OGP Panel Questions

No. QUESTIONS ANSWERS

4001 Draw PFD .

4002 Mark all parameters.

4003 What is the purpose of scrubber?

4004 What will happen if liquid is carried over to compr?

4005 What are the safeguards in a scrubber?

4006 What will you do if gas feed is low?

4007 What wil you do if Omar CPF S/D?

4008 What will you do if Export line SDV shut off?

4009 What is the type of Controller in export line?

4010 What is the MEG injection pressure?

4011 What is the minimum Dp required across glycol inj?

4012 What is the purpose of minimum Dp required?

4013 What is the MEG injection flow rate?

4014 How do you know that the rate is not enough/

4015 What is the pH of Rich and Lean MEG?

4016 What is the concentration of rich and lean MEG?

Why hot oil is not used directly from the heater for
4017
MEG reboiler ?

What is the suction and disch.pressure of refrigeration


4018
compressor?

4019 What are the parameters in slug catcher?


4020 What are the safeguards of slug catcher?

What will happen if Depropanizer pressure and temp


4021
icrease?

4022 What are the safeguards for inlet separator

4023 How will you prepare V-605 for vessel entry PTW?

What are the Surge symptoms and how is it


4024
controlled?

4025 What is the gas test required for Vessel entry?

4026 What is Conform / Non conform Entry?

4027 What is mandatory before a vessel entry?

4028 Where will you put the SPADES in a vessel for entry?

4029 What is positive isolation?

4030 What type of isolation required for H2S ANSI 300?

4031 What is Pyrophoric iron and what is the protection?

4032 What are the chemicals you are using in OGP?

What are the Hazards and protection for chemical


4033
handling?

What will you do at high level in flare knock out drum


4034
if LSHH was found in OVERRIDE?

4035 What is override and what is the purpose of it?

4036 What are the safeguards for Gas export compressor?

4037 What precaution you will take for work at height?

4038 What is excavation certificate and who will sign?

What is the depth limit which needs excavation


4039
certificate?
4040 What is the inst.air header pressure?

4041 What is the difference between inst.air and utility air?

4042 How do you know that the inst.air is dry?

4043 What is the ON LINE analyser reading of inst.air ?

4044 How nitrogen is produced in OGP?

4045 What are the data in FISCAL meter in gas export line?

What is the diffference between Operating Manual and


4046
Operating procedure.?

What is the composition of Sales gas export, LPG, and


4047
Condensate?

4048 What is the percent of C5+ in LPG? Why?

What type of flow instruments used for Gas export,


4049
LPG and Condensate export?

4050 What supplies nitrogen to Hot oil tank blanket gas?

4051 What is the purpose of purge gas to flare header?

4052 What supplies fuel gas to OPP if OGP shut down?

4053 What will happen in OPP if fuel gas is wet?

4054 What is the purpose of dry air to instruments?

4055 What is the dessiccant used in instrument air dryers?

How much time is required to depressurise gas plant


4056
after ESD?

4057 What is the emergency procedure?

4058 What is auto drain? Where is it provided?


4059 What is the PSV set pressure in Depropanizer?

What will you do if override continues more than four


4060
days?