Vous êtes sur la page 1sur 271

CHAPTER NO.

24

ELECTRIC INSTALLATION
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull
boxes, inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(i) ½" dia (15 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe ½" dia (15 mm i/d) 7.00 metre 52.82 per mtr. 369.74
2 Clamp ½" dia (15 mm i/d) 10.00 Nos. 4.00 each 40.00
3 G.I bend ½" dia (15 mm i/d) 1.00 No. 8.00 each 8.00
4 Gutties 20.00 Nos. 6.00 dozen 10.00
5 Screw 1" to ¾" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
6 Inspection box ½" dia (15 mm) 1.00 No. 2.08 each 2.08
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28
Total 437.45
Contractor's Profit & Overh 20 Percent 87.49
Total 524.94
Material per metre 479.84 ÷ 7 74.99 74.99

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES
Labour rate per Metre Rs. 17.42 Say 17.40
Labour rate per Rft Rs. 5.31 Say 5.30
Composite rate per Metre Rs. 92.42 Say 92.40
Composite rate per Rft Rs. 28.18 Say 28.20

Page 1
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(ii) ¾" dia (20 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe ¾" dia (20 mm i/d) 7.00 metre 68.07 per mtr. 476.49
2 G.I bend ¾" dia (20 mm i/d) 1.00 No. 14.00 each 14.00
3 Clamp ¾" dia (20 mm i/d) 10.00 Nos. 6.00 each 60.00
4 Gutties 20.00 Nos. 6.00 dozen 10.00
5 Screw 1" to ¾" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
6 Inspection box ¾" dia (20 mm) 1.00 No. 2.33 each 2.33
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 570.45
Contractor's Profit & Overh 20 Percent 114.09
Total 684.54
Material per metre 626.14 ÷ 7 97.79 97.79

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 17.42 Say 17.40


Labour rate per Rft Rs. 5.31 Say 5.30

Composite rate per Metre Rs. 115.22 Say 115.20


Composite rate per Rft Rs. 35.13 Say 35.15

Page 2
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(iii) 1" dia (25 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe 1" dia (25 mm i/d) 7.00 metre 99.90 per mtr. 699.30
2 G.I bend 1" dia (25 mm i/d) 1.00 No. 18.00 each 18.00
3 Clamp 1" dia (25 mm i/d) 10.00 Nos. 8.00 each 80.00
4 Gutties 20.00 Nos. 6.00 dozen 10.00
5 Screw ¾" to 1" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
6 Inspection box 1" dia (25 mm) 1.00 No. 2.33 each 2.33
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 817.26
Contractor's Profit & Overh 20 Percent 163.45
Total 980.71
Material per metre 897.63 ÷ 7 140.10 140.10

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 17.42 Say 17.40


Labour rate per Rft Rs. 5.31 Say 5.30

Composite rate per Metre Rs. 157.53 Say 157.55


Composite rate per Rft Rs. 48.03 Say 48.05

Page 3
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(iv) 1¼" dia (32 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe 1¼" dia (32 mm i/d) 7.00 metre 125.03 per mtr. 875.21
2 Clamp 1¼" dia (32 mm i/d) 10.00 Nos. 10.00 each 100.00
3 G.I bend 1¼" dia (32 mm i/d) 1.00 No. 30.00 each 30.00
4 M.S. Inspection box 1¼" dia (32 mm) 1.00 No. 2.33 each 2.33
5 Gutties 20.00 Nos. 6.00 dozen 10.00
6 Screw ¾" to 1" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 1025.17
Contractor's Profit & Overh 20 Percent 205.03
Total 1230.21
Material per metre 1126.33 ÷ 175.74 175.74

LABOUR (For 50 Metre)

1 Electrician 2.00 Nos. 170.00 per day 340.00


2 Coolies skilled 3.00 Nos. 160.00 per day 480.00

Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40

ITEM RATES

Labour rate per Metre Rs. 21.65 Say 21.65


Labour rate per Rft Rs. 6.60 Say 6.60

Composite rate per Metre Rs. 197.39 Say 197.40


Composite rate per Rft Rs. 60.18 Say 60.20

Page 4
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(v) 1½" dia (40 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe 1½" dia (40 mm i/d) 7.00 metre 150.06 per mtr. 1050.42
2 G.I bend 1½" dia (40 mm i/d) 1.00 Nos. 38.00 each 38.00
3 M.S. Inspection box 1½" dia (40 mm) 1.00 No. 2.67 each 2.67
4 G.I. Clamp 1½" dia (40 mm i/d) 10.00 Nos. 10.00 each 100.00
5 Gutties 20.00 Nos. 6.00 dozen 10.00
6 Screw 1 to ¾" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 1208.72
Contractor's Profit & Overh 20 Percent 241.74
Total 1450.46
Material per metre 1330.43 ÷ 207.21 207.21

LABOUR (For 50 Metre)

1 Electrician 2.00 No. 170.00 per day 340.00


2 Coolies skilled 3.00 Nos. 160.00 per day 480.00

Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40

ITEM RATES

Labour rate per Metre Rs. 21.65 Say 21.65


Labour rate per Rft Rs. 6.60 Say 6.60

Composite rate per Metre Rs. 228.86 Say 228.85


Composite rate per Rft Rs. 69.77 Say 69.75

Page 5
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(vi) 2" dia (50 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe 2" dia (50 mm i/d) 7.00 metre 199.27 per mtr. 1394.89
2 G.I bend 2" dia (50 mm i/d) 1.00 No. 65.00 each 65.00
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. 2.66 each 2.66
4 G.I. Clamp 2" dia (50 mm i/d) 10.00 Nos. 12.00 each 120.00
5 Gutties 20.00 Nos. 6.00 dozen 10.00
6 Screw 1 to ¾" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 1600.18
Contractor's Profit & Overh 20 Percent 320.04
Total 1920.22
Material per metre 1758.85 ÷ 274.32 274.32

LABOUR (For 42 Metre)

1 Electrician 2.00 No. 170.00 per day 340.00


2 Coolies skilled 3.00 Nos. 160.00 per day 480.00

Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40

ITEM RATES

Labour rate per Metre Rs. 25.77 Say 25.75


Labour rate per Rft Rs. 7.86 Say 7.85

Composite rate per Metre Rs. 300.09 Say 300.10


Composite rate per Rft Rs. 91.49 Say 91.50

Page 6
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(vii) 3" dia (80 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe 3" dia (80 mm i/d) 7.00 metre 329.65 per mtr. 2307.55
2 G.I. Clamp 3" dia (80 mm i/d) 10.00 Nos. 18.00 each 180.00
3 M.S. Inspection box 3" dia (80 mm) 1.00 No. 2.67 each 2.67
4 G.I bend 3" dia (80 mm i/d) 1.00 No. 175.00 each 175.00
5 Gutties 20.00 Nos. 6.00 dozen 10.00
6 Screw 1 to ¾" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 2682.85
Contractor's Profit & Overh 20 Percent 536.57
Total 3219.42
Material per metre 2949.77 ÷ 459.92 459.92

LABOUR (For 33 Metre)

1 Electrician 2.00 No. 170.00 per day 340.00


2 Coolies skilled 3.00 Nos. 160.00 per day 480.00

Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40

ITEM RATES

Labour rate per Metre Rs. 32.80 Say 32.80


Labour rate per Rft Rs. 10.00 Say 10.00

Composite rate per Metre Rs. 492.72 Say 492.70


Composite rate per Rft Rs. 150.22 Say 150.20

Page 7
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

(i) ½" dia (15 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe ½" dia (15 mm i/d) 7.00 metre 52.82 per mtr. 369.74
2 G.I. Bend ½" dia (15 mm i/d) 1.00 Nos. 8.00 each 8.00
3 Hooks 8.00 No. 2.00 each 16.00
4 M.S. Inspection box ½" dia (15 mm) 1.00 Nos. 2.08 each 2.08
5 Cement 0.021 Cft. 230.00 P. Bag 4.83
6 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 400.93
Contractor's Profit & Overh 20 Percent 80.19
Total 481.12
Material per metre 442.55 ÷ 7 68.73 68.73

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 25.87 Say 25.85


Labour rate per Rft Rs. 7.89 Say 7.90

Composite rate per Metre Rs. 94.60 Say 94.60


Composite rate per Rft Rs. 28.84 Say 28.85

Page 8
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

(ii) ¾" dia (20 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe ¾" dia (20 mm i/d) 7.00 metre 68.07 per mtr. 476.49
2 G.I. Bend ¾" dia (20 mm i/d) 1.00 Nos. 14.00 each 14.00
3 Hooks 7.00 No. 2.00 each 14.00
4 M.S. Inspection box ¾" dia (20 mm) 1.00 Nos. 2.33 each 2.33
5 Cement 0.021 Cft. 230.00 P. Bag 4.83
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 512.28
Contractor's Profit & Overh 20 Percent 102.46
Total 614.74
Material per metre 564.44 ÷ 7 87.82 87.82

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 25.87 Say 25.85


Labour rate per Rft Rs. 7.89 Say 7.90

Composite rate per Metre Rs. 113.69 Say 113.70


Composite rate per Rft Rs. 34.66 Say 34.65

Page 9
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

(iii) 1" dia (25 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe 1" dia (25 mm i/d) 7.00 metre 99.90 per mtr. 699.30
2 G.I. Bend 1" dia (25 mm i/d) 1.00 Nos. 18.00 each 18.00
3 Hooks 8.00 No. 1.67 each 13.36
4 M.S. Inspection box 1" dia (25 mm) 1.00 Nos. 2.33 each 2.33
5 Cement 0.052 Cft. 230.00 P. Bag 11.96
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 745.58
Contractor's Profit & Overh 20 Percent 149.12
Total 894.70
Material per metre 820.19 ÷ 7 127.81 127.81

LABOUR (For 24 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 26.95 Say 26.95


Labour rate per Rft Rs. 8.22 Say 8.20

Composite rate per Metre Rs. 154.76 Say 154.75


Composite rate per Rft Rs. 47.18 Say 47.20

Page 10
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

(iv) 1¼" dia (32 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe 1¼" dia (32 mm i/d) 7.00 metre 125.03 per mtr. 875.21
2 G.I. Bend 1¼" dia (32 mm i/d) 1.00 Nos. 30.00 each 30.00
3 Hooks 8.00 No. 4.00 each 32.00
4 M.S. Inspection box 1¼" dia (32 mm) 1.00 Nos. 2.33 each 2.33
5 Cement 0.063 Cft. 230.00 P. Bag 14.49
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63
Total 954.66
Contractor's Profit & Overh 20 Percent 190.93
Total 1145.59
Material per metre 1046.69 ÷ 163.66 163.66

LABOUR (For 24 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 26.95 Say 26.95


Labour rate per Rft Rs. 8.22 Say 8.20

Composite rate per Metre Rs. 190.61 Say 190.60


Composite rate per Rft Rs. 58.11 Say 58.10

Page 11
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

(v) 1½" dia (40 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe 1½" dia (40 mm i/d) 7.00 metre 150.06 per mtr. 1050.42
2 G.I. Bend 1½" dia (40 mm i/d) 1.00 Nos. 38.00 each 38.00
3 M.S. Inspection box 1½" dia (40 mm i/d) 1.00 No. 2.67 each 2.67
4 Hooks 8.00 Nos. 4.00 each 32.00
5 Cement 0.074 Cft. 230.00 P. Bag 17.02
6 Sand 0.20 Cft. 350.00 Per % Cft. 0.70

Total 1140.81
Contractor's Profit & Overh 20 Percent 228.16
Total 1368.97
Material per metre 1252.99 ÷ 195.57 195.57

LABOUR (For 22 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 29.40 Say 29.40


Labour rate per Rft Rs. 8.96 Say 8.95

Composite rate per Metre Rs. 224.97 Say 224.95


Composite rate per Rft Rs. 68.59 Say 68.60

Page 12
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

(vi) 2" dia (50 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe 2" dia (50 mm i/d) 7.00 metre 199.27 per mtr. 1394.89
2 G.I. Bend 2" dia (50 mm i/d) 1.00 Nos. 65.00 each 65.00
3 M.S. Inspection box 2" dia (50 mm i/d) 1.00 No. 2.66 each 2.66
4 Hooks 8.00 Nos. 6.00 each 48.00
5 Cement 0.084 Cft. 230.00 P. Bag 19.32
6 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

Total 1530.71
Contractor's Profit & Overh 20 Percent 306.14
Total 1836.85
Material per metre 1679.21 ÷ 262.41 262.41

LABOUR (For 16 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 40.43 Say 40.45


Labour rate per Rft Rs. 12.32 Say 12.35

Composite rate per Metre Rs. 302.83 Say 302.85


Composite rate per Rft Rs. 92.33 Say 92.35

Page 13
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

(vii) 3" dia (80 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe 3" dia (80 mm i/d) 7.00 metre 329.65 per mtr. 2307.55
2 G.I. Bend 3" dia (80 mm i/d) 1.00 No. 175.00 each 175.00
3 M.S. Inspection box 3" dia (80 mm) 1.00 No. 2.67 each 2.67
4 Hooks 8.00 Nos. 8.00 each 64.00
5 G.I. Socket 3" dia (80 mm) 1.00 No. 45.00 each 45.00
6 Cement 0.08 Cft. 230.00 P. Bag 19.32
7 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

Total 2614.38
Contractor's Profit & Overh 20 Percent 522.88
Total 3137.25
Material per metre 2871.23 ÷ 448.18 448.18

LABOUR (For 10 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 64.68 Say 64.70


Labour rate per Rft Rs. 19.72 Say 19.70

Composite rate per Metre Rs. 512.86 Say 512.85


Composite rate per Rft Rs. 156.36 Say 156.35

Page 14
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(i) ½" dia (16 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe ½" dia (16 mm) 7.00 metre 27.39 per mtr. 191.73
2 M.S. Bend ½" dia (16 mm) 1.00 No. 7.00 each 7.00
3 M.S. Inspection box ½" dia (16 mm) 1.00 No. 24.96 dozen 2.08
4 Clamps ½" dia (16 mm) 10.00 Nos. 2.00 each 20.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00

Total 228.83
Contractor's Profit & Overh 20 Percent 45.77
Total 274.59
Material per metre 251.69 ÷ 7 39.23 39.23

LABOUR (For 36 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 12.10 Say 12.10


Labour rate per Rft Rs. 3.69 Say 3.70

Composite rate per Metre Rs. 51.33 Say 51.35


Composite rate per Rft Rs. 15.65 Say 15.65

Page 15
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(ii) ¾" dia (20 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe ¾" dia (20 mm) 7.00 metre 34.28 per mtr. 239.96
2 M.S. Bend ¾" dia (20 mm) 1.00 No. 12.00 each 12.00
3 M.S. Inspection box ¾" dia (20 mm) 1.00 No. 27.96 per doz. 2.33
4 M.S. Clamps ¾" dia (20 mm) 10.00 Nos. 3.00 each 30.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00
7 Cement 0.02 Cft. 230.00 P. Bag 4.83
8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

Total 297.35
Contractor's Profit & Overh 20 Percent 59.47
Total 356.82
Material per metre 325.92 ÷ 7 50.97 50.97

LABOUR (For 36 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 12.10 Say 12.10


Labour rate per Rft Rs. 3.69 Say 3.70

Composite rate per Metre Rs. 63.07 Say 63.05


Composite rate per Rft Rs. 19.23 Say 19.25

Page 16
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(iii) 1" dia (25 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1" dia (25 mm) 7.00 metre 43.20 per mtr. 302.40
2 M.S. Bend 1" dia (25 mm) 1.00 No. 16.00 each 16.00
3 M.S. Inspection box 1" dia (25 mm) 1.00 No. 27.96 per doz. 2.33
4 M.S. Clamps 1" dia (25 mm) 10.00 Nos. 6.00 each 60.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00
7 Cement 0.042 Cft. 230.00 P. Bag 9.66
8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

Total 398.83
Contractor's Profit & Overh 20 Percent 79.77
Total 478.59
Material per metre 334.40 ÷ 7 68.37 68.37

LABOUR (For 36 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 12.10 Say 12.10


Labour rate per Rft Rs. 3.69 Say 3.70

Composite rate per Metre Rs. 80.47 Say 80.45


Composite rate per Rft Rs. 24.53 Say 24.55

Page 17
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(iv) 1¼" dia (32 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1¼" dia (32 mm) 7.00 metre 56.39 per mtr. 394.73
2 M.S. Conduit Bend 1¼" dia (32 mm) 1.00 No. 27.50 each 27.50
3 M.S. Inspection box 1¼" dia (32 mm) 1.00 No. 28.00 per doz. 2.33
4 M.S. Clamps 1¼" dia (32 mm) 10.00 Nos. 8.00 each 80.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00
7 Cement 0.042 Cft. 230.00 P. Bag 9.66
8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

Total 522.66
Contractor's Profit & Overh 20 Percent 104.53
Total 627.19
Material per metre 572.62 ÷ 7 89.60 89.60

LABOUR (For 36 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 12.10 Say 12.10


Labour rate per Rft Rs. 3.69 Say 3.70

Composite rate per Metre Rs. 101.70 Say 101.70


Composite rate per Rft Rs. 31.01 Say 31.00

Page 18
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(v) 1½" dia (40 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1½" dia (40 mm) 7.00 metre 65.25 per mtr. 456.75
2 M.S. Bend 1½" dia (40 mm) 1.00 No. 38.00 each 38.00
3 M.S. Inspection box 1½" dia (40 mm) 1.00 No. 32.00 per doz. 2.67
4 M.S. Clamps 1½" dia (40 mm) 10.00 Nos. 8.00 each 80.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00
7 Cement 0.042 Cft. 230.00 P. Bag 9.66
8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

Total 595.51
Contractor's Profit & Overh 20 Percent 119.10
Total 714.62
Material per metre 652.76 ÷ 7 102.09 102.09

LABOUR (For 32 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 13.61 Say 13.60


Labour rate per Rft Rs. 4.15 Say 4.15

Composite rate per Metre Rs. 115.70 Say 115.70


Composite rate per Rft Rs. 35.27 Say 35.30

Page 19
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(vi) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 2" dia (50 mm) 7.00 metre 81.00 per mtr. 567.00
2 M.S. Conduit Bend 2" dia (50 mm) 1.00 No. 62.00 each 62.00
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. 32.00 per doz. 2.67
4 M.S. Clamps 2" dia (50 mm) 10.00 Nos. 10.00 each 100.00
5 Screw 1.20 Dozen 1.68 dozen 2.02
6 Gutties 1.00 Dozen 6.00 dozen 6.00
7 Cement 0.042 Cft. 230.00 P. Bag 9.66
8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

Total 749.76
Contractor's Profit & Overh 20 Percent 149.95
Total 899.72
Material per metre 822.43 ÷ 7 128.53 128.53

LABOUR (For 26 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 16.75 Say 16.75


Labour rate per Rft Rs. 5.11 Say 5.10

Composite rate per Metre Rs. 145.28 Say 145.30


Composite rate per Rft Rs. 44.29 Say 44.30

Page 20
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.

(i) ½" dia (16 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe ½" dia (16 mm) 7.00 metre 27.39 per mtr. 191.73
2 M.S. Bend ½" dia (16 mm) 1.00 No. 7.00 each 7.00
3 M.S. Inspection box ½" dia (16 mm) 1.00 No. 24.96 per doz. 2.08
4 M.S. Hooks 10.00 Nos. 2.00 each 20.00
5 Cement 0.021 Cft. 230.00 P. Bag 4.83
6 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 225.92
Contractor's Profit & Overh 20 Percent 45.18
Total 271.10
Material per metre 247.29 ÷ 7 38.73 38.73

LABOUR (For 28 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 23.10 Say 23.10


Labour rate per Rft Rs. 7.04 Say 7.05

Composite rate per Metre Rs. 61.83 Say 61.85


Composite rate per Rft Rs. 18.85 Say 18.85

Page 21
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.

(ii) ¾" dia (20 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Condict pipe ¾" dia (20 mm) 7.00 metre 34.28 per mtr. 239.96
2 M.S. Bend ¾" dia (20 mm) 1.00 No. 12.00 each 12.00
3 M.S. Inspection box ¾" dia (20 mm) 1.00 No. 27.96 per doz. 2.33
4 M.S. Hooks 10.00 Nos. 2.00 each 20.00
5 Cement 0.042 Cft. 230.00 P. Bag 9.66
6 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

Total 284.37
Contractor's Profit & Overh 20 Percent 56.87
Total 341.24
Material per metre 310.12 ÷ 7 48.75 48.75

LABOUR (For 28 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 23.10 Say 23.10


Labour rate per Rft Rs. 7.04 Say 7.05

Composite rate per Metre Rs. 71.85 Say 71.85


Composite rate per Rft Rs. 21.91 Say 21.90

Page 22
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.

(iii) 1" dia (25 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1" dia (25 mm) 7.00 metre 43.20 per mtr. 302.40
2 M.S. Bend 1" dia (25 mm) 1.00 No. 16.00 each 16.00
3 M.S. Inspection box 1" dia (25 mm) 1.00 No. 27.96 per doz. 2.33
4 Hooks 10.00 Nos. 2.00 each 20.00
5 Cement 0.052 Cft. 230.00 P. Bag 11.96
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 353.32
Contractor's Profit & Overh 20 Percent 70.66
Total 423.98
Material per metre 385.81 ÷ 7 60.57 60.57

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 25.87 Say 25.85


Labour rate per Rft Rs. 7.89 Say 7.90

Composite rate per Metre Rs. 86.42 Say 86.40


Composite rate per Rft Rs. 26.35 Say 26.35

Page 23
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.

(iv) 1¼" dia (32 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1¼" dia (32 mm) 7.00 metre 56.39 per mtr. 394.73
2 M.S. Conduit Bend 1¼" dia (32 mm) 1.00 No. 27.50 each 27.50
3 M.S. Inspection box 1¼" dia (32 mm) 1.00 No. 28.00 per doz. 2.33
4 M.S. Hooks 10.00 Nos. 4.00 each 40.00
5 Cement 0.063 Cft. 230.00 P. Bag 14.49
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 479.68
Contractor's Profit & Overh 20 Percent 95.94
Total 575.62
Material per metre 524.22 ÷ 7 82.23 82.23

LABOUR (For 24 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 26.95 Say 26.95


Labour rate per Rft Rs. 8.22 Say 8.20

Composite rate per Metre Rs. 109.18 Say 109.20


Composite rate per Rft Rs. 33.29 Say 33.30

Page 24
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.

(v) 1½" dia (40 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1½" dia (40 mm) 7.00 metre 65.25 per mtr. 456.75
2 M.S. Conduit Bend 1½" dia (40 mm) 1.00 No. 38.00 each 38.00
3 M.S. Inspection box 1½" dia (40 mm) 1.00 No. 32.00 per doz. 2.67
4 M.S. Hooks 10.00 Nos. 4.00 each 40.00
5 Cement 0.074 Cft. 230.00 P. Bag 17.02
6 Sand 0.20 Cft. 350.00 Per % Cft. 0.70

Total 555.14
Contractor's Profit & Overh 20 Percent 111.03
Total 666.16
Material per metre 606.56 ÷ 7 95.17 95.17

LABOUR (For 23 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 28.12 Say 28.10


Labour rate per Rft Rs. 8.57 Say 8.55

Composite rate per Metre Rs. 123.29 Say 123.30


Composite rate per Rft Rs. 37.59 Say 37.60

Page 25
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and repairing
surface etc.

(vi) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 2" dia (50 mm) 7.00 metre 81.00 per mtr. 567.00
2 M.S. Conduit Bend 2" dia (50 mm) 1.00 No. 62.00 each 62.00
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. 32.00 per doz. 2.67
4 Hooks 10.00 Nos. 6.00 each 60.00
5 Cement 0.084 Cft. 230.00 P. Bag 19.32
6 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

Total 711.83
Contractor's Profit & Overh 20 Percent 142.37
Total 854.19
Material per metre 778.43 ÷ 7 122.03 122.03

LABOUR (For 22 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 29.40 Say 29.40


Labour rate per Rft Rs. 8.96 Say 8.95

Composite rate per Metre Rs. 151.43 Say 151.45


Composite rate per Rft Rs. 46.16 Say 46.15

Page 26
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.

(i) ½" dia (12 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe ½" dia (12 mm) 10.00 metre 8.25 per mtr. 82.50
2 PVC Bend ½" dia (12 mm) 2.00 No. 1.50 each 3.00
3 M.S. Hook 10.00 No. 2.00 each 20.00
4 PVC Inspection box ½" (12 mm) 2.00 Nos. 25.00 per doz. 4.17
5 Cement 0.042 Cft. 230.00 P. Bag 9.66
6 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

Total 119.75
Contractor's Profit & Overh 20 Percent 23.95
Total 143.70
Material per metre 129.43 ÷ 1 14.37 14.37

LABOUR (For 31 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 20.86 Say 20.85


Labour rate per Rft Rs. 6.36 Say 6.35

Composite rate per Metre Rs. 35.23 Say 35.25


Composite rate per Rft Rs. 10.74 Say 10.75

Page 27
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.

(ii) ¾" dia (20 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe ¾" dia (20 mm) 10.00 metre 10.85 per mtr. 108.50
2 PVC Bend ¾" dia (20 mm) 2.00 No. 3.00 each 6.00
3 M.S. Hook 10.00 No. 2.00 each 20.00
4 PVC Inspection box ¾" dia (20 mm) 2.00 Nos. 25.00 per doz. 4.17
5 Cement 0.052 Cft. 230.00 P. Bag 11.96
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 151.26
Contractor's Profit & Overh 20 Percent 30.25
Total 181.51
Material per metre 163.53 ÷ 1 18.15 18.15

LABOUR (For 30 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 21.56 Say 21.55


Labour rate per Rft Rs. 6.57 Say 6.55

Composite rate per Metre Rs. 39.71 Say 39.70


Composite rate per Rft Rs. 12.10 Say 12.10

Page 28
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.

(iii) 1" dia (25 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1" dia (25 mm) 10.00 metre 14.90 per mtr. 149.00
2 PVC Bend 1" dia (25 mm) 2.00 No. 4.00 each 8.00
3 M.S. Hook 10.00 No. 4.00 each 40.00
4 PVC Inspection box 1" dia (25 mm) 2.00 Nos. 28.00 per doz. 4.67
5 Cement 0.063 Cft. 230.00 P. Bag 14.49
6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 216.79
Contractor's Profit & Overh 20 Percent 43.36
Total 260.14
Material per metre 235.03 ÷ 1 26.01 26.01

LABOUR (For 27 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 23.96 Say 23.95


Labour rate per Rft Rs. 7.30 Say 7.30

Composite rate per Metre Rs. 49.97 Say 49.95


Composite rate per Rft Rs. 15.23 Say 15.25

Page 29
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.

(iv) 1¼" dia (30 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1¼" dia (30 mm) 10.00 metre 22.90 per mtr. 229.00
2 PVC Bend 1¼" dia (30 mm) 2.00 No. 6.00 each 12.00
3 M.S. Hook 10.00 No. 4.00 each 40.00
4 PVC Inspection box 1¼" dia (30 mm) 2.00 Nos. 28.00 per doz. 4.67
5 Cement 0.065 Cft. 230.00 P. Bag 14.95
6 Sand 0.37 Cft. 350.00 Per % Cft. 1.30

Total 301.91
Contractor's Profit & Overh 20 Percent 60.38
Total 362.29
Material per metre 228.053÷ 1 36.23 36.23

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 25.87 Say 25.85


Labour rate per Rft Rs. 7.89 Say 7.90

Composite rate per Metre Rs. 62.10 Say 62.10


Composite rate per Rft Rs. 18.93 Say 18.95

Page 30
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.

(v) 1½" dia (40 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1½" dia (40 mm) 10.00 metre 33.60 per mtr. 336.00
2 PVC Bend 1½" dia (40 mm) 2.00 No. 9.00 each 18.00
3 M.S. Hook 10.00 No. 4.00 each 40.00
4 PVC Inspection box 1½" dia (40 mm) 2.00 Nos. 32.00 per doz. 5.33
5 Cement 0.070 Cft. 230.00 P. Bag 16.10
6 Sand 0.40 Cft. 350.00 Per % Cft. 1.40

Total 416.83
Contractor's Profit & Overh 20 Percent 83.37
Total 500.20
Material per metre 454.67 ÷ 1 50.02 50.02

LABOUR (For 24 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 26.95 Say 26.95


Labour rate per Rft Rs. 8.22 Say 8.20

Composite rate per Metre Rs. 76.97 Say 76.95


Composite rate per Rft Rs. 23.47 Say 23.45

Page 31
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,
including inspection boxes, pull boxes, hooks, cutting, jharriers and
repairing surface etc., complete with all specials.

(vi) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50
2 PVC Bend 2" dia (50 mm) 2.00 No. 15.00 each 30.00
3 M.S. Hook 10.00 No. 4.00 each 40.00
4 Cement 0.084 Cft. 230.00 P. Bag 19.32
5 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

Total 572.66
Contractor's Profit & Overh 20 Percent 114.53
Total 687.19
Material per metre 625.35 ÷ 1 68.72 68.72

LABOUR (For 23 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 28.12 Say 28.10


Labour rate per Rft Rs. 8.57 Say 8.55

Composite rate per Metre Rs. 96.85 Say 96.85


Composite rate per Rft Rs. 29.53 Say 29.55

Page 32
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.

(i) ½" dia (12 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe ½" dia (12 mm) 10.00 metre 8.25 per mtr. 82.50
2 PVC Bend ½" dia (12 mm) 2.00 Nos. 1.50 each 3.00
3 M.S. Clamp/saddle 20.00 Nos. 2.00 each 40.00
4 Gutties 20.00 Nos. 0.50 each 10.00
5 Screws for ½" dia clamp 20.00 Nos. 10.00 per doz. 16.67
6 PVC Inspection Box ½" dia (12 mm) 2.00 Nos. 25.00 per doz. 4.17
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

Total 161.37
Contractor's Profit & Overh 20 Percent 32.27
Total 193.65
Material per metre 176.37 ÷ 1 19.36 19.36

LABOUR (For 80 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.45 Say 5.45


Labour rate per Rft Rs. 1.66 Say 1.65

Composite rate per Metre Rs. 24.81 Say 24.80


Composite rate per Rft Rs. 7.57 Say 7.55

Page 33
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.

(ii) ¾" dia (20 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe ¾" dia (20 mm) 10.00 metre 10.85 per mtr. 108.50
2 PVC Bend ¾" dia (20 mm) 2.00 Nos. 3.00 each 6.00
3 M.S. Clamp ¾" dia (20 mm) 10.00 Nos. 3.00 each 30.00
4 Screws for ¾" dia clamp 20.00 Nos. 10.00 per doz. 16.67
5 PVC Inspection Box ¾" dia (20 mm) 2.00 Nos. 25.00 per doz. 4.17
6 Cement 0.021 Cft. 230.00 P. Bag 4.83
7 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

Total 170.37
Contractor's Profit & Overh 20 Percent 34.07
Total 204.45
Material per metre 186.27 ÷ 1 20.44 20.44

LABOUR (For 80 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.45 Say 5.45


Labour rate per Rft Rs. 1.66 Say 1.65

Composite rate per Metre Rs. 25.89 Say 25.90


Composite rate per Rft Rs. 7.89 Say 7.90

Page 34
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.

(iii) 1" dia (25 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1" dia (25 mm) 10.00 metre 14.90 per mtr. 149.00
2 PVC Bend 1" dia (25 mm) 2.00 Nos. 4.00 each 8.00
3 M.S. Clamp/saddle 1 dia (25 mm) 20.00 Nos. 6.00 each 120.00
4 Screws for 1" dia clamp 20.00 Nos. 12.00 per doz. 20.00
5 Gutties 20.00 Nos. 6.00 per doz. 10.00
6 PVC Inspection Box 1" dia (25 mm) 2.00 Nos. 28.00 per doz. 4.67
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

Total 316.71
Contractor's Profit & Overh 20 Percent 63.34
Total 380.05
Material per metre 347.23 ÷ 1 38.00 38.00

LABOUR (For 80 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.45 Say 5.45


Labour rate per Rft Rs. 1.66 Say 1.65

Composite rate per Metre Rs. 43.45 Say 43.45


Composite rate per Rft Rs. 13.25 Say 13.25

Page 35
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.

(iv) 1¼" dia (30 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1¼" dia (30 mm) 10.00 metre 22.90 per mtr. 229.00
2 PVC Bend 1¼" dia (30 mm) 2.00 Nos. 6.00 each 12.00
3 M.S. Clamp/saddle 1¼" dia (30 mm) 20.00 Nos. 8.00 each 160.00
4 Gutties 20.00 Nos. 6.00 per doz. 10.00
5 Screws for 1¼" dia clamp 20.00 Nos. 15.00 per doz. 25.00
6 PVC Inspection Box 1¼" dia (30 mm) 2.00 Nos. 28.00 per doz. 4.67

Total 440.67
Contractor's Profit & Overh 20 Percent 88.13
Total 528.80
Material per metre 484.73 ÷ 1 52.88 52.88

LABOUR (For 70 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 6.22 Say 6.20


Labour rate per Rft Rs. 1.90 Say 1.90

Composite rate per Metre Rs. 59.10 Say 59.10


Composite rate per Rft Rs. 18.02 Say 18.00

Page 36
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.

(v) 1½" dia (40 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1½" dia (40 mm) 10.00 metre 33.60 per mtr. 336.00
2 PVC Bend 1½" dia (40 mm) 2.00 Nos. 9.00 each 18.00
3 M.S. Clamp/saddle 1½" dia (40 mm) 20.00 Nos. 8.00 each 160.00
4 Gutties 20.00 Nos. 6.00 per doz. 10.00
5 Screws for 1½" dia clamp 20.00 Nos. 18.00 per doz. 30.00
6 PVC Inspection Box 1½" dia (40 mm) 2.00 Nos. 32.00 per doz. 5.33
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

Total 564.37
Contractor's Profit & Overh 20 Percent 112.87
Total 677.24
Material per metre 619.67 ÷ 1 67.72 67.72

LABOUR (For 70 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 6.22 Say 6.20


Labour rate per Rft Rs. 1.90 Say 1.90

Composite rate per Metre Rs. 73.95 Say 73.95


Composite rate per Rft Rs. 22.55 Say 22.55

Page 37
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps
inspection boxes, pull boxes bends, tees repairing surface etc., complete
with all specials.

(vi) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50
2 PVC Bend 2" dia (50 mm) 2.00 Nos. 15.00 each 30.00
3 M.S. Clamp/saddle 2" dia (50 mm) 20.00 Nos. 10.00 each 200.00
4 Gutties 20.00 Nos. 6.00 per doz. 10.00
5 Screws for 2" dia clamp 20.00 Nos. 30.00 per doz. 50.00
6 PVC Inspection Box 2" dia (50 mm) 2.00 Nos. 32.00 per doz. 5.33
7 Cement 0.021 Cft. 230.00 P. Bag 4.83
8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

Total 782.66
Contractor's Profit & Overh 20 Percent 156.53
Total 939.20
Material per metre 860.02 ÷ 1 93.92 93.92

LABOUR (For 58 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 7.51 Say 7.50


Labour rate per Rft Rs. 2.29 Say 2.30

Composite rate per Metre Rs. 101.43 Say 101.45


Composite rate per Rft Rs. 30.92 Say 30.90

Page 38
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.

(i) ½" dia (12 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe ½" dia (12 mm) 1.00 metre 14.40 per mtr. 14.40
2 Socket ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
3 Nipple ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
4 Check Nuts ½" dia (12 mm) 2.00 Nos. 5.00 each 10.00
5 Soldering etc. L.S 8.00

Total 46.40
Contractor's Profit & Overh 20 Percent 9.28
Total 55.68

LABOUR (For 32 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00
3 Welding charges 2.00 joints 8.00 per joints 16.00

Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72

ITEM RATES

Labour rate per Metre Rs. 14.27 Say 14.25


Labour rate per Rft Rs. 4.35 Say 4.35

Composite rate per Metre Rs. 69.95 Say 69.95


Composite rate per Rft Rs. 21.33 Say 21.35

Page 39
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.

(ii) ¾" dia (20 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe ¾" dia (20 mm) 1.00 metre 19.68 per mtr. 19.68
2 G.I. Socket ¾" dia (20 mm) 2.00 Nos. 5.00 each 10.00
3 G.I. Nipple ¾" dia (20 mm) 2.00 Nos. 6.00 each 12.00
4 Check Nuts ¾" dia (20 mm) 2.00 Nos. 8.00 each 16.00
5 Solder joint L.S 8.00

Total 65.68
Contractor's Profit & Overh 20 Percent 13.14
Total 78.82

LABOUR (For 30 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00
3 Welding charges 2.00 joints 8.00 per joint 16.00

Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72

ITEM RATES

Labour rate per Metre Rs. 15.22 Say 15.20


Labour rate per Rft Rs. 4.64 Say 4.65

Composite rate per Metre Rs. 94.04 Say 94.05


Composite rate per Rft Rs. 28.67 Say 28.65

Page 40
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.

(iii) 1" dia (25 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe 1" dia (25 mm) 1.00 metre 22.60 per mtr. 22.60
2 G.I. Socket 1" dia (25 mm) 2.00 Nos. 7.00 each 14.00
3 G.I. Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
4 Check Nuts 1" dia (25 mm) 2.00 Nos. 12.00 each 24.00
5 Solder L.S 8.00

Total 84.60
Contractor's Profit & Overh 20 Percent 16.92
Total 101.52

LABOUR (For 29 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00
3 Welding charges 2.00 joints 8.00 per joints 16.00

Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72

ITEM RATES

Labour rate per Metre Rs. 15.75 Say 15.75


Labour rate per Rft Rs. 4.80 Say 4.80

Composite rate per Metre Rs. 117.27 Say 117.25


Composite rate per Rft Rs. 35.75 Say 35.75

Page 41
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.

(iv) 1¼" dia (32 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe 1¼" dia (32 mm) 1.00 metre 29.52 per mtr. 29.52
2 G.I. Socket 1¼" dia (32 mm) 2.00 Nos. 12.00 each 24.00
3 G.I. Nipple 1¼" dia (32 mm) 2.00 Nos. 14.00 each 28.00
4 Check Nuts 1¼" dia (32 mm) 2.00 Nos. 16.00 each 32.00
5 Solder L.S 8.00

Total 121.52
Contractor's Profit & Overh 20 Percent 24.30
Total 145.82

LABOUR (For 24 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00
3 Welding charges 2.00 joints 8.00 per joints 16.00

Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72

ITEM RATES

Labour rate per Metre Rs. 19.03 Say 19.05


Labour rate per Rft Rs. 5.80 Say 5.80

Composite rate per Metre Rs. 164.85 Say 164.85


Composite rate per Rft Rs. 50.26 Say 50.25

Page 42
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.

(v) 1½" dia (40 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe 1½" dia (40 mm) 1.00 metre 39.37 per mtr. 39.37
2 G.I. Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
3 G.I. Nipple 1½" dia (40 mm) 2.00 Nos. 20.00 each 40.00
4 Check Nuts 1½" dia (40 mm) 2.00 Nos. 20.00 each 40.00
5 Solder L.S 8.00

Total 157.37
Contractor's Profit & Overh 20 Percent 31.47
Total 188.84

LABOUR (For 22 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00
3 Welding charges 2.00 joints 8.00 per joints 16.00

Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72

ITEM RATES

Labour rate per Metre Rs. 20.76 Say 20.75


Labour rate per Rft Rs. 6.33 Say 6.35

Composite rate per Metre Rs. 209.60 Say 209.60


Composite rate per Rft Rs. 63.90 Say 63.90

Page 43
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.

(vi) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe 2" dia (50 mm) 1.00 metre 55.77 per mtr. 55.77
2 G.I. Socket 2" dia (50 mm) 2.00 Nos. 21.00 each 42.00
3 G.I. Nipple 2" dia (50 mm) 2.00 Nos. 22.00 each 44.00
4 Check Nuts 2" dia (50 mm) 2.00 Nos. 25.00 each 50.00
5 Solder L.S 8.00

Total 199.77
Contractor's Profit & Overh 20 Percent 39.95
Total 239.72

LABOUR (For 20 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00
3 Welding charges 2.00 joints 8.00 per joints 16.00

Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72

ITEM RATES

Labour rate per Metre Rs. 22.84 Say 22.85


Labour rate per Rft Rs. 6.96 Say 6.95

Composite rate per Metre Rs. 262.56 Say 262.55


Composite rate per Rft Rs. 80.05 Say 80.05

Page 44
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of
sockets, nipples and check nuts etc complete.

(vii) 3" dia (80 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe 3" dia (80 mm) 1.00 metre 110.00 per mtr. 110.00
2 G.I. Socket 3" dia (80 mm) 2.00 Nos. 45.00 each 90.00
3 G.I. Nipple 3" dia (80 mm) 2.00 Nos. 25.00 each 50.00
4 Check Nuts 3" dia (80 mm) 2.00 Nos. 20.00 each 40.00
5 Solder L.S 12.00

Total 302.00
Contractor's Profit & Overh 20 Percent 60.40
Total 362.40

LABOUR (For 15 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00
3 Welding charges 2.00 joints 8.00 per joints 16.00

Total 346.00
Sundries 10 Percent 34.60
Total 380.60
Contractor's Profit & Overh 20 Percent 76.12
Total 456.72

ITEM RATES

Labour rate per Metre Rs. 30.45 Say 30.45


Labour rate per Rft Rs. 9.28 Say 9.30

Composite rate per Metre Rs. 392.85 Say 392.85


Composite rate per Rft Rs. 119.77 Say 119.75

Page 45
DESCRIPTION OF ITEM:

Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-main)
purposes including bends special etc., in floor, wall or trenches.

(i) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50
2 PVC Bend 2" dia (50 mm) 2.00 Nos. 15.00 each 30.00
3 M.S Hooks 10.00 Nos. 4.00 each 40.00
4 PVC Inspection box 2.00 Nos. 32.00 per doz. 5.33
5 Cement 0.084 Cft. 230.00 P. Bag 19.32
6 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

Total 577.99
Contractor's Profit & Overh 20 Percent 115.60
Total 693.59
Material per metre 631.22 ÷ 69.36 69.36

LABOUR (For 23 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 28.12 Say 28.10


Labour rate per Rft Rs. 8.57 Say 8.55

Composite rate per Metre Rs. 97.48 Say 97.50


Composite rate per Rft Rs. 29.72 Say 29.70

Page 46
DESCRIPTION OF ITEM:

Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-main)
purposes including bends special etc., in floor, wall or trenches.

(ii) 3" dia (80 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 3" dia (75 mm) 10.00 metre 66.75 per mtr. 667.50
2 PVC Bend 3" dia (75 mm) 2.00 Nos. 25.00 each 50.00
3 PVC Inspection box 2.00 Nos. 40.00 per doz. 6.67
4 Cement 0.106 Cft. 230.00 P. Bag 24.38
5 Sand 0.25 Cft. 350.00 Per % Cft. 0.88

Total 749.42
Contractor's Profit & Overh 20 Percent 149.88
Total 899.31
Material per metre 818.58 ÷ 89.93 89.93

LABOUR (For 20 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 32.34 Say 32.35


Labour rate per Rft Rs. 9.86 Say 9.85

Composite rate per Metre Rs. 122.27 Say 122.25


Composite rate per Rft Rs. 37.28 Say 37.30

Page 47
DESCRIPTION OF ITEM:

Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-main)
purposes including bends special etc., in floor, wall or trenches.

(iii) 4" dia (100 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 4" dia (100 mm) 10.00 metre 88.00 per mtr. 880.00
2 PVC Bend 4" dia (100 mm) 2.00 Nos. 65.00 each 130.00
3 PVC Inspection box 2.00 Nos. 48.00 per doz. 8.00
4 Cement 0.106 Cft. 230.00 P. Bag 24.38
5 Sand 0.25 Cft. 350.00 Per % Cft. 0.88

Total 1043.26
Contractor's Profit & Overh 20 Percent 208.65
Total 1251.91
Material per metre 1141.80 ÷ 125.19 125.19

LABOUR (For 20 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 32.34 Say 32.35


Labour rate per Rft Rs. 9.86 Say 9.85

Composite rate per Metre Rs. 157.53 Say 157.55


Composite rate per Rft Rs. 48.03 Say 48.05

Page 48
DESCRIPTION OF ITEM:

Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and sub main)
including clamps bends etc., complete with all specials.

(i) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50
2 PVC Bend 2" dia (50 mm) 2.00 Nos. 15.00 each 30.00
3 M.S Clamp 20.00 Nos. 10.00 each 200.00
4 PVC Inspection boxes 2.00 Nos. 32.00 per doz. 5.33
5 Gutties 20.00 Nos. 6.00 per doz. 10.00
6 Cement 0.021 Cft. 230.00 P. Bag 4.83
7 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

Total 732.87
Contractor's Profit & Overh 20 Percent 146.57
Total 879.44
Material per metre 802.27 ÷ 1 87.94 87.94

LABOUR (For 58 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 7.51 Say 7.50


Labour rate per Rft Rs. 2.29 Say 2.30

Composite rate per Metre Rs. 95.45 Say 95.45


Composite rate per Rft Rs. 29.10 Say 29.10

Page 49
DESCRIPTION OF ITEM:

Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and sub main)
including clamps bends etc., complete with all specials.

(ii) 3" dia (80mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 3" dia (75 mm) 10.00 metre 66.75 per mtr. 667.50
2 PVC Bend 3" dia (75 mm) 2.00 Nos. 25.00 each 50.00
3 M.S Clamp 20.00 Nos. 18.00 each 360.00
4 PVC Inspection boxes 2.00 Nos. 32.00 per doz. 5.33
5 Screws for 3" dia clamp 40.00 Nos. 12.00 per doz. 40.00
6 Gutties 40.00 Nos. 6.00 per doz. 20.00
7 Cement 0.042 Cft. 230.00 P. Bag 9.66
8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

Total 1152.91
Contractor's Profit & Overh 20 Percent 230.58
Total 1383.50
Material per metre 1155.92 ÷ 138.35 138.35

LABOUR (For 40 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 10.89 Say 10.90


Labour rate per Rft Rs. 3.32 Say 3.30

Composite rate per Metre Rs. 149.24 Say 149.25


Composite rate per Rft Rs. 45.50 Say 45.50

Page 50
DESCRIPTION OF ITEM:

Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and sub main)
including clamps bends etc., complete with all specials.

(iii) 4" dia (100 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 4" dia (100 mm) 10.00 metre 88.00 per mtr. 880.00
2 PVC Bend 4" dia (100 mm) 2.00 Nos. 65.00 each 130.00
3 M.S Clamp 20.00 Nos. 15.00 each 300.00
4 Gutties 40.00 Nos. 6.00 per doz. 20.00
5 Screws for 4" dia clamp 40.00 Nos. 12.00 per doz. 40.00
6 PVC Inspection boxes 2.00 Nos. 48.00 per doz. 8.00
7 Cement 0.084 Cft. 230.00 P. Bag 19.32
8 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

Total 1398.16
Contractor's Profit & Overh 20 Percent 279.63
Total 1677.79
Material per metre 1533.77 ÷ 167.78 167.78

LABOUR (For 35 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 12.45 Say 12.45


Labour rate per Rft Rs. 3.79 Say 3.80

Composite rate per Metre Rs. 180.22 Say 180.25


Composite rate per Rft Rs. 54.95 Say 54.95

Page 51
DESCRIPTION OF ITEM:

Item No. 8 Supply and erection of wooden strip batten for wiring purposes including cl
insulation cleats etc.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 100 Metre)

1 Strip casing 100.00 metre 300.00 % per mtr. 300.00


2 Gutties 10.00 Nos. 6.00 per doz. 5.00
3 Clamp & nails 300.00 Nos. 10.00 % No. 30.00
4 Screw 7.25 Dozen 1.68 Dozen 12.18
5 Insulated cleats 100.00 Nos. 1.00 each 100.00

Total 447.18
Contractor's Profit & Overh 20 Percent 89.44
Total 536.62
Material per metre 491.70 ÷ 1 5.37 5.37

LABOUR (For 200 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 2.18 Say 2.20


Labour rate per Rft Rs. 0.66 Say 0.65

Composite rate per Metre Rs. 7.54 Say 7.55


Composite rate per Rft Rs. 2.30 Say 2.30

Page 52
DESCRIPTION OF ITEM:

Item No. 9 Supply and erection of sahl wood casing and capping for wiring purposes,
including insulation cleats, screws etc., complete.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 100 Metre)

1 Casing Sahlwood 100.00 metre 24.00 per mtr. 2400.00


2 Screw 20.00 Nos. 3.25 P. Doz. 5.42
3 Gutties 20.00 Nos. 6.00 per doz. 10.00
4 Insulated cleats 20.00 Nos. 0.25 each 5.00
5 Screw for cover 0.60 Dozen 1.68 Dozen 1.01

Total 2421.42
Contractor's Profit & Overh 20 Percent 484.28
Total 2905.71
Material per metre 2662.00 ÷ 29.06 29.06

LABOUR (For 200 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 2.18 Say 2.20


Labour rate per Rft Rs. 0.66 Say 0.65

Composite rate per Metre Rs. 31.24 Say 31.25


Composite rate per Rft Rs. 9.52 Say 9.50

Page 53
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.029" = 1 coil 90.00 metre 4.31 per mtr. 387.90
Wastage (3%) 11.64

Total 399.54
Contractor's Profit & Overh 20 Percent 79.91
Total 479.44
Material per metre 439.49 ÷ 9 5.33 5.33

LABOUR (For 100 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.36 Say 4.35


Labour rate per Rft Rs. 1.33 Say 1.35

Composite rate per Metre Rs. 9.68 Say 9.70


Composite rate per Rft Rs. 2.95 Say 2.95

Page 54
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(ii) 3/0.91 mm (3.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.036" = 1 coil 90.00 metre 6.24 per mtr. 561.60
Wastage (3%) 16.85

Total 578.45
Contractor's Profit & Overh 20 Percent 115.69
Total 694.14
Material per metre 636.29 ÷ 9 7.71 7.71

LABOUR (For 100 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.36 Say 4.35


Labour rate per Rft Rs. 1.33 Say 1.35

Composite rate per Metre Rs. 12.07 Say 12.05


Composite rate per Rft Rs. 3.68 Say 3.70

Page 55
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(iii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.029" = 1 coil 90.00 metre 8.91 per mtr. 801.90
Wastage (3%) 24.06

Total 825.96
Contractor's Profit & Overh 20 Percent 165.19
Total 991.15
Material per metre 908.55 ÷ 9 11.01 11.01

LABOUR (For 100 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.36 Say 4.35


Labour rate per Rft Rs. 1.33 Say 1.35

Composite rate per Metre Rs. 15.37 Say 15.35


Composite rate per Rft Rs. 4.69 Say 4.70

Page 56
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre 11.28 per mtr. 1015.20
Wastage (3%) 30.46

Total 1045.66
Contractor's Profit & Overh 20 Percent 209.13
Total 1254.79
Material per metre 1150.22 ÷ 13.94 13.94

LABOUR (For 90 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.84 Say 4.85


Labour rate per Rft Rs. 1.48 Say 1.50

Composite rate per Metre Rs. 18.78 Say 18.80


Composite rate per Rft Rs. 5.73 Say 5.75

Page 57
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre 16.09 per mtr. 1448.10
Wastage (3%) 43.44

Total 1491.54
Contractor's Profit & Overh 20 Percent 298.31
Total 1789.85
Material per metre 1640.70 ÷ 19.89 19.89

LABOUR (For 80 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.45 Say 5.45


Labour rate per Rft Rs. 1.66 Say 1.65

Composite rate per Metre Rs. 25.33 Say 25.35


Composite rate per Rft Rs. 7.72 Say 7.70

Page 58
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(vi) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre 42.87 per mtr. 3858.30
Wastage (3%) 115.75

Total 3974.05
Contractor's Profit & Overh 20 Percent 794.81
Total 4768.86
Material per metre 4371.45 ÷ 52.99 52.99

LABOUR (For 65 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 6.70 Say 6.70


Labour rate per Rft Rs. 2.04 Say 2.05

Composite rate per Metre Rs. 59.69 Say 59.70


Composite rate per Rft Rs. 18.20 Say 18.20

Page 59
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(vii) 19/1.32 mm (19/0.052")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.052" = 1 coil 90.00 metre 57.04 per mtr. 5133.60
Wastage (2%) 102.67

Total 5236.27
Contractor's Profit & Overh 20 Percent 1047.25
Total 6283.53
Material per metre 5759.90 ÷ 69.82 69.82

LABOUR (For 70 Metre)

1 Electrician 2.00 Nos. 170.00 per day 340.00


2 Cooly skilled 3.00 Nos. 160.00 per day 480.00

Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40

ITEM RATES

Labour rate per Metre Rs. 15.46 Say 15.45


Labour rate per Rft Rs. 4.71 Say 4.70

Composite rate per Metre Rs. 85.28 Say 85.30


Composite rate per Rft Rs. 26.00 Say 26.00

Page 60
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(viii) 19/1.63 mm (19/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.064" = 1 coil 90.00 metre 133.33per 90 mtr. 11999.70


Wastage (2%) 239.99

Total 12239.69
Contractor's Profit & Overh 20 Percent 2447.94
Total 14687.63
Material per metre 13464.0 ÷ 163.20 163.20

LABOUR (For 60 Metre)

1 Electrician 2.00 Nos. 170.00 per day 340.00


2 Cooly skilled 3.00 Nos. 160.00 per day 480.00

Total 820.00
Sundries 10 Percent 82.00
Total 902.00
Contractor's Profit & Overh 20 Percent 180.40
Total 1082.40

ITEM RATES

Labour rate per Metre Rs. 18.04 Say 18.05


Labour rate per Rft Rs. 5.50 Say 5.50

Composite rate per Metre Rs. 181.24 Say 181.25


Composite rate per Rft Rs. 55.25 Say 55.25

Page 61
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.029" = 1 coil 90.00 metre 5.00 per mtr. 450.00
Wastage (3%) 13.50

Total 463.50
Contractor's Profit & Overh 20 Percent 92.70
Total 556.20
Material per metre 509.85 ÷ 9 6.18 6.18

LABOUR (For 90 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.84 Say 4.85


Labour rate per Rft Rs. 1.48 Say 1.50

Composite rate per Metre Rs. 11.02 Say 11.00


Composite rate per Rft Rs. 3.36 Say 3.35

Page 62
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(ii) 3/0.91 mm (3/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.036" = 1 coil 90.00 metre 6.00 per mtr. 540.00
Wastage (3%) 16.20

Total 556.20
Contractor's Profit & Overh 20 Percent 111.24
Total 667.44
Material per metre 611.82 ÷ 9 7.42 7.42

LABOUR (For 90 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.84 Say 4.85


Labour rate per Rft Rs. 1.48 Say 1.50

Composite rate per Metre Rs. 12.26 Say 12.25


Composite rate per Rft Rs. 3.74 Say 3.75

Page 63
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(iii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.029" = 1 coil 90.00 metre 8.00 per mtr. 720.00
Wastage (3%) 21.60

Total 741.60
Contractor's Profit & Overh 20 Percent 148.32
Total 889.92
Material per metre 815.76 ÷ 9 9.89 9.89

LABOUR (For 90 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.84 Say 4.85


Labour rate per Rft Rs. 1.48 Say 1.50

Composite rate per Metre Rs. 14.73 Say 14.75


Composite rate per Rft Rs. 4.49 Say 4.50

Page 64
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre 9.50 per mtr. 855.00
Wastage (3%) 25.65

Total 880.65
Contractor's Profit & Overh 20 Percent 176.13
Total 1056.78
Material per metre 968.72 ÷ 9 11.74 11.74

LABOUR (For 85 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.12 Say 5.15


Labour rate per Rft Rs. 1.56 Say 1.55

Composite rate per Metre Rs. 16.87 Say 16.85


Composite rate per Rft Rs. 5.14 Say 5.15

Page 65
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre 15.00 per mtr. 1350.00
Wastage (3%) 40.50

Total 1390.50
Contractor's Profit & Overh 20 Percent 278.10
Total 1668.60
Material per metre 1529.55 ÷ 18.54 18.54

LABOUR (For 76 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.73 Say 5.75


Labour rate per Rft Rs. 1.75 Say 1.75

Composite rate per Metre Rs. 24.27 Say 24.25


Composite rate per Rft Rs. 7.40 Say 7.40

Page 66
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(vi) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre 40.00 per mtr. 3600.00
Wastage (3%) 108.00

Total 3708.00
Contractor's Profit & Overh 20 Percent 741.60
Total 4449.60
Material per metre 4078.80 ÷ 49.44 49.44

LABOUR (For 66 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 6.60 Say 6.60


Labour rate per Rft Rs. 2.01 Say 2.00

Composite rate per Metre Rs. 56.04 Say 56.05


Composite rate per Rft Rs. 17.09 Say 17.10

Page 67
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.029" = 1 coil 90.00 metre 4.96 per mtr. 446.40
Wastage (3%) 13.39

Total 459.79
Contractor's Profit & Overh 20 Percent 91.96
Total 551.75
Material per metre 505.77 ÷ 9 6.13 6.13

LABOUR (For 100 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.36 Say 4.35


Labour rate per Rft Rs. 1.33 Say 1.35

Composite rate per Metre Rs. 10.49 Say 10.50


Composite rate per Rft Rs. 3.20 Say 3.20

Page 68
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(ii) 3/0.91 mm (3/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.036" = 1 coil 90.00 metre 7.26 per mtr. 653.40
Wastage (3%) 19.60

Total 673.00
Contractor's Profit & Overh 20 Percent 134.60
Total 807.60
Material per metre 740.30 ÷ 9 8.97 8.97

LABOUR (For 100 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.36 Say 4.35


Labour rate per Rft Rs. 1.33 Say 1.35

Composite rate per Metre Rs. 13.33 Say 13.35


Composite rate per Rft Rs. 4.06 Say 4.05

Page 69
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(iii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.074" = 1 coil 90.00 metre 9.89 per mtr. 890.10
Wastage (3%) 26.70

Total 916.80
Contractor's Profit & Overh 20 Percent 183.36
Total 1100.16
Material per metre 1008.48 ÷ 12.22 12.22

LABOUR (For 100 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.36 Say 4.35


Labour rate per Rft Rs. 1.33 Say 1.35

Composite rate per Metre Rs. 16.58 Say 16.60


Composite rate per Rft Rs. 5.05 Say 5.05

Page 70
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre 14.88 per mtr. 1339.20
Wastage (3%) 40.18

Total 1379.38
Contractor's Profit & Overh 20 Percent 275.88
Total 1655.25
Material per metre 1517.31 ÷ 18.39 18.39

LABOUR (For 90 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.84 Say 4.85


Labour rate per Rft Rs. 1.48 Say 1.50

Composite rate per Metre Rs. 23.23 Say 23.25


Composite rate per Rft Rs. 7.08 Say 7.10

Page 71
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre 21.02 per mtr. 1891.80
Wastage (3%) 56.75

Total 1948.55
Contractor's Profit & Overh 20 Percent 389.71
Total 2338.26
Material per metre 2143.41 ÷ 25.98 25.98

LABOUR (For 80 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.45 Say 5.45


Labour rate per Rft Rs. 1.66 Say 1.65

Composite rate per Metre Rs. 31.43 Say 31.45


Composite rate per Rft Rs. 9.58 Say 9.60

Page 72
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copper
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pipes/M.S
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(vi) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre 43.58 per mtr. 3922.20
Wastage (3%) 117.67

Total 4039.87
Contractor's Profit & Overh 20 Percent 807.97
Total 4847.84
Material per metre 4443.85 ÷ 53.86 53.86

LABOUR (For 65 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 6.70 Say 6.70


Labour rate per Rft Rs. 2.04 Say 2.05

Composite rate per Metre Rs. 60.57 Say 60.55


Composite rate per Rft Rs. 18.47 Say 18.45

Page 73
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduit/PVC
pipe/G.I wire/trenches etc., (rate per cable only).

(i) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre 42.87 per mtr. 3858.30
Wastage (2%) 77.17

Total 3935.47
Contractor's Profit & Overh 20 Percent 787.09
Total 4722.56
Material per metre 4329.01 ÷ 52.47 52.47

LABOUR (For 66 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 6.60 Say 6.60


Labour rate per Rft Rs. 2.01 Say 2.00

Composite rate per Metre Rs. 59.07 Say 59.05


Composite rate per Rft Rs. 18.01 Say 18.00

Page 74
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).

(ii) 19/0.32 mm (19/0.052")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.052" = 1 coil 90.00 metre 57.04 per mtr. 5133.60
Wastage (2%) 102.67

Total 5236.27
Contractor's Profit & Overh 20 Percent 1047.25
Total 6283.53
Material per metre 5759.90 ÷ 69.82 69.82

LABOUR (For 60 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 7.26 Say 7.25


Labour rate per Rft Rs. 2.21 Say 2.20

Composite rate per Metre Rs. 77.08 Say 77.10


Composite rate per Rft Rs. 23.50 Say 23.50

Page 75
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).

(iii) 19/0.63 mm (19/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.064" = 1 coil 90.00 metre 77.71 per mtr. 6993.90
Wastage (2%) 139.88

Total 7133.78
Contractor's Profit & Overh 20 Percent 1426.76
Total 8560.53
Material per metre 7847.16 ÷ 95.12 95.12

LABOUR (For 55 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 7.92 Say 7.90


Labour rate per Rft Rs. 2.41 Say 2.40

Composite rate per Metre Rs. 103.04 Say 103.05


Composite rate per Rft Rs. 31.41 Say 31.40

Page 76
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).

(iv) 19/2.11 mm (19/0.083")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.083" = 1 coil 90.00 metre 150.60 per mtr. 13554.00
Wastage (2%) 271.08

Total 13825.08
Contractor's Profit & Overh 20 Percent 2765.02
Total 16590.10
Material per metre 12207.59 ÷ 184.33 184.33

LABOUR (For 50 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 8.71 Say 8.70


Labour rate per Rft Rs. 2.66 Say 2.65

Composite rate per Metre Rs. 193.05 Say 193.05


Composite rate per Rft Rs. 58.86 Say 58.85

Page 77
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).

(v) 37/1.83 mm (37/0.072")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.072" = 1 coil 90.00 metre 209.59 per mtr. 18863.10
Wastage (2%) 377.26

Total 19240.36
Contractor's Profit & Overh 20 Percent 3848.07
Total 23088.43
Material per metre 21264.40 ÷ 256.54 256.54

LABOUR (For 29 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 15.02 Say 15.00


Labour rate per Rft Rs. 4.58 Say 4.60

Composite rate per Metre Rs. 271.56 Say 271.55


Composite rate per Rft Rs. 82.79 Say 82.80

Page 78
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).

(vi) 37/2.11 mm (37/0.083")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.083" = 1 coil 90.00 metre 261.34 per mtr. 23520.60
Wastage (2%) 470.41

Total 23991.01
Contractor's Profit & Overh 20 Percent 4798.20
Total 28789.21
Material per metre 26390.11 ÷ 319.88 319.88

LABOUR (For 24 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 18.15 Say 18.15


Labour rate per Rft Rs. 5.53 Say 5.55

Composite rate per Metre Rs. 338.03 Say 338.05


Composite rate per Rft Rs. 103.06 Say 103.05

Page 79
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed copper
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S conduits/PVC
pipe/G.I wire/trenches etc., (rate per cable only).

(vii) 37/2.62 mm (37/0.103")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.103" = 1 coil 90.00 metre 403.24 per mtr. 36291.60
Wastage (2%) 725.83

Total 37017.43
Contractor's Profit & Overh 20 Percent 7403.49
Total 44420.92
Material per metre 40719.18 ÷ 493.57 493.57

LABOUR (For 17 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 25.62 Say 25.60


Labour rate per Rft Rs. 7.81 Say 7.80

Composite rate per Metre Rs. 519.19 Say 519.20


Composite rate per Rft Rs. 158.29 Say 158.30

Page 80
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.029" = 1 coil 90.00 metre 13.21 per mtr. 1188.90
Wastage (3%) 35.67

Total 1224.6
Contractor's Profit & Overh 20 Percent 244.91
Total 1347.03
Material per metre 1347.03 ÷ 14.97 14.97

LABOUR (For 90 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.84 Say 4.85


Labour rate per Rft Rs. 1.48 Say 1.50

Composite rate per Metre Rs. 19.81 Say 19.80


Composite rate per Rft Rs. 6.04 Say 6.05

Page 81
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(ii) 3/0.91 mm (3/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.036" = 1 coil 90.00 metre 17.12 per mtr. 1540.80
Wastage (3%) 46.22

Total 1587.02
Contractor's Profit & Overh 20 Percent 317.40
Total 1904.43
Material per metre 1745.73 ÷ 21.16 21.16

LABOUR (For 90 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.84 Say 4.85


Labour rate per Rft Rs. 1.48 Say 1.50

Composite rate per Metre Rs. 26.00 Say 26.00


Composite rate per Rft Rs. 7.93 Say 7.95

Page 82
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(iii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.029" = 1 coil 90.00 metre 23.36 per mtr. 2102.40
Wastage (3%) 63.07

Total 2165.47
Contractor's Profit & Overh 20 Percent 433.09
Total 2598.57
Material per metre 2382.02 ÷ 28.87 28.87

LABOUR (For 90 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 4.84 Say 4.85


Labour rate per Rft Rs. 1.48 Say 1.50

Composite rate per Metre Rs. 33.71 Say 33.70


Composite rate per Rft Rs. 10.28 Say 10.30

Page 83
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre 33.08 per mtr. 2977.20
Wastage (3%) 89.32

Total 3066.52
Contractor's Profit & Overh 20 Percent 613.30
Total 3679.82
Material per metre 3373.17 ÷ 40.89 40.89

LABOUR (For 85 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.12 Say 5.15


Labour rate per Rft Rs. 1.56 Say 1.55

Composite rate per Metre Rs. 46.01 Say 46.00


Composite rate per Rft Rs. 14.03 Say 14.05

Page 84
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre 47.38 per mtr. 4264.20
Wastage (3%) 127.93

Total 4392.13
Contractor's Profit & Overh 20 Percent 878.43
Total 5270.55
Material per metre 4831.34 ÷ 58.56 58.56

LABOUR (For 76 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.73 Say 5.75


Labour rate per Rft Rs. 1.75 Say 1.75

Composite rate per Metre Rs. 64.29 Say 64.30


Composite rate per Rft Rs. 19.60 Say 19.60

Page 85
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(vi) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre 80.88 per mtr. 7279.20
Wastage (2%) 145.58

Total 7424.78
Contractor's Profit & Overh 20 Percent 1484.96
Total 8909.74
Material per metre 8167.26 ÷ 99.00 99.00

LABOUR (For 66 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 6.60 Say 6.60


Labour rate per Rft Rs. 2.01 Say 2.00

Composite rate per Metre Rs. 105.60 Say 105.60


Composite rate per Rft Rs. 32.19 Say 32.20

Page 86
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3 core 1 coil 90.00 metre 16.75 per mtr. 1507.50
Wastage (3%) 45.23

Total 1552.73
Contractor's Profit & Overh 20 Percent 310.55
Total 1863.27
Material per metre 1708.00 ÷ 20.70 20.70

LABOUR (For 85 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.12 Say 5.15


Labour rate per Rft Rs. 1.56 Say 1.55

Composite rate per Metre Rs. 25.83 Say 25.85


Composite rate per Rft Rs. 7.87 Say 7.85

Page 87
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(ii) 3/0.91 mm (3/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3 core 1 coil 90.00 metre 27.00 per mtr. 2430.00
Wastage (3%) 72.90

Total 2502.90
Contractor's Profit & Overh 20 Percent 500.58
Total 3003.48
Material per metre 2753.19 ÷ 33.37 33.37

LABOUR (For 85 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.12 Say 5.15


Labour rate per Rft Rs. 1.56 Say 1.55

Composite rate per Metre Rs. 38.50 Say 38.50


Composite rate per Rft Rs. 11.74 Say 11.75

Page 88
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(iii) 3/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.029" = 1 coil 90.00 metre 33.03 per mtr. 2972.70
Wastage (3%) 89.18

Total 3061.88
Contractor's Profit & Overh 20 Percent 612.38
Total 3674.26
Material per metre 3368.07 ÷ 40.83 40.83

LABOUR (For 85 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.12 Say 5.15


Labour rate per Rft Rs. 1.56 Say 1.55

Composite rate per Metre Rs. 45.95 Say 45.95


Composite rate per Rft Rs. 14.01 Say 14.00

Page 89
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre 46.96 per mtr. 4226.40
Wastage (2%) 84.53

Total 4310.93
Contractor's Profit & Overh 20 Percent 862.19
Total 5173.11
Material per metre 4742.02 ÷ 57.48 57.48

LABOUR (For 76 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.73 Say 5.75


Labour rate per Rft Rs. 1.75 Say 1.75

Composite rate per Metre Rs. 63.21 Say 63.20


Composite rate per Rft Rs. 19.27 Say 19.25

Page 90
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre 67.89 per mtr. 6110.10
Wastage (2%) 122.20

Total 6232.30
Contractor's Profit & Overh 20 Percent 1246.46
Total 7478.76
Material per metre 6855.53 ÷ 83.10 83.10

LABOUR (For 72 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 6.05 Say 6.05


Labour rate per Rft Rs. 1.84 Say 1.85

Composite rate per Metre Rs. 89.15 Say 89.15


Composite rate per Rft Rs. 27.18 Say 27.20

Page 91
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(vi) 7/1.13 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre 138.77 per mtr. 12489.30
Wastage (2%) 249.79

Total 12739.09
Contractor's Profit & Overh 20 Percent 2547.82
Total 15286.90
Material per metre 14012.99÷ 169.85 169.85

LABOUR (For 63 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 6.91 Say 6.90


Labour rate per Rft Rs. 2.11 Say 2.10

Composite rate per Metre Rs. 176.77 Say 176.75


Composite rate per Rft Rs. 53.89 Say 53.90

Page 92
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.

(i) 3/70.74 m,m (3/0.29")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.029" = 1 coil 90.00 metre 22.40 per mtr. 2016.00
Wastage (3%) 60.48

Total 2076.48
Contractor's Profit & Overh 20 Percent 415.30
Total 2491.78
Material per metre 2284.12 ÷ 27.69 27.69

LABOUR (For 80 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.45 Say 5.45


Labour rate per Rft Rs. 1.66 Say 1.65

Composite rate per Metre Rs. 33.13 Say 33.15


Composite rate per Rft Rs. 10.10 Say 10.10

Page 93
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.

(ii) 3/0.91 mm (3/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.036" = 1 coil 90.00 metre 34.51 per mtr. 3105.90
Wastage (3%) 93.18

Total 3199.08
Contractor's Profit & Overh 20 Percent 639.82
Total 3838.89
Material per metre 3518.98 ÷ 42.65 42.65

LABOUR (For 80 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.45 Say 5.45


Labour rate per Rft Rs. 1.66 Say 1.65

Composite rate per Metre Rs. 48.10 Say 48.10


Composite rate per Rft Rs. 14.66 Say 14.65

Page 94
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.

(iii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.029" = 1 coil 90.00 metre 43.32 per mtr. 3898.80
Wastage (2%) 77.98

Total 3976.78
Contractor's Profit & Overh 20 Percent 795.36
Total 4772.13
Material per metre 4374.45 ÷ 53.02 53.02

LABOUR (For 76 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.73 Say 5.75


Labour rate per Rft Rs. 1.75 Say 1.75

Composite rate per Metre Rs. 58.76 Say 58.75


Composite rate per Rft Rs. 17.91 Say 17.90

Page 95
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre 56.72 per mtr. 5104.80
Wastage (2%) 102.10

Total 5206.90
Contractor's Profit & Overh 20 Percent 1041.38
Total 6248.28
Material per metre 5727.59 ÷ 69.43 69.43

LABOUR (For 76 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 5.73 Say 5.75


Labour rate per Rft Rs. 1.75 Say 1.75

Composite rate per Metre Rs. 75.16 Say 75.15


Composite rate per Rft Rs. 22.91 Say 22.90

Page 96
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre 78.38 per mtr. 7054.20
Wastage (2%) 141.08

Total 7195.28
Contractor's Profit & Overh 20 Percent 1439.06
Total 8634.34
Material per metre 7914.81 ÷ 95.94 95.94

LABOUR (For 72 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 6.05 Say 6.05


Labour rate per Rft Rs. 1.84 Say 1.85

Composite rate per Metre Rs. 101.99 Say 102.00


Composite rate per Rft Rs. 31.09 Say 31.10

Page 97
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.

(vi) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre 176.60 per mtr. 15894.00
Wastage (2%) 317.88

Total 16211.88
Contractor's Profit & Overh 20 Percent 3242.38
Total 19454.26
Material per metre 17833.07÷ 216.16 216.16

LABOUR (For 63 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 6.91 Say 6.90


Labour rate per Rft Rs. 2.11 Say 2.10

Composite rate per Metre Rs. 223.07 Say 223.05


Composite rate per Rft Rs. 68.01 Say 68.00

Page 98
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cable.

(vii) 19/1.32 mm (19/0.052")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.052" = 1 coil 90.00 metre 251.08 per mtr. 22597.20
Wastage (2%) 451.94

Total 23049.14
Contractor's Profit & Overh 20 Percent 4609.83
Total 27658.97
Material per metre 25354.06÷ 307.32 307.32

LABOUR (For 45 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 9.68 Say 9.70


Labour rate per Rft Rs. 2.95 Say 2.95

Composite rate per Metre Rs. 317.00 Say 317.00


Composite rate per Rft Rs. 96.65 Say 96.65

Page 99
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.

(i) 19/1.32 mm (19/0.052")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.052" = 1 coil 90.00 metre 110.56 per mtr. 9950.40
Wastage (2%) 199.01

Total 10149.41
Contractor's Profit & Overh 20 Percent 2029.88
Total 12179.29
Material per metre 11164.35÷ 135.33 135.33

LABOUR (For 45 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 9.68 Say 9.70


Labour rate per Rft Rs. 2.95 Say 2.95

Composite rate per Metre Rs. 145.01 Say 145.00


Composite rate per Rft Rs. 44.21 Say 44.20

Page 100
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.

(ii) 19/1.63 mm (19/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.064" = 1 coil 90.00 metre 159.62 per mtr. 14365.80
Wastage (2%) 287.32

Total 14653.12
Contractor's Profit & Overh 20 Percent 2930.62
Total 17583.74
Material per metre 16118.43 ÷ 195.37 195.37

LABOUR (For 42 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 10.37 Say 10.35


Labour rate per Rft Rs. 3.16 Say 3.15

Composite rate per Metre Rs. 205.75 Say 205.75


Composite rate per Rft Rs. 62.73 Say 62.75

Page 101
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with
G.I wire 16 SWG.

(iii) 19/1.83 mm (19/0.072")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.072" = 1 coil 90.00 metre 210.82 per mtr. 18973.80
Wastage (2%) 379.48

Total 19353.28
Contractor's Profit & Overh 20 Percent 3870.66
Total 23223.93
Material per metre 21288.60 ÷ 258.04 258.04

LABOUR (For 40 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 10.89 Say 10.90


Labour rate per Rft Rs. 3.32 Say 3.30

Composite rate per Metre Rs. 268.93 Say 268.95


Composite rate per Rft Rs. 81.99 Say 82.00

Page 102
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with
G.I wire 16 SWG.

(iv) 19/2.11 mm (19/0.083")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.083" = 1 coil 90.00 260.65 per mtr. 23458.50


Wastage (2%) 469.17

Total 23927.67
Contractor's Profit & Overh 20 Percent 4785.53
Total 28713.20
Material per metre 26320.44 ÷ 319.04 319.04

LABOUR (For 37 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 11.77 Say 11.75


Labour rate per Rft Rs. 3.59 Say 3.60

Composite rate per Metre Rs. 330.81 Say 330.80


Composite rate per Rft Rs. 100.86 Say 100.85

Page 103
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.

(v) 37/1.83 mm (37/0.072")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.072" = 1 coil 90.00 metre 404.84 per mtr. 36435.60
Wastage (2%) 728.71

Total 37164.31
Contractor's Profit & Overh 20 Percent 7432.86
Total 44597.17
Material per metre 40880.74 ÷ 495.52 495.52

LABOUR (For 36 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 12.10 Say 12.10


Labour rate per Rft Rs. 3.69 Say 3.70

Composite rate per Metre Rs. 507.62 Say 507.60


Composite rate per Rft Rs. 154.76 Say 154.75

Page 104
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.

(vi) 37/2.11 mm (37/0.083")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.083" = 1 coil 90.00 metre 536.83 per mtr. 48314.70
Wastage (2%) 966.29

Total 49281.00
Contractor's Profit & Overh 20 Percent 9856.20
Total 59137.19
Material per metre 54209.09 ÷ 657.08 657.08

LABOUR (For 30 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 14.52 Say 14.50


Labour rate per Rft Rs. 4.43 Say 4.45

Composite rate per Metre Rs. 671.60 Say 671.60


Composite rate per Rft Rs. 204.76 Say 204.75

Page 105
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.

(vii) 37/2.36 mm (37/0.093")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.093" = 1 coil 90.00 metre 675.03 per mtr. 60752.70
Wastage (2%) 1215.05

Total 61967.76
Contractor's Profit & Overh 20 Percent 12393.55
Total 74361.31
Material per metre 68164.53 ÷ 826.24 826.24

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 17.42 Say 17.40


Labour rate per Rft Rs. 5.31 Say 5.30

Composite rate per Metre Rs. 843.66 Say 843.65


Composite rate per Rft Rs. 257.21 Say 257.20

Page 106
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connection, in
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured with G
wire 16 SWG.

(viii) 37/2.62 mm (37/0.103")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.103" = 1 coil 90.00 metre 807.02 per mtr. 72631.80
Wastage (2%) 1452.64

Total 74084.44
Contractor's Profit & Overh 20 Percent 14816.89
Total 88901.33
Material per metre 81492.88 ÷ 987.79 987.79

LABOUR (For 20 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 21.78 Say 21.80


Labour rate per Rft Rs. 6.64 Say 6.65

Composite rate per Metre Rs. 1009.57 Say 1009.55


Composite rate per Rft Rs. 307.80 Say 307.80

Page 107
DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.

(i) 10 x 10 cm (4" x 4") (100 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 4" x 4" (100 x 100 mm) 1.00 No. 50.00 each 50.00
2 Cement 0.021 Cft. 230.00 P. Bag 4.83
3 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 55.11
Contractor's Profit & Overh 20 Percent 11.02
Total 66.13

LABOUR (For 20 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 21.78 Say 21.80


Composite rate for Each Rs. 87.91 Say 87.90

Page 108
DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.

(ii) 17.5 x 10 cm (7" x 4") (175 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 7" x 4" (175 x 100 mm) 1.00 No. 60.00 each 60.00
2 Cement 0.026 Cft. 230.00 P. Bag 5.98
3 Sand 0.09 Cft. 350.00 Per % Cft. 0.32

Total 66.30
Contractor's Profit & Overh 20 Percent 13.26
Total 79.55

LABOUR (For 16 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 27.23 Say 27.25


Composite rate for Each Rs. 106.78 Say 106.80

Page 109
DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.

(iii) 22.5 x 10 cm (9" x 4") (225 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 9" x 4" (225 x 100 mm) 1.00 No. 69.00 each 69.00
2 Cement 0.032 Cft. 230.00 P. Bag 7.36
3 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 76.64
Contractor's Profit & Overh 20 Percent 15.33
Total 91.97

LABOUR (For 12 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 36.30 Say 36.30


Composite rate for Each Rs. 128.27 Say 128.25

Page 110
DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.

(iv) 20 x 25 cm (8" x 10") (200 x 250 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 8" x 10" (200 x 250 mm) 1.00 No. 95.00 each 95.00
2 Cement 0.036 Cft. 230.00 P. Bag 8.28
3 Sand 0.150 Cft. 350.00 Per % Cft. 0.53

Total 103.81
Contractor's Profit & Overh 20 Percent 20.76
Total 124.57

LABOUR (For 10 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Page 111
Labour rate for Each Rs. 43.56 Say 43.55
Composite rate for Each Rs. 168.13 Say 168.15

DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.

(v) 25 x 30 cm (10" x 12") (250 x 300 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 10" x 12" (250 x 300 mm) 1.00 No. 125.00 each 125.00
2 Cement 0.047 Cft. 230.00 P. Bag 10.81
3 Sand 0.155 Cft. 350.00 Per % Cft. 0.54

Total 136.35
Contractor's Profit & Overh 20 Percent 27.27
Total 163.62

LABOUR (For 8 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 54.45 Say 54.45


Composite rate for Each Rs. 218.07 Say 218.05

Page 112
DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm) deep,
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring, includin
making holes for regulators, switches, plugs, etc.

(vi) 30 x 35 cm (12" x 14") (300 x 350 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 12" x 14" (300 x 350 mm) 1.00 No. 188.00 each 188.00
2 Cement 0.052 Cft. 230.00 P. Bag 11.96
3 Sand 0.180 Cft. 350.00 Per % Cft. 0.63

Total 200.59
Contractor's Profit & Overh 20 Percent 40.12
Total 240.71

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 313.31 Say 313.30

Page 113
DESCRIPTION OF ITEM:

Item No. 15 Supply and erectionof round block of Sahl wood, 10 x 4 cm 4" x 1½"
(100 x 40 mm).

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Round block 0.544 No. 12.00 each 6.53


2 W. Gutti 1½" x 1" (40 x 25 mm) 1.00 No. 6.00 per doz. 0.50
3 Screw 1.00 Dozen 3.25 per doz. 0.27

Total 7.30
Contractor's Profit & Overh 20 Percent 1.46
Total 8.76

LABOUR (For 70 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 6.22 Say 6.20


Composite rate for Each Rs. 14.98 Say 15.00

Page 114
DESCRIPTION OF ITEM:

Item No. 16 Supply and erection of teak wood board, 4.5 cm 1¾" (45 mm) thick.

(i) 17.5 x 10 cm (7" x 4") (175 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Teak Wood Board 7" x 4" (175 x 100 mm) 1.00 No. 20.00 each 20.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 12.00 per dozen 2.00

Total 23.00
Contractor's Profit & Overh 20 Percent 4.60
Total 27.60

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 8.71 Say 8.70


Composite rate for Each Rs. 36.31 Say 36.30

Page 115
DESCRIPTION OF ITEM:

Item No. 16 Supply and erection of teak wood board, 4.5 cm 1¾" (45 mm) thick.

(ii) 22.5 x 10 cm (9" x 4") (225 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Teak Wood Board 9" x 4" (225 x 100 mm) 1.00 No. 25.00 each 25.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 12.00 per dozen 2.00

Total 28.00
Contractor's Profit & Overh 20 Percent 5.60
Total 33.60

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 8.71 Say 8.70


Composite rate for Each Rs. 42.31 Say 42.30

Page 116
DESCRIPTION OF ITEM:

Item No. 16 Supply and erection of teak wood board, 4.5 cm 1¾" (45 mm) thick.

(iii) 20 x 25 cm (8" x 10") (200 x 250 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Teak Wood Board 8" x 10" (200 x 250 mm) 1.00 No. 30.00 each 30.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 12.00 per dozen 2.00

Total 33.00
Contractor's Profit & Overh 20 Percent 6.60
Total 39.60

LABOUR (For 45 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 9.68 Say 9.70


Composite rate for Each Rs. 49.28 Say 49.30

Page 117
DESCRIPTION OF ITEM:

Item No. 16 Supply and erection of teak wood board, 4.5 cm 1¾" (45 mm) thick.

(iv) 25 x 30 cm (10" x 12") (250 x 300 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Teak Wood Wooden Board 10" x 12" (250 x 300 mm) 1.00 No. 40.00 each 40.00
2 W. Gutti 4.00 Nos. 6.00 per dozen 2.00
3 Screw 4.00 Nos. 15.00 per dozen 5.00

Total 47.00
Contractor's Profit & Overh 20 Percent 9.40
Total 56.40

LABOUR (For 40 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 10.89 Say 10.90


Composite rate for Each Rs. 67.29 Say 67.30

Page 118
DESCRIPTION OF ITEM:

Item No. 16 Supply and erection of teak wood board, 4.5 cm 1¾" (45 mm) thick.

(v) 30 x 35 cm (12" x 14") (300 x 350 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Teak Wood Board 12" x 14" (300 x 350 mm) 1.00 No. 60.00 each 60.00
2 W. Gutti 4.00 Nos. 6.00 per dozen 2.00
3 Screw 4.00 Nos. 15.00 per dozen 5.00

Total 67.00
Contractor's Profit & Overh 20 Percent 13.40
Total 80.40

LABOUR (For 35 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 12.45 Say 12.45


Composite rate for Each Rs. 92.85 Say 92.85

Page 119
DESCRIPTION OF ITEM:

Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1¾" (45 mm) thick.

(i) 17.5 x 10 cm (7" x 4") (175 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Sahl Wood Board 7" x 4" (175 x 100 mm) 1.00 No. 21.50 each 21.50
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 15.00 per dozen 2.50

Total 25.00
Contractor's Profit & Overh 20 Percent 5.00
Total 30.00

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 8.71 Say 8.70


Composite rate for Each Rs. 38.71 Say 38.70

Page 120
DESCRIPTION OF ITEM:

Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1¾" (45 mm) thick.

(ii) 22.5 x 10 cm (9" x 4") (225 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Sahl Wood Board 9" x 4" (225 x 100 mm) 1.00 No. 30.00 each 30.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 15.00 per dozen 2.50

Total 33.50
Contractor's Profit & Overh 20 Percent 6.70
Total 40.20

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 8.71 Say 8.70


Composite rate for Each Rs. 48.91 Say 48.90

Page 121
DESCRIPTION OF ITEM:

Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1¾" (45 mm) thick.

(iii) 20 x 25 cm (8" x 10") (200 x 250 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Sahl Wood Board 8" x 10" (200 x 250 mm) 1.00 No. 35.00 each 35.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 12.00 per dozen 2.00

Total 38.00
Contractor's Profit & Overh 20 Percent 7.60
Total 45.60

LABOUR (For 45 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 9.68 Say 9.70


Composite rate for Each Rs. 55.28 Say 55.30

Page 122
DESCRIPTION OF ITEM:

Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1¾" (45 mm) thick.

(iv) 25 x 30 cm (10" x 12") (250 x 300 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Sahl Wood Board 10" x 12" (250 x 300 mm) 1.00 No. 45.00 each 45.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 12.00 per dozen 2.00

Total 48.00
Contractor's Profit & Overh 20 Percent 9.60
Total 57.60

LABOUR (For 40 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 10.89 Say 10.90


Composite rate for Each Rs. 68.49 Say 68.50

Page 123
DESCRIPTION OF ITEM:

Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1¾" (45 mm) thick.

(v) 30 x 35 cm (12" x 14") (300 x 350 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Sahl Wood Board 12" x 14" (300 x 350 mm) 1.00 No. 60.00 each 60.00
2 W. Gutti 2.00 Nos. 6.00 per dozen 1.00
3 Screw 2.00 Nos. 15.00 per dozen 2.50

Total 63.50
Contractor's Profit & Overh 20 Percent 12.70
Total 76.20

LABOUR (For 35 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 12.45 Say 12.45


Composite rate for Each Rs. 88.65 Say 88.65

Page 124
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.

(a) Double pole:

(i) Main Switch 15/20 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main switch 15/20 Amp. 500 volts 1.00 No. 120.00 each 120.00
2 G.I Flexible pipe 1" dia (25 mm) 0.50 metre 22.60 per mtr. 11.30
3 Angle iron board including paints (9"x9"x1½") 1.00 No. 80.00 each 80.00
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
5 Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
6 Socket 1" dia (25 mm) 3.00 Nos. 7.00 each 21.00
7 Check nut 1" dia (25 mm) 1.00 No. 12.00 each 12.00
8 Thimble 8.00 Nos. 6.00 each 48.00
9 Cement 0.032 Cft. 230.00 P. Bag 7.36
10 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 375.94
Contractor's Profit & Overh 20 Percent 75.19
Total 451.13

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 145.20 Say 145.20


Composite rate for Each Rs. 596.33 Say 596.35

Page 125
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.

(a) Double pole:

(ii) Main switch 30/35 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 30/35 Amp. 500 volts 1.00 No. 350.00 each 350.00
2 G.I Flexible pipe 1" dia (25 mm) 0.50 metre 22.60 per mtr. 11.30
3 L-Iron board including paint (9"x12"x1½") 1.00 No. 100.00 each 100.00
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
5 Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
6 Socket 1" dia (25 mm) 3.00 Nos. 7.00 each 21.00
7 Check nut 1" dia (25 mm) 1.00 No. 12.00 each 12.00
8 Thimble 8.00 Nos. 6.00 each 48.00
9 Cement 0.032 Cft. 230.00 P. Bag 7.36
10 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 625.94
Contractor's Profit & Overh 20 Percent 125.19
Total 751.13

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 145.20 Say 145.20


Composite rate for Each Rs. 896.33 Say 896.35

Page 126
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.

(a) Double pole:

(iii) Main switch 60/65 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 60/65 Amp. 500 volts 1.00 No. 886.00 each 886.00
2 G.I Flexible pipe 1½" dia (38 mm) 0.50 metre 39.37 per mtr. 19.68
3 L-Iron board including paint (10"x12"x1½") 1.00 No. 150.00 each 150.00
4 Nipple 1½" dia (38 mm) 2.00 Nos. 20.00 each 40.00
5 Socket 1½" dia (38 mm) 2.00 Nos. 15.00 each 30.00
6 Check nut 1½" dia (38 mm) 2.00 Nos. 20.00 each 40.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
8 Cement 0.032 Cft. 230.00 P. Bag 7.36
9 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 1233.32
Contractor's Profit & Overh 20 Percent 246.66
Total 1479.99

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 217.80 Say 217.80


Composite rate for Each Rs. 1697.79 Say 1697.80

Page 127
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.

(a) Double pole:

(iv) Main switch 100 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 100 Amp. 500 volts 1.00 No. 1300.00 each 1300.00
2 G.I Flexible pipe 1½" dia (38 mm) 0.50 metre 39.37 per mtr. 19.68
3 L-Iron board including paint (10"x12"x1½") 1.00 No. 150.00 each 150.00
4 Nipple 1½" dia (38 mm) 2.00 Nos. 20.00 each 40.00
5 Socket 1½" dia (38 mm) 2.00 Nos. 15.00 each 30.00
6 Check nut 1½" dia (38 mm) 2.00 Nos. 20.00 each 40.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
8 Cement 0.032 Cft. 230.00 P. Bag 7.36
9 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 1647.32
Contractor's Profit & Overh 20 Percent 329.46
Total 1976.79

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 217.80 Say 217.80


Composite rate for Each Rs. 2194.59 Say 2194.60

Page 128
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.

(b) Triple pole:

(i) Main switch 15/20 Amp (500 Volts).

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 15/20 Amp. 500 volts 1.00 No. 400.00 each 400.00
2 G.I Flexible pipe 1" dia (25 mm) 0.50 metre 22.60 per mtr. 11.30
3 L-Iron board including paint (9"x12"x1½") 1.00 No. 100.00 each 100.00
4 Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
5 Socket 1" dia (25 mm) 2.00 Nos. 7.00 each 14.00
6 Check nut 1" dia (25 mm) 2.00 Nos. 12.00 each 24.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
8 Cement 0.032 Cft. 230.00 P. Bag 7.36
9 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 632.94
Contractor's Profit & Overh 20 Percent 126.59
Total 759.53

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 217.80 Say 217.80


Composite rate for Each Rs. 977.33 Say 977.35

Page 129
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.

(b) Triple pole:

(ii) Main switch 30/35 Amp (500 Volts).

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 30/35 Amp. 500 volts 1.00 No. 650.00 each 650.00
2 L-Iron board including paint (10"x12"x1½") 1.00 No. 150.00 each 150.00
3 G.I Flexible pipe 1" dia (25 mm) 0.50 metre 22.60 per mtr. 11.30
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
5 Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
6 Socket 1" dia (25 mm) 2.00 Nos. 7.00 each 14.00
7 Check nut 1" dia (25 mm) 2.00 Nos. 12.00 each 24.00
8 Thimble 8.00 Nos. 6.00 each 48.00
9 Cement 0.032 Cft. 230.00 P. Bag 7.36
10 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 980.94
Contractor's Profit & Overh 20 Percent 196.19
Total 1177.13

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 145.20 Say 145.20


Composite rate for Each Rs. 1322.33 Say 1322.35

Page 130
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.

(c) Triple pole, with neutral link:

(i) Main switch 30/35 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 30/35 Amp. 500 volts 1.00 No. 713.00 each 713.00
2 L-Iron board including paint (10"x12"x1½") 1.00 No. 150.00 each 150.00
3 G.I Flexible pipe 1" dia (25 mm) 0.50 metre 22.60 per mtr. 11.30
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
5 Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00
6 Socket 1" dia (25 mm) 2.00 Nos. 7.00 each 14.00
7 Check nut 1" dia (25 mm) 2.00 Nos. 12.00 each 24.00
8 Thimble 8.00 Nos. 6.00 each 48.00
9 Cement 0.032 Cft. 230.00 P. Bag 7.36
10 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

Total 1043.94
Contractor's Profit & Overh 20 Percent 208.79
Total 1252.73

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 145.20 Say 145.20


Composite rate for Each Rs. 1397.93 Say 1397.95

Page 131
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.

(c) Triple pole, with neutral link:

(ii) Main switch 60/65 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 60/65 Amp. 500 volts 1.00 No. 1070.00 each 1070.00
2 L-Iron board including paint (12"x15"x1½") 1.00 No. 170.00 each 170.00
3 G.I Flexible pipe 1¼" dia (32 mm) 0.50 metre 29.52 per mtr. 14.76
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 1500.00 % No. 60.00
5 Nipple 1½" dia (40 mm) 2.00 Nos. 20.00 each 40.00
6 Socket 1¼" dia (32 mm) 2.00 Nos. 12.00 each 24.00
7 Check nut 1¼" dia (32 mm) 2.00 Nos. 16.00 each 32.00
8 Cement 0.052 Cft. 230.00 P. Bag 11.96
9 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 1423.35
Contractor's Profit & Overh 20 Percent 284.67
Total 1708.02

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 217.80 Say 217.80


Composite rate for Each Rs. 1925.83 Say 1925.85

Page 132
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches with kit
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet covering, inclu
bonding to earth with necessary flexible pipe and thimbles, etc.

(c) Triple pole, with neutral link:

(iii) Main switch 100 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 100 Amp. 500 volts 1.00 No. 1840.00 each 1840.00
2 L-Iron board including paint (12"x18"x1½") 1.00 No. 200.00 each 200.00
3 G.I Flexible pipe 1½" dia (40 mm) 0.50 metre 39.37 per mtr. 19.68
4 Brass Nipple 1½" dia (40 mm) 2.00 Nos. 40.00 each 80.00
5 Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
8 Cement 0.052 Cft. 230.00 P. Bag 11.96
9 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 2242.27
Contractor's Profit & Overh 20 Percent 448.45
Total 2690.73

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.62 No. 160.00 per day 259.20

Total 429.20
Sundries 10 Percent 42.92
Total 472.12
Contractor's Profit & Overh 20 Percent 94.42
Total 566.54

ITEM RATES

Labour rate for Each Rs. 283.27 Say 283.25


Composite rate for Each Rs. 2974.01 Say 2974.00

Page 133
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.

(i) 60/65 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch with triple pole and 1.00 No. 1100.00 each 1100.00
2 Flexible pipe 1½" (40 mm) 0.50 metre 39.37 per mtr. 19.68
3 L-Iron board including paint (10"x15"x1½") 1.00 No. 190.00 each 190.00
4 Brass Nipple 1½" dia (40 mm) 2.00 Nos. 40.00 each 80.00
5 Brass check nut 1½" (40 mm) 2.00 Nos. 20.00 each 40.00
6 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
7 Brass Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
8 Thimble 60/65 Amp 4.00 Nos. 6.00 each 24.00

Total 1543.68
Contractor's Profit & Overh 20 Percent 308.74
Total 1852.43

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 217.80 Say 217.80


Composite rate for Each Rs. 2070.23 Say 2070.25

Page 134
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.

(ii) 100 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 100 Amp. 500 volts 1.00 No. 1920.00 each 1920.00
2 Flexible pipe 1½" (40 mm) 0.50 metre 39.37 per mtr. 19.69
3 L-Iron board including paint (12"x18"x1½") 1.00 No. 200.00 each 200.00
4 Brass Nipple 1¼" dia (32 mm) 2.00 Nos. 30.00 each 60.00
5 Brass check nut 1¼" (32 mm) 2.00 Nos. 16.00 each 32.00
6 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
7 Brass Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
8 Thimble 100 Amp. 4.00 Nos. 10.00 each 40.00

Total 2361.69
Contractor's Profit & Overh 20 Percent 472.34
Total 2834.03

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.62 No. 160.00 per day 259.20

Total 429.20
Sundries 10 Percent 42.92
Total 472.12
Contractor's Profit & Overh 20 Percent 94.42
Total 566.54

ITEM RATES

Labour rate for Each Rs. 283.27 Say 283.25


Composite rate for Each Rs. 3117.31 Say 3117.30

Page 135
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.

(iii) 150 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 150 Amp. 500 volts 1.00 No. 2200.00 each 2200.00
2 L-Iron board including paint (15"x18"x1½") 1.00 No. 230.00 each 230.00
3 Flexible pipe 1½" (40 mm) 0.50 metre 39.37 per mtr. 19.68
4 Brass Nipple 1¼" dia (32 mm) 2.00 Nos. 30.00 each 60.00
5 Brass Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
6 Thimble 150 Amp. 4.00 Nos. 19.00 each 76.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00

Total 2675.68
Contractor's Profit & Overh 20 Percent 535.14
Total 3210.82

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.62 No. 160.00 per day 259.20

Total 429.20
Sundries 10 Percent 42.92
Total 472.12
Contractor's Profit & Overh 20 Percent 94.42
Total 566.54

ITEM RATES

Labour rate for Each Rs. 283.27 Say 283.25


Composite rate for Each Rs. 3494.09 Say 3494.10

Page 136
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.

(iv) 200 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 200 Amp. 500 volts 1.00 No. 4000.00 each 4000.00
2 L-Iron board including paint (15"x18"x1½") 1.00 No. 230.00 each 230.00
3 Flexible pipe 1½" (40 mm) 0.50 metre 39.37 per mtr. 19.68
4 Brass Nipple 1¼" dia (32 mm) 2.00 Nos. 30.00 each 60.00
5 Brass Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
6 Brass check nut 1¼" (32 mm) 2.00 Nos. 16.00 each 32.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
8 Copper Thimble 200 Amp. 4.00 Nos. 28.00 each 112.00

Total 4543.68
Contractor's Profit & Overh 20 Percent 908.74
Total 5452.42

LABOUR (For 1 No.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate for Each Rs. 646.80 Say 646.80


Composite rate for Each Rs. 6099.22 Say 6099.20

Page 137
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.

(v) 300 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 300 Amp. 500 volts 1.00 No. 5566.00 each 5566.00
2 Flexible pipe 1½" (40 mm) 0.50 metre 39.37 per mtr. 19.68
3 L-Iron board including paint (15"x18"x1½") 1.00 No. 230.00 each 230.00
4 Brass Nipple 1¼" dia (32 mm) 2.00 Nos. 30.00 each 60.00
5 Brass Socket 1½" dia (40 mm) 2.00 Nos. 15.00 each 30.00
6 Brass check nut 1¼" (32 mm) 2.00 Nos. 16.00 each 32.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
8 Copper Thimble 300 Amp. 4.00 Nos. 55.00 each 220.00

Total 6217.68
Contractor's Profit & Overh 20 Percent 1243.54
Total 7461.22

LABOUR (For 1 No.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate for Each Rs. 646.80 Say 646.80


Composite rate for Each Rs. 8108.02 Say 8108.00

Page 138
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.

(vi) 400 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 400 Amp. 500 volts 1.00 No. 7550.00 each 7550.00
2 L-Iron board including paint (15"x18"x1½") 1.00 No. 230.00 each 230.00
3 Flexible pipe 2" (50 mm) 0.50 metre 55.77 per mtr. 27.89
4 Brass Nipple 2 dia (50 mm) 2.00 Nos. 80.00 each 160.00
5 Brass Socket 2" dia (50 mm) 2.00 Nos. 21.00 each 42.00
6 Brass check nut 2" (50 mm) 2.00 Nos. 25.00 each 50.00
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
8 Copper Thimble 400 Amp. 4.00 Nos. 75.00 each 300.00

Total 8419.89
Contractor's Profit & Overh 20 Percent 1683.98
Total 10103.86

LABOUR (For 1 No.)

1 Electrician 1.25 No. 170.00 per day 212.50


2 Coolies skilled 3.00 Nos. 160.00 per day 480.00

Total 692.50
Sundries 10 Percent 69.25
Total 761.75
Contractor's Profit & Overh 20 Percent 152.35
Total 914.10

ITEM RATES

Labour rate for Each Rs. 914.10 Say 914.10


Composite rate for Each Rs. 11017.96 Say 11017.95

Page 139
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switches with tr
pole and neutral link and HRC fuses, on angle iron board with 3 mm (1/8")
thick M.S sheet covering, including bonding to earth with necessary flexible
pipe and thimbles.

(vii) 500 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 500 Amp. 500 volts 1.00 No. 10268.00 each 10268.00
2 L-Iron board including paint (15"x18"x1½") 1.00 No. 230.00 each 230.00
3 Flexible pipe 4" (100 mm) 0.50 metre 175.00 per mtr. 87.50
4 Brass Nipple 4" dia (100 mm) 2.00 Nos. 200.00 each 400.00
5 Brass Socket 4" dia (100 mm) 2.00 Nos. 75.00 each 150.00
6 Brass check nut 4" (100 mm) 2.00 Nos. 55.00 each 110.00
7 Reg bolts 12" x 5/8" (300 x 16 mm) 4.00 Nos. 20.00 each 80.00
8 Copper Thimble 500 Amp. 4.00 Nos. 100.00 each 400.00
8 Cement 0.203 Cft. 230.00 P. Bag 46.69
9 Sand 0.99 Cft. 350.00 Per % Cft. 3.47

Total 11775.66
Contractor's Profit & Overh 20 Percent 2355.13
Total 14130.79

LABOUR (For 1 No.)

1 Electrician 1.50 Nos. 170.00 per day 255.00


2 Coolies skilled 3.00 Nos. 160.00 per day 480.00

Total 735.00
Sundries 10 Percent 73.50
Total 808.50
Contractor's Profit & Overh 20 Percent 161.70
Total 970.20

ITEM RATES

Labour rate for Each Rs. 970.20 Say 970.20


Composite rate for Each Rs. 15100.99 Say 15101.00

Page 140
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(i) 2 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/aluminium clad 2 way15 Amp. per way 1.00 No. 108.00 each 108.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 229.20
Contractor's Profit & Overh 20 Percent 45.84
Total 275.04

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 347.64 Say 347.65

Page 141
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(ii) 3 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/aluminium clad 3 way15 Amp. per way 1.00 No. 118.00 each 118.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 239.20
Contractor's Profit & Overh 20 Percent 47.84
Total 287.04

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 359.64 Say 359.65

Page 142
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(iii) 4 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 4 way15 Amp. per way 1.00 No. 163.00 each 163.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 284.20
Contractor's Profit & Overh 20 Percent 56.84
Total 341.04

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 413.64 Say 413.65

Page 143
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(iv) 5 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 5 way15 Amp. per way 1.00 No. 213.00 each 213.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 334.20
Contractor's Profit & Overh 20 Percent 66.84
Total 401.04

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 473.64 Say 473.65

Page 144
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(v) 6 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 6 way15 Amp. per way 1.00 No. 248.00 each 248.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 369.20
Contractor's Profit & Overh 20 Percent 73.84
Total 443.04

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 515.64 Say 515.65

Page 145
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(vi) 7 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 7 way15 Amp. per way 1.00 No. 295.00 each 295.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 416.20
Contractor's Profit & Overh 20 Percent 83.24
Total 499.44

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 572.04 Say 572.05

Page 146
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(vii) 8 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 8 way15 Amp. per way 1.00 No. 338.00 each 338.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 459.20
Contractor's Profit & Overh 20 Percent 91.84
Total 551.04

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 623.64 Say 623.65

Page 147
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(viii) 9 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 9 way15 Amp. per way 1.00 No. 378.00 each 378.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 499.20
Contractor's Profit & Overh 20 Percent 99.84
Total 599.04

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 671.64 Say 671.65

Page 148
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(ix) 10 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 10 way15 Amp. per way 1.00 No. 438.00 each 438.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 559.20
Contractor's Profit & Overh 20 Percent 111.84
Total 671.04

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 743.64 Say 743.65

Page 149
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(x) 11 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 11 way15 Amp. per way 1.00 No. 478.00 each 478.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 599.20
Contractor's Profit & Overh 20 Percent 119.84
Total 719.04

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 791.64 Say 791.65

Page 150
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(xi) 12 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 12 way15 Amp. per way 1.00 No. 508.00 each 508.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 629.20
Contractor's Profit & Overh 20 Percent 125.84
Total 755.04

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 72.60 Say 72.60


Composite rate for Each Rs. 827.64 Say 827.65

Page 151
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(xii) 2 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 2 way 30 Amp. per way 1.00 No. 120.00 each 120.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 241.20
Contractor's Profit & Overh 20 Percent 48.24
Total 289.44

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 108.90 Say 108.90


Composite rate for Each Rs. 398.34 Say 398.35

Page 152
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(xiii) 3 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 3 way 30 Amp. per way 1.00 No. 130.00 each 130.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 251.20
Contractor's Profit & Overh 20 Percent 50.24
Total 301.44

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 108.90 Say 108.90


Composite rate for Each Rs. 410.34 Say 410.35

Page 153
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(xiv) 4 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 4 way 30 Amp. per way 1.00 No. 175.00 each 175.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 296.20
Contractor's Profit & Overh 20 Percent 59.24
Total 355.44

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 108.90 Say 108.90


Composite rate for Each Rs. 464.34 Say 464.35

Page 154
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(xv) 5 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 5 way 30 Amp. per way 1.00 No. 225.00 each 225.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 346.20
Contractor's Profit & Overh 20 Percent 69.24
Total 415.44

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 108.90 Say 108.90


Composite rate for Each Rs. 524.34 Say 524.35

Page 155
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(xvi) 6 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 6 way 30 Amp. per way 1.00 No. 260.00 each 260.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 381.20
Contractor's Profit & Overh 20 Percent 76.24
Total 457.44

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 108.90 Say 108.90


Composite rate for Each Rs. 566.34 Say 566.35

Page 156
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(xvii) 7 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 7 way 30 Amp. per way 1.00 No. 310.00 each 310.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 431.20
Contractor's Profit & Overh 20 Percent 86.24
Total 517.44

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 108.90 Say 108.90


Composite rate for Each Rs. 626.34 Say 626.35

Page 157
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(xviii) 8 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 8 way 30 Amp. per way 1.00 No. 350.00 each 350.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 471.20
Contractor's Profit & Overh 20 Percent 94.24
Total 565.44

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 108.90 Say 108.90


Composite rate for Each Rs. 674.34 Say 674.35

Page 158
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(xix) 9 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 9 way 30 Amp. per way 1.00 No. 390.00 each 390.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 511.20
Contractor's Profit & Overh 20 Percent 102.24
Total 613.44

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 108.90 Say 108.90


Composite rate for Each Rs. 722.34 Say 722.35

Page 159
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution board, 250
on angle iron frame of suitable size with 3 mm (1/8") M.S sheet covering:

(xx) 10 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 10 way 30 Amp. per way 1.00 No. 450.00 each 450.00
2 L-Iron board (9"x 9"x1½") (225 x 225 x 40 mm) 1.00 No. 80.00 each 80.00
3 PVC Flexible pipe ½" dia (12 mm) 0.50 metre 16.40 per mtr. 8.20
4 PVC Socket ½" dia (12 mm) 4.00 Nos. 0.70 each 2.80
5 PVC Nipple ½" dia (12 mm) 4.00 Nos. 5.00 each 20.00
6 PVC Check nut ½" dia (12 mm) 2.00 Nos. 3.50 each 7.00
7 PVC bushes ½" dia (12 mm) 8.00 Nos. 0.40 each 3.20

Total 571.20
Contractor's Profit & Overh 20 Percent 114.24
Total 685.44

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Coolies skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 108.90 Say 108.90


Composite rate for Each Rs. 794.34 Say 794.35

Page 160
DESCRIPTION OF ITEM:

Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply with four
copper bars, including glazed porcelain bridges, on angle iron board, fixed
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:

(i) 60 Amp. with 4 copper bars size 1½" x 1/8" (40 x 3 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Porcelain (Imported) 8.00 Nos. 100.00 each 800.00


2 Copper strip 1½" x 1/8" x 14" (40 x 3 x 350 mm) 4.00 Nos. 140.00 each 560.00
3 Box 1.5 mm thick 1.00 No. 69.00 each 69.00
4 L-Iron board 18" x 12" x 1½" (450 x 300 x 40 mm) 1.00 No. 200.00 each 200.00
5 Reg bolts 9 x 5/8 (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
6 Cement 0.063 Cft. 230.00 P. Bag 14.49
7 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 1704.12
Contractor's Profit & Overh 20 Percent 340.82
Total 2044.94

LABOUR (For 2 Nos.)

1 Electrician 1.50 Nos. 170.00 per day 255.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 395.00
Sundries 10 Percent 39.50
Total 434.50
Contractor's Profit & Overh 20 Percent 86.90
Total 521.40

ITEM RATES

Labour rate for Each Rs. 260.70 Say 260.70


Composite rate for Each Rs. 2305.64 Say 2305.65

Page 161
DESCRIPTION OF ITEM:

Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply with four
copper bars, including glazed porcelain bridges, on angle iron board, fixed
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:

(ii) 100 Amp. with 4 copper bars size 1½" x 1/8" (40 x 3 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Porcelain (Imported) 8.00 Nos. 100.00 each 800.00


2 Copper strip 14" x 1½" x 1/8" (350 x 40 x 3 mm) 4.00 Nos. 140.00 each 560.00
3 Box 1.5 mm thick 1.00 No. 69.00 each 69.00
4 L-Iron board 18" x 12" x 1½" (450 x 300 x 40 mm) 1.00 No. 200.00 each 200.00
5 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
6 Cement 0.063 Cft. 230.00 P. Bag 14.49
7 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 1704.12
Contractor's Profit & Overh 20 Percent 340.82
Total 2044.94

LABOUR (For 2 Nos.)

1 Electrician 1.50 No. 170.00 per day 255.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 395.00
Sundries 10 Percent 39.50
Total 434.50
Contractor's Profit & Overh 20 Percent 86.90
Total 521.40

ITEM RATES

Labour rate for Each Rs. 260.70 Say 260.70


Composite rate for Each Rs. 2305.64 Say 2305.65

Page 162
DESCRIPTION OF ITEM:

Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply with four
copper bars, including glazed porcelain bridges, on angle iron board, fixed
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:

(iii) 200 Amp. with 4 copper bars size 2" x 1/8" (50 x 3 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Porcelain (Imported) 8.00 Nos. 100.00 each 800.00


2 Copper strip 14" x 2" x 1/8" (350 x 50 x 3 mm) 4.00 Nos. 200.00 each 800.00
3 Box 1/16 (2 mm) thick 1.00 No. 69.00 each 69.00
4 L-Iron board 18" x 12" x 1½" (450 x 300 x 40 mm) 1.00 No. 200.00 each 200.00
5 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
6 Cement 0.063 Cft. 230.00 P. Bag 14.49
7 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 1944.12
Contractor's Profit & Overh 20 Percent 388.82
Total 2332.94

LABOUR (For 2 Nos.)

1 Electrician 2.00 Nos. 170.00 per day 340.00


2 Coolies (helper) 2.00 Nos. 140.00 per day 280.00

Total 620.00
Sundries 10 Percent 62.00
Total 682.00
Contractor's Profit & Overh 20 Percent 136.40
Total 818.40

ITEM RATES

Labour rate for Each Rs. 409.20 Say 409.20


Composite rate for Each Rs. 2742.14 Say 2742.15

Page 163
DESCRIPTION OF ITEM:

Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply with four
copper bars, including glazed porcelain bridges, on angle iron board, fixed
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:

(iv) 300 Amp. with 4 copper bars size 2" x 3/16" (50 x 4 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Porcelain (Imported) 8.00 Nos. 100.00 each 800.00


2 Copper strip 2" x 3/16" x 14" (50 x 4 x 350 mm) 4.00 Nos. 200.00 each 800.00
3 Box 1/16" (2 mm) thick 1.00 No. 69.00 each 69.00
4 L-Iron board 18" x 12" x 1½" (450 x 300 x 40 mm) 1.00 No. 200.00 each 200.00
5 Reg bolts 2 "x 5/8" (50 x 16 mm) 4.00 Nos. 15.00 each 60.00
6 Cement 0.063 Cft. 230.00 P. Bag 14.49
7 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 1944.12
Contractor's Profit & Overh 20 Percent 388.82
Total 2332.94

LABOUR (For 2 Nos.)

1 Electrician 2.50 Nos. 170.00 per day 425.00


2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

Total 745.00
Sundries 10 Percent 74.50
Total 819.50
Contractor's Profit & Overh 20 Percent 163.90
Total 983.40

ITEM RATES

Labour rate for Each Rs. 491.70 Say 491.70


Composite rate for Each Rs. 2824.64 Say 2824.65

Page 164
DESCRIPTION OF ITEM:

Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply with four
copper bars, including glazed porcelain bridges, on angle iron board, fixed
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:

(v) 500 Amp. with 4 copper bars size 2" x ¼" (50 x 6 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Porcelain (Imported) 8.00 Nos. 100.00 each 800.00


2 Copper strip 14" x 2" x ¼" (350 x 50 x 6 mm) 4.00 Nos. 600.00 each 2400.00
3 Box 1/16" (2 mm) thick 1.00 No. 69.00 each 69.00
4 L-Iron board 18" x 12" x 1½" (450 x 300 x 40 mm) 1.00 No. 200.00 each 200.00
5 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. 15.00 each 60.00
6 Cement 0.084 Cft. 230.00 P. Bag 19.32
7 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

Total 3549.16
Contractor's Profit & Overh 20 Percent 709.83
Total 4258.99

LABOUR (For 2 Nos.)

1 Electrician 2.00 Nos. 170.00 per day 340.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 480.00
Sundries 10 Percent 48.00
Total 528.00
Contractor's Profit & Overh 20 Percent 105.60
Total 633.60

ITEM RATES

Labour rate for Each Rs. 316.80 Say 316.80


Composite rate for Each Rs. 4575.79 Say 4575.80

Page 165
DESCRIPTION OF ITEM:

Item No. 22 (i) Supply and erection of plain pendent lamp holder, complete, with bakelite l
holder and flexible twin wire 23/0.0076" upto 2 metre length (without bulb
shade).

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Pendent lamp holder bakelite 1.00 No. 12.00 each 12.00


2 Flexible twin wire 23/0.0076 (23/0.195 mm) 2.00 metre 4.96 per mtr. 9.92

Total 21.92
Contractor's Profit & Overh 20 Percent 4.38
Total 26.30

LABOUR (For 24 Nos.)

1 Electrician 0.50 No. 170.00 per day 85.00

Total 85.00
Sundries 10 Percent 8.50
Total 93.50
Contractor's Profit & Overh 20 Percent 18.70
Total 112.20

ITEM RATES

Labour rate for Each Rs. 4.68 Say 4.70


Composite rate for Each Rs. 30.98 Say 31.00

Page 166
DESCRIPTION OF ITEM:

Item No. 22 (ii) Extra for additional length of flexible wire, beyond 2 metres.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

2 Flexible twin wire 23/0.0076 (23/0.195 mm) 1.00 metre 4.96 per mtr. 4.96

Total 4.96
Contractor's Profit & Overh 20 Percent 0.99
Total 5.95

ITEM RATE

Composite rate per Metre Rs. 5.46 Say 5.45


Composite rate per ft. Rs. 1.66 Say 1.65

Page 167
DESCRIPTION OF ITEM:

Item No. 23 Supply and erection of counter weight pendent with porcelain counter weig
and fitting on bakelite lamp holder, with flexible twin wire 23/0.0076" comp
(without bulb & shade).

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Flexible twin wire 23/0.0076 (23/0.195 mm) 3.00 metre 4.96 per mtr. 14.88
2 Bakelite lamp holder 1.00 No. 12.00 each 12.00
3 Counter weight with accessories 1.00 No. 60.00 each 60.00

Total 86.88
Contractor's Profit & Overh 20 Percent 17.38
Total 104.26

LABOUR (For 12 Nos.)

1 Electrician 0.50 No. 170.00 per day 85.00

Total 85.00
Sundries 10 Percent 8.50
Total 93.50
Contractor's Profit & Overh 20 Percent 18.70
Total 112.20

ITEM RATES

Labour rate for Each Rs. 9.35 Say 9.35


Composite rate for Each Rs. 113.61 Say 113.60

Page 168
DESCRIPTION OF ITEM:

Item No. 24 Supply and erection of stiff pendent with brass/metal pipe 6.3 cm (2.5") lon
15 mm (½") dia brass oxidised or painted along lamp holder with VIR/PVC c
3/0.74 mm (3/0.029").

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass pipe ½" dia (12 mm) 2.00 metre 52.00 per mtr. 104.00
2 Canopy nipple & hook 1.00 job 20.00 per job 20.00
3 Brass lamp holder 1.00 No. 20.00 each 20.00
4 VIR/PVC cable 3/0.29 2.00 metre 6.00 per mtr. 12.00

Total 156.00
Contractor's Profit & Overh 20 Percent 31.20
Total 187.20

LABOUR (For 30 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 13.64 Say 13.65


Composite rate for Each Rs. 200.84 Say 200.85

Page 169
DESCRIPTION OF ITEM:

Item No. 25 Supply and erection of 22.5 cm (9") long swan neck plain brass/steel brass
oxidised bracket lamp holder, complete.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass bracket 1.00 No. 24.00 each 24.00


2 Brass lamp holder 1.00 No. 12.00 each 12.00
3 VIR/PVC Cable 3/0.029 0.50 metre 6.00 per mtr. 3.00

Total 39.00
Contractor's Profit & Overh 20 Percent 7.80
Total 46.80

LABOUR (For 29 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 14.11 Say 14.10


Composite rate for Each Rs. 60.91 Say 60.90

Page 170
DESCRIPTION OF ITEM:

Item No. 26 Supply and erection of wall type/pole type bracket, with double cover water
tight reflector, flexible wire and brass holder.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Pipe ¾" dia (20 mm) 1.00 metre 68.07 per mtr. 68.07
2 Brass nipple 1.00 No. 18.00 each 18.00
3 Brass lamp holder 1.00 No. 16.00 each 16.00
4 Double cone reflector 1.00 No. 55.00 each 55.00
5 Flexible wire 1.00 metre 4.00 per mtr. 4.00

Total 161.07
Contractor's Profit & Overh 20 Percent 32.21
Total 193.28

LABOUR (For 21 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 19.49 Say 19.50


Composite rate for Each Rs. 212.77 Say 212.75

Page 171
DESCRIPTION OF ITEM:

Item No. 27 Supply and erection of bakelite button holder shade, large size.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Button Switch holder 1.00 No. 13.00 each 13.00


2 Bakelite screwed cover 1.84 Dozen 3.25 P. Doz 5.98

Total 18.98
Contractor's Profit & Overh 20 Percent 3.80
Total 22.78

LABOUR (For 100 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 3.17 Say 3.15


Composite rate for Each Rs. 25.94 Say 25.95

Page 172
DESCRIPTION OF ITEM:

Item No. 28 Supply and erection of call bell 220/250 volts, fixed on teak wood board
17.5 x 10 cm (7" x 4").

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Call bell 1.00 No. 60.00 each 60.00


2 Board 7" x 4" (175 x 100 mm) 1.00 No. 20.00 each 20.00
3 Screw 1.85 Dozen 3.25 P. Doz 6.01

Total 86.01
Contractor's Profit & Overh 20 Percent 17.20
Total 103.22

LABOUR (For 30 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 13.64 Say 13.65


Composite rate for Each Rs. 116.86 Say 116.85

Page 173
DESCRIPTION OF ITEM:

Item No. 29 Supply and erection of bell push or bed switch, with 5 metre twin flexible
wire 23/0.0076"

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Bed switch/bell push 1.00 No. 8.00 each 8.00


2 Flexible wire 23/0.0076" (23/0.195 mm) 5.00 metre 4.96 per mtr. 24.80

Total 32.80
Contractor's Profit & Overh 20 Percent 6.56
Total 39.36

LABOUR (For 80 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 2.81 Say 2.80


Composite rate for Each Rs. 42.17 Say 42.15

Page 174
DESCRIPTION OF ITEM:

Item No. 30 Supply and erection of celling rose, bakelite.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Ceiling rose 1.00 No. 13.00 each 13.00


2 Iron screw 1.50 Nos. 3.25 P. Doz. 0.41

Total 13.41
Contractor's Profit & Overh 20 Percent 2.68
Total 16.09

LABOUR (For 48 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.68 Say 4.70


Composite rate for Each Rs. 20.76 Say 20.75

Page 175
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(i) Open type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch 5 Amp 1.00 No. 11.00 each 11.00


2 Screw 1.50 Nos. 3.25 P. Doz. 0.41

Total 11.41
Contractor's Profit & Overh 20 Percent 2.28
Total 13.69

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 18.18 Say 18.20

Page 176
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(ii) Piano type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch 5 Amp piano type 1.00 No. 10.00 each 10.00


2 Screw 1.50 Nos. 3.25 P. Doz. 0.41

Total 10.41
Contractor's Profit & Overh 20 Percent 2.08
Total 12.49

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 16.98 Say 17.00

Page 177
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(iii) Switch ring type, recessed.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch ring type 1.00 No. 6.00 each 6.00

Total 6.00
Contractor's Profit & Overh 20 Percent 1.20
Total 7.20

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 11.69 Say 11.70

Page 178
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(iv) Switch plate type recessed.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch plate type 1.00 No. 9.00 each 9.00


2 Screw 1.50 Nos. 3.25 P. Doz. 0.41

Total 9.41
Contractor's Profit & Overh 20 Percent 1.88
Total 11.29

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 15.78 Say 15.80

Page 179
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(v) Double control, open type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Double control switch 1.00 No. 11.00 each 11.00


2 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 11.54
Contractor's Profit & Overh 20 Percent 2.31
Total 13.85

LABOUR (For 44 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60

ITEM RATES

Labour rate for Each Rs. 6.15 Say 6.15


Composite rate for Each Rs. 20.00 Say 20.00

Page 180
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(vi) Double control, ring type recessed.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Double control switch recessed type 1.00 No. 10.00 each 10.00
2 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 10.54
Contractor's Profit & Overh 20 Percent 2.11
Total 12.65

LABOUR (For 44 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60

ITEM RATES

Labour rate for Each Rs. 6.15 Say 6.15


Composite rate for Each Rs. 18.80 Say 18.80

Page 181
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(vii) Double control, piano type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Double control piano type 1.00 No. 9.00 each 9.00


2 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 9.54
Contractor's Profit & Overh 20 Percent 1.91
Total 11.45

LABOUR (For 44 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60

ITEM RATES

Labour rate for Each Rs. 6.15 Say 6.15


Composite rate for Each Rs. 17.45 Say 17.45

Page 182
DESCRIPTION OF ITEM:

Item No. 32 Supply and erection of switches 10/15 Amp.

(i) Open type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch 10/15 Amp 1.00 No. 11.00 each 11.00


2 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 11.54
Contractor's Profit & Overh 20 Percent 2.31
Total 13.85

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 18.34 Say 18.35

Page 183
DESCRIPTION OF ITEM:

Item No. 32 Supply and erection of switches 10/15 Amp.

(ii) Recessed type switch 10/15 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch 10/15 Amp. recessed 1.00 No. 13.00 each 13.00


2 Mechine Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 13.54
Contractor's Profit & Overh 20 Percent 2.71
Total 16.25

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 20.74 Say 20.75

Page 184
DESCRIPTION OF ITEM:

Item No. 33 Supply and erection of wall socket with 3 pin 5 Amp. shoe.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 3 pin 5 Amp wall socket 1.00 No. 12.00 each 12.00


2 Shoe 1.00 No. 8.00 each 8.00
3 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 20.54
Contractor's Profit & Overh 20 Percent 4.11
Total 24.65

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 29.14 Say 29.15

Page 185
DESCRIPTION OF ITEM:

Item No. 34 Supply and erection of 3 pin 5 Amp. wall socket.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Wall socket 3 pin 5 Amp. 1.00 No. 8.00 each 8.00


2 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 8.54
Contractor's Profit & Overh 20 Percent 1.71
Total 10.25

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 14.74 Say 14.75

Page 186
DESCRIPTION OF ITEM:

Item No. 35 Supply and erection of 3 pin 10/15 Amp. wall socket.

(i) Open type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Wall socket 10/15 Amp. 1.00 No. 11.00 each 11.00


2 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 11.54
Contractor's Profit & Overh 20 Percent 2.31
Total 13.85

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 18.34 Say 18.35

Page 187
DESCRIPTION OF ITEM:

Item No. 35 Supply and erection of 3 pin 10/15 Amp. wall socket.

(ii) Wall socket 10/15 Amp. recessed.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Wall socket 10/15 Amp. recessed 1.00 No. 13.00 each 13.00
2 Machine Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 13.54
Contractor's Profit & Overh 20 Percent 2.71
Total 16.25

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 20.74 Say 20.75

Page 188
DESCRIPTION OF ITEM:

Item No. 36 Supply and erection of 3 pin switch and plug combined, recessed type:

(i) 5 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plugs 3 pin and switch (combine) 5 Amp. 1.00 No. 36.00 each 36.00
2 Machine Screw 4.00 Nos. 3.25 P. Doz. 1.08

Total 37.08
Contractor's Profit & Overh 20 Percent 7.42
Total 44.50

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 48.99 Say 49.00

Page 189
DESCRIPTION OF ITEM:

Item No. 36 Supply and erection of 3 pin switch and plug combined, recessed type:

(ii) 10/15 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plugs 3 pin and switch (combine) 10/15 Amp. 1.00 No. 48.00 each 48.00
2 Machine Screw 5.00 Nos. 3.25 P. Doz. 1.35

Total 49.35
Contractor's Profit & Overh 20 Percent 9.87
Total 59.23

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 63.71 Say 63.70

Page 190
DESCRIPTION OF ITEM:

Item No. 37 Supply and erection of 3 pin 10/15 Amp. wall socket with shoe open type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Wall socket 3 pin 10/15 Amp. 1.00 No. 25.00 each 25.00
2 Shoe 3 pin 1.00 No. 10.00 each 10.00
3 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 35.54
Contractor's Profit & Overh 20 Percent 7.11
Total 42.65

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 4.49 Say 4.50


Composite rate for Each Rs. 47.14 Say 47.15

Page 191
DESCRIPTION OF ITEM:

Item No. 38 Supply and erection of cut out, bakelite:

(i) Open type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cut out bakelite 1.00 No. 13.00 each 13.00


2 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 13.54
Contractor's Profit & Overh 20 Percent 2.71
Total 16.25

LABOUR (For 90 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 2.49 Say 2.50


Composite rate for Each Rs. 18.74 Say 18.75

Page 192
DESCRIPTION OF ITEM:

Item No. 38 Supply and erection of cut out, bakelite:

(ii) Recessed type cut out.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cut out 1.00 No. 15.00 each 15.00


2 Machine Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 15.54
Contractor's Profit & Overh 20 Percent 3.11
Total 18.65

LABOUR (For 90 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 2.49 Say 2.50


Composite rate for Each Rs. 21.14 Say 21.15

Page 193
DESCRIPTION OF ITEM:

Item No. 39 Supply and erection of button holder:

(i) Bakelite large size.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Button holder large 1.00 No. 9.00 each 9.00


2 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 9.54
Contractor's Profit & Overh 20 Percent 1.91
Total 11.45

LABOUR (For 80 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 2.81 Say 2.80


Composite rate for Each Rs. 13.84 Say 13.85

Page 194
DESCRIPTION OF ITEM:

Item No. 39 Supply and erection of button holder:

(ii) Button holder Brass.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Button holder 1.00 No. 12.00 each 12.00


2 Screws 2.00 Nos. 3.25 P. Doz. 0.54

Total 12.54
Contractor's Profit & Overh 20 Percent 2.51
Total 15.05

LABOUR (For 80 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 2.81 Say 2.80


Composite rate for Each Rs. 17.86 Say 17.85

Page 195
DESCRIPTION OF ITEM:

Item No. 40 Supply and erection of brass bracket with holder.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass bracket with holder 1.00 No. 17.00 each 17.00


2 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 17.54
Contractor's Profit & Overh 20 Percent 3.51
Total 21.05

LABOUR (For 60 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 3.74 Say 3.75


Composite rate for Each Rs. 24.79 Say 24.80

Page 196
DESCRIPTION OF ITEM:

Item No. 41 Supply and erection of bell push, open/recessed type (without flexible wire)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Bell push 1.00 No. 8.00 each 8.00


2 Screw 2.00 Nos. 3.25 P. Doz. 0.54

Total 8.54
Contractor's Profit & Overh 20 Percent 1.71
Total 10.25

LABOUR (For 90 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 2.49 Say 2.50


Composite rate for Each Rs. 12.74 Say 12.75

Page 197
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(i) 15/20 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 15/20 Amp. 1.00 No. 10.00 each 10.00


2 Screw 1.00 Nos. 3.25 P. Doz. 0.27

Total 10.27
Contractor's Profit & Overh 20 Percent 2.05
Total 12.33

LABOUR (For 60 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60

ITEM RATES

Labour rate for Each Rs. 4.51 Say 4.50


Composite rate for Each Rs. 16.84 Say 16.85

Page 198
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(ii) 30/35 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 30/35 Amp. 1.00 No. 17.00 each 17.00


2 Screw 1.00 Nos. 3.25 P. Doz. 0.27

Total 17.27
Contractor's Profit & Overh 20 Percent 3.45
Total 20.73

LABOUR (For 55 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60

ITEM RATES

Labour rate for Each Rs. 4.92 Say 4.90


Composite rate for Each Rs. 25.65 Say 25.65

Page 199
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(iii) 60/65 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 60/65 Amp. 1.00 No. 40.00 each 40.00


2 Screw 1.00 Nos. 3.25 P. Doz. 0.27

Total 40.27
Contractor's Profit & Overh 20 Percent 8.05
Total 48.33

LABOUR (For 36 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60

ITEM RATES

Labour rate for Each Rs. 7.52 Say 7.50


Composite rate for Each Rs. 55.84 Say 55.85

Page 200
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(iv) 100 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 100 Amp. 1.00 No. 75.00 each 75.00


2 Screw 1.00 Nos. 3.25 P. Doz. 0.27

Total 75.27
Contractor's Profit & Overh 20 Percent 15.05
Total 90.33

LABOUR (For 32 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60

ITEM RATES

Labour rate for Each Rs. 8.46 Say 8.45


Composite rate for Each Rs. 98.78 Say 98.80

Page 201
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(v) 200 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 200 Amp. 1.00 No. 150.00 each 150.00


2 Screw 1.00 Nos. 3.25 P. Doz. 0.27

Total 150.27
Contractor's Profit & Overh 20 Percent 30.05
Total 180.33

LABOUR (For 28 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60

ITEM RATES

Labour rate for Each Rs. 9.66 Say 9.65


Composite rate for Each Rs. 189.99 Say 190.00

Page 202
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(vi) 300 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 300 Amp. 1.00 No. 225.00 each 225.00


2 Screw 1.00 Nos. 3.25 P. Doz. 0.27

Total 225.27
Contractor's Profit & Overh 20 Percent 45.05
Total 270.33

LABOUR (For 28 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10 Percent 20.50
Total 225.50
Contractor's Profit & Overh 20 Percent 45.10
Total 270.60

ITEM RATES

Labour rate for Each Rs. 9.66 Say 9.65


Composite rate for Each Rs. 279.99 Say 280.00

Page 203
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(vii) 400 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 400 Amp. 1.00 No. 280.00 each 280.00


2 Screw 1.00 Nos. 3.25 P. Doz. 0.27

Total 280.27
Contractor's Profit & Overh 20 Percent 56.05
Total 336.33

LABOUR (For 25 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 12.67 Say 12.65


Composite rate for Each Rs. 349.00 Say 349.00

Page 204
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(viii) 500 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 500 Amp. 1.00 No. 310.00 each 310.00


2 Screw 2.00 No. 0.40 each 0.80

Total 310.80
Contractor's Profit & Overh 20 Percent 62.16
Total 372.96

LABOUR (For 25 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 12.67 Say 12.65


Composite rate for Each Rs. 385.63 Say 385.65

Page 205
DESCRIPTION OF ITEM:

Item No. 43 Supply and erection of tube light, including rod, choke, starter with frame,
flexible wire, including connection from ceiling rose, etc., complete:

(i) Double rod (80 watts) with two chokes and 2 starters.

Detail Unit Rate (Metric System) per Set

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Tube rod 2.00 Nos. 75.00 each 150.00


2 Chokes 2.00 Nos. 72.00 each 144.00
3 Starters 2.00 Nos. 14.00 each 28.00
4 Frame with holder 1.00 job 250.00 per job 250.00
5 Flexible wire 2.00 metre 4.00 per mtr. 8.00
Hooks, Chain L.S 20.00

Total 600.00
Contractor's Profit & Overh 20 Percent 120.00
Total 720.00

LABOUR (For 4 Sets)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for each Set Rs. 79.20 Say 79.20


Composite rate for each Set Rs. 799.20 Say 799.20

Page 206
DESCRIPTION OF ITEM:

Item No. 43 Supply and erection of tube light, including rod, choke, starter with frame,
flexible wire, including connection from ceiling rose, etc., complete:

(ii) Single rod (40 watts) with one choke and one starter.

Detail Unit Rate (Metric System) per Set

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Tube rod 1.00 No. 75.00 each 75.00


2 Choke 1.00 No. 72.00 each 72.00
3 Starter 1.00 No. 14.00 each 14.00
4 Frame set 1.00 No. 75.00 each 75.00
5 Flexible wire 2.00 metre 4.00 per mtr. 8.00
Hooks, Chain L.S 20.00

Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

LABOUR (For 5 Sets)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for each Set Rs. 63.36 Say 63.35


Composite rate for each Set Rs. 380.16 Say 380.15

Page 207
DESCRIPTION OF ITEM:

Item No. 43 Supply and erection of tube light, including rod, choke, starter with frame,
flexible wire, including connection from ceiling rose, etc., complete:

(iii) Single round tube, 32 watts, with one choke and one starter, without cover.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Round tube 32 watts 1.00 No. 100.00 each 100.00


2 Starter 1.00 No. 16.00 each 16.00
3 Choke 1.00 No. 100.00 each 100.00
4 Holder 2.00 Nos. 22.00 each 44.00
5 Base 1.00 No. 40.00 each 40.00
6 Flexeble wire 2.00 metre 4.00 per mtr. 8.00
7 Hooks 1.00 No. 4.00 each 4.00

Total 312.00
Contractor's Profit & Overh 20 Percent 62.40
Total 374.40

LABOUR (For 5 Sets)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 63.36 Say 63.35


Composite rate for Each Rs. 437.76 Say 437.75

Page 208
DESCRIPTION OF ITEM:

Item No. 43 Supply and erection of tube light, including rod, choke, starter with frame,
flexible wire, including connection from ceiling rose, etc., complete:

(iv) Round tube, 32 watts, with one choke and one starter, with cover.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Round tube 32 watts 1.00 No. 100.00 each 100.00


2 Starter 1.00 No. 16.00 each 16.00
3 Choke 1.00 No. 100.00 each 100.00
4 Holder 2.00 Nos. 22.00 each 44.00
5 Base 1.00 No. 40.00 each 40.00
6 Plastic cover 1.00 No. 160.00 each 160.00
7 Flexeble wire 2.00 metre 4.00 per mtr. 8.00
8 Hooks 1.00 No. 4.00 each 4.00

Total 472.00
Contractor's Profit & Overh 20 Percent 94.40
Total 566.40

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 52.80 Say 52.80


Composite rate for Each Rs. 619.20 Say 619.20

Page 209
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing M.S iron box for housing main switches, made of 1.5 m
(1/16") thick M.S sheet, with locking arrangement, including painting:

(i) 60 x 35 x 15 cm (24" x 14" x 6")

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
1 M.S sheet 1.5 mm thick
Base side 1 x 24/12 x 14/12 (1 x 600 x 350 mm)
Long side 2 x 24/12 x 7½ ÷ 12 (2x600x190mm)
Short side 2 x 14/12 x 7½ ÷ 12 (2x350x190mm)
Top 1 x 24 x 12 x 14 ÷ (600 x 350 x 150 mm)
1.04 Sqm @ 12.20 Kg/Sqm 12.68 kg 29.00 per kg 367.72
2 Angle Iron 25 x 25 x 3 mm/Sqm
2 x 24" = 48" (2 x 600 mm)
2 x 14" = 28" (2 x 350 mm)
4 x 7.12 = 30" (4 x 190 mm)
=
0.82 Sqm @ 6.08 Kg/Sqm 1.70 kg 1.70 kg 24.00 each 40.80
3 Handle chromium plated 1.00 No. 15.00 each 15.00
4 Painting 0.178 Gallon 450.00 Gallon 80.10
5 Hinges 3.00 Nos. 2.50 each 7.50
6 Locking arrangement L.S 60.00

Total 571.12
Contractor's Profit & Overh 20 Percent 114.22
Total 685.34

LABOUR (For 4 Nos.)

1 Black Smith 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00
3 Painter 0.125 No. 170.00 per day 21.25
4 Electrician 1.00 No. 170.00 per day 170.00

Total 501.25
Sundries 10 Percent 50.13
Total 551.38
Contractor's Profit & Overh 20 Percent 110.28
Total 527.87

ITEM RATES

Labour rate for Each Rs. 131.97 Say 131.95


Composite rate for Each Rs. 817.31 Say 817.30

Page 210
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing M.S iron box for housing main switches, made of 1.5 m
(1/16") thick M.S sheet, with locking arrangement, including painting:

(ii) 95 x 40 x 20 cm (38" x 16" x 8")

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
1 M.S sheet 38"x16"x 8" thick (1965x406x200mm)
Base side 1x38/12x16/12 (965x406mm) = 0.39 Sqm
Long side 2x38/12x8/12 (2x965x200mm) = 0.39 Sqm
Short side 2x16/12x8/12 (2x406x200mm) = 0.17 Sqm
Top 1x38/12x16/12 (1x965x406mm) = 0.39 Sqm
1.34 Sqm
1.34 Sqm @ 12.45 Kg/Sqm 16.70 kg 29.00 per kg 484.30
2 Angle Iron 1" x 1" x 1/8" (25 x 25 x 3mm)
2 x 965 mm = 1.93 R/m
2 x 406 mm = 0.82 R/m
4 x 200 mm = 0.80 R/m
3.55 R/m
3.55 R/m @ 0.632 Kg/R/m 2.25 kg 24.00 per kg 54.00
3 Handle chromium plated 1.00 No. 15.00 each 15.00
4 Paint 0.045 Gallon 450.00 Gallon 20.25
5 Hinges 3.00 Nos. 2.50 each 7.50
6 Locking arrangement L.S 60.00

Total 641.05
Contractor's Profit & Overh 20 Percent 128.21
Total 769.26

LABOUR (For 3 Nos.)

1 Black Smith 1.25 Nos. 170.00 per day 212.50


2 Cooly (helper) 1.00 No. 140.00 per day 140.00
3 Painter 0.125 No. 170.00 per day 21.25
4 Electrician 1.00 No. 170.00 per day 170.00

Total 543.75
Sundries 10 Percent 54.38
Total 598.13
Contractor's Profit & Overh 20 Percent 119.63
Total 717.75

ITEM RATES
Labour rate for Each Rs. 239.25 Say 239.25
Composite rate for Each Rs. 1008.51 Say 1008.50

Page 211
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing M.S iron box for housing main switches, made of 1.5 m
(1/16") thick M.S sheet, with locking arrangement, including painting:

(iii) 105 x 52.5 x 22.5 cm (42" x 21" x 9")

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
1 M.S sheet 42" x 21" x 9" thick (1067 x 534 x 225mm)
Base side 1 x 42/12 x 21/12 (1076x534mm)
Long side 2 x 42/12 x 9/12 (2x1067x225mm)
Short side 2 x 21/12 x 9/12 (2x534x225mm)
Top 1 x 42 (1x1067x534mm)
12 12 1.872 Sqm
1872 Sqm @ 27.44 Per Sqm (51.36 lbs) 23.30 kg 29.00 per kg 675.70
2 Angle Iron 1" x 1" x 1/8 (25x25x3mm)
2 x 42" = 84" (2x1076)
2 x 21" = 42" (2x534)
4 x 9" = 36" (4x225mm)
162" or 13.5 ft. (4.12 R/m)
412 ft. 1.394 lbs/PRM 5.74 lbs 2.60 kg 24.00 per kg 62.40
3 P/F chromium plated 1.00 No. 15.00 each 15.00
4 P/F Hinges 3.00 Nos. 2.50 each 7.50
Paint 0.054 Gallon 450.00 Gallon 24.30
Locking arrangement L.S 60.00

Total 844.90
Contractor's Profit & Overh 20 Percent 168.98
Total 1013.88

LABOUR (For 2 Nos.)

1 Black Smith 1.25 Nos. 170.00 per day 212.50


2 Colly (helper) 1.00 No. 140.00 per day 140.00
3 Painter 0.17 No. 170.00 per day 28.90
4 Electrician 1.00 No. 170.00 per day 170.00
Total 551.40
Sundries 10 Percent 55.14
Total 606.54
Contractor's Profit & Overh 20 Percent 121.31
Total 727.85

ITEM RATES

Labour rate for Each Rs. 363.92 Say 363.90


Composite rate for Each Rs. 1377.80 Say 1377.80

Page 212
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing M.S iron box for housing main switches, made of 1.5 m
(1/16") thick M.S sheet, with locking arrangement, including painting:

(iv) 135 x 70 x 27.5 cm (54" x 28" x 11")

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
1 M.S sheet (54" x 28" 11") thick (1372x710x280mm)
Base side 1 x 54/12 x 28/12 (1372x710mm)
Long side 2 x 54/12 x 11/12 (2x1372x280mm)
Short side 2 x 28/12 x 11/12 (2x710x280mm)
Top 1 x 54/12 x 28/12 (1x1372x710mm)
3.12 Sqm
3.12 Sqm @ 27.44 lbs/Per Sqm (85.50 lbs) 38.78 kg 29.00 per kg 1124.62
2 Angle Iron 1" x 1" x 1/8" (25x25x3mm)
1x2 x 54"= 108" (2x1372mm)
2 x 28" = 56" (2x710mm)
4 x 11" = 44" (4x280mm)
5.28 R/M
5.28 R/M @ 1.39 lbs/Per R/M
7.36 lbs (7.36 lbs) 3.34 kg 24.00 per kg 80.16
3 Handle chromium plated 1.00 No. 15.00 each 15.00
4 Hinges with screws 4.00 Nos. 2.50 each 10.00

5 Locking arrangement L.S 60.00

Total 1289.78
Contractor's Profit & Overh 20 Percent 257.96
Total 1547.74

LABOUR (For 2 Nos.)

1 Black Smith 1.50 No. 170.00 per day 255.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00
3 Painter 0.25 No. 170.00 per day 42.50
4 Electrician 1.00 No. 170.00 per day 170.00

Total 607.50
Sundries 10 Percent 60.75
Total 668.25
Contractor's Profit & Overh 20 Percent 133.65
Total 801.90

ITEM RATES
Labour rate for Each Rs. 400.95 Say 400.95
Composite rate for Each Rs. 1948.69 Say 1948.70

Page 213
DESCRIPTION OF ITEM:

Item No. 45 Supply and erection of girder clamp hook, 16 mm (5/8") with M.S plate 25 x
with bolts and nuts for hanging ceiling fans.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Girder clamp hock 5/8" (16 mm) with


M.S plate 1" x ¼" (25 x 6 mm) 1.00 No. 80.00 each 80.00
2 Nut & bolts ½" (12 mm) 1½" (40 mm) long 2.00 Nos. 2.00 each 4.00

Total 84.00
Contractor's Profit & Overh 20 Percent 16.80
Total 100.80

LABOUR (For 30 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 10.56 Say 10.55


Composite rate for Each Rs. 111.36 Say 111.35

Page 214
DESCRIPTION OF ITEM:

Item No. 46 Supply and erection of girder strut, of M.S tee section 40 x 40 x 6 mm (1½"
1½" x ¼") complete with clamp, bolts and nuts, etc., including fixing with
cement concrete 1 : 3 : 6.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

5.00 kg
1 T - Iron ¼" x 1½" x 1½" x 5½" (11.00 lbs) 22.00 110.00
Clamps 1.00 kg 40.00 per kg 40.00
2 Nut & Bolts 1" (25 mm) 3.00 No. 2.00 each 6.00
3 Manufacturing 1.00 No. 74.66 each 74.66

Total 230.66
Contractor's Profit & Overh 20 Percent 46.13
Total 276.79

LABOUR (For 30 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 13.64 Say 13.65


Composite rate for Each Rs. 290.43 Say 290.45

Page 215
DESCRIPTION OF ITEM:

Item No. 47 Supply and erection of roof suspension hook,16mm (5/8" dia) rod with 75x4
(3 x 1½" x 1/8") M.S Steel Channel, with clamp, bolts & nuts etc., including
with cement concrete 1:3:6.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Steel channel 75 x 40 x 3 mm
1.5 R/m @ 6.90 Kg/R/m 10.35 kg 10.35 kg 25.00 per kg 258.75
2 Hook 5/8" (16 mm) with nut & bolts 1.00 No. 30.00 each 30.00
3 Clamp 1.00 No. 16.00 each 16.00
4 Cement 0.042 Cft. 230.00 P. Bag 9.66
5 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

Total 314.83
Contractor's Profit & Overh 20 Percent 62.97
Total 377.80

LABOUR (For 28 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 14.61 Say 14.60


Composite rate for Each Rs. 392.41 Say 392.40

Page 216
DESCRIPTION OF ITEM:

Item No. 48 Supply and erection of roof suspension hook, of M.S plate 75 x 40 x 13 mm
(3 x 1½" x ½") with 16 mm (5/8") hook, complete with bolts and nuts and fix
with cement concrete 1 : 3 : 6.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron plate 3"x1½"x½" (0.862x40x12mm) 6.96 lbs


3.16 kg 3.16 kg 30.00 per kg 94.80
2 Hook 5/8" with bolts & nut 1.00 No. 30.00 each 30.00
3 Cement 0.063 Cft. 230.00 P. Bag 14.49
4 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 139.92
Contractor's Profit & Overh 20 Percent 27.98
Total 167.90

LABOUR (For 21 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 19.49 Say 19.50


Composite rate for Each Rs. 187.39 Say 187.40

Page 217
DESCRIPTION OF ITEM:

Item No. 49 Supply and erection of 3/8" (10 mm) dia M.S bar fan hook placed at the time
casting of slab.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S bar hook 3/8" (!0 mm) dia 1.00 No. 8.00 each 8.00

Total 8.00
Contractor's Profit & Overh 20 Percent 1.60
Total 9.60

LABOUR (For 39 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 5.75 Say 5.75


Composite rate for Each Rs. 15.35 Say 15.35

Page 218
DESCRIPTION OF ITEM:

Item No. 50 Erection of circular L.T pole in cement concrete 1 : 3 : 6, one metre below
ground level (excluding the cost of pole), including cement concrete collar
(1 : 2 : 4) excavation of foundation and finishing surface.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement concrete 1:3:6 (1.22x.300x1.0) 0.3714 Cum 0.3714 Cum 2056.90 Per Cum 763.93

Total 763.93
Contractor's Profit & Overh 20 Percent 152.79
Total 572.13

LABOUR (For 4 Nos.)

1 Cement concrete 1 : 3 : 6 0.3714 Cum 557.58 Cum 207.09


2 Excavation of foundatin 0.3714 Cum 21.88 Cum 8.13
3 Erection of pole in position
Plumber 0.50 No. 170.00 per day 85.00
Helper 2.00 Nos. 75.00 per day 150.00
4 Extra labour for shuttering L.S 10.00

Total 460.21
Sundries 10 Percent 46.02
Total 506.23
Contractor's Profit & Overh 20 Percent 101.25
Total 607.48

ITEM RATES

Labour rate for Each Rs. 151.87 Say 151.85


Composite rate for Each Rs. 724.00 Say 724.00

Page 219
DESCRIPTION OF ITEM:

Item No. 51 Supply and erection of bracket of M.S channel 75 x 40 x 6 mm (3"x1½"x¼")


section:

(i) 0.60 metre (2') long for 2 lines.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Steel channel (25 x 13 x 6 mm)


0.600 @ 5.22 Kg 3.18 Kg
Steel plate (75 x 20 x 20 mm) 0.79 Kg
3.97 Kg 3.97 Kg 25.00 per kg 99.25
Bolts and nuts 5/8" dia (16 mm) 2.00 Nos. 4.00 each 8.00

Total 107.25
Contractor's Profit & Overh 20 Percent 21.45
Total 128.70

LABOUR (For 7 Nos.)

1 Black Smith 1.00 No. 170.00 per day 170.00


2 Electrician 0.25 No. 170.00 per day 42.50

Total 212.50
Sundries 10 Percent 21.25
Total 233.75
Contractor's Profit & Overh 20 Percent 46.75
Total 280.50

ITEM RATES

Labour rate for Each Rs. 40.07 Say 40.05


Composite rate for Each Rs. 168.77 Say 168.75

Page 220
DESCRIPTION OF ITEM:

Item No. 51 Supply and erection of bracket of M.S channel 75 x 40 x 6 mm (3"x1½"x¼")


section:

(ii) 1.20 metre (4') long, for 4 lines.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Steel channel 75 x 13 x 6 mm
1.322 m @ 5.22 Kg/Rm 6.35 Kg
Iron plate 75 x 20 x 6 mm 0.80 Kg
7.15 Kg 7.15 Kg 25.00 per kg 178.75
Bolts and nuts 5/8" dia (16 mm) 2.00 Nos. 4.00 each 8.00
Manufacturing charges 1 job 74.66 per job 74.66

Total 261.41
Contractor's Profit & Overh 20 Percent 52.28
Total 313.69

LABOUR (For 6 Nos.)

1 Black Smith 1.00 No. 170.00 per day 170.00


2 Electrician 0.25 No. 170.00 per day 42.50

Total 212.50
Sundries 10 Percent 21.25
Total 233.75
Contractor's Profit & Overh 20 Percent 46.75
Total 280.50

ITEM RATES

Labour rate for Each Rs. 46.75 Say 46.75


Composite rate for Each Rs. 360.44 Say 360.45

Page 221
DESCRIPTION OF ITEM:

Item No. 52 Supply and erection of anchor rod Henley type for pole, including necessary
clamps and 7/12" stay wire, straining screws, etc., erected in cement concre
1 : 3 : 6 and collar of cement concrete.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 Stay wire 7/12" 10.00 metre 10.00 per mtr. 100.00


2 Double clamp 1.00 No. 60.00 each 60.00
3 Steining Screw 1.00 No. 30.00 each 30.00
4 Eye bolts 1.00 No. 8.00 each 8.00
5 Cement 0.064 Cft. 230.00 P. Bag 14.72
6 Sand 0.16 Cft. 350.00 Per % Cft. 0.56
7 Bajri 0.322 1200.00 P. Cft. 3.86

Total 217.15
Contractor's Profit & Overh 20 Percent 43.43
Total 260.58
Material per metre 235.40 ÷ 1 26.0577 26.06

LABOUR (For 70 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 2.00 Nos. 140.00 per day 280.00

Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00

ITEM RATES

Labour rate per Metre Rs. 8.49 Say 8.50


Labour rate per Ft. Rs. 2.59 Say 2.60

Composite rate per Metre Rs. 34.54 Say 34.55


Composite rate per Ft. Rs. 10.53 Say 10.55

Page 222
DESCRIPTION OF ITEM:

Item No. 53 Supply and erection of stay for house service pipe, erected with straining
screws and 7/14" stay wire, complete.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 5 Metre)

1 Stay wire 7/14" 5.00 metre 5.00 per mtr. 25.00


2 Double clamp 9" dia (225 mm) 1.00 No. 15.00 each 15.00
3 Stearining Screw 1.00 No. 30.00 each 30.00
4 Hook size 1.00 No. 15.00 each 15.00
5 Eye bolts 1.00 No. 17.00 each 17.00
6 Cement 0.064 Cft. 230.00 P. Bag 14.72
7 Sand 0.16 Cft. 350.00 Per % Cft. 0.56
8 Bajri 0.322 1200.00 P. Cft. 3.86

Total 121.15
Contractor's Profit & Overh 20 Percent 24.23
Total 145.38
Material per metre 129.80 ÷ 5 29.0754 29.08

LABOUR (For 35 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10 Percent 33.00
Total 363.00
Contractor's Profit & Overh 20 Percent 72.60
Total 435.60

ITEM RATES

Labour rate per Metre Rs. 12.45 Say 12.45


Labour rate per Ft. Rs. 3.79 Say 3.80

Composite rate per Metre Rs. 41.57 Say 41.55


Composite rate per Ft. Rs. 12.67 Say 12.65

Page 223
DESCRIPTION OF ITEM:

Item No. 54 Supply and erection of house service pipe Henley (G.I pipe water quality) or
pole, type, 50 mm (2" dia) erected to install insulated overhead line, includi
shackle insulator for holding insulated wire and straining devices for bearer
wire and other accessories, etc., complete.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 4 Metre)

1 G.I. pipe 2" dia (50 mm) 4.00 metre 199.27 per mtr. 797.08
2 Shakle insulator 1.00 No. 40.00 each 40.00
3 Clamp double 1.00 No. 40.00 each 40.00
4 Clamp 2" dia (50 mm) 1.00 No. 55.00 each 55.00
5 Rag bolts 5/8" 9" (16 x 225 mm) 1.00 No. 15.00 each 15.00
6 G.I bend 2" (50 mm) cap 2.00 Nos. 65.00 each 130.00
7 G.I Reducing socket 2 x ¾" dia (50 x 20 mm) 1.00 No. 40.00 each 40.00
8 M.S bolts for suport 1.00 No. 16.00 each 16.00
9 Cement 0.064 Cft. 230.00 P. Bag 14.72
10 Sand 0.16 Cft. 350.00 Per % Cft. 0.56
11 Bajri 0.322 1200.00 P. Cft. 3.86

Total 1152.23
Contractor's Profit & Overh 20 Percent 230.45
Total 1382.67
Material per metre 1090.45 ÷ 345.67 345.67

LABOUR (For 12 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

Total 490.00
Sundries 10 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20 Percent 107.80
Total 646.80

ITEM RATES

Labour rate per Metre Rs. 53.90 Say 53.90


Labour rate per Ft. Rs. 16.43 Say 16.45

Composite rate per Metre Rs. 306.89 Say 306.90


Composite rate per Ft. Rs. 93.56 Say 93.55

Page 224
DESCRIPTION OF ITEM:

Item No. 55 Supply and erection of house service pipe 50 mm (2" dia) G.I pipe Henley or
pole type, for bare copper wire overhead line, including shackle insulator,
straining devices and other accessories, etc.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 4 Metre)

1 G.I. pipe (water quality) 4.00 metre 199.27 per mtr. 797.08
2 Shakle insulator 1.00 No. 40.00 each 40.00
3 Clamp double 1.00 No. 40.00 each 40.00
4 Clamp 2" dia (50 mm) 1.00 No. 55.00 each 55.00
5 Rag bolts 5/8" 9" (16 x 225 mm) 1.00 No. 15.00 each 15.00
6 G.I bend 2" (50 mm) cap 2.00 Nos. 65.00 each 130.00
7 G.I Reducing socket 2 x ¾" dia (50 x 20 mm) 1.00 No. 40.00 each 40.00
8 M.S bar suport 1.00 No. 16.00 each 16.00
9 Cement 0.042 Cft. 230.00 P. Bag 9.66
10 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

Total 1143.16
Contractor's Profit & Overh 20 Percent 228.63
Total 1371.79
Material per metre 1081.65 ÷ 342.95 342.95

LABOUR (For 12 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 2.00 Nos. 140.00 per day 280.00

Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00

ITEM RATES

Labour rate per Metre Rs. 49.50 Say 49.50


Labour rate per Ft. Rs. 15.09 Say 15.10

Composite rate per Metre Rs. 392.45 Say 392.45


Composite rate per Ft. Rs. 119.65 Say 119.65

Page 225
DESCRIPTION OF ITEM:

Item No. 56 Supply and erection of lightening arrestor horn type, complete.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Lightening arrestor 1.00 No. 200.00 each 200.00

Total 200.00
Contractor's Profit & Overh 20 Percent 40.00
Total 240.00

LABOUR (For 5 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 81.84 Say 81.85


Composite rate for Each Rs. 321.84 Say 321.85

Page 226
DESCRIPTION OF ITEM:

Item No. 57 Supply and erection of shackle insulator, medium size.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Shackle insulator (medium size) 1.00 No. 40.00 each 40.00

Total 40.00
Contractor's Profit & Overh 20 Percent 8.00
Total 48.00

LABOUR (For 7 Nos.)

1 Electrician 0.33 No. 170.00 per day 56.10

Total 56.10
Sundries 10 Percent 5.61
Total 61.71
Contractor's Profit & Overh 20 Percent 12.34
Total 74.05

ITEM RATES

Labour rate for Each Rs. 10.58 Say 10.60


Composite rate for Each Rs. 58.58 Say 58.60

Page 227
DESCRIPTION OF ITEM:

Item No. 58 Supply and erection of pin insulator, green medium size.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Pin insulator green (medium size) 1.00 No. 11.00 each 11.00

Total 11.00
Contractor's Profit & Overh 20 Percent 2.20
Total 13.20

LABOUR (For 7 Nos.)

1 Electrician 0.33 No. 170.00 per day 56.10

Total 56.10
Sundries 10 Percent 5.61
Total 61.71
Contractor's Profit & Overh 20 Percent 12.34
Total 74.05

ITEM RATES

Labour rate for Each Rs. 10.58 Say 10.60


Composite rate for Each Rs. 23.78 Say 23.80

Page 228
DESCRIPTION OF ITEM:

Item No. 59 Supply and erection of bare copper conductor wire, No.2 to No.10 SWG,
including binding wire No.16 SWG.

Detail Unit Rate (Metric System) per Kg

Qty Rate Per Unit Amount (Rs.)

MATERIAL
13.61 kg
1 Copper wire No.2 to 10 (30.00 lbs) 80.00 per kg 1088.80
2 Binding wire No.16 1.00 lbs 28.00 per kg 12.70
0.454 kg
Total 1101.50
Contractor's Profit & Overh 20 Percent 220.30
Total 1321.81
Per Kg 1211.65 ÷ 97.12 97.12

LABOUR (For 90 Lbs) 40.82 Kg

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Kg Rs. 5.50 Say 5.50


Composite rate per Kg Rs. 102.62 Say 102.60

Page 229
DESCRIPTION OF ITEM:

Item No. 60 Supply and erection of G.I wire of all sizes, including binding wire No.16 SW
for support of rubber wire or earthing wire, pole to pole, etc.

Detail Unit Rate (Metric System) per Kg

Qty Rate Per Unit Amount (Rs.)

MATERIAL
13.61 kg
1 G.I wire (all size) (30.00 lbs) 27.00 per kg 367.47
2 Binding wire No.16 (1.00 lbs) 28.00 per kg 12.71
0.454 kg

Total 380.18
Contractor's Profit & Overh 20 Percent 76.04
Total 456.22
Material cost per Kg 418.20 ÷ 1 33.52 33.52

LABOUR (For 90 Lbs) 40.83 Kg

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Kg Rs. 5.50 Say 5.50


Composite rate per Kg Rs. 39.02 Say 39.00

Page 230
DESCRIPTION OF ITEM:

Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on G.I wire
No.8 SWG bearer wire and in house service pipe, including connection
through joint box:

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 47 Metre)

1 PVC/weather proof cable 3/0.029" (3/0.74 mm)


Single core 47.00 metre 8.80 per mtr. 413.60
2 Leather or wooden cleats 25.00 Nos. 1.00 each 25.00
1.81 kg
3 G.I wire No.8 SWG (4.00 lbs) 27.00 kg 48.87
4 Eye - bolts 2.00 Nos. 17.00 each 34.00

Total 521.47
Contractor's Profit & Overh 20 Percent 104.29
Total 625.76
Material cost per metre 573.62 ÷ 4 13.31 13.31

LABOUR (For 90 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate per Metre Rs. 4.55 Say 4.55


Labour rate per Ft. Rs. 1.39 Say 1.40

Composite rate per Metre Rs. 15.49 Say 15.50


Composite rate per Ft. Rs. 4.77 Say 4.75

Page 231
DESCRIPTION OF ITEM:

Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on G.I wire
No.8 SWG bearer wire and in house service pipe, including connection
through joint box:

(ii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 47 Metre)

1 PVC/weather proof cable /0.029" (7/0.74 mm)


Single core 47.00 metre 13.75 per mtr. 646.25
1.81 kg
2 G.I wire No.8 SWG (4.00 lbs) 27.00 kg 48.87
3 Eye - bolts 2.00 Nos. 17.00 each 34.00
4 Cut out 2.00 Nos. 13.00 each 26.00
5 T. Wooden board 7" x 4" (175 x 100 mm) 1.00 No. 20.00 each 20.00
6 Wooden & leather cleats 25.00 Nos. 1.00 each 25.00

Total 800.12
Contractor's Profit & Overh 20 Percent 160.02
Total 960.14
Material cost per metre 880.13 ÷ 47 20.43 20.43

LABOUR (For 90 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate per Metre Rs. 4.55 Say 4.55


Labour rate per Ft. Rs. 1.39 Say 1.40

Composite rate per Metre Rs. 24.98 Say 25.00


Composite rate per Ft. Rs. 7.61 Say 7.60

Page 232
DESCRIPTION OF ITEM:

Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on G.I wire
No.8 SWG bearer wire and in house service pipe, including connection
through joint box:

(iii) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 47 Metre)

1 PVC/weather proof cable /0.036" (7/0.91 mm)


Single core 47.00 metre 20.00 per mtr. 940.00
1.81 kg
2 G.I wire No.8 SWG (4.00 lbs) 27.00 kg 48.87
3 Eye - bolts 2.00 Nos. 17.00 each 34.00
4 Cut out 2.00 Nos. 13.00 each 26.00
5 T. Wooden board 7" x 4" (175 x 100 mm) 1.00 No. 20.00 each 20.00
6 Wooden & leather cleats 25.00 Nos. 2.00 each 50.00

Total 1118.87
Contractor's Profit & Overh 20 Percent 223.77
Total 1342.64
Material cost per metre 1230.76 ÷ 28.57 28.57

LABOUR (For 90 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate per Metre Rs. 4.55 Say 4.55


Labour rate per Ft. Rs. 1.39 Say 1.40

Composite rate per Metre Rs. 33.11 Say 33.10


Composite rate per Ft. Rs. 10.10 Say 10.10

Page 233
DESCRIPTION OF ITEM:

Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on G.I wire
No.8 SWG bearer wire and in house service pipe, including connection
through joint box:

(iv) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 47 Metre)

1 PVC/weather proof cable /0.044" (7/1.12 mm)


Single core 47.00 metre 24.00 per mtr. 1128.00
1.81 kg
2 G.I wire No.8 SWG (4.00 lbs) 27.00 kg 48.87
3 Eye - bolts 2.00 Nos. 17.00 each 34.00
4 Cut out 2.00 Nos. 13.00 each 26.00
5 T. Wooden board 7" x 4" (175 x 100 mm) 1.00 No. 20.00 each 20.00
6 Wooden & leather cleats 25.00 Nos. 2.00 each 50.00

Total 1306.87
Contractor's Profit & Overh 20 Percent 261.37
Total 1568.24
Material cost per metre 1437.56 ÷ 33.37 33.37

LABOUR (For 80 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate per Metre Rs. 4.55 Say 4.55


Labour rate per Ft. Rs. 1.39 Say 1.40

Composite rate per Metre Rs. 34.30 Say 34.30


Composite rate per Ft. Rs. 10.46 Say 10.45

Page 234
DESCRIPTION OF ITEM:

Item No. 62 Supply and erection of all aluminium stranded hard drawn bare conductor o
size 7/3.099 mm (7/0.122").

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Aluminium stranded hard drawn bare


conductor 7/3.099 mm (7/0.122") 1.00 No. 19.80 each 19.80

Total 19.80
Contractor's Profit & Overh 20 Percent 3.96
Total 23.76

LABOUR (For 26 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Metre Rs. 8.63 Say 8.65


Labour rate per Ft. Rs. 2.63 Say 2.65

Composite rate per Metre Rs. 32.39 Say 32.40


Composite rate per Ft. Rs. 9.88 Say 9.90

Page 235
DESCRIPTION OF ITEM:

Item No. 63 Supply and erection of street light pole bracket 30 mm (1¼") G.I pipe 2 met
long, complete with 2 No. pole clamp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Pipe 1¼" dia (32 mm) 7 ft. (2.13 metre) 2.13 metre 125.03 per mtr. 266.31
2 Cost of clamp 2.00 Nos. 20.00 each 40.00

Total 306.31
Contractor's Profit & Overh 20 Percent 61.26
Total 367.58

LABOUR (For 6 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 68.20 Say 68.20


Composite rate for Each Rs. 435.78 Say 435.80

Page 236
DESCRIPTION OF ITEM:

Item No. 64 Supply and erection of pole mounted street light, holders, shade and glass,
etc., for fitting 125/250 watts mercury vapour lamp (excluding cost of lamp

(i) G.E.C design

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Pole street with holder shade and glass


for mercury vapour lamp 125/250 complete 1.00 No. 1000.00 each 1000.00
2 Bracket 1.00 No. 100.00 each 100.00
3 Clamps with bolts & nuts etc. 2.00 Nos. 60.00 each 120.00

Total 1220.00
Contractor's Profit & Overh 20 Percent 244.00
Total 1464.00

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 136.40 Say 136.40


Composite rate for Each Rs. 1600.40 Say 1600.40

Page 237
DESCRIPTION OF ITEM:

Item No. 64 Supply and erection of pole mounted street light, holders, shade and glass,
etc., for fitting 125/250 watts mercury vapour lamp (excluding cost of lamp

(ii) Phillips design

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of fitting complete with holder


shade and glass 1.00 No. 1722.85 each 1722.85
2 Cost of bracket 1¼" (32 mm) G.I pipe
7 ft. long half round 1.00 No. 326.00 each 326.00
3 Cost of pole clamp with bolt & nuts 2.00 Nos. 100.00 each 200.00

Total 2248.85
Contractor's Profit & Overh 20 Percent 449.77
Total 2698.62

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 136.40 Say 136.40


Composite rate for Each Rs. 2835.02 Say 2835.00

Page 238
DESCRIPTION OF ITEM:

Item No. 65 Supply and fitting of mercury vapour lamp, complete with choke set.

(i) 125 watt lamp

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Vapour mercury lamp 125 watt


with choke set 649 + 330 = 979.00 1.00 Nos. 979.00 each 979.00

Total 979.00
Contractor's Profit & Overh 20 Percent 195.80
Total 1174.80

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 52.80 Say 52.80


Composite rate for Each Rs. 1227.60 Say 1227.60

Page 239
DESCRIPTION OF ITEM:

Item No. 65 Supply and fitting of mercury vapour lamp, complete with choke set.

(ii) 250 watt lamp

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Vapour mercury lamp 250 watt


with choke set 2558 + 100 = 3658 1.00 Nos. 2031.54 each 2031.54

Total 2031.54
Contractor's Profit & Overh 20 Percent 406.31
Total 2437.85

LABOUR (For 5 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 63.36 Say 63.35


Composite rate for Each Rs. 2501.21 Say 2501.20

Page 240
DESCRIPTION OF ITEM:

Item No. 66 Manufacture and erection of angle iron lattice steel structure pole 10923 m
long (9348 mm ground level) 355 mm square at base & 204 mm square at to
electric distribution line, using 1¼"x1¼"x3/16" angle iron legs and ¾"x¾"x1
angle iron bracings 420 mm long fixed between legs on all the four sides in
diagonal position, and 1¾" x 1¾" x 3/16" angle iron on top and 4 bands of M
flat iron 2" x ¼", 305 mm centre to centre, as per standard drawing, includi
silverpainting of pole 3 coats, excavation and refilling of foundation, cemen
concrete 1 : 2 : 4, 1807 x 500 x 500 mm for foundation, etc., complete in all
respects.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Angle iron 1¼"x1¼"x3/16" (32x32x4 mm)


Legs 4x10923 mm = 43692mm = 143.35 ft.
143.35 ft. @ 1.47 lbs/ft. = 210.72 lbs
2 Angle Iron ¾"x¾"x1/8 (20x20x3 mm)
Bracing 18x4x420mm = 30240mm or 99.21 ft.
99.21 ft. @ 0.58 lbs/ft. = 57.54 lbs
3 Angle Iron 1"x1"1/8 (25x25x3 mm)
Bracing 3x4x385mm = 4620 mm or 15.16 ft.
15.16 ft. @ 0.80 lbs/ft. 12.13 lbs
280.39 lbs 127.22 kg 24.00 per kg 3053.28
4 M.S. flat 2x¼" (50 x 6 mm)
4x4x204 mm = 3264 mm = 10.71 ft.
10.71 ft. @ 1.70 lbs/ft. = 18.21 lbs 8.26 kg 22.00 per kg 181.72
5 Angle Iron 1¾"x1¾"x3/16" (44x44x4 mm)
4x4x204 mm = 3264mm = 10.71 ft.
10.71 ft. @ 2.11 lbs/ft. = 22.60 lbs 10.25 kg 24.00 per kg 246.00
6 Silver paint 0.25 gallon @ 550 per gallon 0.25 gallon 550.00 per gln. 137.50
7 Cement concrete 1 : 2 :4
foundation 500x500x1728 mm = 0.43 m
15.06 Cft 15.06 Cft. 78.65 per Cft 1184.47
8 Pre cast cement concrete 1 : 2 : 4
2x100x100x100 = 2000000 mm or 0.07 Cft
0.07 Cft 0.07 Cft. 64.78 per Cft 4.53

Total 4807.50
Contractor's Profit & Overh 20 Percent 961.50
Total 5769.00

Page 241
Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Black Smith 1.50 Nos. 170.00 per day 255.00


Cooly (helper) 3.00 Nos. 140.00 per day 420.00
2 Welding charges
No. of weld 2(72+12+16) = 200 Nos. 200.00 Nos. 4.00 each 800.00
3 Drilling hole 20.00 Nos. 4.00 each 80.00
Painter 0.25 No. 170.00 per day 42.50
4 Excavation 500x500x1576 mm = 394000000
or 13.91 Cft (Item 4b Chap. 3) 13.91 Cum 1.27 per Cft 17.69
5 Concrete 1:2:4
Foundation 500x500x1728 mm = 432000000
15.06 Cft (Item 5f Chap. 6) 15.06 Cum 18.45 per Cft 277.89
6 Pre cast cement concrete 1:2:4
2x100x100x100 = 2000000 mm or 0.07 Cft 0.07 Cum 17.55 per Cft 1.23
(Item 10 Chap. 6)
Total 1894.31
Sundries 10 Percent 189.43
Total 2083.74
Contractor's Profit & Overh 20 Percent 416.75
Total 2500.49

ITEM RATES

Labour rate for Each Rs. 2500.49 Say 2500.50


Composite rate for Each Rs. 8269.49 Say 8269.50

Page 242
DESCRIPTION OF ITEM:

Item No. 67 Manufacture and erection of galvanized angle iron lattice steel structure
pole 11.30 metre long (9.85 metre above ground level), 875mm square at
base, 350mm square at top, for electric distribution line, using 50x50x4mm
high tensile steel angle iron legs, and 310x310x3mm M.S angle iron bracin
fixed between legs on all the four sides in diagonal position, as per standar
drawing including silver painting of pole, excavation and refilling of
foundation, one ft. thick cement concrete 1:3:6 foundation of outer size
2.44x1.067x1.067 metre complete in all respects.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Angle iron 50x50x4mm (lattice steel)


Legs 4x30 ft. = 120 ft.
Studs 4x7 = 28 = 148 ft. 1.96 lbs/Rft = 290.08 lbs
131.62 kg 131.62 kg 24.00 per kg 3158.88
2 Angle Iron 1 3/8 x 1 3/8 3 x 1/8
Braces 4x16x2.75 = 176 ft.
@ 1.55 lbs/ft. = 272.8 lbs = 123.77 kg 123.77 kg 24.00 per kg 2970.48
3 M.S plate 5/32" thick
13¾"x13¾"x5/32" = 0.017 Cft
@ 493 lbs/Cft = 8.38 lbs 3.80 kg 3.80 kg 29.00 per kg 110.20

4 Silver paint 0.25 gallon 0.25 gallon 550.00 per gln. 137.50
5 Cement concrete 1:3:6
(3.5 x 3.5 x 0.5) = 6.13 Cft
(1 x 3.5 x 6.5) = 22.75 Cft
(1 x 1.5 x 6.5) = 9.75 Cft
38.63 Cft 38.63 Cum 41.68 per Cum 1609.94

Total 7987.00
Contractor's Profit & Overh 20 Percent 1597.40
Total 9584.40

Page 243
Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Black Smith 1.50 Nos. 170.00 per day 255.00


2 Cooly (helper) 3.00 Nos. 140.00 per day 420.00
3 Welding charges (No. of weld)
Bacing 64 x 2 = 128 Nos.
T/plate 1 x 4 = 4 Nos.
132 Nos.
132 Nos. weld 132.00 Nos. 4.00 per weld 528.00
4 Drilling hole 8.00 Nos. 4.00 per hole 32.00
5 Painter 0.25 No. 170.00 per day 42.50
6 Excavation of foundation
(3.5 x 3.5 x 7.5) (Item 4b Chap. 3) 91.88 Cft 91.88 Cft 1.27 per Cft 116.82

7 Cement Concrete 1:3:6 (Item 3a Chap. 6) 38.630 Cft 11.29 per Cft 435.98

8 Earth filling(1.5x.5 x 6.5) (Item 15(ii) Chap. 14.63 Cft 14.630 Cft 1.09 per Cft 16.01

Total 1365.03
Sundries 10 Percent 136.50
Total 1501.53
Contractor's Profit & Overh 20 Percent 300.31
Total 1801.84

ITEM RATES

Labour rate for Each Rs. 1801.84 Say 1801.85


Composite rate for Each Rs. 11386.24 Say 11386.25

Page 244
DESCRIPTION OF ITEM:

Item No. 68 Earthing of iron clad/aluminium switches, etc., with G.I wire No.8 SWG in G.
pipe 15 mm (½" dia) recessed or on surface of wall and floor, complete with
1.5 metre long G.I pipe, 50 mm (2" dia) with reducing socket 4 to 5 metre
below ground level, and 2 metre away from building plinth.

Detail Unit Rate (Metric System) per Job

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Boring 10.00 metre 22.40 per mtr. 224.00


2 G.I pipe ½" (12 mm) Ø (medium quality) 8.00 metre 52.82 per mtr. 422.56
0.907 kg
3 G.I wire No.8 SWG @ (2 lbs) (2.00 lbs) 27.00 kg 24.49
4 G.I pipe 2" (50 mm) Ø (medium quality) 1.50 metre 199.27 per mtr. 298.91
5 G.I reducing socket size 2 x ½" (50 x 13 mm) 1.00 No. 32.00 each 32.00
6 G.I bend ½" (13 mm) Ø 4.00 No. 8.00 each 32.00
7 Cement 0.063 Cft. 230.00 P. Bag 14.49
8 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 1049.07
Contractor's Profit & Overh 20 Percent 209.81
Total 1258.89

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 2.00 Nos. 140.00 per day 280.00

Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00

ITEM RATES

Labour rate for Each Rs. 297.00 Say 297.00


Composite rate for Each Rs. 1555.89 Say 1555.90

Page 245
DESCRIPTION OF ITEM:

Item No. 69 Earthing of Metallic cases, etc., with G.I wire No.8 SWG, in 15 mm (½" dia) G
pipe, best quality:

(i) On surface, including clamps, etc.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I pipe ½" dia (12 mm) 7.00 metre 52.82 per mtr. 369.74
0.454 kg
2 G.I wire No.8 SWG (1.00 lbs) 27.00 per kg 12.26
3 G.I clamp ½" dia (12 mm) 6.00 Nos. 2.00 each 12.00
4 G.I bolts 2" x ¼" dia (50 x 6 mm) 1.00 No. 2.00 each 2.00
5 Gutties 10.00 Nos. 6.00 per doz. 5.00
6 Screw ¾" (20 mm) 10.00 Nos. 3.25 each 2.71
7 G.I bend ½" dia (12 mm) 1.00 No. 8.00 each 8.00

Total 411.71
Contractor's Profit & Overh 20 Percent 82.34
Total 494.05
Material per Metre 145.48 ÷ 70.58 70.58

LABOUR (For 40 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate per Metre Rs. 10.23 Say 10.25


Labour rate per Ft. Rs. 3.12 Say 3.10

Composite rate per Metre Rs. 80.81 Say 80.80


Composite rate per Ft. Rs. 24.64 Say 24.65

Page 246
DESCRIPTION OF ITEM:

Item No. 69 Earthing of Metallic cases, etc., with G.I wire No.8 SWG, in 15 mm (½" dia) G
pipe, best quality:

(ii) Recessed in wall, including hooks, jharries and making good surface.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I pipe ½" dia (12 mm) 7.00 metre 52.82 per mtr. 369.74
0.454 kg
2 G.I wire No.8 SWG (1.00 lbs) 27.00 kg 12.26
3 G.I bolts 2" x ¼" dia (50 x 6 mm) 1.00 No. 2.00 each 2.00
4 Hooks 6.00 Nos. 4.00 each 24.00
5 G.I bend ½" dia (12 mm) 1.00 Nos. 8.00 each 8.00
6 Cement 0.063 Cft. 230.00 P. Bag 14.49
7 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

Total 431.12
Contractor's Profit & Overh 20 Percent 86.22
Total 517.34
Material per Metre 470.64 ÷ 73.91 73.91

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 2.00 No. 140.00 per day 280.00

Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00

ITEM RATES

Labour rate per Metre Rs. 23.76 Say 23.75


Labour rate per Ft. Rs. 7.24 Say 7.25

Composite rate per Metre Rs. 97.67 Say 97.65


Composite rate per Ft. Rs. 29.78 Say 29.80

Page 247
DESCRIPTION OF ITEM:

Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.

(a) G.I wire:

(i) 8 SWG

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)


0.68 kg
1 G.I wire No.8 SWG (1.50 lbs) 27.00 per kg 18.36
2 Copper themble 1.00 No. 6.00 each 6.00
3 G.I Nuts & Bolts 2" long ½" Ø (50 mm x 13 mm) 1.00 No. 6.00 each 6.00
4 G.I clamp 1.00 No. 8.00 each 8.00
5 Cement 0.042 Cft. 230.00 P. Bag 9.66
6 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

Total 48.44
Contractor's Profit & Overh 20 Percent 9.69
Total 58.13
Material per Metre 51.00 ÷ 7 8.30 8.30

LABOUR (For 50 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Metre Rs. 4.49 Say 4.50


Labour rate per Ft. Rs. 1.37 Say 1.35

Composite rate per Metre Rs. 12.79 Say 12.80


Composite rate per Ft. Rs. 3.90 Say 3.90

Page 248
DESCRIPTION OF ITEM:

Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.

(a) G.I wire:

(ii) 16 SWG

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I wire No.16 SWG 0.112 kg 27.00 per kg 3.02


2 Copper themble 1.00 No. 6.00 each 6.00
3 G.I Nuts & Bolts 1½" x ¼" long (40 x 6 mm) 1.00 No. 4.00 each 4.00
4 Cement 0.011 Cft. 230.00 P. Bag 2.42
5 Sand 0.03 Cft. 350.00 Per % Cft. 0.11

Total 15.54
Contractor's Profit & Overh 20 Percent 3.11
Total 18.65
Material per Metre 16.53 ÷ 7 2.66 2.66

LABOUR (For 50 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Metre Rs. 4.49 Say 4.50


Labour rate per Ft. Rs. 1.37 Say 1.35

Composite rate per Metre Rs. 7.15 Say 7.10


Composite rate per Ft. Rs. 2.18 Say 2.20

Page 249
DESCRIPTION OF ITEM:

Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.

(b) Copper wire:

(i) 16 SWG

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 Copper wire No.16 SWG 0.133 kg 105.00 per kg 13.97


2 Copper themble 1.00 No. 6.00 each 6.00
3 G.I Nuts & Bolts 1½" x ¼" long (40 x 6 mm) 1.00 No. 4.00 each 4.00
4 Cement 0.011 Cft. 230.00 P. Bag 2.42
5 Sand 0.03 Cft. 350.00 Per % Cft. 0.11

Total 26.49
Contractor's Profit & Overh 20 Percent 5.30
Total 31.78
Material per Metre 28.56 ÷ 7 4.54 4.54

LABOUR (For 50 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Metre Rs. 4.49 Say 4.50


Labour rate per Ft. Rs. 1.37 Say 1.35

Composite rate per Metre Rs. 9.03 Say 9.05


Composite rate per Ft. Rs. 2.75 Say 2.75

Page 250
DESCRIPTION OF ITEM:

Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.

(b) Copper wire:

(ii) 20 SWG

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 Copper wire No.20 SWG 0.035 kg 105.00 per kg 3.68


2 Copper themble 1.00 Nos. 6.00 each 6.00
3 G.I Nuts & Bolts 1½" x ¼" long 1.00 Nos. 2.00 each 2.00
4 Cement 0.011 Cft. 230.00 P. Bag 2.42
5 Sand 0.03 Cft. 350.00 Per % Cft. 0.11

Total 14.20
Contractor's Profit & Overh 20 Percent 2.84
Total 17.03
Material per Metre 15.04 ÷ 7 2.43 2.43

LABOUR (For 50 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Metre Rs. 4.49 Say 4.50


Labour rate per Ft. Rs. 1.37 Say 1.35

Composite rate per Metre Rs. 6.92 Say 6.90


Composite rate per Ft. Rs. 2.11 Say 2.10

Page 251
DESCRIPTION OF ITEM:

Item No. 71 Erection only, of lightening conductor of copper staple, and copper nails an
cement, sand mortar.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 Gutties 8.00 Nos. 6.00 per doz. 4.00


2 Copper nail 8.00 Nos. 2.00 each 16.00
3 Copper stapple 4.00 Nos. 4.00 each 16.00
4 Cement 0.021 Cft. 230.00 P. Bag 4.83
5 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

Total 41.04
Contractor's Profit & Overh 20 Percent 8.21
Total 49.25
Material per Metre 44.00 ÷ 7 7.04 7.04

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate per Metre Rs. 16.37 Say 16.35


Labour rate per Ft. Rs. 4.99 Say 5.00

Composite rate per Metre Rs. 23.40 Say 23.40


Composite rate per Ft. Rs. 7.14 Say 7.15

Page 252
DESCRIPTION OF ITEM:

Item No. 72 Supply and erection of 600 x 600x3mm (2'x2x1/8") copper plate, including
riveting to copper tape and placing in mixture of salt & charcoal, etc.

Detail Unit Rate (Metric System) per Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
9.98 kg
1 Copper plate 600x600x3mm=0.00133 Cum (22.00 lbs) 96.00 per kg 958.08
@ 550 lbs/cft 22 lbs 36.30 kg
2 Char coal (80.00 lbs) 4.00 per kg 145.20
18.15 kg
3 Salt (40.00 lbs) 6.00 per kg 108.90

Total 1212.18
Contractor's Profit & Overh 20 Percent 242.44
Total 1454.62

LABOUR (For 3 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 2.00 Nos. 140.00 per day 280.00

Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00

ITEM RATES

Labour rate for Each Rs. 198.00 Say 198.00


Composite rate for Each Rs. 1652.62 Say 1652.60

Page 253
DESCRIPTION OF ITEM:

Item No. 73 Supply and erection of copper tape, including copper staple copper nails,
cement, sand, etc.

(i) Tape 40 x 3 mm (1½" x 1/8")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Copper tap 1½"x1/8" = 1 metre 1.00 kg


1 metre = 0.004 Cft @ 550 lbs/Cft = 2.2 lbs (2.20 lbs) 105.00 per kg 105.00
2 Gutties 1.00 No. 6.00 per doz. 0.50
3 Copper nail 1.00 No. 2.00 each 2.00
4 Copper staple 1.00 No. 4.00 each 4.00

Total 111.50
Contractor's Profit & Overh 20 Percent 22.30
Total 133.80

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 2.00 Nos. 140.00 per day 280.00

Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00

ITEM RATES

Labour rate per Metre Rs. 23.76 Say 23.75


Labour rate per Rft Rs. 7.24 Say 7.25

Composite rate per Metre Rs. 157.56 Say 157.55


Composite rate per Rft Rs. 48.04 Say 48.05

Page 254
DESCRIPTION OF ITEM:

Item No. 73 Supply and erection of copper tape, including copper staple copper nails,
cement, sand, etc.

(ii) Tape 50 x 3 mm (2" x 1/8")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Copper tap 2"x1/8" = 1 metre 1.22 kg


1 metre = 0.005 Cft @ 550 lbs/Cft = 2.7 lbs (2.27 lbs) 105.00 per kg 128.10
2 Copper nail 1.00 No. 1.00 each 1.00
3 Copper staple 1.00 No. 4.00 each 4.00
4 Gutties 1.00 No. 6.00 per doz. 0.50

Total 133.60
Contractor's Profit & Overh 20 Percent 26.72
Total 160.32

LABOUR (For 25 Metre)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 2.00 Nos. 140.00 per day 280.00

Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overh 20 Percent 99.00
Total 594.00

ITEM RATES

Labour rate per Metre Rs. 23.76 Say 23.75


Labour rate per Rft Rs. 7.24 Say 7.25

Composite rate per Metre Rs. 184.08 Say 184.10


Composite rate per Rft Rs. 56.12 Say 56.10

Page 255
DESCRIPTION OF ITEM:

Item No. 74 Supply and erection of 25 mm (1"/dia) and one metre long lightning conduc
copper rod with 5 spikes on ball and base, etc., complete.

Detail Unit Rate (Metric System) per Job

Qty Rate Per Unit Amount (Rs.)

MATERIAL

Copper rod 1" dia (25 mm) = 1 metre


with 5 spikes on ball and base
1 Weight of rod 9.9 lbs
2 weight of ball 3.00 lbs
3 weight of base and spikes 1.00 lbs
13.90 lbs (13.90 lbs) 105.00 per kg 661.50
6.30 kg

Total 661.50
Contractor's Profit & Overh 20 Percent 132.30
Total 793.80

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Job Rs. 136.40 Say 136.40


Composite rate for Each Job Rs. 930.20 Say 930.20

Page 256
DESCRIPTION OF ITEM:

Item No. 75 Supply and erection of electric energy metre, including metre testing fee, e

(a) Single phase:

(i) 1 x 10 Amp 250 volts

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Energy metre 10 Amp. Single phase 250 Volts 1.00 No. 350.00 each 350.00
2 Testing Fee L.S 120.00

Total 470.00
Contractor's Profit & Overh 20 Percent 94.00
Total 564.00

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 56.10 Say 56.10


Composite rate for Each Rs. 620.10 Say 620.10

Page 257
DESCRIPTION OF ITEM:

Item No. 75 Supply and erection of electric energy metre, including metre testing fee, e

(a) Single phase:

(ii) 1 x 30 Amp 250 volts

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Energy metre 30 Amp. Single phase 250 Volts 1.00 No. 350.00 each 350.00
2 Testing Fee L.S 120.00

Total 470.00
Contractor's Profit & Overh 20 Percent 94.00
Total 564.00

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 56.10 Say 56.10


Composite rate for Each Rs. 620.10 Say 620.10

Page 258
DESCRIPTION OF ITEM:

Item No. 75 Supply and erection of electric energy metre, including metre testing fee, e

(b) Three phase, 4 wires

(i) 3 x 15 Amp. 400 volts

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Energy metre 3 x 15 Amp. Three phase 400 Volts 1.00 No. 1500.00 each 1500.00
2 Testing Fee L.S 240.00

Total 1740.00
Contractor's Profit & Overh 20 Percent 348.00
Total 2088.00

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 112.20 Say 112.20


Composite rate for Each Rs. 2200.20 Say 2200.20

Page 259
DESCRIPTION OF ITEM:

Item No. 75 Supply and erection of electric energy metre, including metre testing fee, e

(b) Three phase, 4 wires

(ii) 3 x 50 Amp. 400 volts

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Energy metre 3 x 50 Amp. Three phase 400 Volts 1.00 No. 1500.00 each 1500.00
2 Testing Fee L.S 240.00

Total 1740.00
Contractor's Profit & Overh 20 Percent 348.00
Total 2088.00

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 158.40 Say 158.40


Composite rate for Each Rs. 2246.40 Say 2246.40

Page 260
DESCRIPTION OF ITEM:

Item No. 75 Supply and erection of electric energy metre, including metre testing fee, e

(b) Three phase, 4 wires

(iii) 3 x 80 Amp. 400 volts

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Energy metre 3 x 80 Amp. Three phase 400 Volts 1.00 No. 1500.00 each 1500.00
2 Testing Fee L.S 240.00

Total 1740.00
Contractor's Profit & Overh 20 Percent 348.00
Total 2088.00

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10 Percent 24.00
Total 264.00
Contractor's Profit & Overh 20 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 158.40 Say 158.40


Composite rate for Each Rs. 2246.40 Say 2246.40

Page 261
DESCRIPTION OF ITEM:

Item No. 76 Rewinding of A.C ceiling fan, capacitor type, including cost of wire, leatheri
paper cotton tape, soldering, etc.

(i) 1200 mm (48") sweep, 275 - 300 RPM

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Leatheride paper L.S 10.00


1.02 kg
2 Copper wire No.32 SWG - 26 SWG (2.25 lbs) 105.00 per kg 107.10
3 Soldring and vanishing hoop wire No.3 Job 38.00
4 Deduction cost of 2¼ lbs (1.02 kg) copper wire old 2.25 lbs 88.00 per kg (-) 89.76
1.02 kg

Total 65.34
Contractor's Profit & Overh 20 Percent 13.07
Total 78.41

LABOUR (For 4 Nos.)

1 Electrician 1.50 No. 170.00 per day 255.00


2 Cooly (helper) 0.50 No. 140.00 per day 70.00

Total 325.00
Sundries 10 Percent 32.50
Total 357.50
Contractor's Profit & Overh 20 Percent 71.50
Total 429.00

ITEM RATES

Labour rate for Each Rs. 107.25 Say 107.25


Composite rate for Each Rs. 185.66 Say 185.65

Page 262
DESCRIPTION OF ITEM:

Item No. 76 Rewinding of A.C ceiling fan, capacitor type, including cost of
wire, leatheride paper cotton tape, soldering, etc.

(ii) 1400 mm (56") sweep, 250 - 275 RPM

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Leatheride paper and cotten tape Job 10.00


1.13 kg
2 Enemal wire No.26 SWG to 32 SWG (2.50 lbs) 250.00 per kg 282.50
3 Soldering and varnishing 1.00 No. 60.00 each 60.00
4 Loop wire 4 loop 3/0.029 (3/0.74 mm) 4.00 ft. 3.00 per Rft 12.00
5 Deduction cost of old material 2.50 lbs 88.00 per kg (-) 99.44
1.13 kg

Total 265.06
Contractor's Profit & Overh 20 Percent 53.01
Total 318.07

LABOUR (For 4 Nos.)

1 Electrician 1.50 No. 170.00 per day 255.00


2 Cooly (helper) 0.75 No. 140.00 per day 105.00

Total 360.00
Sundries 10 Percent 36.00
Total 396.00
Contractor's Profit & Overh 20 Percent 79.20
Total 475.20

ITEM RATES

Labour rate for Each Rs. 118.80 Say 118.80


Composite rate for Each Rs. 436.87 Say 436.85

Page 263
DESCRIPTION OF ITEM:

Item No. 77 Rewinding of A.C exhaust fan, including cost of wire,


leatheride paper, cotton tape, soldering, etc.

(i) 375 mm (15") sweep, and 1300 - 1500 RPM

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Leatheride paper and cotten tape Job 10.00


0.68 kg
2 Enamel wire No.26 SWG to 32 SWG (1.50 lbs) 250.00 per kg 170.00
3 Varnishing and soldering Job 48.00
4 Deduction cost of old material 1.50 lbs 88.00 per kg (-) 59.84
0.68 kg

Total 168.16
Contractor's Profit & Overh 20 Percent 33.63
Total 201.79

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 74.80 Say 74.80


Composite rate for Each Rs. 276.59 Say 276.60

Page 264
DESCRIPTION OF ITEM:

Item No. 77 Rewinding of A.C exhaust fan, including cost of wire,


leatheride paper, cotton tape, soldering, etc.

(ii) 450 mm (18") sweep, and 1300 - 1500 RPM

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Leatheride paper and cotten tape Job 10.00


0.79 kg
2 Enamel wire No.26 SWG to 32 SWG (1.75 lbs) 250.00 per kg 197.50
3 Varnishing and soldering Job 40.00
4 Loop wire 3/0.029" (3/0.74 mm) 4.00 ft. 3.00 per ft. 12.00
5 Deduction cost of old material 1.75 lbs 88.00 per kg (-) 69.52
0.79 kg

Total 189.98
Contractor's Profit & Overh 20 Percent 38.00
Total 227.98

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 74.80 Say 74.80


Composite rate for Each Rs. 302.78 Say 302.80

Page 265
DESCRIPTION OF ITEM:

Item No. 78 Rewinding of pedestal fan 600 mm (24") sweep, and 900 - 950
RPM, including wire, leatheride paper, cotton, tape, etc.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Leatheride paper and cotten tape Job 10.00


0.91 kg
2 Enamel wire No.26 SWG to 32 SWG (2.00 lbs) 250.00 per kg 227.50
3 Varnishing and soldering Job 52.00
4 Deduction cost of old material (2.00 lbs) 88.00 per lbs (-) 80.08
0.91 kg

Total 209.42
Contractor's Profit & Overh 20 Percent 41.88
Total 251.30

LABOUR (For 5 Nos.)

1 Electrician 2.00 No. 170.00 per day 340.00

Total 340.00
Sundries 10 Percent 34.00
Total 374.00
Contractor's Profit & Overh 20 Percent 74.80
Total 448.80

ITEM RATES

Labour rate for Each Rs. 89.76 Say 89.75


Composite rate for Each Rs. 341.06 Say 341.05

Page 266
DESCRIPTION OF ITEM:

Item No. 79 Supply and fitting of regulator nob with shaft and plate of
electric fan regulator.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Knob with shaff and plate 1.00 No. 50.00 each 50.00

Total 50.00
Contractor's Profit & Overh 20 Percent 10.00
Total 60.00

LABOUR (For 16 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 14.03 Say 14.05


Composite rate for Each Rs. 74.03 Say 74.05

Page 267
DESCRIPTION OF ITEM:

Item No. 80 Supply and fitting of capacitor 2.2 uf, for ceiling fans.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Capacitor 2.2 uf 1.00 No. 73.00 each 73.00

Total 73.00
Contractor's Profit & Overh 20 Percent 14.60
Total 87.60

LABOUR (For 20 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 11.22 Say 11.20


Composite rate for Each Rs. 98.82 Say 98.80

Page 268
DESCRIPTION OF ITEM:

Item No. 81 Supply and fitting of ball bearing of size 6201, 6202 or 6203, for ceiling fans

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Ball bearing size (6201, 6202 or 6203) 1.00 No. 50.00 each 50.00

Total 50.00
Contractor's Profit & Overh 20 Percent 10.00
Total 60.00

LABOUR (For 16 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 14.03 Say 14.05


Composite rate for Each Rs. 74.03 Say 74.05

Page 269
DESCRIPTION OF ITEM:

Item No. 82 Rewinding regulator of ceiling fan (1200/1400 mm) sweep, to control
3/4 speeds.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
0.18 kg
1 Enamel copper wire No.26 SWG to 32 SWG (0.403 lbs) 250.00 kg 45.00
2 Leathoride paper, cotten tape and vinishing L.S 10.00
3 Deduct cost of old material (0.403 lbs) 88.00 per kg (-) 15.84
0.18 kg
Total 39.16
Contractor's Profit & Overh 20 Percent 7.83
Total 46.99

LABOUR (For 8 Nos.)

1 Electrician 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10 Percent 17.00
Total 187.00
Contractor's Profit & Overh 20 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 28.05 Say 28.05


Composite rate for Each Rs. 75.04 Say 75.05

Page 270
DESCRIPTION OF ITEM:

Item No. 83 Erection of ceiling fan alongwith regulator (all sizes), including carriage
from local Railway Station/Store to site of work, electric wire/cable for
suspension rod and board connection, and cutting threading on the rod,
where necessary.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 PVC wire 3/0.029" 2.00 metre 5.12 per mtr. 10.24

Total 10.24
Contractor's Profit & Overh 20 Percent 2.05
Total 12.29

LABOUR (For 10 Nos.)

1 Carriage from stone to site L.S 80.00


2 Cutting & threading G.I pipe (22mm) dia 8.00 Nos. 7.53 each 60.23
3 Electrician 1.00 No. 170.00 per day 170.00
4 Cooly (helper) 1.00 No. 140.00 per day 140.00

Total 450.23
Sundries 10 Percent 45.02
Total 495.25
Contractor's Profit & Overh 20 Percent 99.05
Total 594.30

ITEM RATES

Labour rate for Each Rs. 59.43 Say 59.45


Composite rate for Each Rs. 71.72 Say 71.70

Page 271

Vous aimerez peut-être aussi