Académique Documents
Professionnel Documents
Culture Documents
A Shortcut to Determine
Optimal Steam Pipe
Diameter
Srbislav Genić
Branislav Jaćimović
Univ. of Belgrade
S
team distribution pipelines are the necessary link oversized pipes, higher heat loss will produce a larger vol-
between the steam boiler/generator and the steam ume of condensate, which requires more steam trapping to
user. An efficient steam distribution system is essen- avoid the delivery of wet steam.
tial to deliver steam of the appropriate quality and pressure The larger pressure drop of an undersized pipeline may
to the proper equipment. Installation and maintenance of the limit the availability of lower-pressure steam to only the
steam system are important issues that must be considered point of use, increasing the risk of erosion, water hammer,
at the design stage. Both oversized and undersized pipelines and noise due to the inherent increase in steam velocity.
can have operational problems. Pipes, valves, fittings, etc., Mathematically rigorous methods for selecting pipe
in oversized pipelines will be more expensive than neces- diameters are time-consuming because they involve itera-
sary, with higher capital and installation costs, and more tive procedures to determine the minimum total capital and
support work and insulation. Additionally, in a system with operating costs. Simple equations can provide reasonably
22 www.aiche.org/cep August 2018 CEP Copyright © 2018 American Institute of Chemical Engineers (AIChE)
accurate estimates of optimum pipe diameters in the initial where F is the factor that includes the cost of valves, fit-
stages of a design, which can serve as a good starting point tings, and construction.
for a more rigorous procedure.
The first pipeline optimization model based on econom- Pipeline operating cost
ics initially applied to turbulent flowing fluids in hydrauli- The operating cost of a pipeline depends on the energy
cally smooth pipes, and it was later broadened to accommo- consumption necessary to achieve fluid flow through
date laminar flow; a new model was recently developed for the pipeline.
hydraulically rough pipes. All of these models were devel- The energy balance of any flow system includes specific
oped for fluids that receive energy from pumps, compres- energies calculated at the system inlet and outlet. A general
sors, blowers, or fans that are powered by electric motors, form of the energy balance equation is:
so none of them can be used for steam pipelines (1–3).
This article presents a simple optimization model to
estimate the diameter of steam pipelines, and discusses the
role of parameters such as plant location and fuel type. Two For steady-state processes, the accumulation of energy
example calculations compare the recommended steam is zero, and for insulated pipelines, heat loss through pipe
velocities in the literature and the solutions obtained from walls is negligible, so the energy balance equation for a
the proposed model. pipeline is simplified to:
Copyright © 2018 American Institute of Chemical Engineers (AIChE) CEP August 2018 www.aiche.org/cep 23
Heat Transfer
Greek Letters
Δp = pressure drop, Pa
Δpfr = pressure loss due to friction, Pa
Δpml = minor pressure loss, Pa where A is a simplifying term that combines values specific
ε = absolute pipe roughness, m to individual pipelines:
η = viscosity, Pa-sec
ξ = Darcy friction factor
ρ = density, kg/m3
and B is a simplifying term that incorporates the pipe diam-
Indices eter and the friction factor:
in = inlet
opt = optimal
out = outlet
The pipeline friction factor, in general, depends on Reyn-
olds number:
24 www.aiche.org/cep August 2018 CEP Copyright © 2018 American Institute of Chemical Engineers (AIChE)
capital costs, so 0.01 ≤ b ≤ 0.05. It is common for process
plants to operate 90–95% of the time, so Y = 8,000 hr/yr.
The factor that incorporates the cost of valves, fittings,
where η (Pa-sec) is the fluid viscosity and ε (m) is the abso- and construction, F, is the most difficult to evaluate because
lute roughness of the internal pipe surface. The relative pipe it varies significantly from one application to another. For
roughness is Rr = ε/D. Pipe relative roughness, according to short pipelines with smaller diameters and without fittings
open literature data, ranges from 0 to 0.0333. and supports, F is as low as 3, while for larger pipelines
Like many other gases and vapors, steam is almost with fittings, F may be as high as 11. When no other data
always transported in the turbulent regime due to its den- are available, it is safe to assume a value of F around 6 or 7.
sity and viscosity. Nevertheless, to complete the model, The coefficient J for minor pressure losses is 5–10% for
Eqs. 15a–c calculate the friction factors for laminar, transi- very large pipelines, but it can be 100%, or even more, for
tion, and turbulent flow (4): shorter pipelines with many fittings (10).
Boiler efficiency, E, is usually around 0.88 for oil fuel
and 0.92 for natural gas systems.
Example calculations
These two examples illustrate the calculations involved
in the proposed model. Results are compared to the litera-
ture recommendations (5–9). The parameters needed to
calculate A depend strongly on the local market conditions,
boiler efficiency, and fuel type; these examples use the
data presented in Table 1 to calculate A. Table 2 shows the
Equation 15a is used for laminar flow, when Re < 2,000. values of (AB)1/(5+n) used to find the optimal diameter based
Equation 15b is used for transition flow, 2,000 < Re < 4,000. on flow regime and fuel type.
Equation 15c is used for turbulent flow, Re > 4,000. Example 1. A carbon steel steam pipeline transports
For laminar flow, the explicit solution of Eq. 13 is low-pressure saturated steam. The steam flowrate is
B = 3.24. For the other flow regimes, the mean value of B 1,000 kg/hr and the pipe’s absolute roughness through its
should be estimated after integration. lifecycle is ε = 0.5 mm.
Solving Eq. 13 for transition flow:
Table 1. Parameters for calculating the simplifying term A.
Source: Ref 3.
Parameter Example 1 Example 2
Y 8,000 hr/yr 8,000 hr/yr
CF 0.16 $/Nm3 0.29 $/kg
For turbulent flow (with an upper limit on the integral
J 0.5 0.5
of Re = 108):
m 330 330
n 1.5 1.5
E 0.92 0.88
K 36 MJ/ Nm3 40 MJ/kg
F 6.5 6.5
The friction factor must be known to obtain the optimal
pipe diameter, so an iterative procedure is needed to solve a+b 0.2 0.2
Eq. 11. One way to solve Eq. 11 is to assume a friction fac- A 281×10–6 479×10–6
tor and apply the iterative procedure. Since steam typically
flows in the turbulent regime, a single iteration is sufficient Table 2. Values of (AB)1/(5+n) for
to solve the problem. laminar, transition, and turbulent flow.
The working life of an energy plant in a chemical Flow Regime Example 1 Example 2
process industries (CPI) facility is at least five years, but Laminar, B= 3.24 0.341 0.370
may be as long as 20 years. Usually a value of a between
Transition, B= 3.86 0.350 0.380
0.2 yr–1 and 0.05 yr–1 is acceptable for most plants. Mainte-
Turbulent, B= 4.34 0.356 0.387
nance costs of a pipeline are usually assumed to be 1–5% of
Article continues on next page
Copyright © 2018 American Institute of Chemical Engineers (AIChE) CEP August 2018 www.aiche.org/cep 25
Heat Transfer
Table 3. Comparison of saturated steam velocities calculated by Eq. 18 and literature recommendations for Example 1.
Superheated Dopt, mm Velocity, m/sec
Steam Pressure, (from Eq. 18)
Eq. 18 Ref. 5 Ref. 6 Ref. 7 Ref. 8 Ref. 9
bar
1 122.6 37.0 28.6 16.0
2 103.2 28.6 23.0 14.1
60
20 bar 10 bar
15 bar The procedure is the same as in the previous example.
8 bar
50
5 bar
Table 4 presents the results based on Eq. 19 and recom-
mended velocities (5–9). Figure 2 plots annualized cost as
a function of pipe diameter at a pressure of 30 bar. Only in
40
the vicinity of the minimum diameter of 437 mm is it pos-
Annual Cost, ($/yr)/m
2 bar
1 bar sible to achieve annualized costs under $200/yr per meter
30 of pipeline.
Comparing the examples. In Example 1, velocities
recommended in the literature yield results that match
20
those obtained by Eq. 11 reasonably well. However,
in Example 2, the steam velocities recommended in the lit-
10
erature produce results that deviate significantly from those
Optimal Velocity obtained by Eq. 11, and they cannot be recommended for
engineering purposes (6–8). Although the recommendations
0
10 20 30 40 50 60 obtained from the literature are in everyday use by many
Velocity, m/sec engineers and are published in well-known books,
p Figure 1. Annualized cost per meter of pipeline as a function of steam it has to be noted that they cannot be linked to an
velocity. The red line connects the optimized results for Example 1. economic criterion.
26 www.aiche.org/cep August 2018 CEP Copyright © 2018 American Institute of Chemical Engineers (AIChE)
Table 4. Comparrison of saturated steam velocities calculated by Eq. 19 and literature recommendations for Example 2.
Closing thoughts
Since pipeline capital and operating costs can signifi-
cantly influence total plant expenses, fluid transportation is Literature Cited
always a significant economic factor in a plant’s design. 1. Genereaux, R. P., “Fluid–Flow Design Methods,” Industrial and
The simple optimization model of pipe diameter for Engineering Chemistry, 29, pp. 385–388 (1937).
2. Sarchet, B. R., and A. P. Colburn, “Economic Pipe Size in the
steam pipelines can be applied to both superheated and Transportation of Viscous and Nonviscous Fluids,” Industrial
saturated steam pipelines and includes the cost of fuel for and Engineering Chemistry, 32, pp. 1249–1252 (1940).
the boiler operation. The values calculated by the proposed 3. Genić, S., et al., “Economic Optimization of Pipe Diameter for
model differ significantly from methods and data recom- Complete Turbulence,” Energy and Buildings, 45, pp. 335–338
mended in the literature. (2012).
4. Genić, S., and B. Jaćimović, “Reconsideration of the Friction
Optimal pipeline diameters in any particular project
Factor Data and Equations for Smooth, Rough, and Transi-
must be determined by a profitability study that includes the tion Pipe Flow” presented at the 1st International Conference
optimization of various pipeline parameters. Other con- on Computational Methods and Applications in Engineering,
siderations when designing a steam piping system include Timisoara, Romania (May 2018).
the piping’s material of construction, the thickness of the 5. Tube Turns, Inc., “Piping Engineering,” 6th Ed., Louisville, KY,
(1986).
piping, the efficiency of the system, and any other financial
6. Simpson, L. L., “Sizing Piping for Process Plants,” Chemical
incentives or penalties that might be imposed upon plant Engineering, 75 (14), pp. 192–193 (1968).
construction. The simple model proposed here can be used 7. Walas, S. M., “Chemical Process Equipment — Selection and
as a guideline in early stages of design for quick estima- Design,” Butterworth-Heinemann, Boston, MA (1990).
tions, so it should be treated as just a small piece of 8. Ludwig, E. E., “Applied Process Design for Chemical and Petro-
the design puzzle. CEP chemical Plants,” Gulf Publishing Co., Houston, TX (1991).
9. “VDI Heat Atlas,” 2nd Ed., Springer-Verlag Berlin Heidelberg,
4,000 Berlin (2010).
Operational Cost
1,000 Acknowledgments
The authors thank the Ministry of Education, Science, and Technological
600 Development of Serbia for partial support of this study through the Project
of Energy Efficiency.
Annual Cost, ($/yr)/m
200
Copyright © 2018 American Institute of Chemical Engineers (AIChE) CEP August 2018 www.aiche.org/cep 27