INDONESIA XL SEAHAWK PROJECT   

MOP Dismantle 

Huawei Technologies Co., Ltd.


All rights reserved
Revision 1.0
INDONESIA XL SEAHAWK PROJECT   

MOP Dismantle 

Prepared by:  Eko Imam Minardi    Date: November 2018   

Reviewed by:  Adhi Kurniawan    Date: November 2018   

Emilza Yuswar   

Approved by:  Zhangfan    Date: November 2018   

Rev.1.0   
Contents 

1 Implementation porpuse and Requerment ……………….…………………………4 

2 EHS (Environment Health Safety)…………………………………………………5 

3 Support Documents …………………………………………………………………..7 

4 Tools for dismantle ……………………………………………………………………7 

5 Process Dismantle Procedure ……………………………………………………..…9 

6 Step By Step Dismantle Procedure ………………………………………………….12 

Page 3 of 19
I. IMPLEMENTATION PURPOSE & REQUIREMENTS:
Huawei  are  required  to  keep  an inventory of all hardware that will  be  removed or  dismantled 

from site and forwarded to the Huawei warehouse.   

Huawei shall provide a list of equipment to be redeployed, Back to warehouse XL & Huawei per 

site basis, and record by ISDP SQC – EATP Dismantle   

Huawei will dismantle and clean up Huawei Equipment material     

Huawei  will  ensure  and  secure  all  dismantled  equipment  is  complete  and  in  proper  working 

order for redeployment (where required), and can be utilized in the future.   

II. EHS (Environment Health Safety)


2.1.   Instruction 

This  section  describes  the  safety  precautions  you  must  take  before  dismantling 
equipment. 
 To ensure safety of humans and the equipment, pay attention to the safety symbols 
on the equipment and all the safety instructions in this document. 
 The  "NOTE",  "CAUTION",  and  "WARNING"  marks  in  other  documents  do  not 
represent  all  the  safety  instructions.  They  are  only  supplements  to  the  safety 
instructions. 
 Installation and maintenance personnel must understand basic safety precautions to 
avoid hazards. 

2.2. General Requirement 

To  minimize  risk  of  personal  injury  and  damage  to  equipment,  read  and  follow  all  the 
precautions in this document before performing any installation or maintenance. 
 
Ensure  that  the  instructions  provided  in  this  document  are  followed  completely.  This 
section also provides guidelines for selecting the measuring and testing devices. 

2.3. Human Safety 

 Do not operate the device or cables during lightning strikes. 
 At least two persons are required to lift the chassis. When lifting it, keep your back 
straight and move stably. 
 Do not wear jewelry or watches when you operate the device. 
 
 
 
 
 

Page 4 of 19
2.4. Safety Briefing before Work 
Team Leader must hold a site  installation tools box talk  with engineers or technician  in 
site,  the  Team  leader  must  fully  explain  all  of  the  work  activities  and  all  engineers  or 
technician informed of their individual roles & responsibilities be clearly defined. 
Engineer  or  technicians  of  the  team  are  to  be  briefed  in  the  first  aid  and  site  accident 
procedures and be made fully aware of the contact call numbers in case of any incidents, 
all near misses are to be recorded and reported as they occur. 

 
 
 
 

Page 5 of 19
Safety Briefing contents:   
 Step by step dismantled equipment. 
 Visual checking analysis of tower or structure condition, the site structure must be in a 
safe and fit for purpose condition and safe from other dangers such as animals such as 
large spiders, snakes, bees, monkeys etc. 
 
 
III. SUPPORT DOCUMENT
The supporting documents that must be learning and bring to site by installer’s team are: 
1.   Work Permit (Huawei and TP) name of team member must same with work 
Permit. 

2. MOP Dismantle. 

3. EHS Document (JSA : Job safety Analysis) 

4. Etc, if any 

IV. Tools for Dismantle

Please prepare tools before dismantle, this below are tools mandatory for Dismantle.
Minimum Requirements: dismantled Tools Checklist

Item Description Qty Tools

1 Ropes minimum 150 Meter - SWL 200Kg. 1

2 Carabineer Steel - 23Kn - Screw lock 2

3 Pulley Block/Snatch Block - SWL 200Kg 1

Safety Signs (Working at Heights –


3
4 Emergency call – PPE)
5 Barricade Tape Minimum 100 Meter 1

Page 6 of 19
Single Flat Webbing Cargo Sling ‐ 5m ‐   
6 2
150Kg

Complete set of professional hand tools & Tool 1


7
box. Set

PPE Requirement (Personnel Protective Equipment)


Item Description Qty
1 Safety Shoes 4 Pasang
2 Full body Harness, with shock absorbing lanyard & horizontal lanyard 2 Set
3 Safety Helmet ground 2 Ea
4 Safety Helmet Climbing 2 Ea
5 First AID box 1 Set
6 Pass ID L0 for Team Leader 1 Pcs
7 WAH Certificate and Electricity Certificated 2 Pcs
Tools packing list

1. Spidol marker = 2 pcs

2. Paper A4 = 10 pcs

3. Bubble Wrap = 1 set

Page 7 of 19
 Certificated climb, electricity, First AID and Pass ID must be have as mandatory. 

   

First AID Certificated  TKPK1/WAH/TKBT2 Certificated 

   

Electricity Certificated  PASS ID Valid 

Page 8 of 19
V. Process Dismantled Procedure
5.1. Flow Chart Dismantled
 
Start
 
 
  Work Permit, Access, MOP Doc ,
 
 
Tools & Equipment check, Team tool box talk safety 
 
 
 
Call NOC & Info FOP XL before start activity Dismantle 
 

 
Power Off Equipment 
 

 
Dismantled Equipment, RRU, Antenna, Feeder, Mounting 
 

 
Dismantled BBU, RF Board 
 

  Check list dismantled all Equipment’s 
 

 
Packaging Dismantle Equipment
 

  Site Cleaning 

  Upload Doc to ISDP TASK EATP Dismantle

  TASK ISDP EATP Dismantle Review

  TASK ISDP EATP Dismantle CLOSED 

 Pick up & Hand over Equipment Dismantle to Warehouse   

 
Finish 
Page 9 of 19
5.2. Step By Step Dismantled 

No.  Activity Day 1st  Details  PIC 

1  Work Permit, Access, MOP,  Make sure before  Subcont 

The dismantling works must  dismantle equipment, 

be informed to PIC Huawei  document must be rady to 

for dismantled least 2 days  the site   

in advanced before work   Make sure name of 

start, as to prepare for the  activity team on site must 

on site supervision if  same with work permit   

necessary. 

2  Tools & Equipment check,  Make sure before dismantle  Subcont 

Team tool box talk safety  equipment, tools and safety 

good condition 

3  Take Photo before  Make sure before dismantle  Huawei & subcont   

start Dismantled  activity coordination with 

  Huawei team and Req TASK 

ISDP SQC – EATP Dismantle   

4  Dismantled Equipment RRU,   Two person climb to  Subcont 

Antenna, Feeder &  tower for install rope, 

Mounting    pulley. 

 Two person dismantled 

RRU, Antenna, Feeder & 

Mounting   

5  Dismantled Equipment BBU  One person dismantled RRU,  Subcont 

& RF board      Antenna, Feeder & Mounting 

  
Page 10 of 19
 

6  ISOMA – Break    Istirahat, Sholat & Makan  Subcont 

7  Check list equipment &  Check list all equipment  Subcont 

packing list    dismantled and packing list 

8  Site Clean    Site Clean site after  Subcont 

dismantled 

9  Upload Doc to ISDP SQC –  Site Clean site after  Subcont 

EATP Dismantle    dismantled 

10  Task ISDP SQC Review    Task ISDP EATP Dismantle  HTI – HS   

Review Approval L1 : PT. 

Huawei , L2: PT. HS 

( Representative XL )   

11  Pick Up & Handover all  Pick Up all equipment’s to  Subcont – Huawei – 

equipment’s to Warehouse  Warehouse Huawei  HS   

Huawei   

12       

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Page 11 of 19
VI. Step By Step Dismantled Process
6.1. Dismantled Huawei Equipment RRU, Antenna, Feeder & Mounting. 

Step by Dismantled Equipment RRU, Antenna, Feeder & Mounting : 

 Ensure the pulley blocks are secured firmly and correctly in the Leg Tower.
 No member below the equipment Huawei , communicate well with rope controller.
 Lift slowly and stop slowly under control at all times, follow the lift & climb as it rises.
 Dismantled Huawei Equipment.RRU/Antenna/Mounting/Feeder

 Dismantled Accessories Feeder,RRU ( Bracket RRU, Connector Power RRU, Cable

Feeder, SFP ).

 Carefully for material treatment while dismantle on progress and material storage, make

sure no damage on material and potential for material damage. Put material in tidy and

safe condition on site.

 Dislodged all material dismantle Equipment Huawei please be carefully without damage

on material.

 For dismantle jumper antenna ex Huawei , don't escaping to the jumper feeder, very high

risk broken connector and make high VSWR.

6.2. Dismantled Equipment BBU & RF board   

Step by step Dismantled Equipment BBU & RF board:

1. Power off MCB Huawei at DCDU , make sure have tag name/Label    . 

2. Protect cable power with isolation tape. 

3. Dismantle Cable power. 

4. Equipment Huawei must be attaching with label, and material name. 

5. Dislodged all material dismantle Equipment Huawei    please be carefully without 

damage on material. 

Page 12 of 19
6.3. Check list equipment & packing lst 

 
 

Page 13 of 19
 

 
Page 14 of 19
 

Step by step check list equipment & packing list: 

 Check list all equipment dismantle equipment in form /templated Cheklist Material

 Packing with Card board & Bubble wrap

 Packing list must have tag Label

 Doc Berita Acara Dismantle all equipment’s dismantled must be sign PIC Subcont

Team.& PT. HS / Customer

 Recheck each material dismantled must be suitable with Document Dismantle

 
Page 15 of 19
 

6.4. Site Clean 

 Clear up the equipment room and the outdoors.

 Recheck if any remain material suppose include for dismantle.

 Make sure you have prepared document waiver site clean with sign landlord.

 No garbage or discarded materials shall be left on site.

6.5. Upload Doc to ISDP TASK EATP Dismantle     

 
Page 16 of 19
 

6.6. Task ISDP EATP Dismantle Review   

 
 

 Task ISDP EATP Dismantle Review Approval L1 : PT. Huawei , L2: PT. HS 

( Representative XL )   

6.7. Pick Up all equipment to warehouse Huawei & XL 

 
Page 17 of 19
 

 Be careful while move equipment to Car PICKUP. 

 Protection all equipment in the car with Tarpoulin . 

6.8.   Hand Over Equipment Dismantle to PT. HS / XL

 Hand over Equipment Dismantle to PT. HS / XL   