LOSA ALIGERADA F´C 175 KG/CM2 COSTO UNITARIO M3

25 M3/ DIA
DESCRIPCION UNIDADCUADRICANTIDPRECIO PARCIAL
MANO DE OBRA
CAPATAZ HH 0.1200 14.27 1.71 6.88 0.83
OPERARIO HH 0.9600 11.80 11.33 6.25 6.00
OFICIAL HH 0.6400 10.64 6.81 4.38 2.80
PEON HH 3.5200 9.61 33.83 3.75 13.20
OPERADOR EQUIPOLIV HH 0.6400 10.64 6.81 6.25 4.00
60.49 26.83
MATERIALES
ARENA GRUESA M3 0.57 30.00 17.10
PIEDRA CHANCADA M3 0.58 75.00 43.50
CEMENTO BLS 8.85 19.80 175.23
235.83 235.83
EQUIPO
HERRAMIENTAS MANUAL %MO 0.03 60.49 1.81 0.80
MEZCLADORA HM 0.3200 10.00 3.20 3.20
VIBRADOR HN 0.3200 10.00 3.20 3.20
8.21 7.20
TOTAL 304.53 269.86

LOSA ALIGERADA F´C 210 KG/CM2 COSTO UNITARIO M3


25 M3/ DIA
DESCRIPCION UNIDADCUADRICANTIDPRECIO PARCIAL
MANO DE OBRA
CAPATAZ HH 0.1200 14.27 1.71 6.88 0.83
OPERARIO HH 0.9600 11.80 11.33 6.25 6.00
OFICIAL HH 0.6400 10.64 6.81 4.38 2.80
PEON HH 3.5200 9.61 33.83 3.75 13.20
OPERADOR EQUIPOLIV HH 0.6400 10.64 6.81 6.25 4.00
60.49 26.83
MATERIALES
ARENA GRUESA M3 0.55 30.00 16.50
PIEDRA CHANCADA M3 0.56 75.00 42.00
CEMENTO BLS 10.21 19.80 202.16
260.66 260.66
EQUIPO
HERRAMIENTAS MANUAL %MO 0.03 60.49 1.81 0.80
MEZCLADORA HM 0.3200 10.00 3.20 3.20
VIBRADOR HN 0.3200 10.00 3.20 3.20
8.21 7.20
TOTAL 329.36 294.69
ALIGERADO ENCOFRADO Y DESENCOFR COSTO UNITARIO M2
15 M2 DIA
DESCRIPCION UNIDADCUADRICANTIDPRECIO PARCIAL
MANO DE OBRA
CAPATAZ HH 0.1000 0.05 14.27 0.76 6.88 0.36
OPERARIO HH 1.0000 0.53 11.80 6.25 6.25 3.31
OFICIAL HH 1.0000 0.53 10.64 5.64 4.38 2.32
PEON HH 1.0000 0.53 9.61 5.09 3.75 1.99
17.74 7.98
MATERIALES
CLAVOS PARA MADERA 0.25 3.50 0.88
ALAMBRE NEGRO N 8 0.40 3.50 1.40
MADERA TORNILLO 5.10 3.50 17.85
20.13 20.13
EQUIPO
HERRAMIENAS MANUALES %MO 0.03 17.74 0.53 0.24
0.53
TOTAL 38.40 28.35
costos unitarios ELECTRI

INSTALACIONES ELECTRICAS

SALIDA PARA TECHO C/CABLE AWG TW 2.5 MM (14) + DUCTO PVC SEL 18 MM(5/8)

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.16


OPERARIO HH 1.0000 1.60
PEON HH 1.0000 1.60

MATERIALES
CABLE TW # 14 AWG 2.5 MM M 9.00
CAJA RECTANGULAR GALV. 4" x 2 1/8" UNID 0.50
CAJA OCTOGONAL GALV. 4" x 2 1/8" UNID 1.00
INTERRUPTOR DE BAQUELITA 25OV-15 AM M3 1.00
CINTA AISLANTE UNID 0.10
TUB. PVC SEL P/INST. ELECTRICA 5/8" X 3 M PZA 1.50
CURVA LIVIANO PVC SAP P/INST. ELEC. 5/8" UNID 3.00
CONEXIÓN CAJA PVC SEL P/INS ELECT 5/8" UNID 2.00

EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL

SALIDA DE PARED C/CABLE AWG TW 4.0 MM (12) + DUCTO PVC SEL 1 MM(3/4)

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.20


OPERARIO HH 1.0000 2.00
PEON HH 0.7500 1.50

MATERIALES
CABLE TW # 12 AWG 4.0 MM M 9.00
CAJA RECTANGULAR GALV. 4" x 2 1/8" UNID 0.50
CAJA OCTOGONAL GALV. 4" x 2 1/8" UNID 1.00
CINTA AISLANTE UNID 0.10
TUB. PVC SAP P/INST. ELECTRICA 3/4" X 3 M PZA 1.50
CURVA PESADO PVC SAP P/INST. ELEC. 3/4" UNID 1.00
CURVA LIVIANO PVC SEL P/INST. ELEC. 3/4" UNID 1.00
EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL

SALIDA PARA SPOT LIGHT CON PVC

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.16


OPERARIO HH 1.0000 1.60
PEON HH 0.7500 1.20

MATERIALES
CABLE TW # 14 AWG 2.5 MM M 9.00
INTERRUPTOR SIMPLE BIPOLAR BAKELITA UNID 0.90
SPOT LIGHT CROMADO UNID 1.00
CAJA OCTOGONAL GALV. LIVIANA 4" x 4" X 2 1/2 UNID 1.43
CINTA AISLANTE PZA 0.10
TUB PVC SEL P/INST ELECT DE 5/8" X 3 M UNID 1.32

EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL

SALIDA PARA CENTROS DE LUZ C/ INTERRUPTOR DE CONMUTACION

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.20


OPERARIO HH 1.0000 2.00
PEON HH 0.7500 1.50

MATERIALES
CABLE TW # 14 AWG 2.5 MM M 9.00
CAJA RECTANGULAR GALV. 4" x 2 1/8" UNID 1.00
CAJA OCTOGONAL GALV. 4" x 2 1/8" UNID 1.00
INTERRUPTOR DE CONMUTACION UNID 1.00
CINTA AISLANTE UNID 0.10
TUB. PVC SEL P/INST. ELECTRICA 3/4" X 3 M PZA 1.50
CURVA LIVIANO PVC SAP P/INST. ELEC. 3/4" UNID 3.00
CONEXIÓN CAJA PVC SEL P/INS ELECT 3/4" UNID 3.00
EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL

SALIDA PARA TOMACORRIENTES BIPOLARES SIMPLE CON PVC

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.16


OPERARIO HH 1.0000 1.60
PEON HH 0.7500 1.20

MATERIALES
CABLE TW # 14 AWG 2.5 MM M 8.15
CAJA RECTANGULAR GALV. 4" x 2 1/8" UNID 1.00
TOMACORRIENTE SIMPLE PLANO BAKELITA UNID 1.00
CINTA AISLANTE UNID 0.10
TUB. PVC SEL P/INST. ELECTRICA 3/4" X 3 M PZA 1.50
UNION PVC SEL 3/4" UNID 1.00
CONEXIÓN CAJA PVC SEL P/INS ELECT 3/4" UNID 2.00

EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL

SALIDA PARA TOMACORRIENTES BIPOLARES DOBLE CON PVC

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.16


OPERARIO HH 1.0000 1.60
PEON HH 0.7500 1.20

MATERIALES
CABLE TW # 14 AWG 2.5 MM M 8.15
CAJA RECTANGULAR GALV. 4" x 2 1/8" UNID 1.00
TOMACORRIENTE DOBLE PLANO BAKELITA UNID 1.00
CINTA AISLANTE UNID 0.10
TUB. PVC SEL P/INST. ELECTRICA 3/4" X 3 M PZA 1.50
UNION PVC SEL 3/4" UNID 1.00
CONEXIÓN CAJA PVC SEL P/INS ELECT 3/4" UNID 2.00
EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL

SALIDA PARA TERMA CON PVC

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.16


OPERARIO HH 1.0000 1.60
PEON HH 0.7500 1.20

MATERIALES
CABLE TW # 12 AWG 2.5 MM M 1.70
CAJA OCTOGONAL GALV. 4" x 2 1/8" UNID 1.00
PLACA SALIDA THERMA UNID 1.00
CINTA AISLANTE UNID 0.10
TUB. PVC SEL P/INST. ELECTRICA 5/8" X 3 M PZA 1.50
CURVA LIVIANO PVC SAP P/INST. ELEC. 5/8" UNID 3.00

EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL

SALIDA DE FUERZA PARA COCINA CON PVC

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.10


OPERARIO HH 1.0000 1.00
PEON HH 1.0000 1.00

MATERIALES
CABLE TW # 10 AWG M 10.50
CAJA OCTOGONAL GALV. 4" x 2 1/8" UNID 1.00
CINTA AISLANTE UNID 0.10
TUB. PVC SAP P/INST. ELECTRICA 1" X 3 M PZA 1.20
CURVA LIVIANO PVC SEL P/INST. ELEC. 1" UNID 1.00

EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL
SALIDA PARA TELEFONO DIRECTO( DE SERVICIO PUBLICO)

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.27


OPERARIO HH 1.0000 2.67
PEON HH 0.7500 2.00

MATERIALES
CAJA RECTANGULAR. LIVIANA 4" X 2 1/2 UNID 1.00
PLACA DE SALIDA TELEVISION Y TELEFONO UNID 1.00
TUB PVC SEL P/INST ELECT DE 5/8" X 3 M UNID 1.40
CURVA LIVIANO PVC SEL P/INST. ELEC. 5/8" UNID 1.00

EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL
SALIDA PARA ANTENA DE TELEVISION CON PVC
DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.20


OPERARIO HH 1.0000 2.00
PEON HH 0.7500 1.50

MATERIALES
CAJA RECTANGULAR. LIVIANA 4" X 2 1/2 UNID 1.00
PLACA DE SALIDA TELEVISION Y TELEFONO UNID 1.00
TUB PVC SEL P/INST ELECT DE 5/8" X 3 M UNID 1.50
CURVA LIVIANO PVC SEL P/INST. ELEC. 5/8" UNID 1.00

EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL
SALIDA PARA TIMBRE TIPO GONG CON PVC

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.20


OPERARIO HH 1.0000 2.00
PEON HH 0.7500 3.00

MATERIALES
CABLE TW # 8 M 9.00
PULSADOR UNIPOLAR SIMPLE UNID 1.00
CAJA RECTANGULAR GALV. 4" x 2 1/8" UNID 2.00
TIMBRE DING GONG UNID 1.00
CINTA AISLANTE UNID 0.10
TUB. PVC SEL P/INST. ELECTRICA 5/8" X 3 M PZA 2.00
CURVA LIVIANO PVC SAP P/INST. ELEC. 1/2" UNID 2.00

EQUIPOS
HERRAMIENTAS %MO 5.00

TOTAL

TUBERIA PVC SAP (ELECTRICAS) D=3/4"

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.03


OPERARIO HH 1.0000 0.27
PEON HH 1.0000 0.27

MATERIALES
PEGAMENTO PARA TUBRIA FORDUIT GL 8.15
TUB. PVC SEL P/INST. ELECTRICA 3/4" X 3 M UNID
CURVA PVC SAP LUZ 3/4" UNID 1.00
UNION PVC SEL 3/4" UNID 1.00

EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL

TUBERIA PVC SAP (ELECTRICAS) 1"

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.03


OPERARIO HH 1.0000 0.32
PEON HH 1.0000 0.32

MATERIALES
PEGAMENTO PARA TUBERIA FORDUIT GL 8.15
TUB. PVC SEL P/INST. ELECTRICA 1" X 3 M UNID 1.00
CURVA PVC SAP LUZ 1" UNID 1.00
UNION PVC SEL 1" UNID 0.10

EQUIPOS
HERRAMIENTAS %MO 3.00

TOTAL
TABLERO DE DISTRIBUCION 12 POLOS

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.40


OPERARIO HH 1.0000 4.00
PEON HH 0.5000 2.00

MATERIALES
TABLERO DE DISTRIBUCION DE 12 POLOS UNID 1.00

EQUIPOS
HERRAMIENTAS %MO 3.00

TABLERO DE DISTRIBUCION 2 X 30 AMP

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.05


OPERARIO HH 1.0000 0.50
PEON HH 0.5000 0.25

MATERIALES
TABLERO DE MONOFASICO 2 X 30 AMP UNID 1.00

EQUIPOS
HERRAMIENTAS %MO 3.00

TABLERO DE DISTRIBUCION TRIFASICO 3 X 30 AMP

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.05


OPERARIO HH 1.0000 0.50
PEON HH 0.5000 0.25

MATERIALES
TABLERO DE TRIFASICO 3 X 30 AMP UNID 1.00
EQUIPOS
HERRAMIENTAS %MO 3.00

TABLERO DE DISTRIBUCION TRIFASICO 3 X 60 AMP

DESCRIPCION UNIDAD CUADRILLA CANTIDAD

MANO DE OBRA

CAPATAZ HH 0.1000 0.05


OPERARIO HH 1.0000 0.50
PEON HH 0.5000 0.25

MATERIALES
TABLERO DE TRIFASICO 3 X 60 AMP UNID 1.00

EQUIPOS
HERRAMIENTAS %MO 3.00
nitarios ELECTRICAS

PRECIO PARCIAL P/REDUC TOTAL

12.65 2.02 6.88 1.10


11.50 18.40 6.25 10.00
9.00 14.40 3.75 6.00
34.82 17.10

1.20 10.80
2.00 1.00
2.00 2.00
4.50 4.50
4.00 0.40
5.00 7.50
1.50 4.50
0.50 1.00
31.70 31.70

34.82 1.04 0.05

67.57 48.85

PRECIO PARCIAL P/REDUC TOTAL

12.65 2.53 6.88 1.38


11.50 23.00 6.25 12.50
9.00 13.50 6.25
39.03 20.13

1.80 16.20
2.00 1.00
2.00 2.00
4.00 0.40
6.00 9.00
1.20 1.20
1.20 1.20
31.00 31.00

39.03 1.17 0.06

71.20 51.19

PRECIO PARCIAL P/REDUC TOTAL

12.65 2.02 0.00 0.00


11.50 18.40 0.00 0.00
9.00 10.80 0.00
31.22 #VALUE!

1.20 10.80
4.50 4.05
15.00 15.00
3.00 4.29
4.00 0.40
5.00 6.61

41.15 41.15

31.22 0.94 #VALUE!

73.31 #VALUE!

PRECIO PARCIAL P/REDUC TOTAL

12.65 2.53 0.00 0.00


11.50 23.00 0.00 0.00
9.00 13.50 0.00 0.00
39.03 0.00

1.20 10.80
2.00 2.00
2.00 2.00
5.00 5.00
4.00 0.40
5.00 7.50
1.20 3.60
0.80 2.40
33.70 33.70
39.03 1.17 0.00

73.90 33.70

PRECIO PARCIAL P/REDUC TOTAL

12.65 2.02 0.00 0.00


11.50 18.40 0.00 0.00
9.00 10.80 0.00 0.00
31.22 0.00

1.20 9.78
2.00 2.00
5.00 5.00
4.00 0.40
5.00 7.50
1.50 1.50
0.80 1.60
27.78 27.78

31.22 0.94 0.00

59.94 27.78

PRECIO PARCIAL P/REDUC TOTAL

12.65 2.02 0.00 0.00


11.50 18.40 0.00 0.00
9.00 10.80 0.00 0.00
31.22 0.00

1.20 9.78
2.00 2.00
6.00 6.00
4.00 0.40
5.00 7.50
1.50 1.50
0.80 1.60
28.78 28.78
31.22 0.94 0.00

60.94 28.78

PRECIO PARCIAL P/REDUC TOTAL

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00

0.00 0.00
#REF! #REF!
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
#REF! #REF!

0.00 0.00 0.00

#REF! #REF!

PRECIO PARCIAL P/REDUC TOTAL

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00

0.00 0.00
#REF! #REF!
0.00 0.00
0.00 0.00
#REF! #REF!
#REF! #REF!

0.00 0.00 0.00

#REF! #REF!
PRECIO PARCIAL P/REDUC TOTAL

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00 0.00

0.00 0.00

PRECIO PARCIAL P/REDUC TOTAL

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00 0.00

0.00 0.00

PRECIO PARCIAL P/REDUC TOTAL

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
#REF! #REF!
0.00 0.00
0.00 0.00
0.00 0.00
#REF! #REF!
#REF! #REF!

0.00 0.00 0.00

#REF! #REF!

PRECIO PARCIAL P/REDUC TOTAL

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00 0.00

0.00 0.00

PRECIO PARCIAL P/REDUC TOTAL

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
#VALUE!

0.00 0.00 0.00

#REF! #REF!

PRECIO PARCIAL P/REDUC TOTAL

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00 0.00

PRECIO PARCIAL P/REDUC TOTAL

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00 0.00

PRECIO PARCIAL P/REDUC TOTAL

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00 0.00

PRECIO PARCIAL P/REDUC TOTAL

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00 0.00


PRECIOS INSUMOS ELECTRICAS salario

CAPATAZ 12.6500 L12 6.875 m12 6.875


OPERARIO 11.5000 L13 6.250 m13 6.25
OFICIAL 10.0000 L14 4.375 m14 4.375
TOPOGRAF 11.5000 L15 6.250 m15 6.25
PEON 9.0000 L16 3.750 m16 3.75
CABLE # 8, AWG 6.00 MM 3.0000 L17
CABLE # 10, AWG 2.5 MM 2.0000 L18
CABLE # 12, AWG 4.0 MM 1.8000 L19
CABLE # 14, AWG 5.00 MM 1.2000 L20
CAJA RECTANGULAR GALV. 4" x 2 1/8" 2.0000 L21
CAJA OCTOGONAL GALV. 4" x 2 1/8" 2.0000 L22
CAJA GALV. 4" x 4 X 2 1/2" 3.0000 L23
TUB. PVC SEL P/INST. ELECT 5/8" X 3 M 5.0000 L24
TUB. PVC SEL P/INST. ELECT 3/4" X 3 M 6.0000 L25
TUB. PVC SEL P/INST. ELECT 1" X 3 M 8.0000 L26
TUB. PVC SAP P/INST. ELECT 3/4" X 3 M 15.0000 L27
CURVA PVC SAP P/INST. ELEC. 3/4" 1.2000 L28
CURVA PVC SAP P/INST. ELEC. 1" 2.0000 L29
CURVA PVC SEL P/INST. ELEC. 5/8" 1.5000 L30
CONEXIÓN CAJA PVC SEL P/INS ELECT 3/4" 0.8000 L31
CONEXIÓN CAJA PVC SEL P/INS ELECT 5/8" 0.5000 L32
CONEXIÓN CAJA PVC SAP P/INS ELECT 3/4" 2.0000 L33
INTERRUPTOR DE CONMUTAC 25OV-15 AM 5.0000 L34
INTERRUPTOR SIMPLE DE BAQUELITA 4.5000 L35
INTERRUPTOR DE BAQUELITA 25OV-15 AM 5.0000 L36
INTERRUPTOR TERMOMAGNETICO 2 X 30 A 60.0000 L37
INTERRUPTOR TERMOMAGNETICO 2 X 60 A 80.0000 L38
TOMACORRIENTE SIMPLE PLANO BAKELITA 5.0000 L39
TOMACORRIENTE DOBLE PLANO BAKELITA 6.0000 L30
UNION PVC 3/4" 1.5000 L41
TABLERO GABINETE 12 POLOS 150.0000 L42
PULSADOR UNIPOLAR SIMPLE 15.0000 L43
TIMBRE DIG DONG 25.0000 L44
SPOT LIGTH CROMADO 15.0000 L45
PLACA SALIDA TELEFONO TELEVISION 3.0000 L46
PLACA SALIDA TERMA 3.0000 L47
CINTA AISLANTE 4.0000 L48
PEGAMENTO PVC FORDUIT 15.0000 L49
O12
O13
O14
O15
O16
JUNTA DE DILATACION CON TEKNOPOR DE 1" COSTO UNITARIO M
30 M/ DIA
DESCRIPCION UNIDAD CUADRILLA CANTIDAD PRECIO PARCIAL
MANO DE OBRA
CAPATAZ HH 0.1000 0.03 16.25 0.43
OPERARIO HH 1.0000 0.27 11.25 3.00
3.43
MATERIALES
ARENA GRUESA M3 0.01 35.00 0.35
ASFALTO RC 250 GLN 0.02 10.00 0.22
0.57
EQUIPO
HERRAMIENAS MANUALES %MO 0.03 3.43 0.10
0.10
TOTAL 4.11