Académique Documents
Professionnel Documents
Culture Documents
UNIVERSITAS INDONESIA
FACULTY OF ENGINEERING
CIVIL ENGINEERING DEPARTMENT
DEPOK
AUGUST 2017
Universitas Indonesia
ii
Universitas Indonesia
iii
Signature :
Date : 18th August 2017
Signature :
Tanggal : 18th August 2017
Universitas Indonesia
iv
PREFACE
Praise to God Almighty, for His blessings and His mercy, that we were given a
chance to experience an internship at PT PP (Persero), and finish this report. This
final report is written in order to meet one of the requirements to complete the
Internship subject at Civil Engineering, Faculty of Engineering, Universitas
Indonesia and to achieve a degree in Engineering as well. We are aware that without
the help and guidance of our supervisor and several parties, it will not be an easy
task to complete this final report. That being said, we would like to give our humble
gratitude for:
(1) Ayomi Dita Rarasati, S.T, M.T, PhD, as our supervisor whom has given us the
pleasure of her time, work, and thoughts in guiding us in our Internship and
our Internship Final Report.
(2) PT PP (Persero), as the company whom we had the pleasure with in
welcoming us as their interns in their project as well as providing datas that
are needed in this report.
(3) Mr. Yadi Triyadi and Friends, as construction manager and supervisors whom
manages the associated project as well as guiding us throughout our internship.
(4) Writers’ parents, whom have provided their moral support and prayers.
(5) Friends, whom we have shared knowledge with regarding our project.
All in all, we would like to pray to God that He would bless all parties that has
helped us in completing this report.
Universitas Indonesia
v
ABSTRACT
This final report is written for the purpose of writing and to describe our
knowledge in which we have obtained during our internship period. This
knowledge is crucial for students as students can know what can be done and
what is being done by civil engineers from the contractor’s perspective. Where
majority of the activities done in actual work environment differs significantly
than what we had learned in in-class learning session in Universitas Indonesia.
The purpose of this final report is to give a different perspective on components
that are being done and its application in the real world in construction projects,
specifically Transmart Depok Project. The scope of this report include Methods of
Contruction, Project Management, Health and Safety Environment Protection,
Project Resources and Project Problem .
Keywords :
Methods of Contruction, Project Management, Health and Safety Environment
Protection, Project Tools & Resources and Project Problem .
Universitas Indonesia
vi
TABLE OF CONTENT
Universitas Indonesia
vii
Universitas Indonesia
viii
FIGURE LIST
Universitas Indonesia
ix
Universitas Indonesia
x
TABLE LIST
Universitas Indonesia
1
CHAPTER 1
PREFACE
1.1 Background
Indonesia is currently pursuing the high standard of education in accordance of time and
technology. To achieve this standard, students that are currently pursuing the undergraduate
studies and graduate studies are essential to experience the field of work before graduated.
However, the quality parameters are not limited to ingenuity in science and theory, but also
includes the ability to apply the theory and knowledge to the field. Giving the chance to observe
and discover real life work activities will accommodate students about the application of
knowledge that was taught in the institution. The working experience will help the students to be
more prepared in encountering the work field in the future.
In Civil Engineering Department, Universitas Indonesia, the students are given the
chance to experience the work field through Internship subject. The Internship subject one of the
requirements to achieve the bachelor’s degree in engineering. It is designed especially for students
in final academic years, in which the students are already stuffed with abounding knowledge of
civil engineering science. Consequently, learning the Internship subject in the final years aims to
provide general ideas before finally plunged in the work specifically in civil engineering fields.
Civil engineering is the study of every aspect of human infrastructure that defines the
modern civilization. The civil engineering field is related to the design, construction and
maintenance of physical buildings and environments, such as including roads, bridges, canals,
dams and buildings. The study of Civil Engineering prepares students to become planners,
consultants, designers, constructors and managers of the civil engineering work area.
The insights from the Internship are expected to helps the students prepare the knowledge
in regard to the application of theory in the field. Learning the theory of civil engineering science
is not enough for a student to fully understand the concept of civil engineering. Experience through
the work field is necessary in providing general ideas in civil engineering work as well as
enhancing the skill for students to work in civil engineering field.
Universitas Indonesia
2
Universitas Indonesia
3
Universitas Indonesia
4
In this chapter five it will explain every kind of effort that do by the contractor side to
ensure the safety of the worker, including the rights and responsibility, and what the risk
that do for keeping the safety of the worker.
.
f) Chapter 6-Conclusion
In this final chapter, the contain will be conclusion that obtain from the observation the
project location also some suggestion that can be give for development activities of
internship program or to implement in the next project.
Universitas Indonesia
5
CHAPTER 2
GENERAL VIEW OF THE PROJECT
Universitas Indonesia
6
TransMart Depok project location map can be seen in Figure 2.1 and Floor-plan of the
project can be seen in Figure 2.3, until Figure 2.6
Universitas Indonesia
7
Universitas Indonesia
8
Universitas Indonesia
9
Universitas Indonesia
10
Universitas Indonesia
11
Universitas Indonesia
12
Universitas Indonesia
13
Universitas Indonesia
14
Universitas Indonesia
15
Universitas Indonesia
16
Universitas Indonesia
17
Universitas Indonesia
18
6. Height of Building : 28 m
7. Structural Material : Reinforced Concrete
8. Reinforced Steel Material : Deform Steel
9. Foundation Type : Pile Foundation
10. Project Boundaries :
• North : Jalan Dewi Sartika and Street Stores
• South : Settlements
• East : Settlements
• West : Settlements
11. Structure Material :
1) Concrete
• Basement 3 Floor : K-350
• Plate, Beam, Column : K-300
• Stairs, Ramp : K-300
• Test Pile : K-300
• Bored Pile : K-300
• Diaphragm Wall : K-300
2) Steel
• Plate, Beam, Column : BJTS 40, fy 400 Mpa
• Stairs, Ramp : BJTS 40, fy 400 Mpa
• Diaphragm Wall : BJTS 40, Fy 400 Mpa
• Bolt : ASTM A-325F (HTB)
• Welding Electrodes : E-70xx
3) Reinforced Steel
• Deformed : fy = 400 kg/cm2
• Plain : fy = 300 kg/cm2
4) Formwork Unloading
• Side Beam, Wall : 12 hours
• Unloaded Column : 12 hours
Universitas Indonesia
19
• Plate : 7 days
• Beam (without cons. load) : 7 days
• Scaffolding around beam : 7 days
• Scaffolding beam and slab : 14 days
• Scaffolding Cantilever : 21 days
Universitas Indonesia
20
Universitas Indonesia
20
CHAPTER III
CONSTRUCTION METHOD
3.1 INTRODUCTION
This supermarket is designed with 8 stories with 3 basement below surface and the
average height of each story is thereabout 3 meters in each basement for ground floor
is 5 meters, mezzanine 2.5 meters, first and second floors is 5 meters and third which
is the top floor is 17.5 meters. For the top floor the roof is precast that is made by steel,
based on this project plan top floor will be used for playground such as rollercoaster.
However rest of the building use concrete material for structural. In internship process,
our teams came at field project in Transmart Supermarket Project on column works at
the first floor level. At this level, the column has been distinguished into 5 type which
are c01(Red Circle), c02b(Orange Circle), c05(Blue Circle), c04(Red Square),
c05a(Green Circle). every type of column of this level has different dimension, this
difference are made because of the consultant may have to considered regarding to the
load above these structure, more larger dimension more strength to retain load above.
On figure of floor plan for first floor with column plan to indicate where columns are
plotted.
Universitas Indonesia
21
These circles and square on the picture are indicate where the columns are
plotted. With this floor plan the contractor will know which column they in progress.
Detail of each column should be drawn in the beginning of construction project from
materials that are going to use for framework and dimension. The example of column
detail where were in progress while our teams arrived on field project:
Universitas Indonesia
22
Universitas Indonesia
23
Universitas Indonesia
24
Universitas Indonesia
25
In accordance with figure 2 and 3 this drawing explain that C01 Column dimension which
has 3.9 meters with covered by gypsum at the outer layer of column but at the top of column they
use plywood since it will be connected to the beam, slab and column above this floor.
Column width : 70 cm
Every construction work process particularly in structural work, each process has it is own
standards as a reference to ensure quality of work achieve satisfaction that are being produced. In
this project, Transmart Depok Supermarket project main contractor is PT. PP (Persero) that has a
position to carry out, maintain and control all construction process quality by labors such as; form
work installation, concrete casting, reinforcement bars and work methods. Furthermore, the
contractor also re – check material to make concrete by slump test, The last jobs is control
procurement and delivery of materials that are going to use for construction process. Whole part
of contractor jobs is according to the standards issued by PT. Catur Inti Dinamika as the structural
consultant of the project. However, PT. Gratama Consultant as the construction management
consultant, works to control and make sure that whole job description and tasks given to the main
contractor. For the last is Architecture, MEP, Lightning, Interior and Landscape consultant are
handle by PT. Garis Rancang Bangun that works to ensure all job description and task that given
to the PT. PP (Persero).
Universitas Indonesia
26
In this section can be started while sub – structure components (excavation, foundation,
ground anchor, and retaining wall) have been finished where it used to support the main structure
or facilitate the labors in construction, and the contractor will continue then to build the structure.
Structural works includes ramp works, emergency stairs, column, beam, and slab. However, our
team started internship on column beam and slab work at the basement second level which is the
sub – structural work had been finished while team started internship. In Transmart Depok
Supermarket project, it has some typical at some floors such as at the top floor, the column and
Universitas Indonesia
27
beam are using steel structure with I section. Then at basement (1, 2 and 3) and ground floor have
ramp whereas entrance for cars to parking lots. Furthermore job sequence for basement (1, 2, and
3), ground floor, mezzanine floor, first floor and second floor start from column works, followed
by beam works and last in slab works, those works has the same sequence which should be installed
form work, reinforced steel bar fabrication and installation, ramp works, emergency stairs and last
is finished with concrete casting and curing. In this section, it will elaborate the details of each
structural works for every single floor since this project has several typical.
Column is used primarily to hold axial compressive load from the self – weight of the
building structure. This structural components is a support that will distribute the load and lateral
(vertical) force to the foundation. The stiffness of column will determine the magnitude of the
lateral force retained by that column. The dimension of column is depending on the distribution of
loads that it sustain. Usually column distinguished into two shape which are four square and round
columns. Rectangular (square) shape column is commonly used since the design and
manufacturing process is simple and easy to apply in project and in this project they use rectangular
as well. In this project the columns are separated into precast and cast – in situ, for third basement
until second floor used cast – in situ. However, on the top floor they use precast steel column with
I section which stand for make the construction quicker and efficient.
In this section, the report will discuss more detail regarding to the methods used in column in the
Transmart Depok Supermarket project, here are the stages of construction methods includes:
a. Marking
In order to determine columns location, the engineering make measurement and
mapping of the project. Marking points or lines are used as a basis to determining the
location of the column formwork and reinforcement. Moreover, the determination of the
location of column itself are done by using Theodolite tool. This action is continuously
occur in column construction from the bottom to the top of structure.
Column position should be centric and uses limitation of design tolerance according
to the previous floor since the shape of this building is not really complicated hence the
position will be uniformed. Therefore, checking is needed to prevent any instance of tilting.
Universitas Indonesia
28
Reference points can be applied to maintain centricity of each column in every floor.
Additionally, it can be considered as the column layout and utilize it as a guide pole for
other columns by following distances that have been determined in the planning. The
checking process is done by placing a theodolite or a laser equipment tool at the marking
point then checking the straightness column.
b. Reinforced steel bars fabrication
In order to make stronger concrete, it needs steel bars to retain any external loads. The
column consist of main reinforced bars and shear reinforced bars. The main reinforced bars
functions to resist moment and force, shear reinforced bars are used to hold shear force.
Reinforced steel bars itself has two common types such as threaded steel bars and
unthreaded steel bars. Threaded steel is used as main reinforced bars of the concrete
structure. Unthreaded steel is usually used for binding the threaded steel bars when it is
making column it acts shear reinforced bars.
Diameter : 22 meters
Length : 12 meters
Universitas Indonesia
29
Shear bars are made using a cutting and bending machine, which then are installed to
the cut main reinforced bars by binding it with steel wires. After the bars are formed,
concrete blocks are plugged around to control thickness of cover concrete. In order to retain
lateral force, need to install stirrup for column with the distance is 10cm for each stirrup.
c. Installation of reinforcement steel bars
The column reinforcement bars installation are done by binding them with steel wires
in between the main reinforcement and distribution bars that has been installed on previous
floor column. The reinforcement steel bars that has been made by the labors on the ground
are lifted and dropped at the installation location using a lifted tower crane by the operator.
Afterwards the reinforcement column are connected to the overlapping part using a steel
wire.
Throughout dropping process of the reinforcement bars to existing reinforcement
column, the labors manually straighten up the reinforcing connection in order to achieve
perfection of accuracy in measurement while concrete casting.
After the reinforced steel bars are connected to reinforcement columns, the labors
justify shear reinforcement bars in accordance to the gap specification. Afterwards, the
reinforcement bar columns are tightened and supported by ropes before placing the
formwork to prevent bending and while preparing to install formwork, the surveyor check
the elevation and straightness of column.
d. Formwork and scaffolding
Before proceed to the concrete casting, it need to build or plot the case to shape the
concrete into rectangular or round and it called as formwork. In this project, it used
rectangular shape therefore the contactor have to buy rectangular formwork by labors. This
formworks are made by plywood phenol with thickness of 18 mm supported by steel. This
tool can be used for seven to nine times before the change of plywood is necessary or while
some cases like cracking on the plywood. The height of the formwork is 5 meters for each
formwork set.
Universitas Indonesia
30
Universitas Indonesia
31
e. Concrete Casting
The next steps is concrete casting inside formwork. This action usually occurs at
midnight since this neighbor has terrific congestion at day. In Transmart Depok
Supermarket project use the quality of concrete column is K 300 for all column and for the
slump test 14±2 cm. Before casting, Quality Control (QC) surveyor and construction
manager must evaluate specification of column such as elevation, straightness, and gap in
between bars and concrete cover. For concrete design, this project chemical admixture is
Waterproof Integral to resist the water come in to column.
During concrete casting process, weather needs to be considered in order to maintain
the quality of concrete. Concrete casting cannot be done during rain and at day because
concrete tend to overheat while the intensity of heat exceed the concrete limitation
especially in Depok that has high temperature at day. At midnight, trucks usually came 4
to 5 every concrete casting but it is only first truck that has to do slump test. The samples
are taken 4 and it will bring by surveyor to the nearest lab but in this project the samples
will investigate in Trisakti University Civil Engineering Laboratory. As mention above, 4
samples will investigate in separate time for the first sample will investigate at first day,
second sample at seventh day, third at fourteenth day, and fourth at twenty-eighth day.
Actually the sample should be investigated for every truck but the engineering said that it
depends on request from the owner.
Afterwards pouring adhesive chemical mixture to connect existing concrete with new
concrete. This adhesive chemical mixture is used to improve bonding of existing with new
concrete. To cast columns, Tremie pipe should be plot at the top of the formwork. The
internal concrete vibrator should be not exceed 2 meter above the formwork since if it is
more than that the mixture will be ruined, if the consistency of the concrete is low do not
use water since it also mess up the mixture and to deal with it the labors are allowed to use
external vibrator.
f. Formwork Dismantling
The column formwork will be released 12 hours after casted. Steps for dismantling
process is started by releasing screws. While removing screws and side braces, column
formwork has been tied with steel chain of tower crane to prevent formwork collapse. After
Universitas Indonesia
32
finishing dismantled, the tower crane move formwork to other side and labors prepare for
the next column.
3.4.2 Beam and Slab Work (All Floors except 3th Floor)
In order to resist vertical loads, shear force and bending moment, structural member that
fit to that issues is beam. Transmart Depok Supermarket project beams are made by reinforced
concrete. These beams are with a normal reinforced concrete tensile strength due to the addition
of main or primary reinforcement and shear reinforcement. However for slabs, it also resist vertical
load, shear force and bending moment, the difference is it has larger area and volume then beam.
This section will discuss further in detail of construction method beams and slab work in Transmart
Depok Supermarket project. The stages of construction methods includes:
Universitas Indonesia
33
Side Stopper
Universitas Indonesia
34
Tembereng
Vertical
Post
Girder
U-Head
Figure 3.4.2.2 Concrete casting bottom side
Source: Writer’s Documentation 2017
Universitas Indonesia
35
relat pipe at upper part. Finished the arrangement of reinforcement bars for slab and beam,
the bars are connected each other tied by tire wire.
c. Concrete casting
After finishing formwork and reinforcement bars, move to the next step is concrete
casting. Basically it has the same methods with the column section that Quality Control
supervisor check the specification of beam and slab such as dimension of beam, spacing
and size of steel following technical drawing that given by consultant and QC need to ask
4 samples to Adhimix that used for slump test. Those 4 samples used for first day, seventh
day, fourteenth day, and twenty-eighth day however the samples only need for one truck
in concrete casting process according to owner suggestion. The slump concrete
requirement for beam and slab is 12 ± 2 cm with the quality of concrete is K – 300 and
especially for basement 3 it has K – 350 since it should be strong enough to retain loads
above it. The slump test has lower than column because beam has less time consuming
until it casted, more slump easier to set the shape but it takes longer to be casted. In order
Universitas Indonesia
36
to pouring the concrete into beam and slab, is not allowed to pour exceed 2 meters from
the edge of Bucket since it will ruined the mixture of concrete design and if the concrete is
a little bit wet or dry do not add more water just use internal concrete vibrator. Afterwards,
close the concrete by formwork and leave it until 14 days.
Universitas Indonesia
37
cause cracks to the concrete surface. Setting time is a period of time when the concrete
reaches maximum strength. In slab and beam work, curing is done by spraying water
frequently to keep concrete wet in 10 until 12 hours in seven days and to avoiding directly
heat from the sun, the engineers wear gunny sack on the floor. Another method is by closing
surface of slab by using a wet gunny sack to prevent evaporation.
e. Formwork Dismantling
Formwork releasing cannot be done immediately after the concrete is cast. However,
beams and slabs will be loaded soon because in order to level up the building, the worker
will put another formwork on the top of beams and slab casted, therefore, the formwork
stay longer in order to get the maximum strength of beams and slabs which will take 14
days.
In Transmart Depok Supermarket Project, the emergency staircase type that are built is
Half Turn stairs with 30° of gradient. This emergency staircase type is the most common use for
build staircase since it can be constructed within the confined vertical stair well and this half turn
stairs can be easier to fit into any kind of architectural plan. The emergency staircases are placed
in the edge of each floors.
The material that are used for emergency staircase is concrete cast – in place or commonly
called as in – situ RC stair. The decision engineers to use RC stairs because it will maintain it is
strength and integrity for a reasonable period during an outbreak of fire, it is non – combustible,
stronger and hardwearing. This concrete staircase has some typical such as inclined slab stair,
cranked slab stair, string beam stair, and cantilever stair. In this supermarket project, they used
Universitas Indonesia
38
cranked slab stairs. These stairs are very often used as special feature since the half space landing
has no visible support being design as cantilever slab. Bending, buckling and torsion stresses are
induced with this form of design creating the need for the reinforcement to both faces of the landing
and the waist slab, therefore the amount of reinforcement required is high which can sometimes
creating site problem with regards to placing and compacting the concrete.
Universitas Indonesia
39
In order to build emergency staircase there are several stage of construction method
includes:
Universitas Indonesia
40
To install the scaffolding and formwork are pretty much the same with previous
section, which the top of scaffolding contains a U – head that act as the foundation of
girder and formwork (bodeman) that made by plywood is placed on girder. At first the
workers need to place girder at the bottom of staircase since it is hollow and need to
make temporary foundation for scaffolding. Afterwards connect all vertical post with
vertical ledger and strengthen it with vertical diagonal. On the top of vertical post, place
U – head to retain girder, formwork and workers above it.
Universitas Indonesia
41
This reinforcement steel bar has been shaped on the floor by the workers with the
design plan that is made by the consultant.
Universitas Indonesia
42
c. Concrete Casting
For concrete casting in emergency stairs, the engineers used K – 300 for quality of
concrete. Basically for the method of concrete casting is the same with the previous
section it needs 4 samples which are first day, seventh day, fourteenth day, and twenty-
eighth day and the requirement of slump concrete is 12 ± 2 cm and also it is not allowed
to pour concrete exceed 2 meters from the edge of bucket. The casting will be
dismantled after 21 days since this structure is cantilever need longer to make concrete
is ready to install tiles.
d. Railing
Every convenient stairs need railing to make the user safer especially for emergency
stairs, when a disaster is coming to the building then people try to escape safely and
quick from building. For Transmart Depok Supermarket Project, they build railing with
height is 1 meter from the stair and the same gradient.
Universitas Indonesia
43
In order to build car access into basement on Transmart Depok Supermarket Project, the
engineers make Ramp. In definition ramp is sloped pathways used both inside and outside
buildings used to provide access between vertical levels. Ramps provide an alternative to stairs for
wheelchair users, people with mobility issues and people with prams, bicycles and other wheeled
items. In this project the ramps are built in all basement and ground floor with 4.3° or 1:3 for the
gradient. The calculation for gradient is made by consultant. Based on engineers side in
construction field, this configuration is made to give ease access for driver to drive more safely
and comfortable. With 3 meters width of ramp, it is only make one lane and one line for each ramp
therefore it has one entrance and one exit for cars. The stages of construction method includes:
Universitas Indonesia
44
In order to install the scaffolding and formwork it is the same steps with the
emergency staircase, that the top of the scaffolding contains a U – head as a temporary
to retain girder and formwork (bodeman) above it. The position of bodeman is placed
above girder since it acts mold. However before install the scaffolding, the workers
should to place girder at the bottom of the ramp since it is hollow.
Universitas Indonesia
45
c. Concrete Casting
In concrete casting section, the concrete quality for ramps are K – 300. In this stage
it also has the same steps and requirement needs such as 4 samples for slump test and
12 ± 2 cm for allowable slump. The casting will be dismantled after 21 days because it
is cantilever structure. However for this section has special case that the workers make
drainage and traction after dismantle casting, these actions purpose to transfer water
flow while raining and ease driver to climb up because of traction that is made on ramp
In Transmart Depok Supermarket Project, the owner plan to make entertainment area such
as playground, mini castle, roller coaster, and etc. in order to make an entertainment area at the top
floor, the consultant make a design to compress budget and time they make columns and beams
are precast. In order to install column, first of all column precast is carried by tower crane from
ground, then rotate it 90° until the column stand vertically and the workers give instructions to
tower crane operator to set it correctly and other workers start to attach precast column on column
cast in situ by bolts, these action are taking several hours per column.
Universitas Indonesia
46
Universitas Indonesia
47
Universitas Indonesia
48
3.5 PROBLEMS
In construction field, any actions can be changed following the owner request and the plan
was not as a guidance anymore. During construction process in Transmart Depok, it has some
changes and some of them were important because it will affected cost, time and value. For
example, the owner suddenly asked contractor and consultant to build larger area at the top of
building because they wanted to have rollercoaster and other games.
Universitas Indonesia
49
That requested are made while third floor is in progressing to build 3 cast in situ column.
On that case the consultant re – design upper construction and it turned out with the precast (see
Figure 3.4.5.2) and they combine between cast in situ columns with precast columns, beams and
slabs.
Universitas Indonesia
50
CHAPTER IV
PROJECT MANAGEMENT
4.1 INTRODUCTION
A project is a sequence of temporary activities which has a beginning and an end that are
planned in order to achieve a completed product, service and result. However, the product or result
itself may not necessarily be temporary. A project has to have an ending, whether it refers to that
the project is completed or it is terminated because of the unachievable objective or goals. A
project may also produce unique output while being carried out repetitively. A project can enhance
an existing product and it also has the capability to create a product that can produce another
service.
In a construction project, it is certain that not only the technical aspects such as construction
methods that may affect the course of a project and the output it produces, but there are many non-
technical aspects which influences the success of the project as well. One of the non-technical
aspects of the most important is the project management. Project Management is the application
of knowledge, tools, technique and skills to meet a certain project requirement. Project
management process are divided into five categories, such as: Initiating, Planning, Executing,
Monitoring and Controlling, and Post Construction project. Therefore, although the success of a
construction project construction will be assessed from the results that are produced, however if
there are no fees, no good time management, and the lack of control over the quality, the results
will be difficult to achieve. To that end, in this chapter, the overall project management process
that the author collected from Transmart Depok Supermarket construction project will be
presented.
4.2 TIME MANAGEMENT
Theoretical basis
Based on the Project Management Body of Knowledge (PMBOK), project time
management is a management that includes the processes required to manage the project
completion time. In other words, time management project with regard to planning and scheduling
of all activities in the project so that the project can be run on time and as efficiently as possible.
In project management there are several processes or steps needed are:
Universitas Indonesia
51
• Schedule Management Plan, the process of defining or setting policies, procedures and
documentation for planning, developing, organizing, implementing, and controlling the
project schedule.
• Define Activities, is the process of identifying and documenting the specific activities that
need to be done to produce the project deliverables.
• Sequence Activities, is the process of identifying and documenting relationships between
jobs in the project.
• Estimate Activity Resources is the process of assessing the type and amount of material,
human resources, equipment and the need to carry out any work.
• Estimate Activity durations, is the process of assessing the amount of time required to
complete each activity with the amount of resources that have been estimated.
• Develop Schedule, is the process of analyzing a series of work, duration, resource
requirements, and schedule constraints to create a model of scheduling.
• Control Schedule, is the process of monitoring the status of project activities to update the
progress of the project and to manage changes to the initial scheduling to achieve the
original plan.
Transmart Depok Supermarket construction project is scheduled to begin on April 1st, 2016
and ending on 30th June 2017 with a planned duration of time of 16 months and 29 days. The
duration is based on the activity and duration of each activity undertaken to complete Transmart
Depok Supermarket project.
In Transmart Depok Supermarket project, the Master Schedule be a mutual agreement
between the parties PT. PP (persero). as the executor (contractor) and PT. Alfa Retail Indo as the
owner. However, in practice, the contracting parties have internal duration for each activity that
might be sooner than that contained in the Master Schedule, where different durations are possible
to speed up the work in the event of a delay so that the project can be completed on time.
Universitas Indonesia
52
No Personil APR MEI JUN JUL AGST SEP OKT NOP DES JAN FEB MAR APR MEI JUN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1 Project Manager
17 Drafter
18 Logistik
19 Umum
2016
No Personil APR MEI JUN JUL AGST SEP OKT NOP DES
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 Project Manager
Universitas Indonesia
53
2017
No Personil JAN FEB MAR APR MEI JUN
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 Project Manager
L
I
B
Figure 4.1.2 Schedule of the managers
Source: PT.PP (Persero) Tbk, 2017
In field project the schedule of site engineering manager (SEM) not always the same with
schedule above. In some reason, site engineering manager usually came to Transmart Depok
Supermarket office at night because he have to do engineering training in PT.PP (persero) central
office. It was happened to project manager that he come to project office not always corresponding
with the schedule, but he often to come almost seven days in a week.
In addition, as described in the previous section, in the implementation of a project is
necessary to time control in order to determine the progress of the projects carried out, where the
time control system is embodied in the form of S-curves
Universitas Indonesia
54
Universitas Indonesia
55
Universitas Indonesia
56
Universitas Indonesia
57
Universitas Indonesia
58
Universitas Indonesia
59
Estimate Costs
Estimate costs is the process of developing an approximation of the monetary resources
needed to complete project activities, or in simpler terms, it is a process where it determines the
amount of cost required to complete project work. Cost estimates are a prediction that is based on
the information known at a given point in time. Cost estimates include the identification and
consideration of costing alternatives to initiate and complete the project. Costs are estimated for
all resources that will be charged to the project. This includes, but is not limited to, labor, materials,
equipment, services, and facilities, as well as special categories such as an inflation allowance,
cost of financing, or contingency costs. Indirect costs, if they are included in the project estimate,
can be included at the activity level or at higher levels.
The Estimate Costs process will produce Activity Cost Estimates and Basis of Estimates,
as well as update (if any) project documents. Basis of Estimates may include documentation of all
assumptions, documentation of historical data, documentation of any constraints, indication of the
range of possible estimates as well as indication of the confidence level of the final estimation.
Determine Budget
Determine Budget is a process of aggregating the estimated costs of individual activities
or work packages to establish an authorized cost baseline. This process determines the cost
baseline against which project performance can be monitored and controlled. A project budget
includes all the funds authorized to execute the project. The Determine Budget process will
produce cost baseline, project funding requirements, and update (if any) project documents.
The cost baseline is the approved version of the time-phased project budget, but excludes
management reserves which can only be changed through formal change control procedures and
is used as a basis for comparison to actual results. It is developed as a summation of the approved
budgets for the different schedule activities. Total funding requirements and periodic funding
requirements (e.g., quarterly, annually) are derived from the cost baseline. The cost baseline will
include projected expenditures plus anticipated liabilities. Funding often occurs in incremental
amounts that are not continuous, and may not be evenly distributed. The total funds required are
those included in the cost baseline, plus management reserves, if any. Funding requirements may
include the source(s) of the funding.
Universitas Indonesia
60
Control Costs
Control costs is a process of monitoring the status of the project to update the project costs and
managing changes to the cost baseline. This process provides the means to recognize variance
from the plan in order to take corrective action and minimize risk. Project cost control includes:
• Influencing the factors that create changes to the authorized cost baseline;
• Ensuring that all change requests are acted on in a timely manner;
• Managing the actual changes when and as they occur;
• Ensuring that cost expenditures do not exceed the authorized funding by period, by WBS
component, by activity, and in total for the project;
• Monitoring cost performance to isolate and understand variances from the approved cost
baseline;
• Monitoring work performance against funds expended;
• Preventing unapproved changes from being included in the reported cost or resource
usage;
• Informing appropriate stakeholders of all approved changes and associated cost; and
• Bringing expected cost overruns within acceptable limits.
Cost control process normally is carried out during project execution period, where usually
there is difference between the actual working conditions with the planned condition which needs
re-adjustments in cost control which leads to the need of updating the cost baseline. Using Earned
Value Management (EVM), cost variance can provide information on predicted cost, and whether
proceeding projects are below or higher than intended planned cost.
In Transmart Depok Supermarket Project, the cost control department is managed by the
commercial manager, quantity surveyor and the buyer. The commercial manager is in charge in
managing material supply requests from the site manager. The material supply requests will then
be assessed regarding its quantity according to available budget before compiling the material
supply requests into a report, where the quantity surveyor will re-check whether the costs required
in the material supply report complies with the current available budget and whether the decision
can be sustainable cost-wise in the future.
The decision making also consider with the WBS that have been made before the construction
begin, this component is the boundary of all actions. The quantity surveyor is also in charge of
documenting every decision that are made. If the material supply report is approved, the quantity
Universitas Indonesia
61
surveyor will then convey and submit the finalized decision to the commercial manager, where the
commercial manager will issue the buyer to buy the site manager’s requested materials. However
during construction process, sometimes the owner give another request or change it then the project
management will have meeting with other occupants to brainstorming about control cost, time,
and also quality.
Basically while the owner give another request or change the request, they give money for
extra request but without extending time such as at the top floor of the Transmart Depok
Supermarket, at first the owner intended to place a roller coaster because of some reason.
Meanwhile after 6 month the owner changed they mind and they decided to place a roller coaster
at the top floor therefore the contractor make a deal to the owner to give extra money for build
special floor at the top since it was changed the plan.
Universitas Indonesia
62
Transmart Depok Supermarket project also uses the service of a construction management
consultant which is PT. Gratama Consultant where it acts as a supervisor on behalf of the owner
which is PT.Alfa Retail Indo. The construction management consultant in this project was
appointed directly by the owner. Additionally, broadly speaking, the role of construction
management is concerned with roles ranging from the supervision and control of materials,
implementation, equipment to labor.
Quality Control
Quality control in Transmart Depok Supermarket project can be divided into three
components: quality control of materials, quality execution, and human resources and labor. The
three components can clearly be seen in the following discussion:
• Quality Control of Material
Universitas Indonesia
63
Material is the cornerstone of a construction work. The quality control of the material that are
to be used is the main thing that must be done. Hopefully, by the material quality control, the final
results of the construction project can meet the standards or quality requirements. Here are a few
examples of materials control carried out on Transmart Depok Supermarket Project :
a. Concrete Quality
The components of reinforced concrete structures are the component that are most widely
used in the project, therefore the amount of concrete required is not small. To adjust the
concrete products produced with the required specifications to the work, PT.PP (persero).
represented by a structural site engineer structure along with representatives of the construction
management consultant conducted a review of mixing for each quality of concrete needed for
each batch of the concrete. This was done to determine the composition of the concrete
according to the quality required, these activities are usually called job mixing.
In addition, concrete quality control is also performed at the time of acceptance of the
concrete at the project site. Quality control testing is done in the form slump and preparing test
specimens for each 7m3 (1 mixer truck) concrete delivered. Slump test is witnessed and
measured directly by the construction management consultant, therefore if there is any
mismatch of the test results with the required specifications, the concrete can be denied
admission. To manufacture the test object itself, four cylindrical samples for each 10m3 of
concrete were tested for the seventh day, fourteenth day, 28th day and the last test specimen
used as a backup in case of errors and failures in testing.
In the event of a decrease in the strength of the concrete at the time of the test, which
resulted in non-compliance with the required specifications, the test was conducted by
destructive testing such as hammer test. If after these tests there is a decrease in the strength,
the concrete construction will be considered to be demolished or given special treatment in
accordance with the recommendations of the outcome of negotiations with MK, owner and
planner. This is done to maintain the quality of the resulting projects.
Universitas Indonesia
64
Based on figure 4.4.1 which is a map of third floor, it shows that in Transmart Depok
Supermarket Project divide this area into 11 areas. Not only for third floor, it is applying to all
floors in this building. They said this consideration to minimize any mistaken from low quality
of concrete that delivered from concrete company. PT. PP (persero) has contract in which
concrete company such as Hoclim, and Adhimix, these company had been chosen by the
contractor with owner permission. Based on the experience of engineers in PT. PP (Persero)
every project at least has 2 concrete company once they only use one concrete company and
sometimes this concrete company has problem such as coming late or low quality, it will
affected for whole part of the building. Besides that, the purpose of this map is to scheduling
the dates and time of concrete delivery and execution of it.
Universitas Indonesia
65
Universitas Indonesia
66
These form of concrete tests are gathered from the laboratory that are mentioned. Forms
purpose of this form is to make sure that this project use finest quality of concrete. The tests
Universitas Indonesia
67
that were done are Compressive strength test, Water permeability, and Water Absorption test,
for slump test were done when concrete trucks came on site.
Trisakti concrete test form is used as report from the laboratory to the quality control
division then he will make new report based on Trisakti concrete form as accountability to
project manager and if the result is not well, then usually project manager will gather occupants
and having impromptu meeting. Consideration of choosing Trisakti laboratory rather than
others, is based on contract in between owner with the contractor and the laboratory although
Transmart Depok Supermarket Project location is nearby UI.
b. Steel Quality
In practice, steel reinforcement is one of the materials that is most used after the concrete. In
the process of reinforcement procurement, some tests were conducted. The first test is testing the
density of the proposed reinforcing steel material that was given by vendor, where it aims to ensure
the compliance with the rebar’s quality and specifications given on the brochure. Further testing
is testing the tensile strength and static arch conducted in the laboratory. This testing is done to
ensure a strong tension value of the reinforcing steel used in accordance with the required
specifications. Physically, reinforcing steel of good quality must meet several requirements
namely:
i. It has the same average cross-sectional size
ii. Has appropriate size with working drawings specifications
iii. Free from dirt, rust, oil layer, and does not crack or peel
Universitas Indonesia
68
In figure 4 which is Reinforced Steel Checklist, the objective of this form is to make sure all
delivery of reinforced steel come on time and complete. As figure above the table is divided into
3 section which are I, II, and III. These sections are indicated of completeness of delivery material,
first row means the materials already complete at first delivery, for second and third rows means
that the delivery complete at second and third times.
Actually not only the completeness but the details of materials should be matched. This failure
occurred during construction progress such as steel wire, as checklist form on Ikatan Tulangan
Universitas Indonesia
69
(steel wire) he wrote circle and gave a comment that the delivery did not match with the request
from Consultant.
Universitas Indonesia
70
there is also team members that are later added to or dismissed from the team as the project
progresses. Project team members often referred to as project staff. Although each member has a
role and responsibility, the involvement of individual members in the planning and decision-
making is very profitable. The participation of the team members during the planning stage will
add their expertise to the work processes and increase their commitment to the project.
1. Plan Human Resource Management: the process of identifying and documenting roles and
responsibilities, required skills, reporting relationships and create a plan of management
staff.
2. Acquire Project Team: a process to ensure the availability of human resources and get the
team needed to complete project activities
3. Develop Project Team: the process of increasing the competency, the interaction of team
members, and build a working environment to improve project performance
4. Manage Project Team: the process of evaluating the performance of the team members, get
feedback, solve problems and manage change to optimize project work
a. Owner
Owner is the owner of the idea and funds to build or deliver the project where the owner can
appoint an expert or a legal entity to conduct as the planning process pleases. The owner of this
project is PT. Alfa Retail Indo. The Owner has the duty and authority as follows:
Universitas Indonesia
71
b. Planning consultant
The planning consultant functions to implement procurement planning documents,
construction documents, providing an explanation of work at the time of the auction and providing
clarification and completion suggestions on planning issues that arise during the construction
phase. The planning consultant works since the planning stage until the time of handover by the
contractor. In this project there are several planning consultants which have expertise in their
fields.
• PT. Garis Rancang Bangun as Architectural Planning Consultant.
• PT. Catur Inti Dinamika as a Structural Planning Consultant.
• PT. Garis Rancang Bangun as Mechanical and Electrical Planning Consultant.
The planning consultant has duties and authorities as follows:
• Design and plan a structure according to the owner’s likings and orders
• Has overall responsibility for all planning that are made
• Give consideration and advice on every structural work
• Make all project calculations project based on the technical data that was previously set
Universitas Indonesia
72
appointed by the owner is PT Gratama Consultant. The construction management consultant has
duties and authorities as follows:
• Approve work plans and shop drawings of the contractors
• Conduct daily surveillance which includes monitoring of the quality of materials,
equipment, labor and direct supervision of the field work practice, and supervision of the
testing of materials and equipment
• Evaluating the results of tests performed by contractors
• Coordinate various parties related to the construction work practice
• Pause or withhold a job under certain circumstances when there is a deviation or irrelevant
practices that are set by the regulations contained in the contract documents
• Prepare and submit monthly reports and final report to owner
d. Contractor
The contractor or service provider is the party that won the procurement tender of construction
services in which they have a duty to implement or work on the project in accordance with the
agreed contract. In Transmart Depok Supermarket project, the main contractor is PT.PP (persero).
The contractor has duties and authorities as follows:
• Create work methods
• Carry out work in accordance with the contract
• Prepare material, labor, equipment and everything that is used to support the project
• Carry out revisions and design changes as instructed by the owner
• Has overall responsibility for all the work and the errors of any related works regarding the
contractor’s scope of work
• Hand over finished work to the owner
In the project, there are a group of people in the contractor’s team who have a working
relationship, cooperate and interact with each other in carrying out a scope of work in the field of
construction to achieve a common goal which is levelled according to their position and expertise
which altogether forms an organizational structure. The project organizational structure serves to
set facilitate each members in coordinating the project from the given directives or orders
according to their position and status.
Universitas Indonesia
73
Transmart Depok Supermarket Project is leading by Project Manager which is Mr. Ir. Arso
Anggoro, with all commands during construction progress come from Project Manager. The
Project Manager has subordinates that are Site Engineering Manager (SEM), Site Operation
Manager (SOM), and Site Administration Manager (SAM), these sections have direct order from
the Project Manager and also they are responsibility of their jobs. Site Engineering Manager acts
as day – to – day managers on a construction site, and the main source of technical advice and
quality control for everyone working on it. The role also involves levelling and surveying a site,
checking drawings and quantities and ensuring the accuracy of calculation from consultant works,
for this section takes over by Mr. Triyadi and he is our supervisor during internship.
A site operation manager has a broad role and managing day – to – day activities during
construction progress, analyzing statistic and write report, and he also have to do a lot of interaction
with human resources such as mandor (Foreman) and he’s subordinates to control the operation.
Universitas Indonesia
74
Not only the human resources, but all the operations that should be successfully done such as
concrete casting actions, installing precast and so on, in this section takes over by Mr. Suyadi.
Last manager is a site administration manager that takes over by Mr. M. Fajar. A great
administration manager has excellent communication and organizational skills. The ideal
candidate will be well-versed in departmental procedures, procurement and policies it will be able
to actively discover new ways to do the job more efficiently. The goal is to ensure all support
activities are carried on efficiently and effectively to allow the other operations to function
properly.
The organizational structure in Transmart Depok Supermarket Project has other sections that
have ordered directly by Project Manager which are Quality Control and Health Safety and
Environment. These two section have no subordinates thus they job are independent since during
construction progress, budget should be compressed and all action should be effective therefore
the project manager is selective to choose the most experience and expert occupants for this
section.
In quality control that is Mr. Sujanto jobs, he is the most important things in every construction
project since it control the quality of everything start from materials until human resources. For
the quality of materials, he should interpret and review shop drawings for example in concrete
casting situation, in Transmart Depok Supermarket Project they use 2 different concrete company
and each concrete company has different areas to pour their concrete. As quality control he has to
monitor concrete casting to pour in exact place and time based on shop drawing that has been
planned by consultant. For quality of workers, he has to educate workers on the required standards.
Health safety and environment section takes over by two occupants which are Mr. Budianto
and Mr. Gofar. These two people are partner with the same jobs description. In this section, they
have to educate workers to use costume that are should be used during construction progress such
as helmet, vest and boots, monitor workers to make sure all of them are wearing costume during
construction progress and give punishment whether they are not using costume during construction
progress. In facts, in this section both of them are not collaborates well since only one man is done
his job really well even though he is almost taking all of this jobs and the other more likely has
longer rest then that man.
Universitas Indonesia
75
Universitas Indonesia
76
Identity Risk
The Identify Risks process of PMBOK Project Risk Management entails identifying risks
and documenting their characteristics. Identify Risks is a process that you’ll revisit several times
during the project. For example, you may identify risks during the daily team meeting. Key inputs
to this process are: Risk Management Plan, Activity Cost and Duration Estimates, Scope Baseline,
and Stakeholder Register. There may be other project documents, such as Assumptions Log and
Work Performance Reports, which can help in this process. Some Tools and Techniques used in
this process are: Brainstorming, SWOT Analysis, and Expert Judgment. The output of this process
is the Risk Register, which contains the list of potential risks and the potential responses. Project
Risk Management is one of the critical PMBOK Project Management knowledge areas.
Universitas Indonesia
77
Universitas Indonesia
78
Problems
During this project not whole parts were going well although the plans were well – prepared
and well – consideration, there are some problems that occurred in construction management
section.
• Time Management
• Schedule of employee particularly on managers it does not match with reality, such
as our supervisor. In the schedule, he has to come to construction field at least once
in a week but sometime he has not come to the construction field because of some
reasons.
• It has extended time for this project because of procurement at the finishing,
actually this issue was the owner mistaken since they did last procurement. Last
procurement is the roller coaster and other games for the top floor. The influence
of that action, last wall as finishing for this construction were late.
• Quality Management
• In concrete test it only use 1 sample for 4-5 trucks. In this section, were actually
based on the owner request but it is break the engineering ethics, since during
construction process every truck has to be tested no matter.
• It is less effective for concrete test since the test is done in Trisakti although the
project is located in Depok. Based on the engineers interviewed, this action is made
because of the contract between contractor company and the laboratory, although
the place between this laboratory with the construction field.
• Human Resources
• For some reasons, there are some employee in this project seems lack of duty. For
example like one of the HSE occupants are frequently seems took more rest than
Universitas Indonesia
79
the other one. Once our teams came to the construction field, as a HSE he should
give any directions to avoid any kind accidents for every stakeholders however he
just gave us a letter of statement and other paper that include of any action that
should not do without any explanation from him.
Universitas Indonesia
80
CHAPTER 5
HEALTH, SAFETY, AND ENVIRONMENTAL PROTECTION
5.1 Introduction
Safety is very necessary in any kind of workplace. In the construction industry,
there are a lot of hazard that present in the project site. There are risks associated with every
workplace. In some industries, the outcome of a typical incident may be relatively slight,
for example an office worker shaken and upset by slipping on a wet floor. In other
industries, specifically in the construction work area, a typical incident can have far more
severe consequences, such as a worker pinned beneath an overturned structure, a building
worker hurt in a fall, or a steel worker caught up in machinery. Even more extreme
consequences may also lead to death. Accidents create not only personal grief and distress
but also huge financial costs and unwelcome negative publicity for the organization and
industry concerned. They are of great interest and concern to all of the organization’s
stakeholders such as its employees, managers, shareholders, local residents and businesses,
and suppliers.
Therefore, a certain precise management system is crucial in the involvement of a
construction process. This management system includes an organizational structure, plan,
responsibility, implementation, procedure, process, and resources needed for development,
implementation, achievement, assessment, and maintenance of occupational health and
safety policy in controlling the risk where it is associated with work activities in order to
create a comfortable and safe workplace, and also productive, where usually it is called by
HSE management.
said, Health Safety and Environmental Protection is vitally important in the building and
construction industry. Every worker has the right to work in a safe environment, and
employers should ensure safety is their number one priority on site. Employees have the
right to stop work if there is an imminent risk to their health and safety. If this occurs,
employees must follow any reasonable direction of their employer to perform other work
that is safe and appropriate for them.
HSE are all the conditions and factor which it can affect to the safety and health of
the worker or even another concerned stakeholder such as the contractor, supplier, guest,
or even the society around the work area. On the other hand, the explanation from ILO
(International Labor Organization) is that Health Safety and Environment acts as an
activity to prevent and increase the degree of physique, mental, as well as its social aspects
into the highest level for all workers in every position to prevent the declination of health
of the workers caused by the condition of their job; protect every work from any possible
risk that may happen from any factors that will be detrimental to health; placement of
workers in their designated work place should be in accordance with the physiological and
psychology of the workers itself.
5.3 Rules of HSE in TransMart
HSE regulations and programs on TransMart Depok project is the implementation
of the legislation on occupational safety and health that have been set by the government
and the implementation of regulatory standards of the HSE division of PT. PP (Persero)
Tbk. Basic HSE regulations used as a reference in the TransMart Depok project include:
1. Safety standards of PT. PP (Persero) Tbk.
2. Act No. 1 of 1970 About the Work Safety
3. The Minister of Health No. 1405 / Menkes / SK / XI / 2002
4. The Minister of Manpower Regulation No. 2 of 1980 On Medical Examination
of Labor
5. Act No. 18 of 2008 on Waste Management
6. Minister of Environment Decree No. 112 of 2003 on Water Quality Domestic
Waste
7. Act Number 23 Year 1997 on Environmental Management
82
Besides the official standard regulation of HSE, PT PP (Persero) Tbk has its
own standard quality of safety environment.
done throughout the project. This program is presented in the form of a list of programs, rules of
the related program, program implementation schedule, and the person in charge of each HSE
program.
There are several implementation to the project, which are:
Safety Agreement
Before entering the project site, all of the individuals must read and sign the Agreement
provided by the HSE officer, including submitting their copy of identity card. The individuals are
not limited to the workers and employees of the project site but also any visitors that needs to enter
the project site. The agreement is consisted of required conditions and equipment that the person
must obey. Every individual who has not yet visit the project site or in their first time visiting the
project site are directly be commanded to enter the HSE office and sign the agreement.
Personal Protection Equipment (APD).
Personal Protection Equipment or Alat Pelindung Diri (APD) is the equipment set
mandatory to be equipped inside the project site. The function of APD is to protect the safety of
the person or the people around it. The APD also gives alert to the anyone of the worker’s existence
in the project site and preventing from the any potential dangerous risks. PT PP (Persero) Tbk has
its own standard for the APD which are safety boots, hard helmet and construction vest.
During the implementation, any workers who do not use the proper safety equipment will
be given a warning letter. If a worker is caught not following the rules for the second time, that
worker will be fired. This method is used to prevent any worker that is not constantly following
the HSE rules. The HSE officers are controlling and observing the workers every day to make sure
that the HSE Safety rules is properly followed.
85
Safety Talk
Besides that, there is a safety talk once in a month for every worker. A safety talk is a
hands-on way to remind workers that health and safety are important on the job. Each talk takes
about five minutes and can help workers recognize and control hazards on the project. Safety talks
demonstrate the commitment of employers and workers to health and safety. Use the Safety Talk
Report Form to keep a record of each talk delivered. Record the date, topic, and names of attendees.
Incident
The HSE organization is fully responsible for the safety of people, both inside the project
and outside the project. Whenever there is an accident during the work, the project work will be
stopped immediately for a certain amount of time. The HSE organization also conduct a
cooperation with the nearby hospital, which is Rumah Sakit Bhakti Yudha. The purpose of this
cooperation is to fasten the process of treating the injury of the workers. The HSE of the project
86
site will be the one to asked for responsibility if there is any accident happens inside the project
site as well as its surroundings.
Figure 5.4 Rumah Sakit Bhakti Yudha that cooperate with TransMart Depok project
Source: Kota.com
Figure 5.5 The distance between RS Bhakti Yudha and TransMart Depok
Source: Google Maps, 2017
87
Based on the Figure 5.5, the location of RS Bhakti Yudha and TransMart Depok is not far.
It can be easily reached by only 5 minutes using a car. The flexibility in the location between RS
Bhakti Yudha and TransMart Depok project site allows the workers or any visitors to be escorted
directly to the hospital when an accident happens. The cooperation between PT PP (Persero) Tbk
and RS Bhakti Yudha was established before the project work starts. It is one of conditions that
must be fulfilled before starting a project of PT PP (Persero) Tbk.
5,6 Problem
There are some problems that was seen in regard to the HSE during the construction work
of TransMart Depok. Even though that the PT PP already provide the whole APD for all the
workers, some of the workers are still not following the safety standard.
Figure 5.6 Workers do not wear full APD equipment during concrete casting
Source: Writer’s Documentation, 2017
As seen in Figure 5.5, some workers only wear the hard helmet and safety boots, without
wearing any construction vest. The construction vest may not seem very influential as an alert of
the existence of a person, which is why some of the workers did not wear the construction vest.
88
The construction vest itself gives more prominently presence of a person. It may also be happening
due to the limited HSE supervisor during the construction work.
These rules violation occurs is highly due to the former rules that was applied. Up until
March 2017, the HSE officer confirmed a rule for the workers who violate the safety standard. The
consequences for not following the safety standard is a fine to the foreman of the worker. Later
on, the HSE will charge to the foreman which had the worker who violate the safety standard (not
wearing proper APD). However, it turns out that this method of consequences is not effective
because the worker does not certainly pay to the foremen for his own violation. Due to that, the
HSE Officer change the consequences for not using the proper APD. The new consequences are
giving warning letter the first time the workers are violating the safety standard. The warning letter
warns that the next time they done it again, they will be fired immediately.
89
CHAPTER 6
CONCLUSION
Attending the Internship subject in TransMart Depok project has certainly giving experience
for the writers in regard to civil engineering project. During the Internship subject, the writers
directly experience the work inside the project site including the structural work, construction
management and HSE application. These experiences and knowledge which obtained through the
Internship at TransMart Depok has supplied the writer’s preparation in entering the work field
later.
The writers have fulfilled the purposes of the Internship Program as written in Section 1.2
Including observing and study the construction method and construction management in
TransMart Depok. The construction management includes the understanding the detail of some
division’s task of quality management, time management and human resources management. The
writers also encounter some problems inside the project side such as the changes in structural
placement and unequipped safety attire by the workers.
The Internship Report solely written based on the writer’s experience during the Internship
subject at TransMart Depok. The Internship Report is surely gainful in sharing about the works in
the construction project. Hopefully, this Internship report may be beneficial for both the writers
and the reader.
Universitas Indonesia
90
APPENDIXES
Universitas Indonesia
91
Fig
Figure 7.2 Lecturer Supervisor’s Log
Source: Writer’s Documentation, 2017
Universitas Indonesia
92
Universitas Indonesia
93
Universitas Indonesia
94
Universitas Indonesia
94
Universitas Indonesia
95
Universitas Indonesia
96
Universitas Indonesia
97
Universitas Indonesia