Académique Documents
Professionnel Documents
Culture Documents
24
ELECTRIC INSTALLATION
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull
boxes, inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe ½" dia (15 mm i/d) 7.00 metre 52.82 per mtr. 369.74
2 Clamp ½" dia (15 mm i/d) 10.00 Nos. 4.00 each 40.00
3 G.I bend ½" dia (15 mm i/d) 1.00 No. 8.00 each 8.00
4 Gutties 20.00 Nos. 6.00 dozen 10.00
5 Screw 1" to ¾" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
6 Inspection box ½" dia (15 mm) 1.00 No. 2.08 each 2.08
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 437.45
Contractor's Profit & Overh 20 Percent 87.49
Total 524.94
Material per metre 479.84 ÷ 7 74.99 74.99
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Labour rate per Metre Rs. 17.42 Say 17.40
Labour rate per Rft Rs. 5.31 Say 5.30
Composite rate per Metre Rs. 92.42 Say 92.40
Composite rate per Rft Rs. 28.18 Say 28.20
Page 1
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe ¾" dia (20 mm i/d) 7.00 metre 68.07 per mtr. 476.49
2 G.I bend ¾" dia (20 mm i/d) 1.00 No. 14.00 each 14.00
3 Clamp ¾" dia (20 mm i/d) 10.00 Nos. 6.00 each 60.00
4 Gutties 20.00 Nos. 6.00 dozen 10.00
5 Screw 1" to ¾" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
6 Inspection box ¾" dia (20 mm) 1.00 No. 2.33 each 2.33
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 570.45
Contractor's Profit & Overh 20 Percent 114.09
Total 684.54
Material per metre 626.14 ÷ 7 97.79 97.79
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 2
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe 1" dia (25 mm i/d) 7.00 metre 99.90 per mtr. 699.30
2 G.I bend 1" dia (25 mm i/d) 1.00 No. 18.00 each 18.00
3 Clamp 1" dia (25 mm i/d) 10.00 Nos. 8.00 each 80.00
4 Gutties 20.00 Nos. 6.00 dozen 10.00
5 Screw ¾" to 1" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
6 Inspection box 1" dia (25 mm) 1.00 No. 2.33 each 2.33
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 817.26
Contractor's Profit & Overh 20 Percent 163.45
Total 980.71
Material per metre 897.63 ÷ 7 140.10 140.10
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 3
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe 1¼" dia (32 mm i/d) 7.00 metre 125.03 per mtr. 875.21
2 Clamp 1¼" dia (32 mm i/d) 10.00 Nos. 10.00 each 100.00
3 G.I bend 1¼" dia (32 mm i/d) 1.00 No. 30.00 each 30.00
4 M.S. Inspection box 1¼" dia (32 mm) 1.00 No. 2.33 each 2.33
5 Gutties 20.00 Nos. 6.00 dozen 10.00
6 Screw ¾" to 1" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 1025.17
Contractor's Profit & Overh 20 Percent 205.03
Total 1230.21
Material per metre 1126.33 ÷ 175.74 175.74
Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40
ITEM RATES
Page 4
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe 1½" dia (40 mm i/d) 7.00 metre 150.06 per mtr. 1050.42
2 G.I bend 1½" dia (40 mm i/d) 1.00 Nos. 38.00 each 38.00
3 M.S. Inspection box 1½" dia (40 mm) 1.00 No. 2.67 each 2.67
4 G.I. Clamp 1½" dia (40 mm i/d) 10.00 Nos. 10.00 each 100.00
5 Gutties 20.00 Nos. 6.00 dozen 10.00
6 Screw 1 to ¾" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 1208.72
Contractor's Profit & Overh 20 Percent 241.74
Total 1450.46
Material per metre 1330.43 ÷ 207.21 207.21
Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40
ITEM RATES
Page 5
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe 2" dia (50 mm i/d) 7.00 metre 199.27 per mtr. 1394.89
2 G.I bend 2" dia (50 mm i/d) 1.00 No. 65.00 each 65.00
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. 2.66 each 2.66
4 G.I. Clamp 2" dia (50 mm i/d) 10.00 Nos. 12.00 each 120.00
5 Gutties 20.00 Nos. 6.00 dozen 10.00
6 Screw 1 to ¾" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 1600.18
Contractor's Profit & Overh 20 Percent 320.04
Total 1920.22
Material per metre 1758.85 ÷ 274.32 274.32
Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40
ITEM RATES
Page 6
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe 3" dia (80 mm i/d) 7.00 metre 329.65 per mtr. 2307.55
2 G.I. Clamp 3" dia (80 mm i/d) 10.00 Nos. 18.00 each 180.00
3 M.S. Inspection box 3" dia (80 mm) 1.00 No. 2.67 each 2.67
4 G.I bend 3" dia (80 mm i/d) 1.00 No. 175.00 each 175.00
5 Gutties 20.00 Nos. 6.00 dozen 10.00
6 Screw 1 to ¾" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 2682.85
Contractor's Profit & Overh 20 Percent 536.57
Total 3219.42
Material per metre 2949.77 ÷ 459.92 459.92
Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40
ITEM RATES
Page 7
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.
1 G.I. Pipe ½" dia (15 mm i/d) 7.00 metre 52.82 per mtr. 369.74
2 G.I. Bend ½" dia (15 mm i/d) 1.00 Nos. 8.00 each 8.00
3 Hooks 8.00 No. 2.00 each 16.00
4 M.S. Inspection box ½" dia (15 mm) 1.00 Nos. 2.08 each 2.08
5 Cement 0.021 Cft. 230.00 P. Bag 4.83
6 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 400.93
Contractor's Profit & Overh 20 Percent 80.19
Total 481.12
Material per metre 442.55 ÷ 7 68.73 68.73
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 8
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.
1 G.I. Pipe ¾" dia (20 mm i/d) 7.00 metre 68.07 per mtr. 476.49
2 G.I. Bend ¾" dia (20 mm i/d) 1.00 Nos. 14.00 each 14.00
3 Hooks 7.00 No. 2.00 each 14.00
4 M.S. Inspection box ¾" dia (20 mm) 1.00 Nos. 2.33 each 2.33
5 Cement 0.021 Cft. 230.00 P. Bag 4.83
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 512.28
Contractor's Profit & Overh 20 Percent 102.46
Total 614.74
Material per metre 564.44 ÷ 7 87.82 87.82
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 9
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.
1 G.I. Pipe 1" dia (25 mm i/d) 7.00 metre 99.90 per mtr. 699.30
2 G.I. Bend 1" dia (25 mm i/d) 1.00 Nos. 18.00 each 18.00
3 Hooks 8.00 No. 1.67 each 13.36
4 M.S. Inspection box 1" dia (25 mm) 1.00 Nos. 2.33 each 2.33
5 Cement 0.052 Cft. 230.00 P. Bag 11.96
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 745.58
Contractor's Profit & Overh 20 Percent 149.12
Total 894.70
Material per metre 820.19 ÷ 7 127.81 127.81
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 10
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.
1 G.I. Pipe 1¼" dia (32 mm i/d) 7.00 metre 125.03 per mtr. 875.21
2 G.I. Bend 1¼" dia (32 mm i/d) 1.00 Nos. 30.00 each 30.00
3 Hooks 8.00 No. 4.00 each 32.00
4 M.S. Inspection box 1¼" dia (32 mm) 1.00 Nos. 2.33 each 2.33
5 Cement 0.063 Cft. 230.00 P. Bag 14.49
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 954.66
Contractor's Profit & Overh 20 Percent 190.93
Total 1145.59
Material per metre 1046.69 ÷ 163.66 163.66
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 11
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.
1 G.I. Pipe 1½" dia (40 mm i/d) 7.00 metre 150.06 per mtr. 1050.42
2 G.I. Bend 1½" dia (40 mm i/d) 1.00 Nos. 38.00 each 38.00
3 M.S. Inspection box 1½" dia (40 mm i/d) 1.00 No. 2.67 each 2.67
4 Hooks 8.00 Nos. 4.00 each 32.00
5 Cement 0.074 Cft. 230.00 P. Bag 17.02
6 Sand 0.20 Cft. 350.00 Per % Cft. 0.70
Total 1140.81
Contractor's Profit & Overh 20 Percent 228.16
Total 1368.97
Material per metre 1252.99 ÷ 195.57 195.57
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 12
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.
1 G.I. Pipe 2" dia (50 mm i/d) 7.00 metre 199.27 per mtr. 1394.89
2 G.I. Bend 2" dia (50 mm i/d) 1.00 Nos. 65.00 each 65.00
3 M.S. Inspection box 2" dia (50 mm i/d) 1.00 No. 2.66 each 2.66
4 Hooks 8.00 Nos. 6.00 each 48.00
5 Cement 0.084 Cft. 230.00 P. Bag 19.32
6 Sand 0.24 Cft. 350.00 Per % Cft. 0.84
Total 1530.71
Contractor's Profit & Overh 20 Percent 306.14
Total 1836.85
Material per metre 1679.21 ÷ 262.41 262.41
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 13
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.
1 G.I. Pipe 3" dia (80 mm i/d) 7.00 metre 329.65 per mtr. 2307.55
2 G.I. Bend 3" dia (80 mm i/d) 1.00 No. 175.00 each 175.00
3 M.S. Inspection box 3" dia (80 mm) 1.00 No. 2.67 each 2.67
4 Hooks 8.00 Nos. 8.00 each 64.00
5 G.I. Socket 3" dia (80 mm) 1.00 No. 45.00 each 45.00
6 Cement 0.08 Cft. 230.00 P. Bag 19.32
7 Sand 0.24 Cft. 350.00 Per % Cft. 0.84
Total 2614.38
Contractor's Profit & Overh 20 Percent 522.88
Total 3137.25
Material per metre 2871.23 ÷ 448.18 448.18
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 14
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe ½" dia (16 mm) 7.00 metre 27.39 per mtr. 191.73
2 M.S. Bend ½" dia (16 mm) 1.00 No. 7.00 each 7.00
3 M.S. Inspection box ½" dia (16 mm) 1.00 No. 24.96 dozen 2.08
4 Clamps ½" dia (16 mm) 10.00 Nos. 2.00 each 20.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00
Total 228.83
Contractor's Profit & Overh 20 Percent 45.77
Total 274.59
Material per metre 251.69 ÷ 7 39.23 39.23
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 15
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe ¾" dia (20 mm) 7.00 metre 34.28 per mtr. 239.96
2 M.S. Bend ¾" dia (20 mm) 1.00 No. 12.00 each 12.00
3 M.S. Inspection box ¾" dia (20 mm) 1.00 No. 27.96 per doz. 2.33
4 M.S. Clamps ¾" dia (20 mm) 10.00 Nos. 3.00 each 30.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00
7 Cement 0.02 Cft. 230.00 P. Bag 4.83
8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21
Total 297.35
Contractor's Profit & Overh 20 Percent 59.47
Total 356.82
Material per metre 325.92 ÷ 7 50.97 50.97
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 16
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 1" dia (25 mm) 7.00 metre 43.20 per mtr. 302.40
2 M.S. Bend 1" dia (25 mm) 1.00 No. 16.00 each 16.00
3 M.S. Inspection box 1" dia (25 mm) 1.00 No. 27.96 per doz. 2.33
4 M.S. Clamps 1" dia (25 mm) 10.00 Nos. 6.00 each 60.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00
7 Cement 0.042 Cft. 230.00 P. Bag 9.66
8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42
Total 398.83
Contractor's Profit & Overh 20 Percent 79.77
Total 478.59
Material per metre 334.40 ÷ 7 68.37 68.37
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 17
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 1¼" dia (32 mm) 7.00 metre 56.39 per mtr. 394.73
2 M.S. Conduit Bend 1¼" dia (32 mm) 1.00 No. 27.50 each 27.50
3 M.S. Inspection box 1¼" dia (32 mm) 1.00 No. 28.00 per doz. 2.33
4 M.S. Clamps 1¼" dia (32 mm) 10.00 Nos. 8.00 each 80.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00
7 Cement 0.042 Cft. 230.00 P. Bag 9.66
8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42
Total 522.66
Contractor's Profit & Overh 20 Percent 104.53
Total 627.19
Material per metre 572.62 ÷ 7 89.60 89.60
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 18
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 1½" dia (40 mm) 7.00 metre 65.25 per mtr. 456.75
2 M.S. Bend 1½" dia (40 mm) 1.00 No. 38.00 each 38.00
3 M.S. Inspection box 1½" dia (40 mm) 1.00 No. 32.00 per doz. 2.67
4 M.S. Clamps 1½" dia (40 mm) 10.00 Nos. 8.00 each 80.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00
7 Cement 0.042 Cft. 230.00 P. Bag 9.66
8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42
Total 595.51
Contractor's Profit & Overh 20 Percent 119.10
Total 714.62
Material per metre 652.76 ÷ 7 102.09 102.09
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 19
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 2" dia (50 mm) 7.00 metre 81.00 per mtr. 567.00
2 M.S. Conduit Bend 2" dia (50 mm) 1.00 No. 62.00 each 62.00
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. 32.00 per doz. 2.67
4 M.S. Clamps 2" dia (50 mm) 10.00 Nos. 10.00 each 100.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00
7 Cement 0.042 Cft. 230.00 P. Bag 9.66
8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42
Total 749.76
Contractor's Profit & Overh 20 Percent 149.95
Total 899.72
Material per metre 822.43 ÷ 7 128.53 128.53
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 20
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.
1 M.S. Conduit pipe ½" dia (16 mm) 7.00 metre 27.39 per mtr. 191.73
2 M.S. Bend ½" dia (16 mm) 1.00 No. 7.00 each 7.00
3 M.S. Inspection box ½" dia (16 mm) 1.00 No. 24.96 per doz. 2.08
4 M.S. Hooks 10.00 Nos. 2.00 each 20.00
5 Cement 0.021 Cft. 230.00 P. Bag 4.83
6 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 225.92
Contractor's Profit & Overh 20 Percent 45.18
Total 271.10
Material per metre 247.29 ÷ 7 38.73 38.73
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 21
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.
1 M.S. Condict pipe ¾" dia (20 mm) 7.00 metre 34.28 per mtr. 239.96
2 M.S. Bend ¾" dia (20 mm) 1.00 No. 12.00 each 12.00
3 M.S. Inspection box ¾" dia (20 mm) 1.00 No. 27.96 per doz. 2.33
4 M.S. Hooks 10.00 Nos. 2.00 each 20.00
5 Cement 0.042 Cft. 230.00 P. Bag 9.66
6 Sand 0.12 Cft. 350.00 Per % Cft. 0.42
Total 284.37
Contractor's Profit & Overh 20 Percent 56.87
Total 341.24
Material per metre 310.12 ÷ 7 48.75 48.75
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 22
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.
1 M.S. Conduit pipe 1" dia (25 mm) 7.00 metre 43.20 per mtr. 302.40
2 M.S. Bend 1" dia (25 mm) 1.00 No. 16.00 each 16.00
3 M.S. Inspection box 1" dia (25 mm) 1.00 No. 27.96 per doz. 2.33
4 Hooks 10.00 Nos. 2.00 each 20.00
5 Cement 0.052 Cft. 230.00 P. Bag 11.96
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 353.32
Contractor's Profit & Overh 20 Percent 70.66
Total 423.98
Material per metre 385.81 ÷ 7 60.57 60.57
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 23
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.
1 M.S. Conduit pipe 1¼" dia (32 mm) 7.00 metre 56.39 per mtr. 394.73
2 M.S. Conduit Bend 1¼" dia (32 mm) 1.00 No. 27.50 each 27.50
3 M.S. Inspection box 1¼" dia (32 mm) 1.00 No. 28.00 per doz. 2.33
4 M.S. Hooks 10.00 Nos. 4.00 each 40.00
5 Cement 0.063 Cft. 230.00 P. Bag 14.49
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 479.68
Contractor's Profit & Overh 20 Percent 95.94
Total 575.62
Material per metre 524.22 ÷ 7 82.23 82.23
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 24
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.
1 M.S. Conduit pipe 1½" dia (40 mm) 7.00 metre 65.25 per mtr. 456.75
2 M.S. Conduit Bend 1½" dia (40 mm) 1.00 No. 38.00 each 38.00
3 M.S. Inspection box 1½" dia (40 mm) 1.00 No. 32.00 per doz. 2.67
4 M.S. Hooks 10.00 Nos. 4.00 each 40.00
5 Cement 0.074 Cft. 230.00 P. Bag 17.02
6 Sand 0.20 Cft. 350.00 Per % Cft. 0.70
Total 555.14
Contractor's Profit & Overh 20 Percent 111.03
Total 666.16
Material per metre 606.56 ÷ 7 95.17 95.17
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 25
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.
(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.
1 M.S. Conduit pipe 2" dia (50 mm) 7.00 metre 81.00 per mtr. 567.00
2 M.S. Conduit Bend 2" dia (50 mm) 1.00 No. 62.00 each 62.00
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. 32.00 per doz. 2.67
4 Hooks 10.00 Nos. 6.00 each 60.00
5 Cement 0.084 Cft. 230.00 P. Bag 19.32
6 Sand 0.24 Cft. 350.00 Per % Cft. 0.84
Total 711.83
Contractor's Profit & Overh 20 Percent 142.37
Total 854.19
Material per metre 778.43 ÷ 7 122.03 122.03
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 26
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.
1 PVC pipe ½" dia (12 mm) 10.00 metre 8.25 per mtr. 82.50
2 PVC Bend ½" dia (12 mm) 2.00 No. 1.50 each 3.00
3 M.S. Hook 10.00 No. 2.00 each 20.00
4 PVC Inspection box ½" (12 mm) 2.00 Nos. 25.00 per doz. 4.17
5 Cement 0.042 Cft. 230.00 P. Bag 9.66
6 Sand 0.12 Cft. 350.00 Per % Cft. 0.42
Total 119.75
Contractor's Profit & Overh 20 Percent 23.95
Total 143.70
Material per metre 129.43 ÷ 1 14.37 14.37
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 27
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.
1 PVC pipe ¾" dia (20 mm) 10.00 metre 10.85 per mtr. 108.50
2 PVC Bend ¾" dia (20 mm) 2.00 No. 3.00 each 6.00
3 M.S. Hook 10.00 No. 2.00 each 20.00
4 PVC Inspection box ¾" dia (20 mm) 2.00 Nos. 25.00 per doz. 4.17
5 Cement 0.052 Cft. 230.00 P. Bag 11.96
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 151.26
Contractor's Profit & Overh 20 Percent 30.25
Total 181.51
Material per metre 163.53 ÷ 1 18.15 18.15
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 28
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.
1 PVC pipe 1" dia (25 mm) 10.00 metre 14.90 per mtr. 149.00
2 PVC Bend 1" dia (25 mm) 2.00 No. 4.00 each 8.00
3 M.S. Hook 10.00 No. 4.00 each 40.00
4 PVC Inspection box 1" dia (25 mm) 2.00 Nos. 28.00 per doz. 4.67
5 Cement 0.063 Cft. 230.00 P. Bag 14.49
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 216.79
Contractor's Profit & Overh 20 Percent 43.36
Total 260.14
Material per metre 235.03 ÷ 1 26.01 26.01
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 29
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.
1 PVC pipe 1¼" dia (30 mm) 10.00 metre 22.90 per mtr. 229.00
2 PVC Bend 1¼" dia (30 mm) 2.00 No. 6.00 each 12.00
3 M.S. Hook 10.00 No. 4.00 each 40.00
4 PVC Inspection box 1¼" dia (30 mm) 2.00 Nos. 28.00 per doz. 4.67
5 Cement 0.065 Cft. 230.00 P. Bag 14.95
6 Sand 0.37 Cft. 350.00 Per % Cft. 1.30
Total 301.91
Contractor's Profit & Overh 20 Percent 60.38
Total 362.29
Material per metre 228.053÷ 1 36.23 36.23
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 30
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.
1 PVC pipe 1½" dia (40 mm) 10.00 metre 33.60 per mtr. 336.00
2 PVC Bend 1½" dia (40 mm) 2.00 No. 9.00 each 18.00
3 M.S. Hook 10.00 No. 4.00 each 40.00
4 PVC Inspection box 1½" dia (40 mm) 2.00 Nos. 32.00 per doz. 5.33
5 Cement 0.070 Cft. 230.00 P. Bag 16.10
6 Sand 0.40 Cft. 350.00 Per % Cft. 1.40
Total 416.83
Contractor's Profit & Overh 20 Percent 83.37
Total 500.20
Material per metre 454.67 ÷ 1 50.02 50.02
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 31
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.
1 PVC pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50
2 PVC Bend 2" dia (50 mm) 2.00 No. 15.00 each 30.00
3 M.S. Hook 10.00 No. 4.00 each 40.00
4 Cement 0.084 Cft. 230.00 P. Bag 19.32
5 Sand 0.24 Cft. 350.00 Per % Cft. 0.84
Total 572.66
Contractor's Profit & Overh 20 Percent 114.53
Total 687.19
Material per metre 625.35 ÷ 1 68.72 68.72
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 32
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.
1 PVC pipe ½" dia (12 mm) 10.00 metre 8.25 per mtr. 82.50
2 PVC Bend ½" dia (12 mm) 2.00 Nos. 1.50 each 3.00
3 M.S. Clamp/saddle 20.00 Nos. 2.00 each 40.00
4 Gutties 20.00 Nos. 0.50 each 10.00
5 Screws for ½" dia clamp 20.00 Nos. 10.00 per doz. 16.67
6 PVC Inspection Box ½" dia (12 mm) 2.00 Nos. 25.00 per doz. 4.17
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21
Total 161.37
Contractor's Profit & Overh 20 Percent 32.27
Total 193.65
Material per metre 176.37 ÷ 1 19.36 19.36
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 33
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.
1 PVC pipe ¾" dia (20 mm) 10.00 metre 10.85 per mtr. 108.50
2 PVC Bend ¾" dia (20 mm) 2.00 Nos. 3.00 each 6.00
3 M.S. Clamp ¾" dia (20 mm) 10.00 Nos. 3.00 each 30.00
4 Screws for ¾" dia clamp 20.00 Nos. 10.00 per doz. 16.67
5 PVC Inspection Box ¾" dia (20 mm) 2.00 Nos. 25.00 per doz. 4.17
6 Cement 0.021 Cft. 230.00 P. Bag 4.83
7 Sand 0.06 Cft. 350.00 Per % Cft. 0.21
Total 170.37
Contractor's Profit & Overh 20 Percent 34.07
Total 204.45
Material per metre 186.27 ÷ 1 20.44 20.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 34
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.
1 PVC pipe 1" dia (25 mm) 10.00 metre 14.90 per mtr. 149.00
2 PVC Bend 1" dia (25 mm) 2.00 Nos. 4.00 each 8.00
3 M.S. Clamp/saddle 1 dia (25 mm) 20.00 Nos. 6.00 each 120.00
4 Screws for 1" dia clamp 20.00 Nos. 12.00 per doz. 20.00
5 Gutties 20.00 Nos. 6.00 per doz. 10.00
6 PVC Inspection Box 1" dia (25 mm) 2.00 Nos. 28.00 per doz. 4.67
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21
Total 316.71
Contractor's Profit & Overh 20 Percent 63.34
Total 380.05
Material per metre 347.23 ÷ 1 38.00 38.00
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 35
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.
1 PVC pipe 1¼" dia (30 mm) 10.00 metre 22.90 per mtr. 229.00
2 PVC Bend 1¼" dia (30 mm) 2.00 Nos. 6.00 each 12.00
3 M.S. Clamp/saddle 1¼" dia (30 mm) 20.00 Nos. 8.00 each 160.00
4 Gutties 20.00 Nos. 6.00 per doz. 10.00
5 Screws for 1¼" dia clamp 20.00 Nos. 15.00 per doz. 25.00
6 PVC Inspection Box 1¼" dia (30 mm) 2.00 Nos. 28.00 per doz. 4.67
Total 440.67
Contractor's Profit & Overh 20 Percent 88.13
Total 528.80
Material per metre 484.73 ÷ 1 52.88 52.88
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 36
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.
1 PVC pipe 1½" dia (40 mm) 10.00 metre 33.60 per mtr. 336.00
2 PVC Bend 1½" dia (40 mm) 2.00 Nos. 9.00 each 18.00
3 M.S. Clamp/saddle 1½" dia (40 mm) 20.00 Nos. 8.00 each 160.00
4 Gutties 20.00 Nos. 6.00 per doz. 10.00
5 Screws for 1½" dia clamp 20.00 Nos. 18.00 per doz. 30.00
6 PVC Inspection Box 1½" dia (40 mm) 2.00 Nos. 32.00 per doz. 5.33
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21
Total 564.37
Contractor's Profit & Overh 20 Percent 112.87
Total 677.24
Material per metre 619.67 ÷ 1 67.72 67.72
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 37
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.
1 PVC pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50
2 PVC Bend 2" dia (50 mm) 2.00 Nos. 15.00 each 30.00
3 M.S. Clamp/saddle 2" dia (50 mm) 20.00 Nos. 10.00 each 200.00
4 Gutties 20.00 Nos. 6.00 per doz. 10.00
5 Screws for 2" dia clamp 20.00 Nos. 30.00 per doz. 50.00
6 PVC Inspection Box 2" dia (50 mm) 2.00 Nos. 32.00 per doz. 5.33
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21
Total 782.66
Contractor's Profit & Overh 20 Percent 156.53
Total 939.20
Material per metre 860.02 ÷ 1 93.92 93.92
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 38
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe ½" dia (12 mm) 1.00 metre 14.40 per mtr. 14.40
2 Socket ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
3 Nipple ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
4 Check Nuts ½" dia (12 mm) 2.00 Nos. 5.00 each 10.00
5 Soldering etc. L.S 8.00
Total 46.40
Contractor's Profit & Overh 20 Percent 9.28
Total 55.68
Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72
ITEM RATES
Page 39
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe ¾" dia (20 mm) 1.00 metre 19.68 per mtr. 19.68
2 G.I. Socket ¾" dia (20 mm) 2.00 Nos. 5.00 each 10.00
3 G.I. Nipple ¾" dia (20 mm) 2.00 Nos. 6.00 each 12.00
4 Check Nuts ¾" dia (20 mm) 2.00 Nos. 8.00 each 16.00
5 Solder joint L.S 8.00
Total 65.68
Contractor's Profit & Overh 20 Percent 13.14
Total 78.82
Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72
ITEM RATES
Page 40
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe 1" dia (25 mm) 1.00 metre 22.60 per mtr. 22.60
2 G.I. Socket 1" dia (25 mm) 2.00 Nos. 7.00 each 14.00
3 G.I. Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
4 Check Nuts 1" dia (25 mm) 2.00 Nos. 12.00 each 24.00
5 Solder L.S 8.00
Total 84.60
Contractor's Profit & Overh 20 Percent 16.92
Total 101.52
Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72
ITEM RATES
Page 41
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe 1¼" dia (32 mm) 1.00 metre 29.52 per mtr. 29.52
2 G.I. Socket 1¼" dia (32 mm) 2.00 Nos. 12.00 each 24.00
3 G.I. Nipple 1¼" dia (32 mm) 2.00 Nos. 14.00 each 28.00
4 Check Nuts 1¼" dia (32 mm) 2.00 Nos. 16.00 each 32.00
5 Solder L.S 8.00
Total 121.52
Contractor's Profit & Overh 20 Percent 24.30
Total 145.82
Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72
ITEM RATES
Page 42
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe 1½" dia (40 mm) 1.00 metre 39.37 per mtr. 39.37
2 G.I. Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
3 G.I. Nipple 1½" dia (40 mm) 2.00 Nos. 20.00 each 40.00
4 Check Nuts 1½" dia (40 mm) 2.00 Nos. 20.00 each 40.00
5 Solder L.S 8.00
Total 157.37
Contractor's Profit & Overh 20 Percent 31.47
Total 188.84
Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72
ITEM RATES
Page 43
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe 2" dia (50 mm) 1.00 metre 55.77 per mtr. 55.77
2 G.I. Socket 2" dia (50 mm) 2.00 Nos. 21.00 each 42.00
3 G.I. Nipple 2" dia (50 mm) 2.00 Nos. 22.00 each 44.00
4 Check Nuts 2" dia (50 mm) 2.00 Nos. 25.00 each 50.00
5 Solder L.S 8.00
Total 199.77
Contractor's Profit & Overh 20 Percent 39.95
Total 239.72
Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72
ITEM RATES
Page 44
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe 3" dia (80 mm) 1.00 metre 110.00 per mtr. 110.00
2 G.I. Socket 3" dia (80 mm) 2.00 Nos. 45.00 each 90.00
3 G.I. Nipple 3" dia (80 mm) 2.00 Nos. 25.00 each 50.00
4 Check Nuts 3" dia (80 mm) 2.00 Nos. 20.00 each 40.00
5 Solder L.S 12.00
Total 302.00
Contractor's Profit & Overh 20 Percent 60.40
Total 362.40
Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72
ITEM RATES
Page 45
DESCRIPTION OF ITEM:
Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-main)
purposes including bends special etc., in floor, wall or trenches.
1 PVC Pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50
2 PVC Bend 2" dia (50 mm) 2.00 Nos. 15.00 each 30.00
3 M.S Hooks 10.00 Nos. 4.00 each 40.00
4 PVC Inspection box 2.00 Nos. 32.00 per doz. 5.33
5 Cement 0.084 Cft. 230.00 P. Bag 19.32
6 Sand 0.24 Cft. 350.00 Per % Cft. 0.84
Total 577.99
Contractor's Profit & Overh 20 Percent 115.60
Total 693.59
Material per metre 631.22 ÷ 69.36 69.36
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 46
DESCRIPTION OF ITEM:
Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-main)
purposes including bends special etc., in floor, wall or trenches.
1 PVC Pipe 3" dia (75 mm) 10.00 metre 66.75 per mtr. 667.50
2 PVC Bend 3" dia (75 mm) 2.00 Nos. 25.00 each 50.00
3 PVC Inspection box 2.00 Nos. 40.00 per doz. 6.67
4 Cement 0.106 Cft. 230.00 P. Bag 24.38
5 Sand 0.25 Cft. 350.00 Per % Cft. 0.88
Total 749.42
Contractor's Profit & Overh 20 Percent 149.88
Total 899.31
Material per metre 818.58 ÷ 89.93 89.93
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 47
DESCRIPTION OF ITEM:
Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-main)
purposes including bends special etc., in floor, wall or trenches.
1 PVC Pipe 4" dia (100 mm) 10.00 metre 88.00 per mtr. 880.00
2 PVC Bend 4" dia (100 mm) 2.00 Nos. 65.00 each 130.00
3 PVC Inspection box 2.00 Nos. 48.00 per doz. 8.00
4 Cement 0.106 Cft. 230.00 P. Bag 24.38
5 Sand 0.25 Cft. 350.00 Per % Cft. 0.88
Total 1043.26
Contractor's Profit & Overh 20 Percent 208.65
Total 1251.91
Material per metre 1141.80 ÷ 125.19 125.19
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 48
DESCRIPTION OF ITEM:
Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and sub main)
including clamps bends etc., complete with all specials.
1 PVC Pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50
2 PVC Bend 2" dia (50 mm) 2.00 Nos. 15.00 each 30.00
3 M.S Clamp 20.00 Nos. 10.00 each 200.00
4 PVC Inspection boxes 2.00 Nos. 32.00 per doz. 5.33
5 Gutties 20.00 Nos. 6.00 per doz. 10.00
6 Cement 0.021 Cft. 230.00 P. Bag 4.83
7 Sand 0.06 Cft. 350.00 Per % Cft. 0.21
Total 732.87
Contractor's Profit & Overh 20 Percent 146.57
Total 879.44
Material per metre 802.27 ÷ 1 87.94 87.94
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 49
DESCRIPTION OF ITEM:
Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and sub main)
including clamps bends etc., complete with all specials.
1 PVC Pipe 3" dia (75 mm) 10.00 metre 66.75 per mtr. 667.50
2 PVC Bend 3" dia (75 mm) 2.00 Nos. 25.00 each 50.00
3 M.S Clamp 20.00 Nos. 18.00 each 360.00
4 PVC Inspection boxes 2.00 Nos. 32.00 per doz. 5.33
5 Screws for 3" dia clamp 40.00 Nos. 12.00 per doz. 40.00
6 Gutties 40.00 Nos. 6.00 per doz. 20.00
7 Cement 0.042 Cft. 230.00 P. Bag 9.66
8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42
Total 1152.91
Contractor's Profit & Overh 20 Percent 230.58
Total 1383.50
Material per metre 1155.92 ÷ 138.35 138.35
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 50
DESCRIPTION OF ITEM:
Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and sub main)
including clamps bends etc., complete with all specials.
1 PVC Pipe 4" dia (100 mm) 10.00 metre 88.00 per mtr. 880.00
2 PVC Bend 4" dia (100 mm) 2.00 Nos. 65.00 each 130.00
3 M.S Clamp 20.00 Nos. 15.00 each 300.00
4 Gutties 40.00 Nos. 6.00 per doz. 20.00
5 Screws for 4" dia clamp 40.00 Nos. 12.00 per doz. 40.00
6 PVC Inspection boxes 2.00 Nos. 48.00 per doz. 8.00
7 Cement 0.084 Cft. 230.00 P. Bag 19.32
8 Sand 0.24 Cft. 350.00 Per % Cft. 0.84
Total 1398.16
Contractor's Profit & Overh 20 Percent 279.63
Total 1677.79
Material per metre 1533.77 ÷ 167.78 167.78
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 51
DESCRIPTION OF ITEM:
Item No. 8 Supply and erection of wooden strip batten for wiring purposes including cl
insulation cleats etc.
Total 447.18
Contractor's Profit & Overh 20 Percent 89.44
Total 536.62
Material per metre 491.70 ÷ 1 5.37 5.37
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 52
DESCRIPTION OF ITEM:
Item No. 9 Supply and erection of sahl wood casing and capping for wiring purposes,
including insulation cleats, screws etc., complete.
Total 2421.42
Contractor's Profit & Overh 20 Percent 484.28
Total 2905.71
Material per metre 2662.00 ÷ 29.06 29.06
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 53
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
1 PVC cable 3/0.029" = 1 coil 90.00 metre 4.31 per mtr. 387.90
Wastage (3%) 11.64
Total 399.54
Contractor's Profit & Overh 20 Percent 79.91
Total 479.44
Material per metre 439.49 ÷ 9 5.33 5.33
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 54
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
1 PVC cable 3/0.036" = 1 coil 90.00 metre 6.24 per mtr. 561.60
Wastage (3%) 16.85
Total 578.45
Contractor's Profit & Overh 20 Percent 115.69
Total 694.14
Material per metre 636.29 ÷ 9 7.71 7.71
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 55
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
1 PVC cable 7/0.029" = 1 coil 90.00 metre 8.91 per mtr. 801.90
Wastage (3%) 24.06
Total 825.96
Contractor's Profit & Overh 20 Percent 165.19
Total 991.15
Material per metre 908.55 ÷ 9 11.01 11.01
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 56
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
1 PVC cable 7/0.036" = 1 coil 90.00 metre 11.28 per mtr. 1015.20
Wastage (3%) 30.46
Total 1045.66
Contractor's Profit & Overh 20 Percent 209.13
Total 1254.79
Material per metre 1150.22 ÷ 13.94 13.94
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 57
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
1 PVC cable 7/0.044" = 1 coil 90.00 metre 16.09 per mtr. 1448.10
Wastage (3%) 43.44
Total 1491.54
Contractor's Profit & Overh 20 Percent 298.31
Total 1789.85
Material per metre 1640.70 ÷ 19.89 19.89
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 58
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
1 PVC cable 7/0.064" = 1 coil 90.00 metre 42.87 per mtr. 3858.30
Wastage (3%) 115.75
Total 3974.05
Contractor's Profit & Overh 20 Percent 794.81
Total 4768.86
Material per metre 4371.45 ÷ 52.99 52.99
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 59
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
1 PVC cable 19/0.052" = 1 coil 90.00 metre 57.04 per mtr. 5133.60
Wastage (2%) 102.67
Total 5236.27
Contractor's Profit & Overh 20 Percent 1047.25
Total 6283.53
Material per metre 5759.90 ÷ 69.82 69.82
Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40
ITEM RATES
Page 60
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
Total 12239.69
Contractor's Profit & Overh 20 Percent 2447.94
Total 14687.63
Material per metre 13464.0 ÷ 163.20 163.20
Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40
ITEM RATES
Page 61
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
1 PVC cable 3/0.029" = 1 coil 90.00 metre 5.00 per mtr. 450.00
Wastage (3%) 13.50
Total 463.50
Contractor's Profit & Overh 20 Percent 92.70
Total 556.20
Material per metre 509.85 ÷ 9 6.18 6.18
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 62
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
1 PVC cable 3/0.036" = 1 coil 90.00 metre 6.00 per mtr. 540.00
Wastage (3%) 16.20
Total 556.20
Contractor's Profit & Overh 20 Percent 111.24
Total 667.44
Material per metre 611.82 ÷ 9 7.42 7.42
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 63
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
1 PVC cable 7/0.029" = 1 coil 90.00 metre 8.00 per mtr. 720.00
Wastage (3%) 21.60
Total 741.60
Contractor's Profit & Overh 20 Percent 148.32
Total 889.92
Material per metre 815.76 ÷ 9 9.89 9.89
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 64
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
1 PVC cable 7/0.036" = 1 coil 90.00 metre 9.50 per mtr. 855.00
Wastage (3%) 25.65
Total 880.65
Contractor's Profit & Overh 20 Percent 176.13
Total 1056.78
Material per metre 968.72 ÷ 9 11.74 11.74
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 65
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
1 PVC cable 7/0.044" = 1 coil 90.00 metre 15.00 per mtr. 1350.00
Wastage (3%) 40.50
Total 1390.50
Contractor's Profit & Overh 20 Percent 278.10
Total 1668.60
Material per metre 1529.55 ÷ 18.54 18.54
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 66
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
1 PVC cable 7/0.064" = 1 coil 90.00 metre 40.00 per mtr. 3600.00
Wastage (3%) 108.00
Total 3708.00
Contractor's Profit & Overh 20 Percent 741.60
Total 4449.60
Material per metre 4078.80 ÷ 49.44 49.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 67
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
1 PVC cable 3/0.029" = 1 coil 90.00 metre 4.96 per mtr. 446.40
Wastage (3%) 13.39
Total 459.79
Contractor's Profit & Overh 20 Percent 91.96
Total 551.75
Material per metre 505.77 ÷ 9 6.13 6.13
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 68
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
1 PVC cable 3/0.036" = 1 coil 90.00 metre 7.26 per mtr. 653.40
Wastage (3%) 19.60
Total 673.00
Contractor's Profit & Overh 20 Percent 134.60
Total 807.60
Material per metre 740.30 ÷ 9 8.97 8.97
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 69
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
1 PVC cable 7/0.074" = 1 coil 90.00 metre 9.89 per mtr. 890.10
Wastage (3%) 26.70
Total 916.80
Contractor's Profit & Overh 20 Percent 183.36
Total 1100.16
Material per metre 1008.48 ÷ 12.22 12.22
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 70
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
1 PVC cable 7/0.036" = 1 coil 90.00 metre 14.88 per mtr. 1339.20
Wastage (3%) 40.18
Total 1379.38
Contractor's Profit & Overh 20 Percent 275.88
Total 1655.25
Material per metre 1517.31 ÷ 18.39 18.39
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 71
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
1 PVC cable 7/0.044" = 1 coil 90.00 metre 21.02 per mtr. 1891.80
Wastage (3%) 56.75
Total 1948.55
Contractor's Profit & Overh 20 Percent 389.71
Total 2338.26
Material per metre 2143.41 ÷ 25.98 25.98
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 72
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
1 PVC cable 7/0.064" = 1 coil 90.00 metre 43.58 per mtr. 3922.20
Wastage (3%) 117.67
Total 4039.87
Contractor's Profit & Overh 20 Percent 807.97
Total 4847.84
Material per metre 4443.85 ÷ 53.86 53.86
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 73
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduit/PVC
pipe/G.I wire/trenches etc., (rate per cable only).
1 PVC cable 7/0.064" = 1 coil 90.00 metre 42.87 per mtr. 3858.30
Wastage (2%) 77.17
Total 3935.47
Contractor's Profit & Overh 20 Percent 787.09
Total 4722.56
Material per metre 4329.01 ÷ 52.47 52.47
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 74
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).
1 PVC cable 19/0.052" = 1 coil 90.00 metre 57.04 per mtr. 5133.60
Wastage (2%) 102.67
Total 5236.27
Contractor's Profit & Overh 20 Percent 1047.25
Total 6283.53
Material per metre 5759.90 ÷ 69.82 69.82
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 75
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).
1 PVC cable 19/0.064" = 1 coil 90.00 metre 77.71 per mtr. 6993.90
Wastage (2%) 139.88
Total 7133.78
Contractor's Profit & Overh 20 Percent 1426.76
Total 8560.53
Material per metre 7847.16 ÷ 95.12 95.12
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 76
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).
1 PVC cable 19/0.083" = 1 coil 90.00 metre 150.60 per mtr. 13554.00
Wastage (2%) 271.08
Total 13825.08
Contractor's Profit & Overh 20 Percent 2765.02
Total 16590.10
Material per metre 12207.59 ÷ 184.33 184.33
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 77
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).
1 PVC cable 37/0.072" = 1 coil 90.00 metre 209.59 per mtr. 18863.10
Wastage (2%) 377.26
Total 19240.36
Contractor's Profit & Overh 20 Percent 3848.07
Total 23088.43
Material per metre 21264.40 ÷ 256.54 256.54
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 78
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).
1 PVC cable 37/0.083" = 1 coil 90.00 metre 261.34 per mtr. 23520.60
Wastage (2%) 470.41
Total 23991.01
Contractor's Profit & Overh 20 Percent 4798.20
Total 28789.21
Material per metre 26390.11 ÷ 319.88 319.88
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 79
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).
1 PVC cable 37/0.103" = 1 coil 90.00 metre 403.24 per mtr. 36291.60
Wastage (2%) 725.83
Total 37017.43
Contractor's Profit & Overh 20 Percent 7403.49
Total 44420.92
Material per metre 40719.18 ÷ 493.57 493.57
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 80
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 3/0.029" = 1 coil 90.00 metre 13.21 per mtr. 1188.90
Wastage (3%) 35.67
Total 1224.6
Contractor's Profit & Overh 20 Percent 244.91
Total 1347.03
Material per metre 1347.03 ÷ 14.97 14.97
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 81
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 3/0.036" = 1 coil 90.00 metre 17.12 per mtr. 1540.80
Wastage (3%) 46.22
Total 1587.02
Contractor's Profit & Overh 20 Percent 317.40
Total 1904.43
Material per metre 1745.73 ÷ 21.16 21.16
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 82
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 7/0.029" = 1 coil 90.00 metre 23.36 per mtr. 2102.40
Wastage (3%) 63.07
Total 2165.47
Contractor's Profit & Overh 20 Percent 433.09
Total 2598.57
Material per metre 2382.02 ÷ 28.87 28.87
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 83
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 7/0.036" = 1 coil 90.00 metre 33.08 per mtr. 2977.20
Wastage (3%) 89.32
Total 3066.52
Contractor's Profit & Overh 20 Percent 613.30
Total 3679.82
Material per metre 3373.17 ÷ 40.89 40.89
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 84
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 7/0.044" = 1 coil 90.00 metre 47.38 per mtr. 4264.20
Wastage (3%) 127.93
Total 4392.13
Contractor's Profit & Overh 20 Percent 878.43
Total 5270.55
Material per metre 4831.34 ÷ 58.56 58.56
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 85
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 7/0.064" = 1 coil 90.00 metre 80.88 per mtr. 7279.20
Wastage (2%) 145.58
Total 7424.78
Contractor's Profit & Overh 20 Percent 1484.96
Total 8909.74
Material per metre 8167.26 ÷ 99.00 99.00
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 86
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 3 core 1 coil 90.00 metre 16.75 per mtr. 1507.50
Wastage (3%) 45.23
Total 1552.73
Contractor's Profit & Overh 20 Percent 310.55
Total 1863.27
Material per metre 1708.00 ÷ 20.70 20.70
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 87
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 3 core 1 coil 90.00 metre 27.00 per mtr. 2430.00
Wastage (3%) 72.90
Total 2502.90
Contractor's Profit & Overh 20 Percent 500.58
Total 3003.48
Material per metre 2753.19 ÷ 33.37 33.37
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 88
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 7/0.029" = 1 coil 90.00 metre 33.03 per mtr. 2972.70
Wastage (3%) 89.18
Total 3061.88
Contractor's Profit & Overh 20 Percent 612.38
Total 3674.26
Material per metre 3368.07 ÷ 40.83 40.83
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 89
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 7/0.036" = 1 coil 90.00 metre 46.96 per mtr. 4226.40
Wastage (2%) 84.53
Total 4310.93
Contractor's Profit & Overh 20 Percent 862.19
Total 5173.11
Material per metre 4742.02 ÷ 57.48 57.48
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 90
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 7/0.044" = 1 coil 90.00 metre 67.89 per mtr. 6110.10
Wastage (2%) 122.20
Total 6232.30
Contractor's Profit & Overh 20 Percent 1246.46
Total 7478.76
Material per metre 6855.53 ÷ 83.10 83.10
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 91
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
1 PVC cable 7/0.064" = 1 coil 90.00 metre 138.77 per mtr. 12489.30
Wastage (2%) 249.79
Total 12739.09
Contractor's Profit & Overh 20 Percent 2547.82
Total 15286.90
Material per metre 14012.99÷ 169.85 169.85
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 92
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.
1 PVC cable 3/0.029" = 1 coil 90.00 metre 22.40 per mtr. 2016.00
Wastage (3%) 60.48
Total 2076.48
Contractor's Profit & Overh 20 Percent 415.30
Total 2491.78
Material per metre 2284.12 ÷ 27.69 27.69
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 93
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.
1 PVC cable 3/0.036" = 1 coil 90.00 metre 34.51 per mtr. 3105.90
Wastage (3%) 93.18
Total 3199.08
Contractor's Profit & Overh 20 Percent 639.82
Total 3838.89
Material per metre 3518.98 ÷ 42.65 42.65
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 94
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.
1 PVC cable 7/0.029" = 1 coil 90.00 metre 43.32 per mtr. 3898.80
Wastage (2%) 77.98
Total 3976.78
Contractor's Profit & Overh 20 Percent 795.36
Total 4772.13
Material per metre 4374.45 ÷ 53.02 53.02
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 95
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.
1 PVC cable 7/0.036" = 1 coil 90.00 metre 56.72 per mtr. 5104.80
Wastage (2%) 102.10
Total 5206.90
Contractor's Profit & Overh 20 Percent 1041.38
Total 6248.28
Material per metre 5727.59 ÷ 69.43 69.43
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 96
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.
1 PVC cable 7/0.044" = 1 coil 90.00 metre 78.38 per mtr. 7054.20
Wastage (2%) 141.08
Total 7195.28
Contractor's Profit & Overh 20 Percent 1439.06
Total 8634.34
Material per metre 7914.81 ÷ 95.94 95.94
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 97
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.
1 PVC cable 7/0.064" = 1 coil 90.00 metre 176.60 per mtr. 15894.00
Wastage (2%) 317.88
Total 16211.88
Contractor's Profit & Overh 20 Percent 3242.38
Total 19454.26
Material per metre 17833.07÷ 216.16 216.16
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 98
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.
1 PVC cable 19/0.052" = 1 coil 90.00 metre 251.08 per mtr. 22597.20
Wastage (2%) 451.94
Total 23049.14
Contractor's Profit & Overh 20 Percent 4609.83
Total 27658.97
Material per metre 25354.06÷ 307.32 307.32
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 99
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.
1 PVC cable 19/0.052" = 1 coil 90.00 metre 110.56 per mtr. 9950.40
Wastage (2%) 199.01
Total 10149.41
Contractor's Profit & Overh 20 Percent 2029.88
Total 12179.29
Material per metre 11164.35÷ 135.33 135.33
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 100
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.
1 PVC cable 19/0.064" = 1 coil 90.00 metre 159.62 per mtr. 14365.80
Wastage (2%) 287.32
Total 14653.12
Contractor's Profit & Overh 20 Percent 2930.62
Total 17583.74
Material per metre 16118.43 ÷ 195.37 195.37
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 101
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with
G.I wire 16 SWG.
1 PVC cable 19/0.072" = 1 coil 90.00 metre 210.82 per mtr. 18973.80
Wastage (2%) 379.48
Total 19353.28
Contractor's Profit & Overh 20 Percent 3870.66
Total 23223.93
Material per metre 21288.60 ÷ 258.04 258.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 102
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with
G.I wire 16 SWG.
Total 23927.67
Contractor's Profit & Overh 20 Percent 4785.53
Total 28713.20
Material per metre 26320.44 ÷ 319.04 319.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 103
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.
1 PVC cable 37/0.072" = 1 coil 90.00 metre 404.84 per mtr. 36435.60
Wastage (2%) 728.71
Total 37164.31
Contractor's Profit & Overh 20 Percent 7432.86
Total 44597.17
Material per metre 40880.74 ÷ 495.52 495.52
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 104
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.
1 PVC cable 37/0.083" = 1 coil 90.00 metre 536.83 per mtr. 48314.70
Wastage (2%) 966.29
Total 49281.00
Contractor's Profit & Overh 20 Percent 9856.20
Total 59137.19
Material per metre 54209.09 ÷ 657.08 657.08
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 105
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.
1 PVC cable 37/0.093" = 1 coil 90.00 metre 675.03 per mtr. 60752.70
Wastage (2%) 1215.05
Total 61967.76
Contractor's Profit & Overh 20 Percent 12393.55
Total 74361.31
Material per metre 68164.53 ÷ 826.24 826.24
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 106
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.
1 PVC cable 37/0.103" = 1 coil 90.00 metre 807.02 per mtr. 72631.80
Wastage (2%) 1452.64
Total 74084.44
Contractor's Profit & Overh 20 Percent 14816.89
Total 88901.33
Material per metre 81492.88 ÷ 987.79 987.79
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 107
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 4" x 4" (100 x 100 mm) 1.00 No. 50.00 each 50.00
2 Cement 0.021 Cft. 230.00 P. Bag 4.83
3 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 55.11
Contractor's Profit & Overh 20 Percent 11.02
Total 66.13
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 108
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 7" x 4" (175 x 100 mm) 1.00 No. 60.00 each 60.00
2 Cement 0.026 Cft. 230.00 P. Bag 5.98
3 Sand 0.09 Cft. 350.00 Per % Cft. 0.32
Total 66.30
Contractor's Profit & Overh 20 Percent 13.26
Total 79.55
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 109
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 9" x 4" (225 x 100 mm) 1.00 No. 69.00 each 69.00
2 Cement 0.032 Cft. 230.00 P. Bag 7.36
3 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 76.64
Contractor's Profit & Overh 20 Percent 15.33
Total 91.97
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 110
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 8" x 10" (200 x 250 mm) 1.00 No. 95.00 each 95.00
2 Cement 0.036 Cft. 230.00 P. Bag 8.28
3 Sand 0.150 Cft. 350.00 Per % Cft. 0.53
Total 103.81
Contractor's Profit & Overh 20 Percent 20.76
Total 124.57
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 111
Labour rate for Each Rs. 43.56 Say 43.55
Composite rate for Each Rs. 168.13 Say 168.15
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 10" x 12" (250 x 300 mm) 1.00 No. 125.00 each 125.00
2 Cement 0.047 Cft. 230.00 P. Bag 10.81
3 Sand 0.155 Cft. 350.00 Per % Cft. 0.54
Total 136.35
Contractor's Profit & Overh 20 Percent 27.27
Total 163.62
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 112
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 12" x 14" (300 x 350 mm) 1.00 No. 188.00 each 188.00
2 Cement 0.052 Cft. 230.00 P. Bag 11.96
3 Sand 0.180 Cft. 350.00 Per % Cft. 0.63
Total 200.59
Contractor's Profit & Overh 20 Percent 40.12
Total 240.71
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 113
DESCRIPTION OF ITEM:
Item No. 15 Supply and erectionof round block of Sahl wood, 10 x 4 cm 4" x 1½"
(100 x 40 mm).
MATERIAL
Total 7.30
Contractor's Profit & Overh 20 Percent 1.46
Total 8.76
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 114
DESCRIPTION OF ITEM:
Item No. 16 Supply and erection of teak wood board, 4.5 cm 1¾" (45 mm) thick.
MATERIAL
1 Teak Wood Board 7" x 4" (175 x 100 mm) 1.00 No. 20.00 each 20.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 12.00 per dozen 2.00
Total 23.00
Contractor's Profit & Overh 20 Percent 4.60
Total 27.60
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 115
DESCRIPTION OF ITEM:
Item No. 16 Supply and erection of teak wood board, 4.5 cm 1¾" (45 mm) thick.
MATERIAL
1 Teak Wood Board 9" x 4" (225 x 100 mm) 1.00 No. 25.00 each 25.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 12.00 per dozen 2.00
Total 28.00
Contractor's Profit & Overh 20 Percent 5.60
Total 33.60
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 116
DESCRIPTION OF ITEM:
Item No. 16 Supply and erection of teak wood board, 4.5 cm 1¾" (45 mm) thick.
MATERIAL
1 Teak Wood Board 8" x 10" (200 x 250 mm) 1.00 No. 30.00 each 30.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 12.00 per dozen 2.00
Total 33.00
Contractor's Profit & Overh 20 Percent 6.60
Total 39.60
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 117
DESCRIPTION OF ITEM:
Item No. 16 Supply and erection of teak wood board, 4.5 cm 1¾" (45 mm) thick.
MATERIAL
1 Teak Wood Wooden Board 10" x 12" (250 x 300 mm) 1.00 No. 40.00 each 40.00
2 W. Gutti 4.00 Nos. 6.00 per dozen 2.00
3 Screw 4.00 Nos. 15.00 per dozen 5.00
Total 47.00
Contractor's Profit & Overh 20 Percent 9.40
Total 56.40
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 118
DESCRIPTION OF ITEM:
Item No. 16 Supply and erection of teak wood board, 4.5 cm 1¾" (45 mm) thick.
MATERIAL
1 Teak Wood Board 12" x 14" (300 x 350 mm) 1.00 No. 60.00 each 60.00
2 W. Gutti 4.00 Nos. 6.00 per dozen 2.00
3 Screw 4.00 Nos. 15.00 per dozen 5.00
Total 67.00
Contractor's Profit & Overh 20 Percent 13.40
Total 80.40
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 119
DESCRIPTION OF ITEM:
Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1¾" (45 mm) thick.
MATERIAL
1 Sahl Wood Board 7" x 4" (175 x 100 mm) 1.00 No. 21.50 each 21.50
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 15.00 per dozen 2.50
Total 25.00
Contractor's Profit & Overh 20 Percent 5.00
Total 30.00
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 120
DESCRIPTION OF ITEM:
Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1¾" (45 mm) thick.
MATERIAL
1 Sahl Wood Board 9" x 4" (225 x 100 mm) 1.00 No. 30.00 each 30.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 15.00 per dozen 2.50
Total 33.50
Contractor's Profit & Overh 20 Percent 6.70
Total 40.20
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 121
DESCRIPTION OF ITEM:
Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1¾" (45 mm) thick.
MATERIAL
1 Sahl Wood Board 8" x 10" (200 x 250 mm) 1.00 No. 35.00 each 35.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 12.00 per dozen 2.00
Total 38.00
Contractor's Profit & Overh 20 Percent 7.60
Total 45.60
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 122
DESCRIPTION OF ITEM:
Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1¾" (45 mm) thick.
MATERIAL
1 Sahl Wood Board 10" x 12" (250 x 300 mm) 1.00 No. 45.00 each 45.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 12.00 per dozen 2.00
Total 48.00
Contractor's Profit & Overh 20 Percent 9.60
Total 57.60
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 123
DESCRIPTION OF ITEM:
Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1¾" (45 mm) thick.
MATERIAL
1 Sahl Wood Board 12" x 14" (300 x 350 mm) 1.00 No. 60.00 each 60.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 15.00 per dozen 2.50
Total 63.50
Contractor's Profit & Overh 20 Percent 12.70
Total 76.20
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 124
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
1 Main switch 15/20 Amp. 500 volts 1.00 No. 120.00 each 120.00
2 G.I Flexible pipe 1" dia (25 mm) 0.50 metre 22.60 per mtr. 11.30
3 Angle iron board including paints (9"x9"x1½") 1.00 No. 80.00 each 80.00
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
5 Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
6 Socket 1" dia (25 mm) 3.00 Nos. 7.00 each 21.00
7 Check nut 1" dia (25 mm) 1.00 No. 12.00 each 12.00
8 Thimble 8.00 Nos. 6.00 each 48.00
9 Cement 0.032 Cft. 230.00 P. Bag 7.36
10 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 375.94
Contractor's Profit & Overh 20 Percent 75.19
Total 451.13
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 125
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
1 Main Switch 30/35 Amp. 500 volts 1.00 No. 350.00 each 350.00
2 G.I Flexible pipe 1" dia (25 mm) 0.50 metre 22.60 per mtr. 11.30
3 L-Iron board including paint (9"x12"x1½") 1.00 No. 100.00 each 100.00
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
5 Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
6 Socket 1" dia (25 mm) 3.00 Nos. 7.00 each 21.00
7 Check nut 1" dia (25 mm) 1.00 No. 12.00 each 12.00
8 Thimble 8.00 Nos. 6.00 each 48.00
9 Cement 0.032 Cft. 230.00 P. Bag 7.36
10 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 625.94
Contractor's Profit & Overh 20 Percent 125.19
Total 751.13
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 126
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
1 Main Switch 60/65 Amp. 500 volts 1.00 No. 886.00 each 886.00
2 G.I Flexible pipe 1½" dia (38 mm) 0.50 metre 39.37 per mtr. 19.68
3 L-Iron board including paint (10"x12"x1½") 1.00 No. 150.00 each 150.00
4 Nipple 1½" dia (38 mm) 2.00 Nos. 20.00 each 40.00
5 Socket 1½" dia (38 mm) 2.00 Nos. 15.00 each 30.00
6 Check nut 1½" dia (38 mm) 2.00 Nos. 20.00 each 40.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
8 Cement 0.032 Cft. 230.00 P. Bag 7.36
9 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 1233.32
Contractor's Profit & Overh 20 Percent 246.66
Total 1479.99
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 127
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
1 Main Switch 100 Amp. 500 volts 1.00 No. 1300.00 each 1300.00
2 G.I Flexible pipe 1½" dia (38 mm) 0.50 metre 39.37 per mtr. 19.68
3 L-Iron board including paint (10"x12"x1½") 1.00 No. 150.00 each 150.00
4 Nipple 1½" dia (38 mm) 2.00 Nos. 20.00 each 40.00
5 Socket 1½" dia (38 mm) 2.00 Nos. 15.00 each 30.00
6 Check nut 1½" dia (38 mm) 2.00 Nos. 20.00 each 40.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
8 Cement 0.032 Cft. 230.00 P. Bag 7.36
9 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 1647.32
Contractor's Profit & Overh 20 Percent 329.46
Total 1976.79
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 128
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
1 Main Switch 15/20 Amp. 500 volts 1.00 No. 400.00 each 400.00
2 G.I Flexible pipe 1" dia (25 mm) 0.50 metre 22.60 per mtr. 11.30
3 L-Iron board including paint (9"x12"x1½") 1.00 No. 100.00 each 100.00
4 Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
5 Socket 1" dia (25 mm) 2.00 Nos. 7.00 each 14.00
6 Check nut 1" dia (25 mm) 2.00 Nos. 12.00 each 24.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
8 Cement 0.032 Cft. 230.00 P. Bag 7.36
9 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 632.94
Contractor's Profit & Overh 20 Percent 126.59
Total 759.53
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 129
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
1 Main Switch 30/35 Amp. 500 volts 1.00 No. 650.00 each 650.00
2 L-Iron board including paint (10"x12"x1½") 1.00 No. 150.00 each 150.00
3 G.I Flexible pipe 1" dia (25 mm) 0.50 metre 22.60 per mtr. 11.30
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
5 Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
6 Socket 1" dia (25 mm) 2.00 Nos. 7.00 each 14.00
7 Check nut 1" dia (25 mm) 2.00 Nos. 12.00 each 24.00
8 Thimble 8.00 Nos. 6.00 each 48.00
9 Cement 0.032 Cft. 230.00 P. Bag 7.36
10 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 980.94
Contractor's Profit & Overh 20 Percent 196.19
Total 1177.13
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 130
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
1 Main Switch 30/35 Amp. 500 volts 1.00 No. 713.00 each 713.00
2 L-Iron board including paint (10"x12"x1½") 1.00 No. 150.00 each 150.00
3 G.I Flexible pipe 1" dia (25 mm) 0.50 metre 22.60 per mtr. 11.30
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
5 Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
6 Socket 1" dia (25 mm) 2.00 Nos. 7.00 each 14.00
7 Check nut 1" dia (25 mm) 2.00 Nos. 12.00 each 24.00
8 Thimble 8.00 Nos. 6.00 each 48.00
9 Cement 0.032 Cft. 230.00 P. Bag 7.36
10 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 1043.94
Contractor's Profit & Overh 20 Percent 208.79
Total 1252.73
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 131
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
1 Main Switch 60/65 Amp. 500 volts 1.00 No. 1070.00 each 1070.00
2 L-Iron board including paint (12"x15"x1½") 1.00 No. 170.00 each 170.00
3 G.I Flexible pipe 1¼" dia (32 mm) 0.50 metre 29.52 per mtr. 14.76
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
5 Nipple 1½" dia (40 mm) 2.00 Nos. 20.00 each 40.00
6 Socket 1¼" dia (32 mm) 2.00 Nos. 12.00 each 24.00
7 Check nut 1¼" dia (32 mm) 2.00 Nos. 16.00 each 32.00
8 Cement 0.052 Cft. 230.00 P. Bag 11.96
9 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 1423.35
Contractor's Profit & Overh 20 Percent 284.67
Total 1708.02
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 132
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
1 Main Switch 100 Amp. 500 volts 1.00 No. 1840.00 each 1840.00
2 L-Iron board including paint (12"x18"x1½") 1.00 No. 200.00 each 200.00
3 G.I Flexible pipe 1½" dia (40 mm) 0.50 metre 39.37 per mtr. 19.68
4 Brass Nipple 1½" dia (40 mm) 2.00 Nos. 40.00 each 80.00
5 Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
8 Cement 0.052 Cft. 230.00 P. Bag 11.96
9 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 2242.27
Contractor's Profit & Overh 20 Percent 448.45
Total 2690.73
Total 429.20
Sundries 10 Percent 42.92
Total 472.12
Contractor's Profit & Overh 20 Percent 94.42
Total 566.54
ITEM RATES
Page 133
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.
MATERIAL
1 Main Switch with triple pole and 1.00 No. 1100.00 each 1100.00
2 Flexible pipe 1½" (40 mm) 0.50 metre 39.37 per mtr. 19.68
3 L-Iron board including paint (10"x15"x1½") 1.00 No. 190.00 each 190.00
4 Brass Nipple 1½" dia (40 mm) 2.00 Nos. 40.00 each 80.00
5 Brass check nut 1½" (40 mm) 2.00 Nos. 20.00 each 40.00
6 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
7 Brass Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
8 Thimble 60/65 Amp 4.00 Nos. 6.00 each 24.00
Total 1543.68
Contractor's Profit & Overh 20 Percent 308.74
Total 1852.43
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 134
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.
MATERIAL
1 Main Switch 100 Amp. 500 volts 1.00 No. 1920.00 each 1920.00
2 Flexible pipe 1½" (40 mm) 0.50 metre 39.37 per mtr. 19.69
3 L-Iron board including paint (12"x18"x1½") 1.00 No. 200.00 each 200.00
4 Brass Nipple 1¼" dia (32 mm) 2.00 Nos. 30.00 each 60.00
5 Brass check nut 1¼" (32 mm) 2.00 Nos. 16.00 each 32.00
6 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
7 Brass Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
8 Thimble 100 Amp. 4.00 Nos. 10.00 each 40.00
Total 2361.69
Contractor's Profit & Overh 20 Percent 472.34
Total 2834.03
Total 429.20
Sundries 10 Percent 42.92
Total 472.12
Contractor's Profit & Overh 20 Percent 94.42
Total 566.54
ITEM RATES
Page 135
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.
MATERIAL
1 Main Switch 150 Amp. 500 volts 1.00 No. 2200.00 each 2200.00
2 L-Iron board including paint (15"x18"x1½") 1.00 No. 230.00 each 230.00
3 Flexible pipe 1½" (40 mm) 0.50 metre 39.37 per mtr. 19.68
4 Brass Nipple 1¼" dia (32 mm) 2.00 Nos. 30.00 each 60.00
5 Brass Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
6 Thimble 150 Amp. 4.00 Nos. 19.00 each 76.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
Total 2675.68
Contractor's Profit & Overh 20 Percent 535.14
Total 3210.82
Total 429.20
Sundries 10 Percent 42.92
Total 472.12
Contractor's Profit & Overh 20 Percent 94.42
Total 566.54
ITEM RATES
Page 136
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.
MATERIAL
1 Main Switch 200 Amp. 500 volts 1.00 No. 4000.00 each 4000.00
2 L-Iron board including paint (15"x18"x1½") 1.00 No. 230.00 each 230.00
3 Flexible pipe 1½" (40 mm) 0.50 metre 39.37 per mtr. 19.68
4 Brass Nipple 1¼" dia (32 mm) 2.00 Nos. 30.00 each 60.00
5 Brass Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
6 Brass check nut 1¼" (32 mm) 2.00 Nos. 16.00 each 32.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
8 Copper Thimble 200 Amp. 4.00 Nos. 28.00 each 112.00
Total 4543.68
Contractor's Profit & Overh 20 Percent 908.74
Total 5452.42
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 137
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.
MATERIAL
1 Main Switch 300 Amp. 500 volts 1.00 No. 5566.00 each 5566.00
2 Flexible pipe 1½" (40 mm) 0.50 metre 39.37 per mtr. 19.68
3 L-Iron board including paint (15"x18"x1½") 1.00 No. 230.00 each 230.00
4 Brass Nipple 1¼" dia (32 mm) 2.00 Nos. 30.00 each 60.00
5 Brass Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
6 Brass check nut 1¼" (32 mm) 2.00 Nos. 16.00 each 32.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
8 Copper Thimble 300 Amp. 4.00 Nos. 55.00 each 220.00
Total 6217.68
Contractor's Profit & Overh 20 Percent 1243.54
Total 7461.22
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 138
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.
MATERIAL
1 Main Switch 400 Amp. 500 volts 1.00 No. 7550.00 each 7550.00
2 L-Iron board including paint (15"x18"x1½") 1.00 No. 230.00 each 230.00
3 Flexible pipe 2" (50 mm) 0.50 metre 55.77 per mtr. 27.89
4 Brass Nipple 2 dia (50 mm) 2.00 Nos. 80.00 each 160.00
5 Brass Socket 2" dia (50 mm) 2.00 Nos. 21.00 each 42.00
6 Brass check nut 2" (50 mm) 2.00 Nos. 25.00 each 50.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
8 Copper Thimble 400 Amp. 4.00 Nos. 75.00 each 300.00
Total 8419.89
Contractor's Profit & Overh 20 Percent 1683.98
Total 10103.86
Total 692.50
Sundries 10 Percent 69.25
Total 761.75
Contractor's Profit & Overh 20 Percent 152.35
Total 914.10
ITEM RATES
Page 139
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.
MATERIAL
1 Main Switch 500 Amp. 500 volts 1.00 No. 10268.00 each 10268.00
2 L-Iron board including paint (15"x18"x1½") 1.00 No. 230.00 each 230.00
3 Flexible pipe 4" (100 mm) 0.50 metre 175.00 per mtr. 87.50
4 Brass Nipple 4" dia (100 mm) 2.00 Nos. 200.00 each 400.00
5 Brass Socket 4" dia (100 mm) 2.00 Nos. 75.00 each 150.00
6 Brass check nut 4" (100 mm) 2.00 Nos. 55.00 each 110.00
7 Reg bolts 12" x 5/8" (300 x 16 mm) 4.00 Nos. 20.00 each 80.00
8 Copper Thimble 500 Amp. 4.00 Nos. 100.00 each 400.00
8 Cement 0.203 Cft. 230.00 P. Bag 46.69
9 Sand 0.99 Cft. 350.00 Per % Cft. 3.47
Total 11775.66
Contractor's Profit & Overh 20 Percent 2355.13
Total 14130.79
Total 735.00
Sundries 10 Percent 73.50
Total 808.50
Contractor's Profit & Overh 20 Percent 161.70
Total 970.20
ITEM RATES
Page 140
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/aluminium clad 2 way15 Amp. per way 1.00 No. 108.00 each 108.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 229.20
Contractor's Profit & Overh 20 Percent 45.84
Total 275.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 141
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/aluminium clad 3 way15 Amp. per way 1.00 No. 118.00 each 118.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 239.20
Contractor's Profit & Overh 20 Percent 47.84
Total 287.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 142
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 4 way15 Amp. per way 1.00 No. 163.00 each 163.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 284.20
Contractor's Profit & Overh 20 Percent 56.84
Total 341.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 143
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 5 way15 Amp. per way 1.00 No. 213.00 each 213.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 334.20
Contractor's Profit & Overh 20 Percent 66.84
Total 401.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 144
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 6 way15 Amp. per way 1.00 No. 248.00 each 248.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 369.20
Contractor's Profit & Overh 20 Percent 73.84
Total 443.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 145
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 7 way15 Amp. per way 1.00 No. 295.00 each 295.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 416.20
Contractor's Profit & Overh 20 Percent 83.24
Total 499.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 146
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 8 way15 Amp. per way 1.00 No. 338.00 each 338.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 459.20
Contractor's Profit & Overh 20 Percent 91.84
Total 551.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 147
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 9 way15 Amp. per way 1.00 No. 378.00 each 378.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 499.20
Contractor's Profit & Overh 20 Percent 99.84
Total 599.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 148
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 10 way15 Amp. per way 1.00 No. 438.00 each 438.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 559.20
Contractor's Profit & Overh 20 Percent 111.84
Total 671.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 149
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 11 way15 Amp. per way 1.00 No. 478.00 each 478.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 599.20
Contractor's Profit & Overh 20 Percent 119.84
Total 719.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 150
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 12 way15 Amp. per way 1.00 No. 508.00 each 508.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 629.20
Contractor's Profit & Overh 20 Percent 125.84
Total 755.04
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 151
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 2 way 30 Amp. per way 1.00 No. 120.00 each 120.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 241.20
Contractor's Profit & Overh 20 Percent 48.24
Total 289.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 152
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 3 way 30 Amp. per way 1.00 No. 130.00 each 130.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 251.20
Contractor's Profit & Overh 20 Percent 50.24
Total 301.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 153
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 4 way 30 Amp. per way 1.00 No. 175.00 each 175.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 296.20
Contractor's Profit & Overh 20 Percent 59.24
Total 355.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 154
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 5 way 30 Amp. per way 1.00 No. 225.00 each 225.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 346.20
Contractor's Profit & Overh 20 Percent 69.24
Total 415.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 155
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 6 way 30 Amp. per way 1.00 No. 260.00 each 260.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 381.20
Contractor's Profit & Overh 20 Percent 76.24
Total 457.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 156
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 7 way 30 Amp. per way 1.00 No. 310.00 each 310.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 431.20
Contractor's Profit & Overh 20 Percent 86.24
Total 517.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 157
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 8 way 30 Amp. per way 1.00 No. 350.00 each 350.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 471.20
Contractor's Profit & Overh 20 Percent 94.24
Total 565.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 158
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 9 way 30 Amp. per way 1.00 No. 390.00 each 390.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 511.20
Contractor's Profit & Overh 20 Percent 102.24
Total 613.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 159
DESCRIPTION OF ITEM:
Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:
MATERIAL
1 Iron/Aluminium clad 10 way 30 Amp. per way 1.00 No. 450.00 each 450.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20
Total 571.20
Contractor's Profit & Overh 20 Percent 114.24
Total 685.44
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 160
DESCRIPTION OF ITEM:
Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply with four
copper bars, including glazed porcelain bridges, on angle iron board, fixed
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:
(i) 60 Amp. with 4 copper bars size 1½" x 1/8" (40 x 3 mm)
MATERIAL
Total 1704.12
Contractor's Profit & Overh 20 Percent 340.82
Total 2044.94
Total 395.00
Sundries 10 Percent 39.50
Total 434.50
Contractor's Profit & Overh 20 Percent 86.90
Total 521.40
ITEM RATES
Page 161
DESCRIPTION OF ITEM:
Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply with four
copper bars, including glazed porcelain bridges, on angle iron board, fixed
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:
(ii) 100 Amp. with 4 copper bars size 1½" x 1/8" (40 x 3 mm)
MATERIAL
Total 1704.12
Contractor's Profit & Overh 20 Percent 340.82
Total 2044.94
Total 395.00
Sundries 10 Percent 39.50
Total 434.50
Contractor's Profit & Overh 20 Percent 86.90
Total 521.40
ITEM RATES
Page 162
DESCRIPTION OF ITEM:
Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply with four
copper bars, including glazed porcelain bridges, on angle iron board, fixed
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:
(iii) 200 Amp. with 4 copper bars size 2" x 1/8" (50 x 3 mm)
MATERIAL
Total 1944.12
Contractor's Profit & Overh 20 Percent 388.82
Total 2332.94
Total 620.00
Sundries 10 Percent 62.00
Total 682.00
Contractor's Profit & Overh 20 Percent 136.40
Total 818.40
ITEM RATES
Page 163
DESCRIPTION OF ITEM:
Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply with four
copper bars, including glazed porcelain bridges, on angle iron board, fixed
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:
(iv) 300 Amp. with 4 copper bars size 2" x 3/16" (50 x 4 mm)
MATERIAL
Total 1944.12
Contractor's Profit & Overh 20 Percent 388.82
Total 2332.94
Total 745.00
Sundries 10 Percent 74.50
Total 819.50
Contractor's Profit & Overh 20 Percent 163.90
Total 983.40
ITEM RATES
Page 164
DESCRIPTION OF ITEM:
Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply with four
copper bars, including glazed porcelain bridges, on angle iron board, fixed
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:
(v) 500 Amp. with 4 copper bars size 2" x ¼" (50 x 6 mm)
MATERIAL
Total 3549.16
Contractor's Profit & Overh 20 Percent 709.83
Total 4258.99
Total 480.00
Sundries 10 Percent 48.00
Total 528.00
Contractor's Profit & Overh 20 Percent 105.60
Total 633.60
ITEM RATES
Page 165
DESCRIPTION OF ITEM:
Item No. 22 (i) Supply and erection of plain pendent lamp holder, complete, with bakelite l
holder and flexible twin wire 23/0.0076" upto 2 metre length (without bulb
shade).
MATERIAL
Total 21.92
Contractor's Profit & Overh 20 Percent 4.38
Total 26.30
Total 85.00
Sundries 10 Percent 8.50
Total 93.50
Contractor's Profit & Overh 20 Percent 18.70
Total 112.20
ITEM RATES
Page 166
DESCRIPTION OF ITEM:
Item No. 22 (ii) Extra for additional length of flexible wire, beyond 2 metres.
MATERIAL
2 Flexible twin wire 23/0.0076 (23/0.195 mm) 1.00 metre 4.96 per mtr. 4.96
Total 4.96
Contractor's Profit & Overh 20 Percent 0.99
Total 5.95
ITEM RATE
Page 167
DESCRIPTION OF ITEM:
Item No. 23 Supply and erection of counter weight pendent with porcelain counter weig
and fitting on bakelite lamp holder, with flexible twin wire 23/0.0076" comp
(without bulb & shade).
MATERIAL
1 Flexible twin wire 23/0.0076 (23/0.195 mm) 3.00 metre 4.96 per mtr. 14.88
2 Bakelite lamp holder 1.00 No. 12.00 each 12.00
3 Counter weight with accessories 1.00 No. 60.00 each 60.00
Total 86.88
Contractor's Profit & Overh 20 Percent 17.38
Total 104.26
Total 85.00
Sundries 10 Percent 8.50
Total 93.50
Contractor's Profit & Overh 20 Percent 18.70
Total 112.20
ITEM RATES
Page 168
DESCRIPTION OF ITEM:
Item No. 24 Supply and erection of stiff pendent with brass/metal pipe 6.3 cm (2.5") lon
15 mm (½") dia brass oxidised or painted along lamp holder with VIR/PVC c
3/0.74 mm (3/0.029").
MATERIAL
1 Brass pipe ½" dia (12 mm) 2.00 metre 52.00 per mtr. 104.00
2 Canopy nipple & hook 1.00 job 20.00 per job 20.00
3 Brass lamp holder 1.00 No. 20.00 each 20.00
4 VIR/PVC cable 3/0.29 2.00 metre 6.00 per mtr. 12.00
Total 156.00
Contractor's Profit & Overh 20 Percent 31.20
Total 187.20
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 169
DESCRIPTION OF ITEM:
Item No. 25 Supply and erection of 22.5 cm (9") long swan neck plain brass/steel brass
oxidised bracket lamp holder, complete.
MATERIAL
Total 39.00
Contractor's Profit & Overh 20 Percent 7.80
Total 46.80
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 170
DESCRIPTION OF ITEM:
Item No. 26 Supply and erection of wall type/pole type bracket, with double cover water
tight reflector, flexible wire and brass holder.
MATERIAL
1 G.I. Pipe ¾" dia (20 mm) 1.00 metre 68.07 per mtr. 68.07
2 Brass nipple 1.00 No. 18.00 each 18.00
3 Brass lamp holder 1.00 No. 16.00 each 16.00
4 Double cone reflector 1.00 No. 55.00 each 55.00
5 Flexible wire 1.00 metre 4.00 per mtr. 4.00
Total 161.07
Contractor's Profit & Overh 20 Percent 32.21
Total 193.28
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 171
DESCRIPTION OF ITEM:
Item No. 27 Supply and erection of bakelite button holder shade, large size.
MATERIAL
Total 18.98
Contractor's Profit & Overh 20 Percent 3.80
Total 22.78
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 172
DESCRIPTION OF ITEM:
Item No. 28 Supply and erection of call bell 220/250 volts, fixed on teak wood board
17.5 x 10 cm (7" x 4").
MATERIAL
Total 86.01
Contractor's Profit & Overh 20 Percent 17.20
Total 103.22
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 173
DESCRIPTION OF ITEM:
Item No. 29 Supply and erection of bell push or bed switch, with 5 metre twin flexible
wire 23/0.0076"
MATERIAL
Total 32.80
Contractor's Profit & Overh 20 Percent 6.56
Total 39.36
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 174
DESCRIPTION OF ITEM:
MATERIAL
Total 13.41
Contractor's Profit & Overh 20 Percent 2.68
Total 16.09
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 175
DESCRIPTION OF ITEM:
MATERIAL
Total 11.41
Contractor's Profit & Overh 20 Percent 2.28
Total 13.69
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 176
DESCRIPTION OF ITEM:
MATERIAL
Total 10.41
Contractor's Profit & Overh 20 Percent 2.08
Total 12.49
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 177
DESCRIPTION OF ITEM:
MATERIAL
Total 6.00
Contractor's Profit & Overh 20 Percent 1.20
Total 7.20
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 178
DESCRIPTION OF ITEM:
MATERIAL
Total 9.41
Contractor's Profit & Overh 20 Percent 1.88
Total 11.29
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 179
DESCRIPTION OF ITEM:
MATERIAL
Total 11.54
Contractor's Profit & Overh 20 Percent 2.31
Total 13.85
Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60
ITEM RATES
Page 180
DESCRIPTION OF ITEM:
MATERIAL
1 Double control switch recessed type 1.00 No. 10.00 each 10.00
2 Screw 2.00 Nos. 3.25 P. Doz. 0.54
Total 10.54
Contractor's Profit & Overh 20 Percent 2.11
Total 12.65
Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60
ITEM RATES
Page 181
DESCRIPTION OF ITEM:
MATERIAL
Total 9.54
Contractor's Profit & Overh 20 Percent 1.91
Total 11.45
Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60
ITEM RATES
Page 182
DESCRIPTION OF ITEM:
MATERIAL
Total 11.54
Contractor's Profit & Overh 20 Percent 2.31
Total 13.85
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 183
DESCRIPTION OF ITEM:
MATERIAL
Total 13.54
Contractor's Profit & Overh 20 Percent 2.71
Total 16.25
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 184
DESCRIPTION OF ITEM:
Item No. 33 Supply and erection of wall socket with 3 pin 5 Amp. shoe.
MATERIAL
Total 20.54
Contractor's Profit & Overh 20 Percent 4.11
Total 24.65
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 185
DESCRIPTION OF ITEM:
MATERIAL
Total 8.54
Contractor's Profit & Overh 20 Percent 1.71
Total 10.25
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 186
DESCRIPTION OF ITEM:
Item No. 35 Supply and erection of 3 pin 10/15 Amp. wall socket.
MATERIAL
Total 11.54
Contractor's Profit & Overh 20 Percent 2.31
Total 13.85
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 187
DESCRIPTION OF ITEM:
Item No. 35 Supply and erection of 3 pin 10/15 Amp. wall socket.
MATERIAL
1 Wall socket 10/15 Amp. recessed 1.00 No. 13.00 each 13.00
2 Machine Screw 2.00 Nos. 3.25 P. Doz. 0.54
Total 13.54
Contractor's Profit & Overh 20 Percent 2.71
Total 16.25
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 188
DESCRIPTION OF ITEM:
Item No. 36 Supply and erection of 3 pin switch and plug combined, recessed type:
(i) 5 Amp.
MATERIAL
1 Plugs 3 pin and switch (combine) 5 Amp. 1.00 No. 36.00 each 36.00
2 Machine Screw 4.00 Nos. 3.25 P. Doz. 1.08
Total 37.08
Contractor's Profit & Overh 20 Percent 7.42
Total 44.50
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 189
DESCRIPTION OF ITEM:
Item No. 36 Supply and erection of 3 pin switch and plug combined, recessed type:
MATERIAL
1 Plugs 3 pin and switch (combine) 10/15 Amp. 1.00 No. 48.00 each 48.00
2 Machine Screw 5.00 Nos. 3.25 P. Doz. 1.35
Total 49.35
Contractor's Profit & Overh 20 Percent 9.87
Total 59.23
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 190
DESCRIPTION OF ITEM:
Item No. 37 Supply and erection of 3 pin 10/15 Amp. wall socket with shoe open type.
MATERIAL
1 Wall socket 3 pin 10/15 Amp. 1.00 No. 25.00 each 25.00
2 Shoe 3 pin 1.00 No. 10.00 each 10.00
3 Screw 2.00 Nos. 3.25 P. Doz. 0.54
Total 35.54
Contractor's Profit & Overh 20 Percent 7.11
Total 42.65
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 191
DESCRIPTION OF ITEM:
MATERIAL
Total 13.54
Contractor's Profit & Overh 20 Percent 2.71
Total 16.25
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 192
DESCRIPTION OF ITEM:
MATERIAL
Total 15.54
Contractor's Profit & Overh 20 Percent 3.11
Total 18.65
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 193
DESCRIPTION OF ITEM:
MATERIAL
Total 9.54
Contractor's Profit & Overh 20 Percent 1.91
Total 11.45
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 194
DESCRIPTION OF ITEM:
MATERIAL
Total 12.54
Contractor's Profit & Overh 20 Percent 2.51
Total 15.05
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 195
DESCRIPTION OF ITEM:
MATERIAL
Total 17.54
Contractor's Profit & Overh 20 Percent 3.51
Total 21.05
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 196
DESCRIPTION OF ITEM:
Item No. 41 Supply and erection of bell push, open/recessed type (without flexible wire)
MATERIAL
Total 8.54
Contractor's Profit & Overh 20 Percent 1.71
Total 10.25
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 197
DESCRIPTION OF ITEM:
MATERIAL
Total 10.27
Contractor's Profit & Overh 20 Percent 2.05
Total 12.33
Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60
ITEM RATES
Page 198
DESCRIPTION OF ITEM:
MATERIAL
Total 17.27
Contractor's Profit & Overh 20 Percent 3.45
Total 20.73
Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60
ITEM RATES
Page 199
DESCRIPTION OF ITEM:
MATERIAL
Total 40.27
Contractor's Profit & Overh 20 Percent 8.05
Total 48.33
Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60
ITEM RATES
Page 200
DESCRIPTION OF ITEM:
MATERIAL
Total 75.27
Contractor's Profit & Overh 20 Percent 15.05
Total 90.33
Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60
ITEM RATES
Page 201
DESCRIPTION OF ITEM:
MATERIAL
Total 150.27
Contractor's Profit & Overh 20 Percent 30.05
Total 180.33
Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60
ITEM RATES
Page 202
DESCRIPTION OF ITEM:
MATERIAL
Total 225.27
Contractor's Profit & Overh 20 Percent 45.05
Total 270.33
Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60
ITEM RATES
Page 203
DESCRIPTION OF ITEM:
MATERIAL
Total 280.27
Contractor's Profit & Overh 20 Percent 56.05
Total 336.33
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 204
DESCRIPTION OF ITEM:
MATERIAL
Total 310.80
Contractor's Profit & Overh 20 Percent 62.16
Total 372.96
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 205
DESCRIPTION OF ITEM:
Item No. 43 Supply and erection of tube light, including rod, choke, starter with frame,
flexible wire, including connection from ceiling rose, etc., complete:
(i) Double rod (80 watts) with two chokes and 2 starters.
MATERIAL
Total 600.00
Contractor's Profit & Overh 20 Percent 120.00
Total 720.00
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 206
DESCRIPTION OF ITEM:
Item No. 43 Supply and erection of tube light, including rod, choke, starter with frame,
flexible wire, including connection from ceiling rose, etc., complete:
(ii) Single rod (40 watts) with one choke and one starter.
MATERIAL
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 207
DESCRIPTION OF ITEM:
Item No. 43 Supply and erection of tube light, including rod, choke, starter with frame,
flexible wire, including connection from ceiling rose, etc., complete:
(iii) Single round tube, 32 watts, with one choke and one starter, without cover.
MATERIAL
Total 312.00
Contractor's Profit & Overh 20 Percent 62.40
Total 374.40
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 208
DESCRIPTION OF ITEM:
Item No. 43 Supply and erection of tube light, including rod, choke, starter with frame,
flexible wire, including connection from ceiling rose, etc., complete:
(iv) Round tube, 32 watts, with one choke and one starter, with cover.
MATERIAL
Total 472.00
Contractor's Profit & Overh 20 Percent 94.40
Total 566.40
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 209
DESCRIPTION OF ITEM:
Item No. 44 Providing and fixing M.S iron box for housing main switches, made of 1.5 m
(1/16") thick M.S sheet, with locking arrangement, including painting:
MATERIAL
1 M.S sheet 1.5 mm thick
Base side 1 x 24/12 x 14/12 (1 x 600 x 350 mm)
Long side 2 x 24/12 x 7½ ÷ 12 (2x600x190mm)
Short side 2 x 14/12 x 7½ ÷ 12 (2x350x190mm)
Top 1 x 24 x 12 x 14 ÷ (600 x 350 x 150 mm)
1.04 Sqm @ 12.20 Kg/Sqm 12.68 kg 29.00 per kg 367.72
2 Angle Iron 25 x 25 x 3 mm/Sqm
2 x 24" = 48" (2 x 600 mm)
2 x 14" = 28" (2 x 350 mm)
4 x 7.12 = 30" (4 x 190 mm)
=
0.82 Sqm @ 6.08 Kg/Sqm 1.70 kg 1.70 kg 24.00 each 40.80
3 Handle chromium plated 1.00 No. 15.00 each 15.00
4 Painting 0.178 Gallon 450.00 Gallon 80.10
5 Hinges 3.00 Nos. 2.50 each 7.50
6 Locking arrangement L.S 60.00
Total 571.12
Contractor's Profit & Overh 20 Percent 114.22
Total 685.34
Total 501.25
Sundries 10 Percent 50.13
Total 551.38
Contractor's Profit & Overh 20 Percent 110.28
Total 527.87
ITEM RATES
Page 210
DESCRIPTION OF ITEM:
Item No. 44 Providing and fixing M.S iron box for housing main switches, made of 1.5 m
(1/16") thick M.S sheet, with locking arrangement, including painting:
MATERIAL
1 M.S sheet 38"x16"x 8" thick (1965x406x200mm)
Base side 1x38/12x16/12 (965x406mm) = 0.39 Sqm
Long side 2x38/12x8/12 (2x965x200mm) = 0.39 Sqm
Short side 2x16/12x8/12 (2x406x200mm) = 0.17 Sqm
Top 1x38/12x16/12 (1x965x406mm) = 0.39 Sqm
1.34 Sqm
1.34 Sqm @ 12.45 Kg/Sqm 16.70 kg 29.00 per kg 484.30
2 Angle Iron 1" x 1" x 1/8" (25 x 25 x 3mm)
2 x 965 mm = 1.93 R/m
2 x 406 mm = 0.82 R/m
4 x 200 mm = 0.80 R/m
3.55 R/m
3.55 R/m @ 0.632 Kg/R/m 2.25 kg 24.00 per kg 54.00
3 Handle chromium plated 1.00 No. 15.00 each 15.00
4 Paint 0.045 Gallon 450.00 Gallon 20.25
5 Hinges 3.00 Nos. 2.50 each 7.50
6 Locking arrangement L.S 60.00
Total 641.05
Contractor's Profit & Overh 20 Percent 128.21
Total 769.26
Total 543.75
Sundries 10 Percent 54.38
Total 598.13
Contractor's Profit & Overh 20 Percent 119.63
Total 717.75
ITEM RATES
Labour rate for Each Rs. 239.25 Say 239.25
Composite rate for Each Rs. 1008.51 Say 1008.50
Page 211
DESCRIPTION OF ITEM:
Item No. 44 Providing and fixing M.S iron box for housing main switches, made of 1.5 m
(1/16") thick M.S sheet, with locking arrangement, including painting:
MATERIAL
1 M.S sheet 42" x 21" x 9" thick (1067 x 534 x 225mm)
Base side 1 x 42/12 x 21/12 (1076x534mm)
Long side 2 x 42/12 x 9/12 (2x1067x225mm)
Short side 2 x 21/12 x 9/12 (2x534x225mm)
Top 1 x 42 (1x1067x534mm)
12 12 1.872 Sqm
1872 Sqm @ 27.44 Per Sqm (51.36 lbs) 23.30 kg 29.00 per kg 675.70
2 Angle Iron 1" x 1" x 1/8 (25x25x3mm)
2 x 42" = 84" (2x1076)
2 x 21" = 42" (2x534)
4 x 9" = 36" (4x225mm)
162" or 13.5 ft. (4.12 R/m)
412 ft. 1.394 lbs/PRM 5.74 lbs 2.60 kg 24.00 per kg 62.40
3 P/F chromium plated 1.00 No. 15.00 each 15.00
4 P/F Hinges 3.00 Nos. 2.50 each 7.50
Paint 0.054 Gallon 450.00 Gallon 24.30
Locking arrangement L.S 60.00
Total 844.90
Contractor's Profit & Overh 20 Percent 168.98
Total 1013.88
ITEM RATES
Page 212
DESCRIPTION OF ITEM:
Item No. 44 Providing and fixing M.S iron box for housing main switches, made of 1.5 m
(1/16") thick M.S sheet, with locking arrangement, including painting:
MATERIAL
1 M.S sheet (54" x 28" 11") thick (1372x710x280mm)
Base side 1 x 54/12 x 28/12 (1372x710mm)
Long side 2 x 54/12 x 11/12 (2x1372x280mm)
Short side 2 x 28/12 x 11/12 (2x710x280mm)
Top 1 x 54/12 x 28/12 (1x1372x710mm)
3.12 Sqm
3.12 Sqm @ 27.44 lbs/Per Sqm (85.50 lbs) 38.78 kg 29.00 per kg 1124.62
2 Angle Iron 1" x 1" x 1/8" (25x25x3mm)
1x2 x 54"= 108" (2x1372mm)
2 x 28" = 56" (2x710mm)
4 x 11" = 44" (4x280mm)
5.28 R/M
5.28 R/M @ 1.39 lbs/Per R/M
7.36 lbs (7.36 lbs) 3.34 kg 24.00 per kg 80.16
3 Handle chromium plated 1.00 No. 15.00 each 15.00
4 Hinges with screws 4.00 Nos. 2.50 each 10.00
Total 1289.78
Contractor's Profit & Overh 20 Percent 257.96
Total 1547.74
Total 607.50
Sundries 10 Percent 60.75
Total 668.25
Contractor's Profit & Overh 20 Percent 133.65
Total 801.90
ITEM RATES
Labour rate for Each Rs. 400.95 Say 400.95
Composite rate for Each Rs. 1948.69 Say 1948.70
Page 213
DESCRIPTION OF ITEM:
Item No. 45 Supply and erection of girder clamp hook, 16 mm (5/8") with M.S plate 25 x
with bolts and nuts for hanging ceiling fans.
MATERIAL
Total 84.00
Contractor's Profit & Overh 20 Percent 16.80
Total 100.80
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 214
DESCRIPTION OF ITEM:
Item No. 46 Supply and erection of girder strut, of M.S tee section 40 x 40 x 6 mm (1½"
1½" x ¼") complete with clamp, bolts and nuts, etc., including fixing with
cement concrete 1 : 3 : 6.
MATERIAL
5.00 kg
1 T - Iron ¼" x 1½" x 1½" x 5½" (11.00 lbs) 22.00 110.00
Clamps 1.00 kg 40.00 per kg 40.00
2 Nut & Bolts 1" (25 mm) 3.00 No. 2.00 each 6.00
3 Manufacturing 1.00 No. 74.66 each 74.66
Total 230.66
Contractor's Profit & Overh 20 Percent 46.13
Total 276.79
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 215
DESCRIPTION OF ITEM:
Item No. 47 Supply and erection of roof suspension hook,16mm (5/8" dia) rod with 75x4
(3 x 1½" x 1/8") M.S Steel Channel, with clamp, bolts & nuts etc., including
with cement concrete 1:3:6.
MATERIAL
1 Steel channel 75 x 40 x 3 mm
1.5 R/m @ 6.90 Kg/R/m 10.35 kg 10.35 kg 25.00 per kg 258.75
2 Hook 5/8" (16 mm) with nut & bolts 1.00 No. 30.00 each 30.00
3 Clamp 1.00 No. 16.00 each 16.00
4 Cement 0.042 Cft. 230.00 P. Bag 9.66
5 Sand 0.12 Cft. 350.00 Per % Cft. 0.42
Total 314.83
Contractor's Profit & Overh 20 Percent 62.97
Total 377.80
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 216
DESCRIPTION OF ITEM:
Item No. 48 Supply and erection of roof suspension hook, of M.S plate 75 x 40 x 13 mm
(3 x 1½" x ½") with 16 mm (5/8") hook, complete with bolts and nuts and fix
with cement concrete 1 : 3 : 6.
MATERIAL
Total 139.92
Contractor's Profit & Overh 20 Percent 27.98
Total 167.90
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 217
DESCRIPTION OF ITEM:
Item No. 49 Supply and erection of 3/8" (10 mm) dia M.S bar fan hook placed at the time
casting of slab.
MATERIAL
1 M.S bar hook 3/8" (!0 mm) dia 1.00 No. 8.00 each 8.00
Total 8.00
Contractor's Profit & Overh 20 Percent 1.60
Total 9.60
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 218
DESCRIPTION OF ITEM:
Item No. 50 Erection of circular L.T pole in cement concrete 1 : 3 : 6, one metre below
ground level (excluding the cost of pole), including cement concrete collar
(1 : 2 : 4) excavation of foundation and finishing surface.
MATERIAL
1 Cement concrete 1:3:6 (1.22x.300x1.0) 0.3714 Cum 0.3714 Cum 2056.90 Per Cum 763.93
Total 763.93
Contractor's Profit & Overh 20 Percent 152.79
Total 572.13
Total 460.21
Sundries 10 Percent 46.02
Total 506.23
Contractor's Profit & Overh 20 Percent 101.25
Total 607.48
ITEM RATES
Page 219
DESCRIPTION OF ITEM:
MATERIAL
Total 107.25
Contractor's Profit & Overh 20 Percent 21.45
Total 128.70
Total 212.50
Sundries 10 Percent 21.25
Total 233.75
Contractor's Profit & Overh 20 Percent 46.75
Total 280.50
ITEM RATES
Page 220
DESCRIPTION OF ITEM:
MATERIAL
1 Steel channel 75 x 13 x 6 mm
1.322 m @ 5.22 Kg/Rm 6.35 Kg
Iron plate 75 x 20 x 6 mm 0.80 Kg
7.15 Kg 7.15 Kg 25.00 per kg 178.75
Bolts and nuts 5/8" dia (16 mm) 2.00 Nos. 4.00 each 8.00
Manufacturing charges 1 job 74.66 per job 74.66
Total 261.41
Contractor's Profit & Overh 20 Percent 52.28
Total 313.69
Total 212.50
Sundries 10 Percent 21.25
Total 233.75
Contractor's Profit & Overh 20 Percent 46.75
Total 280.50
ITEM RATES
Page 221
DESCRIPTION OF ITEM:
Item No. 52 Supply and erection of anchor rod Henley type for pole, including necessary
clamps and 7/12" stay wire, straining screws, etc., erected in cement concre
1 : 3 : 6 and collar of cement concrete.
Total 217.15
Contractor's Profit & Overh 20 Percent 43.43
Total 260.58
Material per metre 235.40 ÷ 1 26.0577 26.06
Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00
ITEM RATES
Page 222
DESCRIPTION OF ITEM:
Item No. 53 Supply and erection of stay for house service pipe, erected with straining
screws and 7/14" stay wire, complete.
Total 121.15
Contractor's Profit & Overh 20 Percent 24.23
Total 145.38
Material per metre 129.80 ÷ 5 29.0754 29.08
Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60
ITEM RATES
Page 223
DESCRIPTION OF ITEM:
Item No. 54 Supply and erection of house service pipe Henley (G.I pipe water quality) or
pole, type, 50 mm (2" dia) erected to install insulated overhead line, includi
shackle insulator for holding insulated wire and straining devices for bearer
wire and other accessories, etc., complete.
1 G.I. pipe 2" dia (50 mm) 4.00 metre 199.27 per mtr. 797.08
2 Shakle insulator 1.00 No. 40.00 each 40.00
3 Clamp double 1.00 No. 40.00 each 40.00
4 Clamp 2" dia (50 mm) 1.00 No. 55.00 each 55.00
5 Rag bolts 5/8" 9" (16 x 225 mm) 1.00 No. 15.00 each 15.00
6 G.I bend 2" (50 mm) cap 2.00 Nos. 65.00 each 130.00
7 G.I Reducing socket 2 x ¾" dia (50 x 20 mm) 1.00 No. 40.00 each 40.00
8 M.S bolts for suport 1.00 No. 16.00 each 16.00
9 Cement 0.064 Cft. 230.00 P. Bag 14.72
10 Sand 0.16 Cft. 350.00 Per % Cft. 0.56
11 Bajri 0.322 1200.00 P. Cft. 3.86
Total 1152.23
Contractor's Profit & Overh 20 Percent 230.45
Total 1382.67
Material per metre 1090.45 ÷ 345.67 345.67
Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80
ITEM RATES
Page 224
DESCRIPTION OF ITEM:
Item No. 55 Supply and erection of house service pipe 50 mm (2" dia) G.I pipe Henley or
pole type, for bare copper wire overhead line, including shackle insulator,
straining devices and other accessories, etc.
1 G.I. pipe (water quality) 4.00 metre 199.27 per mtr. 797.08
2 Shakle insulator 1.00 No. 40.00 each 40.00
3 Clamp double 1.00 No. 40.00 each 40.00
4 Clamp 2" dia (50 mm) 1.00 No. 55.00 each 55.00
5 Rag bolts 5/8" 9" (16 x 225 mm) 1.00 No. 15.00 each 15.00
6 G.I bend 2" (50 mm) cap 2.00 Nos. 65.00 each 130.00
7 G.I Reducing socket 2 x ¾" dia (50 x 20 mm) 1.00 No. 40.00 each 40.00
8 M.S bar suport 1.00 No. 16.00 each 16.00
9 Cement 0.042 Cft. 230.00 P. Bag 9.66
10 Sand 0.12 Cft. 350.00 Per % Cft. 0.42
Total 1143.16
Contractor's Profit & Overh 20 Percent 228.63
Total 1371.79
Material per metre 1081.65 ÷ 342.95 342.95
Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00
ITEM RATES
Page 225
DESCRIPTION OF ITEM:
Item No. 56 Supply and erection of lightening arrestor horn type, complete.
MATERIAL
Total 200.00
Contractor's Profit & Overh 20 Percent 40.00
Total 240.00
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 226
DESCRIPTION OF ITEM:
MATERIAL
Total 40.00
Contractor's Profit & Overh 20 Percent 8.00
Total 48.00
Total 56.10
Sundries 10 Percent 5.61
Total 61.71
Contractor's Profit & Overh 20 Percent 12.34
Total 74.05
ITEM RATES
Page 227
DESCRIPTION OF ITEM:
Item No. 58 Supply and erection of pin insulator, green medium size.
MATERIAL
1 Pin insulator green (medium size) 1.00 No. 11.00 each 11.00
Total 11.00
Contractor's Profit & Overh 20 Percent 2.20
Total 13.20
Total 56.10
Sundries 10 Percent 5.61
Total 61.71
Contractor's Profit & Overh 20 Percent 12.34
Total 74.05
ITEM RATES
Page 228
DESCRIPTION OF ITEM:
Item No. 59 Supply and erection of bare copper conductor wire, No.2 to No.10 SWG,
including binding wire No.16 SWG.
MATERIAL
13.61 kg
1 Copper wire No.2 to 10 (30.00 lbs) 80.00 per kg 1088.80
2 Binding wire No.16 1.00 lbs 28.00 per kg 12.70
0.454 kg
Total 1101.50
Contractor's Profit & Overh 20 Percent 220.30
Total 1321.81
Per Kg 1211.65 ÷ 97.12 97.12
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 229
DESCRIPTION OF ITEM:
Item No. 60 Supply and erection of G.I wire of all sizes, including binding wire No.16 SW
for support of rubber wire or earthing wire, pole to pole, etc.
MATERIAL
13.61 kg
1 G.I wire (all size) (30.00 lbs) 27.00 per kg 367.47
2 Binding wire No.16 (1.00 lbs) 28.00 per kg 12.71
0.454 kg
Total 380.18
Contractor's Profit & Overh 20 Percent 76.04
Total 456.22
Material cost per Kg 418.20 ÷ 1 33.52 33.52
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 230
DESCRIPTION OF ITEM:
Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on G.I wire
No.8 SWG bearer wire and in house service pipe, including connection
through joint box:
Total 521.47
Contractor's Profit & Overh 20 Percent 104.29
Total 625.76
Material cost per metre 573.62 ÷ 4 13.31 13.31
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 231
DESCRIPTION OF ITEM:
Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on G.I wire
No.8 SWG bearer wire and in house service pipe, including connection
through joint box:
Total 800.12
Contractor's Profit & Overh 20 Percent 160.02
Total 960.14
Material cost per metre 880.13 ÷ 47 20.43 20.43
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 232
DESCRIPTION OF ITEM:
Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on G.I wire
No.8 SWG bearer wire and in house service pipe, including connection
through joint box:
Total 1118.87
Contractor's Profit & Overh 20 Percent 223.77
Total 1342.64
Material cost per metre 1230.76 ÷ 28.57 28.57
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 233
DESCRIPTION OF ITEM:
Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on G.I wire
No.8 SWG bearer wire and in house service pipe, including connection
through joint box:
Total 1306.87
Contractor's Profit & Overh 20 Percent 261.37
Total 1568.24
Material cost per metre 1437.56 ÷ 33.37 33.37
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 234
DESCRIPTION OF ITEM:
Item No. 62 Supply and erection of all aluminium stranded hard drawn bare conductor o
size 7/3.099 mm (7/0.122").
MATERIAL
Total 19.80
Contractor's Profit & Overh 20 Percent 3.96
Total 23.76
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 235
DESCRIPTION OF ITEM:
Item No. 63 Supply and erection of street light pole bracket 30 mm (1¼") G.I pipe 2 met
long, complete with 2 No. pole clamp.
MATERIAL
1 G.I. Pipe 1¼" dia (32 mm) 7 ft. (2.13 metre) 2.13 metre 125.03 per mtr. 266.31
2 Cost of clamp 2.00 Nos. 20.00 each 40.00
Total 306.31
Contractor's Profit & Overh 20 Percent 61.26
Total 367.58
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 236
DESCRIPTION OF ITEM:
Item No. 64 Supply and erection of pole mounted street light, holders, shade and glass,
etc., for fitting 125/250 watts mercury vapour lamp (excluding cost of lamp
MATERIAL
Total 1220.00
Contractor's Profit & Overh 20 Percent 244.00
Total 1464.00
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 237
DESCRIPTION OF ITEM:
Item No. 64 Supply and erection of pole mounted street light, holders, shade and glass,
etc., for fitting 125/250 watts mercury vapour lamp (excluding cost of lamp
MATERIAL
Total 2248.85
Contractor's Profit & Overh 20 Percent 449.77
Total 2698.62
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 238
DESCRIPTION OF ITEM:
Item No. 65 Supply and fitting of mercury vapour lamp, complete with choke set.
MATERIAL
Total 979.00
Contractor's Profit & Overh 20 Percent 195.80
Total 1174.80
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 239
DESCRIPTION OF ITEM:
Item No. 65 Supply and fitting of mercury vapour lamp, complete with choke set.
MATERIAL
Total 2031.54
Contractor's Profit & Overh 20 Percent 406.31
Total 2437.85
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 240
DESCRIPTION OF ITEM:
Item No. 66 Manufacture and erection of angle iron lattice steel structure pole 10923 m
long (9348 mm ground level) 355 mm square at base & 204 mm square at to
electric distribution line, using 1¼"x1¼"x3/16" angle iron legs and ¾"x¾"x1
angle iron bracings 420 mm long fixed between legs on all the four sides in
diagonal position, and 1¾" x 1¾" x 3/16" angle iron on top and 4 bands of M
flat iron 2" x ¼", 305 mm centre to centre, as per standard drawing, includi
silverpainting of pole 3 coats, excavation and refilling of foundation, cemen
concrete 1 : 2 : 4, 1807 x 500 x 500 mm for foundation, etc., complete in all
respects.
MATERIAL
Total 4807.50
Contractor's Profit & Overh 20 Percent 961.50
Total 5769.00
Page 241
Detail Unit Rate (Metric System) for Each
LABOUR
ITEM RATES
Page 242
DESCRIPTION OF ITEM:
Item No. 67 Manufacture and erection of galvanized angle iron lattice steel structure
pole 11.30 metre long (9.85 metre above ground level), 875mm square at
base, 350mm square at top, for electric distribution line, using 50x50x4mm
high tensile steel angle iron legs, and 310x310x3mm M.S angle iron bracin
fixed between legs on all the four sides in diagonal position, as per standar
drawing including silver painting of pole, excavation and refilling of
foundation, one ft. thick cement concrete 1:3:6 foundation of outer size
2.44x1.067x1.067 metre complete in all respects.
MATERIAL
4 Silver paint 0.25 gallon 0.25 gallon 550.00 per gln. 137.50
5 Cement concrete 1:3:6
(3.5 x 3.5 x 0.5) = 6.13 Cft
(1 x 3.5 x 6.5) = 22.75 Cft
(1 x 1.5 x 6.5) = 9.75 Cft
38.63 Cft 38.63 Cum 41.68 per Cum 1609.94
Total 7987.00
Contractor's Profit & Overh 20 Percent 1597.40
Total 9584.40
Page 243
Detail Unit Rate (Metric System) for Each
LABOUR
7 Cement Concrete 1:3:6 (Item 3a Chap. 6) 38.630 Cft 11.29 per Cft 435.98
8 Earth filling(1.5x.5 x 6.5) (Item 15(ii) Chap. 14.63 Cft 14.630 Cft 1.09 per Cft 16.01
Total 1365.03
Sundries 10 Percent 136.50
Total 1501.53
Contractor's Profit & Overh 20 Percent 300.31
Total 1801.84
ITEM RATES
Page 244
DESCRIPTION OF ITEM:
Item No. 68 Earthing of iron clad/aluminium switches, etc., with G.I wire No.8 SWG in G.
pipe 15 mm (½" dia) recessed or on surface of wall and floor, complete with
1.5 metre long G.I pipe, 50 mm (2" dia) with reducing socket 4 to 5 metre
below ground level, and 2 metre away from building plinth.
MATERIAL
Total 1049.07
Contractor's Profit & Overh 20 Percent 209.81
Total 1258.89
Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00
ITEM RATES
Page 245
DESCRIPTION OF ITEM:
Item No. 69 Earthing of Metallic cases, etc., with G.I wire No.8 SWG, in 15 mm (½" dia) G
pipe, best quality:
1 G.I pipe ½" dia (12 mm) 7.00 metre 52.82 per mtr. 369.74
0.454 kg
2 G.I wire No.8 SWG (1.00 lbs) 27.00 per kg 12.26
3 G.I clamp ½" dia (12 mm) 6.00 Nos. 2.00 each 12.00
4 G.I bolts 2" x ¼" dia (50 x 6 mm) 1.00 No. 2.00 each 2.00
5 Gutties 10.00 Nos. 6.00 per doz. 5.00
6 Screw ¾" (20 mm) 10.00 Nos. 3.25 each 2.71
7 G.I bend ½" dia (12 mm) 1.00 No. 8.00 each 8.00
Total 411.71
Contractor's Profit & Overh 20 Percent 82.34
Total 494.05
Material per Metre 145.48 ÷ 70.58 70.58
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 246
DESCRIPTION OF ITEM:
Item No. 69 Earthing of Metallic cases, etc., with G.I wire No.8 SWG, in 15 mm (½" dia) G
pipe, best quality:
(ii) Recessed in wall, including hooks, jharries and making good surface.
1 G.I pipe ½" dia (12 mm) 7.00 metre 52.82 per mtr. 369.74
0.454 kg
2 G.I wire No.8 SWG (1.00 lbs) 27.00 kg 12.26
3 G.I bolts 2" x ¼" dia (50 x 6 mm) 1.00 No. 2.00 each 2.00
4 Hooks 6.00 Nos. 4.00 each 24.00
5 G.I bend ½" dia (12 mm) 1.00 Nos. 8.00 each 8.00
6 Cement 0.063 Cft. 230.00 P. Bag 14.49
7 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 431.12
Contractor's Profit & Overh 20 Percent 86.22
Total 517.34
Material per Metre 470.64 ÷ 73.91 73.91
Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00
ITEM RATES
Page 247
DESCRIPTION OF ITEM:
Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.
(i) 8 SWG
Total 48.44
Contractor's Profit & Overh 20 Percent 9.69
Total 58.13
Material per Metre 51.00 ÷ 7 8.30 8.30
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 248
DESCRIPTION OF ITEM:
Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.
(ii) 16 SWG
Total 15.54
Contractor's Profit & Overh 20 Percent 3.11
Total 18.65
Material per Metre 16.53 ÷ 7 2.66 2.66
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 249
DESCRIPTION OF ITEM:
Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.
(i) 16 SWG
Total 26.49
Contractor's Profit & Overh 20 Percent 5.30
Total 31.78
Material per Metre 28.56 ÷ 7 4.54 4.54
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 250
DESCRIPTION OF ITEM:
Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.
(ii) 20 SWG
Total 14.20
Contractor's Profit & Overh 20 Percent 2.84
Total 17.03
Material per Metre 15.04 ÷ 7 2.43 2.43
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 251
DESCRIPTION OF ITEM:
Item No. 71 Erection only, of lightening conductor of copper staple, and copper nails an
cement, sand mortar.
Total 41.04
Contractor's Profit & Overh 20 Percent 8.21
Total 49.25
Material per Metre 44.00 ÷ 7 7.04 7.04
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 252
DESCRIPTION OF ITEM:
Item No. 72 Supply and erection of 600 x 600x3mm (2'x2x1/8") copper plate, including
riveting to copper tape and placing in mixture of salt & charcoal, etc.
MATERIAL
9.98 kg
1 Copper plate 600x600x3mm=0.00133 Cum (22.00 lbs) 96.00 per kg 958.08
@ 550 lbs/cft 22 lbs 36.30 kg
2 Char coal (80.00 lbs) 4.00 per kg 145.20
18.15 kg
3 Salt (40.00 lbs) 6.00 per kg 108.90
Total 1212.18
Contractor's Profit & Overh 20 Percent 242.44
Total 1454.62
Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00
ITEM RATES
Page 253
DESCRIPTION OF ITEM:
Item No. 73 Supply and erection of copper tape, including copper staple copper nails,
cement, sand, etc.
MATERIAL
Total 111.50
Contractor's Profit & Overh 20 Percent 22.30
Total 133.80
Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00
ITEM RATES
Page 254
DESCRIPTION OF ITEM:
Item No. 73 Supply and erection of copper tape, including copper staple copper nails,
cement, sand, etc.
MATERIAL
Total 133.60
Contractor's Profit & Overh 20 Percent 26.72
Total 160.32
Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00
ITEM RATES
Page 255
DESCRIPTION OF ITEM:
Item No. 74 Supply and erection of 25 mm (1"/dia) and one metre long lightning conduc
copper rod with 5 spikes on ball and base, etc., complete.
MATERIAL
Total 661.50
Contractor's Profit & Overh 20 Percent 132.30
Total 793.80
Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20
ITEM RATES
Page 256
DESCRIPTION OF ITEM:
Item No. 75 Supply and erection of electric energy metre, including metre testing fee, e
MATERIAL
1 Energy metre 10 Amp. Single phase 250 Volts 1.00 No. 350.00 each 350.00
2 Testing Fee L.S 120.00
Total 470.00
Contractor's Profit & Overh 20 Percent 94.00
Total 564.00
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 257
DESCRIPTION OF ITEM:
Item No. 75 Supply and erection of electric energy metre, including metre testing fee, e
MATERIAL
1 Energy metre 30 Amp. Single phase 250 Volts 1.00 No. 350.00 each 350.00
2 Testing Fee L.S 120.00
Total 470.00
Contractor's Profit & Overh 20 Percent 94.00
Total 564.00
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 258
DESCRIPTION OF ITEM:
Item No. 75 Supply and erection of electric energy metre, including metre testing fee, e
MATERIAL
1 Energy metre 3 x 15 Amp. Three phase 400 Volts 1.00 No. 1500.00 each 1500.00
2 Testing Fee L.S 240.00
Total 1740.00
Contractor's Profit & Overh 20 Percent 348.00
Total 2088.00
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 259
DESCRIPTION OF ITEM:
Item No. 75 Supply and erection of electric energy metre, including metre testing fee, e
MATERIAL
1 Energy metre 3 x 50 Amp. Three phase 400 Volts 1.00 No. 1500.00 each 1500.00
2 Testing Fee L.S 240.00
Total 1740.00
Contractor's Profit & Overh 20 Percent 348.00
Total 2088.00
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 260
DESCRIPTION OF ITEM:
Item No. 75 Supply and erection of electric energy metre, including metre testing fee, e
MATERIAL
1 Energy metre 3 x 80 Amp. Three phase 400 Volts 1.00 No. 1500.00 each 1500.00
2 Testing Fee L.S 240.00
Total 1740.00
Contractor's Profit & Overh 20 Percent 348.00
Total 2088.00
Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80
ITEM RATES
Page 261
DESCRIPTION OF ITEM:
Item No. 76 Rewinding of A.C ceiling fan, capacitor type, including cost of wire, leatheri
paper cotton tape, soldering, etc.
MATERIAL
Total 65.34
Contractor's Profit & Overh 20 Percent 13.07
Total 78.41
Total 325.00
Sundries 10 Percent 32.50
Total 357.50
Contractor's Profit & Overh 20 Percent 71.50
Total 429.00
ITEM RATES
Page 262
DESCRIPTION OF ITEM:
Item No. 76 Rewinding of A.C ceiling fan, capacitor type, including cost of
wire, leatheride paper cotton tape, soldering, etc.
MATERIAL
Total 265.06
Contractor's Profit & Overh 20 Percent 53.01
Total 318.07
Total 360.00
Sundries 10 Percent 36.00
Total 396.00
Contractor's Profit & Overh 20 Percent 79.20
Total 475.20
ITEM RATES
Page 263
DESCRIPTION OF ITEM:
MATERIAL
Total 168.16
Contractor's Profit & Overh 20 Percent 33.63
Total 201.79
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 264
DESCRIPTION OF ITEM:
MATERIAL
Total 189.98
Contractor's Profit & Overh 20 Percent 38.00
Total 227.98
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 265
DESCRIPTION OF ITEM:
Item No. 78 Rewinding of pedestal fan 600 mm (24") sweep, and 900 - 950
RPM, including wire, leatheride paper, cotton, tape, etc.
MATERIAL
Total 209.42
Contractor's Profit & Overh 20 Percent 41.88
Total 251.30
Total 340.00
Sundries 10 Percent 34.00
Total 374.00
Contractor's Profit & Overh 20 Percent 74.80
Total 448.80
ITEM RATES
Page 266
DESCRIPTION OF ITEM:
Item No. 79 Supply and fitting of regulator nob with shaft and plate of
electric fan regulator.
MATERIAL
1 Knob with shaff and plate 1.00 No. 50.00 each 50.00
Total 50.00
Contractor's Profit & Overh 20 Percent 10.00
Total 60.00
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 267
DESCRIPTION OF ITEM:
Item No. 80 Supply and fitting of capacitor 2.2 uf, for ceiling fans.
MATERIAL
Total 73.00
Contractor's Profit & Overh 20 Percent 14.60
Total 87.60
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 268
DESCRIPTION OF ITEM:
Item No. 81 Supply and fitting of ball bearing of size 6201, 6202 or 6203, for ceiling fans
MATERIAL
1 Ball bearing size (6201, 6202 or 6203) 1.00 No. 50.00 each 50.00
Total 50.00
Contractor's Profit & Overh 20 Percent 10.00
Total 60.00
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 269
DESCRIPTION OF ITEM:
Item No. 82 Rewinding regulator of ceiling fan (1200/1400 mm) sweep, to control
3/4 speeds.
MATERIAL
0.18 kg
1 Enamel copper wire No.26 SWG to 32 SWG (0.403 lbs) 250.00 kg 45.00
2 Leathoride paper, cotten tape and vinishing L.S 10.00
3 Deduct cost of old material (0.403 lbs) 88.00 per kg (-) 15.84
0.18 kg
Total 39.16
Contractor's Profit & Overh 20 Percent 7.83
Total 46.99
Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40
ITEM RATES
Page 270
DESCRIPTION OF ITEM:
Item No. 83 Erection of ceiling fan alongwith regulator (all sizes), including carriage
from local Railway Station/Store to site of work, electric wire/cable for
suspension rod and board connection, and cutting threading on the rod,
where necessary.
MATERIAL
Total 10.24
Contractor's Profit & Overh 20 Percent 2.05
Total 12.29
Total 450.23
Sundries 10 Percent 45.02
Total 495.25
Contractor's Profit & Overh 20 Percent 99.05
Total 594.30
ITEM RATES
Page 271