Vous êtes sur la page 1sur 52

This degree project has been carried out on behalf

of the department of Power Modules at Ericsson.


Supervisor at Ericsson: Anders Petersson

Input interface requirements on board mounted DC/DC converters

Krav på ingångsgränssnittet till kortmonterade DC/DC-omvandlare

ALEXANDRA CRONEBÄCK

Degree project, in Electrical engineering, second level


Supervisor at KTH: Elias Said
Examiner: Thomas Lindh
School of Technology and Health
TRITA-STH 2013:33

Royal Institute of Technology


School of Technology and Health
136 40 Handen, Sweden
http://www.kth.se/sth

i
Abstract
This thesis has been carried out on behalf of the department of Power Modules at Ericsson.

In a telecom system interface A is a physical point between the power supply system and the
telecommunication equipment described in a European standard called ETSI EN 300 132-2. This
interface is also described in the American standard ATIS-0600315.2007. For board-mounted
products, such as DC/DC converters, a well-defined input interface description is lacking.

The goal of this thesis was to evaluate if the requirements in the standards ETSI EN 300 132-2 and
ATIS-0600315.2007 are viable for the input interface of DC/DC converters. A part of this goal was
also to investigate and analyze how the systems, in which the DC/DC converters operate, works.

To be able to determine if any of the two standards, ETSI and ATIS, are viable for use for the input
interface, both were reviewed and described with focus on voltage levels and transients.

In the information gathering phase it became clear that an extended limitation was needed. Therefore,
in order to investigate what happens from interface A to the input interface of DC/DC converters, the
system used in this thesis is the EBS LOD (Ericsson Blade System – Low Ohmic Distribution). EBS is
one of the systems in Core sites.

The report describes the construction of EBS where in the PFM (Power Fan Module), backplanes and
various boards are important parts. Furthermore some key principles within Core sites, such as HOD
(High Ohmic Distribution), LOD, Two-wire system and Three-wire system, are also described in order
to explain how the EBS system works.

EBS (including PIM (Power Interface Module)) was modeled in OrCad PSpice, with both one board
and 26 boards, and was simulated with different transients at an input to the system. The simulation
results show that the high voltages never reach the DC/DC converter and that they therefore are well
protected from transients in an EBS LOD system.

In order to determine whether the standards ETSI and ATIS are viable for the input interface of
DC/DC converters, it is concluded that more investigations, tests and simulations are needed.

iii
Sammanfattning
Detta examensarbete har utförts på uppdrag av avdelningen Power Modules på Ericsson.

I ett telekommunikationssystem är gränssnitt A en fysisk punkt mellan kraftsystemet och


telekomutrustningen som beskrivs i en europeisk standard som kallas ETSI EN 300 132-2. Detta
gränssnitt är också beskrivet i den amerikanska standarden ATIS-0.600.315.2007. För kortmonterade
produkter, såsom DC/DC-omvandlare, saknas en beskrivning av ett väldefinierat ingångsgränssnitt.

Målet med detta examensarbete var att utvärdera om kraven i standarderna ETSI EN 300 132-2 och
ATIS-0.600.315.2007 är applicerbara på ingångsgränssnittet till DC/DC-omvandlare. En del av detta
mål var också att utreda och analysera hur systemen, i vilka DC/DC-omvandlare finns, fungerar.

För att kunna avgöra om de två standarderna ETSI och ATIS var applicerbara, granskades de och
beskrevs med fokus på spänningsnivåer och transienter.

I informationsinsamlingsfasen stod det klart att en utökad avgränsning behövdes. Slutsatsen av denna
begränsning var att systemet som skulle användas i detta examensarbete var EBS LOD (Ericsson
Blade System – Low Ohmic Distribution), för att undersöka vad som händer från gränssnittet A till
ingångsgränssnittet av DC/DC omvandlare. EBS är ett av systemen inom Core sites.

I rapporten beskrivs konstruktionen av EBS där PFM (Power Fan Module), backplan och olika kort
anges som viktiga delar. Dessutom beskrivs några viktiga principer inom Core sites, såsom HOD
(High Ohmic Distribution), LOD, Två-ledar-system och Tre-ledar-system.

EBS (inklusive PIM (Power Interface Module)) modellerades i OrCad Pspice, med både ett kort och
26 kort, och simulerades med olika transienter på en av ingångarna till systemet. Simuleringsresultaten
visar att de höga spänningarna aldrig når DC/DC-omvandlaren och att dessa alltså är väl skyddade mot
transienter i ett EBS LOD system.

För att kunna avgöra om standarderna ETSI och ATIS är applicerbara på ingångsgränssnittet till
DC/DC-omvandlare är slutsatsen att flera utredningar, tester och simuleringar behöver göras.

v
Acknowledgements
I would like to thank Anders Petersson, my supervisor at Ericsson, for his support and contribution of
knowledge to this thesis. I would also like to thank Åke Ericsson, for contributing valuable
information about Core sites, and Mattias Andersson, for advices and help with simulations. And last
but not least I want to thank Elias Said, my supervisor at KTH STH, for giving me advice and
guidance during this thesis and feedback to the report.

Alexandra Cronebäck
Stockholm, May 2013

vii
Table of contents
1 Abbreviations .................................................................................................................................. 1
2 Introduction ..................................................................................................................................... 3
2.1 Background ............................................................................................................................. 3
2.2 Problem definition ................................................................................................................... 3
2.3 Goals........................................................................................................................................ 4
2.4 Delimitations ........................................................................................................................... 4
2.5 Methods ................................................................................................................................... 4
3 Standards ......................................................................................................................................... 5
3.1 Standard from ETSI................................................................................................................. 5
3.1.1 Requirements ................................................................................................................... 5
3.2 Standard from ATIS ................................................................................................................ 9
3.2.1 Voltage levels/Voltage requirements ............................................................................ 10
4 System ........................................................................................................................................... 12
4.1 Core site................................................................................................................................. 12
4.1.1 HOD & LOD ................................................................................................................. 12
4.1.2 Two-wire or three-wire system ..................................................................................... 14
4.1.3 Redundancy ................................................................................................................... 15
4.1.4 Ericsson Blade System .................................................................................................. 15
5 Simulation ..................................................................................................................................... 18
5.1 System definition................................................................................................................... 18
5.1.1 PIM ................................................................................................................................ 19
5.1.2 PFM ............................................................................................................................... 23
5.1.3 The system in PSpice .................................................................................................... 25
6 Results ........................................................................................................................................... 26
6.1 Simulation with -53 V and one board.................................................................................... 26
6.2 Simulation with -53 V and 26 boards .................................................................................... 26
6.3 Transient simulation with one board ..................................................................................... 28
6.4 Transient simulation with 26 boards ..................................................................................... 31
6.5 ATIS transient at input to PIM .............................................................................................. 34
7 Analysis ......................................................................................................................................... 36
7.1 Standards ............................................................................................................................... 36
7.2 Extended delimitations .......................................................................................................... 36
7.3 Data analysis.......................................................................................................................... 37
7.3.1 No transient ................................................................................................................... 37

ix
7.3.2 Transient PFM ............................................................................................................... 37
7.3.3 Transient PIM ................................................................................................................ 38
7.3.4 DC/DC converter ........................................................................................................... 38
8 Conclusions ................................................................................................................................... 39
9 Continous work ............................................................................................................................. 40
10 References ..................................................................................................................................... 41
11 Figure references ........................................................................................................................... 42

x
1 Abbreviations
BSC – Base Station Controller
CMXB – Component Main Switch Board
DC – Direct Current
EBS – Ericsson Blade System
EGEM2 – Evolved Generic Ericsson Magazine 2
EPDU/PDU – Enclosed Power Distribution Unit/Power Distribution Unit
HOD – High Ohmic Distribution
LOD – Low Ohmic Distribution
PDF – Power Distribution Frame
PFM – Power Fan Module
PIM – Power Interface Modules
RBS – Radio Base Station
RNC – Radio Network Controller
SCXB – System Control Switch Board
SGSN-MME – Serving GPRS Support Node – Mobility Management Entity
TVS – Transient Voltage Suppression
TLE – Telecommunications Load Equipment

1
2
2 Introduction
This thesis has been carried out on behalf of the department of Power Modules at Ericsson.

2.1 Background
Ericsson is a world-leading provider of telecommunications equipment and related services to mobile
and fixed network operators globally.

Ericsson has a department specialized in developing power modules. Their board-mounted products
can be divided into DC/DC converters, intermediate bus converters (IBC), Point Of Load (POL)
regulators, Power Interface Modules (PIM) and Board Power Management (BPM) supporting product.
The products are primarily designed for telecom and datacom systems, such as radio base stations and
switches/routers, but they are also used in medical and industrial applications, among other branches
(1).

In a telecom power distribution system different interfaces are described in standards. One of these
standards is ETSI EN 300 132-2. The interface described there is called interface A and is a physical
point between the power supply system and the power consuming telecommunication equipment, see
Figure 1 (2). However, for board-mounted products, such as DC/DC converters, a well-defined input
interface description is lacking.

Today, when developing power modules in general and DC/DC converters in particular there are no
standards specified for the input interface, instead past developing references combined with specified
demands has been used to verify the requirements of each power module.

Interface A
DC power supply conductors

DC Power Supply
Distribution & Telecom equipment
protection System block

Input interface
DC/DC
? converter

Telecom equipment
System block
Interface A

Figure 1: Where to find interface A and the input interface of a DC/DC converter.
The question mark represents undefined parts of the system. [1]

2.2 Problem definition


This thesis has investigated how the European standards ETSI EN 300 132-2 works and if the
requirements in this standard are viable to use also for the input interface for DC/DC converter in
telecom and datacom systems. Since Power Modules deals a lot with the American market, the
American standard ATIS-0600315.2007 has also been investigated. ATIS and ETSI are the most
common standards used for interface A around the world.

3
The thesis has been looking into this from different angles regarding relevant requirements such as:

 Power Line Disturbances


 Voltage Spikes
 Current Ripple
 Inrush current
 Relevant steady state voltage requirements
 Earthing and bonding and the difference between two-wire and three-wire distribution system
(if any)
 Other aspects that may have been relevant.

2.3 Goals
The goal of this thesis was to evaluate if the requirements in the standard ETSI EN 300 132-2 and the
standard ATIS-0600315.2007 are viable for the input interface of DC/DC converters or if there were
any other relevant standards that could be used. This information in turn may be used by Ericsson for
future designs guidance when developing DC/DC converters and as a reference for an application
note.

A part of the goal in this thesis was also to investigate and analyze how the systems, in which the
DC/DC converters operate, works. This includes analyzing feeds to the inputs to the DC/DC
converters and how well protected the converters are in the systems.

2.4 Delimitations
This thesis has been limited to investigate DC/DC converters in telecom and datacom systems. During
the process of working with this thesis further delimitations has been included. These delimitations are
described in 7.2 Extended delimitations.

2.5 Methods
To gather information for this thesis following methods has been used.

 Literature studies of the different standards.


 Literature studies of different systems at Ericsson.
 Interviews with relevant co-workers at Ericsson.

When sufficient information has been gathered simulations (in OrCad PSpice) has been executed and
results have been analyzed throughout the process.

4
3 Standards
As described in the introduction the standards ETSI EN 300 132-2 and ATIS-0600315.2007 plays an
important role in this work. This section discusses the key points of these two standards.

3.1 Standard from ETSI


The standard ETSI EN 300 132-2 is a European Standard (EN) and is produced by ETSI Technical
Committee Environmental Engineering (EE).

This standard describes the requirements for the interface between telecom and datacom (ICT)
equipment and its power supply, also called interface A. The standard is not only used for providing
electrical compatibility at this point, it is also used for different system blocks connected to the same
power supply.

The reason for a need of a standard for this interface is to secure the usage of the same characteristics
for all telecom and datacom equipments. This makes it easier for different load units to interwork and
makes the installation, operation and maintenance of equipment/systems from different origins
simpler.

3.1.1 Requirements
In ETSI EN 300 132-2 the requirements are defined as followed (2, page 6):

 the output of the power supply equipment or power supply installation of telecommunications centers
providing power at the interface "A";
 the power supply input of any type of telecommunications and datacom (ICT) equipment installed at
telecommunication centres that are connected to interface "A" powered by DC;
 any type of telecommunications and datacom (ICT) equipment, installed in access networks and
customers' premises, the DC interface "A" of which is also used by equipment requiring a supply to the
present document.
 any type of telecommunication and datacom (ICT) equipment powered by DC, used in the fixed and
mobile networks installed in different locations as building, shelter, street cabinet.

DC power supply conductors

Telecom equipment

System block
Interface A

Figure 2: Definition of interface A [2].

5
3.1.1.1 Voltage levels
In ETSI it is stated that the nominal voltage at interface A shall be -48 VDC, it is negative because the
positive conductor is connected to earth.

It is also stated that the normal service voltage range for this system shall be -40.5 VDC to -57.0 VDC at
interface A. That is the range where the system operates most of the time and there should not be a
degradation of service performance at this range.

The range where the equipment is not expected to maintain normal service but will survive
undamaged is called abnormal service voltage range. This voltage range at interface A is found in
Table 1.

From (VDC) To (VDC)


0.0 -40.5
-57.0 -60.0
Table 1: Abnormal service voltage range for a -40 VDC system.

When the supply is back to normal voltage range, the telecommunications and datacom equipment
shall resume operating according to its specifications. The power supply shall not have been
disconnected by operations of e.g. circuit breakers or fuses.

-60 VDC systems

If a -60 VDC system is used some of the requirements at interface A will change. The nominal value of
the supply voltage shall be -60.0 VDC and the normal service voltage range shall be -50.0 VDC to -72.0
VDC.

The abnormal service voltage range is found in Table 2 (2).

From (VDC) To (VDC)


0.0 -50.0
-72.0 -75.0
Table 2: Abnormal service voltage range for a -60 VDC system.

3.1.1.2 Voltage transients


One reason for transients at interface A is when faults occur in the power distribution system, which
can be e.g. a short circuit of the negative conductors to any earthed part of the equipment (3). This sort
of transients is characterized by a voltage drop in the range: 0 VDC to -40.5 VDC, and then an
overvoltage with a value over the maximum steady state abnormal service voltage range.

If a voltage transient has occurred the equipment shall continue to function, without manual
intervention, within its operational specification and the equipment should not have been disconnected
from the power supply by operation of circuit breakers and fuses.

To make the power supply system more secure some minor arrangements may be needed, for
example dual feeding system, high-ohmic distribution system and independent power distribution (2).

The following information about voltage transients are described in a technical report, ETSI TR
100 283, referenced in the ETSI standard.

6
Power distribution
It is common that the equipment in telecommunication centers has a backup battery in case of a mains
failure. A problem with these batteries are that they can store a very large amount of energy, which
can result in a delivery of currents far in access of the ratings of fuses and circuit breakers under fault
conditions.

In a typical power distribution system (see Figure 3) in a large installation, current is supplied from
both the power plant and battery. Furthermore this current is broken down into a number of lower
current feeds at each Power Distribution Frame (PDF). Given that the feeds have a lower current, the
power cable which supplies the PDFs are sized according to the current they have to carry as well as
the voltage drop that can be tolerated. These cables are also protected by suitably rated fuses or
breakers in each PDF.

Figure 3: A power distribution with only the negative conductors [3].

Description of transients
In branches of the distribution that is not associated with the fault a voltage transient can occur, it can
for example be a branch sharing the same secondary PDF as the branch with the fault. This transient
can be divided into two parts, the first part begins when the error occur (t0, see Figure 4) and ends
when the protection device clears (t1). The second part begins where the first part ends and finishes
when the voltage returns to its value before the fault was applied (t2).

7
Figure 4: Waveforms of a voltage transient and a current transient [4].

Part 1 (t0 to t1): Initially there is a large voltage drop, se voltage curve in Figure 4. This drop is caused
by inductance in the parts of the fault circuit that are shared with the branch in question and the
duration off this drop depends on the value of the inductance. If the value of the inductance is small
the voltage will recover quickly. If the inductance value is large then the fault current might not reach
the value limited by the resistance in the cables from the battery. If this happens the fuse may clear the
fault circuit before it reaches the determined optimal value.

To reduce the fault current and voltage drop, cables with different sizes and resistances can be used to
apportioning the resistance.

Part 2 (t1 to t2): When the fault circuit is open there is a higher flow of current in the cables. The
energy created by this higher flow of current needs to gradually reduce without harming the equipment
connected to the power distribution. This increase in energy is possible to absorb with the capacitances
distributed over the power distribution. These capacitances may i.e. be placed in the PDFs or by the
entrance to the DC/DC converters. This is made to create a “hold up” function during part one of the
transient. Another way to make the energy disperse faster is to use absorbing transients units. These
units will then works as zener diodes to quickly absorb the energy. These zener diodes are placed over
the positive and negative conductor (3).

3.1.1.3 Protection of a power supply


To protect the power supply at interface A, circuit breakers, fuses and equivalent devices can be used.
These protection devices are defined with a current value of 1.5 times Im (maximum steady state input
current, stated by the manufactures). These definitions are made to avoid that the normal service
voltage range is affected by the protection devices (2).

A difference between fuses and circuit breakers is the reaction speed to fault currents.
To break a current with a higher value than the stated one, the fuse needs time, and the higher the
current the faster the fuse will reach is meltdown and execute. Although even if the values of the
current are extremely high the fuse will still have a limited execution time. These execution times may
vary between 1 ms to 10 ms depending on design of the fuse and the level of the current.

8
Circuit breakers react differently to higher currents than fuses do. In the case of circuit breakers the
issues is the inertia of the breakers mechanics and connections which determines the time to clear the
higher current. The execution time for the circuit breakers is, compared to fuses, longer and spans
between 4 ms to over 15 ms (3).

3.1.1.4 Inrush current


To set a limit for the inrush current a ratio between the inrush current (It) and maximum steady state
current (Im) at interface A is used. Figure 5 shows the limits that the ratio shall not exceed when the
voltage is within the normal service range. The criteria are summarized in ETSI EN 300 132-2 as
followed (2, page 13):

 Below 0.1 ms, the inrush current is not defined.


 Below 0.9 ms the It/Im ratio shall be lower than 48.
 Above 1 ms: the curve corresponds to the maximum tripping limit of majority of existing protective
devices.

Figure 5: Ratio of the inrush current (It) and the maximum steady state current (Im) [5].

3.2 Standard from ATIS


The ATIS standard ATIS-0600315.2007 “Voltage levels for DC-powered equipment used in the
telecommunications environment” is an American National Standard produced by the Alliance for
Telecommunications Industry Solutions (ATIS) and approved by American National Standards
Institute, Inc (ANSI).

This standard does not use the expression interface A, instead they refer to telecommunications load
equipment (TLE). TLE is an equipment powered by a DC power system with a primary or secondary
distribution.

9
3.2.1 Voltage levels/Voltage requirements
A -48 volts TLE shall meet its operational requirements with following values:

Nominal voltage Maximum VDC Typical VDC Minimum VDC


-48 -40.0 -53.0 -56.7
Table 3: Steady state voltages.

If the TLE is exposed to a voltage between 0 VDC and the maximum voltage level or a voltage between
0 VDC and the minimum voltage level it shall not be permanently damaged or have its performance
degraded. The equipment shall restart automatically after the voltage is returned to a level under -48
VDC without manual intervention.

3.2.1.1 Cutoff and recovery


The equipment shall have a built in function that will turn the equipment off if the voltage at the input
goes over -38.5 VDC (±1.0 VDC) for more than 10 seconds, or reduce the power that the equipment
utilizes with less than 20 % over -38.5 VDC (±1.0 VDC).

The equipment shall remain in these states until the voltage has returned to a level of -45 VDC (±3.0
VDC), unless the voltage is between 0 and -20 VDC for more than 20 ms, then it is allowed to recover at
voltages larger than -38.5 VDC (±1.0 VDC).

The cutoff and recovery shall not permanently damage the equipment or degrade the performance of
it. It shall also not cause fuses or circuit breakers to operate. The equipment shall recover to normal
operation within 30 minutes as a standard without manual intervention.

3.2.1.2 Transients
A TLE with an overvoltage transient of -75 VDC, a reasonable worst case scenario, applied between the
input terminals shall continue to operate properly, and shall not be damaged or degraded in
performance. The following requirements shall be met:

 A rise and fall time of 10 VDC/ms (±1.0 VDC)


 Rise and fall rates measured at 10 % and 90 % points.
 A duration of 9.5 ms (±0.5 ms)

Transients from protective device operation


As pointed out in the section of the ETSI standard transients can occur because of operations of
protective devices. In ATIS the total protective device operation transient is described with a figure,
see Figure 6. At first, the voltage drops from 50 V to 5 V, after around 10 ms there is an impulse
transient to the level of 100 V. After 50 µs the voltage drops to 75 V and after around 10 ms the
voltage is back to 50 V (4). Notable is that the voltage in the figure is positive, but the same curve can
be used for negative values.

10
Figure 6: Total protective device operation transient [6].

11
4 System
In order to simulate and analyze what happens from interface A to the input interface of Power
Modules DC/DC converters, an identification of different systems must be made and an examination
of what components the systems contains. Two of the areas where DC/DC converters are used are
Radio Base Stations (RBS’s) and Core sites. This thesis has been concentrated on the Core sites.

4.1 Core site


Core site products ranges from cabinet solutions, to secure power supply and cables, where all
products are standardized. This makes the installation for a complete Core site easier and the reliability
higher. The products are developed parallel with different network nodes, enabling a support for e.g.
controllers, Base Station Controller (BSC), Radio Network Controller (RNC), EVO, Media Gateways,
GPRS nodes and circuit-switched nodes (5).

Ericsson Blade System (EBS) is a system used for several applications in Core. Before the description
of the EBS, some important key principles will be explained, that are different distributions and wire
arrangements.

4.1.1 HOD & LOD


There are two principles which are mainly used in a -48 VDC telecommunication system, the High
Ohmic Distribution (HOD) and the Low Ohmic Distribution (LOD). These systems are quite different
in terms of structure, but they both fulfill requirements such as electromagnetic compatibility (EMC),
reliability, basic safety requirements etc. Both principles also meets standards such as ETSI and ANSI,
and has a full service input voltage range between approximately -40 to -57 VDC .

4.1.1.1 HOD
The HOD principle (see Figure 7) has a 30 mΩ (Rstrip) resistor in series with a circuit breaker (15 A for
500 W and 30 A for 800 W) at the output of the -48 VDC power plant. With the help of Rstrip HOD can
maintain the output voltage from the power plant within the normal service range (-40.5 VDC to -57.0
VDC) during the period of a transient before a circuit breaker operates. This means that the HOD-
arrangement will make sure that the voltage never will drop below -43 VDC at short circuits and
overloads.

Rstrip Cabinet
A-feed
AC 30 A 30 m Ω
DC
Rstrip
RB B-feed
30 A 30 m Ω

Figure 7: The HOD principle [7].

12
More features of the HOD-system:

 The size of a short circuit current is limited to maximum 1 kA.


 A great advantage with HOD is: If a single fault occurs in the system, only a limited part is
affected. This means that the part of the system that is not affected can continue to function as
usual. The same applies if a part of the system is totally knocked out.
 A HOD system can never be connected directly to a LOD system. This has been solved with
an adapter, an EPDU/PDU (Enclosed Power Distribution Unit/Power Distribution Unit),
which is placed between the systems and converts LOD to HOD.
 HOD with the power 500 W has been Ericsson's standard power since the 1970s but from year
2000 the power has increased to 800 W. This is an upper limit due to power loss and a large
voltage drop across the 30 mΩ resistor.

4.1.1.2 LOD
The LOD principle (see Figure 8) has a hold-up capacitor by the input to the telecommunication
equipment. This is needed if there, as an example, is a short circuit, since the voltage from the power
plant will drop below -40 VDC in an LOD system. With the help of a blocking diode the hold-up
capacitor will maintain the voltage above lower limits during the 10 ms of a transient until the circuit
breaker operates. The size of a short circuit current can be 3-5 kA.

More features of the LOD-system:

 Since there are no requirements for a resistor and a circuit breaker at the output of the power
plant, there is a larger freedom at this stage.
 A current limiter is needed to keep the inrush current from the capacitor on an acceptable
level.
 The overall efficiency will be reduced because of the continuous power loss in the blocking
diode during normal service.

Hold up
capacitor &
B-feed blocking diode
60 A
Cabinet
A-feed
AC 250 A 60 A
C
DC
RB
250 A

Figure 8: The LOD principle [7].

13
4.1.2 Two-wire or three-wire system
The choice between a two-wire or three-wire power arrangement is often determined by the
organizations history, traditions, what is already installed, knowledge and experience, since both of the
systems meets electric safety standards and EMC standards.

Figure 9: Two-wire and a three-wire system [8].

4.1.2.1 Two-wire
This system has a common positive return conductor and DC Protective Earth (see Figure 9). The
positive conductor is connected to the framework of the subrack.

Some of the advantages with a two-wire power arrangement:

 There are several parameters that make this system more cost efficient compared with the
three-wire system. There are no safety requirements for galvanic isolated DC/DC converters,
it uses simpler filters, filters are only needed in the negative conductor, and there are no costs
for isolation between the positive conductor and the frame of the subrack.
 The positive conductor works as a DC protective earth conductor for fault currents until the
circuit breaker operates.
 The total resistance is very low, since all the positive conductors are connected in parallel.

Some of the disadvantages with a two-wire power arrangement:

 There are few outgoing distributions because of small power plants, to keep the voltage drop
below a certain level Strengthening Cables must be used. They are often 50 mm2 and are
routed along and in parallel with the shortest positive conductor to prevent high current in
these conductors.

4.1.2.2 Three-wire
The positive conductor in three-wire arrangement is isolated from the frameworks of the subrack and a
separate DC Protective Earth is connected to the subrack. The DC/DC converters in the systems must
be isolated.

14
An advantage with a three-wire power arrangement:

 Strengthening cables are not needed.

Some of the disadvantages with a three-wire power arrangement:

 Compared to the 2-wire system, this system requires higher cost since galvanic isolated
DC/DC converters is a requirement and costs for the isolation between the positive conductor
and the frame on the subrack.
 More complex low frequency and high frequency filters.

4.1.3 Redundancy
To achieve a high reliability, most of Ericsson’s telecom systems have redundant feeds, one A-feed
and one B-feed. During normal service the power consumption will be divided equally between the
two feeds. An output of 800 W will be divided into 400 W at feed-A and 400 W at feed-B. If one of
the feeds would go down, the other one will take over the total power consumption (5).

4.1.4 Ericsson Blade System


Ericsson Blade System (EBS) is a system used for several telecommunication systems with different
interfaces and processing capacities. It can be used for different control nodes and the hardware can be
changed for desired application. EBS can be configured for example server applications or traditional
circuit switching.

4.1.4.1 Construction
The cabinet used is the BYB 501 (see Figure 10), which is the most commonly used cabinet for Core
products (6). The cabinet has room for three subracks and one cabinet switch. If the system is
supposed to be used with IT-equipment the BYB 504 can be used instead, since it has different
dimensions.

The name of the subracks is Evolved Generic Ericsson Magazine 2 (EGEM2) and the EBS
components are placed in here. EGEM2 take care of the power, cooling and provides the basic
structure for switching and routing (7).

An important part of the subrack is the Power Fan Module (PFM). There are two PFMs in one
subrack, one for feed-A and one for feed-B. Every PFM contains a fan unit that controls three fans
depending on the temperature in the rack. The PFMs two inputs, with power from the same voltage
source, are combined with the help of different power blocks to one output. The output is connected to
one of the power rails (A-feed or B-feed) in the backplane. There are different types of PFMs:

 HOD, 2400 W or 3200 W, with a two-wire power distribution.


 LOD, 2400 W or 3200 W, with a two-wire power distribution (8) (9).

The EGEM2 has 24 slots for different kinds of boards, plus two slots dedicated for System Control
Switch Board (SCXB) and two slots dedicated for Component Main Switch Board (CMXB). The 24
slots have an Ethernet connection through the backplane to both the SCXBs and the CMCBs, this is
called dual star Ethernet topology. The boards have two inputs and get its power from the backplane,
from both the A-feed and B-feed.

15
There are more devices that can be connected to the EBS but they are not important for this project,
these are for example a converter for optical Ethernet connections or boards for other applications. The
important devices for the investigation of the input interface are the PFM, the backplane and boards
for Core applications. It is on these boards which the DC/DC converters are placed (7).

Cabinet BYB 501

Ethernet switches,
SCXB & CMXB

Power & fan


module (PFM) x 3

Processing
blades/Processor
boards

Subrack (EGEM2) x 3

Figure 10: Ericsson Blade System for SGSN-MME [9].

16
4.1.4.2 Core och EBS
EBS is a system that will be used in the future for some of Core applications. Examples of these are
SGSN-MME and Evo Controller. To get an overview of what kind of systems it can be, here are two
short descriptions:

SGSN-MME stands for Serving GPRS Support Node – Mobility Management Entity. This system is
used in GSM (2G), WCDMA (3G) and LTE (4G) networks for switching packet-data and for
management of the mobility (10).

The Evo Controller is a controller used for GSM, CDMA and WCDMA networks. The latest version,
Evo Controller 8200, can be used as a multi controller with both BSC (used for GSM) and RNC (used
for UMTS) in the same configuration. It can also be used only as a BSC or RNC. The development of
the efficiency of the controllers is important, this due to the increasing data traffic caused by the many
smart phones used in the world (11).

These two systems differ a bit but the power units are the same, and that are also the important parts
for this project.

17
5 Simulation
After completing the identification of the system, the next step was to perform a number of
simulations. In order to complete the simulation and make it as reliable as possible, a more detailed
analysis of the system parts was needed. The simulation was performed in the program OrCad Pspice.

5.1 System definition


An EBS are either HOD or LOD, the choice between the two is decided by which PFM being used.
The system can also be either HOD or LOD depending on the power distribution used to power it.

HOD systems are slowly being phased out, and will not be used at Ericsson in the future. Therefore,
this project has been concentrated on the LOD version of EBS.

With the help from Åke Ericsson, Expert of Site Power and Grounding at Ericsson, a model of EBS
was drawn (see Figure 11) containing the following parts:

 PFM
o Current limiter
 Backplane
 A maximum of 28 boards, 24 slots for general boards and 4 dedicated slots for SCXB/CMXB.
o One board:
 Current limiter (PIM)
 DC/DC-converter

In order to make a better visualization of how the system works, in figure 11, the system has been
divided in to multiple interfaces where the entrance to the DC/DC-converters was named interface C.

BP Interface B
Interface A PFM A

Boards (max 28)

Board

PFM B PIM DC
DC
A
B

Interface C

Figure 11: The LOD EBS system from interface A to interface C with only negative conductors.

18
In order to do a simulation with this system, more technical information was needed for the PFM and
the PIM.

5.1.1 PIM
The PIMs main function is to limit high inrush currents. To do this the PIM quickly turns of and then
turns on again, but limits the current to the chosen current limit. If the current limit is reached for
another 1-3 ms the PIM will shut down again. The PIM is constructed to withhold a transient input up
to 100 V.

In this work a PIM with a power of 200 W has been chosen. It has a current limit of 8.3 A and an input
voltage of 36-75 V. The PIM has two inputs, an A-feed and a B-feed where the positive pole is earth
(12).

Figure 13 is a model of the PIM with a constant load made in PSpice. The main goal when
constructing this model was to make it work as realistic as possible in the simulation. The model was
created together with Mattias Andersson, Senior Electrical engineer at Power Modules.

5.1.1.1 Description of the model


Figure 12 shows a voltage source (V7) providing a pulse called Vpulse. It can be replaced by any
preferred voltage source. The resistor used represents the impedance in the pulse. The resistance is
derived from the test method C2 in ATIS (4).

The component D6 in Figure 12 is a Transient Voltage Suppression (TVS) diode also known as a
transorb. The TVS diode protects against high voltage transients by starting conduct current at a
particular voltage, in this case at 64 V. The diode can either be uni-directional (one diode) or bi-
directional (two diodes in series) (13). In the PIM a bi-directional diode is used, this to protect against
reversed polarity. But the component used in the PIM was only available as a uni-directional version
I1
for PSpice.
8.3Adc

R2 D1
D8

Dbreak
0.5 STTH3002G

V7
V1 = 50 D6
V2 = 75 SMCJ64A
TD = 2m
TR = 2u
TF = 2u
PW = 10m
PER = 20m

0 I2

8.3Adc

R3 input to PIM with Vpulse.


Figure 12:The D4
D9

Dbreak
0.5 STTH3002G

V8
V1 = 50
D7
V2 = 75 19 SMCJ64A
TD = 2m
TR = 2u
TF = 2u
PW = 10m
PER = 20m
I1

8.3Adc

R2 D1
D8

Dbreak
0.5 STTH3002G

V7
V1 = 50 D6
V2 = 75 SMCJ64A
TD = 2m
TR = 2u
TF = 2u
PW = 10m
PER = 20m

V1

0 I2 C1
100u

8.3Adc

R3 D4
D9

Dbreak
0.5 STTH3002G

V8
V1 = 50 0
D7
V2 = 75
TD = 2m SMCJ64A
TR = 2u
TF = 2u
PW = 10m
PER = 20m
D1

STTH3002G

V1

G2
+
-
C1 G OUT
100u -5.6
0
IN

D4 U4
V6
200 X
X Y
Y
STTH3002G DIVIDER2
0

Figure 13: Model of PIM with a constant load.

20
Figure 14 shows a current limiter and it uses a current source limited to 8.3 A. When the input voltage
is 0 there are no current in the main circuit, but the current limiter (I1) has a flow of 8.3 A. The higher
the current in the main circuit, the lesser current will flow through the diode (D8). This is due to the
Kirchoffs current law. Given that D8 is a diode the current from the main circuit will take the path
through the current source, and this means that the current in the main circuit never can exceed 8.3 A.

The diode used is an ideal diode. If a non-ideal diode were to be used a voltage drop would occur and
the output voltage from the PIM would exceed the input voltage, when the opposite is wanted. To
make an (almost) ideal diode, Dbreak is used with following text in the model:
.model Dbreak D Is=1e-14 n=0.0001
This results in a voltage drop of 0.0001 V.

I1

8.3Adc

R2 D1
D8

Dbreak
0.5 STTH3002G
Figure 14: The current limiter.

50 In Figure 15 there D6
are two diodes, D1 and D4. These are so called ORing diodes and are used when
100 SMCJ64A
2m conductors needs to be connected. The diodes are used as a failsafe for the conductors. If one of the
2u
2u conductors malfunctions, resulting in a current drop, the higher current in the still functioning
= 10m conductor is prohibited from pushing in to the malfunctioning conductor.
= 20m

Shown as C1 in Figure 15 is a capacitor, with capacitance that is common used on the output of the
I1
PIM or input to the DC/DC converter.
8.3Adc

R2 D1
D8

Dbreak
0.5 STTH3002G

0 I2
D6
SMCJ64A

m
m 8.3Adc

R3 D4
D9
G2
+
-
0 I2 Dbreak C1 G
0.5 100u
STTH3002G
8.3Adc

R3 D4 V6
D9
200
Dbreak
0.5 STTH3002G
0
50
D7
100
2m SMCJ64A
D7 0
2u SMCJ64A
2u Figure 15: ORing diodes and output capacitor.
10m
= 20m

0 21

0
The load of the PIM, shown in Figure 16, is made to represent the DC/DC converter. It is a constant
power load, which means that the effect is kept at the same level at all times, in this case at 200 W.
This is an ideal circuit, although in reality the effect cannot be withheld to an exact level at all times.

In Figure 16 the DC-voltage source V6 is divided with the output voltage from the PIM, and the
voltage ratio goes out from U4. To limit the voltage and with that the current, a limiter is used. This
avoids the circuit from drawing to much current. The smallest amount of voltage in the PIM is 36 V,
which means that the highest current will be 5.6 A (200 W/ 36V = 5.6 A). In addition a converter
named as G2 in the model, is used to convert the voltage to output current. This means that the effect
of the circuit will be 200 W (P = U × I = VOUT_PIM × IOUT_G).

G2
+
-
C1 G OUT
100u -5.6
0

IN
U4
V6
200 X
X Y
Y
DIVIDER2
0

Figure 16: Constant load, representing a DC/DC converter.


0

A number of simulations were made to ensure that model was working as realistically accurate to the
real PIM as possible. Furthermore a comparison to the verification result was made, see Figure 17 and
Figure 18. A voltage step was simulated at the input, the voltage ranged from -50 V down to -75 V and
stayed at that level for 10 ms. The current increases as the voltage decreases, but it do not exceed 8.3
A because of the current limit. Then the circuit stabilizes. The most obvious differences between the
simulation and the verification are that the current does not stay at the current limit in the simulation as
long as in the verification, and also there is no current spike in the simulation. The flanks of VOUT are
in a comparison quite alike in both graphs which are due to charging and discharging of the output
capacitance.

16.6

0
IIN

-40.0
VOUT
VIN

-80.0
0s 2ms 4ms 6ms 8ms 10ms 12ms 14ms 16ms 18ms 20ms
V(V7:-) I(D1) V(G2:3,0)
Time

Figure 17: A simulation of the PIM model. X-axis = 2 ms/div & Y-axis = 40 -/div.

22
VOUT

VIN

IIN

Figure 18: Results from verification of PIM. CO = 100uF, X-axis = 2 ms/div & Y-axis = 50 V/div or 10 A/div.

Notably this is a simplified model and therefore a bit more ideal than a real PIM. An example of this is
the current spike in Figure 18. Since the model can limit the current to a desired value faster than the
PIM there is no current spike in Figure 17.

5.1.2 PFM
The PFM compares to the PIM quite well. It has two inputs but in the PFM both these inputs comes
from the same feed. It has a current limiter, ORing diodes, TVS diodes and an output capacitor (also
called a hold up capacitor in the PFM). One difference that it has is smaller capacitors between the
current limiter and ORing diodes. Of course the PFM has a lot more components, although these
described above are the ones most essential to the simulation.

Some parameters derived from the description of the PFM LOD 2400 W (14):

C ≥ 40 000 uF
L ≤ 1 uH
2400 W, 60 A @ -40.1 V.

According to Åke Ericsson, Expert of Site Power and Grounding at Ericsson, the inductance in a cable
is typically 0.8 µH per meter. In the simulations it is estimated that there is a cable length of 0.5 meters
from the PFM to a board and that is shown with an inductor of 0.4 µH. The PFM model is presented in
Figure 19.

23
I1

215.8Adc

D2
D8
-V_A_IN_1
Dbreak
STTH3002G

D19
D16 D18
SMCJ64A
SMCJ64A SMCJ64A

C6
6.6u

L2
1 2 -V_A_OUT
0.4uH

I2

215.8Adc C8
40m
D5
D9
-V_A_IN_2
Dbreak
STTH3002G

C7
D21 D17 D20
6.6u
SMCJ64A SMCJ64A SMCJ64A

-V_A_0 -V_A_0

Figure 19: Model of PFM.

24
5.1.3 The system in PSpice
The PFM model and the PIM model was connected and combined to one system in PSpice as shown
in Figure 20. To make the model easier to overview, hierarchically blocks where used for the PFM and
the PIM. A double click on the PIM+LOAD block will display the model shown in Figure 13 and a
double click on the PFM_A or PFM_ B blocks will display the model in Figure 19.

R2

PFM_A
0.05

-V_A_IN_1
-V_A_OUT
-V_A_IN_2

V1
-V_A_0 -V_A_0
53Vdc
Board
PFM_A

-V_A_IN

-V_A_0

PFM_B
0
-V_B_IN
-V_B_IN_1 -V_B_OUT
-V_B_IN_2
-V_B_0
-V_B_0
-V_B_0
R3
PFM_B

0.05
PIM+LOAD

V2
53Vdc

Figure 20: The system with PFMs and PIM+LOAD.

25
6 Results
This chapter shows the result of simulations with different scenarios.

6.1 Simulation with -53 V and one board


To see how the voltage changed through the system, a voltage of -53 V was applied on both feeds, see
Figure 20. -53 V is used since it is the value stated as a typical value in ATIS. This value is also stated
as a typical value in the specification for DC/DC converters.

The first simulation result presented in Figure 21 was made with only one board.

-51.4V

-51.6V

VOUT PIM
-51.8V

-52.0V

VOUT PFM_A/VA_IN PIM


-52.2V

-52.4V

-52.6V

-52.8V VIN PFM_A VIN A

-53.0V
0s 1ms 2ms 3ms 4ms 5ms 6ms 7ms 8ms 9ms 10ms 11ms 12ms 13ms 14ms 15ms 16ms 17ms 18ms 19ms 20ms
V(Board.C1:1,Board:-V_A_0) V(V1:-) V(R2:2,0) V(PFM_A:-V_A_OUT,0)
Time

Figure 21: VIN_A = -53 V, VIN PFM_A = -52.9 V, VOUT PFM_A/ VA_IN PIM = -52.2 V & VOUT PIM = -51.5 V.
X-axis = 0.2 ms/div & Y-axis = 0.05 V/div.

The voltage drop over PFM (52.9 V – 52.2 V = 0.7 V) and over PIM (52.2 V – 51.5 V = 0.7 V)
depends on the diodes in the models.

The simulated currents in the feeds from the PFMs to the PIM is roughly 1.94 A respectively. In the
PIM 0.8 mA per feed goes to the TVS diodes.

6.2 Simulation with -53 V and 26 boards


There are room for 28 boards in a subrack, 24 for general boards and four for dedicated boards. Since
only two of the four dedicated boards are mandatory, 26 boards are used in the simulation. All 26
boards will never be used all at the same time, since there is not enough power. The LOD PFM in this
thesis has an output power of 2400 W, where the fans uses 200 W which means that there is 2200 W
left for the boards. To do a simulation with 26 boards a model was made with 1 + 25 boards (Figure
22). The block 25_PIM+LOAD, which uses 2000 W, is 25 times bigger (see Figure 23) than the
PIM+LOAD block which uses 200 W.

26
25_PIM+LOAD

-V_A_IN
R2

-V_A_0
0.05
PFM_A

-V_A_IN_1 -V_B_IN
-V_A_OUT
-V_A_IN_2
V1
-V_B_0
53Vdc
-V_A_0 -V_A_0

PFM_A
25_PIM+LOAD

PFM_B
0
-V_B_IN_1 -V_B_OUT
-V_B_IN_2

-V_B_0
-V_B_0 Board
R3
PFM_B

-V_A_IN
0.05

-V_A_0

V2
-V_B_IN
53Vdc

-V_B_0

PIM+LOAD
0

Figure 22: A model with 1+25 boards.

I1

207.5Adc (8.3*25)

D1
D8
-V_A_IN
Dbreak
STTH3002G

D6
SMCJ64A

-V_A_0

G2
+
-
I2 C1 G OUT
2.5m -56
0
IN

207.5Adc (8.3*25)

D4 U4
D9 V6
X
-V_B_IN 2000 X Y
Dbreak Y
STTH3002G DIVIDER2

D7
SMCJ64A

-V_B_0

Figure 23: The 25_PIM+LOAD block where V6 is 2000 W.

27
The simulation of the system is shown in Figure 24.

-50.0V

VOUT PIM

-50.5V

VOUT PFM_A/ VA_IN PIM


-51.0V

-51.5V

VIN PFM_A
-52.0V

-52.5V

VIN_A
-53.0V
0s 1ms 2ms 3ms 4ms 5ms 6ms 7ms 8ms 9ms 10ms 11ms 12ms 13ms 14ms 15ms 16ms 17ms 18ms 19ms 20ms
V(Board.C1:1,Board:-V_A_0) V(V1:-) V(R2:2,0) V(PFM_A:-V_A_OUT,0)
Time

Figure 24: VIN_A = -53 V, VIN PFM_A = -51.9 V, VOUT PFM_A/ VA_IN PIM = -51.0 V & VOUT PIM = -50.3 V.
X-axis = 0.2 ms/div & Y-axis = 0.1 V/div.

The simulated current in the two PFMs is now 21.9 A respectively, the bigger part of these currents
goes to the block 25_PIM+LOAD and the smaller part goes to PIM+LOAD, which means a current of
1.99 A per feed.

6.3 Transient simulation with one board


As seen in Figure 6, ATIS has defined a curve that represents a protective device transient, this
transient was simulated with a generator VPWL at feed A with the values shown in Figure 25. Feed B
where still at -53 V. The result is shown in Figure 26.

V3
T1 = 0 V1 = 50
T2 = 2m V2 = 50
T3 = 2.012m V3 = 5
T4 = 12.0035m V4 = 5
T5 = 12.0055m V5 = 100
T6 = 12.0555m V6 = 75
T7 = 20.805m V7 = 75
T8 = 23.305m V8 = 50

Figure 25: VPWL source.

28
-0V

-20V

-40V

-60V VOUT PIM

VIN PFM_A
-80V

VOUT PFM_A/ VA_IN PIM


VIN_A

-100V
0s 2ms 4ms 6ms 8ms 10ms 12ms 14ms 16ms 18ms 20ms 22ms 24ms 26ms 28ms 30ms
V(BOARD.C1:1,BOARD:-V_A_0) V(V3:-) V(PFM_A:-V_A_OUT,0) V(PFM_A:-V_A_IN_1,0)
Time

Figure 26: VIN PFM_A = -78.5 V @ -100 V input, VOUT PFM_A/ VA_IN PIM = Start value is -49.6 V and minimum value is
-73.7 V & VOUT PIM = Start value is 51.3 V and minimum value is -73.0 V. X-axis = 0.5 ms/div & Y-axis = 50 V/div.

The reason for the input voltage of PIM being lower than the output voltage in the beginning of the
pulse is because the transient at feed A starts at -50.0 V and the voltage at feed B at -53.0 V. This is
because the ORing diodes will direct the highest voltage to the output. This can also be seen with the
current in Figure 27. The voltage from feed B is larger until 12 ms, it is during this time where it is
only current from feed B which will flow to the output. When 12 ms is reached (this is also when the
input voltage goes to -100 V), the currents will switch because now the voltage from feed A are higher
than the one in feed B. The current simulated will reach a maximum at 5.33 A at feed A and 3.90 A at
feed B.

As seen in Figure 26 the output voltage of the PIM did not go back to its start value within 30 ms,
Figure 28 shows that the voltage is back at -51.3 V around 300 ms.

10

IIN_B IIN_A
-10

-20

-30

-40
VB_IN PIM
-50

-60 VA_IN PIM

-70

-80
0s 2ms 4ms 6ms 8ms 10ms 12ms 14ms 16ms 18ms 20ms 22ms 24ms 26ms 28ms 30ms
V(BOARD:-V_A_IN,0) I(BOARD.D1) I(BOARD.D4) V(PFM_B:-V_B_OUT,0)
Time

Figure 27: The current switches when VB_IN PIM gets bigger than VA_IN PIM. X-axis = 0.5 ms/div & Y-axis = 2 -/div.

29
-0V

VIN_A
-20V

VOUT PIM
-40V

-60V

-80V
VOUT PFM_A/ VA_IN PIM

-100V

-120V
0s 50ms 100ms 150ms 200ms 250ms 300ms 350ms 400ms 450ms 500ms
V(BOARD.C1:1,BOARD:-V_A_0) V(V3:-) V(BOARD:-V_A_IN,0)
Time

Figure 28: VOUT PFM_A/ VA_IN PIM and VOUT PIM recovers at around 300 ms. X-axis = 10 ms/div & Y-axis = 5 V/div.

Figure 29 shows the current in input 1 to PFM_A. In this model the PFM can reduce the current from
input to output, in this case from 215.7 A to 4.6 A. Note that the total input current will be two times
215.7 A. Charging of the output capacitor handles the overcurrent.

240A

200A

IIN PFM_A
160A

120A

80A
IOUT PFM_A

40A

0A

-40A
0s 2ms 4ms 6ms 8ms 10ms 12ms 14ms 16ms 18ms 20ms 22ms 24ms 26ms 28ms 30ms
I(PFM_A.D2) -I(PFM_A.L2)
Time

Figure 29: The current is reduced in the PFM. X-axis = 0.5 ms/div & Y-axis = 10 A/div.

30
6.4 Transient simulation with 26 boards
The same simulation as in the last section was made, but this time with 26 boards. The result in Figure
30 is pretty similar to Figure 26. As an example, input at PFM_A is reduced to the same value, -78.5
V, when the -100 V spike occurs, but there are some differences:

 The input voltage at the A feed at PIM starts at -49.4 V and goes to -72.1 V.
 The output voltage of PIM starts at -49.1 and goes to -71.4V.
 The output voltage of PIM is back to its start value already at 50 ms.
-0V

-20V

-40V
VOUT PIM

-60V

VIN PFM_A
VOUT PFM_A/ VA_IN PIM

-80V

VIN_A

-100V
0s 5ms 10ms 15ms 20ms 25ms 30ms 35ms 40ms 45ms 50ms
V(V3:-) V(PFM_A:-V_A_IN_2,0) V(PFM_A:-V_A_OUT,0) V(Board.C1:1,Board:-V_A_0)
Time

Figure 30: Transient simulation with 26 boards. X-axis = 1 ms/div & Y-axis = 5 V/div.

Figure 31 shows that the current through PFM is higher, but there is still a reduction from input to
output, from 308.7 A to a maximum of 81 A.

320A

280A

240A

IIN PFM_A
200A

160A

120A

80A IOUT PFM_A

40A

0A

-40A
0s 5ms 10ms 15ms 20ms 25ms 30ms 35ms 40ms 45ms 50ms
-I(PFM_A.L2) I(PFM_A.D2)
Time

Figure 31: The current is reduced in the PFM. X-axis = 1 ms/div & Y-axis = 10 A/div.

31
The current in PIM does not change very much, the current from the A feed is maximum 5.3 A and the
current from the B feed is 3.90 A, see Figure 32.

10

IIN_B
-10
IIN_A

-20

-30

-40

VA_IN PIM
-50

-60 VB_IN PIM

-70

-80
0s 5ms 10ms 15ms 20ms 25ms 30ms 35ms 40ms 45ms 50ms
I(Board.D1) I(Board.D4) V(Board:-V_A_IN,0) V(25_PIM+LOAD:-V_B_IN,0)
Time

Figure 32: A graph to show the current switch in PIM. X-axis = 1 ms/div & Y-axis = 2 V/div.

ATIS also defines an impulse protective device operation transient (4), which is a triangle pulse that
goes from 50 V to 100 V with a rise time at around 2 µs and pulse width of 100 µs. A simulation was
made to show how this model handles different pulses. Figure 33 shows how the VPWL generator was
configured.

R2

0.05
PFM_A

-V_A_IN_1
-V_A_
-V_A_IN_2

V3
-V_A_0 -V_
T1 = 0 V1 = 53
T2 = 2m V2 = 53
T3 = 2.002m V3 = 100 PFM_A
T4 = 2.102m V4 = 53
T5 = V5 =
T6 = V6 =
T7 = V7 =
T8 = V8 =

PFM_B
0

-V_B_IN_1 -V_B
Figure 33: VPWL source. -V_B_IN_2

-V
R3 -V_B_0

PFM_B

0.05

V2
53Vdc

32

0
Figure 34 shows the result of the simulation. The input voltage of PFM is reduced to -78.4 V. The
voltage drop created by the pulse is barely visible at the input and output of PIM, there is only a small
voltage drop of 1.5 V on both sides when the impulse occurs. The voltages of the PIM goes back its
normal values after a few milliseconds, VIN = -51.0 V and VOUT = -50.3 V (see Figure 35).

-50V

-60V
VOUT PIM

-70V
VOUT PFM_A/ VA_IN PIM

-80V VIN PFM_A

-90V
VIN_A

-100V
1.96ms 1.98ms 2.00ms 2.02ms 2.04ms 2.06ms 2.08ms 2.10ms 2.12ms 2.14ms 2.16ms 2.18ms 2.20ms 2.22ms 2.24ms 2.26ms 2.28ms 2.30ms
V(Board.C1:1,Board:-V_A_0) V(V3:-) V(PFM_A:-V_A_IN_2,0) V(Board:-V_A_IN,0)
Time

Figure 34: Simulation with a triangle pulse. X-axis = 0.005 ms/div & Y-axis = 2 V/div.

-50.0V

-50.5V

VOUT PIM
-51.0V

-51.5V
VOUT PFM_A/ VA_IN PIM

-52.0V
0s 2ms 4ms 6ms 8ms 10ms 12ms 14ms 16ms 18ms 20ms
V(Board.C1:1,Board:-V_A_0) V(PFM_A:-V_A_OUT,0)
Time

Figure 35: The voltage drops 1.5 V when the impulse occurs. X-axis = 0.5 ms/div & Y-axis = 0.1 V/div.

33
6.5 ATIS transient at input to PIM
The decrease in voltage did not cause the PIM to endure as much pressure as it is supposed to be able
to handle, instead the PFM has taken care of the higher voltages. Because of this, simulations where
made with the ATIS transient directly at the input of the PIM, see Figure 36.

R2

0.5

V3
T1 = 0 V1 = 50
T2 = 2m V2 = 50
T3 = 2.012m V3 = 5
T4 = 12.0035m V4 = 5
T5 = 12.0055m V5 = 100
T6 = 12.0555m V6 = 75
T7 = 20.805m V7 = 75
T8 = 23.305m V8 = 50

Board
R3

-V_A_IN
0.5

-V_A_0

V2
-V_B_IN
53Vdc

-V_B_0

PIM+LOAD
0

Figure 36: PIM with ATIS transient at input.

Figure 37 shows the result of the simulation with one board. The input voltage of PIM goes up to a
maximum of -5 V and down to a minimum of -91.9 V. The output voltage of the PIM goes down to a
minimum of -72.9 V.

20

-0

IIN_B
IIN_A
-20

-40

-60
VOUT PIM
VA_IN PIM

-80

VIN_A

-100
0s 5ms 10ms 15ms 20ms 25ms 30ms 35ms 40ms 45ms 50ms
I(Board.D1) I(Board.D4) V(Board.G2:3,Board:-V_A_0) V(V3:-) V(R2:2,0)
Time

Figure 37: The transient was simulated directly at the input to PIM. X-axis = 1 ms/div & Y-axis = 5 -/div.

34
The simulation with 26 boards shows that the input voltage goes down to -88.7 V (Figure 38).

20

-0

IIN_B
IIN_A
-20

-40

-60
VOUT PIM
VA_IN PIM

-80

VIN_A

-100
0s 5ms 10ms 15ms 20ms 25ms 30ms 35ms 40ms 45ms 50ms
I(Board.D1) I(Board.D4) V(Board.G2:3,Board:-V_A_0) V(V3:-) V(Board:-V_A_IN,0)
Time

Figure 38: Simulation with 26 boards. X-axis = 1 ms/div & Y-axis = 5 -/div.

35
7 Analysis

7.1 Standards
In this thesis two standards has been analyzed and described, they are ETSI and ATIS. These two
standards have a couple of things in common, for example they both specify the nominal voltage of
-48 V. As with normal service voltage range value they say almost the same, ETSI specifies that it
should be -40.5 V to -57.0 V while ATIS says -40.0 to -56.7 V. Although in ETSI the different
voltage levels for a 60 V system is also mentioned, something that ATSI does not describe.

ATIS says that a device must have cut off and recovery functions, this is also mentioned in ETSI,
although not to the same extent.

A difference between the two standards is how they describe the transients from the protective device
operation. They both say that, in the power distribution system, when a fault occurs, there are first a
voltage drop followed by a voltage spike and then the voltage returns to its normal value. Although
this process is described and defined quite differently in the two standards. ATIS describes this event
with firm rules and defined facts with for example defined rise times and fall times. ETSI on the other
hand describes how the event will proceed in more general terms and no exact numbers a mentioned.

An interesting part during the work is how some of the information described in the standards can be
seen in real work at Ericsson. An example of this is how ETSI describes handling the large amounts of
energy where, in one particular case, it says that a capacitance can be used on the input of the device to
absorb the energy. This kind of capacitance is located at the output of the PIM, which is also the input
to the DC/DC converter. ETSI also describes how transient absorbing devices can be used, which both
the PIM and the PFM has in their construction, but they are called TVS diodes instead.

ETSI describes that fuses and circuit breakers can be used to protect the input at interface A. There are
several places in the system where circuit breakers and fuses are used to protect the system, but I have
chosen not to show any of these in my PSpice models, when they don’t directly affect the simulations
when deactivated.

Furthermore both standards handle noise and EMC, but in this thesis these have not been taken in
account.

7.2 Extended delimitations


When starting this thesis it was stated that the work should be limited to telecom and datacom systems,
but during the process of the work it has been found that the limitations had to be narrowed down
further. When investigating Core sites and studying how the RBS systems works it became clear that
the time of this degree project wasn’t enough to take them both on. It was therefore decided together
with my supervisor at Ericsson that the thesis should be focused on Core sites, given that it was easier
to find information about that system compared to RBS. Furthermore we also had better connections
to people who had knowledge about Core sites at Ericsson. As mentioned before this thesis was to
focus on EBS and LOD, EBS because it’s a quite new product, and it’s expected to be improved in the
future. LOD is chosen due to the fact that HOD is gradually being phased out, and it is therefore
smarter to focus on LOD.

36
The boards in the EBS system uses a current limiter, this current limiter can be a PIM, developed by
Power Modules at Ericsson. It was therefore wise to use this particular current limiter, since much of
the information about it could be collected at the department of Power Modules.

It became clear quite early in this thesis that my work with this subject is just a start of a project that
can grow exponentially big. To fulfill the main goal of this thesis regarding if any of the standards can
be viable to use for the input interface of the DC/DC converter, much more investigations, simulations
and testing must be executed. There are within the Core sites other systems of interest and also a great
number of other systems within Ericsson that uses DC/DC converters.

One should also give thought to the fact that it can be very useful not only to investigate which system
that is to be used, but also how these system might affect the modules, are there differences in how
much damage they do to the modules?

7.3 Data analysis


The simulations which were made delivered different results that have been shown by graphs earlier in
this report. In this part of the report an analysis of the results is done and the difference between these
results is also discussed.

7.3.1 No transient
When no transient is placed on the inputs and both feed A and B has - 53 V, not that big of a
difference could be seen on the voltages of the PIM when simulating one board and 26 boards. The
output voltage on the PIM is a bit lower when 26 boards are in parallel, the difference reads -51.5 V +
50.3 V = -1.2 V. The current is a little bit higher when using 26 boards, it reads 1.99 A instead of 1.94
A.

The graphs shows that there is a voltage drop over the PFM and the PIM, this happens because of the
diodes, which each have a voltage drop of 0.7 V, that are used in the models. In reality, the voltage
drop is a bit smaller, due to the fact that transistors are used for ORing instead of diodes as in the case
in the simulations.

7.3.2 Transient PFM


When putting a transient on feed A the result is a bit different. At first the input voltage rise to -5 V, as
this happens the voltage does not rise the same way at the input and output of the PIM. This occurs
both with one board and with 26 boards. The input voltage then quickly goes to -100 V and then rises
to -75 V before it goes back to its starting position. When 26 boards are simulated the output voltage
in the PIM reaches -71.4 V when the input voltage is - 75 V. If it’s only one board the voltage reaches
-73 V instead.

The current in the PIM remains at the same level independent if it is one board or 26 boards. In the
PFM though the current rises if there are multiple boards, this is due to the effect which is higher in
this case.

A difference between one board and multiple boards is that the voltage takes a longer time to go back
to its normal value with one board. This is explained by the big capacitor on the output on the PFM.
For multiple boards the capacitor will instead discharge faster.

37
To show how it can look with different curves, a simulation with a triangle pulse which went from - 50
V to -100 V, has been performed. The voltage over the input to the PFM goes down to the same level
as it had in earlier simulations, which were -78.5 V. On both the input and the output of the PIM, there
was only a small voltage drop of 1.5 V when the pulse occurred. After 10 ms the voltage was back to
its start value.

7.3.3 Transient PIM


Since the voltages in the transient which was placed on the input did not affect the PIM noticeably, the
same transient was placed directly on the input to the PIM, to see how much of the voltage that would
reach the DC/DC converter.

The voltage spike at the PIM input reached -91.9 V when using one board, and -88.7 V when using 26
boards, this compared to PFM which showed -78.5 V when using 26 boards. At the value of -75 V the
voltage follows the input voltage well and moves at equal pace down to normal voltage value. Neither
the voltage reaching -5 V or -100 V can be seen in the output of the PIM.

7.3.4 DC/DC converter


In
Table 4 the data from the technical specification for a DC/DC converter is shown (15):

PKB 4201B PI
Absolute Maximum Ratings Min Max Unit
Input Voltage (VI) -0.5 +80 V
Input voltage transient (Vtr) (tp 100 ms) 100 V
Electrical Specification
Input voltage range (VI) 36 75 V
Output Power (PO) (@ VI = 36 – 75 V) 0 194 W
Output current (IO) 0 40 A
Table 4: Selected data for a DC/DC converter.

When comparing the data from the simulations to the technical specifications for the DC/DC
converter, the values from the output of the PIM is within the values stated in the specification. Note
that the values in the table are positive because the DC/DC converter is specified for negative
grounding.

38
8 Conclusions
The goal of this thesis was to evaluate if the requirements in the two standards ETSI and ATIS are
viable for the input interface of DC/DC converters. I have concluded that it is hard to give a precise
answer regarding how these requirements are met before more tests and investigations have been
performed. Just to name one example why I have come to this conclusion is due to that I have had to
limit out the EMC part of the standards because of the time limit for the thesis and this part also needs
extensive testing and simulations.

Based on my results, I think that it will be difficult to follow either of these standards precisely when it
comes to the input for DC/DC converters. My opinion is that certain adjustments need to be made, one
example is the voltage drop through the system which needs to be calculated when the voltage levels
are set.

There are no exact numbers when it comes to descriptions of transients in the ETSI standard that can
be compared with the DC/DC converters. Therefore it would be interesting to do a simulation with the
transient described in ETSI, since it is more general then the one described in ATIS. But in order to do
that I think that more time and effort needs to be put in to gather more information about how the
PFMs are constructed, can we really use the same model like the ones we use for the PIM? More
information about this simulation in chapter 9 Continous work.

One part of the goal was to investigate and analyze how the system in which the DC/DC converters
operate works. To do this I have mainly used the transient described in the ATIS standard which has
given me sufficient information of how the voltages change through the system. After completing my
simulations it is clear that in the EBS system the DC/DC converters are very well protected. If a fault
occurs at interface A, the PFM will take care of the high voltages, and the PIM will not need to handle
as much voltage as it is designed to handle at a maximum. It is also concluded that if a -100 V
transient occurs at the input to the PIM, this voltage will be reduced and never reach the DC/DC
converter. In the technical specification for the DC/DC converters it is stated that they can handle
transients up to 100 V, but by analyzing this system, that scenario with such high voltage is very
unlikely to happen. But it cannot be ruled out totally, it all depends on how big currents and how high
voltages that can arise at a short circuit nearer to the DC/DC converter in the system. It is also possible
that high currents can slip through to the converters. That is also a reason for more simulations and
even more important, more tests of the real system needs to be done.

I hope that this thesis will be a helpful start for those who want to continue the work of a more
thorough investigation of what happens at the input interface to the DC/DC converters.

39
9 Continous work
Given that the delimitations during the progress of my work has narrowed there is still a lot more to be
done in this field.

There are numerous more systems that need to be investigated, there is EBS HOD and even more
systems within Core sites. Even if the HOD system is to be phased out it is still used and therefore
viable for investigation.

Furthermore an investigation, both within Ericsson and their external clients, needs to be done to see
which systems DC/DC converters are used in. These systems then need to be defined and made in to
models to be viable for simulations.

There are also many more simulations to be done. As an example the already made simulations can be
widened and include testing different lengths of cables, which means varying the impedance. In the
reported simulations an average value of 10 meters are used. Other simulations that could be done are
simulating the EMC, short-circuit of different parts of the system and the transient described in ETSI
(it can also be called a fuse blowing transient).

A fuse blowing transient can be simulated with a short circuit at the input and a switch that can be
opened when the right energy level has been reached. In PSpice two switches can be used, one that can
be closed and one that can be open at certain times (see Figure 39). The last mentioned is set to the
time where desired short circuit current is reached.

More advanced models can be used in the simulations to get an even better comparison to the reality.
Perhaps a model with more realistic voltage drops and more non-ideal components can be used.

In addition to simulations, it would be interesting to compare the simulation results with real tests of
the systems, to see if the simulations can be compared with the reality.

R4
L1
1 2
8uH 2
10m
U1
1ms PFM_A
1
-V_A_IN_1
53Vdc -V_A_OUT
V5 2 -V_A_IN_2

U2
1.4ms -V_A_0 -V_A_0
1
PFM_A

Figure 39: Model of a fuse blowing transient.

40
10 References
(1). Ericsson. Power Modules.
http://www.ericsson.com/ourportfolio/products/power-modules. 2013-02-17.

(2). ETSI, European Telecommunications Standards Institute. Environmental Engineering (EE);


Power supply interface at the input to telecommunications and datacom (ICT) equipment; Part 2:
Operated by -48 V direct current (dc). 2011. EN 300 132 - 2 v2.4.6 .

(3). ETSI, European Telecommunications Standards Institute. Environmental Engineering (EE);


Transient voltages at Interface "A" on telecommunications direct current (dc) power distributions.
2007. TR 100 283 v2.2.1.

(4). ATIS. Voltage levels for DC-powered equipment used in the telecommunications environment.
Washington : Alliance for Telecommunications Industry Solutions, 2007. ATIS-0600315.2007.

(5). Ericsson. -48 Vdc Power Arrangement on Core Sites.

(6). Ericsson. BYB 501 - Modular indoor cabinet. 2012.

(7). Ericsson. Ericsson Blade System. 2012.

(8). Ericsson, Mats Barkell. Power and Fan Module (PFM) for BFD 538 Subrack. 2009. 1551-BFD
140 13/2 Uen.

(9). Ericsson, Ulf Hansson. EGEM2, Design guidelines and rules. 2012. 102 61-BFD 528 001/1 Uen.

(10). Ericsson. Ericsson SGSN-MME.


http://www.ericsson.com/ourportfolio/telecom-operators/sgsn-mme. 2013-04-24.

(11). Ericsson. Controllers. http://www.ericsson.com/ourportfolio/products/controllers. 2013-04-24

(12). Ericsson, Johan Hörman. Tentative Requirement Specification Power Interface Modules C309.
2012. 1/1056 - FCP 108 448/309.

(13). Littelfuse. TVS Diodes. http://www.littelfuse.com/products/tvs-diodes.aspx. 2013-05-10

(14). Ericsson, Åke Ericsson. Requirements Specification for LOD PFM_2400 W. 2010. 1/1056-
BFB14013/2.

(15). Ericsson. PKB 4000B series, Intermediate Bus Converters. 2010. LZT 146 384 R3C.

(16). Ericsson. Core Site.


http://www.ericsson.com/ourportfolio/telecom-operators/core-site. 2013-05-05.

41
11 Figure references
[1] Figure 1, ETSI, European Telecommunications Standards Institute. Environmental
Engineering (EE); Power supply interface at the input to telecommunications and datacom (ICT)
equipment; Part 2: Operated by -48 V direct current (dc). 2011. EN 300 132 - 2 v2.4.6. Page 19,
Figure A1. © European Telecommunications Standards Institute 2007. Further use, modification, copy and/or distribution
are strictly prohibited. ETSI standards are available from http://pda.etsi.org/pda/.

[2] Figure 2, ETSI, European Telecommunications Standards Institute. Environmental


Engineering (EE); Power supply interface at the input to telecommunications and datacom (ICT)
equipment; Part 2: Operated by -48 V direct current (dc). 2011. EN 300 132 - 2 v2.4.6. Page 9, Figure
1. © European Telecommunications Standards Institute 2007. Further use, modification, copy and/or distribution are strictly
prohibited. ETSI standards are available from http://pda.etsi.org/pda/.

[3] Figure 3, ETSI, European Telecommunications Standards Institute. Environmental


Engineering (EE); Transient voltages at Interface "A" on telecommunications direct current (dc)
power distributions. 2007. TR 100 283 v2.2.1. Page 6, Figure 1. © European Telecommunications Standards
Institute 2007. Further use, modification, copy and/or distribution are strictly prohibited. ETSI standards are available from
http://pda.etsi.org/pda/.

[4] Figure 4, ETSI, European Telecommunications Standards Institute. Environmental


Engineering (EE); Transient voltages at Interface "A" on telecommunications direct current (dc)
power distributions. 2007. TR 100 283 v2.2.1. Page 10, Figure 4 and 5. © European Telecommunications
Standards Institute 2007. Further use, modification, copy and/or distribution are strictly prohibited. ETSI standards are
available from http://pda.etsi.org/pda/.

[5] Figure 5, ETSI, European Telecommunications Standards Institute. Environmental


Engineering (EE); Power supply interface at the input to telecommunications and datacom (ICT)
equipment; Part 2: Operated by -48 V direct current (dc). 2011. EN 300 132 - 2 v2.4.6. Page 14,
Figure 2. © European Telecommunications Standards Institute 2007. Further use, modification, copy and/or distribution are
strictly prohibited. ETSI standards are available from http://pda.etsi.org/pda/.

[6] Figure 6, ATIS. Voltage levels for DC-powered equipment used in the telecommunications
environment. Washington : Alliance for Telecommunications Industry Solutions, 2007. ATIS-
0600315.2007. Page 14, Figure 1.

[7] Figure 7 and 8, Ericsson. -48 Vdc Power Arrangement on Core Sites. Page 5, Figure 1.

[8] Figure 9, Ericsson. -48 Vdc Power Arrangement on Core Sites. Page 10, Figure 4.

[9] Figure 10, Ericsson. Ericsson Blade System. Page 3.

42

Vous aimerez peut-être aussi