the locking forces on
For a 600 ton die running in the above 800 ton the machine to enhance the die casting process.
machine this would mean setting the upper
limits for all the tie bars at 170 tons and all Individual tie bar adjustment is not new. It
the lower limits for all the tie bars at 130 tons. has always been available to the operator or
When the automatic adjusting is complete, turn technician by way of manual adjustment. Being
the auto adjustment "OFF" and run production able to do it automatically and with precision is
but continue to monitor the tie bar loads. This relatively new. Adjusting the tie bars manually
is the preferred method. is both difÀ cult and time consuming, especially
on the larger machines.
Another procedure for using the auto tie bar
adjustment to enhance the process is to set the Whenever an individual tie bar adjustment
auto adjust to "ON" and set the individual load is made, the machine must be returned to it's
limits as described in the previous paragraph "home" position as soon as the situation that
as soon as the die is set. Then let the machine caused the adjustment to be made has passed.
continue to adjust during the warm up of the die In other words, if a particular die required a
and while making the initial production castings. particular adjustment, the tie bars must be
This method will allow the machine to "follow" returned to the "home" adjustment as soon as
the die. There is no limit to how many adjust- that die is removed from the machine.
ments the machine will make when using this
method. The process technician must be sure
the process is under complete control (e.g. die Monitoring the Clamping Force
temperature, Á ashing, thermal expansions, etc.). During Production and for SPC
Otherwise the adjustments may never converge
to a workable combination and continue forever. One use for the tie bar tonnage monitoring is to
facilitate the keeping of the die clamping forces
It must be recognized that when the tie in control during production runs. To use them
bars are adjusted from the evenly loaded posi- for that purpose one must À rst set up the ma-
tions from the MTB procedure, the machine chine to the speciÀ ed tonnage (as shown on the
IS "out of square" even if the loads on the tie job set up chart) and adjust the individual tie
bars are balanced. bars, if necessary, as described in the preced-
ing sections. Then, the operating (not set up)
The auto tie bar adjust system is not intend- limits for each tie bar are set into the control-
ed to correct for all die and set up problems. ler. These should also be available on the job set
The die must be: up chart. Some trial and error experimentation
may be required to establish the tonnage lim-
Parallel (i.e. the cover die mounting surface must its, but once established they should not change
be parallel to the ejector die mounting surface) for any one die.
Centered in the machine
When the tonnage limits are exceeded, ether
The proper size for the machine high or low, the monitor will give off a signal
Made so the cast shot projected area is centered (e.g. an alarm) to alert the operator/technician
to the machine as closely as possible or properly of the situation. The operator/technician can
compensated for by proper machine size selection then make the necessary changes to correct the
and proper die size for the machine. condition. The alarm can be a buzzer, a light
on the monitor panel, a large Á ashing light on
Made with sufÀ cient surface contact (i.e. 0.2
top of a control panel, or all of the above. The
square inches per ton of machine rated tonnage
alarm can even signal the casting extracting
which is 160 square inches for an 800 ton ma-
robot to set the casting aside.
chine) between the die and the machine plates
15
Chapte r 2 Clamping System
The actual tie bar loads, and the acceptable Fill the rod hole 2/3 full of a light weight high
limits, can also be monitored with a computer temperature grease.
either at the machine or in a central control Re-install the rod allowing the excess grease to
room. Such data can be used to certify that the squeeze out.
castings were made under the speciÀ ed condi-
Replace the spring if necessary. The spring must
tions, plotted graphically to display trends, and
have sufÀ cient force to move the indicator rod
for establishing probable causes of problems.
during the machine operation.
Things that can cause the tonnage to get out of
speciÀ cation are: Replace the bracket
The individual tie bar tonnages can also be 2. List three things for which clamping force is
needed
sampled randomly and the data used to cre-
ate X-bar and R charts for statistical process 3. How is the clamping force developed?
control (SPC). Although, with real time control
available, it is not clear just how the SPC chart- 4. How is the clamping force of the machine moni-
ing would be an advantage. But, if there is an tored and controlled?
occasion where SPC techniques will help, the 5. How can the casting process and quality of the
data would be available. casting be affected if the clamping force is too
high?
When evaluating the mechanical assemblies and 7. The limit as to how far an individual tie bar may
features of the machine, the load on the tie bars be adjusted away from the " home" position is
a. +/- 5%
must be known. The tie bar load indicators are
b. +/- 25%
used for this purpose. For example, when check-
c. +/- 10%
ing the stack-up of the linkage, there must be a
of the maximum rated tie bar load
load on the tie bars. This concept is developed in
more detail in the NADCA text and course on 8. If an 8 inch diameter tie bar stretches 0.0139
Mechanical Maintenance and Evaluation. inches over 40 inches of length, what is the load
on the tie bar?
The indicator assembly must have preventive
maintenance service yearly. Service consist of:
Clean the hole in the tie bar. Remove all old grease.
16
CHAP T E R
THREE
The subject of "dies" is huge, and there are spacing. If the tie bar center line spacing was
NADCA texts and courses that deal with the 44 inches by 44 inches then:
subject. So for this text, the discussion of dies
is limited to how the dies must be conÀ gured to Die = 0.707 x 44 in.
avoid undesirable loading of the machine. If the
die is too small, has insufÀ cient surface contact = 31 inches x 31 inches
with the machine plate or is offset to the center
of the machine plates, the die can cause dam- When a smaller die is clamped with the full
age to the machine. Quite often the damage is locking force capability of the machine, the
not noticeable at the time. But the machine will machine plate will bend as illustrated (exag-
have accelerated wear if the dies are not prop- gerated) in Figure 3-2. Rigorous control of the
erly sized and positioned. clamping force to be only that required for the
die will minimize the plate deÁ ection. But, if
the die is very small there will be excessive
Die Size plate deÁ ection regardless.
Clamping
Force
1,600,000 Lbs/240 sq. in. = 6,666 psi
DIE
Edges will which is below the 10,000 psi limit. So, the
coin in.
die is suitable for the machine. However, if the
rails were only 2.0 inches wide, the pressure on
the machine plate would be 13,333 psi and that
exceeds the 10,000 psi limit.
18
Dies and Die Set-Up Chapte r 3
Mounting Plate
Traveling
te Plate
Pla Rails
ng Rail Ejector
Die Cavity Block
veli
Tra e
r Di Cavity
cto Support Post
Clamping
Eje Force Cover Die
Support Post
Rail
19
Chapte r 3 Dies and Die Set-Up
TB #3
was moved above the machine center in one 180 TB #3
inch increments. The machine was clamped on 160
TB #4
the MTB with 800 tons and the load on each tie 140
TB #4
TB #3 TB #2
Figure 3-8 This graph shows the effect on tie
bar strain when the MTB was moved off center
in the test with an 800 ton machine described in
24.00
the text. The left vertical scale is the individual
tie bar load in tones, and the bottom horizontal
4.00
22.00 scale is distance the MTB was positioned above
1.00
the machine center in inches.
9.50
7.00
20.00 44.00
Review Questions:
5.38 1.00
2.00
1. What is the ideal minimum die size for a ma-
è3.00
chine?
4.00
a. Yes
b. No
20
CHAP T E R
FOUR
EJECTOR SYSTEMS
Ejecting the casting from the die cavity is ac- The machine ejector system is built into
complished with an ejection system in the die the machine between the back plate and the
(REF. MADCA text and course on Engineering traveling plate with pins or a hydraulic cyl-
Die Casting Dies). The ejector system in the die inder rod end passing through the traveling
casting machine actuates the ejection system in plate to engage the ejector plate in the die.
the die. The power and the sequencing within Figure 4-1 shows the location of the ejector
the casting cycle is accomplished through the system in the machine.
machine ejector system.
Figure 4-1 The machine ejector system is between the back and traveling plates. The machine ejector
system actuates the die ejection system to eject the casting from the die. Pins or a hydraulic cylinder rod
extend through the traveling plate into the die.
Chapte r 4 E jecto r Systems
There are three types of machine ejector After the casting has solidiÀ ed in the die
systems commonly used. These are: the machine opens. As the machine's travel-
ing plate approaches the end (1.0 to 3.0 inches
Bumper plate ejection is typical) of the opening stroke, the ejector
Center hydraulic ejection rods contact the machine's ejector plate. Once
the ejector rods contact the machine's ejector
Hydraulic bumper plate plate, the rods, die ejector plate, die ejector
pins and the casting all stop moving. The ma-
Each type has its own advantages and disad- chine's traveling plate and the die continue to
vantages. move to the full open position of the machine
stripping the die off the casting. The casting
is thus ejected from the die and positioned for
Bumper Plate Ejection removal by an operator or extractor (e.g. a ro-
bot). The die open with casting ejected position
The bumper plate ejection is the simplest and
is shown in Figure 4-4.
provides for the fastest machine operation. The
bumper plate is a vertical plate held in a À xed
position to the back plate of the machine. The When the machine reaches the fully open
bumper plate construction is shown in Figure position, the die ejector plate MUST NOT
4-2. The bumper plate is permanently attached make contact with the die's ejector plate
to the back plate with four (or more) bumper forward stop blocks. If the die ejector plate
posts. The bearing housing for the traveling contacts the forward stop blocks the machine
plate extends through, and is supported by, the opening force will be transmitted to the die
bumper plate. clamps. To insure the correct position of the
die ejector plate in the full open die position,
When the machine closes and the die ap- the ejector rods must be the correct length
and the machine stroke must be properly
proaches the die closed position, the return pins
adjusted. The machine stroke and the ejector
in the die (all the ejector pins are still fully
rod lengths should be provided on the set-up
extended) contact the cover die and push the
chart for the particular die. The dies should
die ejector plate back as the die completes clos-
be designed to use standard lengths of ejector
ing. The die ejector plate pulls all the ejector
rods. The die caster should standardize on the
pins back as it is returned to its "back" position
ejector rod lengths and publish the standard
as shown in Figure 4-3. As the die ejector plate
in their die design standards.
is returned to the back position, the ejector rods
are also pushed to the back position.
The advantages of the bumper plate ejec-
Cover Die
Bumper
Plate
Ejector Die tion are:
Back Traveling Front
Plate Plate Plate
Tie Bar No additional machine cycles must be sequenced
to operate the ejection.
Bumper
Post
Minimum machine cost
22
E jecto r Systems Chapte r 4
Figure 4-3 The machine And die with bum- 2. The die ejector plate, and ejector pins, can
per plate Ejection are shown here In the " die
not be pulled back into the die before the
closed" Position. The die return Pins have
die closes.
pushed the die Ejector plate and the Ejector rods
to the "back" position. The space between the
ends of the ejector rods and the machine ejector
The bumper plate ejector system can experi-
plate must equal the machine stroke less the die ence the following problems:
ejection travel.
1. The ejector rods might bend when the die
Bumper Ejector Die
Cover Die ejection force is high and only four rods
Plate
Back Traveling Front
have been installed. Since the ejector rods
Plate Plate Plate
Tie Bar are quite small in diameter and fairly
long, dies requiring high ejection forces
Bumper
Post
may need more than four ejector rods.
Bearing 2. When the ejector rods are not all the same
Housing
length, the die ejector plate will be tipped.
The die ejector plate will then bind on its
guide pins and bushings. The ejector rods
should be within 0.005 inches of the same
length and be Á ame hardened on both
See Figure 04-05
ends. It is suggested that the rods be made
of SAE 1045 steel.
23
Chapte r 4 E jecto r Systems
with the original surface, and bolt a small Ejector Plate Guide Rods
hardened steel plate over the indented Ejector Plate Return Stop Ejector Plate
Return Pins
area. The ejector rod must be shortened
Ejector Pins
the thickness of the plate. The die ejector
plate can also experience indenting and
should be checked periodically.
24
E jecto r Systems Chapte r 4
a A B b
25
Chapte r 4 E jecto r Systems
0.050 inches of travel which positions the die's a pressure control valve for limiting the force
ejector plate against the return stop blocks in that is applied with the machine's ejector plate.
the die. The ejector plate, pull back rods and With both the circuits shown in Figures 4-10
ejector rods must have free travel so the force and 4-11, the ejector plate will move forward
of the hydraulic cylinders is never applied to faster than it will retract because of the differ-
the die's ejector plate once the die's ejector plate ent piston areas on the rod sides and the head
has reached the back stops in the die. sides of the hydraulic cylinders. The regenera-
Ejector Plate Return Pins
Hydraulic
There may be instances (e.g. if a die does not Ejector Plate
Ejector Plate Guides
Die Ejector Plate Ejector Pins
have return pins, or because of dimensional
variations from die to die) where the die ejec-
tor plate may have to be pulled all the way
back against the stop blocks in the die and
held with the machine's ejector cylinders. In
these instances, the hydraulic pressure must
be reduced to where the pulling force of the
cylinders is low enough to not damage the die.
The NADCA Machine Hydraulic Maintenance
course explains how the hydraulic pressure is
adjusted for these situations.
Forward Stop
When the machine opens and is near (e.g. 1 Return Stop
to 3 inches is typical) from the full open posi-
tion the "start ejection" limit switch is contact- Note: Free motion Ejector Rods
ed and the piston in the ejector cylinder moves Pull Back Rods
the ejector plate forward. The forward travel Figure 4-8 The hydraulic ejector plate is
is accomplished by hydraulic Á uid entering the attached to the traveling plate with hydraulic
rod end of the ejection cylinder. As the cylinder cylinders. the system is shown here with a die
moves forward on the stationary piston, the in the closed position. The die's ejector plate
cylinder base moves forward and that pushes can be pulled back through the use of pull
the machine's ejector plate, the ejector rods, the back rods.
die's ejector plate, the ejector pins and the cast-
ing forward. Thus the casting is ejected from tive circuit shown in Figure 4-12 will have the
the cavity, as shown in Figure 4-9, ready to be same ejector plate speed forward and back if
removed from the die. the cylinder piston rod side area is half the
head side area. Having the rod piston area half
the head piston area is one of the standard con-
A limit switch MUST BE set near the full
À gurations of hydraulic cylinders.
forward position of the die's ejector plate to
stop the forward travel of the machine's ejec-
The hydraulic ejector plate system has the
tor plate. At that forward position, the die's
following advantages.
ejector plate must not make contact with the
forward stops in the die. If the die ejector plate
1. High ejection force
contacts the forward stops, the full force of the
machine's ejector plate will be applied to the 2. Long ejection stroke
clamps holding the die to the traveling plate.
3. Large selection of ejector rod positions. The ejec-
A basic hydraulic circuit for the hydrau- tor rods can be placed near the corners of the
die's ejector plate providing stability to the die's
lic ejector plate is shown in Figure 4-10. The
ejector plate.
circuit has manually adjusted Á ow controls for
both directions of travel. Figure 4-11 shows 4. Die ejector plate pull back
the same circuit that has been enhanced with
26
E jecto r Systems Chapte r 4
Forward Stop
Return Stop
EJECTION
a A B b
27
Chapte r 4 E jecto r Systems
1. The ejector rods might bend when the die ejec- b. False
tion force is high and only four rods have been
3. The lengths of all the ejector rods must be the
installed. Since the ejector rods are quite small in
same within:
diameter and fairly long, dies requiring high ejec-
tion forces may need more than four ejection rods a. 0.005 in.
2. When the ejector rods are not all the same length, b. 0.05 in.
the die ejector plate will be tipped. The die ejector
plate will then bind on its guide pins and bush- c. 0.5 in.
ings. The ejector rods should be within 0.005
4. If a casting is not ejected from the cavity in a
inches of the same length and be Á ame hardened
straight line, the casting may become __________.
on both ends and be made of SAE 1045 steel.
5. Name the three types of ejector systems.
3. The bumper plate can become indented (i.e.
"caved in") where the ejector rod makes contact
with it. The indented material mushrooms up
around the area of ejector rod contact leaving a
raised ring. The indented plate can be repaired
by welding and resurfacing, but that is a major
repair job as the plate must be removed from the
machine. Another method of repair is to hand
grind the raised material to be Á ush with the
original surface, and bolt a small hardened steel
plate over the indented area. The ejector rod
must be shortened the thickness of the plate. The
die ejector plate can also experience indenting
and should be checked periodically.
28
CHAP T E R
FIVE
SHOT END:
COLD CHAMBER SYSTEMS
The plunger must be water cooled because 1. Velocity control of the plunger
it is in direct contact with the molten metal. a. Slow
The cooling water † ows through a pipe through
the middle of the shot rod into and through the i. Close the shot sleeve pour hole
plunger and back through the hole in the shot ii. Critical slow shot velocity
rod around the inlet pipe. The water connec-
tions are made with hoses to the shot rod near b. Fast
the coupling. 2. Position control of where the velocities change
The "C" frame also facilitates the chang- a. Start critical slow shot velocity
ing of the position of the shot sleeve in those b. Start the fast shot velocity
machines with alternate shot sleeve position
capability. The normal shot sleeve position is at c. Start the low impact function
the center of the tie bar spacing. But, when al- d. Start intensiÀ cation
ternate positions are available they are usually
6.00 inches below the center and sometimes 3. Pressure/Force control
both 6.00 inches and 12.00 inches below the
a. Pressure required to achieve the required
center. The remaining equipment is primarily
velocity
the hydraulic and electrical power and control
gear, and that is mostly mounted on the "C" b. IntensiÀ cation
frame. Modern machines have most of the hy-
draulic circuitry manifolded which eliminates The actual values for all these functions are
piping and connections. determined by the die and process engineering
for the particular casting to be made. These
Intensifier Accum.
values would be provided to the process set up
Traveling Plate Front Plate person on some form of job set up chart. The
Die Cavity
Shot Accum. NADCA course on Gating explains how to
C-Frame establish most of these set up values. However,
some of those values might be determined, or
adjusted, through experimentation during the
initial production runs.
Die
Tie Bar
Shot Cylinder
30
Shot E nd : Cold Chambe r Systems Chapte r 5
ü cation pressure after the cavity has ü lled with The newer machines with more advanced
molten metal. The circuit shown in Figure 5-3 hydraulic and monitoring systems allow the po-
has the high pressure gas accumulator for the sitions and velocities to be set through the con-
intensiü cation, but it also has a 2 to 1 differen- trol panel. One such control panel is illustrated
tial piston multiplier cylinder to achieve even in Figure 5- 4 for a digital input and display.
higher intensiü cation pressure. Monitoring systems are also available that
show the plunger performances graphically.
The positions at which the speed or pressure These control panels not only allow the setting
changes occur can be initiated by limit switches of the speeds and positions for the speeds, but
tripped by the plunger as it moves. These limit display to the operator the actual performance
switches must be set (i.e. moved) for each die set of the machine after each shot.
up. Continuous position transducers can also be
used. When a continuous position transducer The modern shot control input and monitor-
is used, the speed shift points are programmed ing systems also provide for the inputting of
through the machine controller. The simplest acceptable performance ranges. Then, if the
machines (generally the older machines) have plunger performance (primarily speed) is slow-
spool type directional valves with needle (for er than the minimum, or faster than the maxi-
the slow shot circuits) † ow control valves and mum some type of alarm will activate. The
adjustable opening poppet valves for the fast alarm can be a simple indicator light on the
shot † ow control. These machines require control panel, or a large † ashing light mounted
manual adjustment of the † ow control valves. in plain view on top of a control panel, or even a
31
Chapte r 5 Shot E nd : Cold Chambe r Systems
from
intensifier
pump
from shot
pump
siren. The "out-of-speciü cation" alarm can also velocity, head side cylinder pressure and rod
cause the part extracting robot to set that cast- side pressure are graphed against plunger posi-
ing aside for additional inspection. It is then up tion. The slow plunger speed is about 15 inches
to the operator or technician to determine the per second and the fast plunger velocity is
cause of the out-of-speciü cation performance about 104 inches per second. The system starts
and make the corrective adjustments. to shift from the slow to the fast velocities at
23 inches of travel. The inertia of the system
The shot performance data can be sent to a requires 0.9 inches of travel to reach the 104
central control computer and be monitored by inches per second fast shot speed. The transi-
maintenance personnel. The shot performance tion performance from slow to fast shot speeds
data can also be used to certify that the castings must be measured and recorded for every
were all made to the speciü ed shot performance. machine. That information must be provided to
the process and die engineers. Then when the
The SERVO system shown in Figure 5-3 is plunger performance settings for a new casting
self compensating. Any small deviation of the are calculated (Ref: NADCA course and text on
plunger speed from the set value causes an im- Gating), the machine reaction performance can
mediate adjustment to the SERVO valve posi- be accounted for.
tion to correct the plunger speed. These sys-
tems will maintain the set plunger speed until Also the fast velocity as shown in ü gure 5-5
the system has reached the limit of its capabil- drops off as the plunger advances. The drop
ity. Then it will alarm. off in velocity is caused by the additional resis-
tance to metal † ow in the die as the die ü lls.
A graphic monitoring system is shown in Every die will have a different resistance to the
Figure 5-5. In that illustration the plunger metal † ow. However, for the machine shown in
32
Shot E nd : Cold Chambe r Systems Chapte r 5
the À gure, the rod side pressure can be reduced that velocity there is no pressure to push on the
further to provide more pressure to maintain molten metal. When the plunger is not mov-
speed if necessary. ing (e.g. at the end of cavity À lling when the
plunger is pushing on the biscuit) all the 1150
psi of hydraulic pressure is actually applied to
the piston, and hence to the molten metal.
900
700
rather than the more common hydrostatic 600
500
circuits, it's performance is velocity dependent. 400
S
The faster the hydraulic Á uid moves through h 300
o
t 200
the valves and pipes, the more pressure losses P
r 100
e
0
there are within the machine. Once the hydrau- s
s 0
1 2 3 4 5 6 7 8 9
u 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 2
metal. The net affects of these velocity depen- Figure 5-6 The power curve of the machine's
dent losses is captured in the PV 2
diagram in a shot system can be measured and plotted on a
2
practical and easily usable form. PV diagram as shown here. Then, the die resis-
tance can be compared to the machine power and
The PV 2 diagram is shown in À gure 5-6. the correct † ow control valve setting established.
33
Chapte r 5 Shot E nd : Cold Chambe r Systems
function of the pressure required to push metal system pressure. Since the metal is still fully
through the gate at various plunger velocities. molten, the pressure on it is applied to the
For the casting's required À lling time, gate size entire projected area within the die. The clamp-
and plunger diameter, there will be a minimum ing force of the machine must be sufÀ cient to
plunger velocity performance that will work. hold the molten metal at the impact pressure
That plunger velocity is computed when the without Á ashing the die.
gating system for the die is designed. If that re-
quired plunger velocity is 108 inches per second, Many, and maybe most, modern machines
(i.e. the intersection of the die resistance curve have what is known as "low impact systems" in
and the machine's performance curve) the valve the hydraulic controls of the shot system. The
opening that results in the lower performance low impact systems shut off the hydraulic Á uid
curve in the À gure is how the Á ow control valve leaving the rod side of the hydraulic shot cylin-
must be set. The plunger velocity is inversely der just before the cavity À lls. Thus the impact
proportional to the square of the plunger diam- force is trapped in the hydraulic cylinder and
eter. So, larger plungers must move slower to not transmitted to the molten metal in the die.
cause the same die cavity À lling behavior.
When the low impact system is operating
2
The maximum machine power curve in a PV properly, much larger castings can be made in
diagram for a particular machine is created a given size machine. Thick castings with low
on a velocity squared diagram by À rst plotting fast shot speeds may not beneÀ t much from a
the hydraulic system pressure (e.g. 1050 psi low impact system. But, the thinner castings
in Figure 5-6) on the pressure scale. Then the that require short À lling times, and hence high
measured speed of the plunger when the Á ow fast shot speeds, can beneÀ t greatly from the
control valve(s) is fully open and there is no low impact system.
molten metal in the shot sleeve is plotted on the
velocity squared scale. The power curve is then The timing of the closing of the hydraulic
a straight line connecting those two points on valve to achieve the low impact is critical. The
the graph. The PV 2
diagram should be created distance between where the low impact valve
and provided to the processing engineer(s) so shift is triggered and where the cavity is full is
the correct plunger size can be selected and the a very short distance and the plunger is moving
correct plunger velocities can be speciÀ ed for very fast. To have it work correctly, the amount
any new die for any new casting. These proce- of metal ladled must be controlled very accu-
dures are described in detail in the NADCA rately. Variation in the size of the biscuit can
courses on the PQ 2
Diagram and on Gating. result in the low impact trigger being too late
(Note: The PQ 2
diagram is the PV 2
diagram (i.e. a large biscuit) and the impact pressure
still happens and the die Á ashes. With a small
adjusted for the cubic volume of molten metal
biscuit, the low impact trigger can be too soon
Á ow rate for a speciÀ c plunger diameter.)
and the casting will not À ll properly.
34
Shot E nd : Cold Chambe r Systems Chapte r 5
to push it through the liquid core of the run- ing the next 40 milliseconds. By controlling the
ners and into the cavity. The solidifying shell delay and the rate of pressure build-up a maxi-
of the biscuit resists any forward motion of the mum pressure can be applied to the molten
plunger. So, an intensiÀ ed pressure is applied metal at all times without Á ashing the die. The
to the hydraulic cylinder to crush the shell so settings for the delay and the build-up rate will
the plunger can advance and keep pressure usually have to be determined experimentally
on the molten core as it is fed into the casting. during the initial production runs of the die.
If the high intensiÀ ed pressure is applied too
soon after the die has À lled, the pressure will To be able to set the delay and build-up rate
be applied to the entire projected area of the die it is necessary to have a shot system perfor-
and can force the die to Á ash. If it is applied too mance monitoring system like that shown in
late, the casting and/or gates will have already Figure 5-7. Otherwise, the technician has no
solidiÀ ed, and no molten metal can be pushed way of knowing what the machine is actually
through. So, the timing of the application of doing and how it responds to adjustments he
pressure and the rate at which the pressure might make to the controls.
builds are critical process parameters.
Multiplier cylinders
Pre-À lls
Accumulators
Regenerative
The high pressure pump supplied accumu- Figure 5-7 The shot performance trace here
lator systems are shown in Figures 5-2 and shows an intensiÀ cation pressure delay of about
5-3. Figure 5-3 also has a multiplier cylinder 25 milliseconds and the intensiÀ cation building
to 3000 psi over a 40 millisecond time period.
that can be used or not used at the operator's/
The intensiÀ cation pressure must not build too
technician's option.
fast or the die will Á ash.
35
Chapte r 5 Shot E nd : Cold Chambe r Systems
Monitoring Equipment
The performance of the shot system monitoring
equipment must be adequate for the situation.
It must:
36
CHAP T E R
SIX
SHOT END:
HOT CHAMBER SYSTEMS
The "A" frame also facilitates the changing 1. Velocity control of the plunger
of the position of the sprue in those machines a. Slow
with alternate shot position capability. The
i. Close the gooseneck inlet hole
normal shot position is at the center of the
tie bar spacing. But, when alternate positions ii. Slow shot velocity
are available they are usually 6.00 inches b. Fast
below the center and sometimes both 6.00
2. Position control of where the velocities change
inches and 12.00 inches below the center. The
remaining equipment is primarily the hy- a. Start slow shot velocity
draulic and electrical power and control gear, b. Start the fast shot velocity
and that is mostly mounted on the "A" frame.
c. Start the low impact function
Modern machines have most of the hydraulic
circuitry manifolded which eliminates piping d. Return plunger
and connections. 3. Pressure/Force control
a. Pressure required to achieve the
required velocity
Shot Cylinder b. Pressure during casting solidiÀ cation
Die Cavity
Plunger Coupler
Plunger
Die
Saddle Bar
Furnace
Nozzle
Functions
The functions of the shot system are to inject
the molten metal into the die under the proper
conditions. That involves precise control of the From Pump
movement of, and force on, the plunger. These
functions are: Figure 6-2 A typical shot system hydraulic
circuit using a proportional valve for both the
slow and fast shot speeds is shown here.
38
Shot E nd : Hot Chambe r Systems Chapte r 6
The actual values for all these functions are The modern shot control input and moni-
determined by the die and process engineering toring systems also provide for the inputting
for the particular casting to be made. These of acceptable performance ranges. Then, if
values would be provided to the process set up the plunger performance (primarily speed) is
person on some form of job set up chart. The slower than the minimum, or faster than the
NADCA course on Gating explains how to maximum some type of alarm will activate.
establish most of these set up values. However, The alarm can be a simple indicator light on
some of those values might be determined, or the control panel, or a large Á ashing light
adjusted, through experimentation during the mounted in plain view on top of a control panel,
initial production runs. or even a siren. The "out-of-speciÀ cation" alarm
can also cause the part extracting robot to set
that casting aside for additional inspection. It is
Velocity and Position then up to the operator or technician to deter-
mine the cause of the out-of-speciÀ cation per-
The shot system has, by far, the most complex formance and make the corrective adjustments.
control system of the entire machine. A typical The shot performance data can be sent to a
hydraulic circuit is illustrated in Figure 6-2. The central control computer and be monitored by
circuit has a single proportional valve to control maintenance personnel and/or used to certify
both the slow shot speed and the fast shot speed. that the castings were all made to the speciÀ ed
The circuit applies a constant hydraulic pressure shot performance.
from a large gas accumulator to the head side of
the hydraulic shot cylinder and then controls the
motion by metering out the hydraulic Á uid from
the rod side of the cylinder.
39
Chapte r 6 Shot E nd : Hot Chambe r Systems
tem requires 0.9 inches of travel to reach the 55 The quality of the casting is very sensitive to
inches per second fast shot speed. The transi- the cavity À lling time. The ability of a shot
tion performance from slow to fast shot speeds system to maintain a speciÀ ed fast velocity is
2
must be measured and recorded for every measured and described by the PV diagram.
machine. That information must be provided to These diagrams show graphically the pressure
the process and die engineers. Then when the that is available to push on the hydraulic piston
plunger performance settings for a new casting at every possible speed of the piston. Since the
are calculated (Ref: NADCA course and text on shot system's hydraulic circuit is a hydrody-
Gating), the machine reaction performance can namic circuit rather than the more common
be accounted for. hydrostatic circuit, it's performance is velocity
dependent. The faster the hydraulic Á uid moves
The slow shot speed closes the gooseneck in- through the valves and pipes, the more pres-
let ports, moves the molten metal up the goose- sure losses there are within the machine. Once
neck channel, and through the nozzle to, or the hydraulic pressure is lost (i.e. used) within
nearly to, the sprue at the die. The slow travel the machine, it can not be used to push on the
through these components allows time for air molten metal. The net affects of these velocity
to vent from the die and can be used to preheat dependent losses is captured in the PV 2
dia-
the metal moving slowly through the nozzle. gram in a practical and easily usable form.
40
Shot E nd : Hot Chambe r Systems Chapte r 6
2
opening that results in the lower performance in detail in the NADCA courses on the PQ
2
curve in the À gure is how the Á ow control valve Diagram and on Gating. (Note: The PQ dia-
2
must be set. The plunger velocity is inversely gram is the PV diagram adjusted for the cubic
proportional to the square of the plunger diam- volume of molten metal Á ow rate for a speciÀ c
eter. So, larger plungers must move slower to plunger diameter.)
cause the same die cavity À lling behavior.
PV Chart
2
Low Impact Systems
Prince Machine Model 629HC SN 96053
1500
1400
1300 Max. Vel. Valve Open 99% At the instant the cavity completely À lls with
1200
Max. Vel. at Selected Valve Opening molten metal there is no place to put any more
1100
1000
900
Die Resistance Line metal, so the plunger must stop moving. The
800
700
kinetic energy in the fast moving plunger, shot
600
500
rod, hydraulic piston and the moving hydraulic
S
h
400
300
Á uid must be dissipated suddenly. The result
o
t
P
200
100
is a sudden and very short (e.g. a few milli-
r
e
s
0
0
seconds) rise in the pressure in the hydraulic
s 1 2 3 4 5 6 7 8 9
u
r
e
0 0 0 0 0 0
(Note: By having metal in the gooseneck, but When the low impact system is operating prop-
measuring the velocity just before the metal en- erly, much larger castings can be made in a given
ters the die, the pressure losses in the gooseneck size machine. Thick castings with low fast shot
2
are captured. The resulting PV is then appro-
speeds may not beneÀ t much from a low impact
priate for comparing machine power to the die
system. But, thinner castings that require short
requirement. However, if one wants to evaluate
À lling times, and hence high fast shot speeds,
the gooseneck efÀ ciency, then the maximum shot
velocity must also be measured with the plunger can beneÀ t greatly from the low impact system.
removed. Then, the difference between the two
diagrams shows the power loss in the gooseneck.) The timing of the closing of the hydraulic
valve to achieve the low impact is critical. The
The power curve is then a straight line con- timing of the low impact trigger is even more
2
necting those two points on the graph. The PV sensitive for hot chamber machines than for
diagram should be created and provided to the cold chamber machines since the total travel of
processing engineer(s) so the correct plunger the plunger to À ll the die is usually much less
size can be selected and the correct plunger ve- for comparable sized castings. The distance
locities can be speciÀ ed for any new die for any between where the low impact valve shift is
new casting. These procedures are described
41
Chapte r 6 Shot E nd : Hot Chambe r Systems
triggered and where the cavity is full is a very Collect quantiÀ able data at a rate of at least
short distance and the plunger is moving very every 0.001 seconds
fast. If the low impact trigger is too late the Record and display capability for:
impact pressure will still happen and the die
will Á ash. If the low impact trigger is too soon Plunger position (dynamic)
the casting will not À ll properly.
Plunger velocity (dynamic)
Once the die has À lled with molten metal, the Tie bar loads. All four bars plus the total.
function of the shot system is to apply a con- (single point readings)
trolled pressure on the metal. The purpose is
to force additional molten or semi-solid metal Temperatures (single point readings)
into the cavity as the metal in the cavity solidi- Be time and position based display.
À es and shrinks. The shrinkage will result in
porosity in the casting if not supplied with new Position based for the slow and fast shot
molten metal as the shrink forms. Force on the Time based for the pressure during solidiÀ cation
plunger applies pressure on the molten metal to
push it through the liquid core of the runners
and into the cavity Nozzle Set-Up
The hot chamber machines do not have The "A" frame is mounted on bars extending
intensiÀ cation systems like the cold chamber outward from the front plate. The "A" frame can
machines. Since the metal pressurized by the be moved along these bars to position it closer
plunger is always liquid, there is no need to to or farther from the front plate. This position
crush a solidiÀ ed biscuit shell. So, the very adjustment is used to apply and release the
high intensiÀ cation forces are not necessary. force holding the nozzle against the die sprue.
The system pressure applied by the plunger The position adjustment also accommodates
pressurizes all the molten metal in the system. different lengths (within limits) of nozzles.
Shrinkage will feed as long as a liquid feed When a nozzle seat becomes damaged, it can
path remains open through the sprue, runners, be re-machined which makes the nozzle a little
gate and cavity. shorter. Then, the adjustability of the "A" frame
accommodates the shorter nozzle.
The amount of plunger movement during
The "A" frame is moved along the bars by
the casting solidiÀ cation time is not a good
indicator of the effectiveness of shrinkage either a manually rotated pinion through the
feeding in the hot chamber machine. There "A" frame engaging gear racks on the bars or
is signiÀ cant leakage of molten metal past with hydraulic "saddle bar" cylinders as shown
the plunger in the gooseneck and that leak- in Figure 6-6. and with the cylinder detail
age changes fairly rapidly with wear on the shown in Figure 6-7. The cylinders shown in
plunger rings. So, the plunger "drift" is actu- the À gure are head side Á ange mounted to the
ally a better indicator of when to replace the front plate. The cylinder rods are connected to
plunger rings. the "A" frame. The cylinders can move the "A"
frame along the supporting rods.
42
Shot E nd : Hot Chambe r Systems Chapte r 6
The force from the pressure on the molten Force Total = 8,800 x 1.5 = 13,254 pounds
metal is:
The amount of force (i.e. the safety factor)
Force = Pressure x Area required is affected by how well the saddle bar
bushings in the "A" frame are maintained. If
where the area is the diameter of the hole in the "A" frame bushings are well lubricated and
the sprue. Assuming a metal pressure (i.e. peak the saddle bar surfaces are in good condition,
impact pressure) is 5000 psi. and the sprue the friction force is quite low.
is 1.5 inch in diameter, the area will be 1.76
square inches and the force is then: When the nozzle is to be removed (either for
die set-up or for nozzle replacement), the nuts
Force = 5,000 x 1.76 = 8,800 pounds holding tension on the springs are backed off
far enough to provide the space necessary to
For safety and to insure overcoming the friction get the nozzle out. The hydraulic cylinders will
between the "A" frame and the bars, the springs still be holding the nozzle in place. Then while
plus the cylinders should exert 1 ú times the supporting the nozzle, so it will not fall when
force from the metal pressure which is: loosened, the hydraulic cylinders are actuated
to move the "A" frame away from the front
plate. The loosened nozzle is then removed.
Shot Shot
Accumulator Cylinder
The hydraulic control circuit for the saddle
cylinders is shown in Figure 6-8. The centered
position of the directional control valve allows
for all force to be removed from the cylinders.
Also, a pressure regulator provides for adjust-
ing the cylinder force.
43
Chapte r 6 Shot E nd : Hot Chambe r Systems
2 2
1. What are the three functions of the shot system?
Area = 0.7854 (4.00 - 1.75 )
2. What are the four phases of the shot process and
= 10.16 square inches/cylinder the primary purpose of each?
The hydraulic pressure required to generate 3. What is the purpose of the slow shot speed?
the 8,254 pounds of force is:
4. What is the function of the "A" Frame?
44
CHAP T E R
SEVEN
MEASURING MACHINE
CAPABILITIES
It is important to know the actual performance tem pressure. The other aspect of any machine
capabilities of the die casting machine. The function is the variability of that function dur-
À rst use is to validate that a new machine ing normal production operation. The machine's
actually has the speciÀ ed capability for which it capability is measured with a capability test.
was purchased. Such a speciÀ cation can be the The exact type of test depends upon which per-
manufacturer's claims or the die caster's re- formance criterion is being measured.
quirements when the machine was purchased.
The next use of the data is to match dies to The most critical machine functions are
the machine and to accurately estimate future described in this chapter along with how the
production rates. This second use of capability performance is measured. Some of these have
data is the most routine use. The third use of been discussed to some level of detail in preced-
such data is to detect any long term deteriora- ing chapters.
tion of the machine's capabilities. Then when
deterioration is detected, the scheduling of the
necessary maintenance and repair to return Plunger Velocity
the machine to it's original performance.
As described in chapters 5 and 6, there are two or
The nominal capability of any single machine three plunger velocities of importance. These are:
function is the À rst aspect to consider. An ex-
Close pour hole
ample is the rated clamping tonnage. Another
example is the maximum dry shot speed (i.e. Slow shot
the PV 2 diagram) at a speciÀ ed hydraulic sys- Fast shot
Chapte r 7 Measu ring Machine Capabi l it ies
0
800 psi
32
1000 psi 1200 psi
40
1 33 42
2 34 43
The actual velocity with no metal in the shot
3 36 45
sleeve must be calibrated to the † ow control 4 37 47
46
Measu ring Machine Capabi l it ies Chapte r 7
1300
diagram is shown here
1200
(plotted on a linear veloc-
1100 ity scale) for a particular
1000 machine. The graph also
900 shows a die resistance
800 line. The lines intersect
P
S
700 (i.e. at 148 inches per
I
S
h
600 second) at the maximum
500
o
t
plunger velocity obtain-
P 400
r able with that die.
e 300
s
s 200
u
r 100
e
0
0
1 2 3 4 5 6 7 8 9
1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2
0 0 0 0 0 0 0 0 0
0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5
Plunger Velocity IPS
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Max. Vel. Binary at #63 Load Max. Vel. at selected Binary Setting
ally plotted as a histogram so the pattern of the NADCA course on Process Control, and
variation can be observed. Then the standard there are many good books and courses on sta-
deviation, , is calculated. Plus three sigma tistical methods besides the NADCA materials.
(+ 3 ) to minus three sigma (-3 ) is usually
considered to be the process capability. The One will usually À nd that the variability of
procedures and calculations are described in the machine making dry (i.e. no metal in the
Subgroup 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Size = 5 Start data in cell C-15
A2= 0.577 153.5 153.6 153.8 153.6 153.3 153.7 153.5 153.6 153.4 153.5 153.2 153.4 153.3 153.6 153.2 153.3 153.7 153.2 153.8 153.5
D4= 2.114 153.2 153.4 153.4 153.6 153.2 153.6 153.3 153.8 153.5 153.5 153.7 153.5 153.4 153.8 153.6 153.3 153.5 153.5 153.5 153.4
d2= 2.326 153.4 153.3 153.5 153.1 153.2 153.5 153.4 153.4 153.8 153.7 153.3 153.6 153.9 153.6 153.4 153.3 153.6 153.2 153.7 153.6
153.2 153.8 153.9 153.5 153.3 153.5 153.3 153.4 153.8 153.4 153.7 153.5 153.4 153.5 153.6 153.5 153.7 153.8 153.4 153.7
153.0 153.8 153.1 153.4 153.4 153.6 153.4 153.6 153.8 153.6 153.7 153.5 153.9 153.8 153.4 153.4 153.4 153.5 153.7 153.3
USL 155.0
UCL 153.7
XBar 153.3 153.6 153.5 153.4 153.3 153.6 153.4 153.6 153.7 153.5 153.5 153.5 153.6 153.7 153.4 153.4 153.6 153.4 153.6 153.5
LCL 153.3
LSL 152.0
UCL 0.835
Range 0.5 0.5 0.8 0.5 0.2 0.2 0.2 0.4 0.4 0.3 0.5 0.2 0.6 0.3 0.4 0.2 0.3 0.6 0.4 0.4
LCL 0
Std. Div. 0.195 0.228 0.321 0.207 0.084 0.084 0.084 0.167 0.195 0.114 0.249 0.071 0.295 0.134 0.167 0.089 0.130 0.251 0.164 0.158
Max Datum = 153.9 Max XBar = 153.7 Max Range = 0.8 1 Sigma = 0.170
Min Datum = 153.0 Min XBar = 153.3 Min Range = 0.2 6 Sigma = 1.019
Difference = 0.9 Difference = 0.40 Difference = 0.6 Z USL = 8.827
Max Datum % above XDBar = 0.26 XDBar = 153.5 RBar = 0.395 Z LSL = 8.839
Min Datum % below XDBar = 0.33 C pk = 17.33
Cp= 2.944
Figure 7-3 The data shown here is for the fast shot speed of a new machine making dry shots at a speciü c
† ow control valve setting. The data is for creating an SPC chart.
47
Chapte r 7 Measu ring Machine Capabi l it ies
XBar
155.0 Figure 7-4 The aver-
ages from Figure 7-3 are
plotted here as an X-bar
154.5
chart with control limits.
154.0
153.5
153.0
152.5
152.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Subgroup Number
shot sleeve) shots is vary small. Figure 7-3 7-4 and 7-5. In Figure 7-5, the À rst À ve groups
shows actual data from a capability study for show a somewhat greater range per group than
the fast shot of a new machine at a particular do the later groups. These initial trends might
fast shot Á ow control valve opening. The data be the result of the warming of the hydraulic
was taken without molten metal in the shot Á uid during the À rst few machine cycles.
sleeve, and the plunger and shot sleeve were at
room temperature and well oiled. The actual capability of the shot performance
is also captured in the data. In Figure 7-3, the
The data is not presented to actually show average speed of all 100 shots is 153.51 inches
a true process capability. Rather, the data is per second and the six sigma (+/- 3 ) varia-
organized, and the calculations made, to create tion is 1.019 (+/- 0.51) inches per second. If the
a statistical process control (SPC) system using shot speed and valve setting relationship is
average and range charts as shown in Figures as shown in Figure 7-1, the 153.5 inches per
7-4 and 7-5. But, the data do show the very second speed would be valve setting 53 at 800
small variation in plunger speed. The data in psi. If the system pressure is 1200 psi, it would
Figure 7-6 shows a slight tend to faster speeds be valve setting of 42 but the machine is 2.5
during the À rst 25 shots, and then a leveling inches per second short of meeting the expected
off. The same data is divided into À ve groups speed. Probably a negligible error.
of À ve data points per group in Figures 7-3,
Range
0.9
0.5
0.4
0.3
0.2
0.1
UCL Range LCL
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Subgroup Number
48
Measu ring Machine Capabi l it ies Chapte r 7
Trend
155
Figure 7-6 All the data
collected for ¿ gures 7-3, 7-4
154.5
and 7-5 are plotted here
in sequence to display
154
any trend. The À rst 25
shots show a slight trend
153.5
in increasing speed.
153
152.5
152
1 4 7
1 1 1 1 2 2 2 3 3 3 4 4 4 4 5 5 5 6 6 6 7 7 7 7 8 8 8 9 9 9
0 3 6 9 2 5 8 1 4 7 0 3 6 9 2 5 8 1 4 7 0 3 6 9 2 5 8 1 4 7 1
0
Shot Number 0
Greater variation is introduced when mak- change signal, and the time to achieve the new
ing actual shots. The heat from the molten velocity once response has started, can be mea-
metal causes the plunge and the shot sleeve sured and quantiÀ ed.
(cold chamber) to change size and shape. The
plunger is water cooled and a different geom- The primary speed changes are:
etry than the shot sleeve, so it will not change
shape the same as will the shot sleeve. Also, Slow to Fast shot speeds
the radial expansion of the shot sleeve is con- Start of Low Impact
tained by the die at the biscuit end, so the
thermal expansion is forced inward to some
degree causing the shot sleeve to close in on Pressure
the biscuit. The result is a constantly changing
friction and/or sticking between the plunger The capabilities of the hydraulic pressures in
and the shot sleeve that affects the speed of the the various machine systems can also be quan-
plunger. SERVO shot systems will correct for tiÀ ed in terms of the ability to adjust the pres-
these varying conditions within some range of sure to any particular speciÀ ed pressure (i.e.
capability. the average pressure) and the pressure varia-
tion over time (i.e. the plus and minus three
standard deviations). The primary system pres-
Process capability studies of the shot perfor-
sures are:
mance may be highly useful for the production
process while making castings. These stud-
Machine closing system
ies can identify what variation is normal and
reasonable for the particular machine and die Shot system
combination.
Piston pressure during slow shot
49
Chapte r 7 Measu ring Machine Capabi l it ies
Clamping Force
The actual force obtainable on each tie bar and
the total force when the machine is clamped
onto a master test block is another capabil-
ity (both average and variation) that can be
quantiÀ ed with a capability test. Like the shot
speed, the tie bar loading will probably be more
variable when operating on a real die than
when clamping on the test block.
Ejector speed
Ejector force
Review Questions
1. List some of the data you must collect during a
capability test.
50
CHAP T E R
EIGHT
ACCUMULATOR SYSTEMS
accumulators used for die casting machine shot Nitrogen Charge Valve
Sight Gage
systems. These are:
Electrical Circuit
Accumulator
With an internal piston
Shot Circuit with Pistonless Accumulator Figure 8-2 Shown here is a typical accumula-
tor circuit using an accumulator with an inter-
Figure 8-1 shows a typical die casting shot hy- nal piston and a separate tank to achieve the
draulic circuit with an accumulator without an required volume of nitrogen. This circuit is for
internal piston. cold chamber machines.
On all hot chamber machines and the older Accumulators with pistons can be mounted
cold chamber machines the accumulator is on the shot cylinder head and the separate
mounted at the back of the machine on the nitrogen tank is mounted on the "C" frame. By
"helper's" side. The newer cold chamber ma- mounting the accumulator at the head of the
chines have it mounted to the helper's side of shot cylinder, the shot line (i.e. the hydraulic
the front plate. Some cold chamber machines piping) between the accumulator and the shot
have the accumulator mounted to the "C" frame cylinder is eliminated. By eliminating the
near the shot cylinder column of hydraulic † uid contained in the shot
52
Accumulato r Systems Chapte r 8
line, the impact force at the end of the shot Electrical Circuit
cylinder stroke is reduced. The hydraulic † uid Accumulator
† ows directly from the accumulator through the Nitrogen Charge Line
pilot operated check valve and the intensiü er
check valves and into the cylinder. The amount
of † uid in motion is minimized and with large
porting in the cylinder head, the velocity of the Pressure Switch
Accumulator Drain
IntensiÀ er Accumulator with Piston
Relief Valve with Devent 4-way
53
Chapte r 8 Accumulato r Systems
valve to energize, the relief valve to (The accumulator pressure will also
de-vent and the pump to load after increase.) Hold the pressure at each
the motor is started. 100 psi increment for approximately
À ve (5) minutes and check for leaks.
Step 3: (For accumulators without pistons Continue making these pressure in-
only) Start the pump. The machine creases until the pressure reaches 300
must be in the manual operation mode psi. above the maximum required op-
and with the relief valve at it's lowest erating pressure. Hold the pressure at
pressure (at or below 100 psi) setting. this maximum for at least 15 minutes.
Step 4: Open the nitrogen charge valve. If a fastener was not properly tightened, or if
CAUTION! Remain clear of the outlet an "O" ring is missing or improperly installed,
of the charge valve. Nitrogen in the it may show up as a leak sometime during the
accumulator can blow out at a high test. Finding such conditions is the purpose of
velocity and can be harmful. the test, but not having a leak during the test
is no guarantee that these types of Á aws do not
Step 5a: (Accumulators without pistons only) exist in the accumulator system.
Open the accumulator shut off valve
to allow the accumulator to À ll with Note: The maximum test pressure must be
hydraulic Á uid. As the accumulator equal to, or above, the running pressure, but
is À lling, the air/nitrogen can escape must not exceed the maximum capacity of the
out of the nitrogen charge valve. machine's hydraulic components.
When the Á uid reaches this valve,
Step 7: Shut off the pump.
the Á uid will start to come out of
the valve. Close the nitrogen charge
Step 8: Open the accumulator drain valve.
valve immediately. When using this
Opening the drain valve allows the
procedure, part of the air in the ac-
hydraulic Á uid to drain back into the
cumulator is bled off and lowers the
reservoir. The accumulator shut off
stored energy in the accumulator
valve must be open while draining ac-
for the test. The accumulator will
cumulators without internal pistons.
continue to À ll. When it is full, the
pressure in the accumulator will be
Step 9: Put a small amount of nitrogen (50
the same as the relief valve setting
(i.e. 100 psi max.) psi max.) into the accumulator as
the hydraulic Á uid is draining. Ni-
trogen in the accumulator puts the
Step 5b: (Accumulators with a piston) Start Á uid under pressure and helps drain
the pump. With the pump running, the accumulator faster. Add nitro-
Á uid will enter the accumulator and gen as needed.
push the piston to the top. The air/
nitrogen in the accumulator on top of Step 10: (Accumulators without internal
the piston will be pushed out through pistons) Shut off the accumulator
the nitrogen charge valve. With the drain valve immediately when the
air/nitrogen bled off, there will be very Á uid is out of the accumulator. The
little stored energy in the accumulator last Á uid that leaves the accumula-
for the test. When the piston reaches tor will be mixed with nitrogen and
the top, the pressure in the accumu- will sound like stones going through
lator below the piston will be at the the drain valve. If nitrogen is allowed
relief valve setting (i.e. 100 psi max.) to enter the reservoir, the Á uid will
become aerated and cause damage to
Step 6: Increase the pressure setting on the the pumps and hydraulic components
relief valve in 100 psi. increments. when the pump(s) are started.
54
Accumulato r Systems Chapte r 8
55
Chapte r 8 Accumulato r Systems
the pressure. To À nd the exact pres- Step 5: Decide on what the À nal pressure in
sure at which the pressure switch is the accumulator is to be at the start
now set refer to the section on "Test of the shot. This pressure should be
the Pressure Switch Setting" below. noted on the process set up sheet for
the die and machine being used. This
Note: When the accumulator is charged to is the pressure required in the accu-
the ü nal required pressure, no more † uid is mulator at the time the shot cylinder
needed in the accumulator. The pumps are starts to move forward.
now unloaded by using the relief valve venting
circuit. The purpose of this venting circuit is to
Step 6: Pre-charge the accumulator with ni-
save power.
trogen to what is speciÀ ed on the hy-
Note: The contacts in the pressure switch draulic circuit or tag on the machine.
being used to cause the de-vent directional For example, it the shot pressure is
valve to energize are now open which allows to be 1000 psi, and the pre-charge
the de-vent valve to de-energize. The opposite is 73%, then the nitrogen is charged
contacts in the switch are now closed. These until it reaches 730 psi (1000 x 0.73).
closed contacts allows (but does not actually
Nitrogen that is put into the accumu-
cause) the shot to be made. When the accumu-
lator under pressure before the hy-
lator pressure is below the required pressure,
the switch will not allow a shot to be made. It draulic Á uid is pumped in is referred
is critical that this switch be properly adjusted. to as the nitrogen pre-charge.
56
Accumulato r Systems Chapte r 8
Step 10: Adjust the pressure switch one quar- directional valve de-energizes, the
ter (1/4) turn more in the same (i.e. relief valve will de-vent and the
lower pressure) direction. This adjust- pump will be loaded.
ment will set the pressure difference
between the relief valve and the pres- Step 2: Close the accumulator drain valve.
sure switch at about 50 psi. As can The accumulator pressure will recov-
be seen, the pressure switch monitors er up to the pressure switch setting
(not controls) the pressure in the ac- and the de-vent directional valve will
cumulator. The relief valve controls again de-energize.
the pressure. To À nd the exact pres-
sure at which the pressure switch is Step 3: Read the pressure on the accumu-
now set refer to the section on "Test lator pressure gage. The pressure
the Pressure Switch Setting" below. read is the pressure setting of the
pressure switch. It must be between
Note: When the accumulator is charged to 50 and 75 psi lower than the À nal
the ü nal required pressure, no more † uid is required pressure. If it is not within
needed in the accumulator. The pumps are that range, adjust the setting and
now unloaded by using the relief valve venting repeat the procedure.
circuit. The purpose of this venting circuit is to
save power.
Note: The difference between the pressure
switch setting and the ü nal required pressure
Note: The contacts in the pressure switch be-
is not something to be concerned about. When
ing used to cause the de-vent directional valve
the machine begins to close in the semi-auto
to energize is now open which allows the de-
or auto cycle the de-vent directional valve will
vent valve to de-energize. The opposite contacts
be energized by other contacts in the machine
in the switch are now closed. These closed con-
control circuit. The energizing of the de-vent di-
tacts allows (but does not actually cause) the
rectional valve causes the accumulator to "top
shot to be made. When the accumulator pres-
off" to the relief valve setting before the shot is
sure is below the required pressure, the switch
made. So every shot will have the same accu-
will not allow a shot to be made. It is critical
mulator pressure at the beginning of the shot.
that this switch be properly adjusted.
57
Chapte r 8 Accumulato r Systems
Step 4: Adjust the pressure switch as de- The accumulator does not recover to the same
scribed in the "Testing the Pressure pressure level each cycle.
Switch Setting" above.
Cause:
Fix: 3. Check the pump for volume efü ciency and repair
or replace the pump if needed.
Check all ü ttings that are exposed to the nitrogen.
Tighten the ü ttings that are leaking. Note: Never
tighten ü ttings with the accumulator charged. Problem 4:
Completely drain the accumulator before per-
forming any work. The Á uid level in the accumulator continues to
drop during the time the shot rod is forward.
Problem 2: Cause:
The shot relay will not energize, so the shot The shot cylinder and/or the shot valves are leak-
cycle will not start. ing allowing a continuous † ow of hydraulic † uid
from the accumulator to the reservoir during the
Causes: dwell time in the cycle.. The most likely cause for
the leakage is component wear.
1. The pressure switch is set too high and the pres-
sure in the accumulator will not trip the switch. Fix:
2. The relief valve setting is too low. The pressure Repair the shot cylinder and/or the shot valves.
in the accumulator is not high enough to trip the
pressure switch.
Problem 5:
3. The relief and/or de-vent directional valves are
worn, keeping the pressure in the accumulator The shot does not "hit hard" (the condition is
from building up to the required level. sometimes referred to as a "spongy" shot) and
58
Accumulato r Systems Chapte r 8
1. Bleed the air out of the shot cylinder when the Fix:
piston is forward and under pressure. Use a high
Drain all the hydraulic † uid and nitrogen from the
pressure hose and needle valve and direct the
† uid into a container. accumulator and repair or replace the shut off
valve. Then return to problem 7.
2. Shut the machine down until the air has come
out of the † uid. This can, in some instances, take
several days. The aerated † uid may have to be Troubleshooting Typical
replaced, the aerated † uid stored to allow the air Problems with Accumulators
to come out, and then the † uid is used later.
with Internal Pistons
Problem 6:
Problem 1:
Sight gage leaks
The pressure in the accumulator drops too low
Fix: during the forward stroke of the shot.
59
Chapte r 8 Accumulato r Systems
Fix: Fix:
1. Check for leaks and make necessary repairs 4. Repair or replace the relief valve and/or the de-
vent directional valve.
2. Tighten the charge valve. It is advisable to put
a pipe plug in the valve outlet to help seal the 5. Check the electrical circuit. The de-vent direc-
nitrogen. tional valve must be energized each cycle as the
machine starts to close.
Problem 3: 6. Check the pump for volume efü ciency and repair
or replace the pump if needed.
The plunger comes to a near stop during the
forward stroke and then continues forward very
Problem 6:
slowly.
The accumulator drains when the machine is
Cause:
not running.
The accumulator ran out of hydraulic † uid because
the piston had reached the bottom. The percent of Cause:
nitrogen is too high.
The accumulator pilot operated check valve, the
Fix: charge line check valve, the pressure switch or the
accumulator drain valve is leaking internally.
Charge the accumulator with the correct amount
of nitrogen. Follow the "Charging Accumulator Fix:
Procedure".
Check each valve and determine which one is leak-
ing. Drain the accumulator completely of hydrau-
Problem 4: lic † uid and nitrogen and repair/replace the
leaking valve.
The pressure level in the accumulator continues
to drop during the time the shot rod is forward. Problem 7:
Cause:
The de-vent directional valve energizes and de-
The shot cylinder is leaking. The most likely compo- energizes every few seconds.
nent in the cylinder assembly that needs repair is
the piston rings or the cylinder sleeve. Cause:
The accumulator does not recover to the same 1. Repair or replace the valves.
pressure after each cycle.
2. Close the accumulator drain valve.
Cause: 3. Recharge the accumulator. Follow the "Recharg-
ing Accumulator" procedure.
1. The relief valve and/or directional valves are
worn.
60
Accumulato r Systems Chapte r 8
Cause: Fix:
2. Aerated hydraulic † uid 2. Repair or replace the intensiü er or the pilot oper-
ated check valve.
Fix:
1. Bleed the air out of the shot cylinder when the Review Questions:
piston is forward and under pressure. Use a high
pressure hose and needle valve and direct the 1. Accumulators are used on die casting machines to:
† uid into a container.
a. Cushion the shot
2. Shut the machine down until the air has come
out of the † uid. This can, in some instances, take b. Store hydraulic power
several days. The aerated † uid may have to be
c. Save energy
replaced, and the aerated † uid stored to allow
the air to come out, and then used later. 2. The term "nitrogen pre-charge" refers to:
The pressure in the intensiÀ cation accumulator b. Using nitrogen to move hydraulic † uid
drops too low during intensiÀ cation. c. Compressing nitrogen when hydraulic † uid
is pumped into the accumulator.
Cause:
3. The function of the nitrogen is to:
1. The nitrogen pre-charge is too low.
a. Hold the hydraulic † uid at the bottom of the
2. The seals on the accumulator piston are leaking. accumulator
61
Chapte r 8 Accumulato r Systems
a. Required pressure in the accumulator at the a. One half of the way up in the accumulator.
start of the shot. b. Two thirds of the way up in the accumulator.
b. Pressure on the metal when the cavity is full. c. One third of the way up in the accumulator.
c. Pressure in the shot cylinder. 11. When hydraulic Á uid is taken out of an accumu-
5. The component in the system that controls the lator, the pressure in the accumulator goes:
À nal required pressure is the: a. Up.
a. Pressure switch. b. Down.
b. Relief valve. c. Stays the same.
c. Pump. 12. If nitrogen leaks from the accumulator while the
6. When the de-vent directional control valve de-en- machine is running, the Á uid level in the accu-
ergizes, the: mulator goes:
c. Save power
8. Pressure switches:
62
CHAP T E R
NINE
PREVENTIVE MAINTENANCE
SUMMARY
The traveling plate supports must be supporting Shot System: Hot Chamber
the plate so there is no weight applied to the tie
bars The gooseneck must locate in the saddle ("A"
Die carriers must be used when needed frame) to maintain alignment between the goose-
neck bore and the hydraulic shot cylinder
The machine lubrication system must be working
The saddle supporting bushings must be in good
properly
condition and greased with high temperature
grease so the nozzle adjustment and force can be
Ejector System maintained
64
CHAP T E R
APPENDIX A
Answers in Bold
a. Open and close the die on a straight line keeping the parting surfaces parallel.
c. Provide power for moving cores in the die and for ejection.
5. How can the casting process and quality of the casting be affected if the clamping force is too
high? It will be difü cult for the die to vent.
6. If the die is not positioned on the machine centerline will the clamping force of the individual tie
bars be affected? Yes, the load on the tie bar closest to the die will be the highest.
7. The limit as to how far an individual tie bar may be adjusted away from the "home" position is
a. +/- 5%
b. +/1 25%
c. +/- 10%
8. If an 8 inch diameter tie bar stretches 0.0139 inches over 40 inches of length, what is the load on
the tie bar?
260 tons
66
Review Quest ion Answe rs Chapte r Appendix A
Answers in Bold
2. If a die is too small for a machine what damage that can occur to the machine?
The traveling and front plates will become bent.
4. The machine provides clamping force. If that force is used effectively depends on the die.
True
5. If a die is not centered between the tie bars of the machine the load on the tie bars is affected.
True
6. Will the total available clamping force be affected if the die is not centered between the tie bars?
Yes
67
Chapte r Appendix A Review Quest ion Answe rs
Answers in Bold
2. The die casting machine provides the power to eject the casting.
True
3. The lengths of all the ejector rods must be the same within:
0.005 inch
4. If a casting is not ejected from the cavity in a straight line, the casting may become __________.
bent or cracked
a. Bumper plate
b. Center hydraulic
68
Review Quest ion Answe rs Chapte r Appendix A
Answers in Bold
2. What are the four phases of the shot process and the primary purpose of each?
1. Slow shot velocity: Controls the wave formation of metal in the cold
chamber while the chamber is being ü lled
3. Fast shot velocity: Provides the desired gate velocity and cavity ü lling time
69
Chapte r Appendix A Review Quest ion Answe rs
Answers in Bold
2. What are the four phases of the shot process and the primary purpose of each?
3. Fast shot velocity: Provides the desired gate velocity and cavity ü lling time
5. What is the purpose of the plunger pressure during casting solidiü cation?
Apply pressure to the molten metal to feed shrinkage in the casting as the shrinkage
develops during solidi ü cation.
70
Review Quest ion Answe rs Chapte r Appendix A
Answers in Bold
1. Velocity
3. Pressure
4. Time
5. Clamping force
2. How, and for what purpose, can these data collected in question 1, be used?
71
Chapte r Appendix A Review Quest ion Answe rs
Answers in Bold
5. The component in the system that controls the ü nal required pressure is the:
Relief valve.
8. Pressure switches:
Monitor the accumulator pressure
10. If an accumulator is pre-charged with nitrogen to a pressure of 666 psi and reaches 1000 psi
when the hydraulic † uid is pumped in, the † uid level will be:
One third of the way up in the accumulator.
11. When hydraulic † uid is taken out of an accumulator, the pressure in the accumulator goes:
Down.
12. If nitrogen leaks from the accumulator while the machine is running, the † uid level in the ac-
cumulator goes:
Up.
72
CHAP T E R
APPENDIX B
1. The Master Test Block must be made to À t the 2. The thickness of the "Hot Roll Plates" should be:
machine for which it will be used. For best
results the block must cover at least 50% of the 200 thru 400 ton 3" thick
plate surface between the ti bar centers. Tie 500 ton 4" thick
bar centers multiplied by 0.707 will equal the
minimum length of one side of the block. The 600 and 800 ton 5" thick
block must be square. The thickness of the block 1000 thru 1600 ton 6" thick
must match the die height speciÀ cations of the
1600 ton and above 8" thick
machine.
74
NORTH AMERICAN DIE CASTING ASSOCIATION