MEDIDAS
Part. N° DESCRIPCIÓN Und CANT # VECES PARCIAL TOTAL
LARGO ANCHO ALTO
01.00.00.00 PRIMER PISO
01.01.00.00 ESTRUCTURA
01.01.01.00 TRABAJOS PRELIMINARES
01.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 234.00
1.00 1.00 40.00 5.85 234.00
MEDIDAS
Part. N° DESCRIPCIÓN Und CANT # VECES PARCIAL TOTAL
LARGO ANCHO ALTO
EJE F-F 1.00 1.00 2.85 0.25 0.20 0.14
EJE H-H 1.00 1.00 3.85 0.25 0.20 0.19
EJE I-I 1.00 1.00 2.18 0.40 0.20 0.17
1.00 1.00 0.68 0.25 0.20 0.03
ENTRE EJE A-A Y B-B 2.00 1.00 2.49 0.25 1.90 2.37
ENTRE EJE B-B Y C-C 2.00 1.00 2.53 0.25 1.90 2.40
1.00 1.00 3.65 0.25 0.20 0.18
1.00 1.00 2.38 0.25 0.20 0.12
1.00 1.00 1.40 0.25 0.20 0.07
ENTRE EJE C-C Y D-D 2.00 1.00 2.85 0.25 1.90 2.71
1.00 1.00 3.11 0.25 0.20 0.16
1.00 1.00 0.90 0.40 0.20 0.07
1.00 1.00 1.65 0.25 0.20 0.08
ENTRE EJE D-D Y E-E 2.00 1.00 2.85 0.25 1.90 2.71
1.00 1.00 2.30 0.25 0.20 0.12
1.00 1.00 0.90 0.40 0.20 0.07
ENTRE EJE E-E Y F-F 2.00 1.00 2.85 0.25 1.90 2.71
1.00 1.00 5.55 0.25 0.20 0.28
1.00 1.00 2.93 0.25 0.20 0.15
1.00 1.00 2.00 0.40 0.20 0.16
ENTRE EJE F-F Y G-G 2.00 1.00 2.97 0.25 1.90 2.82
1.00 1.00 1.25 0.25 0.20 0.06
1.00 1.00 1.18 0.25 0.20 0.06
ENTRE EJE G'-G' Y G''-G'' 2.00 1.00 2.04 0.25 0.20 0.20
ENTRE EJE G''-G'' Y H-H 2.00 1.00 2.04 0.25 0.20 0.20
ENTRE EJE H-H Y H'-H' 2.00 1.00 2.94 0.25 0.20 0.29
ENTRE EJE H'-H' Y I-I 2.00 1.00 2.69 0.25 0.20 0.27
ELEMENTO CONCRETO
Part. Nº METRADO PARCIAL TOTAL
DESCRIPCIÓN
UND. CANT. # VECES L A H
01.01.03.00 OBRAS DE CONCRETO SIMPLE
01.01.03.01 CONCRETO f'c=100 kg/cm2 PARA SOLADOS m2 26.60
ZAPATAS
EJE A-A 3.00 1.20 1.20 4.32
EJE B-B 2.00 1.20 1.20 2.88
EJE C-C 2.00 1.20 1.20 2.88
EJE D-D 2.00 1.20 1.20 2.88
EJE E-E 2.00 1.20 1.20 2.88
EJE F-F 2.00 1.20 1.20 2.88
EJE G-G 2.00 1.20 1.20 2.88
EJE G'-G' 2.00 1.00 1.00
EJE G''-G'' 2.00 1.00 1.00
EJE H-H 2.00 1.00 1.00 2.00
EJE H'-H' 2.00 1.00 1.00
EJE I-I 3.00 1.00 1.00 3.00
01.01.03.03 CONCRETO f'c=140 Kg/cm2 +30% P.G. (T.M. 6") PARA CIMIENTOS CORRIDOS m3 34.71
EJE A-A 2.00 1.00 2.55 0.50 0.60 1.53
EJE B-B 1.00 1.00 5.05 0.40 0.60 1.21
EJE C-C 1.00 1.00 5.05 0.40 0.60 1.21
EJE F-F 1.00 1.00 4.05 0.40 0.60 0.97
EJE H-H 1.00 1.00 5.05 0.40 0.60 1.21
EJE I-I 1.00 1.00 5.10 0.40 0.60 1.22
ENTRE EJE A-A Y B-B 2.00 1.00 3.92 0.50 0.60 2.35
ENTRE EJE B-B Y C-C 2.00 1.00 3.80 0.50 0.60 2.28
1.00 1.00 3.65 0.40 0.60 0.88
1.00 1.00 2.38 0.40 0.60 0.57
1.00 1.00 1.40 0.40 0.60 0.34
ENTRE EJE C-C Y D-D 2.00 1.00 3.80 0.50 0.60 2.28
1.00 1.00 1.08 0.40 0.60 0.26
1.00 1.00 2.03 0.40 0.60 0.49
1.00 1.00 2.55 0.40 0.60 0.61
ENTRE EJE D-D Y E-E 2.00 1.00 3.80 0.50 0.60 2.28
1.00 1.00 2.30 0.40 0.60 0.55
ENTRE EJE E-E Y F-F 2.00 1.00 3.80 0.50 0.60 2.28
1.00 1.00 6.73 0.40 0.60 1.62
1.00 1.00 1.25 0.40 0.60 0.30
1.00 1.00 3.55 0.40 0.60 0.85
ENTRE EJE F-F Y G-G 2.00 1.00 4.40 0.50 0.60 2.64
1.00 1.00 1.25 0.40 0.60 0.30
1.00 1.00 1.18 0.40 0.60 0.28
ENTRE EJE G'-G' Y G''-G'' 2.00 1.00 3.09 0.40 0.60 1.48
ENTRE EJE G''-G'' Y H-H 2.00 1.00 2.72 0.40 0.60 1.31
ENTRE EJE H-H Y H'-H' 2.00 1.00 3.61 0.40 0.60 1.73
ENTRE EJE H'-H' Y I-I 2.00 1.00 3.49 0.40 0.60 1.68
01.01.03.04 CONCRETO F’c=140 Kg/cm2 + 25% P.M (T.M. 3”) PARA SOBRECIMIENTOS m3 4.61
EJE B-B 1.00 1.00 3.25 0.15 0.45 0.22
EJE C-C 1.00 1.00 3.20 0.15 0.45 0.22
EJE F-F 1.00 1.00 3.90 0.15 0.45 0.26
EJE H-H 1.00 1.00 4.05 0.15 0.45 0.27
EJE I-I 1.00 1.00 0.68 0.15 0.45 0.05
ENTRE EJE B-B Y C-C 1.00 1.00 3.90 0.15 0.45 0.26
1.00 1.00 2.50 0.15 0.45 0.17
1.00 1.00 1.65 0.15 0.45 0.11
ENTRE EJE C-C Y D-D 1.00 1.00 1.90 0.15 0.45 0.13
1.00 1.00 2.30 0.15 0.45 0.16
1.00 1.00 1.20 0.15 0.45 0.08
ENTRE EJE D-D Y E-E 1.00 1.00 2.30 0.15 0.45 0.16
ENTRE EJE E-E Y F-F 1.00 1.00 2.65 0.15 0.45 0.18
1.00 1.00 5.40 0.15 0.45 0.36
1.00 1.00 0.75 0.15 0.45 0.05
ENTRE EJE F-F Y G-G 1.00 1.00 1.60 0.15 0.45 0.11
1.00 1.00 1.30 0.15 0.45 0.09
ENTRE EJE G'-G' Y G''-G'' 2.00 1.00 3.09 0.15 0.45 0.42
ENTRE EJE G''-G'' Y H-H 2.00 1.00 2.72 0.15 0.45 0.37
ENTRE EJE H-H Y H'-H' 2.00 1.00 3.61 0.15 0.45 0.49
ENTRE EJE H'-H' Y I-I 2.00 1.00 3.49 0.15 0.45 0.47
ELEMENTO CONCRETO
Part. Nº METRADO PARCIAL TOTAL
DESCRIPCIÓN
UND. CANT. # VECES L A H
EJE H-H 1.00 2.00 4.05 0.45 3.65
EJE I-I 1.00 2.00 0.68 0.45 0.61
ENTRE EJE B-B Y C-C 1.00 2.00 3.90 0.45 3.51
1.00 2.00 2.50 0.45 2.25
1.00 2.00 1.65 0.45 1.49
ENTRE EJE C-C Y D-D 1.00 2.00 1.90 0.45 1.71
1.00 2.00 2.30 0.45 2.07
1.00 2.00 1.20 0.45 1.08
ENTRE EJE D-D Y E-E 1.00 2.00 2.30 0.45 2.07
ENTRE EJE E-E Y F-F 1.00 2.00 2.65 0.45 2.39
1.00 2.00 5.40 0.45 4.86
1.00 2.00 0.75 0.45 0.68
ENTRE EJE F-F Y G-G 1.00 2.00 1.60 0.45 1.44
1.00 2.00 1.30 0.45 1.17
ENTRE EJE G'-G' Y G''-G'' 2.00 2.00 3.09 0.45 5.56
ENTRE EJE G''-G'' Y H-H 2.00 2.00 2.72 0.45 4.90
ENTRE EJE H-H Y H'-H' 2.00 2.00 3.61 0.45 6.50
ENTRE EJE H'-H' Y I-I 2.00 2.00 3.49 0.45 6.28
HOJA DE METRADOS ACERO
01.01.04.03 COLUMNAS
01.01.04.03.01 CONCRETO F'c=210 KG/CM2 EN COLUMNAS m3 15.59
01.01.04.03.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2
COLUMNA C-1 20.00 1.00 0.40 0.25 5.80 11.60 20.00
01.01.04.04 VIGAS
01.01.04.04.01 CONCRETO F'c=210 KG/CM2 EN VIGAS m3 11.21
01.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2
EJE A-A
VP-01 (0.25 X 0.45) 2.00 1.00 2.55 0.25 0.45 0.57 2.00 1.00
EJE B-B
VP-01 (0.25 X 0.45) 1.00 1.00 5.05 0.25 0.45 0.57 1.00 1.00
EJE C-C
VP-01 (0.25 X 0.45) 1.00 1.00 5.05 0.25 0.45 0.57 1.00 1.00
EJE D-D
VP-01 (0.25 X 0.45) 1.00 1.00 5.05 0.25 0.45 0.57 1.00 1.00
EJE E-E
VP-01 (0.25 X 0.45) 1.00 1.00 5.05 0.25 0.45 0.57 1.00 1.00
EJE F-F
VP-01 (0.25 X 0.45) 1.00 1.00 5.05 0.25 0.45 0.57 1.00 1.00
EJE G-G
VP-01 (0.25 X 0.45) 1.00 1.00 5.05 0.25 0.45 0.57 1.00 1.00
HOJA DE METRADOS ESTRUCTURA
ENCOFRADO
METRADO TOTAL
L A(H)/AREA m2
229.42
ENCOFRADO
METRADO TOTAL
L A(H)/AREA m2
3.80 1.90 28.88
3.80 0.30 4.56
4.40 1.90 33.44
4.40 0.30 5.28
205.90
1.30 5.80 150.80
90.35
ENCOFRADO
METRADO TOTAL
L A(H)/AREA m2
115.32
12.02 2.05 24.64
5.60 2.15 12.04
METRADOS ESTRUCTURA
ENCOFRADO
METRADO TOTAL
L A(H)/AREA m2
3.15 2.55 8.03
3.92 2.00 7.84
19.35 1.90 36.77
24.76 1.05 26.00
12.37
0.90 0.60 3.24
0.96 0.60 0.58
2.85 1.10 6.27
2.85 0.50 1.43
2.85 0.30 0.86
METRADOS ESTRUCTURA
ENCOFRADO
METRADO TOTAL
L A(H)/AREA m2
HOJA DE METRADOS DE ARQUITECTURA
VANOS O DISMINUCIONES
PARCIAL TOTAL
ANCHO ALTO
344.07
VANOS O DISMINUCIONES
PARCIAL TOTAL
ANCHO ALTO
HOJA DE METRADOS DE ARQUITECTURA
Nº DIMENSIONES NUMERO
PART. N° DESCRIPCION UND. CANT. PARCIAL CANT.
DE VECES LARGO ANCHO/AREA ALTO DE VECES
01.02.02.00 REVOQUES, ENLUCIDOS Y MOLDURAS
01.02.02.01 TARRAJEO RAYADO PRIMARIO m2
CONTRAZÓCALO
1.00 1.00 138.20 0.10 13.82
ZÓCALO
SS.HH. 01 1.00 1.00 3.50 2.00 7.00
SS.HH. 02 1.00 1.00 1.90 2.00 3.80
SS.HH. 03 1.00 1.00 2.00 2.00 4.00
COCINA 1.00 1.00 2.20 0.55 1.21
EJE C-C INTERIOR 2.00 1.00 1.90 2.75 10.45 1.00 1.00
2.00 1.00 1.30 1.75 4.55
EJE F-F INTERIOR 2.00 1.00 4.05 2.75 22.28 2.00 1.00
ENTRE EJE A-A Y B-B INTERIOR 2.00 1.00 3.92 2.85 22.34
ENTRE EJE B-B Y C-C INTERIOR 2.00 1.00 3.90 2.85 22.23
2.00 1.00 4.05 3.00 24.30 2.00 1.00
2.00 1.00 1.65 3.00 9.90
2.00 1.00 2.50 3.00 15.00 1.00 1.00
ENTRE EJE C-C Y D-D INTERIOR 2.00 1.00 3.80 2.85 21.66
2.00 1.00 1.20 3.00 7.20
2.00 1.00 1.90 3.00 11.40
2.00 1.00 2.30 3.00 13.80
ENTRE EJE D-D Y E-E INTERIOR 2.00 1.00 3.80 2.85 21.66
2.00 1.00 2.30 3.00 13.80
ENTRE EJE E-E Y F-F INTERIOR 2.00 1.00 3.80 2.85 21.66 1.00 1.00
2.00 1.00 4.90 3.00 29.40
2.00 1.00 2.65 3.00 15.90 2.00 1.00
2.00 1.00 0.75 3.00 4.50
ENTRE EJE F-F Y G-G INTERIOR 2.00 1.00 4.40 2.85 25.08
2.00 1.00 1.60 1.00 3.20
2.00 1.00 1.20 3.00 7.20 2.00 1.00
2.00 3.00 0.90 3.00 16.20
2.00 1.00 1.90 3.00 11.40
2.00 1.00 0.50 3.00 3.00
VANOS O DISMINUCIONES
PARCIAL TOTAL
LARGO ANCHO ALTO
29.83
455.80
Part. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGO ANCHO/AREA ALTO
01.02.02.03 TARRAJEO DE COLUMNAS MEZCLA 1:5, E=1.50 CM m2
49.37
EJE A-A
C-2 1.00 2.00 0.20 2.85 1.14
1.00 1.00 0.45 2.75 1.24
EJE B-B
C-1 1.00 1.00 0.60 2.85 1.71
1.00 1.00 0.75 2.85 2.14
EJE C-C
C-1 1.00 1.00 0.60 2.85 1.71
1.00 1.00 0.75 2.85 2.14
EJE D-D
C-1 1.00 2.00 0.75 2.85 4.28
EJE E-E
C-1 1.00 2.00 0.75 2.85 4.28
EJE F-F
C-1 1.00 1.00 0.60 2.85 1.71
1.00 1.00 0.75 2.85 2.14
EJE G-G
C-1 1.00 2.00 0.75 2.85 4.28
EJE G'-G'
C-1 1.00 2.00 0.50 2.85 2.85
EJE G''-G''
C-1 1.00 2.00 0.60 2.85 3.42
EJE H-H
C-1 1.00 2.00 0.60 3.00 3.60
EJE H'-H'
C-1 1.00 2.00 0.60 3.00 3.60
EJE I-I
C-3 1.00 2.00 0.85 3.00 5.10
1.00 1.00 1.35 3.00 4.05
EJE F-F
C-1 1.00 1.00 2.85 2.85
2.00 1.00 2.85 5.70
EJE G-G
C-1 2.00 2.00 2.85 11.40
EJE G'-G'
C-1 2.00 2.00 2.85 11.40
EJE G''-G''
C-1 2.00 2.00 2.85 11.40
EJE H-H
C-1 2.00 2.00 3.00 12.00
EJE H'-H'
C-1 2.00 2.00 3.00 12.00
EJE I-I
C-3 3.00 2.00 3.00 18.00
3.00 1.00 3.00 9.00
Part. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGO ANCHO/AREA ALTO
2.00 1.00 5.05 0.25 2.53
1.00 1.00 1.00 0.25 0.25
1.00 1.00 4.05 0.15 0.61
EJE G-G
VP-01 ( 0.25 x 0.45 )
2.00 1.00 5.05 0.25 2.53
1.00 1.00 5.05 0.25 1.26
EJE H-H
VP-01 ( 0.25 x 0.45 )
HOJA DE METRADOS DE ARQUITECTURA
Part. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGO ANCHO/AREA ALTO
2.00 1.00 5.05 0.25 2.53
1.00 1.00 5.05 0.25 1.26
ENTRE EJE A-A Y B-B
VS ( 0.25 x 0.35 )
1.00 2.00 3.92 0.15 1.18
1.00 2.00 3.92 0.10 0.78
ENTRE EJE B-B Y C-C
VS ( 0.25 x 0.35 )
1.00 2.00 3.80 0.15 1.14
1.00 2.00 3.80 0.10 0.76
V.CH. ( 0.25 x 0.20 )
1.00 2.00 3.80 0.25 1.90
1.00 1.00 2.00 0.25 0.50
ENTRE EJE C-C Y D-D
VS ( 0.25 x 0.35 )
1.00 2.00 3.80 0.15 1.14
1.00 2.00 3.80 0.10 0.76
ENTRE EJE D-D Y E-E
VS ( 0.25 x 0.35 )
1.00 2.00 3.80 0.15 1.14
1.00 2.00 3.80 0.10 0.76
V.CH. ( 0.25 x 0.20 )
1.00 1.00 3.80 0.25 0.95
1.00 1.00 1.90 0.25 0.48
ENTRE EJE E-E Y F-F
VS ( 0.25 x 0.35 )
1.00 2.00 3.55 0.15 1.07
1.00 2.00 3.55 0.10 0.71
ENTRE EJE F-F Y G-G
VS ( 0.25 x 0.35 )
1.00 2.00 4.40 0.15 1.32
1.00 2.00 4.40 0.10 0.88
V.CH. ( 0.25 x 0.20 )
1.00 2.00 4.40 0.25 2.20
1.00 1.00 2.30 0.25 0.58
ENTRE EJE G'-G' Y G''-G''
VS ( 0.25 x 0.35 )
1.00 2.00 3.09 0.60 3.71
1.00 2.00 3.09 0.10 0.62
V.CH. ( 0.25 x 0.20 )
1.00 2.00 1.00 0.25 0.50
1.00 1.00 3.95 0.25 0.99
ENTRE EJE G''-G'' Y H'-H'
VS ( 0.25 x 0.35 )
1.00 2.00 2.72 0.60 3.26
1.00 2.00 2.72 0.10 0.54
EJE F-F
VP-01 ( 0.25 x 0.45 )
2.00 1.00 2.00 4.00
1.00 1.00 3.05 3.05
EJE G-G
VP-01 ( 0.25 x 0.45 )
2.00 1.00 5.05 10.10
EJE H'-H'
VP-01 ( 0.25 x 0.45 )
4.00 1.00 5.05 20.20
ENTRE EJE A-A Y B-B
VS ( 0.25 x 0.35 )
1.00 2.00 3.92 7.84
ENTRE EJE B-B Y C-C
VS ( 0.25 x 0.35 )
1.00 2.00 3.80 7.60
V.CH. ( 0.25 x 0.20 )
1.00 3.00 2.00 6.00
Part. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGO ANCHO/AREA ALTO
01.02.03.00 CIELORRASOS
01.02.03.01 CIELORRASO CON MEZCLA DE CEMENTO-ARENA C:A 1:4 m2 115.32
1.00 1.00 115.32 115.32
01.02.05.00 CONTRAZÓCALOS
01.02.05.01 CONTRAZÓCALO DE CERAMICO, H=10cm, INTERIOR m 138.20
1.00 1.00 138.20 138.20
01.02.06.00 ZÓCALOS
01.02.06.01 ZÓCALO DE CERAMICO SAN LORENZO ESCENZAFORTE BEIGE 0.36X0.36 m2 14.80
SS.HH. 01 1.00 1.00 3.50 2.00 7.00
SS.HH. 02 1.00 1.00 1.90 2.00 3.80
SS.HH. 03 1.00 1.00 2.00 2.00 4.00
Part. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGO ANCHO/AREA ALTO
01.02.07.01 PUERTA DE MADERA P-E1 (0.78X2.90) UND 1.00 1.00 1.00 1.00
01.02.07.02 PUERTA DE MADERA P-E2 (0.85X2.90) UND 1.00 2.00 2.00 2.00
01.02.07.03 PUERTA DE MADERA P-E3 (1.00X2.60) UND 1.00 1.00 1.00 1.00
01.02.07.04 PUERTA DE MADERA P-E4 (0.80X2.90) UND 1.00 1.00 1.00 1.00
01.02.07.05 PUERTA DE MADERA P-1 (1.00X2.40) UND 1.00 1.00 1.00 1.00
01.02.07.06 PUERTA DE MADERA P-2 (1.00X2.85) UND 1.00 1.00 1.00 1.00
01.02.07.07 PUERTA DE MADERA P-3 (0.70X3.00) UND 1.00 1.00 1.00 1.00
01.02.07.08 PUERTA DE MADERA P-4 (0.80X3.00) UND 1.00 1.00 1.00 1.00
01.02.07.09 PUERTA DE MADERA P-5 (0.90X3.00) UND 1.00 1.00 1.00 1.00
01.02.09.00 VIDRIOS
01.02.09.01 MAMPARA DE VIDRIO PM-1 (3.27X2.85) und 1.00
1.00 1.00 1.00
01.02.10.00 PINTURA
01.02.10.01 PINTURA LATEX 2 MANOS, EN CIELORRASOS m2 115.32
1.00 1.00 115.32 115.32
01.02.10.02 PINTURA LATEX 2 MANOS, EN MUROS INTERIORES COLOR BLANCO HUMO m2 455.80
1.00 1.00 455.80 455.80
PART. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGO ANCHO ALTO
01.03.00.00 INSTALACIONES SANITARIAS (PRIMER PISO)
01.03.01.03 SALIDA DE PVC PARA DESAGÜE Pto 1.00 7.00 7.00 7.00
01.03.01.04 SALIDA DE PVC PARA VENTILACION 2" Pto 1.00 4.00 4.00 4.00
01.03.02.02 SUMINISTRO E ISTALACION DE TANQUE ELEVADO Pto 1.00 1.00 1.00 1.00
PART. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGO ANCHO ALTO
01.03.02.03 VALVULA COMPUERTA ESFERICA DE UNION ROSCADA DE 1" Und 1.00 1.00 1.00 1.00
01.03.02.04 VALVULA COMPUERTA ESFERICA DE UNION ROSCADA DE 3/4" Und 1.00 2.00 2.00 2.00
01.03.02.05 VALVULA COMPUERTA ESFERICA DE UNION ROSCADA DE 1/2" Und 1.00 5.00 5.00 5.00
PART. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGO ANCHO ALTO
01.04.00.00 INSTALACIONES ELECTRICAS
01.04.01.00 SALIDAS
01.04.01.01 SALIDA PARA CENTROS DE LUZ Pto 1.00 29.00 29.00 29.00
01.04.01.02 SALIDA PARA TOMACORRIENTE DOBLE C/LINEA DE TIERRA Pto 1.00 30.00 30.00 30.00
01.04.03.02 TUBERIA PVC SAP ELECTRICAS 25mm m 1.00 86.39 86.39 86.39
PART. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGO ANCHO ALTO
01.04.06.00 ARTEFACTOS ELECTRICOS
COLUMNA C-2 2.00 1.00 0.25 0.25 3.20 0.40 1.00 1.00 3.20 3.20
02.01.01.02 VIGAS
02.01.01.02.01 CONCRETO F'c=210 KG/CM2 EN VIGAS m3 3.77
02.01.01.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 20.72
EJE E-E, E'-E', F-F, G-G
VP-01 ( 0.25 X 0.45 ) 2.00 1.00 5.05 0.25 0.45 1.14 1.00 1.00 5.05 1.15 5.81
1.00 1.00 5.35 0.25 0.45 0.60 1.00 1.00 5.35 1.15 6.15
ENTRE EJE E'-E' Y F-F
V.S. ( 0.25 x 0.35 ) 2.00 1.00 1.65 0.25 0.35 0.29 1.00 1.00 1.65 0.95 1.57
ENTRE EJE F-F Y G-G
V.S. ( 0.25 x 0.35 ) 2.00 1.00 4.40 0.25 0.35 0.77 1.00 1.00 4.40 0.95 4.18
V.CH. ( 0.25 x 0.20 ) 1.00 2.00 4.40 0.25 0.35 0.77 1.00 1.00 4.40 0.45 1.98
V.CH. ( 0.25 x 0.20 ) 1.00 1.00 2.30 0.25 0.35 0.20 1.00 1.00 2.30 0.45 1.04
02.02.00.00 ARQUITECTURA
02.02.01.00 MUROS Y TABIQUES DE ALBAÑILERÍA
02.02.01.01 MURO DE SOGA CON LADRILLO PANDERETA m2 150.93
ASENTADO CON MORTERO C:A 1:4
Part. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGOANCHO/AREA ALTO
02.02.02.03 TARRAJEO DE COLUMNAS MEZCLA 1:5, E=1.50 CM m2
31.67
EJE C-C
C-1 1.00 2.00 1.00 3.20 6.40
EJE D-D
C-1 1.00 2.00 0.85 5.07 8.62
EJE E-E
C-1 1.00 2.00 1.15 3.70 8.51
EJE F-F, G-G, H-H
C-1 3.00 2.00 1.00 1.10 6.60
EJE I-I
C-2 1.00 2.00 0.70 1.10 1.54
02.02.03.00 CIELORRASOS
02.02.03.01 CIELORRASO CON MEZCLA DE CEMENTO-ARENA C:A 1:4 m2 16.46
1.00 1.00 16.46 16.46
02.02.05.00 CONTRAZÓCALOS
02.02.05.01 CONTRAZÓCALO DE CERAMICO, H=10cm, INTERIOR m 14.45
1.00 1.00 14.45 14.45
02.02.07.00 PINTURA
02.02.07.01 PINTURA LATEX 2 MANOS, EN CIELORRASOS m2 16.46
1.00 1.00 16.46 16.46
02.02.07.02 PINTURA LATEX 2 MANOS COLOR BLANCO HUMO, EN MUROS INTERIORES m2 248.53
INTERIORES 1.00 1.00 248.53 248.53
PART. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGO ANCHO ALTO
02.03.00.00 INSTALACIONES SANITARIAS (PRIMER PISO)
02.03.01.00 SISTEMA DE DESAGÜE
02.03.01.01 SALIDA DE PVC PARA DESAGÜE Pto 1.00 6.00 6.00 6.00
02.03.01.02 SALIDA DE PVC PARA VENTILACION 2" Pto 1.00 3.00 3.00 3.00
02.03.02.02 VALVULA COMPUERTA ESFERICA DE UNION ROSCADA DE 3/4" Und 1.00 1.00 1.00 1.00
PART. Nº DE MEDIDAS
DESCRIPCIÓN Und CANT PARCIAL TOTAL
Nº VECES LARGO ANCHO ALTO
02.04.00.00 INSTALACIONES ELECTRICAS
02.04.01.00 SALIDAS
02.04.01.01 SALIDA PARA CENTROS DE LUZ Pto 1.00 7.00 7.00 7.00
02.04.01.02 SALIDA PARA TOMACORRIENTE DOBLE C/LINEA DE TIERRA Pto 1.00 7.00 7.00 7.00
02.04.03.02 TUBERIA PVC SAP ELECTRICAS 25mm m 1.00 7.80 7.80 7.80