Activity ID Activity Name Remaining Start Finish 2013 2014 015

Duration Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec an
TTCL & TVC 215 19-Aug-13 14-Jun-14 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
14-Jun-14, TTCL & TVC
Construction 215 19-Aug-13 14-Jun-14
215 19-Aug-13 14-Jun-14 14-Jun-14, Construction
Instrument
75 19-Aug-13 30-Nov-13 14-Jun-14, Instrument
Pipe Rack
C.TTC.IW.PRP010 Instrument Cable Tray Installation - Pipe Rack 50 19-Aug-13 16-Oct-13 30-Nov-13, Pipe Rack
C.TTC.IW.PRP020 Instrument Cable Laying - Pipe Rack 30 28-Oct-13 30-Nov-13
Beneficaited Phosphate
Phospha Rock Storage & Slurry Stablizing Station (21.1) 106 27-Nov-13 23-Apr-14
C.TTC.IW.PAB010 Instrument Cable Tray/Duct Installation - Beneficaited & Slurry 60 27-Nov-13 11-Feb-14 23-Apr-14, Beneficaited Phosphate Rock Stor
C.TTC.IW.PAB020 Instrument JB Installation - Beneficaited & Slurry 30 27-Jan-14 06-Mar-14
C.TTC.IW.PAB030 Field Instrument & Panel Installation - Beneficaited & Slurry 60 09-Jan-14 24-Mar-14
C.TTC.IW.PAB040 Instrument Cabing from JB to Field Instrument - Beneficaited & Slurry 60 12-Feb-14 23-Apr-14
Reaction Section (21.2) 190 10-Sep-13 02-Jun-14
C.TTC.IW.PAR010 Instrument Cable Tray/Duct Installation - Reaction Section 60 10-Sep-13 18-Nov-13 02-Jun-14, Reaction Section (21.2)
C.TTC.IW.PAR020 Instrument JB Installation - Reaction Section 30 24-Oct-13 27-Nov-13
C.TTC.IW.PAR030 Field Instrument & Panel Installation - Reaction Section 80 17-Jan-14 25-Apr-14
C.TTC.IW.PAR040 Instrument Cabing from JB to Field Instrument - Reaction Section 100 29-Jan-14 02-Jun-14
Filtration Section (21.3) 155 18-Oct-13 22-May-14
C.TTC.IW.PAF010 Instrument Cable Tray/Duct Installation - Filtration Section 60 18-Oct-13 27-Dec-13 22-May-14, Filtration Section (21.3)
C.TTC.IW.PAF020 Instrument JB Installation - Filtration Section 30 22-Nov-13 27-Dec-13
C.TTC.IW.PAF030 Field Instrument & Panel Installation - Filtration Section 80 06-Jan-14 14-Apr-14
C.TTC.IW.PAF040 Instrument Cabing from JB to Field Instrument - Filtration Section 100 18-Jan-14 22-May-14
Concentration Section (21.4) 166 09-Oct-13 28-May-14
C.TTC.IW.PAC010 Instrument Cable Tray/Duct Installation - Concentration Section 60 09-Oct-13 18-Dec-13 28-May-14, Concentration Section (21.4
C.TTC.IW.PAC020 Instrument JB Installation - Concentration Section 30 24-Oct-13 27-Nov-13
C.TTC.IW.PAC030 Field Instrument & Panel Installation - Concentration Section 80 28-Jan-14 08-May-14
C.TTC.IW.PAC040 Instrument Cabing from JB to Field Instrument - Concentration Section 60 17-Mar-14 28-May-14
DAP Product Section ((23.1) 174 09-Oct-13 09-Jun-14
C.TTC.IW.DAP010 Instrument Cable Tray/Duct Installation - DAP Product Section 60 09-Oct-13 17-Dec-13 09-Jun-14, DAP Product Section (23.1
C.TTC.IW.DAP020 Instrument JB Installation - DAP Product Section 30 24-Oct-13 27-Nov-13
C.TTC.IW.DAP030 DCS & Mashalling Installation - DAP Product Section 20 04-Feb-14 26-Feb-14
C.TTC.IW.DAP040 DCS Power On - DAP Product Section (Tempo EE Power) 20 27-Feb-14 21-Mar-14
C.TTC.IW.DAP060 Field Instrument & Panel Installation - DAP Product Section 80 10-Feb-14 16-May-14
C.TTC.IW.DAP070 Instrument Cabing from JB to Field Instrument - DAP Product Section 100 10-Feb-14 09-Jun-14
Bulk DAP Storage (23.
(23.2) 81 24-Jan-14 17-May-14
C.TTC.IW.DAB010 Instrument Cable Tray / Duct Installation - Bulk DAP Storage 40 24-Jan-14 17-Mar-14 17-May-14, Bulk DAP Storage (23.2)

C.TTC.IW.DAB020 Instrument JB Installation - Bulk DAP Storage 20 10-Feb-14 05-Mar-14


C.TTC.IW.DAB030 Field Instrument & Panel Installation - Bulk DAP Storage 40 10-Feb-14 28-Mar-14
C.TTC.IW.DAB040 Instrument Cabing from JB to Field Instrument - Bulk DAP Storage 20 22-Apr-14 17-May-14
DAP Packing & Bage Storage
S (23.3a) 73 20-Feb-14 02-Jun-14
C.TTC.IW.DAS010 Instrument Cable Tray/Duct Installation - DAP Packing & Bage Storage 40 26-Feb-14 14-Apr-14 02-Jun-14, DAP Packing & Bage Stora
C.TTC.IW.DAS020 Instrument JB Installation - DAP Packing & Bage Storage 20 26-Feb-14 20-Mar-14
C.TTC.IW.DAS030 Field Instrument & Panel Installation - DAP Packing & Bage Storage 40 20-Feb-14 07-Apr-14
C.TTC.IW.DAS040 Instrument Cabing from JB to Field Instrument - DAP Packing & Bage Storage 30 26-Apr-14 02-Jun-14
Boiler Station and Sla
Slag Area (19.2) 137 05-Dec-13 14-Jun-14
C.TTC.IW.PGB010 Instrument Cable Tray/Duct Installation - Boiler Station and Slag Area 60 05-Dec-13 20-Feb-14 14-Jun-14, Boiler Station and Slag A
C.TTC.IW.PGB020 Instrument JB Installation - Boiler Station and Slag Area 30 08-Feb-14 14-Mar-14
C.TTC.IW.PGB030 DCS & Mashalling Installation - Boiler Station and Slag Area 30 04-Feb-14 10-Mar-14
C.TTC.IW.PGB040 DCS Power On - Boiler Station and Slag Area 20 27-Mar-14 21-Apr-14
C.TTC.IW.PGB060 Field Instrument & Panel Installation - Boiler Station and Slag Area 80 18-Jan-14 26-Apr-14
C.TTC.IW.PGB070 Instrument Cabing from JB to Field Instrument - Boiler Station and Slag Area 60 03-Apr-14 14-Jun-14
Turbine Generation St
Station (19.3) 102 07-Jan-14 28-May-14
28-May-14, Turbine Generation Station
C.TTC.IW.PGT010 Instrument Cable Tray/Duct Installation - Turbine Generator Station 60 07-Jan-14 22-Mar-14
C.TTC.IW.PGT020 Instrument JB Installation - Turbine Generator Station 20 10-Feb-14 05-Mar-14
C.TTC.IW.PGT030 Field Instrument & Panel Installation - Turbine Generator Station 60 08-Feb-14 19-Apr-14
C.TTC.IW.PGT040 Instrument Cabing from JB to Field Instrument - Turbine Generator Station 40 10-Apr-14 28-May-14
Lab and Control Center
Cente (06) 148 03-Sep-13 27-Mar-14
C.TTC.IW.SUB180 Instrument Cable Tray/Duct Installation - Lab and Control Center 40 03-Sep-13* 18-Oct-13 27-Mar-14, Lab and Control Center (06)
C.TTC.IW.SUB190 Instrument JB Installation - Lab and Control Center 30 24-Oct-13 27-Nov-13
C.TTC.IW.SUB200 DCS & Mashalling Installation - Lab and Control Center 20 24-Jan-14 20-Feb-14
C.TTC.IW.SUB220 Instrument Cable Laying & Terminate - Lab and Control Center 40 13-Jan-14 04-Mar-14
C.TTC.IW.SUB230 DCS Power On - Lab and Control Center (EE from 6 kV Distribution Substation) 20 05-Mar-14 27-Mar-14
Compressed Air Station
Statio (09) 126 19-Aug-13 11-Feb-14
C.TTC.IW.COH010 Instrument Cable Tray/Duct Installation - Compressor House 40 19-Aug-13 04-Oct-13 11-Feb-14, Compressed Air Station (09)
C.TTC.IW.COH020 Instrument JB Installation - Compressor House 30 24-Oct-13 27-Nov-13
C.TTC.IW.COH030 Field Instrument & Panel Installation - Compressor House 50 14-Nov-13 14-Jan-14
C.TTC.IW.COH040 Instrument Cabing from JB to Field Instrument - Compressor House 40 19-Dec-13 11-Feb-14
Demin. Water Station (10) 142 19-Aug-13 04-Mar-14
C.TTC.IW.DEM010 Instrument Cable Tray/Duct Installation - Demin/BFW Facilities 40 19-Aug-13 04-Oct-13 04-Mar-14, Demin. Water Station (10)

C.TTC.IW.DEM020 Instrument JB Installation - Demin/BFW Facilities 30 24-Oct-13 27-Nov-13


C.TTC.IW.DEM030 Field Instrument & Panel Installation - Demin/BFW Facilities 60 13-Nov-13 24-Jan-14
C.TTC.IW.DEM040 Instrument Cabing from JB to Field Instrument - Demin/BFW Facilities 50 30-Dec-13 04-Mar-14
Process Waste Water Treatment Station (11.1) 68 07-Dec-13 12-Mar-14
C.TTC.IW.PWW010 Instrument Cable Tray/Duct Installation - Process Waste Water Treatment 40 07-Dec-13 24-Jan-14 12-Mar-14, Process Waste Water Treatment Station
C.TTC.IW.PWW020 Instrument JB Installation - Process Waste Water Treatment 30 07-Dec-13 13-Jan-14
C.TTC.IW.PWW030 Field Instrument & Panel Installation - Process Waste Water Treatment 40 09-Jan-14 28-Feb-14
C.TTC.IW.PWW040 Instrument Cabing from JB to Field Instrument - Process Waste Water Treatment 30 06-Feb-14 12-Mar-14
Fresh Water Cooling S
Station (14.1) 79 07-Jan-14 28-Apr-14
C.TTC.IW.FRW010 Instrument Cable Tray/Duct Installation - Fresh Water Cooling Tower 40 07-Jan-14 27-Feb-14 28-Apr-14, Fresh Water Cooling Station (14.1
C.TTC.IW.FRW020 Instrument JB Installation - Fresh Water Cooling Tower 30 07-Jan-14 15-Feb-14
C.TTC.IW.FRW030 Field Instrument & Panel Installation - Fresh Water Cooling Tower 40 24-Jan-14 17-Mar-14
C.TTC.IW.FRW040 Instrument Cabing from JB to Field Instrument - Fresh Water Cooling Tower 20 03-Apr-14 28-Apr-14
Acidic Water Cooling S
Station (14.2) 95 25-Dec-13 06-May-14
C.TTC.IW.ACW010 Instrument Cable Tray/Duct Installation - Acidic Water Cooling Tower 40 06-Jan-14 25-Feb-14 06-May-14, Acidic Water Cooling Station (1
C.TTC.IW.ACW020 Instrument JB Installation - Acidic Water Cooling Tower 30 06-Jan-14 13-Feb-14
C.TTC.IW.ACW030 Field Instrument & Panel Installation - Fresh Water Cooling Tower 60 25-Dec-13 11-Mar-14
C.TTC.IW.ACW040 Instrument Cabing from JB to Field Instrument - Acidic Water Cooling Tower 40 18-Mar-14 06-May-14
Oil Storage (15) 115 19-Aug-13 25-Jan-14
C.TTC.IW.FOS010 Instrument Cable Tray / Duct Installation - Fuel Oil Storage Tank 40 19-Aug-13 04-Oct-13 25-Jan-14, Oil Storage (15)
C.TTC.IW.FOS020 Instrument JB Installation - Fuel Oil Storage Tank 30 24-Oct-13 27-Nov-13
C.TTC.IW.FOS030 Field Instrument & Panel Installation - Fuel Oil Storage Tank 40 26-Nov-13 14-Jan-14
C.TTC.IW.FOS040 Instrument Cabing from JB to Field Instrument - Fuel Oil Storage Tank 40 07-Dec-13 25-Jan-14
6 kV Distribution Substation
Subs (18.1) 90 09-Sep-13 11-Jan-14
C.TTC.IW.SUB010 Instrument Cable Tray/Duct Installation - 6 kV Distribution Substation 40 09-Sep-13 24-Oct-13 11-Jan-14, 6 kV Distribution Substation (18.1)
C.TTC.IW.SUB020 Instrument JB Installation - 6 kV Distribution Substation 30 23-Nov-13 28-Dec-13
C.TTC.IW.SUB040 Instrument Cable Laying & Terminate - 6 kV Distribution Substation 40 23-Nov-13 11-Jan-14
Substation for Fresh W
Water Cooling Station & Sulfuric Acid Unit (18.2) 143 10-Sep-13 27-Mar-14
C.TTC.IW.SUB050 Instrument Cable Tray/Duct Installation - Fresh Cooling and SA Unit Substation 40 10-Sep-13 25-Oct-13 27-Mar-14, Substation for Fresh Water Cooling Sta
C.TTC.IW.SUB060 Instrument JB Installation - Fresh Cooling and SA Unit Substation 30 24-Oct-13 27-Nov-13
C.TTC.IW.SUB070 Marshalling Installation - Fresh Cooling and SA Unit Substation 20 04-Feb-14 26-Feb-14
C.TTC.IW.SUB080 Instrument Cable Laying & Terminate - Fresh Cooling and SA Unit Substation 40 13-Jan-14 04-Mar-14
C.TTC.IW.SUB210 DCS Power On - Fresh Cooling and SA Unit Substation 20 05-Mar-14 27-Mar-14
Substation for Water S
Supply System (18.5) 65 12-Oct-13 11-Jan-14
C.TTC.IW.SUB090 Instrument Cable Tray/Duct Installation - Water Supply System Substation 40 12-Oct-13 27-Nov-13 11-Jan-14, Substation for Water Supply System (18.5)
C.TTC.IW.SUB100 Instrument JB Installation - Water Supply System Substation 30 23-Nov-13 28-Dec-13
C.TTC.IW.SUB120 Instrument Cable Laying & Terminate - Water Supply System Substation 40 23-Nov-13 11-Jan-14
PA Unit Substation (18.6)
(18 70 07-Oct-13 11-Jan-14
C.TTC.IW.SUB130 Instrument Cable Tray/Duct Installation - PA Unit Substation 40 07-Oct-13 22-Nov-13 11-Jan-14, PA Unit Substation (18.6)
C.TTC.IW.SUB140 Instrument JB Installation - PA Unit Substation 30 23-Nov-13 28-Dec-13
C.TTC.IW.SUB160 Instrument Cable Laying & Terminate - PA Unit Substation 40 23-Nov-13 11-Jan-14

Sheet 1 of 1 Date Revision Checked Approved


25-Jun-13 For information
DAP No.2 VINACHEM PROJECT

Instrument Schedule as of Jun-13