Académique Documents
Professionnel Documents
Culture Documents
This article needs additional citations for verification. Please help improve this
article by adding citations to reliable sources. Unsourced material may be
challenged and removed.
Find sources: "Deep foundation" � news � newspapers � books � scholar � JSTOR
(January 2013) (Learn how and when to remove this template message)
File:Deep foundation drilling.ogv
Drilling of deep piles of diameter 150cm in bridge 423 near Nes Ziona, Israel
Contents
1 Driven foundations
1.1 Pile foundation systems
1.2 Monopile foundation
2 Drilled piles
2.1 Under-reamed piles
2.2 Augercast pile
2.3 Pier and grade beam foundation
3 Specialty piles
3.1 Micropiles
3.2 Tripod piles
3.3 Sheet piles
3.4 Soldier piles
3.5 Screw piles
3.6 Suction Piles
3.7 Adfreeze Piles
3.8 Vibrated stone columns
3.9 Hospital Piles or Gallow Piles
4 Piled walls
4.1 Secant piled walls
4.2 Slurry walls
5 Deep mixing/mass stabilization techniques
6 Classification of pile with respect to type of material
6.1 Timber
6.2 Iron
6.3 Steel
6.4 Prestressed concrete piles
6.5 Composite piles
7 Aquatic pilings/Marine pilings
8 See also
9 Notes
10 References
11 External links
Driven foundations
Monopile foundation
A monopile foundation utilizes a single, generally large-diameter, foundation
structural element to support all the loads (weight, wind, etc.) of a large above-
surface structure.
A large number of monopile foundations[3] have been utilized in recent years for
economically constructing fixed-bottom offshore wind farms in shallow-water subsea
locations.[4] For example, the Horns Rev wind farm from 2002 in the North Sea west
of Denmark utilizes 80 large monopiles of 4 metres diameter sunk 25 meters deep
into the seabed,[5] while the Lynn and Inner Dowsing Wind Farm off the coast of
England went online in 2008 with over 100 turbines, each mounted on a 4.7-metre-
diameter monopile foundation in ocean depths up to 18 metres of water.[6]
The typical construction process for a wind turbine subsea monopile foundation in
sand includes driving a large hollow steel pile, of some 4 m in diameter with
approximately 50mm thick walls, some 25 m deep into the seabed, through a 0.5 m
layer of larger stone and gravel to minimize erosion around the pile. A "transition
piece (complete with pre-installed features such as boat-landing arrangement,
cathodic protection, cable ducts for sub-marine cables, turbine tower flange,
etc.)" is attached to the now deeply driven pile, the sand and water are removed
from the centre of the pile and replaced with concrete. An additional layer of even
larger stone, up to 0.5 m diameter, is applied to the surface of the seabed for
longer-term erosion protection.[4]
Drilled piles
For end-bearing piles, drilling continues until the borehole has extended a
sufficient depth (socketing) into a sufficiently strong layer. Depending on site
geology, this can be a rock layer, or hardpan, or other dense, strong layers. Both
the diameter of the pile and the depth of the pile are highly specific to the
ground conditions, loading conditions, and nature of the project. Pile depths may
vary substantially across a project if the bearing layer is not level.
Drilled piles can be tested using a variety of methods to verify the pile integrity
during installation.
Under-reamed piles
Under-reamed piles have mechanically formed enlarged bases that are as much as 6 m
in diameter.[citation needed] The form is that of an inverted cone and can only be
formed in stable soils. The larger base diameter allows greater bearing capacity
than a straight-shaft pile.
These pile are suited for expansive soils which are often subjected to seasonal
moisture variations, as also filled up ground and loose or soft strata. They are
used in normal ground condition also where economics are favorable. [7][full
citation needed]
Augercast pile
An augercast pile, often known as a continuous flight augering (CFA) pile, is
formed by drilling into the ground with a hollow stemmed continuous flight auger to
the required depth or degree of resistance. No casing is required. A cement grout
mix is then pumped down the stem of the auger. While the cement grout is pumped,
the auger is slowly withdrawn, conveying the soil upward along the flights. A shaft
of fluid cement grout is formed to ground level. Reinforcement can be installed.
Recent innovations in addition to stringent quality control allows reinforcing
cages to be placed up to the full length of a pile when required. A typical
reinforcing cage will consist of 4 to 8 bars from #5 to #8 bars typically 1/3 the
length of the pile with longitudinal circular ties spaced along the length of the
cage. Where tension loads are present it is typical to see a single full length bar
placed at the center of each pile.
Augercast piles cause minimal disturbance, and are often used for noise and
environmentally sensitive sites. Augercast piles are not generally suited for use
in contaminated soils, due to expensive waste disposal costs. In cases such as
these however a displacement pile may provide the cost efficiency of an augercast
pile and minimal environmental impact. In ground containing obstructions or cobbles
and boulders, augercast piles are less suitable as refusal above the design pile
tip elevation may be encountered. In certain cases drill motors that produce more
torque and horsepower may be able to mitigate these events.[citation needed]
Specialty piles
Micropiles
Micropiles, also called mini piles, are often used for underpinning. They are also
used to create foundations for a variety of project types, including highway,
bridge and transmission tower projects. They are especially useful at sites with
difficult or restricted access, or with environmental sensitivity.[9][10]
Micropiles are made of steel with diameters of 60 to 200 mm. Installation of
micropiles through top soil, sand and cobblestones overburden and into soil rock
can be achieved using Air Rotary or Mud Rotary drilling, impact driving, jacking,
vibrating or screwing machinery.[11] Micropiles can also be used to construct a
grout column around the shaft of a standard Helical Pile system, allowing for use
in higher load applications.[12]
Tripod piles
The use of a tripod rig to install piles is one of the more traditional ways of
forming piles. Although unit costs are generally higher than with most other forms
of piling,[citation needed] it has several advantages which have ensured its
continued use through to the present day. The tripod system is easy and inexpensive
to bring to site, making it ideal for jobs with a small number of piles.
Sheet piles
Sheet piles are used to restrain soft soil above the bedrock in this excavation
Sheet piling is a form of driven piling using thin interlocking sheets of steel to
obtain a continuous barrier in the ground. The main application of sheet piles is
in retaining walls and cofferdams erected to enable permanent works to proceed.
Normally, vibrating hammer, t-crane and crawle drilling are used to establish sheet
piles.[citation needed]
Soldier piles
The horizontal earth pressures are concentrated on the soldier piles because of
their relative rigidity compared to the lagging. Soil movement and subsidence is
minimized by maintaining the lagging in firm contact with the soil.[citation
needed]
Soldier piles are most suitable in conditions where well constructed walls will not
result in subsidence such as over-consolidated clays, soils above the water table
if they have some cohesion, and free draining soils which can be effectively
dewatered, like sands.[citation needed]
Unsuitable soils include soft clays and weak running soils that allow large
movements such as loose sands. It is also not possible to extend the wall beyond
the bottom of the excavation and dewatering is often required.[citation needed]
Screw piles
Screw piles, also called helical piers and screw foundations, have been used as
foundations since the mid 19th century in screw-pile lighthouses.[13] Screw piles
are galvanized iron pipe with helical fins that are turned into the ground by
machines to the required depth. The screw distributes the load to the soil and is
sized accordingly.
Suction Piles
Suction piles are used underwater to secure floating platforms. Tubular piles are
driven into the seabed (or more commonly dropped a few metres into a soft seabed)
and then a pump sucks water out at the top of the tubular, pulling the pile further
down.
The proportions of the pile (diameter to height) are dependent upon the soil type.
Sand is difficult to penetrate but provides good holding capacity, so the height
may be as short as half the diameter. Clays and muds are easy to penetrate but
provide poor holding capacity, so the height may be as much as eight times the
diameter. The open nature of gravel means that water would flow through the ground
during installation, causing 'piping' flow (where water boils up through weaker
paths through the soil). Therefore, suction piles cannot be used in gravel seabeds.
[citation needed]
Adfreeze Piles
Adfreeze piles derive their strength from the bond of the frozen ground around them
to the surface of the pile.[citation needed]
Adfreeze pile foundations are particularly sensitive in conditions which cause the
permafrost to melt. If a building is constructed improperly, it will heat the
ground below resulting in a failure of the foundation system.[citation needed]
Piled walls
Sheet piling, by a bridge, was used to block a canal in New Orleans, United States
after Hurricane Katrina damaged it.
These methods of retaining wall construction employ bored piling techniques,
normally CFA or rotary. They provide special advantages where available working
space dictates that basement excavation faces be vertical. Both methods offer
technically effective and offer a cost efficient temporary or permanent means of
retaining the sides of bulk excavations even in water bearing strata. When used in
permanent works, these walls can be designed to accommodate vertical loads in
addition to moments and horizontal forces. Construction of both methods is the same
as for foundation bearing piles. Contiguous walls are constructed with small gaps
between adjacent piles. The size of this space is determined by the strength of the
soils.
Slurry walls
A slurry wall is a barrier built under ground using a mix of bentonite and water to
prevent the flow of groundwater. A trench that would collapse due to the hydraulic
pressure in the surrounding soil does not collapse as the slurry balances the
hydraulic pressure.
Cement, lime/quick lime, flyash, sludge and/or other binders (sometimes called
stabilizer) are mixed into the soil to increase bearing capacity. The result is not
as solid as concrete, but should be seen as an improvement of the bearing capacity
of the original soil.
The technique is most often applied on clays or organic soils like peat. The mixing
can be carried out by pumping the binder into the soil whilst mixing it with a
device normally mounted on an excavator or by excavating the masses, mixing them
separately with the binders and refilling them in the desired area. The technique
can also be used on lightly contaminated masses as a means of binding contaminants,
as opposed to excavating them and transporting to landfill or processing.
A main consideration regarding timber piles is that they should be protected from
rotting above groundwater level. Timber will last for a long time below the
groundwater level. For timber to rot, two elements are needed: water and oxygen.
Below the groundwater level, dissolved oxygen is lacking even though there is ample
water. Hence, timber tends to last for a long time below groundwater level. In
1648, the Royal Palace of Amsterdam was constructed on 13659 timber piles that
still survive today since they were below groundwater level. Timber that is to be
used above the water table can be protected from decay and insects by numerous
forms of wood preservation using pressure treatment (alkaline copper quaternary
(ACQ), chromated copper arsenate (CCA), creosote, etc.).
Splicing timber piles is still quite common and is the easiest of all the piling
materials to splice. The normal method for splicing is by driving the leader pile
first, driving a steel tube (normally 60�100 cm long, with an internal diameter no
smaller than the minimum toe diameter) half its length onto the end of the leader
pile. The follower pile is then simply slotted into the other end of the tube and
driving continues. The steel tube is simply there to ensure that the two pieces
follow each other during driving. If uplift capacity is required, the splice can
incorporate bolts, coach screws, spikes or the like to give it the necessary
capacity.
Iron
Iron may be used for piling. These may be ductile.[15]
Steel
Pipe piles can be driven either open end or closed end. When driven open end, soil
is allowed to enter the bottom of the pipe or tube. If an empty pipe is required, a
jet of water or an auger can be used to remove the soil inside following driving.
Closed end pipe piles are constructed by covering the bottom of the pile with a
steel plate or cast steel shoe.
In some cases, pipe piles are filled with concrete to provide additional moment
capacity or corrosion resistance. In the United Kingdom, this is generally not done
in order to reduce the cost. In these cases corrosion protection is provided by
allowing for a sacrificial thickness of steel or by adopting a higher grade of
steel. If a concrete filled pipe pile is corroded, most of the load carrying
capacity of the pile will remain intact due to the concrete, while it will be lost
in an empty pipe pile.
Steel pipe piles can either be new steel manufactured specifically for the piling
industry or reclaimed steel tubular casing previously used for other purposes such
as oil and gas exploration.
H-Piles are structural beams that are driven in the ground for deep foundation
application. They can be easily cut off or joined by welding or mechanical drive-
fit splicers. If the pile is driven into a soil with low pH value, then there is a
risk of corrosion, coal-tar epoxy or cathodic protection can be applied to slow or
eliminate the corrosion process. It is common to allow for an amount of corrosion
in design by simply over dimensioning the cross-sectional area of the steel pile.
In this way, the corrosion process can be prolonged up to 50 years.
Prestressed concrete piles
Concrete piles are typically made with steel reinforcing and prestressing tendons
to obtain the tensile strength required, to survive handling and driving, and to
provide sufficient bending resistance.
Long piles can be difficult to handle and transport. Pile joints can be used to
join two or more short piles to form one long pile. Pile joints can be used with
both precast and prestressed concrete piles.
Composite piles
A "composite pile" is a pile made of steel and concrete members that are fastened
together, end to end, to form a single pile. It is a combination of different
materials or different shaped materials such as pipe and H-beams or steel and
concrete.
See also
Eurocode EN 1997
International Society for Micropiles
Post in ground construction also called earthfast or posthole construction; a
historic method of building wooden structures.
Stilt house, also known as a lake house; an ancient, historic house type built on
pilings.
Shallow foundations
Pile bridge