Vous êtes sur la page 1sur 1
4. A sub-soil investigation for proposed waste treatment plant has been conducted and allowable bearing capacity at 1.5m below existing ground level is necessary to complete the design. However, the report is yet submitted by the geotechnical company expect experimental results of some locations, which is given below: Eon 3 oa a 0.2 01 ° ° 02 «04 08 1 12 Nocmal Stress (ker?) Also, void ratio, ¢ 32 8.3 N/m? Location of water table is 2.5m below existing ground level Unit weight = Determine the safe bearing capacity at 1.5m depth