management
New perspectives on the
temporary - permanent dilemma
Beyond Project Management
ISBN 91-47-06403-X
O 2002 The Authors and Liber AB
Printed in Sweden by
Daleke Grafiska AB, Malmo 2002
Distribution:
Sweden
Liber Ekonomi. Baltzarsgatan 4,
205 1 0 Malmo, Sweden
tfn 04@258600, fax 040-97 05 5 0
http://www.liber.se
Kundtjanst tfn 08-690 9 3 30, fax 0 8 6 9 0 9 3 0 1
Norway
Abstrakt Forlag AS, Kristian 4's gate 15,
Postboks 6952, St Olaus Plass
0130 Olso, Norge
tel +47 2 3 3 5 79 42, fax +47 2 3 35 7 9 4 1
Denmark
DBK, Siljangade 2-8, P.O. Box 1 7 3 1
DK-2300 Copenhagen S, Denmark
phone: +45 3269 7788, fax: +45 3269 7789
North America
Copenhagen Business School Press
Books International Inc.
P.O. Box 605
Herndon, VA 20172-0605, USA
phone: + 703
I6 6 1 1500, toll-free: + I 8 0 0 758 3756
fax: + I 7 0 3 6 6 1 1 5 0 1
Preface
INTRODUCTION
I The Scandinavian School of Project Studies
KERSTIN SAHLlN-ANDERSSON AND ANDERS SODERHOLM
Key features of the Scandinavian School of Project Studies 11 /
A projectified society 14 / Project portfolios in their corporate context
18 / Relating the temporary and the permanent zo / Project manage-
ment reconsidered 21 / Beyond project management 23
A PROJECTIFIED SOCIETY
z How project management got carried away
TOMAS BLOMQUIST AND ANDERS SODERHOLM
Projcct management as management knowledge 25 I Within industries,
via engineering professionals, and abetted by industry-specific require-
ments 27 / Among industries through consultants: Expanding the scope
and adding generic value 28 /Volume through professional associations:
Picking up the latecomers with success stories and offers of professional
identity j o / Long-term survival through standardization bodies, scien-
tific research, and university training: Creating normative pressure 34 1
Carry on into the future 36
10 Regenerated professionalism
The librarian who went out on her own 187
ELISABETN SUNDIN
Introduction 187 1 The Swedish public sector 189 1 Entrepreneurs and
librarians 193 1 Why the librarian went out on her own 196 1Shifts in
practice 197 / Shifts in theory 199
TABLE OF C O N T E N T S
References
Author presentations
Preface
Life as a project
Maybe also life itself could be a project context. However, while read-
ing Barbara Czarniwska's interview with Rolf Lundin "A Life of a Pro-
ject Researcher" in this book, a story came into my mind: A man was
asked to explain the diversity of his experience in work and in private
life. He answered, "There was no plan I just dived down and swam
around". It sounded strange to his friends in the field of project prac-
tise. He almost regretted his spontaneous answer.
Rolf's comment in his Post Scriptum could have been comforting for
the man: "It also appears that too much of feelings and whims rather
than planning took over my past life".
With my background as a mathematical economist during a long
period of my life I dare trying to formulate a general rule: Looking
back on a person's trajectory of life you always end up falsifying the
hypothesis that it could have been part of a project process. Along the
same modelling line of thought I remember that smooth trajectories
might in a more detailed resolution be of fractal character as in chaos
theory. Changing perspectives means entering new worlds.
Putting project studies and practises in contexts, that really matters,
does also mean opening doors to new worlds of thought.
Jan Odhnoff
Professor Emeritus, Teleinformatics, Royal Institute of
Technology, and founding chairman Swedish ProjectAcademy
The
porations. But, several indicators show that this expansion has taken
place, that it has spread among different industries, and is used for
more varied purposes (see Ekstedt, Lundin, Soderholm & Wirdenius,
1999; Engwall, 1995; Chapter z in this volume). And the forming of
projects in practice is influenced and inspired by widespread writings.
Such reciprocal development of practice and theory is common in the
field of management, for management theory has usually developed in
close interaction with practice and with theoretical developments in
other scientific fields (Engwall, 1992; Sahlin-Andersson & Engwall,
2002).
Many writings on project management have echoed practical man-
agement, and have taken the form of recipes and handbooks on "How
to Manage Better". Such writings have provided valuable inputs to the
discourse and development of new managerial tools. However, they
appear to focus too narrowly on management of the individual project
to be of value to people who are primarily interested in understanding
how projects contribute to and are related to longer-term and wider
developments in organizations, industries, and society. Furthermore,
many of the handbook-type writings in project management assume
ideal conditions for management and change that are seldom found in
practice. Fuzzier and more ambiguous conditions often characterize life
in organizations and society.
The Scandinavian School of Project Studies has taken a wider, and at
the same time closer approach in their studies (see e.g. Soderlund zooob;
Engwall, Steinthbrsson & Soderholm 2002 for different research per-
spectives in this field; Packendorff, 1995). We point to three key featu-
res of the Scandinavian School. First, it has widened the scope of pro-
ject studies beyond that of single projects. Its aim has been to reflect on
and thereby contribute to the understanding of the way in which pro-
jects are contextually related. This broadened view has been triggered
by questions such as: Why has the use of prolects expanded? How are
projects formed from longer-term developments in organizations and
society? How do they contribute to these long-term developments?
How are projects that are pursued simultaneously or sequentially con-
nected with or disconnected from each other? How can one best learn
from one project to another?, and How can one avoid repeating
unwanted procedures from one project to another?
These studies, in other words, analyze the development of projects in
relation to more general organizational and societal changes. With the
THE S C A N D I N A V I A N SCHOOL O F PROJECT STUDIES
A projectified society
Projects abound. There has recently been a great deal of talk about
such concepts as project organizing, project management, project dev-
elopment, to such an extent that one can talk about project organizing
as a management fad or fashion (see Abrahamson, 1996; Ravik, 1996;
Chapter 2, this volume). Also, one can speak of the projectification of
T H E S C A N D I N A V I A N SCHOOL OF PROJECT STUDIES
ited their analysis to the perspective of the project manager. For this
reason, the interrelationships of projects and their relationship with the
wider corporate context, have been under-explored in the project
management literature (Engwall, Steinth6rsson & Soderholm, 2002).
The studies that form the bases for Chapters 5 to 8 in this volume do
not focus primarily on the activities or responsibilities of the individual
project manager, but take a broader view of the ways in which projects
emerge. They demonstrate the development of relationships among
projects and they analyze the effects of these interrelationships on the
unfolding of the individual project.
The embeddedness of projects in wider corporate contexts is multi-
layered and changing. It is not in the hands of individual project man-
agers to control, and it may not always be desirable from the viewpoint
of the individual mangers to integrate and co-ordinate projects too
much. Our analyses of constellations of projects and of the embedded-
ness of projects in their corporate context points to other, often more
difficult issues of management and governance than do studies that are
restricted to individual projects. The fruitfulness of not restricting stud-
ies and analysis to individual projects and the importance of not taking
formal structures as given are clearly shown throughout this volume.
This demonstration of the gains of more contextualized designs of stud-
ies parallels findings in neighboring areas; for example, the develop-
ment of more field-based analyses in organization theory (see Powell &
DiMaggio, 1991; Scott, 1995; Scott et. al., 2000) and the development
of more governance-based rather than government-based studies in
political science (Rosenau & Czempiel, 1992).
When analyzing the embeddedness of projects in their corporate
context, it also becomes apparent that the management of these pro-
cesses is neither simple nor clear-cut. The analysis points to dilemmas
in the ways that projects should be related to their wider context. One
such quandary can be termed the attachment-detachment dilemma.
The basic concept of project organizing is usually to detach a certain
task or a certain procedure from its wider context to allow specific pro-
cedures to develop (as discussed in Chapter 13, this volume). Project
organization may also be a way to separate various parts, objectives,
and relationships of the corporation. Thus, they may be used as a way
to separate activities in order to handle potentially conflicting demands
and objectives (c.f. Cyert & March, 1963). At the same time, concepts
such as project portfolios show, as do Chapters 5 and 6 of this volume,
K E R S T I N S A H L I N - A N D E R S S O N A N D ANDERS SODERHOLM
reproduce, how projects relate to each other and to their broader con-
text, and how individual projects evolve. The close focus on project
progress and the contextualized character of projects point to great
variation (see Hellgren & Stjernberg, 1995, for an empirical study
illustrating this issue). Not all projects can be managed according to the
same recipe.
Both in practice and in the normatively oriented project management
literature, we frequently find comments about projects that unfold in
less ordered and less clear-cut ways than those assumed and prescribed
in the handbooks. However, such examples tend to be regarded as
exceptions to the assumed ideal models. The question is: "How often
should we encounter an exception before accepting it as the normal
state of affairs?"
The comprehensive empirical studies that have been conducted
within the Scandinavian School tradition find that the less ordered and
less clear that projects are, the more frequent the perfectly clear and
ordered projects are desired in many normative models and project text-
books (Larson, 2000; Blomberg, 1998). It seems reasonable, from such
findings, to modify commonly spread project management models
based on empirically observed conditions that deviate from the perfect
situation presented in many textbooks.
The insights gained through research of the Scandinavian School of
Project Studies, invite us not to take the nature of a project for gran-
ted, but to continuously open the black boxes of projects and project
management, as demonstrated in several chapters in this volume.
Chapter 13 broadens the content of project definition processes beyond
planning and active management actions, thus providing us with an
enriched picture of the creation of projects. Project goals are discussed
along similar lines in Chapter 14. Project goals are commonly assumed
in the project management literature to be the result of a comprehensive
planning process and to form the basis for the implementation of those
plans. Chapter 14 reviews the validity of this conclusion and provides
valuable insights into other aspects of the goal-formulating process in
project contexts.
From the project studies pursued by the Scandinavian School, we
learn that in order to understand the outcome of a process, it is of value
to learn about the process - a lesson inspired by empirical studies as
much as by theories of decision-making processes (see e.g. March,
1981; 1994), social interaction, and social psychology (Weick, 1979).
THE SCANDINAVIAN SCHOOL OT: P R O J E ( : T S'rllDIES
ence is held every second year. Between world congresses, both organi-
zations hold national conferences and smaller, focused conferences and
workshops. Nordnet is, for example, the name of an annual conferen-
ce organized by Nordic project management associations.
In these conferences, practitioners, consultants, and scholars meet to
share success stories and practical know-how. The conference themes
indicate a shift from engineering-oriented planning to more general
management issues. One difference between PMI and IPMA is that
PMI conferences over the last ten years have largely focused on inter-
nal project management topics. A number of the themes of PMI and
IPMA conferences are presented in the tables below.
Table 2:2 Themes and locations of IPMA conferences, 1967-2000 (see Eriks-
son, 1997).
Success
t ProFessionalization 1 +Commercialization
+ Volume
Figure 2:1 Flows of project management knowledge.
TOMAS BLOMQUIST AND ANDEKS S C i O E K H O L M
- both projects that they are organized into and projects that they con-
struct themselves in their everyday life. In this analysis, examples of
individual narratives on projects and projectization will be included,
individuals working in the IT sector, in the cultural sector, as entre-
preneurs, as consultants, and even as voluntary community workers.
The problem of this kind of general reasoning is that there are many
different types of projects. Project work is actually not just one homo-
genous work form; it means different things depending on the situation in
which it is performed. The necessity of identifying different types of pro-
jects has also been widely acknowledged in literature during the past
decade (cf Turner & Cochrane, 1993; Packendorff, 1995; Ekstedt et al,
7999).
In the same way as there are many different types of projects, there
are thus also many types of project work situations, ranging from 'per-
fect projects' where the individual works full-time for one single pro-
ject and can devote all of her time to that, to all sorts of 'imperfect' pro-
ject work situations where life is more complicated. We will therefore
look more closely into different sorts of project work situations from
two different dimensions, dimensions that have been important in
understanding the narratives of the individuals interviewed:
AFFILIATION
The project Organisational context
4 *
I. Project-based
work
PROJECT
WORK AS
Exception
1
IV. Independent
entrepreneurship
While the project form of work rests upon the assumption that team
members shall be committed and motivated from the start of each pro-
ject, individuals often feel that not all projects are interesting enough to
THE TEMPORARY SOCIETY AND ITS PhTEhlIES
"In May and June we worked long evenings and weekends in order
to finish the project. Then it was not finished anyway, and we post-
poned it into the autumn, when the next project was supposed t o
start. And now during autumn, we worked in the new project during
day-time and went over t o the old customer company in the even-
ings. The project was miscalculated from the beginning, it became
much larger than we had expected." (Matthew, computer program-
mer)
Usually, most projects are quite interesting despite the time strains,
since each new project is always different from the previous ones in at
least some dimension. What happens is that many individuals start
t o wonder about their professional development and what kinds of
careers that they might be able t o pursue. The 'reward' for committing
oneself t o a demanding project is often expectations on an even higher
degree of commitment to another demanding project. In their current
occupation, the future is perceived as an endless row of new projects,
and it is not unusual to find young people who want to leave the pro-
ject-based operations (i.e. the revenue generating activities of the organ-
izations) for 'strategic' and often less profitable tasks:
"Between us, I've told my bosses that I have now been project man-
ager for eight years, and that I find it damn boring. I don't want t o
d o this full time, anymore, so we have been discussing other tasks.
And one task is projects. Another task is knowledge development,
quality development, methods development, coaching junior consul-
tants and so on." (Edith, project manager)
price for consultancy hours falls below that fixed fee, it means that
consultants will have to add free hours in order t o generate the same
income. The result is often a vicious circle, where urgent situations are
resolved through heroic action, and heroic action becomes the taken-
for-granted solution to urgent situations (cf Perlow, 1997). No one
questions why the urgent situations appeared in the first place.
In order to enhance project-based work for the individual, most people
point at the importance of realistic expectations on each new project
and the necessity of working with only one project at a time. The task
should be interesting and stimulating t o the team and also important
and wanted in the project environment. Moreover, projects should not
be too large andlor too long, and the individual should be able t o con-
trol her own working hours. In addition, finally, someone other than
the individual andlor the project manager should assume some respon-
sibility for career development and other long-term issues, getting an
overview of the individual's entire work situation. Most H R M proced-
ures have been designed for permanent organizations where each indi-
vidual. has a position, not for project-based organizations where pos-
itions are non-existent or are changed all the time (ECOSIP, rqy3).
only a few individuals represent each project. For some managers, the
incessant handling of such projects may lead to a work situation resem-
bling the one in Type I, i.e. a situation in which most of the time is
spent implementing renewal projects (cf I,undin, ryyo).
The usual point of departure for the individual that becomes a par-
ticipant in a renewal project is that she should be able t o perform her
ordinary job while temporarily committing herself t o the project. For
the individuals that are attracted to the renewal effort by interest, this
is easier than for those who are automatically involved due to a certain
position in the organization. In any case, there are always time conflicts
between ordinary work and renewal project participation:
"Well, my priorities are with curing the patients, hut on the other
hand the management control systems must be redesigned, so...
Lately, I have been working ISOX,which is not good, you can't take
it for too long. I have green clothes on me, I might be called to surg-
ery any minute. I always work with the management control system
in the morning, but then I am on emergency duty. Sometimes I sit at
home working before the evening duty, so I hope that this manage-
ment control projcct can be finished somc day, so that everything
works again. It's the same though, for everybody." (George, clinic
head)
Of course, there are also several advantages for those who participate.
One important such advantage is that a renewal project is an opportun-
ity for the participant to widen her competence and show her abilities
t o others. In that way, these projects can become both learning exper-
iences and career steps:
"One of the main problems is that I have the duty to implement this
project, but I have no authority to force anyone else to participate if
they don't want to. I f Sophie says that she has to take care of a sales
conference instead, I just have to accept that. It does not happen all
the time, but there are some clear drawbacks with voluntary partici-
pation. What I can do is to be damn nagging. As the project goes on,
I just become increasingly nagging and persistent. Everyone else has
something else to do, this is not their main concern, so to speak."
(Bill, public relations manager)
The individual is thus often left on her own balancing the ordinary job
and the renewal project. Unlike the case of project-based work (type I),
there are often no clear indications from management on how to be-
have in these situations, and many individuals feel that they never prior-
itise the right things. For some, this dilemma is temporary by nature,
since renewal projects tend to fade out after a while. However, those
who are recognized for good performance in renewal projects are usu-
ally those that are asked anew when new reforms are initiated.
"Loyalties are a bit moved there. Concerning the big telecom com-
pany, it's an old account that we have been building up for three years,
and we have not switched people there often enough. We cannot have
the same people in the same customer's office too long, because then
they start to identify themselves with the customer's organization. We
had one guy who quit, he is still there but he is not with us anymore.
Now, we have taken care of that problem -half a year with the same
customer is the upper limit." (Douglas, project manager)
J O H A N N PACKEYDORFF
Except for a lack of close relations and friendship at work, not being a
permanent member of an organization also means a lack of expect-
ations on long-term contributions to the organization. They are not
expected t o be present for a long time and they do not expect that from
themselves either - the result is a temporary, detached, superficial organ-
izational membership cpisode. Temporary workers are there to fulfill a
task or deliver a project, and it is up t o them to handle their own
competence development and find career opportunities. In addition,
aside from the lack of social affiliation, temporary workers with tem-
porary employment contracts are also exposed t o an economic preca-
riousness:
"It depends entirely on their status, who they are. There is a pro-
letariat of unemployed actors with very little to do. At least where live
theatre is concerned, therc are always a lot of movies and commer-
cials produced. But in live theatre, it's sad - of course you can live
on it, but you have to work with contacts everywhere, d o commer-
cials et cetera." (Stephen, theatre director)
"...a lot of those who we rent out are employed by the companies to
which they are rented out, and suddenly they realize something. This
is actually not that bad, you can try two or three companies during
a year and then you can feel for yourself if you would like to work
for that company or not. You learn how the company works, you
broaden your network, and then you might be offered employment.
Then the employer and the employee have tested each other, it be-
'THE TEMPORARY SOCIETY A N D l'l'S E N E M I E S
"I think that I've always done that - if I had no money, I lust took
any job I could gct. I worked during holidays in some ski resort or
distributed newspapers in the mornings and things like that. So there
are always jobs available if you want some money. I think like that
now also, with my new company, that if I get no assignments I could
always jump in as schoolteacher or so. There are plenty of jobs that
I could have for a while - not until I'm 65 of course, rather to make
sure there is some money." (Sheila, consultant)
"When first came to this school with my daughter, this old feeling
came over me from the time when I went here myself. The house, the
classrooms, the old-fashioned pedagogy. I did not want that for her,
so I decided that I just had to contribute something to the school. I
am a doctor, and I have worked with drug problenls for many years.
So, I became a board member of the parents association and initia-
ted several projects. Right now, it is not easy, because I have a lot to
do at work and I also have this 'prom project' where a group of
parents try to organize and attract sponsors for the best student ball
ever. But then, I will start again with the drug issues. It is just
something that I have t o do, since the school cannot make it on their
own." (Claire, parent)
"I have always worked by projects, except for my new firm - so far
at least. Somehow, I think this is a consequence of starting my pro-
fessional life in the cultural sector. You don't get many permanent
jobs there, rather short assignments. Therefore, I have just slipped
into different ventures from time to time - events, exhibitions, husi-
ness advising, regional development, and voluntary work. I actually
enjoy working in ventures where I know that my effort is limited in
time - I cannot imagine working at the same place until I am 6 5
years old. In a way, my career is thus a result of my personality. It is
T H E TEMPORARY SOCIETY A N D ITS ENEIMIES
Flexible work hours mean flexible family hours. Working extra hours,
often at short notice due to emergencies, also means that these hours
must be taken from somewhere. Sincc most individuals need a fixed
amount of sleep, the extra hours must be taken from the time that
would otherwise have been spent with families and friends. In the wake
of such behavior, divorces and an eroded social network follow. In
addition, since the individual spends most of her time working, work
also tends to occupy the mind - even when home with the family, the
individual reflects upon work and discuss it with her spouse and frie-
nds.
"...the important thing at my previous job was that when the new
legislation was issued, thc projects should be delivered. There, I led
some small projects and also a project big as hell with a large bud-
TIIF, T F M I ' O K A R Y SOCIETY A N D ITS ENEMITS
Flexible family hours imply a need for family projects or a need for
nothing. Given the quite unpredictable and often short time periods
that many project workers can spend with families and friends, there
often evolves a deeply felt urge t o make as good use as possible of the
few precious hours actually available. Otherwise, time will just pass
without being devoted to something special, something that could at
least partially make up for the usual absence. And what is the best way
of achieving something special given a short amount of time and a stream
of everyday routines that can easily consume all the time available? To
organize projects, of course!
One - quite evident - alternative t o create family projects as a
response to work projects, is t o do nothing. Constantly being under a
high and complex workload may deprive the individual of the energy
and creativity needed to initiate something special in her private life,
and off-work hours will thus be spent relaxing and recovering:
"Mostly I spend timc with my family, with my spouse and our kids.
Those outside that... I see my brother occasionally, some close frie-
nds now and then, but they don't get much time, they are in the
outcr layer. But all our acquaiiltances have small children, they know
how it is [laughter]. When you come home you are so damn tired of
order, planning and structures, you don't want to accept that at
home. You cannot be a project manager at home also." (Douglas,
project manager)
"I live as a single downtown - I like to be out, see people, read, take
in pictures, go to the opera. When I work I am totally into it, I can-
not do it otherwise. Then there are some things that have to be put
aside, and that is not so damn funny. Smart guys don't fall down
from the sky [laughter]. But this is quite acceptable. Of course there
is always the hunting season, and I am a part of that, to find the right
guy. But living as a single is not that strange anymore, quite accep-
ted, actually." (Edith)
"Our house was a cheap one, and we have almost no debts on it.
And a very old, very cheap car. And when my husband was to start
his company, we did not calculate on how much he could earn. We
calculated backwards; how much did we need each month to keep
the family going? We also realized that we could skip some costs -
we did not need any childcare since we were both to work from
home. Things like that, counting on a life style, sort of." (Sheila)
THE TEMPORARY SOCIETY .AND ITS E N E M l h S
Ester, Halman & de Moor, 1994; Scott & Meyer, 1994). Customers
want to be able to influence the design and quality of goods and serv-
ices. Increased purchasing power together with the new demand patt-
erns call for more complex and advanced products. Material goods are
linked up with various types of unique services. Consequently, the com-
panies are offering products with an increasing experience and know-
ledge content. Direct dialogue or negotiation between the actors of the
market becomes more common. Unique demand can be met by advan-
ced knowledge specially designed or developed by the team members of
a project. By organizing the knowledge production in the form of a
project it is possible to exploit contributions stemming from different
specialties and traditions (Lundin & Midler, 1998b). A project team may
consist of people from the R&D department, the subcontractors, the
customers, the consultant companies and the universities. A "pluralis-
tic integration" of this kind opens up a development potential not ima-
ginable inside a development department with a permanent staff.
If the changed consumer patterns promote project solutions, they are
facilitated by the great flexibility that comes with the development of
the information and communication technology (ICT). Adaptation to
specific demands of individual customers becomes possible. ICT is a
tool able t o change both time and space aspects of the economy. It facil-
itates the interaction in work life and makes it possible t o gain instant
information on what is happening anywhere on earth. Modern control
engineering makes possible immense variations in the design of pro-
duction. Products and services can be combined in many ways (Beni-
ger, 1986). But the rapid development of ICT also influences the design
of organizations indirectly (Orlikowski, 1992). The division of labor
inside and between organizations can be altered: the physical potential
of decentralization knows almost no bounds. Managers may control an
economic activity where geographical distances are of little importan-
ce. Individuals performing the same work task can be separated, al-
though the exercise of supervision and power remains the same. Pro-
ject organized management, design-teams and development activity can
be combined with outsourced neo-tayloristic production of compo-
nents. Mentally, the decentralization of organizations may come t o a
limit, however, when direct human interaction and the organizational
identity which unites people fade away.
Market relations, transaction costs
and contractual forms in different kinds of
organizations
The increased use of projects and temporary organizations is likely to
affect the contractual relations between companies (organizations) and
customers (the market) as well as between companies and individuals.
The question is how. The change of the formal contract is in most cases
rather easy to describe, as this is re p orted in regulations and legal texts.
The changed relation between permanent versus non-permanent
employment, for example, is in itself a reflection of changed formal
working contracts, at the same time as the increased use of temporary
employees is an indication of a growing importance of informal
contracts. The increased use of project organizations is an even strong-
er indication in that direction. Most informal contracts are however
very difficult to grasp. In the following I will approach this problem by
discussing the relations between organizations and customers and
between the organizations and the individuals in a theoretical context.
The relations between the organizations and their customers are impor-
tant as changed consumer patterns, as already discussed, can be seen as
the driving force in today's general transformation process. Changed
relations between companies and customers are also in many cases a
background to organizational changes inside companies.
Hirshman's categories of exit and voice will be used t o structure this
relation as they directly show informal contractual relations between
the two parties. The exit option is described as: "Some customers stop
buying the firm's products or some members leave the organization".
While voice is a totally different option:" The firm's customers or the
organization's members express their dissatisfaction directly to manage-
ment or to some other authority to which management is subordinate or
through general protest addressed to anyone who cares to listen". In
both cases the management must be engaged to search for the causes and
possible cures of customers' and members' dissatisfaction (Hirshman,
1970). The internal changes will in the following be illustrated by the
way in which transaction costs are distributed. This distribution of costs
is also a way of showing what kind of economic ties (informal contracts)
are at hand (Coase, 1988; North, 1990; Sjostrand 1993). These informal
contracts structure economic activity and are, for example, guiding the
actors when it comes to how, when and where to work.
C O N T R A C T S O F WORK I N A PROJECT - RASED E C O N O M Y
A. Industrial organizations
This model of organizing is first of all adapted to the production of
long series of standardized products. The market tests the attractive-
ness of the outcome. Exit mechanisms of a "take it or leave it" charac-
ter dominate even if there are exceptions. Some component producers
and call-centers are linked to one or just a few buyers. Other compo-
nent producers live in tough international competition dominated by
regular exit mechanisms. In the typical case of quadrant A there is a
minimum of relations between producers and customers. Consumers
are buying commodities without knowledge of how it was produced. A
lot of the components in, for example, electronic equipment are pro-
duced in developing countries under conditions of which we have lim-
ited knowledge. There can also be long periods of time between pro-
duction and purchase. In slack periods the companies' stocks build up.
Organizations in this quadrant are characterized by a hierarchical
decision system that keeps transaction costs down for intra-organiza-
tional search processes and time-consuming internal negotiations. The
organization can be efficient with a limited interaction between levels,
departments and individuals. This system is marred by considerable
monitoring costs, however. Decision-makers build up many levels
between themselves and those who in fact perform the economic act-
ivities. Special functions for supervision and control are built into the
system.
Long lasting formal contracts (often collective) have dominated this
kind o f organization in most industrial countries. This order has been
challenged in some major industrial companies during the last decade.
When for example ABB, at the end of the 1980's introduced the TSO
model (aiming at a reduction of lead time by 50 percent), one of the
most important tools was "the goal-directed groups", which can be
seen as a dramatic change of the working contract. Instead of being
exposed to colltinuous control the employees got the responsibility of
a whole working sequence; from order to delivery. This change could
ESKIL E K S T E D T
C. Project-based organizations
Traditionally, the industrial company participated in all kinds of act-
ivity; from production to market relations. It controlled the internal
resources, the subcontractors, the consultants and it also hosted the
development projects. The company was truly the nexus of all con-
tracts. It was also the bearer of the brand name; a brand name nec-
essary for success in the market. The expansion and spread of project-
based organizations challenge these structures of organizing. Most pro-
ject-based organizations work in close contact with their customers.
Commissioned companies form projects together with, for example,
development, design, planning and personnel units of industrial com-
panies. The economic activity is often closely related to the way in
which the demand of the customers is expressed. It is common that
sellers and buyers work together on the same projects. The exit mech-
anism of the market is to a noticeable extent being replaced by voice
and t o some degree loyalty. Loyalty or trust (a word frequently used
these days) may develop into situations where competition and market
relations are threatened. This dark side of the intimacy of economic
transactions has in periods been debated in the Swedish construction
sector, for example, but have almost been forgotten in modern discuss-
ions about networking (Brochner et al., 1992).
Some of the more successful companies have developed sophistica-
ted negotiations methods to handle the voices of their customers. The
multinational contractor Skanska performs most detailed contractual
discussions with its subcontractors. High negotiation costs in the early
planning stages of a project will be reimbursed if it contributes to fewer
mistakes when the whole production apparatus is involved later on
(Ekstedt & Wirdenius, 1995).
The relation to the customers is directly reflected in the internal
organization of project-based activities. Costs for monitoring (super-
vision) are minimized, as it is in the interest of the project members to
perform the assignment according to the description of the aims. They
of course want to be engaged also in future projects. Instead there are
high costs associated with contracts and negotiations. It is also likely
that collective contracts must make room for individual negotiations,
to support the project members in the unique situation of each project.
The ability of employees to negotiate will consequently be of immense
importance for their work conditions (Ekstedt et al., 1999).
The project organization implies that both the spatial and the time-
based relations between the actors will be manifested in a number of
different arrangements. The work is performed in a great variety of
ways, in a great number of different constellations, and at a great num-
ber of places. Also the rate of working can vary quite a lot. Certain
periods in a project are characterized by low activity, while others are
marked by working round the clock. In many projects influence and
responsibility are to a great extent delegated irrespective of the kind of
formal rule system. Therefore this way of working could be experien-
ced as a threat to the present relations of the labor market. In the pro-
ject organization the work is goal and problem directed instead of rule
directed. Fulfilling the goals according t o a given agreement is the
central endeavor; how this is accomplished is left more open. A detail-
ed regulation of the relations between the actors could be perceived as
a hindrance.
The change from traditional industrial organizing to project organ-
izing may consequently be expressed as a shift from monitoring t o neg-
otiation costs, which has a dramatic impact on the contractual forms.
The formal contract has to be designed in a general way and make
room for individual specifications and negotiations. Contracts of how,
when and where to work must to a high degree be informal and impli-
cit. In the construction sector it is common t o talk ahout professional
codes guiding the members of a team in the different phases of a pro-
ject. The individuals adapt to these codes by long lasting practical exp-
erience and from working with individuals knowing the trade (Polanyi,
19j8;Brochner ct al., 1992).
In other project-based branches these kinds of implicit rules have not
developed yet. Management and IT companies follow a different
approach. They try to induct tacit contracts by convincing the custom-
er t o use their concepts and follow their specially designed programs.
Many consultant companies have taken great pains to develop special
methods for working and for solving problems. Before entering the
market the personnel have t o be trained and convinced of the ideas. It
can be both costly and time-consuming t o replace staff who already are
a part of this special company culture. The investments in human cap-
ital may pay off, however, as the models used are company specific,
which make it possible to keep the customers - and the employees -
locked-in for some time (Ekstedt, zoo^).
Other actors of the C quadrant are independent enough t o create
CONTRACTS O F WORK I N A I'IIOJECT-BASED E C O N O M Y
-
Global renommCe is paired with local presence (Ekstedt et al., 1999).
Figure 4:z Market relations, transaction costs and contractual forms in diffe-
rent kinds of organizations.
Conclusions
Work contracts are closely related to the way economic activity is organ-
ized. The presented model gives a rough but useful picture of the char-
acteristics of different organizational forms. By pointing at the changed
prevalence of the four main categories it is possible t o discuss the con-
tent of the organizational transformation in some depth. The dramatic
change of market relations and transaction costs when moving from
onc category to another gives a platform for describing the changed
contracts of working life. It is even possible t o discuss the development
of informal rules (contracts) guiding the actors when it comes to how,
when and where t o work.
The organizational changes follow some distinct patterns. First of all
there has been an increased use of project organized activity for sev-
eral decades in most industrialized countries. The growing number of
people working in project-based organizations and project-based activ-
ity is striking. There is also an evident expansion of people working in
non-permanent activities. The expansion of temporary agencies is part
of this. The number of self-employed professionals is probably also in-
creasing. However, this does not mean the end of industry, but it does
point to the developnlent of new, often temporary, forms of organizing.
Permanent organizations will certainly not disappear, but they will take
on some new roles. They are needed to create and host temporary organ-
izations and there is still a lot of standardized production run by sub-
contractors who are permanently organized.
Many industrial companies, which at one time had almost all activ-
ities under the same roof, have been transformed into - or lend their
name to - a co-ordinating organization which assemblies, designs and
develops systems of articles combined with services and externalized
component production. One can actually see both projectification and
neo-taylorism at the same time: there is both an increasing use of tem-
porary organizations in the form of projects, and a growth of a minute,
global work division specializing in manufacturing of different compo-
nents. The organizational spheres are, however, much looser in their
composition than the traditional industrial companies and they can
also q ~ ~ i c kchange
ly in size owing t o a varying supply of projects. In
some fields of action, ICT for example, the spheres may also be very
sensitive t o fluctuations of economic demand.
The changed relations between the companies and their customers
are one of the major driving forces in the projectification process.
When developing more complicated and unique products the relations
between producer and consumer become tighter. Exit mechanisms
dominating the market relations of traditional industrial organizations
are exchanged for voice and sometime even loyalty in project based
activities. The closer ties of the economic activity also made their marks
on the internal organizing of the companies. Traditional industrial
companies were characterized by limited internal negotiation and search
costs and great monitoring costs, while the cost profile of the project-
C O N T R A C T S O F W O R K I N A PROJECT-BASED E C O N O M Y
the same partners, utilizing the same type of knowledge and involving
the same individuals. Within the frame of such stable relationships
there is leakiness (despite the noted lack of learning in projects), but
only within the frames of the project. New information and knowledge
is not obtained, as there is limited input from actors outside established
relationships.
Thus, the greater the overlap and similarities in technology and
expertise shared by the partners in an innovation project and the
stronger the ties ainong the partners, the more certain is the context for
.-
the partners. These bonds, common language, norms, and values, can
enhance the flows of information, knowledge, and resources and in-
crease stability in the networks. In contrast, the joining of two different
technological fields in an innovation project, which is common in fast-
paced industries, implies that the project is performed in a newly
established context. Relationships in newly established networks arc
characterized by uncertainty through a lack of expertise and common
routines and practices. One can therefore assume that flows of inform-
ation, knowledge, and resources in newly established contexts will
differ from flows in well-established contexts.
- The second contextual dimension argued t o be of importance for the
stickiness and leakiness of knowledge is the coordination and govern-
ance of business contexts. The coordination and governance of mar-
kets can be driven by both political and market forces and the strength
of these forces can differ in different industries. An interventionist polit-
' '
ical discourse prevailed in Sweden during the 1930s to the 1g8os,
especially in industries argued to be of importance for the welfare of
the nation, such as many service industries. Political forces toward in-
creased joint coordination and cooperation prevailed in these industries.
Market forces dominated the coordination and governance of other
industries, such as the manufacturing industry. In some industries these
market forces steered toward concentration and a low intensity in com-
petition whereas rivalry and intense competition prevailed in other
industries. The political influence on industries changed during the
1990s and competition rather than cooperation became the recipe.
However, different types of governance have impacted o n the structure
of industries and the development of mental structures with the
industries. Porac, Thomas and Baden-Fuller (1989) state that collec-
tive conceptions or mental models develop over time, affecting compc-
titive behavior. The different structures in the context supporting either
STICKINESS AND LEAKINESS IN I N T F R - O I I L A N I Z A T I O N ~ ~INNOVATION
L PROJFCTS
'n+
$
3+
5 Supporting The Fiber-optic
The FMS Case
competition Loser System Case
The Recyclable
Plastic Beer Bottle The Pro Viva Case
Case
88
STICKINESS AND LEAKINESS IN INTER-ORGANIZATIONAL INNOVATION PROlECTS
Process development in an
established production system
The first project studied is the development of a Flexible Manufac-
turing System (FMS) for cutting and welding for AutoNova's new plant
where the Volvo C 70 series was manufactured. AutoNova contracted
a German firm, Carman, for the design and assembly of the production
line, but Volvo and AutoNova decided which firms were to engage and
co-operate within areas where new methods and equipment were to be
examined. The development of the FMS was such a project. The FMS
was used to cut holes in the coach to assemble the front suspension unit
and the antenna and to weld the roof, the back, and the back shelf.
Volvo had agreements with three robot manufacturers that had deli-
vered robots for different plants: ABB Robotics, Kuka, and Prima.
Kuka also designed production lines, and ABB was at the time expan-
ding its business into assembly lines and these two firms were, there-
fore, competitors to Carman. For each installation Volvo compared the
three manufacturers and chose the one that provided the best offer and
technological solution at the time. Volvo contacted the Swedish firm,
ABB Robotics. It was argued that the geographical proximity of Volvo
to ABB and Permanova, the other partner in the project, was important
for the project's efficiency.
Volvo had conducted extensive research on laser technology, but not
on ways of using and integrating the laser with other equipment. Volvo
had earlier encouraged ABB to develop its business into this field. ABB
responded to its request by developing a laser unit at the firm, but it
STICKINESS A N D LEAKINESS IN IXTEK-OKGANIZATIONAL lNNOVATlOK PROJECTS
did not measure up to standards and the unit was closed. AutoNova
therefore contacted Permanova, known as a leading firm in fiber-optics
(an important part of the robot laser system). The core competence of
Permanova's unit for development of production systems was its abili-
ty t o design and integrate laser systems with very different technolog-
ies and products. Volvo had earlier worked with Permanova in several
tests and experiments, and Permanova provided services for some of
Volvo's laser equipment. Volvo and thus AutoNova knew that Perma-
nova was able t o deliver service in a very short time. Rofin Sinar par-
ticipated in the project, but AutoNova's contacts with Rofin Sinar were
made through Permanova because it was smoother t o make Permanova
responsible for the entire laser system.
As a participant in the project, Permanova accepted responsibility
for service and documentation of the installation, guaranteeing securi-
ty and the running of the system. It was therefore necessary to learn
about the entire production line and the other equipment used. Auto-
Nova and the actors involved in other parts of the production line also
needed to learn about the laser system and the FMS installation. Per-
manova therefore offered training programs and manuals on the
systems they developed.
ABB Robotics and Permanova's earlier interaction primarily consis-
ted of the delivery of products in accordance with detailed specifica-
tions, but with limited joint development. The interaction between the
two firms is however described as intense and extensive. Engineers
from both firms came to know each other well through the project,
which was seen as a prerequisite for more comprehensive cooperation.
The involvement and cooperation between the firms and the risk that
was associated with the interaction resulted in a formal cooperative
agreement between the two partners defining their relationship. It was
agreed that if ABB Robotics were to be involved in projects in which
lasers were needed, Permanova should be approached; and if Permano-
va needed robots for laser systems, ABB Robotics should be contacted.
In the other two cases, initial negative stickiness was observed. The
negative stickiness can be explained by the lack of an established con-
text for the project. In both the development of fiber-optical laser
systems, and the development of the fruit drink ProViva, two different
fields of tech~lologywere integrated. The joining of two technological
fields added complexity to the interaction among project participants.
The possible contribution of the knowledge provided by the other
party was difficult to evaluate and the flow of information between the
parties was often hindered. In the fiber-optic case, the geographical
distance between the two firms added to the difficulties perceived. The
initial difficulties in the ProViva project were easier to solve, due to the
geographical proximity between the partners. Differences in and
unawareness of the role distribution and work practice of its partners
can explain the negative stickiness during the initial face in the two
projects. Lack of earlier experience and established relationships
among participants contributed t o the unawareness.
To give an example, Permanova communicated with the people who
were considered to be the most knowledgeable members of the Rofin
staff. The Permanova staff also believed that the information and
knowledge they provided would be incorporated into the design of
parts in the joint product. When it turned out that the information was
not used, the interpretation was that the partner firm was ignorant, and
the relationship was, of course, harmed. Communication was ineffec-
tive, and gave rise t o misinformation causing anxiety and mistrust,
making the process sticky.
Proposition 3: In the initial phase of an innovation project differences
among technological fields, lack of experience and lack of established
relationships hamper communication and lead t o misinformation and
mistrust, which in turn gives rise t o negative stickiness.
Neither of the two projects was organized within the frame of one func-
tional system. Instead, several technological fields and adhering func-
tional systems needed to be matched. Furthermore, the high technolo-
gy involved was characterized by change and uncertainty. The partici-
pants in the projects lacked knowledge of their partners' functional
MARIA BENGTSSON AND I E S S I C A ERlKSSON
The other two projects - the fiber-optic project and the ProViva project
- were performed in newly established contexts and the projects were
mainly characterized by positive leakiness of implicit knowledge into
the projects. The knowledge provided was experimental rather than
standardized. The flow of implicit knowledge was possible due to the
presence of a translator who understood both parties and mediated
knowledge among the involved firms into the project. A two-way
translation of work practice, functional systems, routines, and norms
that prevailed in each technological field made the leakiness of implicit
knowledge possible.
In the Fiber-optic case, an engineer from Permanova spent six month
at Rofin Sinar. Through his interaction with their technicians, an
understanding of the functional systems and routines was received.
With this knowledge, he was able to initiate his colleagues at Perma-
nova into the functional systems of Rofin and to mediate knowledge
about routines of Permanova to Rofin. It was thereby possible to devel-
op shared routines and agreements about the continued flow of inform-
ation, knowledge, and resources between the two different technolo-
gical fields. In the ProViva case, the R&D manager at Skinemejerier,
having knowledge of both the scientific community and the functional
systems of Skinemejerier, helped to mediate the two knowledge
systems into the respective organizations.
MARIA BENGTSSON AND JESSICA ERIKSSON
that the firms have shared with the car manufacturer can be transfe-
rred t o competitors. The fiber-optic project was embedded in the same
competitive context and exposed to the "playing" of suppliers in the
automobile industry. Another dimension was of importance in this
case: Volvo's power position as a large customer, which allowed it t o
force Permanova into interaction with Rofin Sinar's competitors, and
vice versa. Rofin Sinar considered it t o be a problem when Permanova
utilized knowledge gained from their mutual project in cooperation
with other laser source manufacturers. The negative leakiness of know-
ledge in the fiber-optics project could render further commercialization
of the innovation more difficult and harm the relationship between Per-
manova and Rofin Sinar. In order to secure their relationship and t o
avoid negative leakiness, the firms initiated new innovation projects
that might provide benefits from negative leakiness in order t o stay
ahead of the competitors.
Proposition 7 : In the final phase of an innovation project, ( a )contin-
uous exchanges of partners and ( b ) actors' power positions can give
rise to negative leakiness.
The plastic beer bottle project and the ProViva project were organized
in a business context with structural conditions supporting coopera-
tion. The dairy and the brewery industries were heavily influenced by
political decisions, old patterns of interaction, and systems for distri-
buting goods. Despite a deregulation, some conditions that arose
during the regulative era remained, albeit weakened, in the dairy indus-
try. A number of different systems were entwined in both industries,
particularly in the brewery industry.
The cooperation within the brewery industry indicated that the de-
pendency among competitors, the trade association, and customers
was complex, which strongly circumscribed Zeunerts's ability t o act.
Resistance from the customers - political as well as industry pressures
to conform and not to challenge the system - hampered positive leaki-
ness (negative stickiness) when the plastic beer bottle innovation was to
be commercialized. The power positions of some breweries were also
of importance. Larger breweries that strongly influenced the distribu-
tion system were not keen to accept a new plastic beer bottle that pro-
ved t o be totally incompatible with the existing systems. Instead, the
leakiness from the project became negative. When the bottle was intro-
duced and then stopped, knowledge about the technical solution, as
M A R I A B E N G T S S O N A N D JESSICA ERIKSSON
well as the attempt to adjust the bottle to the existing system, were
open for competitors to copy.
In the dairy industry, Skinemejerier had to sell ProViva through the
channels of its competitors, because all dairies remained as distributors
of dairy products to the grocery stores in the respective regional area.
For the commercialization, Skinemejerier was dependent on coopera-
tion with its competitors. Some of the other dairies whose regional dis-
tribution placed them in power positions, hesitated to sell ProViva, per-
ceiving the product t o be a threat. It was thereby possible to hamper
positive leakiness from the project in the final phase.
Proposition 8: In the final phase of an innovation project, estab-
lished and enduring cooperation enhanced by significant actors' power
positions or supported by rules and regulations fosters conformity,
which gives rise to (a) negative stickiness and (b) to negative leakiness,
if competitors can capitalize on the knowledge provided.
Discussion
In our analysis of the four inter-organizational innovation projects, the
phases have emerged as important in understanding contextual influ-
ence on projects. A certain context can have a positive effect on sticki-
ness and leakiness during one phase, but the same context can have a
negative influence on the project in other phases.
First, we have found that a well-established context contributes to
the necessary leakiness of information, knowledge, and resources
during the initial phase. In well-established innovation contexts there
are familiarity, experiences, and supporting systems that allow for effi-
cient communication. This reasoning is in line with Bounty (zooo),
who argues that strategic resources and intellectual capital leak among
R&D scientists across organizational boundaries if acquaintance and
mutual trust develop among the interacting individuals. In well-known
contexts, actors who have previously interacted with each other and have
good "chemistry" form strong relationships (c.f. Larsson, Bengtsson,
Henriksson, & Sparks, 1999). Thus Larsson, Bengtsson, Henriksson, and
Sparks, (1999) argue for the need of a communicative capacity to in-
crease the ability to disclose knowledge to other organizations. A comm-
unicative capacity includes routines and systems for communication,
and such routines and systems exist in well-established contexts.
STICKINESS AND LEAKINESS IN INTER-ORGANIZATIONAL INNOVATION PROJECTS
against shared norms and accepted behavior (c.f. Gnyawali & Madha-
van, 2001).The familiarity and integration among competitors makes
it easy to gain knowledge rapidly about new ideas and to adapt them
t o the rules and norms that prevail. Hence, negative leakiness also is
present in the context.
Competitive governance structures in the market also cause negative
leakiness in the final phase. Gnyawali and Madhavan (2001) suggest
that dense networks are characterized by increased fluidity of resour-
ces. Dense networks will cause increased structural similarities among
potential competitors, making conflict avoidance more difficult and
being expressed as negative leakiness. If there are dynamic competitive
relations pressuring the firms, they could provide an increased flow of
resources from a project considered to be positive within the industry,
and contribute to learning in a wider context. From the point of view
of the firm contributing knowledge, it may he negative leakiness, but it
stimulates further innovativeness. However, if the knowledge generated
within the projects and their value-nets are implicit, the knowledge
translated into the project context also provides the project with some
degree of stickiness, hindering the leakage of knowledge into the exten-
ded network (c.f. Schulz & Jobe, 2001).
Our analysis has focused on contextual influence on the flows of
information, knowledge, and resources in inter-organizational projects.
From our analysis some propositions about the flows have been gene-
rated, and some tentative conclusions have been discussed. Based on
this discussion, we can conclude that the contexts of projects matter,
and that the contextual influence may vary during the course of the
project. A more distinct definition of different types of flows in inno-
vation projccts is needed, however (see e.g. Zander & Kogut's [19951
definition of knowledge as one attempt to do this). This study also
demonstrates that the embeddedness in cooperative and competitive
relationships must be acknowledged and further developed.
Increasingly, a characteristic of many project organizations is the move
toward developing strategic alliances and partnering arrangements
with other ~roject-basedorganizations. Examples of such working
partnerships are ubiquitous, ranging from the multi-partner consortia
working to construct Hong Kong's Chek Lap Kok airport, the Three
Gorges Dam in China, develop the latest generation Airbus model
A380 in Europe, and advance innovative wireless applications in comm-
unications. Although the reasons for promoting such relationships
are numerous, including risk management, economies of scale, and so
forth, little is known about the motivations promoting the push toward
such alliances, the mechanisms by which these alliances are propagated
and reinforced, and the outcomes of cooperative relationships. This
chapter will develop a framework for analyzing the nature of interor-
ganizational cooperation, particularly as it applies to information shar-
ing across organizational boundaries. Using case study examples from
recently initiated information sharing initiatives for planning and devel-
opment projects within the United States, we will examine the nature
' Portions of this chapter were adapted from Nedovic-Budic, Z. and J.K. Pinto, (r99y),"Interor-
ganizational GIS: Issues and prospects," A n m k of Regional Science, 33, 183-195. This resear-
ch was supported by NSF Grants ILS - y81z5zo and IRI - 9630634.
I N F O R M A T I O N SHARING A M O N G PARTNERING PROJECT ORGANIZATIONS
industry, for example, is one with such high financial barriers that the
European consortium that formed Airbus needed active and liberal
funding from member countries to first incubate and eventually create
a viable competitor t o Boeing/McDonnell-Douglas.
Technical - As project organizations often specialize in specific engin-
eering functions or technical operations, a project that requires mul-
tiple forms of technological innovation is usually simply beyond the
capabilities of any one organization. Firms, then, will routinely engage
in joint partnerships with other technical organizations to gain their
expertise, offset their own limitations, and present the client with a
stronger proposal, based o n the ability to offer a full range of services.
From a product perspective, Ford Motor Company has maintained a
long-term link with Mazda of Japan, t o the point of acquiring a min-
ority stake in the company. Ford gains the superior aluminum, small-
block engines that Mazda produces and Mazda benefits through For-
d's excellent car body integrity.
Strategic - Another important motivator for interorganizational coll-
aboration refers to the need t o create strategic alliances (Lundin &
Hartman, zooob). There are any number of reasons why such alliances
are beneficial, including the opportunity to penetrate previously closed
businesses, industries, or even countries, the advantage of gaining
technical benefits from the partner, and the effect of synergies through
the linking of organizations internationally. For example, many western
project firms seeking to gain infrastructure projects in countries that
have historically been difficult to penetrate, such as China or India, will
routinely partner with local companies as a necessary first step to gaining
access to these foreign markets. General Electric first sought to penetrate
the market to supply jet engines to Airbus through developing a strate-
gic partnership with SNECMA, the French engine manufacturer.
In sum, there are a number of practical reasons why project organi-
zations may seriously consider interorganizational collaboration and
information sharing, even with potential rivals. In developing a model
of the motivations and mechanisms for such information sharing
across project organizations, the balance of this chapter will draw
directly from the authors' recent research investigating interorganiza-
tional information sharing within the context of IS projects. Obvious
parallels can be drawn between this form of project and other cases in
which there is strong incentive for project firms to collaborate.
It is useful, before proceeding too far into this discussion, to briefly
INFORAlATTOU S H 4 R I N C ; A M O N G PARTNERINC P R O J E C T O R G A N I Z A T I O N S
define the idea behind the term "collaboration." Due to the inherent
similarities among terms such as collaboration, cooperation, coordina-
tion, and integration, the concepts are often used interchangeably and
indeed, in our discussion, we will at times substitute one term for anoth-
er. Nevertheless, the underlying nature of the construct is t o suggest
joint behavior toward some common goal of interest. This definition
comes from Pinto, Pinto & Prescott (1993) who synthesized the work
done by multiple authors employing these varying terms. Their findings
suggested that regardless of the terminology used, their implicit nature
essentially illuminated the same underlying construct.
flicts (Kumar & van Dissel, 1996) over authority, jurisdiction, and dis-
tribution of power.
Various organizational and environmental factors affect inter-organ-
izational exchange. Those include: stability of the environment; homo-
geneity of organizations; concentration of resources; resource capacity,
domain consensus among the organization, turbulence1 change, and
mutability of organizations in the environment (Cummings 1980).
Organizational connectivity is also related t o organizational internal
factors such as: centrality, formalization, complexity, and intensity (i.e.,
frequency of information flows and amount of resources shared; Van
de Ven and Ferry, 1980; Brown & Brudney, 1993).Calkins et al.,
( 7 9 9 ~present
) five organizational factors that could impact the dec-
ision t o institute standards for data sharing: bureaucratic practices and
standard operating procedures; degree of cross-functional cooperation;
organizational structure; political environment; and corporate culture.
Another factor is the project capacity of the organization, which refers
to "an overall index that measures the proficiency, and effectiveness of
conducting a series of implementation tasks" (Brown & Brudney,
1993).
The change and adaptation that an organization has t o go through
is yet another vital issue in the sharing process. This feature is particu-
larly relevant for project firms that are contemplating engaging in inter-
organizational exchanges for the first time. Any information sharing
effort will involve redefinition of existing tasks and structures and the
establishment of new ones. Institutional inertia and resistance to
change are a common reaction to innovations (Newton et al., 1992;
Craig, 1995). Mcrcdith (1993) identifies ambiguity and complexity as
causes of the organizational resistance t o change and cooperation. The
resistance to structural changes and institutional inertia, however, tend
to diminish as the expected benefits increase (Dueker & Vrana, 1995).
encing, data quality, data transfer and use (Guptill, 1994). The need for
standards increases with the data sharing activities as they become
necessary for determining the fitness of data for different users (Rush-
ton & Frank, 199s). Therefore, setting standards to facilitate sharing
has been widely acknowledged as a critical activity that can reduce the
costs of sharing data (Moyer & Niemann, r q q j ; Bossler, 1995). Inter-
organizational systems may require standards on project information
of a wide variety of types, including planning data (PERT charts, Risk
assessment and abatement procedures, Scope analyses, and WBS) as
well as control documentation (Earned Value Analysis and Configura-
tion Management). The key lies in creating a data standard that allows
all parties to correctly interpret status reports, updates, and other per-
tinent information.
~ ~ G - E Q ~ S D
>
Interorganization 4
ol Relationship
History
-Shored system
- Quolity - J o n t project
lnterdependenclei
Intensity
COORDINATION
1. A~titude
v
Attitude & - Dotabare, hoidwore Negotlotlon
PERCEIVED
Commitment ,
,h,
,, .rs, 1, ~~~~~~~k BENEFITS
- Infarmotion - Commitment/focur
rpoce, - Proied efficiency
- -
sharing applocotioni Perr~rtence - Enhanced decision-
[proprietory,
- Number, stotus ond mle - Communication making
open) of participants t -Client
-Coordination 2. Responsibilities responsiveness
Reasons
* Overarching - Accepmnce
-Backing by resources
-Synergy
- Econom~esof scale
- Overarching g m l r ~ ~ n ~ ~ n o g e m e n t =lorib
- Enhanced
Resources
-Leadership -Rewards collaboration
- Mondote/poiti=o .~ ~ ~ .Match with
~ organizational
/ ~ -Technology
~ ~ ~ i ~
Commiiieer mssion and functonr transfer
Other Factors
-Resources Organizational 3. Perceptions of equity
- Needr
Forms and fairness
Stobllty
-Centralized - Information
- Decenhazed/ - Accerr to data
distrfbuted Decision-moking
- N e w organizationsl -Contribution
processes and forms - Benefits
IMPLEMENTATION
top support, funding, project
scope, management (Bming,
expectations, progress],
ogendas
pol~t~cr/perronol~t~ei/P~iiite
Conceptual framework
The above discussion forms the backdrop t o the development of a con-
ceptual framework that incorporates a variety of salient issues that
must be addressed when contemplating the prospect of interorganiza-
tional project collaboration. While the incentives t o engage in these
sharing relationships are strong, there are also significant challenges
that must be addressed in order to gain maximum benefit from cross-
organizational cooperation. The conceptual framework in Figure One,
addresses some of the key concerns that are relevant to creating a positi-
ve and fruitful relationship across organizational lines. Broadly speaking,
and following our discussion above, we have categorized four sets of
issues that should be addressed in order to promote better project inform-
ation sharing: context, structure, process, and outcomes.
INFORMATION S H A R I N G A M O N G I'ARTNERING PROJECT ORGANIZATIONS
enhancing the likelihood of effective data sharing. Some of the key sugg-
estions include the following:
Customer
values -
t
Product
specifications -
t
Product
properties
a
Figure 7:1 The total quality concept.
Congruence
Market positioning
Volvo was one of the first companies in the world to reduce the pro-
duction rate in 1974. These were serious times for many carmakers,
British Leyland was bleeding, Volkswagen reported huge losses, Auto-
bianchi and Lancia were taken over by Fiat, Alfa Romeo by the state,
Citroen went bust and the French government helped finance a solu-
tion together with Peugeot. A strategy study in Volvo at the time pre-
sented two main options:
to broaden the car program (quickly) to include more than one
model
to invest more aggressively in developing Volvo's other business
areas, primarily the Truck division.
the truck division was combined with a broadening of the car program
(Lindh, 1984). However, the new car project, P172, was stopped
because the car was considered too big and costly in the current oil crisis
that seemed permanent. The only addition to the car program was the
Volvo 340 developed for the DAF-plant. This car was not up to Volvo
standards when it was released. It did not help. Otherwise the only
option was to prolong the life of the 240 series. Among other things an
alliance was formed with Peugeot and Renault to develop engines.
When the market turned to growth again the internal discussion on
market strategies, which had to a large extent been set in motion by the
current quality problems - not least with the Volvo 661343 in Holland,
ended in a decision to move Volvo towards the prestige segment. This
would be accomplished by leading the way for new car models by
introducing the prestige version first (and cheaper versions later). The
first application of this was the Volvo 760. In the meantime Volvo pre-
sented a number of experimental cars (a taxi, a safety car, a gas turbi-
ne car). The design work for the safety car went into the 760. At this
time product development costs for Volvo Car were as high as 10 % of
sales which was far too much. The new car was developed with an eye
to the American market and with extensive testing of customer tastes
in several countries. The launch in nine places at the same time went
well. The "boxy" look of the new car deviated from what Mercedes,
Audi and Ford presented at about the same time in 1982, but in fact
the aerodynamic measures were quite favorable for the 760. Many
interesting technical solutions were included. Sales surpassed expecta-
tions (in 1983 the 760 accounted for 12 % of total sales, a large figure
for a new car in a higher price bracket). In 1984 the less luxurious 740
was introduced. It was helped to a quick start by the success of the 760.
In the middle of the 1980s Volvo Cars stood very strong with a succ-
essful launch of the 700, with the estate version, 745, still to come.
The strength was in the products with their excellent safety records
and robustness. The latter aspect had been an argument since the very
beginning and the former had come gradually with the 240 and then
with the 700 series. The Lambda-sond had been an early, significant
step in emission control. The quality control system, with results tied
to an employee bonus system, had improved quality to top standard.
New forms of production organization were under development.
Strategically the Volvo focus was now on the development of the
Renault alliance. In product development a new direction was staged
by the futuristic Galaxy project initiated in the late 1970s. The task
was to look I 5 years ahead and see what cars were needed beyond the
~ 9 8 0 s One
. of the first things that were discovered was that the custo-
mers voted for front-wheel drive (a difficult concession given the age-
old quarrel on the issue with SAAB colleagues).
The Galaxy project bifurcated into two paths. First came the new
400 series with the first front-wheel drive version (480 ES), in 1986,
which, after a host of quality problems, stabilized nicely. The second
path from Galaxy was the 850, which was the big car supposed to
supersede both the 700 and the 240 series. The project had been going
on for about 10 years when the 850 was launched in 1991. Part of the
explanation for this delay was that both the 240 and the 700 refused
to die. Sales continued at a decent level. Also the solutions in 8 SO requi-
red a comprehensive redesign of the industrial system. The new car had
front-wheel drive and an aluminium engine positioned sideways. It
constituted a large strategic step as it manifested the introduction of
"joy of driving" as a core value. Still a daring "distinct and attractive"
design was largely missing. The 850 was a success from the start with
enthusiastic comments by motor journalists. Volumes rose quickly. The
young project leader, Peter Augustsson, received a lot of attention and
stories about the project began t o emerge as narratives with a "point."
One such story was that at one point in time project members started
to worry that the project dead line would not be met. A meeting was
called t o request that the launch date be postponed. But the project lea-
der had arranged with the CEO beforehand that when he, the project
leader, asked for postponement the CEO would use abuse and a loud
voice in denying a delay and declaring project dead lines sacred once
and for all. The theatre performance worked and the launch date was
kept. Peter Augustsson "got away" with the gambit of deceiving his
fellow project members. He had tried t o obtain a postponement and he
had taken abuse for the team, now they had to help him to deliver since
he was in disgrace with his boss.
The 850 was a strategic project in many ways. As mentioned it marked
a successful shift to front-wheel drive. This manifested "joy of driving"
as a core value for the brand. The movement to a higher price level had
started and the brand image needed re-articulation as well as the com-
pany philosophy and this needed t o be shared among employees in a
new "dialogue." As the dialogue progressed in articulating the compa-
ny philosophy the alliance with Renault kept growing more intimate.. .
PROTECTS A N D (:ORE V A L l J E S
Summary
The "point" of this rather lengthy account of the history of the Volvo
core values is that they are related to critical situations in the company
history. They are emotionally loaded and public. Robustness was a
core argument from the start. Assar Gabrielsson, one of the founding
fathers, is reputed to have pointed out that it is people who drive the
car and that they need protection. Safety became a key success argu-
ment with the 240 series. A car model that would not die served to
build that core asset in the Volvo brand name. It also established Volvo's
lead in the estate car segment, which landed it squarely in the family
car business. The Lambda-sond justified Environmental concern as a
core value. The 700 series constituted a continuation. It added a distin-
ct design that seemed daring at the time even if there were a couple of
cars in the USA with a similar look. The 850 model, launched in 1991,
added the "joy of driving" dimension that was necessary as the brand
strategy was to move the Volvo further up toward the premium car seg-
ment. It also marked a significant break with the earlier argument
against front-wheel drive. The interesting thing about this is that it was
the customer who had the final say. Even if most of the development
engineers still preferred rear-wheel drive they took the Galaxy findings
to heart and acted accordingly. Large changes in the production pro-
cess and component design (especially engines and transmissions) were
required. With this Volvo Car was firmly set in the Premium Car direc-
tion. When Mr. Gyllenhammar signaled that he did not believe that
VCC could make it (save its soul, as it were) on the basis of its new core
values the organization rebelled. The values, contradictory as they may
seem, were shown to be charged with emotional energy. It is against
this background of emotionally loaded and partially contradictory
brand values that our study of argumentation in car development pro-
ject meetings has been conducted.
The problem: Fundamentalist arguments and
project management
The issue then is: how can a fundamentalist approach to certain of the
brand values be combined with effective communication, and mainte-
nance of the customer appreciation of the brand?
The nature of consensus among competent peers on complex issues
could be described using the following constituent ideas (Moscovici &
Doise, 1994, p. 3 ff.):
When consensus develops in a social situation it is typically based on
choice. When facing choice, the group, through the confrontation with
arguments pro and con, are made aware of the danger of error, which
could he eliminated by consensus. We resort to consensus to overcome
the doubt, but also to end divisions and misunderstandings between
defenders of different positions. We believe strongly in the benefits of
mutual criticism and free examination of arguments t o reduce prejudice
and subjective judgment on our way towards a sound decision. But as
we approach choice and action there is a convergence of individuals to
associate with others, to demonstrate commitment t o a shared attitude
towards the contemplated action so that others can rely on us to d o our
part, include us in their plans, group and project. Action presupposes
unity of intention and discipline in pursuit of a common fate.
Consensus goes beyond acceptance or agreement. It binds the team
together - even if everything can be discussed and questioned there is
an underlying obligation t o conclude an agreement that will be kept.
An agreement that is obviously brought about by external pressure
cannot be considered consensual. Consensus is built on common
understanding (Habermas, 1984). Furthermore, there is a link between
consensus and the cultivation of reason. In the end people have a comm-
on principle of intelligence that will bring them in harmony toward
reasoned solutions, enlightened solutions in spite of clashes of interest
or opinion.
We thus have three central conceptions underpinning consensus for-
mation; choice (and the elimination of the danger of error), trust (arri-
ving at an agreement that will be kept), and reason (intelligence through
free exchange of ideas and opinions).
Moscovici & Doise (r994) claim that the premises of classic theories
(that, I . Consensus is best achieved if the group has precise inform-
ation and everybody participates, and, z., it is arrived a t through com-
PROJECTS A N D CORE VALUES
also. increase noise - road noise as well as wind noise. These conse-
quences were expected. There was a noise expert on the development
team in the first of the projects. He divided his time between noise
reduction projects for the Quality department and this project where he
was responsible for "Properties." This meant that he was a quality
assurer regarding the specification written into the contract between
the project leader and top management for this car model. "Properties"
was one of the functional managers in the project who gathered in the
PMG (Project Management Group) meeting half a day every second
week t o follow up the status of the project and take decisions o n pro-
posed solutions to outstanding design problems. The project was loca-
ted away from headquarters, in Holland, at the joint venture production
plant with Mitsubishi. The context for the project was rather complex
due to the facts that the new car was built on Mitsubishi's Carisma plat-
form (modified to reach Volvo safety standards but still focused on
common parts to gain economies of scale) and that production was
"outsourced" to the Dutch joint venture NedCar. The reader may ima-
gine the amount of negotiation with outside parties added to this pro-
ject on top of the traditional problems with interfering functional
departments (cf. Womack et al, 1990). Here we are focusing on contra-
dictions between brand values.
The PMG meetings are long, intensive meetings and the group is large,
about 2 5 people, because of the philosophy developed in Volvo t o achieve
coordination by keeping many members well informed about all aspects of
the project. The consequence of this is that meetings tend to become semi-
nars rather than decision-making occasions. The meetings may be ineffici-
ent, as most respondents complained, but the project can be well coordi-
nated. To solve this problcm the project had a Technical Management
Group (TMG) meeting on the afternoon before the PMG meeting.
Three episodes, involving noise consequences, from the video-recor-
ded PMG meetings have been replayed to participants individually and
their responses t o the question "What is going on here?" have been
audio-taped and transcribed. The episode itself and about 15 interpre-
tations by participants for each episode have been analyzed. Two comm-
on factors emerge. It seems like conflict betwcen core values initiates
discussion on responsibility, and that these discussions tend to push
members towards the periphery of the group. These were the episodes
(forgive the brevity):
Episode I: The noise expert had driven his test car at high speed on the
German "Autobahn" and discovered a wind noise probably stemming
from the trim molding around the windshield and/or sunroof. He
thought he should sound the alarm and he had brought up this quality
problem in the previous day's T M G meeting. The discussion there had
focused on fixing the trim molding and that would be the task of the
"Exterior" lead engineer. In the PMG meeting the project leader, who
was not present at the T M G meeting questioned whether this belonged
to the project. The Quality department should deal with this since it
was the geometry of the base car that was the root of the problem. The
counter argument was that it was the high speed that caused the noise
and it was a strategic issue since customers buying the turbo version
were likely t o drive fast. Anyway there was a simple solution (that in
fact had already been initiated by Quality) and that was to fix the trim
molding better. Now Exterior was anxious to define the problem as a
fixing-the-trim-molding problem rather than a noise problem (you
never know what can happen with noise problems). In the interview
afterwards the noise expert commented that he felt let down by the
project leader; when you bring up strategic issues like this people
should take them seriously and initiate a proper study of the sources
and not jump at simple solutions like this. People will not want to bring
issues up if they are ignored like this (Colleagues indicated that they
thought that he should have known that Quality was already at work
on this problem). Colleagues described Exterior as a person who has
little tolerance for ambiguity and the episode confirmed this view of
him. It was concluded that both the noise expert and Exterior lost posi-
tion in the team in this episode. (Centrifugal move).
Episode 2: The noise expert is reporting in the PMG meeting on the sta-
tus of a large quality project to reduce road noise. A large number of
improvements have been identified, each rendering the odd decibel of
improvement. He is talking about an experiment with a different stiff-
ness in some rubber bushings in the wheel suspensions. He mentions,
in passing, that the current ones deviate from specifications. The pro-
ject leader seizes upon this and asks: How come that we have reject
parts in current production? After moving over possible suspects the
gaze stops at Purchasing, who must admit that he does not know. He
feels accused. It turns out that an earlier discussion with the alliance
partner had ended in a decision that was not registered as a specifica-
P R O J E C T S A N D CORE VALUES
tion. Purchasing had acted correctly; the specification had not been
updated. N o apology. Purchasing felt left as an outsider.
Analysis
Even if these situations, and other ones we have observed, are never
clear cut due t o the complexity of the specific embeddedness of the pro-
ject I claim that a common factor when the project deals with conflicts
between brand values is that member positions in the team shift. It is a
matter of moving towards a more peripheral position because of failure
t o assume, or not being given, responsibility, or the opposite. In another
set of episodes where the project faced constraints from the environ-
ment (cost reviews or time schedule changes) it was found that the
team tended t o band together in the fight for the integrity of the pro-
ject and members who stood up for the project could gain position
(centripetal moves).
There was little reference to the brand values (implicitly taken for
granted) in argumentation, but there were these gains and losses in
position (or social capital). This agrees with a theory of membership
work as presented by Munro (1996),which consists of two aspects:
identity work and alignment.
In order t o be a (competent) member of the team we have to have a
role in the team as a constructive contributor that is recognized by the
others. We work out an identity in the context of the team and the mea-
sure of our success may be some kind of centrality in the group. Then
we are trusted to speak on behalf of the group and make binding com-
mitments. A member that loses face will be under observation. This
seems t o be a strong driving force in premium product design projects.
The other aspect of membership work is "alignment" where acts of
the member are aligned to the common quest of the team. A first requi-
rement for this t o happen is that the common quest is articulated and
that the aligning member has an opportunity to contribute. The articu-
lated common quest is a narrative under construction. It provides the
context (ground) against which the contemplated contribution (figure)
is given meaning, - by the proposer as well as by the assessing mem-
bers of the team. In order for the project narrative to invite the mem-
bership t o work it must exhibit subjunctivity (Bruner, 1986). Subjunc-
tive verbs introduce conditionality, for example, if a student asks me to
become her thesis advisor my answer could be: "You write me a thesis
proposal" indicating that I am inviting her but my action will be con-
ditional upon how I judge her action. In this sense subjunctivity invites
t o membership but introduces possibilities (possible worlds) rather
than certainty.
Another aspect of the articulated narrative is that it helps members
avoid misunderstanding since they work out "implicature" (Grice, 1967)
from a common ground. Grice introduced the Co-operative Principle
meaning that any conversation is a co-operation between participants
who have to follow a large number of rules to accomplish an enjoyable
conversation. The principle is broken down into four maxims (quality,
quantity, relation, manner), and by breaching these maxims a speaker
can signal that there is something behind what is said, an implication.
The co-produced narrative mentioned above provides a joint basis for
sense making and, in this way, for working out implications once the
signal is given.
The point with this schema is that it depicts speech acts as action cast
in a narrative, project shape. When we understand each other's speech
acts in this way it is only natural that we shape our contributions to the
exchange in alignment with, or in opposition to, that narrative. An utter-
ance produces a communicative situation that links people together, via
an object (the text), i.e., somebody is addressing somebody else. This
link is formed when the text does something to the recipient (The sign
"Beware of dog!" gives me a warning; it is an actant). In this way the
recipient attributes what the text is giving t o her by relating the text to
other texts to form a reasonable interpretation (never certain). These
productionlattribution dimensions determine the types of transforma-
tions that are implied. To each of these types of acts can be coupled
ideal conditions of satisfaction (like sincerity).
Next we turn to rhetoric to identify the two strategies (liaison and
dissociation) we use to make people accept our discursive objects. Some-
times persuasive rhetoric is not required since there are procedures that
render conventional what is otherwise not conventional (like contracts
or difference in rank) - silent rhetoric.
Through rhetorical devices, or silent rhetoric, my narrative may get
inserted in your narrative; I will give a contribution t o your project, if
the parties accept such an insertion. Such a mechanism is possible if we
can mobilize the missing link, the instrument that is used in accompli-
shing the narrative. Here Cooren has already laid the ground by sepa-
rating the text from the speaker and point to the text as "actant."
(Latour, 1996). If we look at the contribution (sub-mission) t o the pro-
ject (mission) as an actant we can also see that it is quite possible t o
work under the mission (alignment) without being totally committed t o
all its goals (like the academic can submit a paper t o a journal). If,
however, a participant wants to link hislher identity t o the project (for
career reasons) membership work is the central aspect. We are likely t o
find varying identification with the project among participants in pre-
mium product development. Shifts in their position in the project are
illustrated in the three episodes listed above.
My claim is that the project narrative can accommodate internal
diversity and still maintain team cohesion. Such a narrative I call
"strong." Some properties of a strong narrative are:
I. A strong narrative contains instantiations of the core values of the
organization that the team producing the narrative represents.
This means that the narrative is a carrier of values as applied to
the current and to the expected future time. The story, through the
relations of its constituent parts, presents its meaning, like the bibli-
cal story about the merciful Samaritan presents the virtue of merci-
fulness (cf. also Weick's, 1995, views on sense-making as enactment).
Bruner (1986, 1990) argues that there are two modes of thought,
both irreducible to each other because they have different operating
principles, criteria of well-formedness, and procedures of verification.
One mode, the paradigmatic or logico-scientific builds on conceptua-
lization and formal operation ila the syllogism. It is the traditional
scientific mode of thought with deductive reasoning as ideal and with
a tendency towards universal statements. This mode of thinking leads
to good theory and is suited for arguments applying instrumental
rationality t o demonstrate that a proposed solution is the best given a
clear goal. The other mode, the narrative mode, leads t o a good story
and is well suited for arguments based on value judgment in complex,
multi-goal situations. Judgment of the goodness of a story is based on
its sequentiality (Bruner, 1990, p. 43), the unique sequence of events,
mental states and happenings that involve human beings as actors.
The configuration of the actors in the plot gives them meaning.
PROIECTS A N D CORE VALUES
CHRISTOPHE MIDLER
User perceptible Simple radio Radio Radio with Radio integrated with RDS (Radio Data System) Integrated with in-car PC
product volue integrated compact CD player & TMC (Traffic Message (car phone, navigation
cassette Rodio with interface for Channel) system, speech recognition,
Stereo analogue car phone Radio connected email, fax, phone, TV, CD
Digital (LCD) Remote control on steering CD changer ROMj
display column Digtal Sound Processor Digital Audio Broadcasting
External display on Rodio with digital car
dashboard phone
Additional feature Receiving music Ploy recorded Simultaneously receive Receive specific, filtered Inteructivity; Multimedio;
regarding and information information music, information and traffic inbrmation Customization of products
information transfer smple data
Technological Tubes used since Transistors Additional module: Integrated circuits Speed and capacity of Speed and capaciiy of
progress the beginning of Tape Deck Additional module: CD microprocessors microprocessors
car radios Laser technology: digital Obiect oriented
data compression; robust programming
micro mechanics Communication busses
Flat screen displays
Frequency ronges Short Wove (SW); SW, MW, LW, SW, MW, LW, SW, MW, LW, SW, MW, LW, SW, MW, LW,
Medium Wave Frequency FM FM + subcorrier FM + subcarrier FM + subcurrier and DAB
[MW);Long Wave Modulation (FM] transmission bonds
ILWI
Selection of radio Manually with Manually and Manually and Electronic search of Fully electronic search Electronic with various
stotions rotary button mechanical pre- mechanical pre- stations (Phase Looked [outortore, alternative feotures depending on
[capacitor select buttons select buttons Loop] frequencies, program type selection by customer
technology) recognition, ...I
70 -
60 --
m
9 50 --
C
.-
-- 1
80 81 82 83 84 85 86 87 88 89 90 91 92 93 94
year
offerings. Next, the trend towards smaller size supports a system archi-
tecture dynamic that constitutes a major challenge for the various
industry players. We will address this issue below. Finally, the perma-
nent nature of these redefinitions ensures that, although electronics
plays a crucial, strategic role for car manufacturers, they have never
been able t o master research into the field on their own (witness initi-
al attempts that ended in failure). In the 1970s France's Renault, in par-
ticular, attempted t o develop a subsidiary but had to abandon the idea
because it was unable to maintain the appropriate electronics experti-
se in an environment of constant change.
Consequently, trends in car audio systems are primarily driven by
companies providing electronics technology. This explains the current
problems described in the next section, where we see that enhanced
understanding of how products are used is increasingly essential to pro-
iect success.
Antenna
L Central Unit
-- Abbreviations:
-
Tuner -o Key
board GPS: Global Positioning System
provides exact position OF vehicle
using satellite information
CD
- --
GPS -t, GSM: "Global System for Mobile
CD ROM telephony": Used in Europe but
not in the US &Asia (AMPS
GSM standard]
- -- phone
W:Television
CD: Compact Disc
CD ROM: CD containing software
loud- Tope: Tape Deck
TV speakers
Driver
Figure 8:2 Technical architecture of an ICE system in 2001. Source: Kesseler 1998
rnAftersales
Boldface type: Initial marketing of the innovation. Regular type: Subsequent marketing
Table 8:3 Innovation trajectories in car audio systems. Source: Kesseler 1998
IXTENSIVE INNOVATION CONTEXT A N D DESIGN S Y S T E M D Y N A M I C S
car distributors did not have the electronics expertise t o handle pro-
blems arising from the incorporation of radios into cars. But it had a
major consequence, in that in the eyes of their customers, manufactu-
rers, by virtue of their networks, became responsible for car radio per-
formance. After-sales service gave rise t o a design phase focusing on
improving the compatibility of the car and its radio.
O n the other hand was the emergence a gradual standardization pro-
cess for the car's and the radio's functional and engineering specifica-
tions, whereby each could anticipate the dynamic of the other without
explicit coordination. This standardization involved both the radio's
design constraints to be observed and the evolution of manufacturers'
car specifications, including integration of the DYN format into the
dashboard design, interference suppression in electrical equipment,
provision of necessary connections for powering the radio, and speaker
and antenna prewiring.
' On thc French market, rhe first car radios marketed by OEMs with new cars appeared in 1981
for Renault and in 1989 for Peugeot.
I N T E N S I V E INNOVATION CONTEXT AND D E S I G N 5YbThM D Y N A M I C S
aTechnology
IIPlatform Application
n x Consumer
market
("Aftersales"]
products
n x OEM
products
Bringing these concepts or half products (1,e Masson & Weil, 1999)
to maturity: The third task is to bring the innovation t o a mature
form, so that it can be incorporated into the project without unduly
delaying the release of the final product or endangering production
quality.
The challenge to the supplier and manufacturer as they carry out these
tasks in cooperation with each other is, of course, t o reduce costs as well
as the associated risks of such early exploration. The compatibility pro-
blems that arise in the later stages of a project, when supplier and manu-
facturer fail t o coordinate on a "road map" in such a rapidly developing
area, are significant, as is the risk of duplicate exploratory work.
We must emphasize the twofold aspect of this co-learning process: it
simultaneously involves defining innovative functional specifications
that have the potential for further development, and mapping out the
technological path by which they can be given concrete shape.
Conclusion
By emphasizing the "renewal paradox" of non-innovative, project-
based construction firms, Ekstedt, Lundin and Wirdenius ( ~ 9 9 2poin-
)
ted out the importance of a "permanent" organizational context in
providing a sustainable environment for innovative projects over time.
I K T E N I I V E I N N O V A T I O N CONTEXT AND D E S I G N SYSTEM D Y N A M I C S
In line with this thesis, this chapter illustrates how, over 30 years, the
multiple and diversified innovative breakthroughs in the car ICE
systems trajectory are linked with major changes in the internal organ-
ization of the studied firm in relation to its operating environment.
In the transformation process of the innovative design system of the
firm, the "co-learning," inter-firm cooperation model appears to be the
final, promising but also problematic step in meeting the challenge of
the intensive innovation context. The co-learning situation can be
described in the following matrix. It describes a situation where the
partners of the innovative cooperation are confronted by both impor-
tant economic stakes, in terms of market shares and investment, and
p e a t uncertainties with regard to the possible results. Such a situation
differs from that of a co-research partnership, where the stakes are less
important, and from a co-development alliance, where the focus on the
planned target is a key resource for inter-firm coordination.
BARBRO I. AN Y L. W I L S O N
Introduction
It has been suggested that we are witnessing a marked drift in the way
enterprises are perceived. In his brief essay Lundin (2000) observed
that enterprises exist at two levels - a relatively "permanent" one that
might be considered "traditional" in an organizational sense and a
relatively transient one, where teams were assembled t o carry out tasks
within certain budget constraints of a monetary and temporal nature.
The expressed view was the permanent organization is intended to live
on for an indefinite period of time, while the temporary one was plann-
ed t o have a limited lifespan. It was also implied that permanent organ-
izations achieved stability through routinization of its operations.
Looking backwards into the history of organizing human ventures,
it is easy t o point out that temporary organizations must have been
abundant. Most of them could be associated with what might be call-
ed "one-of a kind" projects, such as Stonehenge and the pyramids, or
making trips to collect Danegeld. Yet these projects were not wholly
unique. There are other stone-settings like Stonehenge. Likewise, there
are many pyramids and variations on pyramids such as the ziggurat.
Further, we know of many Viking chieftains who went south, bent on
trade and plunder. But in these cases the enterprise and the project were
synonymous. The permanent, routine-based organizations are no
ORGANIZING I N TWO MODES
modern inventions either. The Roman army and the Catholic Church
are often being mentioned as outstanding examples. These organiza-
tions, of course, also ran projects in a sense. Every new campaign,
every new cathedral could be seen as a project, even if the constraints
on the project were more vague than those of modern projects.
Indeed, it is not clear that projcctification is necessarily a trend. It
might rather be a symptom of the present situation in the global eco-
nomy. Twenty or twenty-five years ago it was fashionable to talk about
Kondratieff waves (c.f, Mensch, 1979). That is, the economies of
industrialized nations were winding down a "long wave" of develop-
ment that would bring about a significant change from stagnation at
that time to unlimited opportunity. Without making a judgment on the
use of these waves in economic forecasting, it seems to us that those
predictions have materialized. New industries have been formed, e.g.,
software and biogenetics, and old ones have reinvented themselves to
accommodate new technologies. Future economic historians thus will
likely look back on this period as a turbulent one in which a new long
wave was formed.
Nevertheless, the issues that Professor Lundin has raised with regard
to temporary and permanent organizations serve as a framework for
understanding how organized entities, organizations, enterprises, or
public agencies apparently are in the process of evolving. The discuss-
ion in this paper is oriented toward how projects are embedded in such
organizational settings, and how learning takes place in the two types
of organizations that were mentioned earlier, namely routine-based
ones and project-based ones. The suggestion that is presented is that
modern enterprises are mixtures of "the permanent" and "the tempo-
rary." This observation has been described as projectification, etc., and
appears to be a mixture of old and new phenomena. In this regard,
most research fails to provide a good understanding of how the per-
manent and the temporary are distinguished and how they are inter-
linked. The reason for this oversight is that theorizing has tended to be
overly concerned with formal or informal structures for grouping activ-
ities. A better way of viewing this matter, we suggest, is to picture both
the temporary and the permanent organization as comprised of flows
of activities.
Our feeling is that observations support the suggestion that tem-
porary organizations and permanent organizations appear bonded
more closely than present theory indicates. That is, routine-based organ-
B A R B R O I. A N E L L A N D T I M O T H Y L . WILSON
' Othcr hypotheses are of course possible. The one presented here, of course, is the one that we
think is most consistent with observations.
O R G A N I Z I N G IN T W O MODES
FOCUS
I
1 PROJECTS
C. The temporary
organization.
D. The "one of a kind"
organization. I
Figure 9:1 Organizational Settings and Foci of Modern Organisations.
B A R B R O I. A N E L L A N D T l M O T l l Y 1.. W I L S O N
0bservations
An organization, any organization, is (supposed to be) a tool used by
people individually or in groups to accomplish a wide variety of goals.
Its existence is not an end in itself. In other words, an organization
embodies the collective knowledge, values, and visions of people who
are consciously (and sometimes unconsciously) attempting t o obtain
something they desire or value. An organization is a response to and a
means of creating value that satisfies some human need. New organi-
zations are spawned when new technologies become available and new
needs are discovered, and organizations die or are transformed when
the needs they satisfied are no longer important or have been replaced
by other needs (Jones, 1995). In this section we reflect on three of the
quadrants in Figure 9:1 - the fourth, one of a kind organizations, is of
lesser interest at present.
are not genes. An individual cannot change his or her genes, but an
organization can change its routines.
For evolution t o take place, four processes are of critical importan-
ce. One leads to the creation of variation, intentional or unintentional.
The second one, retention, leads t o some variations being favored, that
is repeated in the case of routines, while others fade away and are
extinguished. The third process, that of retention, leads to incorpora-
tion of the selected variations in populations, for instance in routines
in organizations (Nelson & Winter, 1992:Aldrich, 1999).The favorably
selected variations may spread by a process of diffusion (Dawkins,
1976). These processes occur in a setting where competition for scarce
resources occurs. The processes of selection and retention might also be
understood as a form of learning.
Variations might be generated from several sources, for instance
from planned changes, from simple mistakes, or from random inci-
dents. In such a situation, doing things by projects offers possibilities
for learning, by introducing variations that the permanent organization
can select and maintain. In this way, the project might be seen as a
quasi-experiment, that is, as a part of the trial and error way in which
organizations explore existing possibilities. In this regard, it has been
suggested that one characteristic of "excellent" firms is that they con-
tinually conduct these experiments (Peters & Waterman, 1982). One
might perhaps say that the permanent organization has learnt
something from the temporary one when changes in routines, routine
cycles, or sets of routine cycles are changed.'
The "planned change" approach can, however, produce errors o r
failures. Turner (~qqq), in fact, suggests that these types of projects
carry with them a high failure rate. That is, the output of these simple
trials cannot be completely controlled and might introduce more harm-
ful than helpful variations. From an output assessment standpoint,
the organization has learned little if the projects leave no traces of
changes, preferably improvements, in existing cycles of routines or in
the routines themselves. Many change projects in organizations cause
a temporary uproar, but after a while, the normal mode of operations
is restored.
Other criteria for learning of course also exist, such as changes in the common value and belief
systems.
B A R B R O I. ANELL A N D T I M O T H Y L. WILSON
and delivering the project's output t o the clients which often causes
problem in soft projects, and, of course, concerning human resources
management in all its aspects.
' This theory has served as the basis for much of the prolect-assoc~atedwork of the Scandinavian
school of project studies. At the Calgary meeting of IRNOP in 1998 seven of the nine papers on
the trmporary organization cited this work (Hanman et al., 1998). It is interesting, however,
that in a lecture t o one of the author's (TLW) courses Professor Lundin (2002) stressed it was
"a" theory, not specifically "the" theory. He thus left open the possibilities for redevelopment
o r modification. Perhaps this book will take some steps in that direction.
BARBRO I . A N E L L AND TIMO'I'HY L. W I L S O N
The term "project" gets applied t o virtually everything temporary organizations do. In a prac-
tical sense this practice is understandable. The very tem "projcct" in general usage implies
something will ger done. Thus, who in their right mind would say they were planning some
Lindblomian action, or even worse yet, a boondoggle?
' Wehster (The American Cullcgc Dictionary) has the following definition for a boondoggle -
slang: work of little or no practical value.
B A R B R O I. A N E L L A N D TIMOTHY L. WILSON
means for getting things done, the only thing sure about boondoggles
is that they will cost money.
Naturally there is a continuum between "real" projects and boon-
doggles. B2B project organizations depend upon projects for their
income. They thus must be competitive in their bids, develop relation-
ships with their customers, and produce the results they promise.
Because these organizations receive ongoing reviews from their custo-
mers, their projects must be specified in terms of customer understan-
ding and be generally successful. Boondoggles represent wishful think-
ing. Anyone can get involved in a boondoggle, and the less the experi-
ence an organization has in planning projects, the better the possibility
of a boondoggle resulting.
It should be noted, however, that boondoggles are not the sole
responsibility of project initiators. Two parties are required to produce
a contract. There must be a funding source as well as a provider. Some
of the best boondoggles have "deep pockets," a funding source with
infinite resources and little inclination to ask about results. It follows
that state and federal governments make good customers for boon-
doggles. Agencies have budget allocations that require spending, and
agency budgets tend to be historically determined. That is, the expen-
ditures from the previous year are used to set the budget level for the
coming year. Programs are rarely evaluated. Thus, a timely report is an
adequate result of a central government project.
Government agencies, on the other hand, do not have sole title to
boondoggles. Certainly industrial organizations support their share of
boondoggles. Of special interest are those unique "projects" that firms
enter into that promise their renewal. It has been suggested that these
projects are rarely successful (Ekstedt, et al., 1999, 118). Without a
clear definition of a task to be fulfilled and an explicitly defined time
limitation, success as it is generally defined could hardly be expected.
other case we would now cite is Hewlett Packard's merger with Com-
paq. A merger team has been assembled to oversee that transition. Its
dedication toward the permanent organization (our hypothesis) is cap-
tured in its "clean team" designation (Economist, zoozb). Further,
members of that team will stay with the merged organization after it is
confirmed (Lohr, 2002).
With regard to learning, it is interesting to note that although ques-
tions of learning from projects to routines has received concern (Sijder-
lund, 2000, 68; Ekstedt. et al., 1999, 124-154),the question of lear-
ning from routines to projects is seldom discussed. Both types of know-
ledge might be needed to improve performance in organizations. We
thus would like to reflect on the "learning dilemma" of present theory.
It would appear that this concern might be exaggerated. March (1994)
has suggested that learning and knowledge accumulation are evolutio-
nary processes. Additionally, he and his co-workers (March et a!.,
1991) would seemingly argue that not only does the permanent organ-
ization learn from a project, but its competitors would also. Simply
put, this philosophy suggests learning and knowledge accumulation are
not outcomes, but paths that lead to outcomes. Thus, looking for evi-
dence that a project team has stored its knowledge somehow may be
the wrong model in learning and knowledge assessment.
The definitions of individual learning are built on changes in cogni-
tive structures, which are difficult to observe and on changes in beha-
vior, which are less difficult to measure (Bjijrkegren, 1989; Ostergren
& Miillern, 1995). Translated to organizational learning, changes in
cognitive structures might be likened to changes in central common
perceptions and values and changes in behavior to changes in impor-
tant routines (Bjorkegren, 1989). Two types of learning from projects
therefore might be surmised. On the one hand, there is learning about
project management, i.e., the organization becomes more proficient at
running projects. On the other hand, there is the learning to utilize
results from the output of projects. An example of the first type of lear-
ning could be that the organization grows better at running product
development projects, while an example of the second type of learning
might be that the organization becomes more proficient at creating new
products or product variations.
Culture, of course, is important in encouraging team members to
share information, and successful project organizations appear to be
"good" places to work (Brown & Eisenhardt, 1997). In these atmos-
ORGANIZING IN TWO MODES
Reflections
Looking hack, economic historians may see these times as a period of
turbulence in the world economy. Amidst this turbulence, projects and
project organizations have emerged as a means for getting things
accomplished. It will be interesting to see what these historians have to
say about these times - in particular what they have to say about the
use of projects to get organizations to adapt to their environment. We
think the various pictures that have been developed for organizations
are symptomatic of this period.
We see organizational adaptation as an evolutionary process. The
nature of evolutionary processes is that some entities, e.g. organiza-
tions, will cease to exist. Others will modify and continue to grow. The
utilization of regenerative projects is but one option for creating varia-
tion, and there are no guarantees that the variation that is created will
B A R B R O I. AiiELL A N D TIMOTHY L. W I L S O N
the "Library" she runs with a capital "L" in what follows) submitted
a tender for the local branch of the city library where she was working,
in competition with the head librarian of the municipality. This was at
the beginning of the ~ q g o s i.e.
, a time when changes were sweeping
over the public sector, of which the library was a part. Her tender att-
racted great attention, practically created a stir, in the municipality,
both among other librarians and the civil servants and politicians who
dealt with the tender and decided who was to be granted the contract
to be the provider. Even among the most zealous advocates of privati-
zation, her tender aroused confusion (Sundin, 2000).
The story about the Library and the Librarian includes many of the
key questions of our time regarding organizational change. It is
through the latter, i.e. organizations on both the private and public
sides, that society, work, business, etc. change. All changes take place
within them and through them. There is no business outside of organ-
izations and no public sector that is not accommodated within an orga-
nization. In this case it is primarily the municipality as organization,
library service as organization and finally the specific Library in ques-
tion that are of relevance. These units of description and analyses are
closely connected constructed by and constructing each other. How-
ever - the position of these organizations and the scope of action for
the actors are influenced, perhaps even directed, by decisions taken on
the national level. Another important precondition, both for the organ-
izations and for the individuals, is history. This is one of the reasons
that attention has to be paid to the growth of library activities and to
librarians as a group. Over time, the culture of organizations and the
identity of occupations and individuals are created and developed.
Neither culture nor identity is easily changed.
This case touches on several theoretical fields and on reliable ways
of describing and understanding society and organizational change. In
this article I will focus on a few aspects. Both the course of events and
the result are "a child of its time" - a time when the public sector was
transformed in the direction presented here. The central distinction
between the private and the public sector seem to be far from unam-
biguous and perhaps obsolete.
The municipality in which the Librarian is active is not unique, even
if unusually ideologically motivated. The will for change existed
throughout the country. The municipal actors sought change. An in-
creased number of entrepreneurs and increased entrepreneurial spirit in
REGENERATED PROFESSIONALlSM
cipal, libraries are a relatively new phenomenon. This form was not
fully implemented until the 1960s. Previously there were parish librari-
es and libraries run by popular movements.
Library science became an academic subject with a clear occupatio-
nal orientation at the beginning of the 1970s when the School of Lib-
rary and Information Science was founded. Before that, librarians were
sometimes the local elementary school teacher or upper-class women
who worked in their spare time (Olsson, 1991; Aberg, 1979). The local
elementary school teacher was usually a man, and upper class women
were, obviously, women. Thus, the work of' librarian has not had as
unambiguous a femalc gender label as it does today. Entrepreneurship,
on the other hand, has a male gender label (Jonson-Ahl, 2002; Sundin,
2002).
According t o AKU 2001 there are presently almost 7,000 librarians
in the country, about 80% of which are women. The percentage of
women among municipally employed librarians is even higher. Librari-
an is a low-wage occupation, considering the long education that lib-
rarians receive. Women, as so often is the case, earn less than men and
less than nurses and secondary school teachers, two other low-wage
occupations in which women are over represented (SCB AWLA Tabell
11, 2000).
The role of libraries is: culture, information and education (Audun-
son, iyy5). "This conception of the library as a universe of knowledge
is deeply rooted in the self-understanding of librarians". The idea of
general education seems t o live on, something that can also be seen
with the Librarian. As a group, librarians have been the bearers and
advocates of a democratic view of culture. A part of this has been felt
by many to mean that libraries should he owned, administered and run
by the public sector, that they should be a part of the modern welfare
state. Profit and other economic concepts do not fit in well with that
self-understanding and characterization (Sundin, zooo).
Librarians have a strong belief in the importance of their own work,
something that is considered t o characterize professions. Librarians
meet several of the other general criteria for professions as well: they
have an approved academic education, they hold the leading posts
within their sector and they have their own culture. Other criteria for
professions are not met by this group. Among those are not being in
control of their own sector - there are libraries that are run without lib-
rarians and library activity that is "thrown together" with other activ-
REGENERATED PROFESSIONA1.ISM
ities, such as recreational facilities. All in all, I find it apt to refer to lib-
rarians as a semi-profession with intimate knowledge in their field and
a strong occupational identity (Etzioni, 1969; Hagerlind, 1991; Selan-
der, 1989).
Librarians are often described as devoted t o their occupation and
their work. As a rule, those who become managers and are put in charge
of economic matters see themselves in the first place as librarians. This
leads to a task-oriented organizational culture and attempts t o remain
aloof from strategic and economic considerations. Such considerations
are considered t o be narrow-minded and an obstruction t o the work of
bringing culture t o the people (Egerdal, 1992). From this follows that
librarians according to Egerdahl describe themselves as "passive, intro-
verted, obedient, humanistic oriented and interested in cultural". He
adds that as "a trade group they are really on thin ice in terms of man-
agement ability, drive and organizational talent". Given such characte-
ristics, librarians have difficulties promoting themselves and marketing
their activities. The activities are also very difficult to evaluate. They
are typical non-profit organizations that are difficult to conceive of
making a profit. They seem to lack what is necessary for adopting a
result unit type of model.
In the quotation from Egerdal ( ~ q g z )as , well as from others, the
characteristics of librarians would seem to be the direct opposite of entre-
preneurial characteristics and, moreover, of male characteristics.
However both the Librarian and many of her occupational colleagues
work for and in their libraries in a way that has to be characterized as
innovative, i.e. entrepreneurial. A devotion and love of the library is a
strong force. This is considered to be one of the strengths of the pro-
fessions, and it is found among librarians.
Libraries are and have been located together with other recreational
facilities, like sports, in some communities because they are seen as
variations on the same recreational theme. To the librarians there are
unique and valuable characteristics of libraries which can be threatened
if libraries have t o cooperate or compete with recreational activities.
ELISABETH S U N D I N
Shifts in practice
The invitation to submit tenders was preceded by a specification of
conditions from the politicians in charge of procurement. The period of
time for submitting tenders was short, and the decisions were made
late. Everyone involved complains about this leading to short-term
thinking and risks of discontinuity. In addition to the Librarian, the
municipality also submitted a tender via the head librarian. The tenders
differed not only with regard to price but also with regard to the con-
tent of the service to be offered. The Librarian wanted very much to
have a branch in a nearby village, which would be more costly. After
some discussions and a certain amount of turbulence, the Librarian's
proposal was accepted -however, she had been forced to "give in" on
the issue of the branch.
The formulation of the contract follows the characteristics of pro-
jects; time, money, aims and means. It was stated what services were to
be offered to the general public at the library and in conjunction with
the library as well as under what conditions. In the conditions there
was no mention of the work having to be performed by trained libra-
rians. (The demand for occupational training is, however, mentioned in
relation to schools and childcare). What is to be offered through the
library are books and media services and activities designed to promote
reading. In her tender the Librarian specified various target groups,
such as childcare and a book service to nearby villages. Among the con-
ditions, for example, are opening and closing times. It can seem as if
the conditions do not leave very much leeway for innovation and crea-
tivity.
In the tender the prices of the services offered are specified. The peri-
ods of time for inviting tenders roughly coincide with election periods.
The follow-up of whether the terms of the contract are being adhered
t o takes place both formally through reports submitted and informally.
Both the village where the Library is located and the municipality are
so small that rumors of possible problems spread. In this case, the other
librarians in the municipality also act as "watchdogs".
When the Librarian won the contract, her Library was removed
from the area of responsibility of the main librarian. This is a conse-
quence of the result unit model that was implemented. However, this is
simpler in principle than in practice. A number of problems involving
lines of demarcation and questions that had not been anticipated arose.
Would the Librarian, as had been the case previously, get access to the
book collections at the other libraries in the municipality, and, if so, on
what conditions? Who would pay for the transportation of books
when borrowers at the Library wanted books that had t o be brought
from one of the other libraries in the municipality? Would the Library
be included among the municipal libraries listed in the brochure of the
main library, and, if so, who would pay for this?
Certain practical problems followed directly and indisputably with
the new regime. Insurance had t o be acquired, alarms installed, book-
keeping arranged, etc. The Librarian also began looking for new part-
ners t o collaborate with in order to increase the volume of purchases
and trying t o attract new readers and visitors to the Library. The latter
was done in a number of ways - by cooperating with schools, daycare
centers, medical centers and the local swimming pool.
Some of the decisions that were taken and measures that were imple-
mented by the Librarian had the aim of decreasing costs. It should be
remembered that among the motives the municipality had for resorting
t o alternative providers were and are economic considerations, i.e.
there was and is a desire t o keep costs down. In order to bring about
lower offers in tenders and lower costs, modifications of existing activ-
ities are generally required. The Librarian tries to reduce costs by review-
ing each specific expenditure. She is on the lookout for favorable
contracts for everything: for purchases, for transportation, for book-
keeping, for cleaning, etc. She always considers performing duties, like
REGENERATED PROFESSIOKALISM
Shifts in theory
The Librarian was not the only one to find herself working under new
conditions. As has probably become apparent, this was the case for all
of the other librarians as well. They were not only affected by demands
for decreased costs but also by demands for re-orienting their thinking
regarding what the relevant organizational unit is for them. Each lib-
rary became either its own result unit or became part of a result-unit
that was otherwise a school, daycare center, or recreational center of
some kind. Librarians were now to orient themselves toward the result-
units. This was completely foreign to most of the librarians. In their
professional way, they saw their responsibility as being broader and
oriented toward the reading public in general.
The new organizational model demanded new ways of thinking
challenging prevailing cultures and replacing them with a uniform one
characterized by economic criteria. The demands for change involved
ELISABETH SUNDIN
I
importance of "libraries t o the )eoplen, their partic~pationis perma-
nent, but they put different em] asis on the structurd. The majority of
the librarians emphasize the im ~ r t a n c eof the structure being perma-
nent, meaning publicly owned, vhile the Librarian is positive t o new
and temporary solutions as Ion as it is in line with Her librarian iden-
tity. These differences are label I by Soderlund pernianent organizing
versus project organizing and he rgues for different cohtrol forms conn-
ected t o each typology. To the :rmanent organizingttype he connects
bureaucratic andlor clan contr and to the Project organizing a pro-
fessional and/or clan control. :I this seems to be in line with what
happened in the community st1 ied.
The observations and discu
entrepreneurial theories and ho
d
ions above should e integrated into
,fully contribute to niaking them more
true to the reality of today. Thc .ibrarianYsentreprenkurial action is t o
use the project form in line wit her visions of a good library. She can
do that as she is "protected" b her (semi)-professional belonging and
values. She is accepted by man; ~f her colleages as sHe is a good libra-
rian. The resistance towards ot :r providers of library-services is com-
pact. Classical entrepreneurial 1 :ories emanate from a time and a con-
text prior to the development c the welfare state. Tfie variant of these
theories that categorize reason for going into business on one's own
into push reasons and pull reasl 1s are useful in relation t o the case pre-
sented but in an unexpected w. . The Librarian's dedision t o submit a
tender for her Library can be : :n as her being forced by an impossi-
ble situation - not due t o her c liking her work. O n the contrary, she
made the decision hecause she 1 :d her work so mucd. It was the desire
to be able t o work as before t i r drew her away from the municipali-
ty. For others the desire t o rerr In within the p b l i c sector is decisive.
The tough economic conditio "push" them even harder into the
municipality. Private alternative in whatever way they are defined, are
perceived as a greater threat 1 xn the poor municipal economy and
reorganizations. These librariz s feel, very simply, that is it wrong.
"Privatization is in principle w ng. Certain things sAould be operated
on a non-profit basis". With ti t attitude there is ncr other alternative
than remaining within the pub : sphere and "fightidg" for one's own
activity there. This opinion is ared by some politiLians deep within
the camp of advocates of prival ation. They cannot imagine "pure pri-
vatization" either. As expressec ~y one of the non-stkialist politicians:
"I would still think twice. or t ,ee times, about what consequences it
could have... there are differences in principle between different activi-
ties". Many also openly express a fear that the initiative taken by the
Librarian will begin a process from which there is no turning back.
"What will happen if people start submitting tenders for each other's
libraries?"
The Librarian who went into business on her own illustrates the diff-
iculties that are discussed in the literature attempting to describe and
analyze what the transformation of the public sector really entails. It
seems as if Barbara Czarniawska's (1992)conclusions about the para-
doxes of the public sector, which were mentioned above, are just as
applicable now as they were ten years ago when they were written.
Decentralization, for example, which was effectuated through a result
unit model, was implemented through centralization. This also means
that small organizations, such as the Library, and small organizational
units, such as the other branches of the library, are subordinated to lar-
ger ones, such as the main library. An increased number of small alter-
native providers is not a clear sign that the position of small organiza-
tions has been strengthened. It can just as well mean that the large
organizations are splitting potential opposition into many smaller
organizations.
Hereafter
The new principles for management and procurement in the municipa-
lity affected all of the librarians. They were all put in a more constrai-
ned economic situation. However, they dealt with this in different ways
- the Librarian by using the project form as a construction of an ent-
repreneurial possibility, others by resisting in both the participation
and structure dimensions. What are the implications for the future of
these strategies - mainly of the strategy of the Librarian?
The Librarian who went into business on her own had worked
within her occupation for many years when she submitted a tender for
her Library. She knew what libraries were and she knew what she wan-
ted to do with her Library. What she wants corresponds to what her
colleagues want - they are all part of the same tradition. There is no
difference to be found in that respect. The major distinction involves
who should be in charge of libraries, i.e. form rather than content. The
majority feel that libraries are and should be synonymous with publicly
R E G E N E R A T E D PROFLSSIONALISLV
run activity. The Librarian feels it is the activity that is of central impor-
tance - not the form in which it is operated. Her professional partici-
pation and commitment is permanent, the adequate structure can be
ado p ted to the circumstances. She does see certain advantages of being
on hcr own -however, these involve a feeling, not the work or the atti-
tude toward borrowers. For many librarians the public employer is a
part of the nature of the occupation and, consequently, of one's own
identity. For these people, public ownership, which is strongly associa-
ted with profit or rather the lack of profit and economic incentives, is
of central importance. It is a part of the occupational identity. Interes-
tingly enough, it cannot be said that the union as an organization had
a negative view of the initiative taken by the Librarian. She was herself
active in the union. It was rather the occupational group with referen-
ce to professional criteria that was most vocal.
Librarians unquestionably display professional features - they borrow
their frames of reference from each other and, thereby, obtain their
legitimacy from each other. O n the central question in this article, that
of under whose auspices the activity should be run, the Librarian is
relatively alone in her view. With the concepts introduced above; she is
the only one to disconnect participation from structure. Or rather, she
is alone in accepting the practical consequences of her view - others
who, like her, emphasize the unique aspects of libraries are unable to
ignore the significance of public ownership - to them structure is as
important as participation. The opponents to the Librarian sometimes
argue by decreasing the differences: "What is really private with the
Librarian's library?", asks one of the other head librarians rhetorically.
All libraries, even the one run by the Librarian, receive all of their reve-
nue directly from the taxpayers. The content of the activity is the same
and, thus, the costs are of a very similar nature. To classify the Libra-
rian's activity as private and other municipal libraries as public is, in
many ways, difficult to justify. Despite that the majority of librarians
fear the consequences of the Librarian's initiative. Her small initiative
has implications of big institutional changes.
The Librarian and her colleagues are examples of a development
that we, probably, are going to see more of. The new management and
control systems that are applied by large organizations are going to
split the semi-professions and perhaps even the professions. The iden-
tities of groups and individuals are being shaken. There are many signs
that the librarians, as a group, can be the major losers in the negotia-
tions to follow in the tracks of the new municipal regulations. The new
organizational models and management systems are a threat to the lib-
rarians. We have seen, for example, that librarians are being replaced
by recreational directors, that the specification of conditions does not
contain requirements that there be trained librarians, etc. This has been
possible because librarians have not achieved the position of a profess-
ion and, thus, do not have the legitimacy to dictate conditions for
procurement. Neither have they managed to describe their competence
in concrete and convincing terms to decision-makers. As a result, they
are not seen as indispensable. By presenting her project the Librarian
handles a tool of change for institutional change of great significance.
By means of the Librarian who went into business on her own, a pic-
ture was presented of how an individual acts in order to deal with
changes that "befall" her as a result of decisions taken by a large organ-
ization. We also saw examples of other librarians acting in a comple-
tely different way. The differences are due to the possibility of making
several interpretations of the historical legacy and the professional
identity that developed as a result. The case is also a clear example of
how political decisions andlor decisions taken by large organizations
have direct consequences for the work and lives of individual people as
well as for the identity and negotiating strength of groups. Those
changes that took place also entail that established ways of viewing
societal phenomena may need to be revised and, consequently, even
social science theories. That the actions of large organizations influen-
ce the lives of people is nothing new. One of the circumstances that is
new this time, and that the libraries and the Librarian are a part of, is
that the public sector is contracting after a relatively long period of
expansion. Another thing that is new is that there is an attempt to
transfer the logic of one sector to another on the basis of political deci-
sions. These seemingly abstract changes influence the everyday lives of
individual people - in this case the everyday lives of the members of the
occupation more than the everyday lives of the citizens, at least so far.
ementarities in
TOMAS M U L L E R N
But my message today is that the real revolution is not about tech-
nology. It is not about a new model of computing based on the
Internet. We are witnessing nothing less than the rise of a new econ-
omy - a digital economy - and a new global medium that will be the
single most important driver of business, economic and social
change in the coming century.
The technology (Internet) is new but the rhetorical figure remains basi-
cally the same: new technology creates a need for change. In this chap-
ter further consideration is given to the quest for organizing in compa-
nies to adapt to continuously changing conditions. The informed reader
should be well acquainted with the more fanciful labels currently in
vogue in the search for the holy grail of organizing, be it organizatio-
nal forms like networks (Nohria & Ghoshal, r997), cells (Miles &
Snow, 1996), and virtual corporations (Davidow & Malone, ~ q g z )or ,
management concepts like regenerating strategy (Hamel & Prahalad,
1994) and knowledge management (Nonaka & Takeuchi, 1995). But
what is true and what is false in this ongoing discussion on management
M O V I N G B E Y O N D T H E RHETORIC OF THE POST-MODERN C O R P O R A T I O N
and organizing? And how do we move beyond the totalizing and deter-
ministic rhetoric of Ghoshal & Bartlett in the quotation above?
This chapter draws on recent research into new and innovative forms
of organizing and develops a frame of reference that is applied to two
cases. The first case is a Swedish high-tech firm in the defense industry
- Saab Training Systems - renowned for its consistent implementation
of a team-based structure and a strong focus on HR-issues (including an
elaborate incentive system and a strong focus on learning). The second
case is the network giant - Cisco systems - with a special focus on the
implementation of the global network model in Sweden.
Boundary crossing
Several authors suggest that the multidivisional form is being superse-
ded by the so-called network form (Nohria & Ghoshal, 1997). A key
characteristic of the suggestion is the tendency to move beyond the
boundaries of the single corporation and develop more elaborate and
complex value constellations. The often discussed contemporary phe-
nomena of external networks, alliances, virtual and imaginary organi-
zations, etc., are all elements in a process of changing/dissolving the
single, unified organization as the central locus of interest. We see a
M O V I N G B r , Y O N D T H E KHE'l'ORIC OF THE POST-AMODERN C O R P O R A T I O N
Temporary forms
A central issue in the literature on innovative forms of organizing is the
need for building more flexible structures. Driven by the rapid devel-
opment of information technology, and not least the Internet, both the
need for and possibilities to develop more flexible structures and fast-
moving forms of organizing have increased. A common assumption is
that flexibility is enhanced by adopting more temporary ways of organ-
izing. Ekstedt et al. ( ~ q y y )Jessen
, (1yy6), Hamilton (1yy7), among
others, hold that the new architecture of the modern corporation is t o
an increasing degree an architecture of temporary organizing. This can
take the form of formal projects, and by paying attention t o process,
emphasizing horizontal and vertical networks transcending the single
organization, or focusing on the knowledge creating and utilizing
efforts in corporations. The literature on new and innovative forms of
organizing, and on human resource management, often stresses the use
of decentralized, group-based structures. Concepts like team-based
structures, project forms of organizing, and organizational learning are
often used to describe the features of new forms of organizing.
A marked trend in the literature o n new and innovative forms of
organizing is the focus on processes and dynamic aspects. From an
HRM-perspective, Mirvis (1997) holds that leading companies focus
more on organizing for innovation by involving employees, conducting
training and mentoring programs, using flexible work arrangements
and team-based work redesign. In the field of project management, it
is often maintained that companies organized by projects can be an
important arena for innovation (Andersson & Larsson, 1998) and learn-
ing (Lundin & Soderholm, 1997). The notion of the projectified society,
with an increasing number of companies organized by projects or other
forms of temporary organizations, draws the attention to processes in
companies, how they organize innovation and the on-going business
processes. O r t o quote Hastings (1996):
The resulting organization can be conceived of as a constantly chang-
ing kaleidoscope of teams, forming, delivering work and dissolving as
required.
The changes towards more networked and temporary forms also has
implications on how people in organizations are dealt with. It is often
argued that values change and that younger generations appraise
notions like freedom, work and authority/responsibility differently
than older generations. Together with structural changes in many
industries with a move towards more knowledge-intensive production
systems and products, the changes in values pose new challenges for
recruiting, training and motivating employees. Pfeffer (1998) says that
M O V I N G DT.YOhlD T H E RHETORIC O F THE POST-MODERN C O R P O R A T I O N
1999).
The Internet and Intranets grew in importance and so did Cisco.
Cisco's almost exclusive knowledge within this area at such an early
stage made it the leader of networking and by 1998 it became the num-
ber one supplier of routers and switches. Today, the company's product
line consists of a wide range of networking solutions and their core
products -routers and LAN and WAN switches. Cisco's wide product
range enables it to provide their customers with end-to-end network
solutions (Saloner & Spence, 2002; Tempest, 1999).
Technological advancements, which cannot be internally developed
within six months, are acquired by companies with the necessary
' The Cisco case has been prepared by Johanna Fnglert and Mikaela Graf.
214
MOVING BEYOND THE RHETORIC O F THE POST-MODERN CORPORATION
knowledge (Byrne & Elgin, 2002). In the past eight years, Cisco has
acquired 73 companies, using its unique acquisition growth strategy. In
order to extract knowledge from the acquired companies, Cisco needed
a successful human resource management and an effective integration
of new companies without losing intellectual capital (O'Reilly & Pfeffer,
2000).
Cisco has adapted its products and technology to its future anticipa-
tion of how the organization should be run in the future. John Cham-
bers, CEO of Cisco, quoted in Morgridge & Heskett (zooo), said that
companies not only will connect themselves to a "New World
Network", but they will also be faced by changing assumptions conn-
ected to competition and the development of organizations. These
assumptions are: organizations will be oriented around networks, as
opposed to hierarchies, capabilities will be focused on technological
advantage, emphasis will lay on the interdependence of partners, and
organizations will be built on change rather than on stability (Ibid).
All employees within the organization are part of Cisco's networked
environment, which gives them a wide range of support systems. The
most important forms of employee support are the Internet-provided
learning programs. Cisco has an E-Learning Initiative site where the
employees can complete various courses and to satisfy the need for
Internet-qualified people, Cisco has also founded a network of acade-
mies that trains people in subjects such as network basics and trouble-
shooting.
Cisco's employees are connected by the "Cisco Employee Connec-
tion" (CEC), which is an Intranet designed to provide information and
services. According to Cisco, CEC's benefits are manifold, including
instant global communications, enhanced productivity, consistent busi-
ness systems, lower business costs, scalability, and facilitation of
employee acculturation (www.cisco.com, 2002; Rankin & Parent,
1997). "C~SCO Connection Online" (CCO) is a combination of Internet
and Intranet applications accessible to customers, partners, sharehol-
ders, prospects, and employees. The CCO gives these parties informa-
tion and services, such as software upgrades, technical assistance, order
status, seminar registration, documentation and training.
The CEC and the CCO are the contents of what Cisco calls its glo-
bal networked business model. This model facilitates information shar-
ing, the cultivation of relationships between various parties, increases
speed and minimizes costs, which are needed to succeed in a global
environment (www.cisco.com, 2002). In order to describe the Global
Network model of Cisco, a more detailed analysis of Cisco Sweden is
made below. The empirical material is based on interviews with the
CEO, the Information and PR manager and the H R manager at Cisco
Sweden. The number of employees at Cisco Sweden is approximately
zoo and they are divided into various departments, such as administ-
ration, sales, marketing and R&D. The R&D department is one of four
in Europe. The others are situated in Italy, Scotland, and Israel.
Cisco Sweden is connected to Cisco by the global networked busi-
ness model, which provides for a close co-operation between all parts
of Cisco. For example, the marketing department in Sweden consists of
only four people but to help them they have the other marketing
departments in Scandinavia, Europe, and the United States. The
network is used in all parts of the organization and it is the glue that
holds the organization together. Since Cisco is a vast organization with
entities in more than 67 countries, the network is an important tool to
ensure close co-operation (www.cisco.com, 2002). According to the
H R manager, the advantage of working with a network such as Cisco's
is 24-hour, seven-day access to all information. This can also be consi-
dered a disadvantage since it entails one has always to be available. It
is no longer important to be in the office to be reachable. There are no
office boundaries and one can be reached everywhere, e.g. at home,
abroad, or, of course, in the office.
All employees get an access card that works as a key to all of Cisco's
offices across the world. It is based on the concept that Cisco is their
employer and not the individual entities. It is possible for an employee
in Sweden to be reached at an office in England, if he or she happens
to be there. A Cisco employee can log on to any telephone or compu-
ter and can be as easily reached as if at hislher home office.
Innovative technology is one of the most important interests of
Cisco. To maintain the technology, knowledge-sharing and cooperation
are of paramount importance. This is, to a large extent, done cross-bor-
der and, therefore, necessitates the use of the global networked busi-
ness model. Since Cisco Sweden is one of four R&D departments in
Europe, it is part of a matrix from which knowledge is chosen depen-
ding on what is needed for the different projects. Cisco Sweden is curr-
ently working on a project together with entities in Italy, India, the UK
and the United States. This requires cross-cultural boundaries to over-
come and maintain a close contact within the project. During the course
M O V I N G B E Y O N D THE KHE1'ORIC O F THE POST-MODERN CORPORATION
of the project there are various milestones that are set and each entity
develops different parts that must be completed at the set date. In order
for all parts to be compatible, it is important that information is shared
and communication is open.
Projects are initiated by requests from customers. When a customer
approaches Cisco with a problem, it is most likely that customers in,
for example, Germany and Italy will have it as well. The market is the
same regardless of the country. The problem generates an idea that the
local marketing department communicates to Cisco in San Jos6 where
decisions are taken whether to start up a project or not, and if so which
entities have the competence and resources needed to develop it. Eve-
rything in Cisco is customer-oriented and customer success is the main
goal. To ensure innovation and boost creativity, Cisco has a two-per-
son unit that works with compensation and benefits. Cisco has
something called CAP awards, which commends innovative employees.
Externally, Cisco also has adopted the concept of open communica-
tion. Their customers, partners and suppliers are all part of their eco-
system. The partners are connected to the global networked business
model and the suppliers are integrated into the supply chain manage-
ment from design to production, which results in a faster and more
efficient production of Cisco products.
Concluding reflections
The two cases described above, though very different, illustrate a num-
ber of points connected to the frame of reference presented earlier. In
the area of boundary-crossing, the two companies show some interes-
ting features, with the hard-working Cisco consistently trying to
expand the network of external contacts. The Cisco Ecosystem, which
is a concept widely spread in the company, describes the elaborate
network of relations in three layers. The boundary-crossing elements in
Cisco are balanced by a very strong focus on the technology, and with
a very strong core of the Ecosystem. In the interviews conducted in
Cisco Sweden, the respondents verified that the Headquarters in the
US work very hard at integrating the different parts of the company.
Another aspect of boundary-crossing in Cisco is the open technological
standard and the ambition that the Cisco products should work with
products from other suppliers. It is not a closed system, one of the
respondents said.
Cisco is clearly a living example of an internal network organization,
with a strong emphasis on IT-tools for running the network. The Global
Networked Business Model relies on the intranet CEC and the so-
called CCO where customers, partners, and many others can gain
access and receive information and services. The knowledge sharing,
experience, and open communication are important prerequisites for
the continuous innovation needed to survive in a highly competitive
industry.
M O V I N G B E Y O N D 'I HE RHETORIC OF THE POST-MODERN C O R P O R A T I O N
ing the capacity to deliver on time, but a major challenge is to keep the
same tempo in innovation. Compared to Saab, Cisco has been more
successful in integrating production and innovation. A comparison
between the two companies shows that Cisco has succeeded in bringing
together and integrating a vast number of resources all over the globe,
buying companies and integrating partners and suppliers in the net-
work. The ability to cross boundaries and integrate different resources
in a network model seems to be a prerequisite for building an innov-
ative and flexible organization.
Saab Training Systems and Cisco put a lot of emphasis on human
resource management, and it is impossible to summarize all aspects of
this broad area within the scope of this chapter. However, it is worth
highlighting a number of the more prominent features. In the Saab case
knowledge management and motivation are two very important pillars
of the HR-philosophy of the company. The former CEO developed a
very elaborate learning philosophy in the early ~ g g o s with
, a strong
emphasis on the individual and group-level learning. The basis for the
learning philosophy was the idea of experiential learning, where expe-
riments and risk-taking were encouraged. The strong learning focus
was also strengthened by a complex incentive system based on indivi-
dual, group and company level performance.
In the Cisco case the integration of new employees and the integra-
tion of acquired companies is a high priority within the field of HRM.
The respondents in the interviews stress the need to have a 'cultural fit'
between the acquired company and Cisco. Though we have not been
able to verify the results of this cultural integration, the company has
high ambitions, and the strategies are thoroughly implemented. Lear-
ning is also a high priority in Cisco and one example of the different
tools used for that is the so-called E-learning Initiative Site where the
employees can take different courses within the Cisco Academy.
The highly developed thinking on human resource management in
both companies reflects an important insight concerning innovative
forms of organizing. More complex and dynamic forms of organizing,
where boundary-crossing and temporary aspects have been highligh-
ted, are usually found in highly competitive and knowledge-intensive
industries where people do matter. Both cases confirm the basic premi-
se of O'Reilly I11 & Pfeffer (2000)that companies need to create cul-
tures and systems in which people can actually use their talents for the
benefit of the company.
LMOVING BEYOND THE RHETORIC O F THE POST-MODERN CORPORATION
More hypothetically the two cases illustrate two stylized forms of organ-
izing - one with an internal focus on building a network (Saab Training
Systems) and one with an external focus (Cisco). As described above,
the two cases differ in how they manage to draw on the complement-
arities between boundary-crossing and temporary forms of organizing.
The more open approach of Cisco creates possibilities and challenges.
We have seen that Cisco, compared to Saab, has managed to keep a
more explorative approach to learning, partly by adding to the internal
capabilities by buying companies. The major challenges are to keep
control over this complex network and manage to communicate between
its different parts. When it comes to coordination, Cisco relies a lot on
cultural control with the CEO being very active in creating a sense of
community in the company. This is further underpinned by the extend-
ed electronic network. The approach of Cisco is clearly more risky but
can also produce impressive results with tremendous growth.
The cases of Saab Training Systems and Cisco illustrates a number
of important elements in new and innovative forms of organizing. The
two areas of boundary-crossing and temporary forms were used to cap-
ture some aspects of the emerging innovative practices. The challenge
of organizing is, to a growing degree, a matter of organizing for flexi-
bility under conditions of complexity and change, and both cases show
that companies are rapidly adopting a number of network characteris-
tics to achieve that.
The Cisco concept of an Ecosystem is a good metaphor for the emer-
ging models of organizing. It illustrates the need to map the complexity
M O V I N G BEYOND THE RHE'I'OKIC O F THE POST-MODERN CORPORATION
had ignored until the 1970s. Namely, how science actually is done -
not how it normatively is supposed to be carried out, and, the way
technological artifacts are actually designed and deployed - not how
textbooks in engineering instruct us (Monteiro, 2000). ANT is built on
the assumption that society (and organizations') is a completely inter-
woven socio-technical web that consists of a heterogeneous network of
actors, inscriptions, work practices, and institutional and organizatio-
nal arrangements (Hanseth & Monteiro, 1997:185). Furthermore,
ANT does not make an a priori distinction between the technical and
the social, while the theory was developed to analyze situations where
the separation of these elements was difficult (Callon, 1999). Thus, it
can be claimed that a temporary organization is an actor network
mobilized in order to solve a certain task. Moreover, the network con-
tains actors with different roles and relations, work practices, and insti-
tutional and organizational arrangements.
Given this background the chapter has two aims. First, Lundin and
Soderholm's (1995) theory of the temporary organization will be
discussed from an actor network perspective. Second, by that discuss-
ion, a basis will be formed to discuss how transition of efforts of the
temporary organization can be regarded, in order to bridge the gap
between tenlporality and permanency.
The further outline of the chapter is organized as follows. First, there
is a brief overview of the theory of the temporary organization. This is
followed by an introduction of some central ideas and concepts in ANT
that can be applied to temporary organizations. Next, there is a discuss-
ion of the theory of the temporary organizations and ANT. Finally,
there is a discussion about how transition of efforts made in the tem-
porary organizations can be considered by using concepts from ANT.
The definition of task is the raison d'dtre for the temporary organiza-
tion, and it is dependent on a limited number of defined tasks. The task
can be repetitive or a one time event. When the task is repetitive, actors
know what should be done and who should do it; however, when the
task is unique actors do not know immediately how to act (op cit:440).
When the team in temporary organizations is considered, the rela-
tionship between individuals and the team (participation in the team is
time limited) may imply that conflicting interests are accepted. Mem-
bership in the team depends upon common interest in a specific task,
force, or coincident.
The fourth basic concept is transition, which is described as follows
(op cit:442):
The four phases in the life cycle of a temporary organization are re-
named by Lundin and Soderholm to focus on the activities of each
phase. During action-based entrepreneurialism, the first phase, there is
an obvious need for an entrepreneur to initiate the temporary organiza-
tion. However, the skills of the entrepreneur are different depending on
whether there is a repetitive or unique task that needs to be performed.
The second step, fragmentation for commitment building, has the
following purposes (op cit:446f):
H E N R l K C.J. 1.INDEROTH
"it delimits the scope, simplifies the task, and provides a time hori-
zon to facilitate the handling of the task. O n the other hand, it works
as a mechanism for securing commitment among potential members
of the temporary organization".
In this phase, the task is spelled out and delimited, so success in some
kind of definition will be achieved.
The third step, planned isolation, is the phase where predetermined
actions, inscribed in plans, are supposed to be carried out in order to
complete the task. In this phase, it is also important to minimize distur-
bance, which can threaten the actions in the temporary organization.
The final step in the life cycle is the institutionalized termination, where
one of the essential components is bridging. Experiences gained during
the lifetime of the organization have t o be transferred to other tem-
porary or permanent settings. The suggested key to this transfer is indi-
vidual learning that would bridge the knowledge from the temporary
organization into the new settings (op cit: 449f).
The model outlined has brought valuable insights to the organizing of
temporary organizations by focusing on action. The question remains,
however, about how the transfer of results from the temporary organi-
zation can be effectively incorporated into a more permanent setting.
characteristics concerning the task that would he solved. So, how can
the process of mobilizing the actor network be considered? By using the
language of ANT, the process can be viewed as a process of translation
where the interest of the different actors is translated into an interest
that is common for all of them. Translation can be understood as foll-
ows (Callon & Latour, 1981279):
PMI and IPMA have had a powerful influence on how action would be
carried out in a temporary organization by defining how projects are
organized and how roles of the actors are defined. These organizations'
views on how to organize temporary organizations are further mani-
fested through conferences about project management, literature
published on the topic, and certification of project managers. Taken
together these manifests of heterogeneous animate and inanimate ele-
ments are than an expression for a powerful actor network.
theless, how can the project process for "fuzzy projects" be regarded if
the concept of black boxes is used in order to illustrate the transition
of efforts made in the T O into a more permanent setting?
Linderoth (2000) has implicitly argued that a project process where
open, or general-purpose technologies are introduced into an organi-
zation in order t o trigger change, cannot be discussed in general becau-
se it is not known how technology use will develop. Instead, there is a
need to view the process as a development of different fields of appli-
cation. This perspective originates from Gutek et al. (1984:234) who
claim that advanced IT consists of "a set of loosely bounded capabili-
ties that can be implemented in different ways". However, the diffe-
rence between Linderoth's and Gutek et al.'s perspective is that a
discussion about fields of application is more precise since it is known
what would be implemented, which is a result of the learning process
during the interaction between the technology and the user. Nevertheless,
the account for an ongoing learning process is not clear-cut. A study of
advanced manufacturing technology shows that there are windows of
opportunities for learning and technology adaptation (Tyre 81 Orli-
kowski, 1994). However, it is also claimed that usage of new IT-applica-
tions triggers changes in small invisible steps and after a while can lead
to a total transformation of work routines (Orliokowski, ~ 9 9 6 ) .
Thus, how can this discussion about the development of fields of
application be connected t o the discussion about black boxes as a
means for transition of TO'S efforts? As stated earlier, a black box does
not have to be sealed if a development of technology usage proceeds.
But against the background of the development of field of application
it may be more appropriate t o discuss this in terms of several black
boxes instead of one black box. The routinised use of a field of appli-
cation can be considered as the sealing of one small black box, which
implies that if a renewal effort is to be successful a number of black
boxes are t o be transferred and merged together and develop into a lar-
ger one.
The proposed project process of fuzzy projects gives new insights
into the process compared to models that consider the process as more
or less a straightforward process. Models proposing a straightforward
project process might be correct for less open technologies or when
tasks are clearly defined. However, in cases of open technologies, or
unique tasks, a process of learning has t o occur if fields of application
are to be developed and used.
H E N K I K C.J. L I N D E R O T H
Concluding remarks
The discussion in this chapter about actor network theory and the the-
ory of the temporary organization has showed that ANT can be used
to enhance the understanding of temporary organizations. The main
contribution of ANT to the theory of the temporary organization has
been to broaden the view of the transition concept by using the concept
of black boxes and fuzzy projects. Nevertheless, in this chapter a first
attempt has been made to combine ANT and the theory of the tem-
porary organization. Nevertheless, there is much room for studies to
combine ANT and the theory of the temporary organization. Further-
more, it has only been discussed how ANT can contribute to the theo-
ry of the temporary organization, but future research should examine
how the theory of the temporary organization can contribute to ANT.
Further studies in this area could be the ever-present issue of how to
preserve learning and knowledge after the termination of a project.
This topic could contribute to both the understanding of the tempora-
ry organization and to ANT with respect to the field of organizational
learning.
The attractiveness of projects:
Controllability and adventure
The attractiveness of projects, claims Sahlin (1996), lies in their associ-
ation with both controllability and unpredictability. They are associa-
ted with something planned, rational and ordered, and at the same time
with flexibility, change and adventure. This double identity make pro-
jects attractive, but it may also present a dilemma t o project-managers.
This dilemma is more or less present in all organizing processes, where
one has t o strike a balance between freedom and control, but it takes
on a particular character when it comes to projects, because of their
delimited and temporal character. Of course, some projects are more
controllable while others are closer t o adventure, but it is common for
projects to give rise t o expectations of both.
Both aspects - controllability and unpredictability - follow from the
possibility of delimiting a project. One way of controlling a complex
situation is t o divide it into smaller pieces, or projects, each of which
appears controllable. By organizing an operation as a series of projects
centered on individual tasks of limited time spans and involving speci-
fic people with specifically allocated resources, control appears achie-
vable. So, creating a project through delimiting a specific time, task,
KERSTIN SAHLlN-ANDERSSON
jects tend to become too isolated from their contexts, which may result
in unrealistic, inappropriate, or even disastrous results (Hall, 1980;
Sahlin-Andersson, 1986). Rigid boundaries may result in a project that
is so isolated from its context that project members develop unrealistic
expectations and plans that they then fail to realize (note the parallel to
"group think" as analyzed by Janis, 1972). Hermetically sealed boun-
daries can also prevent learning from being transferred from one pro-
ject to another. This may cause problems, especially in project-based
companies where there is a concern that experience gained in one pro-
ject should be applied in others in the future. Projects should thus not
be too isolated or delimited from each other. Project entrepreneurs and
project managers' have to strike a balance between delimiting and conn-
ecting the task, the time and the institutions of the project.
How then are such boundaries to be established and of what do they
consist? Just as with organizational boundaries (Scott 1998, chapter 8;
Brunsson and Sahlin-Andersson, zooo), project boundaries d o not
appear automaticall y as the project is formed, and are not set in stone
once and for all. Instead, they are socially formed, and boundaries have
to be continuously defined, sustained, or changed. This is why I suggest
that boundary setting, revision, and maintenance are such important
aspects that they deserve to be defined and analyzed as distinct aspects
of project management. In this chapter I will present a framework for
analyzing such project boundary work, and my discussion will point to
the considerations and dilemmas that project entrepreneurs face as they
pursue such boundary work.
I have borrowed the tern1 "boundary work" from Gieryn (1999). He
analyzed "how boundaries of science are episodically established,
sustained, enlarged, policed, breached, and sometimes erased in defen-
se, pursuit, or denial of epistemic authority" (p. xi). The boundary
work of science is primarily concerned with legitimacy and jurisdiction,
as it aims at distinguishing what is scientific from that which is not.
Seen in this light, the boundary work of science may seem to have litt-
le to do with that of project management. But just as the boundary
work of science is a discursive endeavor which aims to draw a rhetori-
cal boundary distinguishing outsiders from insiders, and where the acti-
When writing abour project entrepreneurs rather than only project managers, I would like to
emphasize that project boundar y work is not only, or even mainly pursued by appointed projcct
managers. As the examples below show, such boundary work is a more dispersed task encom-
passing a broad group of proponents, stakeholders and managers ot projects.
KEKS'I'IN S A H I . I N - A N D E R S S O N
vities, resources, norms, and regulations applying inside the boundary are
distinguished from those outside, so is the boundary work of project
management rhetorically drawn. Even though the boundary work that
Gieryn analyzes comes from a very different field and was done partly for
different purposes, his work suggests a way to specify both what boun-
daries are and how they are set. This motivates a brief account below of
boundary work as the concept has been defined and used by Gieryn.
The rest of the chapter is structured as follows. First, the concept of
boundary work is elaborated on and applied to projects. Second, three
types of boundaries - temporal, task, and institutional - are defined
and exemplified. Examples typifying boundary work are taken from a
series of case studies of large projects. These cases concern three major
projects that have been pursued by Swedish cities and counties: a sports
arena (Sahlin-Andersson, 1989); a research park (Sahlin-Andersson
and Soderholm, 1987; Sahlin-Andersson, 1990);and a theater (Lundin,
1980; Sahlin-Andersson, 1986). Using these examples, I will illustrate
how project entrepreneurs pursue boundary work, what dilemmas they
face as they seek to strike a balance between demarcation from and
connection with the context, and how this boundary work is related to
project entrepreneurs' seeking to attain controllability and/or "adven-
ture." The projects were all defined and perceived as major, even extra-
ordinary projects, and the studies of them partly focused on the mea-
ning of the definition of the projects as "extraordinary." I will expand
upon this central aspect of boundary work: the identification of the
project as it is defined and presented throughout the process.
Boundary work
Gieryn (1999) defined boundary work as "the discursive attribution of
selected qualities to scientists, scientific methods, and scientific claims
for the purpose of drawing theoretical boundaries between science and
some less authoritative residual non-science" (p. 5 ) . A cultural space in
which scientists can act and interact is delineated by the way in which
science is presented and represented. Boundaries define insiders and
outsiders, and separate scientific activities from other activities. These
boundaries are constantly being drawn and redrawn. And the bounda-
ries differ depending on who draws the boundaries, and against whom
and what. Hence, boundary work is an ongoing interpretive activity.
PROJECT MANAGEMENT A S B O U N D A R Y W O R K
projects, but are even more important: the very definition of a project,
in general as well as in particular contexts, is a temporal one. Projects
have been analyzed as temporary organizations (L,undin and Soder-
holm, rqqs), and the starting and ending time is what demarks a project.
Many projects are initiated in response to or in anticipation of major
events -just think of the many projects that were started in connection
to the millennium change. Major buildings are planned to celebrate
anniversaries of cities or companies, or to support Olympic games,
world championships, or other major public events. Such events moti-
vate projects and supply both a starting date and a deadline for the pro-
ject. They also tend to define the very meaning of or definition of the
project. Hence, when a project is motivated by or connected to an
event, the project is placed in a certain context and is delimited in cer-
tain ways relative to this context.
A recent, well-known public Swedish project is the construction of
what has become known as the "Stockholm Globe Arena". This pro-
ject provides an interesting example of temporal boundary work. This
arena was opened for the world ice hockey championship in 1989, and
has since been used for sports, entertainment, and other public events.
The arena takes the form of a spherical building with a roof height of
8 5 meters and a diameter of I 10meters. The building of this arena was
the result of a long process, including a project competition arranged
by the city of Stockholm. The project did not comprise just an arena,
but a whole block including a hotel, offices, and a shopping center.
The planning of this arena had, as is true of many major projects, a
long history. For many years the politicians saw it as a drawback that
Stockholm did not have an arena big enough to house the world hockey
championship, large concerts, or other major events. Municipal govern-
ment, however, found it impossible to build a new arena at public
expense. Two circumstances made it possible to start planning the
arena. In the early 1980s another public project was made possible
because a new financial model for financing the project was designed:
private companies were given the opportunity to build commercial
buildings on publicly-owned land in return for reconstructing the pub-
lic railway station. It was thought that a similar financial solution
could facilitate the construction of the sports arena, and project plann-
ing began. Moreover, there was a good chance that Stockholm would
be given the opportunity to host the world ice hockey championship
once they had an arena big enough - possibly in 1987.
PROJECT MAKACEMENT AS BOUNDARY WORK
approval, and once again it turned out that the project had been over-
loaded with tasks and expectations and had become too expensive.
This brief account illustrates a case where boundaries were partly
quite firmly drawn, with a clear demarcation between thc project and
its context. The appointed project group drew boundaries around the
task by referring to its long history, the implication being that such a
long history virtually demanded something "extra." The idea became
ingrained with repetition that UmeH would have no use for a smaller
theater: either a big and unique one or nothing at all. In part these same
boundaries did not detach the project from its context, as additional
tasks were repeatedly incorporated into the project. At the same time it
was clear that temporal boundaries were being redrawn, as the project
was presented anew each time it was restarted after rejection by the
municipal council. Temporal boundaries relative to the history of the
project were partly drawn. However, there were no temporal bounda-
ries for the completion of the project; it was not connected to any spe-
cific event and did not have to meet a fixed deadline.
What finally led to the building of a new theatre in Umed was the
revised boundary work of the project entrepreneurs. Instead of either
over-loading the project or proposing temporary solutions, the project
was divided in two. Temporary production premises for the opera com-
pany were built separately, and in this way the theatrelcommunity cen-
ter project was scaled down2. The location of the new theatre had been
established in the 1970s. Now, since opera production facilities were
eliminated from the planned building (the opera would still use the new
theater for performances), there would be space for a library - another
long planned-for establishment. However, the library was organized
and treated as a separate project, and had already been approved by
the time revised plans for the scaled-down theatrelcommunity center
project were finally being approved by the city council in the early
19sos.
As the task of the theatre project was redefined, the contextual rela-
tions of the project changed. It can work the other way too: task boun-
daries may be formed as the context of the project is defined and rede-
fined. Observations from a study of the establishment of a regional
This, however, also meant rhat the project was not completely removed from the local govern-
ment agenda. In the year zooo the building began on new premises for the opera. The new pre-
mises invcluded an opera theater and a concert hall.
250
PROJECT MANAGEMENT AS BOUNDARY W O R K
' The research park was built on county-owncd land, and research centers were cstahlished that
were closely connected with the hospital and the dental care unlts run under county authority.
Thc county had no authority over the national railway system, hut the county was the respon-
sible authority for regional trains.
KERSTIN SAHL IN -ANDERSSON
This calls for institutional boundary work, and the following section
describes how such work can proceed. Again, observations from the
Stockholm Globe Arena project serve as my main examples, as the for-
ming and managing of this project incorporated active institutional
boundary work. Few recent Swedish projects have attracted as much
public attention as the Stockholm Globe Arena project. Above all, it
seems that the big, spectacular, and extraordinary in both the form and
development of the project captured public imagination. By the time of
its completion, the project was claimed to mark a new means of city
planning. But when planning started, the project was not generally
regarded as being of any vital strategic value. "Most of the politicians
and managers in the city just saw it as building one more sports arena,"
said one of the planners. Thus the planning was assigned to rather low
levels in the city administration. The planners working on the project
were afraid that the whole matter would be forgotten: they understood
the delegation of the planning work to such low levels to mean that the
project was not of vital importance. In addition, the economic basis of
the project seemed weak. The only way the planners thought the pro-
ject could attract enough attention, so that it would not just be stowed
in a desk drawer, was to make it bigger, both in terms of the extent of
the planned business premises and by formulating the project as
"world class" and extraordinary.
The definition of the project, and the competition directives, display-
ed a somewhat mixed typification. Some of the directives were specific
and detailed: for example, the project location and deadline were fixed,
and the floor area of the proposed offices, shopping center, hotel, and
recreation areas were specified. In other aspects the directives left con-
siderable leeway for interpretation. While certain specifications were
predetermined, the groups competing for the contract were encouraged
to interpret the program freely, and come up with new ideas. At the
same time as the program purported to be "world class," other speci-
fications clearly signaled a low cost profile.
Only a few groups of companies responded to the municipal govern-
ment's invitation, and several of these found it difficult to get their
work started. They found the city council's competition directives, and
hence its project definition, to be unrealistic, inconsistent, and vague in
places. Compounding this was the fact that the project was to be loca-
ted in a less attractive part of the city: construction and real estate com-
panies were rather looking for possibilities to build in the northern part
P R O I E C T MANAGELVENT AS BOUNDARY WORK
of the city where the demand for offices was high. One of the groups
that started working on the project soon disbanded.
During the initial work, however, the project caught the interest of
the architects participating in the group that later disbanded. They
were less bothered by the ambiguity, since many architects are used to
participating in design competitions. In such cases competition is the
important thing - an opportunity for architects to learn and market
themselves - while the actual construction of the buildings is not
always certain. So the architects started working on a design, and
having found an idea which was spectacular and clear enough, eventu-
ally managed to assemble a new group of companies, including real
estate, construction, and other interested parties needed to produce a
workable proposal for the competition. Again, the extraordinary
aspects of the project were being emphasized. This emphasis served as
a way to attract potential collaborators' interest, and it served as a way
t o break with institutionalized practices and relations in the field.
The new group, that was assembled in this way, worked under tight
time constraints, and had little time to work through either the group
dynamics or the model to present t o the city. Moreover, the group devi-
ated in important ways from the competition specifications, as their
alternative was based on the architects' concept of a spherical arena
combined with a much denser commercial area than was proposed by
the city (approximately 150,ooo vs. the specified 75,000 square
meters). As the group developed their alternative they modified the
proposed financial model too. They proposed that, in exchange for
building the arena, the commercial consortium should own rather than
rent the land for the commercial buildings. (In addition, the city was
asked t o pay SEK 80 nlillion of the costs, as had already been allocated
in the city budget). This latter deviation from the program was notab-
le, in that it ran counter to a long-standing city policy that municipal
land was in principle inalienable. Clearly this alternative - and the pre-
sentation of it - emphasized the extraordinary character of the project.
As the competition proceeded, four proposals were under considera-
tion; the city was under considerable pressure to make the decision in
time to meet the 1989 deadline. Even though another alternative follo-
wed the competition directives much more closely, several jury mem-
bers were attracted by the more spectacular but also more ambiguous
proposal with its larger commercial development, different financial
model, and spherical arena. The ambiguity of this proposal, and the
KERSTlN SAHLIN-ANDERSSON
fact that the financial model broke with institutionalized city policies,
were excused by referring to the extraordinary character of the project.
By defining and understanding the proiect as "extraordinary," those
favoring the project emphasized that it was an exception. Hence, even
though this particular case went against earlier policies, it did not mean
that the policy was being questioned or was up for revision.
Second, viewing the project as extraordinary meant it was seen as
unique, implying that no comparable objects or references existed. This
excused the lack of clear plans. The presentation of the project in quite
spectacular, extraordinary and at times unexpected ways also partly
buffered it from criticism. Some plans for the project appeared so diff-
erent, and for this reason were not taken seriously and hence were
neither much supported nor criticized.
The exceptional and multifaceted character of this project became
ingrained as the group of planners emphasized the extraordinary fea-
tures in order to make the project visible and attractive. At the same
time, this definition allowed those joining the project team to develop
their own views of it, and to emphasize the extraordinary character still
further. By defining the projcct as "extraordinary," the city opened up
the project to "adventure" and change, and gave up some of its con-
trolling capacity.
There were, however, recurring attempts to tone down the extraor-
dinary character of the project and instead emphasize its ordinary fea-
tures. Such definitions open up the boundaries between the project and
its context, enabling learning and comparisons. One attempt to seek to
understand and pursue the Globe project in more ord~naryterms was
found when the competition started. Several competition groups com-
pared the Globe project to other major city-planned projects and found
it to be much less clear and supported by fewer formal decisions. When
they asked the city planners for clarifications, but without getting any
clear answers, they read this as a sign that the project lacked broad
support, and this led several groups to withdraw from active participa-
tion in the project.
Another attempt to understand - and revise - the project in more
ordinary terms was made by the construction companies in the archi-
tects' group that advocated the spherical arena design. The way the
architects assembled the group and conducted the project, did, in many
ways, break with institutionalized field principles. For example, some
less-established construction companies were recruited to the group by
PROIECT MANAGEMENT AS BOUNDARY WORK
course, the Globe project did not itself cause these shifts, which were
global in scope. But for those at the time who were arguing for greater
private involvement in public planning, the Globe project served as a
good example. However, a project is a better precedent for future plann-
ing if it is not defined as so "extraordinary," so those using such a case
as an example will describe it as ordinary and normal rather than as
exceptional. Hence, to allow a project to create an opening for or to
support future institutional changes, the institutional boundary work
must continue. Initially and during the process a project that is defined
extraordinary draws new institutional boundaries so that earlier insti-
tutionalized patterns do not seem to apply. The definition of a project
as "extraordinary" allows for new or changed procedures and rela-
tions. In order for the project to influence future patterns, however, it
must be redefined as less extraordinary.
In similar ways, many change projects are defined and described as
"new", thereby signaling the break with earlier modes of operation.
This has clearly been the case with recent public service reforms around
the world. Such reforms have been presented - b y the reformers as well
as by proponents and analysts of such reforms more generally - as
"new public management". The definition of New Public Management
(NPM) is general rather than specific. What is more, it is sometimes
argued for and defined not as a new form of governing, but rather in
terms of what it is not - i.e., the old public administration and bureau-
cracy. This feature is most clearly captured by the word "new", which
signals that it is a way of managing that breaks with previous tradi-
tions. Even though parts of what is today included in NPM is not par-
ticularly new - in relation to previous ways t o administer the public
services or in relation t o theories and principles for management that
have been taught in business schools and practised in business (Jacobs-
son and Sahlin-Andersson, 1995; Furusten and Lerdell, 1998) - when
circulating these models under the heading of NPM, this label clearly sig-
nals a break with the past and the introduction of something new. The
emphasis of the "new" attracts attention, and makes the reform project
that are persued under this label interesting for those who want to break
with previous institutions. As the public sector was being questioned in
many western countries in the late So's, projects that so clearly signaled
a break with the past and the introduction of something new attracted a
lot of interest (c.f. Olson et al., 1998; Christensen et al., 2001).
PROJECT MANAGEMENT A S BOUNDARY WORK
"The Globe project was 'speedy', time pressured, large, and difficult.
This kind of project always turns out to be more expensive than ini-
tially expected, said the Stockholm Commissioner, who also meant
that 'the great adventure' after all was worth all this."
And the interview continues with another comment from the politician
to the outcome of the project:
"But we had the guillotine over our heads, in that the Globe had t o
be completed for the world ice hockey championship in the spring of
1989."
iences are gained from actions performed, and secondly because time
elapses and future outcomes gradually get closer. At project end, know-
ledge exists that was impossible to acquire at project initiation. At this
point, the meaning of the project's goal is reinterpreted and the demar-
cation of the project scope is often revised. Ex post, we always know
more than ex ante.
The rest of the chapter is structured in four sections. Firstly, the basic
conceptual model of project management is outlined and the ideal of
the project goal that constitutes and controls project execution is
discussed. This is the model that will bc critically examined in subse-
quent sections. In the second section, the political aspects of project
selection and goal setting are discussed, with the claim that ambiguit-
ies and inconsistencies are natural components of most project assign-
ments. The third section addresses the knowledge aspects of project
execution, emphasizing how practical actions change the way the sti-
pulated project goal was initially intcrpreted. In the final section, the
chapter concludes with a discussion o n how experiences from perfor-
med project actions influence expectations regarding project outcomes.
The point is that evolutionary features of project goals are intrinsic ele-
ments of every project execution.
The chapter primarily addresses projects which have a technical core, e.g. projects in product
dcvclopment or building consrroction. The discussion might he applicable to other types of pro-
jects as well, but thar is beyond the scope of this chapter.
In this way, Project Management IS one of the ultimate and most explicit forms of "Manage-
menr hy Objectives".
MATS ENGWALI
Client
Goal
ments and changes. However, since these often mean changing a long
series of activities that have in turn been building on each other since
project initiation, late revisions are usually both complicated and cost-
ly to implement.
These goals should then he broken down systematically into clear and
consistent objectives, sub-objectives and milestones, which should sub-
sequently be translated into project activities and work-packages. Since
these work-packages are the basic input of project planning and sche-
duling, this kind of breakdown analysis is taught as the cornerstone for
all project planning and scheduling.
For practical project managers, this approach usually makes sense:
in practice, too many projects seem to be initiated without thorough
and well-prepared goals. Furthermore, the practical process of brea-
king down goals into objectives, sub-objectives, and work-packages is
a good collective exercise for the project team. By discussing the pro-
ject objectives in depth with each other, a conceptual structure of the
project assignment at hand is constructed. Problematic ambiguities in
the goal, differences in the interests of the stakeholders, and any misun-
T H E FUTILE DREAM OF THE PERFECT G O A L
"Boys, you have t o remember [...I that if you are going t o calculate
the cost of building a power plant, underestimate your calculations
so that construction work can start. There are no power plants that
are only half-completed." (Grennberg, 1998: 6)
ries over time: it relates future outcomes to actions and activities carried
out today. Through the goal, the actors involved can create a common
future. It becomes possible to coordinate the actions of today with
expected outcomes in the future. However, in relation to other kinds of
goals, the time specificity of project goals makes them distinct.
Project goals have traditionally been discussed as a basis for defining
the demarcation line between the tasks that do belong to (or ought to
belong to) the project and those that do not. This is the function em-
phasized in most project management literature. Clear, consistent, and
realistic objectives are claimed to enable the project manager to gain
control over the project execution process. Simultaneously, they are
claimed to protect her from being blamed for failures and problems
outside the project work.
However, the project goal also creates expectations. A t project initi-
ation, there is a stipulated, abstract project goal; there are resources
allocated to the project; and there are expectations regarding future
outcomes, but also regarding the process of creating the outcomes.
Through the execution process, the goals evolve from abstract visions
into concrete experiences: words are interpreted, actions are perfor-
med, and the world changes. During the course of the process, expec-
tations regarding the project are transformed, due to experiences gai-
ned from performing actions in combination with the fact that (calen-
dar) time is elapsing and the predicted future is approaching.
Usually, the transformation of expectations has two effects on pro-
ject execution: ( I ) the project goal is reinterpreted and redefined, and
( 2 ) the project demarcations are renegotiated with the environment.
Thus, the distance decreases between experiences gained from actions
performed within the project and expectations regarding future actions
in the project. At the end of the project, experiences and expectations
are coherent. However, at this point, the expectations have a different
meaning to what they did at project initiation.
THE FU'I'ILE DREAM OF THE PERFECT GOAL
-----------
Negotiations on dernorcd~ons
Definite goal
-
Ambiguous
1 Interpretations of content /
Resources + + De facto results
Expectation -----------
Experience through action
Negotiations on demarcations
Experience
) TIME
PROJECTEXECUTION
ODERLUND
Introduction
The question of "what is" a project may be differentiated from that of
"what goes on" in a project. Broadly, we associate the first question
with ambitions to define and specify structural characteristics of pro-
jects, and the second with various ways of conceptualizing the activiti-
es or processes involved. Moreover, while there is considerable agree-
ment in the literature as well as among practitioners as to "what is" a
project and the accompanying structural arrangements, we contend
there is far less convergence of views of "what goes on" in projects.
One central issue concerns the relevance of "rationalistic" accounts of
the project process. Above all, it is the traditional "planning-oriented"
project management literature that has been criticized for advocating
too simplistic recipes and for resting on overly "rationalistic" assump-
tions. Instead, critics argue, we should acknowledge the prevalence of
the not-so-rational processes involved and be open to the fact that even
other, alternative "rationalities" are important. Despite the attacks,
however, the normative literature on project management still, largely
unconcerned, suggests the skilful use of sophisticated planning techni-
ques as a sine qua non for successful project performance.
Apparently the view of project processes that is depicted in this plann-
ing-oriented project literature is a very resilient one. This should per-
haps come as no surprise. The idea that careful and extensive planning
should precede action has long roots, not only in project management
WHAT GOES O N I N PROTECTS?
texts, but also in other management literature. Very few would argue
that this is not part of the truth. What most critics claim is rather that
it is not the whole truth or the most important part of the truth about
project processes. In sum we have traditional allegedly rationalistic
accounts of these processes as well as a number of good arguments pro-
blematizing these representations and suggesting, to a greater or lesser
extent, what would provide a better view of project processes. Obviously,
these discussions relate to conceptualizations of processes at a high
level of generality. Staying with such a level of analysis we will not deal
explicitly with process issues, for example at the individual or project
group level.
Against this background we will continue these efforts to explore the
question of how to conceptualize project processes. In doing so we are
going to present how some Scandinavian authors have chosen to comm-
ent on the planning-orientation of the traditional literature and their
ideas of possible amendments. While recognizing the merits of these
attempts we believe that especially the implications of "uncertainty"
being a characteristic of project processes are still not very well spelled
out. In order to take a step forward we suggest here a conceptualiza-
tion of project processes as constituting problem-solving or knowledge
development processes. In this respect we build mainly on Popperian
epistemology and some of the writings of Weick and March.
Phrased in an evolutionary terminology, we also present a simple
three-phase model of the project process, incorporating a pre-selection, a
variation and a learning phase. Generally, this model aims at displaying
how uncertainty is being reduced in a trial-and-error manner, through
iterations, each of which includes this three-phase scheme. Unlike most
other critics of the planning-oriented literature this model stresses the
importance of specific and relatively stable goals. It also explicitly ack-
nowledges that error elimination and "reality-checking" are vital ele-
ments of these problem-solving processes. Such a framing, we believe,
is rather easily translated into project practice. Furthermore, the
aspects that are stressed in our model are highly significant in many of
the firm-specific project process manuals that are used in practice.
Finally, while it is true that our approach is a kind of rationalistic
endeavor, it is very far from the traditional planning-oriented rationa-
lism discussed above. Instead it relies basically on the idea of "critical
rationalism" - a view of epistemology dating back to the Pre-Socratic
era of Greek philosophy (Popper, 1998).
LAKS L l N D K V l S T A N D J O N A S S O D E K L U N D
The basic assumption of such a view is thus that project success is very
much a matter of establishing clear, operational goals in the first phase
and plans including breakdown and specifications of activities in the
second phase. If these two pre-execution phases are well managed the
actual project work will run smoothly and predictably. As argued by
Christensen & Kreiner (1991), however, the project is then turned into
a bureaucratic procedure that may be carried out rather routinely and
unconsciously - and when uncertainty is a significant feature such a
planning-oriented procedure will tend to be counter-productive. When
uncertainty is high, they argue, a goal-setting procedure cannot reduce
uncertainty enough. Attempting to further openness, agreement and
operationalization as to what isfshould be the project goal would rather
be to conjure uncertainty than to deal with it rationally. Instead, they
maintain, the critical issue during the goal-setting phase is to "create
motivation". Similarly, in the second phase, realistic planning is not
seen as an option; the role of plans is rather to provide useful symbolic
input for further communication and (again) for bringing about moti-
vation.
WHAT GOES O N I N P R O I E C T S ?
"The plan will match actual outcome, not because plans build on
correct experiences and valid assumptions about prevailing circum-
stances, hut because the plan in itself motivates the participants to
reach the planned outcome" (Christensen & Kreiner, 1991, p. 75).
better or "newer" than what was planned, much more may be learnt and
it may not even have been possible to start the project if goals and plans
were to be clearer at the outset. In sum, the message announced in the
introduction of the book is that the rational model should be abandoned.
A comment.
Taking a point of departure in the PMI four-phase model of "what goes
on" in a project, we are able to summarize the Scandinavian critique.
Apparently both Christensen & Kreiner and Lundin & Soderholm
broadly accept the idea of four sequential phases, although they ack-
nowledge that in practice there will be considerable overlap among
them. What they take issue with is the notions associated with each
phase and the general planning logic that the model implies. Common
to them is that they are uneasy mainly with the first two phases. Goals,
they argue, cannot or should not constitute a firm corner-stone for the
following process. Nor is it possible to carefully plan and specify a
priori what activities will have to be carried out. For Christensen &
Kreiner it is the high degree of "contextual uncertainty" that turns pro-
jects into much more open affairs, where issues of motivation and lear-
ning rather come to the forefront. For Lundin & Soderholm as well
uncertainty is underrated by traditional literature, leading to its inabi-
lity to acknowledge the need for entrepreneurship and rhetoric and the
symbolic functions of plans. In Sahlin-Andersson similar ideas are
displayed and developed more fully into a "strategy of ambiguity" in
which the benefits of unclear goals, plans decoupled from actual prac-
tice, are also recognized.
At a more general level, the critique appears to be directed at the deci-
sion-theoretic assumptions permeating traditional project literature and
the underestimation of the degree of "uncertainty" typically involved. In
order to understand "what goes on" in a project we are therefore well
advised to acknowledge the rationalities connected to rhetoric, symbo-
lism and action orientation - all of which would appear as "irrational"
from the point of view of classical decision-theoretic perceptions.
L A R S LINDKVIST AND J O N A S SODERLUND
. .. and a continuation
In furthering the ideas described above, one alternative would be to take
seriously the fact that many parties are involved and discuss how issues
of power and interests are played out in project processes. Another
alternative is t o continue on the theme of uncertainty. We will enter this
second path and try to carry the discussion a step forward by framing
the uncertainty issue within a knowledge development perspective. In
doing so, we will adhere t o a definition of "what is" a project stressing
the point that projects are characterized by having specific goals. Very
much unlike the ideas related to the first of the four phases discussed
above, we will thus conceive of such goals as being vital for the process
of generating knowledge in projects. As outlined below we suggest that
project processes may be seen as goal-directed learning processes.
Regarding the second of these phases we d o not disagree much with
the arguments presented above; when uncertainty is significant an
iterative approach rather than aprioric planning will be efficient (Lind-
kvist, Soderlund & Tell, 1998). So, in our view of projects, while
"what" t o achieve is typically rather well specified, it is very much up
t o the team t o find out "how" t o accomplish this, during the project
execution phase.
In some contrast with the Scandinavian critics, we will accordingly
focus mainly on the reduction of operational uncertainty related to the
implementationlexecution phase. Essentially we thus delimit our
discussion to the project level, mirroring also the fact that the kind of
industrial product development projects we have experience of (see
Berggren & Lindkvist, 2001) are plagued by lower degrees of contex-
tual uncertainty than those which the Scandinavian critics presumably
have in mind.
WHAT GOES O N IN PROIECTS?
Project organization
The conception of "what is" a project held by most practitioners is that
of a form of organization where there is a group of individuals who
should carry out a certain task or solve a given problem. Moreover, the
goals to be achieved are specified, including the time and money at the
project's disposal. While projects have quite specific goals or expecta-
tions, it is up t o the team t o find out how the problems should be
solved. Project teams thus typically enjoy a considerable amount of
autonomy within limits set. Such a view of projects as a kind of organ-
ization form is also typically adhered t o in the literature, and it is not
a new one.
Project organizing
Given our view of projects as associated with fairly well specified goals
or expectations, it is thus the uncertainty surrounding the issue of
"how" t o solve the problem that is brought into focus. In the termino-
logy of Weick (r996), such situations are "weak" in the sense that there
is limited or highly ambiguous guidance as to what actions should be
undertaken. In these situations local trial-and-error processes may be
relied upon to reduce uncertainty.
LARS LINDKVIST A N D JONAS S O D E R L U N D
A process model
Project organizing thus constitutes a way of dealing with uncertainty.
A project team with a specified goal t o achieve and granted enough
autonomy may establish an iterative learning process enabling action in
the context of uncertain "how" situations. This is done through a kind
of trial-and-error process, the characteristics of which we will consider
in more detail below. Consistent with our emphasis on the project goal,
we start by identifying some important functions of goals in a project
context. We then approach the issue of imagination and variety and
WHAT GOES O N I N PROJECTS?
4. A summa y figure
In the analytical model suggested there are thus three phases or types
of activities associated with each iteration in the problem-solving pro-
cess. First, the model underlines that projects presuppose that someone
has a problem, an interest or a goal - providing some direction to the
creative imaginative efforts. Second, it stresses the need to promote
imagination and the generation of a variety of ideas, perspectives, guess-
es, etc. Third, to compensate for our limited guessing abilities and dog-
matism a critical methodology is advocated. Such a model of how
knowledge is developed and practical learning takes place through a
series of iterations is of course very far from providing a picture that
closely resembles the richness and idiosyncrasy of real life project
LARS LINDKVIST A N D J O N A S S O D E R L U N D
work. We do believe, however, that there is also a need for such simpli-
fied accounts of project processes - provided they actually catch some
of the reality of "what goes on" in projects.
Figure The
IJ:~ project process model.
Conclusions
In this chapter we suggest that the issue of "what goes on" in projects
may be approached from a problem-solving or knowledge develop-
ment perspective. Moreover, relying on the ideas of Popper and Weick,
our way of signifying the project process - by identifying phases of pre-
selection, variation and learning - t o some extent mirrors evolutionary
terminology. In a sense, this process view suggests the possibility of a
project methodology, a specification of vital aspects that should he
recognized in carrying out a project. In this methodology the impor-
tance of goals or expectations is highlighted. In order to guide further
efforts they should be reasonably clear and specific. Furthermore, the
need for critical inquiry and reflection, promoted by various procedu-
res for "reality testing", is stressed. A basic assumption is thus that
expectations are clear enough t o be contradictable and that there is also
such a thing as "reality data" with power enough to provide deviances
vis-i-vis expectations.
Obviously, "what goes on" in a project may be analyzed in many
ways and at many levels of analysis. Paralleling the approaches in plann-
ing-oriented project literature and those of the Scandinavian critics,
the terminology used in this chapter is of necessity a rather abstract
one, placing many important questions outside of its scope and
interest. At the level of analysis chosen, one central issue is the rele-
vance of rationalistic accounts of project processes and possible alter-
WHAT GOES O N IN P R O J E C T S ?
RL: You know, when you said that you want to talk "about my career"
I was ready to cancel, because I don't feel that I've had a career. I've just
lived my life, that's all. It sometimes becomes a straight line when you tell
it, but in reality, it just happens to you. It's in the accounting of it that
one introduces causal links. But, why not? I can do it like everybody else.
So let's start by saying that I come from social class three-and-a-half.=
' "Perhaps, we all live in what might be called an 'interview society', in which interviews scem
central to malung sense of our lives." (Silverman, r993, p.19)
' A now forgotten official classification of employzcs in Sweden: group one were people with high-
er education, group two qualified workers, group three unqualified labor.
THE LIFE O F A P R O J E C T RESEARCHER
BC: ? ? ?
RL: My father was a miner and my mother did some cleaning jobs, so
we were rather hard up. I was born in Uppsala, but grew up in Danne-
mora, a mining town where my father had a job. But it was a tem-
porary job, so we soon moved to the region of Vasterls.
One early memory is my father telling me, "You know, you don't
have to have the same life I've had". Something like that. My parents
didn't have any opportunities, economically speaking, to shape their
life in a different way, so I felt that all hopes were centered on me.
Sometimes I wondered, as many children do: "Are these really my
parents?" At any rate, that's what he said: "You need not have the life
that I had". Nothing stronger than that. Just as if he'd been struck by
the thought.
Then there was the school. I was rather good at it, even if it was a
small provincial school - several classes in one classroom. The next
stage was secondary school. You must know that in my family there
was some cousin on my mother's side who graduated from high school,
and that was the closest that any of us had come to higher education.
The day I was to start secondary school, my mother said just before
I left (I needed to travel into Vasteris, because we lived in the country-
side): "You know, it's not too late to change your mind. You can finish
elementary school and get yourself a job, like everybody else...". So it
must have been my own achievement motivation, or something, hecau-
se they never said "You must fight for a better life!", never asked me
what happened at school.
was always on good terms with the teachers - most likely because I was
obedient, orderly, and helpful. What did I want to be when I grew up?
A teacher seemed to be a good choice. We admired them and I'd heard
that they made good money. At any rate, this was a different job than
working in the mine or on a construction site. Then I thought about
becoming an officer in the military - I don't know where this idea came
from, because there was no such tradition in our family. Perhaps it had
to do with the fact that I was taller than the other children and ran
more quickly. For a while, at least, because they caught up with me
very soon. But for a while I felt like Superman.
I finished school in 1962, and went into military service for nine
months in rq6zlrq63. I still don't remember what made me choose
business economics at university. There was a teacher I liked very much
- politically extremely right wing - who made us cheer for Karl the
XIIth. But he was very good at mathematics and physics, and so was I.
And then I had a chum who was called Bjorn Staberg; he didn't do mili-
tary service, so he started university earlier than the rest of us did, and
enrolled at Goteborg School of Economics and Commercial Law. This
could be the reason that my classmate, Christer As, and I applied to
Goteborg rather than Stockholm. Christer was very eager to learn, so
we studied all the time and didn't have much of a social life. I rarely
went out in the evenings and I didn't feel at ease when I did. Still, this
was when I met my first wife.
At high school I felt very insecure with girls. I never understood
them, and 1 must admit that this is true even now. I thought that I'd
better dedicate myself to studies. And then there was Christer, who
always challenged me in a sense, because he liked to compete and to be
best at exams. I still remember the last exam I took - I almost failed
one subject. It was called Contemporary Organization Theory and
Axel Targama was responsible for it. I had to take an oral, because my
written test wasn't good enough. I must admit that it felt nice to be the
internal examiner at his doctoral thesis defense some years later.
But then it was all over and I still didn't know what to do. My diplo-
ma thesis focused on communication as an organizational problem - a
speculative work that I did in relation to a project concerning simula-
tion of traffic lights at crossroads. There was a person who wrote a
licentiate thesis on this topic and wanted help with communication
problems. Now when I see a really bad piece of diploma work, I think
of my own - usually to conclude that mine was worse. Because it was
THE LIFE O F A P R O J E C T RESEARCHER
we were married in the spring of 1964. Our first worry was how to find
a flat in Goteborg? I'd been promised a room at a teacher's place on
LinnC Street, but the landlady made a mistake and promised the same
room to someone else. She gave us another room, but we could only
stay there for a month. So I ran around and found a place in a small
back building on Upper Hussar Street - a small kitchen and a small
room, no heating, gas, no toilet of our own. After that I got a student
flat, but we had to leave it when I got my diploma. We moved to Vastra
Frolunda (a suburb of Giitehorg) where we at least had a new flat, and
we lived there until we left for Chicago. Our first daughter, Petra, was
born in 1966 and our second, Anne, in June 1970. SO Anne was three
months old when we went to Chicago. But I had a family fellowship
and it was enough to live on.
It was a shock to come to Chicago. I'd been to the States before,
when I was doing those simulations, and I took a tour in 1968. But
when we came in 1970, it was the end of August or the beginning of
September, and the heat and humidity struck us as if we'd banged into
a wall. We took a taxi to a YMCA hotel where we were to stay until
we could move into our flat, and the driver told us immediately: "What-
ever you do, don't leave your luggage on the street". Then we moved
to our flat on 5zndStreet and started to get used to the cockroaches.
There was no air conditioning, of course. You know, if you've been out
in the cold and come into the warmth of a room, you feel drowsy. We
learned that it works the other way around, too. Regenstein Library a t
the University of Chicago had air-conditioning, and it was so pleasant
to sit there and feel cool. But we felt drowsy and practically fell asleep.
Not good for studying.
Graduate education was very different in the States than in Sweden
at that time, where Walter Goldberg would say: "Read these books and
then come and take an exam". In the USA they had courses like in under-
graduate education. I chose Management Science because it was my
thing and I chose the University of Chicago because I'd met those people
from Carnegie Mellon already. But it so happened that many of the peo-
ple at Chicago came from Carnegie Mellon and had many contacts there.
So even though I was at Chicago, my advisor was from Carnegie: Tom
Morton - young and very enthusiastic.
But the first thing to do was to choose courses. I thought: "organi-
zation or personnel administration". But my adviser was against it.
Nobody took such courses in Management Science; the proper courses
BARBARA C Z A R N l A W S K A
good article. My high evaluation might have to do with the fact that
for me it was a total relearning - writing in a completely different tra-
dition. On the one hand, it was only then that I understood that an
operation analyst is a very lonely person, at least an operation analyst
in the US tradition. It was pure mathematics that one did, sitting alone
in one's office. In operation analysis, one never had a reason to go "out
there", to the field of practice. On the other hand, there was a large
group of people who were interested in the results. Also, because I'd
graduated so quickly, I hadn't used up my fellowship, and I had enough
money left to go to a Management Science conference in Tel Aviv and
present my dissertation. Harvey Wagneri was in the audience, and I
remember that he came to me afterwards and said: "Yes!". I could
easily have stayed in that field.
Sidney Davidsson, who was then the Dean at Chicago School of
Business, called me in the autumn of 1973 and asked if I wanted a job.
I said that unfortunately I have promised to stay in Sweden that year,
but perhaps next year? But then I started to interview my colleagues,
and then we went to visit the municipality, so "next year" never mate-
rialized.
Sten and I didn't have any special analytical tool, although we tran-
scribed the interviews in detail. But most important for the analysis
itself, I thought, was the time that took us to drive home from the inter-
views. Luckily there were always red lights on A ~ e n u e ,so ~ we had
many chances to analyze the interviews. As you know, this essay was
published in Prescriptive Models of Organizations, and Bill Starbuck
made us revise it several times. He wanted us to write a text that was
short, direct, and well-articulated. Perhaps that's why I feel it was
good.
Walter Goldberg and Ulf af Trolle had also interviewed people in
Goteborg in connection with their work, "Need municipal taxes
g r o ~ ? " S. O~ between these two papers, Goteborg municipality was
being interpreted as a manic-depressive organization. The people we
interviewed liked it, and they liked "to be there", in the text. It created
an opportunity for a dialogue that I appreciated very much. Soon we
started doing it en masse, so to speak. There was the story of Vasterbs,
the story of Malmo, and a similar one about Alingsls. The story about
Malmo was called "The Lord's anger is the birth of w i ~ d o m " .Stellan
~
Malmer and Bjorn Brorstrom went to Lulei and wrote "Lulei after
two days of hockey". Soon there was a small group. Perhaps it was Sten
Jonsson who kept us together. At any rate we began to receive money
for research, and that was new! The "myth and wishful thinking"
study was donc during working hours and fuelled by our personal en-
thusiasm.
When we were still in Berlin writing our paper, I received a letter
from my wife. She wanted a divorce. I couldn't understand it. Our
adopted son, Par, was only 4 years old, and our biological daughters,
Anna and Petra, were 5 and 10.I took this letter very hard, and tried
to work through it, but my heart wasn't in it anymore. I felt like I'd
been hit by lightning. When I came back, I was given custody of the
three children, and I lived alone with them in the house we'd bought in
Kungbacka. I went to the office, feeling that I wasn't taking proper care
of the children; then I went home, feeling that I wasn't doing what I
ought to at the office.
Even before I went to the States, I'd worked halftime as Director of
Studies, and later 1was asked if I wanted to be head of the department.
It seemed like a perfect job in the peculiar state of mind I was in then.
It was so easy, and I didn't need to care, didn't need to be deeply cornm-
ited - it worked smoothly anyway. It seemed that all that was needed
was to listen to what people had to say, then summarize it. It was very
different from my previous way of relating to my work with a total
commitment. I remember that we had a very sensitive recruitment pro-
blem, and the then-powerful professor of marketing was involved. I
asked him to come to a board meeting and invited him to present his point
of view, and then said "Thank you. Now we know what we needed to
know. Thank you for coming". I could hear him unloading his fury
outside in the corridor, but I couldn't have cared less. I knew I was
doing the right thing, that the conflict could have degenerated if he'd
been allowed to remain.
I was awarded the title of Associate Professor in 1976,~and soon
after began to apply for chairs. The first was close to Management
'"In 1968, the workers in the mines went on strike against the Swedish state, the owner of the
mine, in spitc of the union\ decision not to.
T H E LIFE O F A PROJECT RESEARCHER
" For traditional reasons, degrees from professional schools are mure appreciated by Swedish
employers than those from universities. Thus faculties and deparrments at universities try to
exploit the old brand names, creating "schools", which, however, are now closer to the US tra-
dition (faculties) than to older European one (Hochschule).
BAKBARA CZARNIAWSKA
a very good idea. Jim March immediately sent a paper, and I didn't
know what to do with it. But I sent it to three independent reviewers,
who came back with very harsh comments. But you know what?
BC: Let me guess: they said that his English had to be corrected?
RL: No, no. Two of them thought I had written it myself. I was rather
pleased, but I was less pleased with my situation. They had quite a few
strong comments. So I sat down and wrote a letter to Jim, and told him
to react. I met him some years later, and he was so pleased: "You know,
I don't get enough criticism nowadays!" I really liked doing the editing.
I received heaps of submissions from Finland. It was as if they had all
those papers in their drawers waiting for an opportunity to let them
out. Some were good and some were less good, but I liked the job. It
was a bit like that with the School: had I only known what it really
meant before I even began thinking about it... But I hadn't, and maybe
that's the reason anything ever gets done. About four years later,
though, I felt that it was too much, and Sten Jonsson took over the editor-
ship.
At a certain point I was tired - with all internal conflicts, all the
work. But then I found a hole in the ice that let me slip up and catch
my breath. It was Anders Edstrom, who suggested that I could start
working for FA-rldet.lZI went to Stockholm and met Hans Wirdenius,
originally a psychologist, who was responsible for research in the con-
struction industry. We decided to do a study of a corporation called
Dios, a very well known construction company in existence since 19 I 8,
whose founder, Anders Dios, was still alive at that time.
It was a family firm that landed in trouble in the 1980s. They deci-
ded to recruit a managing director from outside - a construction engi-
neer whose name was Nils Nilsson. Really and truly, that was his
name. So we went to study this company. I've been shy all my life, but
what I did not expect was that Hans, who was 20 years older than I,
was even more shy, if possible. We sat there, at the FA-rldets office in
Stockholm, and waited for Nils Nilsson to come to be interviewed. A
couple of minutes before the appointment, Hans turned to me and said:
"Right! You run this, and I'll take notes". I didn't even know where
" An independent Council for Research on Enterprise and Work; it does not exist anymore
BARBARA CZARNIAWSKA
their money came from; I knew nothing about them, but I could see
that there was no way out, In came the guy, a military type if I ever saw
one, with steel gray eyes - I don't know if you know what I mean -
those eyes that look at you and you have the feeling that they can see
through you. It was the most difficult interview I have ever conducted.
Whenever I formulated a question, he would turn those eyes on me and
I would think, "What an idiotic question!"
We tried to depict Dios as Nils Nilsson saw it when he joined the
company. At that point, Dios employed five thousand people in Swe-
den and abroad, but everything was concentrated on and around
Anders Dios. It was a family firm: grandchildren all over the world
were the owners. We interviewed Anders Dios, too. It was very interes-
ting, because Diiis and Nilsson were opposites. It was also difficult
because if I have hearing problems, Anders Dios did not hear a thing.
We gave him written questions. He was very tall, almost two meters,
with arms that moved like windmills, 94 or 95 years old. He took our
questions and didn't pay any attention to them, just told his story. He
was totally uncontrollable. We learned that he was in his office seven
days a week. His driver worked for him for the whole week, and they
went visiting construction sites. He did it even after he fractured his
thighbone in the bathtuh. People at the site feared his visits but looked
forward to them. And then there was Nils Nilsson, whose main task
was to change the company and its culture. It didn't work: his rational,
bureaucratic, and analytical style was opposed from the very start.
Finally the twelve owners got together and appointed a new managing
director. Dios died, and the company turned into a real estate compa-
ny that still exists. Hans and I tried to describe all this in our book."
Nils Nilsson took a look at our manuscript and said: "I didn't think
you were going to write about me. 1cannot even show it to my wife!"
Eventually it came out right. I liked the book, and it gave me a break
from this work of organizing the School.'"
Hans was involved in the Project Management Institute since its
inception, and we went to several conferences to present our work on
Dios. We met with a very good response, and I became interested in
RL: Yes, since 1984. We were meeting regularly since 1979, but at first
it was too complicated to move together, with children and all. She has
one son and one daughter. But we have been living together a long
time, and I know her family very well. Her mother was an exceptio-
nally good person. I don't think she ever spoke with malice about any-
body in her life. She died at the same time as Hans. It was difficult to
get used to the thought that they left.
T H E LIFE OF A PROJECT R E S E A R C l l E R
RL: (laughing) If I only knew! I've studied projects quite a while now
- it'll be something like a ten-year anniversary soon. I have a black
notebook where I write down all my good ideas. There aren't many
pages left in this notebook. I don't know. The project theme attracts
much attention and many people, so it becomes almost overcrowded,
if you see what I mean. Then it also becomes more and more specific,
so we're back where we started - at the engineering level. What was a
bit exotic now becomes omnipresent. But I'm still keen on co-organi-
zing that international conference, because it is stimulating. This con-
tact network that we have all over the world is very special, and the
combination of scholars from economic sciences, social sciences, and
engineering is special too. The other summer PMI had its first research
conference. Previously the meetings were mainly for practitioners. I
was an invited speaker at that conference.
BC: Does this mean that you're not afraid of public speeches anymore?
RL: No, not any more. 1 believe that the fear had to do with my
upbringing. My mother and my father weren't shy at home, but it was
only my father who was somewhat outgoing. He would play a sort of
a charming urchin, especially after few drinks, while I was much more
inhibited. I remember those frightening experiences when I had to
make a presentation at school or stand up in the front of the class. I
remember that my best friend told a story of Little Red Riding Hood
and the wolf and everybody laughed at him. He was 12or 13 years old,
and he felt destroyed. Luckily for me, I could play the accordion. I
could take it and play a piece, and what could they say? At the most,
the teacher would say: "Didn't you tap the rhythm a bit too fast with
your foot?" That was about all the criticism 1 got.
But it has always been difficult to speak to a bigger audience. I tend
to think of myself as a very bad lecturer. All my energy goes into sur-
viving the experience of standing there in front of an audience. But now
I've got over it. I've noticed that in some contexts I'm really quite good
at it. I was president of a Rotary Club at the end of the 1980s, and it
was part of my duties to introduce every meeting, so I had to find
something new to say every time. And I noticed that it wasn't so diff-
icult after all. It's easy to get people to laugh and to relax. So now I
BARBARA CZARNIAWSKA
Since the mock interview was made, I was head-hunted for the dean-
ship of JIBS (Jonkoping International Business School). I accepted the
challenge and have held the job since May 2001, so I am no longer at
Umei. Reading the interview chapter under these new circumstances
was quite an odd experience. When I finished the first reading, I know
exactly how Nils Nilsson felt ("I cannot even show it to my wife!").
The story is simply incoherent and too much of "I" and "me", extre-
mely egocentric. On the other hand, Barbara asked me about my life
story. But some of the material is also very close to the forbidden area
-things you generally only talk about if you know that you can confi-
T H E LIFE O F A PROJECT RESEARCHER
de what you say to the listener - the ethical aspect. And even at that,
so much is left out. 1 mentioned only a few of "my" 3 0 or so Ph.D.s.
Professor Kerstin Sahlin-Andersson is not part of the story, even
though she wrote "my" first (i. e., her) thesis on projects.
It also appears that too much of feelings and whims rather than
planning took over my past life. In general, my generation does not like
to think of itself in that way. O n the other hand, one of the seven theses
at JIBS during my first year as Dean is all about emotions in manage-
rial work.'' In a sense, that thesis might legitimize this kind of approach
of relative openness.
So all in all, 1 have decided t o go along with the suggestion that the
interview be made public, even though I am not too happy with my
own contribution to the piece. Considering the contents of the chapter,
I cannot help but wonder what the story might have been if Barbara
had interviewed me on another day and in another mood. My guess is
that the story would likely have come out differently. Thus, a serious
question I have for Barbara concerning the narrative genre is: "What
can you learn from life stories of this type?"
" Rrundin ( 2 0 0 2 )
References
Abernathy, W.J., & Clark, K.B. (1985). Innovation: Mapping the winds of cre-
ative destruction, Research Policy, 14, 3-22.
Abernathy W.J., & Utterback. (1978). Patterns of Industrial Innovation, Tech-
nology Review, 80, 40-47.
Abrahamson, E. (1991). Managerial Fads and Fashion: The diffusion and
rejection of innovations, Academy of Management Review, 16, 586-612.
Achrol, R.S. (1997). Changes in the theory of interorganizational relations in
marketing: Toward a network paradigm. Iournal of the Academy of Marke-
ting Science, 2 5 ( ~ )56-71.
,
Adler, N. (2000). Managing Complex Product Development. Stockholm: EFI.
. de-scription of technical objects. In W.E. Bijker & J.
Akrich, M. ( ~ 9 9 2 )The
Law, (Ed.), Shaping technologylbuilding society (pp. 205-211). Boston, MA:
MIT-press.
Alchian, A.A., & Demsetz, H. (1972). Production, information costs, and eco-
nomic organization, American Economic Review, 6z(s), 777- 795.
Aldrich, H. (1999). Organizations Evolving. London: Sage.
Andersson, G. (1993) Leva for jobbet och jobba for livet: O m chefsfamiljer-
nas vardag och samlevnadsformer. Stockholm: Brutus Ostlings bokfijrlag
Symposion.
Anderson, H., & Larsson, A. (1998). Projects as an Arena for Innovation Ima-
ges of Projects and their Implications. In Lundin, R.A., & Midler, C. (Eds.),
Projects as Arenas for Renewal and Learning Processes. Boston, MA: Kluwer
Academic Publishers.
Andersson, J. ( ~ 9 8 1 ) .Projektkalkylering inom stationiir indushi - prospek-
tering av ett omrdde for foretagsforskningen. Stockholm: Royal Institute of
Technology.
Anell, B.I. (1998). Patterns of success and failure in renewal projects. In R.A.
Lundin & C. Midler (Eds.), Projects as Arenas for Renewal and Learning Pro-
cesses. Boston, MA: Kluwer.
Anell, B.I. (2000). Managing project portfolios. In F. Hartmann & R.A. Lundin
(Eds.), Projects as Business Constituents and Guiding Motives. Boston, MA:
Kluwer.
Anell, B.I., & Wilson, T.L. (2oooa). Competitive advantage in the knowledge
economy, Journal of Global Competitiveness. 8(1), 70-80.
Anell, B.I., & Wilson, T.L. (zoooh). Transitions in Project Management: Lin-
king Temporary and Permanent organisations. Sydney 2000: IRNOP IV Con-
ference Proceeding.
Aoyama, Y., & Castells M. (1994). Path towards the Information Society:
Employment Structure in the G7 Countriey International Labour Review,
~33(~).
Archibald, R.D. (1976). Managing high technology programs and projects.
New York: John Wiley & Sons.
Arenius, M., Artto, K.A., Lahti, M., & Meklin, J. (2002). Project companies
and the Multi-Project Paradigm: A new management approach. In D.P. Slevin,
D.I. Cleland, & J.K. Pinto (Eds.), The Frontiers of Project Management
Research (pp. 289-307). USA: PMI Project Management Institute.
Aronson, G. (1999). Contingent workers and health and safety, in Work,
employment and society, 439-459.
Art, R.J. (1972). Why we overspend and underaccomplish, Foreign Policy, 9 5-1 I 5.
Ashkenas, R., Ulrich, D., Jick, T., & Kerr, S. (1995) The Boundaryless Orga-
nization, Breaking the Chains of Organizational Structure. San Fransico, CA:
Jossey Bass.
Atkinson, J. (1984). Manpower strategies for flexible organisation, in Perso-
nal Management, August.
Audanson, R. (199 5 ) . Biblioteksforskning mellom ~ r a k s i sog akademia. In L.
Hijglund (Ed).Biblioteken, kulturen och den sociala intelligensen. Boris: Val-
frid i samarbete med Forskningsrddsnamnden.
Audunson, R.A., & Lund, N.W. (Eds.). (zoor). Det sivzliserte informasjons-
samfunn : folkbibliotekenes rolle ved inngangen ti1 en digital tid. Bergen: Fag-
boksforlaget.
Aurell, M. (2001). Arbete och identitet. Om bur stadare blir stadare. Iinko-
ping: Tema teknik och social forandring.
Avots, I. (1969). Why does project managemeht fail?, California Management
Review, I ~ ( I )77-82.
,
Azad, B., & Wiggins, L.A. (1995). Dynamics of inter-organizational geogra-
phic data sharing: A conceptual framework for research. In H.J. Onsrud & G.
Rushton (Eds.),Sharing Geographic Information (pp. 22-43). New Brunswick,
NJ: Center for Urban Policy Research.
Baier, V.E., March, J.G., & Saetren, H. (1986); Implementation and ambiguity,
Scandinavian Journal of Management Studies, z(3-4), 197-2 I 2.
Bauer, R.A. (1968). The study of policy formation: An introduction. In R.A.
Bauer, & K.J. Gergen (Eds.), The study of policy formation. New York: The
Free Press.
Ben Mammoud-Jouini S., & Midler, C. (1999). Compttition par I'innovation
et dynamique de la conception dans les entreprises franqaises. Rtflexions i
partir de la confrontation de trois secteurs, Entreprise et Histoire, 23, 36-62.
Benghozi, P.J., Charue Duboc, F., & Midler, C. (2000). Innovation Based
Competition & Design Systems Dynamics. Paris: L'Harmattan.
Bengtsson, M., & Soderholm, A. (2002). Bridging distances: Organizing
boundary-spanning technology development projects, Regional Studies, 3 6 ( 3 ) ,
263-274.
Beniger, J.R. (1986). The Control Revolution: Technological and Economic
Origins of the Information Society. Cambridge, MA: Harvard University Press.
Bennis, W.G. & Slater, P.E. (1968). The temporary society. New York: Harper
& Row Publishers.
Berggren, C., & Lindkvist, L. (Eds.). (2001). Projekt. Organisation for mB1-
orientering och larande. Lund: Studentlitteratur.
Bergman, G. ( ~ 9 9 0 )Ord
. med historia. Stockholm: Prisma.
Biblioteket som serviceforetag. Kunden i centrum. (1992) Stockholm: FRN.
Bjiirkegren, D. (1989). Hur Organisationer Lar. Lund: Studentlitteratur.
Blau, P.M. (1955). The Dynamics of Bureaucracy, Chicago: University of Chi-
cago Press.
Block, T.R., & J.D. Frame. (1998). The Project Office - A Key to Managing
Projects Effectively. Menlo Park, CA: Crisp Publications.
Blomberg, J. (1998). Myter o m projekt. Stockholm: Nerenius & Santerus.
Blomquist, T., & Packendorff, J. (199th). Ekonomisk styrning for forandring:
En studie av ekonomiska styrinitiativ i halso- och sjukvcirden. Umed: Han-
delshogskolan vid Umed Universitet.
Blomquist, T., & Packcndorff, J. (1~98b).Learning from renewal projects:
Content, context, and embeddedness. In R. Lundin & C. Midler (Eds.), Project
as arenas for renewal and learning processes (pp. 37-46). Dordrecht,: Kluwer
Academic Publishers.
Blomqvist, C. (1996). f marknadens namn. Stockholm: Nerenius & Santtrus.
Blomqvist, P., & Rothstein, B. (2000). Valfardsstatens nya ansikte: demokra-
ti och marknadsreformer inom den offentliga sektorn. Stockhlm: Agora.
Boman 1-1. (1992). Forandringen: En berattelse om svenska ABB och T j o .
Stockholm: Affarsvarlden.
Borum, F., & Christiansen, J. K. (1993). Actors and structure in IS projects:
What makes implementation happen? Scandinavian Journal of Management,
9(1), 5-28.
Bossler, J.D. (1995). Facilitating the sharing of spatial data: Perspectives from
the mapping science committee. In H.J. Onsrud, & G. Rushton (Eds.), Shar-
ing Geographic Information. (pp. 347-54). New Brunswick, NJ: Center for
Urban Policy Research.
Bounty, I. (zooo). Interpersonal and interaction influences on informal resour-
ce exchange between R&D researchers, Academy of Management Journal,
43(1), 5-66.
Rresman, H., Birkinshaw, H.J., & Nobel, R. (1999). Knowledge transfer in
international acquisitions, Journal of International Business Studies, 30(3),
439-462-
Rresman, H., & Solvell, 0. (1997). Local and global forces in the innovation
irocess of the multinational enterprise - an hour-glass model, NORDREFO
1997:3. Special issue: Regional Specialisation and Local Environment - Lear-
ning and Competitiveness.
Brown, J.S., & Duguid, P. (1998). Organizing knowledge, California Man-
agement Review, 40(3), 90-112.
Brown, M.M., & Brudney, J.L. (1993) Modes of geographical information
system adoption in public organizations: Examining the effects of different
implementation structures. Proceedings of the Annual Meeting of the Ameri-
can Society for Public Administration.
Brown, M.M., O'Toole, L.J. Jr., & Brudney, J.L. (1996). Implementing Geo-
graphic Information Systems in Government: An Empirical Assessment of
Local Partnerships.
Brown, S., & Eisenhardt, K. (1997). The art of continuous change: Linking
complexity theory and time-paced evolution in relentlessly shifting organiza-
tions, Administrative Science Quarterly, 42, 1-34.
Bruner, J. (1986). Actual Minds, Possible Worlds. Cambridge, MA: Harvard
University Press.
Bruner, J. (1990). Acts of Meaning. Cambridge, MA:Harvard University Press.
Brunsson, N. (1985). The irrational organization. Chichester: Wiley & Sons.
Brunsson, N. (1989). The Organization of Hypocrisy: Talk, Decision and
Actions in Organizations. Chichester: Wiley.
Brunsson, N., & Jacobsson, B. (Eds.), (2000). A World of Standards. Oxford:
Oxford University Press.
Brunsson, N., & Olsen, J.P. (1990). Makten att reformera. Stockholm: Carls-
sons.
Brunsson, N., & Olsen, J.P. (Eds.). (1993). The reforming organization. London:
Routledge.
REFERENCES
Brunsson, N., & Olsen J.P. (Eds.). (1999). Organizing Organizations. Oslo:
Fagbokforlaget.
Brunsson, N. & Sahlin-Andersson, K. (2000). Constructing Organizations.
The case of Public Sector Reform, Organization Studies, 21(4), 721-746.
Brochner J., Ekstedt E., Lundin R.A., & Wirdenius H. (1992). Att bygga med
kunskap. F0rnyelseform2~ai byggsektorn. Stockholm: Byggforskningsridets
forlag.
Burke, K. (194511969). A Grammar of Motives. Los Angeles: University of
California Press.
Byrne, J.A., & Elgin, B. (2002). Cisco Shopped till It Nearly Dropped, Busi-
ness Week - Ind~striaNTechnolog~ Edition, 3766, 60-61.
Cadin, L., Bender, A-F., de Saint Giniez, V., & Pringle, J. (2000). Carricres
nomades et contextes nationaux, Revue de Gestion des Ressources Humaines,
37, 76-96.
Calkins, J., Epstein, E., Estes, J., H. Onsrud, J. Pinto, G. Rushton, G. & Wiggins,
L. (1991). Sharing of Geographic Information: Research Issues and a Call for
Participation. 1-9 Specialist Meeting Report. Long Beach, CA: National Cen-
ter for Geographic Information and Analysis.
Callon, M. (1986). Some elements of a sociology of translation: domestication
of the scallops and the fisherman of St Brieuc Bay. In J. Law (Ed.), Power,
action and belief. A new sociology of knowledge? (pp 196-233). London:
Routledge.
Callon, M. (1987). Society in making: The stud y of technology as a tool for
sociological analysis. In W.E. Bijker., T. Hughes, & T. Pinch (Eds.), The social
construction of technological systems (pp 83-103). Cambridge, MA: MIT
Press.
Callon, M. (1991). Techno-economic networks and irreversibility. In J. Law
(Ed.), A sociology of monsters. Essays on power, technology and domination
(pp 132-161). London: Routledge & Kegan Paul.
Callon, M. (1999). ANT - the market test. In J. Law, & J. Hassard (Eds.),
Actor Network Theory and after (pp I ~ T - T ~ S ) .Oxford: Blackwell publishers.
Callon, M., & Latour, B. ( ~ 9 8 Unscrewing
~). the big Leviathan, or how actors
macro-structure reality and how sociologists help them to do so. In K. Knorr-
Cetiua, & A. Cicourel (Eds.), Advances in social theory and methodology:
toward an integration of mzcro and macro sociologies (pp 277-303). London:
Routledge & Kegan Paul.
Campbell, H.J. (1991). Impact of Geographic Information Systems on Local
Government, TRP 101. Sheffield: The University of Sheffield, Department of
Town and Regional Planning.
Castells M. (1996). The Rise of the Network Society. Malden, MA: Blackwell.
Caves, R.E., & Porter, M.E. (1977).From Entry Barriers to Mobility Barriers:
Conjectured Decisions and Contrived Deterrence to New Competition, Quar-
terly Journal of Economics, 91, Z ~ T - 2 6 7 .
Chandler, A. (1962). Strategy and Structure. Cambridge MA: The MIT Press.
Chandler, A. (1977).The Visible Hand. Cambridge MA: Harvard University
Press.
Chapel, V. (1996).La croissance par ['innovation : de la dynamique d'appren-
tissage a la rkvklation d'un modele industriel. Le cas Tefal. Thtse de doctorat
sptcialitt IngCnierie et Gestion Thesis, ~ c o l eNationale Supkrieure des Mines
de Paris, Paris.
Chapman, C.B., & Ward, S.C. (1993). Project Risk Management: Processes,
Techniques and Insights. Chichester: John Wiley and Sons.
Chell, E. (1991).The Entrepreneurial Personality. Concepts, Cases and Cate-
gories. London: Routledge.
Chesbrough, H.W., & Teece, D.J. (1996). When is virtual virtuous? Organi-
zing for innovation, Narvard Business Review, 74(r), 65-73.
Christensen, S., & Kreiner, K. (1991). Projektledning. Att leda och lara i en
ofullkomlig uarld. Bjarred: Academia Adacta.
Christensen, T., & Laegreid, P. (Eds.), (2001).New Puhlic Management: The
Transformation of Ideas and Practice. Aldershot: Ashgate.
Cihorra, C.U. (1996).Introduction: What does groupware mean for the organ-
izations hosting it? In C.U. Ciborra (Ed.), Groupware and teamwork (pp
1-19). Chichester: John Wiley & Sons.
Clark, K. B., & Fujimoto, T. (1991).Product development performance. Stra-
tegy, organization and management in the world auto industry. Cambridge,
MA.: Havard Business School Press.
Cleland, D. I., & King, W. R. (1968). Systems analysis and project manage-
ment. New York: McGraw-Hill.
Coase R.H. (1988).The firm, the market, and the law. Chicago: University of
Chicago Press.
Cohen, M.D., March, J.G., & Olsen, J.P. (1972). A garbage can model of
organizational choice, Adminishative Science Quarterly, I ~ ( I ) 1-25,
,
Cooper, R.G., Edgett, S.J., & Kleinschmidt, E.J. (1999). New product port-
folio management: Practices and performance, Journal of Product lnnouation
Management, I 6, 3 3 3-3 j I.
Cooren, F. (2000). The organizing Property of Communication. Amsterdam1
Philadelphia: John Benjamins.
Craig, W.J. (1995). Why we can't share data: Institutional inertia. In H.J.
Onsrud, & G. Rushton (Eds.), Sharzng Geogaphic lnformation (pp. 107-18).
New Brunswick, NJ: Center for Urban Policy Research.
Csik~zentmihal~i, M. (1990). Kreativitet och kulturell utveckling. In G. Klein,
(Ed.), O m kreativitet och flow. Stockholm: Bromberg.
Cuhls K., Blind K., & Grupp, H. (1998). Delphie 98, Studie zur Globalen
Entwicklung uon Wissenschaft und Technik. Karlsruhe: Fruenhofer-Institut
fiir Systemtechnick und Innovationsforschung.
Cummings, T.G. (1980). Interorganization theory and organizational devel-
opment. In T.G. Cummings (Ed.), Systems Theory for Organization Develop-
ment. New York: John Wiley and Sons.
Cyert, R.M. & March, J.G. (1963) A Behavioral Theoy, of the Firm. Engle-
wood Cliffs, N.J: Prentice Hall.
Czarniawska, B. (1997). Narrating the Organization. Drama of Institutional
Identity. Chicago: University of Chicago Press.
Czarniawska, B. (1999). Writing Management - Organization Theory as a
Literary Genre. Oxford: Oxford University Press.
Czarniawska-Jorges, B. (1988). Ideological control in nonideological organ-
izations. New York: Praeger.
Czarniawska-Joerges, B. (1992). Styrningens paradoxer. Scener ur den offent-
liga uerksamheten. Goteborg: Norstedts juridik.
Czamiawska, B., & Jorges, B. (1996). Travels of ideas. In B. Czarniawska, &
G. Sevon (Ed.), Translating organizational change (pp 13-48), Berlin: Walter
de Gruyter.
Czarniawska, B. & Sevbn, G. (Eds.), (1996). Translating Organizational
Change. Berlin: De Gruyter.
D'Aveni, R.A. (1994). Hypercompetition: Managing the dynamics of strategic
maneuvering. New York: The Free Press.
Danielsson, A., & Malmherg, A. (1979). Beslut fattas. Stockholm: Svenska
Arbetsgivareforeningen.
Davidow, W.H., & Malone, M.S. (1992). The Virtual Corporation. New
York: HarperCollins.
Dawes, S.S. (1996). Interagency information sharing: Expected benefits,
Manageable risks,JournaE of Policy Analysis and Management, T 5(3),377-394.
Dawkins, R. (1976). The Selfish Gene. Oxford: Oxford University Press.
Deakin, N., & Walsh, K. (1996). The enablirig state: the role of markets and
contracts. Public Administration, 74, 33-47.
Dickson, P.R. (1996). The static and dynamic mechanics of competition: a
comment on Hunt and Morgan's comparative advantage theory, ,Journal o f
Marketing, 60(4), 102-106.
DiMaggio, P. & Powell, W.W. (1983). The Iron Cage Revisited: Institutional
Isomorphism and Collective Rationality in Organizational Fields, American
Sociological Review, 48, 147-160.
Donaldson, L. (1996). The normal science of structural contingency theory. In
S.R. Clegg, C. Hardy, & W.K. Nord. (Eds.), Handbook of Organzzatronal
Studzes. London: Sage.
Doolin, B. (1999). Sociotechnical networks and information management in
health care, Accountzng, Management & Infomation Technology, 9(2),95-114.
Dueker, K.J., & Vrana, R. ( 1 9 9 ~ )Systems
. Integration: A Reason and a Means
for Data Sharing. In H.J. Onsrud, & G. Rushton (Eds.), Sharing Geographic
Information (pp. 149-71). New Brunswick, NJ: Center for Urban Policy
Research.
Duffy, M., & Dickerson, J.F. (zooz). Enron spoils the party, Time (February
4), 18-25.
Easton, G., & Araujo, L. (1992). Non-economic exchange in industrial
network. In B. Axelsson, & G. Easton (Eds.), Industrial networks - A new
vzew o f reality (pp 63-88). London: Routledge.
Eaton, S.C., & Bailyn, I,. (zooo). Career as life path: Tracing work and life
strategies of biotech professionals. In M. Peiperl, M. Arthur, R. Goffee, & T.
Morris (Eds.), Career frontzers: New conceptions of working lives (pp.
177-198). Oxford: Oxford University Press.
Economist (zooza). The car factory of the future. (February 23), 75-78
Economist (zoozb). Hewlett-Packard and Compaq: Planning to prove them
wrong. (March y), 65.
ECOSIP (V. Giard, & C. Midler, (Eds.). (1993))~Pilotages de prolet et entre-
prises: Diversztb et convergences. Paris: Econornica.
Edelman, M. (1988). Constructing the Political Spectacle. Chicago: Chicago
University Press.
Egerdal, E.R. (1992). Biblioteksjefen som kommunal leder: Lederopplaering
for biblioteksjefer - gir det resultater? In L. Seldtn (Ed.), Riblioteket och fram-
tiden. Goteborg: Centrum for biblioteksforskning.
Eichenwald, K. (2002). Andersen may find its fate in hands of man it fired,
New York Times (March z j ) , As.
Eisenhardt, K.M., & Martin, J.A. (2000). Dynamic capabilities: what are
they? Strategic Management Journal, z r ( s o l r r ) , 1105-1122.
Eisenhardt, K.M., & Tabrizi, B.N. (1995). Accelerating adaptive processes:
Product innovation in the global computer industry, Administrative Science
Quarterly, 40, 84-1 10.
Ekstedt, E. (2001). Interviews in ICT companies, call-centres, manpower lea-
sing companies, Odenskog industrial park 1999-2001, (unpublished).
Ekstedt, E., Lundin, R. A., Soderholm, A., & Wirdenius H. (1999). Neo-
Industrial Organizing - Action, Knowledge Formation and Re-newal in a Pro-
ject-intensive Economy, London: Routledge.
Ekstedt, E., Lundin, R.A., & Wirdenius H. (1992). Conceptions and Renewal
in Construction Companies, European Managevzent Jourrzal, I O ( Z ) , 202-209.
Ekstedt, E., & Wirdenius, H. (1995 ). Renewal Projects: Sender Target and
Receiver Competence in ABB T j o and Skanska jT, Scandinavian Journal o f
Management, I 1(4), 409-421.
Eliasson, G. (1992). Arbetet - dess betydelse, dess innehdll dess kvalitet och
dess ersattning. Stockholm: Almqvist & Wiksell.
Engstrand, A-K. (forthcomming) The Road once Taken. Business, Politics and
I'romotion of Karlskrona and Udevalla in the post-war period. (diss), Work
Life in Transition, Stockholm.
Engwall, L. (1992). Mercury Meets Minerva. Oxford: Pergamon Press.
Engwall, I.. & Zamagni, V. (Eds.), (1998). Management education in histori-
cal perspective, Manchester: Manchester University Press.
Engwall, M. (1990). Flat corporate organizations: A complex environment for
engineering projects. In R. Garies (Ed.), Handbook on management by pro-
jects. Wien: Manz.
Engwall, M. (1995). Jakten pd det effektiva projektet. Stockholm: Nerenius
& Santerus.
Engwall, M. (zooz). Implementation eller innovation. In A. Danielsson, & I.
Holmberg (Eds.), Ledarskapets olika skepnader - exemplets Hallandsds. Lund:
Studentlitteratur.
Engwall, M., Steinth6rsson, S., & Soderholrn, A. (zooz). Temporary organi-
zing - a Viking approach to project management research. In B. Czarniawska,
& G. Sevon, Nordic Lights, Stockholm: Liber
Eriksson, J. (1997). Drivkrafter bakom project. UmeB: UmeH School of Busi-
ness and Economics.
Eskerod, P. (1996). Meaning and action in a multi-project environment, Inter-
national Journal of Project Management, 14(2), 61-65.
Esping-Andersen, G. (1991). The Three Worlds of Welfare Capitalism.
Cambridge: Polity Press.
Ester, P., Halman, L., & De Moor, R., (Eds.). (1994). The Individualizing
Society. Value Change in Europe and North America. Tilburg: Tilburg Uni-
versity Press.
Etzioni, A. ( ~ 9 6 9 )The
. semi-professions and their organization: teachers, nur-
ses social workers. New York.
Evans, J.D. (1995). A case study of infrastructures for sharing geographic
information among environmental agencies. Presentation at NCGIA Young
Scholars Summer Institute on Geographic Information 1995.
Fama, E.F. (.1980). Agency problems and the theory of the firm, Journal of
Political Economy, 88, 288-307.
Fayol, H. (1949). General and Industrial Management. London: Pitman.
Ferlie, E., Ashburner, L., Fitzgerald, I.., & Pettigrew, A. (1996). The new pub-
lic management in action. Oxford: Oxford University Press.
Frank, A.U. (1992). Telecommunication and GIS: Opportunities and chall-
enges. In P. W. Newton, P. R. Zwart, & M. E. Cavil1 (Eds.), Networking Spa-
tial Information Systems (pp. 235-50). London: Belhaven.
Frangsmyr, T. (1974). Drommen om det exakta sprdket. Stockholm: Veten-
skapens trad
Furusten, S. (1999). Popular Management Books. London: Routledge.
Furusten, S., & Lerdell, D. (1998). Managementiseringen av forvaltningen. In
G. Ahrne, (Ed)., Stater sum organisationer (pp. 99-122). Stockholm: Nerenius
& Santkrus.
Gaddis, P.O. (1959). The project manager. Harvard Business Review, 3, 89-97.
Garel, G., Kesseler, A., & Midler, C. (1997) Le co-dkveloppement, dkfinitions,
enjeux et probl2mes. Educations Permanente.
Garel, G., & Midler, C. (1998). An analysis of co-development performance
in automotive development processes: a case study testing a win-win hypoth-
esis. In 5th International Product Development Management Conference
(403). Italy: Como
Garfinkel, H. (1967). Studies in Ethnomethodology. Englewood Cliffs: Pren-
tice-Hall.
Garsten, C. (1999). Betwixt and between: Temporary employees as liminal
subject in flexible organisation, Organization Studies, zo(4), 274-309.
Gates, B. (1996),The Road Ahead. New York: Viking.
George, J.M., & Jones, G.R. ( 2 0 0 2 ) . Organizational Behavior, 3'"d. Upper
Saddle River, NJ: Prentice Hall.
Gershuny, J., & Miles, I., (1983).The New Service Economy. The Transfor-
mation of Employment in Industrial Societies. London: Frances Pinter.
Gersick, C.J.G. (1988).Time and transition in work teams: Toward a new
model o f group development, Academy of management journal, ~ I ( I )9-41.
,
Olson, O., Guthrie, J., & Humphre y C., (Eds.), (1998). Global Warning:
Debating International Developments in New public financial management.
Oslo: Cappelen Akademisk Forlag.
Olson, 0 . & Sahlin-Andersson, K. (1998) Accounting Transformation in an
Advanced Welfare State: The Case of Sweden. In 0. Olson, J. Guthrie & C.
Humphrey (Eds), Global Warning: Debating International Developments in
New Public Financial Management. Oslo: Cappelen Akademisk Forlag.
Olsson, L. (1991). Sammanfattning. In H. Jarv (Ed.), Bibliotekarieyrket. Tra-
dition och forandring (pp. 170-175). Stockholm: Carlssons.
Orlikowski, W. (1992). The duality of technology: Rethinking the concept of
technology in organizations, Organization Science, 3 ( j ) , 398-427.
Orlikowski, W.J. (1996). Improvising organizational transformation over
time: A situated change perspective. Information Systems Research, 7(1), 63-92.
O'Toole, L.J. Jc, & Montjoy, R.S. (1984). Interorganizational policy imple-
mentation: A theoretical perspective, Public Administration Review, 46(6),
497-505.
Packendorff, J. (1993). Projektorganisation och prolek~organisering.Projekt
som plan och temporar organisation. Umeb: Handelshogskolan.
Packendorff, J. (1995). Inquiring into the temporary organisation: New direc-
tions for project management research, Scandinavian Journal of Management,
11(4), 319-333.
Palisi, B.J. (1970). Some suggestions about the transitory - permanence
dimension of organizations, British journal of sociology, 21, 200-206.
Parkin, J. (1996). Organizational decision making and the project manager,
International Journal of Project Management, 14(5), 257-263.
Payne, J.H. (1995). Management of multiple simultaileous projects. Interna-
tionalJouma1 of Project Management, 13(3), 163-168.
Perelman, C., & Olbrechts-Tyteca, L. ( ~ o o o / r 9 6 9 )The
. New Rhetortc - a
Treatise on Argumentation. Notre Dame: University of Notre Dame Press.
Perlow, L.A. (1997). Finding time: How corporations, individuals, and fami-
lies can benefit from new work practices. Ithaca: Cornell Univer-sity Press.
Peters, T.J. (1992). Liberation Management. New York:Knopf.
Peters, T.J., & Waterman, R.H., Jr. (1982). In Search of Excellence: Lessons
from America's Best-run Companies. New York: Harper and Row.
Pettigrew, A. & Fenton, E. (2000). The Innovating Organization. London:
Sage.
Pettigrew, A., Massini, S., & Numagami, T. (2000). Innovative Forms of
Organizing in Europe and Japan, European Management Journal, I 8, 259-73.
Pfeffer, J. (1998). The Human Equation. Building Profits by Putting People
First. Boston, Mass: Harvard Business School Press.
Pinto, J.K. (1996). Power & politics in project management. Sylva, NC: Pro-
ject Management Institute.
Pinto, J.K., & Kharbanda, O.P. (1995). Lessons for an accidental profession,
Business Horizons, March-April, 41-50.
Pinto, J.K., & Onsrud, H.J. (1995). Sharing geographic information across
organizational Boundaries: A research framework. In H.J. Onsrud, & G.
Rushton (Eds.), Sharing Geographic Infomatton (pp. 44-64). New Rruas-
wick, NJ: Center for Urban Policy Research.
Pinto, J.K., & Prescott, J.E. (1990). Planning and tactical factors in the pro-
ject implementation process, Journal of Management Studies, 27(3), 305-327.
Pinto, J.K., & Rouhiainen, P. (2001). Building Customer-Based Project Organ-
izations. New York: Wiley.
Pinto, M.B., Pinto, J.K., & Prescott, J.E. (1993). Antecedents and consequen-
ces of project team cross-functional cooperation, Management Science,
39(12), 1287-1297.
Piron, P. (2000). Managing Joint development in Transnational Alliances the
Case of Fxropean tactical Missile industry. In C. Benghozi, & C. Midler
(Eds.), Innovation Rased Competition and Design Systems Dynamics
(161-193). Paris: L'Harmattan.
Piron, P. (2001). L'alliance en convergence. Developper conjointement dam
l'industrie europkene des missiles tactiques. Ph.D. Thesis, Ecole Polytechnique,
Paris.
PMI ( ~ 9 9 6 )A. guide to the project management body o f knowledge. Upper
Darby, PA: Project Management Institute.
PMI Standards Committee. (1987). Project Management Body o f Knowledge
(PMBOK). Drexel Hill, PA: Project Management Institute.
Polanyi, M. (1958). Personal Knowledge. London: Routledge and Keagan.
Popper, K. (1945). The open society and its enemies. London: Routledge.
Popper, K. (1972). Conjectures and refutations: the growth of scientific know-
ledge. London: Routledge & Kegan Paul.
Popper, K. (1992). In search of a better world. Lectures and essays from thirty
years. London and New York: Routledge.
Popper, K. (1998). The world of Parmenides. Essays on the Presocratic
Enlightenment. New York: Routledge.
Popper, K. (1999). All life is pr~blemsolvin~.
London: Routledge.
Porac, J.F., Thomas, H., & Baden-Fuller, C. (1989). Competitive Groups as
Cognitive Communities: the Cases o f Scottish Knitwear Manufacturers, ]our-
nal of Management Studies, 26(4), 397-416.
Porter M.E. (1980). Competitive Strategy. New York: Free Press.
Porter, M.E. (1990). The competitive advantage of nations. 1.ondon: Macmillan.
Porter M.E. (1998). Clusters and the new economics o f competition, Harvard
Business Review, NovemberlDecember, 77-90.
Potter, J . & Welherell, M. (1987)~Discourse and Social Psychology. London:
Sage.
Powell. W.W. (1998). Learning from collaboration: Knowledge and networks
in the biotechnology and pharmaceutical, California Management Review,
4431, 228-440.
Powell, W.W., and DiMaggio, P. J . (Eds.) ( 1 9 9 ~ )The
. New Institutionalism in
Organizational Analysis. Chicago: University o f Chicago Press.
Powell, W.W., Koput, K.W., & Smith-Doerr, L. (1996). Interorganizational
collaboration and the locis o f innovation: networks o f learning in biotechno-
logy, Administrattve Science Quarterly, 41, 116-145.
Quinland, M., Mayhew, C., & Bohle, P. (2000). Contingent work: health and
safety perspectives or the global expansion of precarious employment, work
disorganisation and occupational health: a review of recent research. Dublin:
European Union Research Workshop.
Rankin, D. & Parent, M. (1997). Cisco Systems kc.: Managing Corporate
Growth using an Intranet. Richard Ivey School of Business The University of
Western Ontario.
Rapp Ricciardi, M. (2001). Projektpsykologt: Produktutueckling ur manni-
skans perspektiv. Goteborg: Goteborg University.
Ringqvist, M. (1966). Om den offentliga sektorn: vad den ger och vad den tar,
Stockholm.
Romer, P. (1991). Increasing Returns and New Development. In W.Barnett, et
a1 (Eds.), Equilibrium Theory and Applications. Cambridge: Cambridge Uni-
versity Press.
Rosenau, J.N., & Czempiel, E-0. (1992). Governance without Government.
Cambridge: Cambridge University press.
Rosenberg, N. (1982) Inside the black box: Technology and Economics.
Cambridge: Cambridge University Press.
Ruef, M. (2002). At the Interstices of Organizations: The Expansion of ohe
Management Consulting Profession, 1933-1997 In K. Sahlin-Andersson & L.
Engwall (Eds.), The Expansion of Management Knowledge: Carriers, Flows
and Sources. Stanford: Stanford University Press.
Rushton, G., & Frank, S. (1995). Sharing spatial data among social
scientists. In H.J. Onsrud, & G. Rushton (Eds.), Sharing Geographic lnfor-
mation (pp. 461-74). New Brunswick, NJ: Center for Urban Policy Research.
Rsvik, K-A. (1996). Deinstitutionalization and the Logic of Fashion. In B.
Czamaiwska, & G. Sev6n (Ed.), Translating Organizational Change (139-
172). Berlin: de Gruyter.
Rsvik, K-A. (2002). The Secrets of the Winners: Management Ideas that Flow.
In K. Sahlin-Andersson, & L. Engwall (Eds.), The Expansion of Management
Knowledge: Carriers, Flows and Sources. Stanford: Stanford University Press
Sabatier, P.A., & Mazmanian, D.A. ( 1 ~ 8 1 )The
. implementation of public
policy. In P.A. Sabatier, & D.A. Mazmanian (Eds.), Effective Policy Imple-
mentation (pp. 3-3 5 ) . Toronto: Lexington Books.
Sacks, H. (1992). Lectures on Conversation. Vol. 1-11, Oxford: Blackwell.
Sahlin, I., Ed. (1996). Projektets paradoxer. Lund: Studentlitteratur.
Sahlin-Anderson, K. (1986). Beslutsprocessens komplexitet. Lund: Doxa.
Sahlin-Andersson, K. (1989). Oklarhetens strategi. Lund: Studentlitteratur.
Sahlin-Andersson, K. (1990). Forskningsparker och foretagsrelationer. Stock-
holm: Regionplane- och trafikkontoret.
Sahlin-Andersson, K. (1994). Group identities as the building block of organ-
izations. A story about nurses daily work, Scandinavian Journal of Manage-
ment, 10(z), June, 1994.
Sahlin-Andersson, K. (1996). 1 styrbarhetens utmarker. In I. Sahlin (Ed.), Pro-
lektets paradoxer, Lund: Studentlitteratur.
Sahlin-Andersson, K. (1998). The social construction of projects. A case study
of organizing of an extraordinary building project - the Stockholm Globe
Arena. In N. Brunsson, & J.P Olsen (Eds.), Organizing Organizations. Oslo:
Fagbokforlaget.
Sahlin-Andersson, K., & Engwall, L. (Eds.), (2002). The Expansion of Man-
agement Knowledge: Carriers, Flows and Sources. Stanford: Stanford Univer-
sity Press.
Sahlin-Andersson, K., & Soderholm, A. (1987). Visionen om framtidens
Sodertorn - en studie av ett regionalt utvecklingsprojekt. Stockholm: BFR
Saloner, G., & Spence, A.M. (zooz). Creating and Capturing Value - Per-
spectives and Cases on Electronic Commerce. USA: John Wiley & Sons Inc.
SCB AMLA Tabell 11. Lonespridning och genomsnittlig mdnadslon efter
yrkesgrupp och kon zooo.
Schon, D.A. (1971). Beyond the Stable State. New York: Random House.
Schulz, M. (2001). The uncertain relevance of newness: organizational lear-
ning and knowledge flows, Academy of Management Journal, 44(4), 661-
681.
Schulz, M., & Jobe, L.A. (2001). Codification and tacitness as knowledge
management strategies: an empirical exploration, Journal of High technology
Management Research, I ~ ( I )I,3 9-1 65.
Schumpeter, J.A. (1942). Capitalism, Socialism and Democracy. New York:
Harper.
Schon, D. (1983). The reflect.ive practitioner - how professionals think in
action. Aldershot: Avebury.
Scott, W.R. (1995). Institutions and Organizations. Thousand Oaks, CA:
Sage.
Scott, W.R. (1998) Organizations: Rational, Natural, and Open Systems.
Upper Saddle River, NJ: Prentice Hell. 4 h edition.
Scott, W.R., & Meyer, J.W. and Associates (1994) Institutional envirotrrnerzts
and organizations. Structural complexity and individualism. Thousand Oaks:
CA Sage.
Scott, W.R., Ruef M., Mendel P.J., & Caronna C.A. (2000). Institutional
Change and Healthcare Organizations: From Professional Dominance to
Managed Care. Chicago: University of Chicago Press.
Selander, S. (Ed.). (1989). Kampen om yrkesutovning, status och kunskap.
Professionaliseringens sociala grund. Lund: Studentlitteratur.
Seldkn, L. (Ed.). (1992). Biblioteket och framtiden. Goteborg: Ccntrum for
biblioteksforskning.
Selin, G. (1990). Att hantera projekt vid produktutveckling. Stockholm: Sve-
riges Mekanforbund.
Selin, G., & Selin, M. (1992). Reason for project management failure zn mul-
tiproject environment using matrix organization. Paper presented at the Pro-
ceedings of 11th International Project Management Congress INTERNET,
Florence.
Selznick, P. ( ~ 9 4 9 )TVA
. and the Grassroots. A study of the sociology of for-
mal organizations. Berkeley, CA: University of California Press.
Selznick, P. (1957), Leadership in Administration. A sociological interpreta-
tion. New York: Harper & Row.
Shenhar, A.J. (2007). One size does not fit all projects: exploring classical con-
tingency domains, Management Science, 47(3), 394-414.
Silverman, D. (1998). Harvey Sacks - Social Science & Conversation analysis.
Cambridge: Polity Press.
Simon, H. (1957). Administrative behavior. New York: The Free Press.
Singelman, J. (1978). From Agriculture to Services. London: Sage.
Sjogren Kallqvist, A. (2002). Projektledning frdn ovan, Stockholm: Royal
Institute of Technology.
Sjostrand, S-E. (Ed.), (1993). Institutional Change. Theory and Empirical Fin-
dings, New York: Sharpe.
Sobek, D.K., Liker, J.K., & Ward, A.C. (1998). Another look at how Toyota
integrates product development, Engineering Management Review, 26(4), 69-
78.
Solli, R., & Czarniawska, C. (Eds.). (2001). Modernisering av storstaden.
Marknad och management i stora stader vid sekelskiftet. Malm6: Liber forlag.
Standish Group. ( ~ 9 9 9 )Chaos:
. A recipe for success.
Stern, L.W., & Craig, C.S., (1971). Interorganizational data systems: The
computer and distribution, Journal of Retailing, 47(2), 73-91.
Stinchcombe, A.L. (1985) Contracts as hierarchical documents. In A.L.
Stinchcombe & C.A. Heimer (Eds.), Organization theory and project man-
agement. Oslo: Norwegian University Press.
Stockport, G.J. & Chaddad, F.R. (2001). FOCUS not Magic: Fast Growth a t
Juniper Networks. Graduate School of Management University of Western
Australia.
Stoner, J.A.F., (1968). Risky and cautius shifts in group decisions: the influen-
ce of widely held values. Journal of Experimental Social Psychologyc. 4,
Strang, D., & Meyer J.W. (1994) Institutional Conditions for Diffusion. In
W.R. Scott & J.W. Meyer (Eds). Institutional Environments and Organiza-
tions. Structural Complexity and lndtvidualism (TOO-112). London: Sage
Suddaby, R., & Greenwood, R. (1999). Colonizing Knowledge: Commodifi-
cation as a Dynamic of Jurisdictio~~al Expansion in Professional Business
Advisory Firms. Paper presented at the Scancor seminar Carrzers of Manage-
ment Knowledge, Stanford, September 1999.
Sundin, E. (1995). Teknik och organisation i teori och praktik. Stockholm:
Nerenius & Santirus.
Sundin, E. (1997). Den offentliga sektorns omvandling och kvinnors och mans
fiiretagande inorn typiskt kvinnliga sektorer. SOU 1997:83. O m makt och kon
I spdren av offentliga sektorns omvandling. Stockholm: Fritzes.
Sundin, E. (2000). Bibliotekarien som startade eget - ett exernpel pd det
mesta. Orebro: FSF.
Sundin, E. (2002). Foretagandets manliga pragling - orsaker och konsekven-
ser. In C. Holmquist, & E. Sundin (Eds.), Foretagerskan. Om kvinnor och en-
trepreniirskap. Stockholm: SNS forlag.
Sundin, E., & Holmcjuist, C. (1990). Kvinnor som foretagare. Osynlighet,
mdngfald, anpassning. Malmo: Liberg.
Sundin, E., & Rapp, G. Staderskorna som forsvann, (forthcoming).
Szulanski, G. (1996). Exploring internal stickiness: impediments to the transfer
of best practice within the firm, Strategic ManagementJournal, 17(10), 27-43.
Soderlund, J. (2000). Temporary organizing - characteristics and control
forms. In R.A. Lundin, & F. Hartman (Eds.), Projects as business constituents
and guiding motives (pp. 6 ~ ~ ~Boston:
4 ) . Kluwer Academic Publishers.
Soderlund, J. (zooob). Time-limited and complex interaction. Studies of
industrial projects. Diss., IMIElDepartment of Management & Economics.
Linkoping university.
Tapscott, D. ( ~ 9 9 9 )Creating
. Value in the Network Economy. Boston, MA: A
Harvard Business Review Book.
Taylor, F.W. (1911). Principles of Scientific Management. New York: Harper
& Row.
Teece, D.J. (1980). Economics of scope and the scope of the enterprise, Jour-
nal of Economic Behavior and Organization, I, 223-247.
Teece, D., & Pisano, G. (1994). The dynamic capabilities of firms: an intro-
duction. Industrial and Corporate Change, 3 ( j ) , 537-556.
Tempest, N. (1999). Cisco Systems, Inc.: Acquisition Integration for Manu-
facturing, Haruard Business School.
Thompson, J.D. (1967). Organizations in Action. New York: McGraw-Hill.
Tjosvold, D. (1988). Cooperative and competitive dynamics within and
between organizational units, Human Relations, 41(6), 425-436.
Toulmin, S. (1991). The dream of an exact language. In B. Goranzon, & M. Flo-
rin (Eds.), Dialogue and technology: Art and knowledge. Berlin: Springer - Verlag
Turner, J.R. (1999). The handbook of project-based management, zmded. Lon-
don: McGraw-Hill.
Turner, J.R., & Cochrane, R.A. (1993). Goals-and methods matrix: Coping
with projects with ill defined goals and/or methods of achieving them, Inter-
national Journal of Project Management, II(+), 93-102.
Tyre, M.J., & Orlikowski, W.J. (1994). Windows of opportunity: Temporal
patterns of technological adaptation in organizations, Organization Science,
5(1), 98-118.
Uzzi, B. (1997). Social structure and competition in interfirm networks: The
paradox of embeddedness, Administrative Science Quarterly, 42(1), 35-67.
Van de Ven, A.H., & Ferry, D.L. (1980). Measuring and Assessing Organiza-
tions. New York: John Wiley and Sons.
Ventura, S.J. (1995). Overarching bodies for coordinating geographic data
sharing at- three levels of government. In H.J. Onsrud, & G. Rushton (Eds.),
Sharing Geographic Information (pp. 172-92). New Brunswick, NJ: Center
for Urban Policy Research.
Vivarelli, M., & Pianta, M. (Eds.). (2000).The Employment Impact of Inno-
vation. London and New York: Routledge.
Von Porat, C. ( 1 9 ~ 6 )PLS
. och FMV - en granskning av ett adrninistrativt
stodsystem. Stockholm: Riksrevisionsverket.
Wallerstedt, E. (2002). From Accounting to Professional Services: The Emer-
gence of a Swedish Auditing Field. In K. Sahlin-Andersson, & L. Engwall
(Eds.), The Expansion of Management Knowledge: Carriers, Flows and Sour-
ces. Stanford: Stanford University Press.
Wanden, S. (r98r). Ekonomiskt tankande. Ett filosofiskt perspektiu. Stock-
holm: P A Norstedts & Soners Forlag.
Waters, D. (1996). Operations Management. Reading, MA: Addison-Wessley.
Weber, M. (1947). The Theory of Social and Economic Organization. Lon-
don: Oxford University Press.
Weick, K.E. (1979). The social psychology of organizing. (2nd ed). Reading,
MA: Addison-Wesley.
Weick, K.E. (1991). Sensemaking in Organizations. Thousand Oaks: Sage.
Weick, K.E. (1996). Enactment and the boundaryless career: Organizing as we
work. In M.B. Arthur, & D.M. Rousseau, (Eds.), The boundaryless career. A
new employment prtnciple for a new organizational era. New York: Oxford
University Press.
Weick, K.E., & Westley, F. (1996). Organizational learning: Affirming an oxy-
moron. In S.R. Clegg, C. Hardy, & W.R. Nord (Eds.), Handbook of Organi-
zation Studies. London: Sage.
Weil, B. (1999). Conception collective, coordination et savoirs. Les rationali-
sations de la conception automobile. Phd Thesis, ~ c o l eNationale Suptrieure
des Mines de Paris, Paris.
Wheelwright, S.C., & Clark, K.B. ( ~ y y z a )Creating
. project plans to focus
product development. Harvard Business Review, (March-April), 70-82.
Wheelwright, S.C., & Clark, K.B. (199 zb). Revolutionizing product develop-
ment. New York: Free Press.
Whipp, R., Adam, B., & Sabelis, 1. (Eds.) (2002). Making Time: Time and
Management zn Modern Organizations. Oxford: Oxford University Press.
Whittington, R., Pettigrew, A., Peck, S.L, Fenton, E.M., & Conyon, M.
( 1 ~ 9 9 )Change
. and Complementarities in the New Competitive Landscape: a
European Panel Study 1992-1796, Organization Science, 10,583-600.
Wilson, H.T. (1977). The American Ideology: Science, Technology and Organ-
ization as Modes of Rationality in Advanced Industrial Societies. London:
Routledge & Kegan Paul.
Wilson, T.L., & Anell, B.I. (2001). Project management as a competitive pre-
script: 85 years of experience at Boeing, Journal of Global Competitiveness,
9(1), 184-193.
Womack, J.P., Jones, D.T., & Roos, D. (1990) The Machine that Changed the
World. New York: MacMillen.
Woodward, J. (1965). Industrial Organization: Theory and Practice. London:
Oxford University Press.
Zander, U. & Kogut, B. (1995). Knowledge and the speed of the transfer and
imitation of organizational capabilities: an empirical test, Organization Scien-
ce, 6(1),76-92.
Aberg, A. (1979). Fr5n Luther till Libris - folkbibliotekens historia i Sverige,
Forr och nu, 4.
ostergren, K., & Miillern, T. (1995). Larandekulturer. UmeP: Umea Universi-
tets Tryckeri.
Ostgota Correspondenten 18.8 1993.
Author presentations
Eskil Ekstedt is professor at the National Institute for Working Life and
the School of Business, Stockholm University. His research has been in
the field of economic and organisational development and its relation-
ship with knowledge formation. At present the focus is on local trans-
formation of business and working life. Co-author of "Neo-Industrial
Organising" (Routledge, 1999).
We have edited this book as a way of showing our appreciation for Rolf A Lundin on his 60'~
birthday. Rolf's research and theorizing has truly inspired all chapters in this volume. For this
reason it seems natural t o include a presentation of professor Rolf A Lundin among the author
presentations.
AUTHOR PRESENTATION