Daily Working Record

Name : PHAL Pisey

Month : Feb 2018


Date Contents Achievement Remark
-Draw method statement for bridge
24 Sat -30% of Substructure.
No.55.
25 Sun

26 Mon -Finished Substructure.


-Draw method statement for bridge
27 Tue -30% of Superstructure.
No.55.
28 Wed -Finished Superstructure.

Month : Mar 2018


Date Contents Achievement Remark
1 Thu -10% of Substructure.
-Draw method statement for bridge
No.59.
2 Fri -20% of Substructure. -Meeting at PISNOKA.

3 Sat Annual Leave