Vous êtes sur la page 1sur 9

WETAR PROJECT

WORKS UPDATE
STATUS in PRECENTAGE (%) Update
No. AREA DRAWING REF. WORKS DESCRIPTION MATERIA Remarks to date
DESIGN PRF WORK DATE
L
1 Lurang Curch Perimeter Fence
Lurang Foundation, Column, Steel Fence, Steel Gate 100 90 70 70 4-Feb-19 - Waiting Material Fence & Gate
2 Pipe Line Madhani & Water Tank New Camp Upgrade
Mining MMS-BTR-MHR-DWG-CS-131_0 Pipe Line 4km, Upgrade Pump 100 100 60 50 22-Jan-19 - Ready to connect WT Madhani
3 Relocation Fuel Pipe, Electric Cable, & Coreshed
Lower Section 40-48-XX-DWG-MECH-001 Fuel Pipe, Uderground Cable, Relocation Coreshed 40 40 0 0 25-Jan-19 - Support rigging to relocate CS
4 Pump Support Rais Up - SWP2
Mining Rais Up 2 meter Pump Pedestal Structure (HB 150) NA NA 100 0 19-Jan-19 - Material Ready
5 Jetty Extension
Jetty MMS-BTR-JTY-DWG-CS-001_0 Jetty Extension with 6 x 20" Container 100 100 70 10 4-Feb-19 - On progress fabricate container
6 Walkway for Temporary Haul Road
Camp Area MMS-BTR-MHR-DWG-CS-132 Concrete Bundwall, Base Course, Portable Bollard 80 0 0 0 23-Jan-19 - Submit work order form
7 Camp Upgrade WB & Beach House
Camp Area MMS-BTR-MBA-DWG-CS-200 WB 1,2,3,5,5 & 2 Block Beach House 100 80 30 10 4-Feb-19 - Waiting CEA from BTR
8 Box Culvert
Kelapa 3 MMS-BTR-MHR-DWG-CS-100_0 Concrete Slab, Wall, Roof, & Apron 100 100 100 100 3-Feb-19 - DONE
9 Security Post
Kampung Baru Refurbish Skid Security Post NA NA 100 100 30-Jan-19 - DONE
10 Water Tank Pad Relocation
Magazine MMS-BTR-MHR-DWG-CS-130_0 Prepare Pad, New Water Tank 20KL 100 100 80 80 19-Jan-19 - Waiting Material
11 Replace Steel Pipe with HDPE Pipe
Lerokis HDPE Pipe 110mm NA 100 100 70 4-Jan-19 - On progress
12 Water Fill
Lerokis Prepare Pad by Earthwork, Install Water Fill Set NA 100 100 0 19-Jan-19 - Waiting Pad
13 Office MIA
MIA MMS-BTR-MBA-DWG-CS-100_0 Building by Container 2", Light Steel & Kalsi 100 100 90 90 4-Jan-19 - Remaining AC & GPO
14 Water Tank Pad MIA
MIA MMS-BTR-MBA-DWG-CS-107_0 Water Tank 20 KL & 5KL, Water Fillter, Shelter 100 100 90 90 4-Feb-19 - Remaining pressure switch
15 Musholla & Toilet MIA
MIA MMS-BTR-MBA-DWG-CS-105_0 Building by Kalsi, Lightsteel & Toilet Container 100 100 100 60 1-Feb-19 - On progress
16 Genset Shelter
MIA MMS-BTR-MBA-DWG-CS-106_0 Shelter, Chainlink Fence, FuelTank Pad 100 100 90 90 31-Jan-19 - Fabricate support fuel tank
17 Soil Lab, Logistic & Warehouse
MIA MMS-BTR-MBA-DWG-CS-104_0 Slab, Cladding by light steel & Spandek 100 100 100 80 31-Jan-19 - On Progress
18 2 x Tower IT (MIA & Lerokis)
Lerokis MMS-BTR-MBA-DWG-CS-115_0 Foundation & Steel Tower with Wire Rope 100 100 90 70 30-Jan-19 - On Progress
19 Workshop
Crusher Area MMS-BTR-MBA-DWG-CS-101_1 Concrete Slab, 4xContainer 20", Igloo 100 100 100 30 4-Feb-19 - On Progress Concrete Slab
20 Washbay & Water Tank Pad
Crusher Area MMS-BTR-MBA-DWG-CS-112_0 Slab, Sedimen Trap, Steel Platform, 2xWT 20KL, Pump, Hose Reel 100 100 50 10 4-Feb-19 - On progress
21 Office & Workshop Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-125_1 4x Container 20" (2 from BTR), Frame Hoist Crane, roof spandex 100 100 80 0 25-Jan-19 - Ready to work
22 Genset Pad & Shelter (Agrreko)
Crusher Area 3 x 1250 KVA 50 0 0 0 25-Jan-19 - Ready to work
23 Musholla & Toilet Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-128 Building by Kalsi, Lightsteel & Toilet Container 100 100 80 0 25-Jan-19 - Ready to work
24 Oil Storage
Crusher Area MMS-BTR-MBA-DWG-CS-124_0 Concrete Pad, Cladding, Roof 100 100 100 0 20-Jan-19 - Prepare pad by Earthwork
25 Retaining Wall
Crusher Area MMS-BTR-CRH-DWG-CS-001 Concrete Retaining Wall 6,5m x 52m 80 40 0 0 5-Feb-19 - Finalize Design
26 WO - Refurbish Female Camp MQ-12
Camp Area MMS-BTR-WO-DWG-CS-004 Refurbish Wall, Roof, & Sanitary Fixtures 100 NA 20 0 2-Feb-19 - Waiting material
27 WO - Refurbish Beach House BH-5
Camp Area MMS-BTR-WO-DWG-CS-005 Refurbish Wall, Roof, & Sanitary Fixtures 100 NA 100 90 4-Feb-19 - Finishing
28 WO - Admin Office Toilet
Camp Area 70-73-01-DWG-CIV-00XX Building Toilet 3 x man, 1 x woman 100 NA 50 0 4-Feb-19 - Ready to work
0
puji

jenis
tumbuha
hewan

AREA
1 Lurang 10 10 AJ/FM
2 Mining 20 SRL/DM
3 Lower Section 30
4 Jetty 40
5 Camp Area 50
6 Kelapa 3 60
7 Kampung Baru 70
8 Magazine 80
9 MIA 90
10 Crusher Area 100
11 Lerokis NA
WETAR PROJECT
Grand Total & Control

WORKS REPORT - 30 JAN 2019 In Progress 0

No. AREA DRAWING REF. WORKS DESCRIPTION Remarks Completed 0


Total 0 #REF!
1 Lurang Curch Perimeter Fence
Lurang Finishing column - Waiting Material Fence & Gate
2 Pipe Line Madhani & Water Tank New Camp Upgrade
Mining MMS-BTR-MHR-DWG-CS-131_0 - - Ready to connect WT Madhani
3 Relocation Fuel Pipe, Electric Cable, & Coreshed
Lower Section - - Support rigging to relocate CS
4 Pump Support Rais Up - SWP2
Mining - - Material Ready
5 Jetty Extension
Jetty MMS-BTR-JTY-DWG-CS-001_0 Fabricate reinforcement 20" Container - On progress fabricate container
6 Walkway for Temporary Haul Road
Camp Area MMS-BTR-MHR-DWG-CS-132 - - Submit work order form
7 Camp Upgrade WB & Beach House
Camp Area MMS-BTR-MBA-DWG-CS-200 Finishing at BH5, Start refurbish at WB2 - Remaining PRF Beach House
8 Box Culvert
Kelapa 3 MMS-BTR-MHR-DWG-CS-100_0 Pouring cocrete roof (6,5 m3) - On Progress reinforcement
9 Security Post
Kampung Baru Install clear glass & plywood for window - Add clear glass
10 Water Tank Pad Relocation
Magazine MMS-BTR-MHR-DWG-CS-130_0 - - Waiting Material
11 Replace Steel Pipe with HDPE Pipe
Lerokis - - Ready to work
12 Water Fill
Lerokis - - Waiting Pad
13 Office MIA
MIA MMS-BTR-MBA-DWG-CS-100_0 Instal formwork and pouring concrete for open drainage - Remaining AC & GPO
14 Water Tank Pad MIA
MIA MMS-BTR-MBA-DWG-CS-107_0 Install Electric system - Remaining fitting
15 Musholla & Toilet MIA
MIA MMS-BTR-MBA-DWG-CS-105_0 Install wall, plumbing for ablution - On progress
16 Genset Shelter
MIA MMS-BTR-MBA-DWG-CS-106_0 - - Fabricate support fuel tank
17 Soil Lab, Logistic & Warehouse
MIA MMS-BTR-MBA-DWG-CS-104_0 - - On Progress
18 2 x Tower IT (MIA & Lerokis)
Lerokis MMS-BTR-MBA-DWG-CS-115_0 - - On Progress
19 Workshop
Crusher Area MMS-BTR-MBA-DWG-CS-101_1 Pouring concrete slab (15 m3) - On Progress Concrete Slab
20 Washbay & Water Tank Pad
Crusher Area MMS-BTR-MBA-DWG-CS-112_0 Install form work - On progress
21 Office & Workshop Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-125_1 - - Waiting layout approved
22 Genset Pad & Shelter (Agrreko)
Crusher Area - - Waiting layout approved
23 Musholla & Toilet Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-128 - - Waiting layout approved
24 Oil Storage
Crusher Area MMS-BTR-MBA-DWG-CS-124_0 - - Prepare pad
25 Retaining Wall
Crusher Area MMS-BTR-CRH-DWG-CS-001 - - Finalize Design
26 WO - Refurbish Female Camp & Beach House
Camp Area Install truss and wall frame, electric cable, plumbing at Female camp - On Proggress
WETAR PROJECT

WORKS REPORT - 31 JAN 2019


No. AREA DRAWING REF. WORKS DESCRIPTION Remarks

1 Lurang Curch Perimeter Fence


Lurang Finishing column - Waiting Material Fence & Gate
2 Pipe Line Madhani & Water Tank New Camp Upgrade
Mining MMS-BTR-MHR-DWG-CS-131_0 - - Ready to connect WT Madhani
3 Relocation Fuel Pipe, Electric Cable, & Coreshed
Lower Section - - Support rigging to relocate CS
4 Pump Support Rais Up - SWP2
Mining - - Material Ready
5 Jetty Extension
Jetty MMS-BTR-JTY-DWG-CS-001_0 Fabricate base plate for beam - On progress fabricate container
6 Walkway for Temporary Haul Road
Camp Area MMS-BTR-MHR-DWG-CS-132 - - Submit work order form
7 Camp Upgrade WB & Beach House
Camp Area MMS-BTR-MBA-DWG-CS-200 Finishing & electric work at BH5, disconnect power at WB 2 - Remaining PRF Beach House
8 Box Culvert
Kelapa 3 MMS-BTR-MHR-DWG-CS-100_0 Prepare formwork for wingwall - On Progress reinforcement
9 Security Post
Kampung Baru - - Add clear glass
10 Water Tank Pad Relocation
Magazine MMS-BTR-MHR-DWG-CS-130_0 - - Waiting Material
11 Replace Steel Pipe with HDPE Pipe
Lerokis - - Ready to work
12 Water Fill
Lerokis - - Waiting Pad
13 Office MIA
MIA MMS-BTR-MBA-DWG-CS-100_0 Instal formwork and pouring concrete for open drainage, install gpo electric - Remaining AC & GPO
14 Water Tank Pad MIA
MIA MMS-BTR-MBA-DWG-CS-107_0 Install Electric system - Remaining fitting
15 Musholla & Toilet MIA
MIA MMS-BTR-MBA-DWG-CS-105_0 Install wall, plumbing for ablution - On progress
16 Genset Shelter
MIA MMS-BTR-MBA-DWG-CS-106_0 - - Fabricate support fuel tank
17 Soil Lab, Logistic & Warehouse
MIA MMS-BTR-MBA-DWG-CS-104_0 - - On Progress
18 2 x Tower IT (MIA & Lerokis)
Lerokis MMS-BTR-MBA-DWG-CS-115_0 Install lightning protection - On Progress
19 Workshop
Crusher Area MMS-BTR-MBA-DWG-CS-101_1 Pouring concrete slab (15 m3) - On Progress Concrete Slab
20 Washbay & Water Tank Pad
Crusher Area MMS-BTR-MBA-DWG-CS-112_0 Install form work - On progress
21 Office & Workshop Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-125_1 - - Waiting layout approved
22 Genset Pad & Shelter (Agrreko)
Crusher Area - - Waiting layout approved
23 Musholla & Toilet Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-128 - - Waiting layout approved
24 Oil Storage
Crusher Area MMS-BTR-MBA-DWG-CS-124_0 - - Prepare pad
25 Retaining Wall
Crusher Area MMS-BTR-CRH-DWG-CS-001 - - Finalize Design
26 WO - Refurbish Female Camp
Camp Area Install electric cable, plumbing at Female camp - On Proggress
WETAR PROJECT

WORKS REPORT - 1 FEB 2019


No. AREA DRAWING REF. WORKS DESCRIPTION Remarks

1 Lurang Curch Perimeter Fence


Lurang Finishing column - Waiting Material Fence & Gate
2 Pipe Line Madhani & Water Tank New Camp Upgrade
Mining MMS-BTR-MHR-DWG-CS-131_0 - - Ready to connect WT Madhani
3 Relocation Fuel Pipe, Electric Cable, & Coreshed
Lower Section - - Support rigging to relocate CS
4 Pump Support Rais Up - SWP2
Mining - - Material Ready
5 Jetty Extension
Jetty MMS-BTR-JTY-DWG-CS-001_0 Fabricate base plate for beam - On progress fabricate container
6 Walkway for Temporary Haul Road
Camp Area MMS-BTR-MHR-DWG-CS-132 - - Submit work order form
7 Camp Upgrade WB & Beach House
Camp Area MMS-BTR-MBA-DWG-CS-200 Disconnect electric power, relocate bed & bunkbed at WB 2 - Remaining PRF Beach House
8 Box Culvert
Kelapa 3 MMS-BTR-MHR-DWG-CS-100_0 Prepare formwork for wingwall - On Progress reinforcement
9 Security Post
Kampung Baru - - Add clear glass
10 Water Tank Pad Relocation
Magazine MMS-BTR-MHR-DWG-CS-130_0 - - Waiting Material
11 Replace Steel Pipe with HDPE Pipe
Lerokis - - Ready to work
12 Water Fill
Lerokis - - Waiting Pad
13 Office MIA
MIA MMS-BTR-MBA-DWG-CS-100_0 Instal formwork and pouring concrete for open drainage, install gpo electric - Remaining AC & GPO
14 Water Tank Pad MIA
MIA MMS-BTR-MBA-DWG-CS-107_0 - - Remaining fitting
15 Musholla & Toilet MIA
MIA MMS-BTR-MBA-DWG-CS-105_0 Install kalsi for wall, instalation electric cable - On progress
16 Genset Shelter
MIA MMS-BTR-MBA-DWG-CS-106_0 - - Fabricate support fuel tank
17 Soil Lab, Logistic & Warehouse
MIA MMS-BTR-MBA-DWG-CS-104_0 - - On Progress
18 2 x Tower IT (MIA & Lerokis)
Lerokis MMS-BTR-MBA-DWG-CS-115_0 - - On Progress
19 Workshop
Crusher Area MMS-BTR-MBA-DWG-CS-101_1 Fabricate support structure - On Progress Concrete Slab
20 Washbay & Water Tank Pad
Crusher Area MMS-BTR-MBA-DWG-CS-112_0 Install form work & slab reinforcement - On progress
21 Office & Workshop Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-125_1 - - Waiting layout approved
22 Genset Pad & Shelter (Agrreko)
Crusher Area - - Waiting layout approved
23 Musholla & Toilet Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-128 - - Waiting layout approved
24 Oil Storage
Crusher Area MMS-BTR-MBA-DWG-CS-124_0 - - Prepare pad
25 Retaining Wall
Crusher Area MMS-BTR-CRH-DWG-CS-001 - - Finalize Design
26 WO - Refurbish Female Camp
Camp Area Install electric cable, plumbing, truss and wall frame at Female camp - On Proggress
WETAR PROJECT

WORKS REPORT - 2 FEB 2019


No. AREA DRAWING REF. WORKS DESCRIPTION Remarks

1 Lurang Curch Perimeter Fence


Lurang Finishing column - Waiting Material Fence & Gate
2 Pipe Line Madhani & Water Tank New Camp Upgrade
Mining MMS-BTR-MHR-DWG-CS-131_0 - - Ready to connect WT Madhani
3 Relocation Fuel Pipe, Electric Cable, & Coreshed
Lower Section - - Support rigging to relocate CS
4 Pump Support Rais Up - SWP2
Mining - - Material Ready
5 Jetty Extension
Jetty MMS-BTR-JTY-DWG-CS-001_0 Fabricate base plate for beam - On progress fabricate container
6 Walkway for Temporary Haul Road
Camp Area MMS-BTR-MHR-DWG-CS-132 - - Submit work order form
7 Camp Upgrade WB & Beach House
Camp Area MMS-BTR-MBA-DWG-CS-200 Electric work, repair ceiling, replace vinil & install ceramics WB 2 - Remaining PRF Beach House
8 Box Culvert
Kelapa 3 MMS-BTR-MHR-DWG-CS-100_0 Prepare to pouring concrete wingwall - On Progress
9 Security Post
Kampung Baru - - Add clear glass
10 Water Tank Pad Relocation
Magazine MMS-BTR-MHR-DWG-CS-130_0 - - Waiting Material
11 Replace Steel Pipe with HDPE Pipe
Lerokis Prepare material - Ready to work
12 Water Fill
Lerokis - - Waiting Pad
13 Office MIA
MIA MMS-BTR-MBA-DWG-CS-100_0 On progress open drainage, install furniture - Remaining AC & GPO
14 Water Tank Pad MIA
MIA MMS-BTR-MBA-DWG-CS-107_0 Electric work - Remaining fitting
15 Musholla & Toilet MIA
MIA MMS-BTR-MBA-DWG-CS-105_0 Install kalsi for wall, instalation electric cable, & install ceramics - On progress
16 Genset Shelter
MIA MMS-BTR-MBA-DWG-CS-106_0 - - Fabricate support fuel tank
17 Soil Lab, Logistic & Warehouse
MIA MMS-BTR-MBA-DWG-CS-104_0 Install exhaust & electric fitting - On Progress
18 2 x Tower IT (MIA & Lerokis)
Lerokis MMS-BTR-MBA-DWG-CS-115_0 - - On Progress
19 Workshop
Crusher Area MMS-BTR-MBA-DWG-CS-101_1 Fabricate support structure - On Progress Concrete Slab
20 Washbay & Water Tank Pad
Crusher Area MMS-BTR-MBA-DWG-CS-112_0 Install form work & slab reinforcement - On progress
21 Office & Workshop Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-125_1 - - Waiting layout approved
22 Genset Pad & Shelter (Agrreko)
Crusher Area - - Waiting layout approved
23 Musholla & Toilet Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-128 - - Waiting layout approved
24 Oil Storage
Crusher Area MMS-BTR-MBA-DWG-CS-124_0 - - Prepare pad
25 Retaining Wall
Crusher Area MMS-BTR-CRH-DWG-CS-001 - - Finalize Design
26 WO - Refurbish Female Camp
Camp Area Install electric cable, plumbing at MQ12; finishing at BH5 - On Proggress
WETAR PROJECT

WORKS REPORT - 4 FEB 2019


No. AREA DRAWING REF. WORKS DESCRIPTION Remarks

1 Lurang Curch Perimeter Fence


Lurang Finishing column - Waiting Material Fence & Gate
2 Pipe Line Madhani & Water Tank New Camp Upgrade
Mining MMS-BTR-MHR-DWG-CS-131_0 - - Ready to connect WT Madhani
3 Relocation Fuel Pipe, Electric Cable, & Coreshed
Lower Section - - Support rigging to relocate CS
4 Pump Support Rais Up - SWP2
Mining - - Material Ready
5 Jetty Extension
Jetty MMS-BTR-JTY-DWG-CS-001_0 Fabricate base plate for beam - On progress fabricate container
6 Walkway for Temporary Haul Road
Camp Area MMS-BTR-MHR-DWG-CS-132 - - Submit work order form
7 Camp Upgrade WB & Beach House
Camp Area MMS-BTR-MBA-DWG-CS-200 Electric work, repair ceiling, replace vinil & install ceramics WB 2 - Remaining PRF Beach House
8 Box Culvert
Kelapa 3 MMS-BTR-MHR-DWG-CS-100_0 Pouring concrete wingwall - On Progress
9 Security Post
Kampung Baru - - Add clear glass
10 Water Tank Pad Relocation
Magazine MMS-BTR-MHR-DWG-CS-130_0 - - Waiting Material
11 Replace Steel Pipe with HDPE Pipe
Lerokis Prepare material - Ready to work
12 Water Fill
Lerokis - - Waiting Pad
13 Office MIA
MIA MMS-BTR-MBA-DWG-CS-100_0 On progress open drainage - Remaining AC & GPO
14 Water Tank Pad MIA
MIA MMS-BTR-MBA-DWG-CS-107_0 - - Remaining fitting
15 Musholla & Toilet MIA
MIA MMS-BTR-MBA-DWG-CS-105_0 Install kalsi for wall, instalation electric cable, & install ceramics - On progress
16 Genset Shelter
MIA MMS-BTR-MBA-DWG-CS-106_0 - - Fabricate support fuel tank
17 Soil Lab, Logistic & Warehouse
MIA MMS-BTR-MBA-DWG-CS-104_0 Install electric fitting - On Progress
18 2 x Tower IT (MIA & Lerokis)
Lerokis MMS-BTR-MBA-DWG-CS-115_0 - - On Progress
19 Workshop
Crusher Area MMS-BTR-MBA-DWG-CS-101_1 Fabricate support structure, pouring concrete slab - On Progress Concrete Slab
20 Washbay & Water Tank Pad
Crusher Area MMS-BTR-MBA-DWG-CS-112_0 Install slab reinforcement - On progress
21 Office & Workshop Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-125_1 - - Waiting layout approved
22 Genset Pad & Shelter (Agrreko)
Crusher Area - - Waiting layout approved
23 Musholla & Toilet Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-128 - - Waiting layout approved
24 Oil Storage
Crusher Area MMS-BTR-MBA-DWG-CS-124_0 - - Prepare pad
25 Retaining Wall
Crusher Area MMS-BTR-CRH-DWG-CS-001 - - Finalize Design
26 WO - Refurbish Female Camp
Camp Area Finishing at BH5 - On Proggress
WETAR PROJECT

WORKS REPORT - 5 FEB 2019


No. AREA DRAWING REF. WORKS DESCRIPTION Remarks

1 Lurang Curch Perimeter Fence


Lurang Finishing - Waiting Material Fence & Gate
2 Pipe Line Madhani & Water Tank New Camp Upgrade
Mining MMS-BTR-MHR-DWG-CS-131_0 Fabricate fitting - Ready to connect WT Madhani
3 Relocation Fuel Pipe, Electric Cable, & Coreshed
Lower Section - - Support rigging to relocate CS
4 Pump Support Rais Up - SWP2
Mining - - Material Ready
5 Jetty Extension
Jetty MMS-BTR-JTY-DWG-CS-001_0 Install base plate for beam - On progress fabricate container
6 Walkway for Temporary Haul Road
Camp Area MMS-BTR-MHR-DWG-CS-132 - - Submit work order form
7 Camp Upgrade WB & Beach House
Camp Area MMS-BTR-MBA-DWG-CS-200 Electric work, repair ceiling, replace vinil & install ceramics WB 2 - Remaining PRF Beach House
8 Box Culvert
Kelapa 3 MMS-BTR-MHR-DWG-CS-100_0 Take off form work - On Progress
9 Security Post
Kampung Baru - - DONE
10 Water Tank Pad Relocation
Magazine MMS-BTR-MHR-DWG-CS-130_0 - - Waiting Material
11 Replace Steel Pipe with HDPE Pipe
Lerokis Prepare material - Ready to work
12 Water Fill
Lerokis - - Waiting Pad
13 Office MIA
MIA MMS-BTR-MBA-DWG-CS-100_0 On progress open drainage - Remaining AC & GPO
14 Water Tank Pad MIA
MIA MMS-BTR-MBA-DWG-CS-107_0 Install elecric system - Remaining fitting
15 Musholla & Toilet MIA
MIA MMS-BTR-MBA-DWG-CS-105_0 Install kalsi for wall, ceiling frame , electric cable - On progress
16 Genset Shelter
MIA MMS-BTR-MBA-DWG-CS-106_0 - - Fabricate support fuel tank
17 Soil Lab, Logistic & Warehouse
MIA MMS-BTR-MBA-DWG-CS-104_0 Install electric fitting - On Progress
18 2 x Tower IT (MIA & Lerokis)
Lerokis MMS-BTR-MBA-DWG-CS-115_0 - - On Progress
19 Workshop
Crusher Area MMS-BTR-MBA-DWG-CS-101_1 Fabricate support structure, install slab reinforement - On Progress Concrete Slab
20 Washbay & Water Tank Pad
Crusher Area MMS-BTR-MBA-DWG-CS-112_0 Install slab reinforcement - On progress
21 Office & Workshop Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-125_1 - - Waiting layout approved
22 Genset Pad & Shelter (Agrreko)
Crusher Area - - Waiting layout approved
23 Musholla & Toilet Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-128 - - Waiting layout approved
24 Oil Storage
Crusher Area MMS-BTR-MBA-DWG-CS-124_0 - - Prepare pad
25 Retaining Wall
Crusher Area MMS-BTR-CRH-DWG-CS-001 - - Finalize Design
26 WO - Refurbish Female Camp
Camp Area Finishing at BH5 - On Proggress
WETAR PROJECT

WORKS REPORT - 7 FEB 2019


No. AREA DRAWING REF. WORKS DESCRIPTION Remarks

1 Lurang Curch Perimeter Fence


Lurang Finishing (last day) - Waiting Material Fence & Gate
2 Pipe Line Madhani & Water Tank New Camp Upgrade
Mining MMS-BTR-MHR-DWG-CS-131_0 - - Ready to connect WT Madhani
3 Relocation Fuel Pipe, Electric Cable, & Coreshed
Lower Section - - Support rigging to relocate CS
4 Pump Support Rais Up - SWP2
Mining - - Material Ready
5 Jetty Extension
Jetty MMS-BTR-JTY-DWG-CS-001_0 Install base plate for beam, coating - On progress fabricate container
6 Walkway for Temporary Haul Road
Camp Area MMS-BTR-MHR-DWG-CS-132 - - Submit work order form
7 Camp Upgrade WB & Beach House
Camp Area MMS-BTR-MBA-DWG-CS-200 Electric work, repair ceiling, install ceramics, install door WB 2 - Remaining PRF Beach House
8 Box Culvert
Kelapa 3 MMS-BTR-MHR-DWG-CS-100_0 - - On Progress
9 Security Post
Kampung Baru - - DONE
10 Water Tank Pad Relocation
Magazine MMS-BTR-MHR-DWG-CS-130_0 - - Waiting Material
11 Replace Steel Pipe with HDPE Pipe
Lerokis Connect pipe at Magazine - Blue WT - Ready to work
12 Water Fill
Lerokis - - Waiting Pad
13 Office MIA
MIA MMS-BTR-MBA-DWG-CS-100_0 On progress open drainage, install furniture - Remaining AC & GPO
14 Water Tank Pad MIA
MIA MMS-BTR-MBA-DWG-CS-107_0 - - Remaining fitting
15 Musholla & Toilet MIA
MIA MMS-BTR-MBA-DWG-CS-105_0 Install ceiling - On progress
16 Genset Shelter
MIA MMS-BTR-MBA-DWG-CS-106_0 - - Fabricate support fuel tank
17 Soil Lab, Logistic & Warehouse
MIA MMS-BTR-MBA-DWG-CS-104_0 - - On Progress
18 2 x Tower IT (MIA & Lerokis)
Lerokis MMS-BTR-MBA-DWG-CS-115_0 - - On Progress
19 Workshop
Crusher Area MMS-BTR-MBA-DWG-CS-101_1 Fabricate support structure, install slab reinforement - On Progress Concrete Slab
20 Washbay & Water Tank Pad
Crusher Area MMS-BTR-MBA-DWG-CS-112_0 Install slab reinforcement - On progress
21 Office & Workshop Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-125_1 - - Waiting layout approved
22 Genset Pad & Shelter (Agrreko)
Crusher Area - - Waiting layout approved
23 Musholla & Toilet Crusher
Crusher Area MMS-BTR-MBA-DWG-CS-128 - - Waiting layout approved
24 Oil Storage
Crusher Area MMS-BTR-MBA-DWG-CS-124_0 - - Prepare pad
25 Retaining Wall
Crusher Area MMS-BTR-CRH-DWG-CS-001 - - Finalize Design
26 WO - Refurbish Female Camp
Camp Area Finishing at BH5 - On Proggress