Académique Documents
Professionnel Documents
Culture Documents
2 March 2007
OSD Approval
_____________________ __________
Mr. Kenneth J. Krieg Date
OUSD(AT&L)
UH-60M Systems Engineering Plan
Milestone C
10 February 2005
OSD Concurrence
_____________________________ _________
DAVID R. CASTELLANO DATE:
Deputy Director
OUSD(AT&L) DS/SE/AS
ii
UH-60M Systems Engineering Plan
iii
UH-60M Systems Engineering Plan
List of changes to the UH-60M Black Hawk Upgrade Modernization Program SEP Appendix A
iv
UH-60M Systems Engineering Plan
TABLE OF CONTENTS
vi
UH-60M Systems Engineering Plan
vii
UH-60M Systems Engineering Plan
viii
UH-60M Systems Engineering Plan
LIST OF FIGURES
LIST OF TABLES
ix
UH-60M Systems Engineering Plan
x
UH-60M Systems Engineering Plan
1.0 Introduction
This Systems Engineering Plan (SEP) for the UH-60M describes the detailed method for
planning and executing all technical activities required to transform the user needs, requirements,
and constraints into an optimized system solution for the UH-60M Program. This SEP covers
both the UH-60M Baseline and Upgrade. The differences for the Upgrade are covered in
Appendix A. This SEP is supported by the Prime Contractor’s Systems Engineering
Management Plan (SEMP) and Integrated Master Plan (IMP). The UHPO will update this SEP
for major milestones and as required throughout the lifecycle of the program.
The UH-60M Modernization Program replaces the existing fleet of UH-60A/Ls with new UH-
60M aircraft to meet Block 1 requirements identified in the “ORD for Recapitalization of the
UH-60 BLACK HAWK Utility Helicopter Fleet.” These ORD requirements identify capabilities
for improved flying qualities, digitization and situational awareness, increased lift and range over
the UH-60A model, extended service life of the aircraft, and increased operational readiness over
the current UH-60A/L models.
1
UH-60M Systems Engineering Plan
The resulting UH-60M helicopter will enhance the commander’s ability to conduct non-linear,
simultaneous, fully integrated operations in order to decisively mass the effects of the divisions’
warfighting assets. The UH-60M will provide digital connectivity for enhanced situational
awareness and improved lift, deployability, and survivability to further increase the
commander’s ability to conduct operations across the entire spectrum of the battlespace. More
specifically the UH-60M will replace the UH-60A/L analog primary flight instruments, as well
as the 1980’s communication and navigation subsystems, with state-of-the-art integrated
displays that provide the pilots information that reflects the current battlefield situation. The
automated features of this integrated system will significantly reduce pilot workload while
enhancing safety and the platform’s ability to operate within the demanding environments of
FAA, military, and international airspaces. The aircraft’s improved lift from the T-700-701D
and its Wide Chord Blades (WCB) will offset some of the increased weight it has received over
the years of modifications. Increased capabilities within the UH-60M detection systems will
provide additional survivability within the changing battlefield environment. The integration of
the Integrated Vehicle Health Management System (IVHMS) will provide the UH-60M with
diagnostic and prognostic capability aimed at safer operations, significant benefits in terms of
parts monitoring, configuration management, and migration towards Condition Based
Maintenance (CBM).
The UH-60M Baseline Program will employ technologies to increase pilot efficiency, increase
mission safety and effectiveness, provide a digital communications architecture, enhance
survivability, improve Reliability and Maintainability (R&M), reduce O&S costs, and allow for
future system growth. The UH-60M crew station design will be compatible with future aviation
life support equipment (ALSE) specifications. It is the intent that the UH-60M BLACK HAWK
will capitalize on the current system design and all technological advances that are appropriate
and compatible in terms of performance, cost, and risk. The requirements contained within the
ORD will be achieved by an evolutionary development and production approach resulting in a
fleet with mixed performance capability. The Utility Helicopters Project Office will meet these
requirements by integrating mature technologies into the UH-60M helicopter. HH-60M aircraft
2
UH-60M Systems Engineering Plan
designated to perform the MEDEVAC mission will integrate the medical mission subsystems
found in the UH-60Q and HH-60L.
The UH-60M Baseline Program is structured to be a low risk, technology insertion program
designed to field the latest technologies into an experience proven, 25 year old airframe design
while keeping program cost and schedule risks to a minimum. Program design considerations
focus on empowering the UH-60M with expanded capabilities to improve the warfighters
situational awareness, increase lift capability, while improving aircraft survivability and
crashworthiness. To this end, the UH-60M design contains the latest in digital avionics in a
more automated cockpit environment to increase the flight crew’s situational awareness while
enabling digital data communication with the modernized, digitized force structure. Improved
propulsion components enable the UH-60M to carry more payload over a further distance under
more adverse hot and high altitude conditions than the legacy UH-60A/L aircraft. New crew and
troop seats and a Crashworthy External Fuel System (CEFS) enhance the crash survivability
characteristics for the flight crew and passengers while the latest aircraft survivability
equipment, such as Improved Hover Infra-red Suppression System (IHIRSS) and Common
Missile Warning System (CMWS), will help defend the aircraft against emerging ground threats.
Eight prototype aircraft will be built under the UH-60M Integration and Qualification contract.
The first prototype aircraft is a UH-60A to UH-60M conversion used for Development Testing
(DT). At the conclusion of DT, aircraft number one will be used by Special Operations for MH-
60M development. The second prototype aircraft is a UH-60L to UH-60M conversion. It is also
being used for DT. Aircraft number three is a new production UH-60M and will be used for Log
Demo and Operational Testing (OT) then transitioned to field operations. Aircraft number four
will be used for IVHMS integration and EMV/EMC testing.
Aircraft numbers five through seven will all be UH-60A to UH-60M conversions used for OT
and then transitioned to field operations. Aircraft number eight will be a UH-60A to HH-60M
MEDEVAC conversion supporting DT (MEDEVAC) and Customer Testing (CT), while
integrating the MEDEVAC subsystems. Proof-of-principle for the MEDEVAC mission
equipment package (MEP) was accomplished under the UH-60Q program, where four
MEDEVAC aircraft were produced and tested.
These first MEDEVAC aircraft were converted from UH-60A platforms, with improvements to
digitize the cockpit, and additions an environmental control system (ECS), hoist, forward-
looking infrared (FLIR), and aviation medical oxygen generating system (AMOGS). Since the
fielded MEDEVAC fleet are UH-60A aircraft, a UH-60A with External Stores Support System
(ESSS) will be used during the Integration/Qualification (I/Q) contract to demonstrate and
validate the integration of the MEDEVAC Mission Equipment Package (MEP) with the UH-
60M. Total requirements for the MEDEVAC mission are 303 aircraft.
3
UH-60M Systems Engineering Plan
increases communications interoperability capability and survivability over the Baseline UH-
60M. The UH-60M Upgrade Program offsets weight growth associated with new capabilities by
employing advanced Fly-By-Wire (FBW) and composite technologies. These technologies
result in a target of no net weight growth for the UH-60M Upgrade Program aircraft over the
UH-60M Baseline Program.
The UH-60M Baseline Program provides the aircraft with digital connectivity for enhanced
situational awareness, improved flight handling qualities and improved lift, range, deployability,
and survivability to further increase the commander’s ability to conduct operations across the
entire spectrum of the battlespace. The UH-60M is a new production aircraft with improvements
to airframe, electrical system, main rotor blades, Advanced Flight Control Computer (AFCC),
flight controls, cockpit/avionics, and ASE. Figure 1 illustrates graphically the improvements for
4
UH-60M Systems Engineering Plan
the UH-60M Modernization Program as compared to the UH-60A/L. Specifically, the UH-60M
configuration will have the following improvements:
Cockpit Digitization
Airframe Improvements Operate on, Integrate with Digitized Battlefield (C2
& SA Interoperability)
Extend Service Life
Long-Range Precision Navigation
Reduced O&S*
Open System Architecture Allows Growth
Increased R&M* Capability
Standardized Fleet Enhanced Survivability through Situational
More Robust in EMI Environment Awareness
Increased Crashworthiness Canadian Marconi Flight Management System and
Fully Coupled Flight Director Decreases Pilot
Propulsion Improvements
Workload
Integrated Health Management System (IVHMS)
Increased Lift and Range* Increased Pilot Mission Mgmt Efficiency
Reduced O&S Costs* Standardized Fleet – long term
Increased R&M* Power PC Processor Family Reduces
Standardized Fleet Obsolescence Impact
Increased Survivability GATM Compliance
Rotor Brake Provisions 4 Rockwell Collins MFDs with Digital Map
Data Transfer from AMPS
5
UH-60M Systems Engineering Plan
Fuel System (CEFS) will improve fuel gauging, decrease fueling time, improve tank
crashworthy capabilities and provide the capability of emergency jettison.
b. Electromagnetic Environmental Effects (E3). The new aircraft will include electrical
wiring shielding to meet the E3 requirements In-Accordance-With (IAW) AVNS-PRF-
10002 and accommodate new electrical systems designs. This includes the removal of all
filter pin adapters and the application of the more stringent ADS37A standard for the
design of new components.
c. Wide Chord Rotor Blade (WCB). The WCB has been qualified and is flying on the test
UH-60M aircraft. This blade offers increased lift over the current blade to provide some
of the lift capability lost due to the increased mission weight of the UH-60M. The
advanced composite main rotor blades consist of a graphite/fiberglass spar and a swept
anhederal blade tip. The WCB has a 16% wider chord than the current
composite/titanium blade. Advances in airfoil and tip geometry, evaluated during six
years of Independent Research & Development (IR&D) testing have resulted in a blade
configuration that has demonstrated substantially improved aerodynamic performance.
At the root end, the wide chord blade attaches to the aircraft in exactly the same manner
as the current UH-60L production blade, except that the blade attachment pins are
approximately 0.1 inch longer than the current production attachment pins. Elimination
of the current blade’s titanium spar allows for the elimination of the Blade Integrity
Monitor (BIM).
d. Flight Control Computer (FCC). The UH-60M FCC is a digital computer that
provides the Stability Augmentation System (SAS), trim and Flight Path Stabilization
(FPS) functions. The SAS function provides aircraft body rate damping in pitch, roll,
yaw and collective. The trim system maintains stick trim in pitch, roll, yaw and
collective through the respective trim actuators. The FPS function maintains helicopter
flight path through control of attitudes, heading, airspeed and lateral acceleration. In
addition, a fully coupled flight director has been added to the flight control system. This
allows coupling to air speed, altitude, navaids, etc. The FCC provides extensive fault
detection of its associated hardware, processors, sensors, actuators via extensive Built In
Test (BIT) capability. There are two FCC’s required per aircraft.
e. Avionics Baseline. The avionics incorporate a dual redundant
communications/navigation MIL-STD-1553 data bus, an ARINC 429 data bus, and an
Ethernet capability. It also includes a Flight Management System (FMS), four Multi-
Function Displays (MFDs), an integrated stormscope, and all hardware and software
necessary to allow the crew to digitally communicate via the Improved Data Modem
(IDM). The FMS provides the pilots with the ability to view and input flight/mission
data, and interface with specific MFD and other subsystem functionality. The MFDs will
provide a wide range of data presentation to include: a moving map with multiple
flight/mission planning overlays, fully certified primary flight instrument displays,
caution advisory and systems status displays, as well as interactive Joint Variable
Message Format (JVMF) data message displays. The avionics will be compliant to Joint
Tactical Architecture-Army (JTA-A) V6.0.
f. Integrated Vehicle Health Monitoring System. The UH-60M/HH-60M will include an
Integrated Vehicle Health Management System (IVHMS) that monitors and records
6
UH-60M Systems Engineering Plan
7
UH-60M Systems Engineering Plan
UH-60A main gearbox from 2,828 shaft horsepower (shp) to 3,400 shp. All UH-60Ms
will receive Rotor Brake provisions on the IDGB.
m. T700-GE-701D Engines. The UH-60M/HH-60M will be powered by two T700-GE-
701D General Electric Turbine engines rated at 1,994 shaft horse power (shp) maximum
rated power (MRP) at sea level standard (SLS). These are T700-GE-701C engines with
upgraded hot section components.
n. AN/AVR-2B Laser Warning. The AN/AVR-2B is a passive threat warning system,
which receives, processes, and displays threat information resulting from aircraft
illumination by lasers. PM Aviation Electronic Systems (AES) will provide the AVR-2B
B-Kit free of charge to the UH-60M Modernization Program. The AN/AVR-2B and the
remaining ASE suite is integrated into the MFD display to provide an integrated
comprehensive threat picture overlayed on the digital map or navigation displays
providing improved situational awareness for the pilot.
o. High Speed Engine Driveshaft. In October of 2003, UH PO issued an Engineering
Change Proposal (ECP) contract to incorporate the improved driveshaft design into the
UH-60L production line. The improved design is expected to reduce the inspection
criteria on the current driveshaft. This change is targeted for implementation in LRIP.
There is currently an Interim Statement Air Qualification (ISAQ) for the Improved
Engine High Speed Driveshaft design for the UH60A/L/Q/M and HH-60L/M. The
improved engine high speed driveshaft design is a joint design funded by the US Navy
and the US Army. The US Navy has already procured shipsets for forced retrofit on the
Sea Hawk and will be incorporating the design into their production line as well.
p. Redesigned Drag Beam. The drag beam redesign program is post Critical Design
Review (CDR) with the next milestone being First Article Test (FAT). Redesigning the
jack pad feature and thickening the structure at the critical area eliminates the stress
corrosion cracking issue in the drag beam.
q. Solid Main Rotor Blade Attachment Pin. Inspections on the blade pin are a significant
maintenance burden to the field. The new main rotor blade pin features a solid core with
no expanding segments. Core material was changed to a material that is corrosion
resistant. The new design is expected to have an unlimited retirement life and will
eliminate the burdensome inspections that are required on the expandable pins. The new
pin is more expensive than the existing pin due to the material change and initial single
sourcing.
8
UH-60M Systems Engineering Plan
Prior to Milestone (MS) B, the UH-60M Program Manager (PM) developed a System
Engineering Master Plan (SEMP) that was then used by the Contractor, Sikorsky Aircraft
Corporation, to develop an Integrated Master Plan (IMP). The IMP was delivered to the UH-
60M PO as part of the System Development and Demonstration (SDD) program. These
programmatic documents serve as the basis for this document and have been updated in support
of the Milestone C Defense Acquisition Board (DAB) decision.
The ORD for Recapitalization of the UH-60 BLACK HAWK Utility Helicopter Fleet first
received JROC approval on 5 March 2001 (JROCM 046-01). It acknowledges the need to
address the deficiencies within the aging BLACK HAWK fleet. These deficiencies were
validated by the Aviation and Missile Command (AMCOM)in the studies commissioned on
Utility and Cargo Helicopter Lift Requirements (Dated 9 August 1995 (validated 1998)) and the
Utility Helicopter Fleet Modernization (Dated January 1999). The General Officer Steering
Committee (GOSC) for these studies concluded in January 1999 that a pure UH-60 recapitalized
fleet was desired, however, affordability constraints and maturation of key technologies drove an
evolutionary acquisition approach. This ORD and follow-on Capability Documents reflect that
evolutionary approach with the incremental upgrade of the entire Utility Helicopter fleet to meet
future capability requirements. The ORD was updated on 5 March 2005 to support the MS C
decision to proceed with Increment 1 (Block 1) production. Follow-on incremental capability
improvements are supported with the appropriate phased Capability Documents. A Doctrine,
Organization, Training, Materiel, Leadership, Organization, Materiel, Personnel and Soldiers
Facilities (DOTMLOMLPFS) determination analysis was completed by the U.S. Army Aviation
Center (USAAVNC) and non-materiel alternatives were judged to be inadequate. Requirements
Analysis and Analysis of Alternatives conducted under the oversight of AMCOM and Training
and Doctrine Command (TRADOC) support the requirements set forth in the ORD.
9
UH-60M Systems Engineering Plan
requirements identified within the GATM ORD and Federal Aviation Administration (FAA)
documents. It has been under configuration management since the Integration and Qualification
contract/phase was initiated, updated to what is now the “F” version, signed on 25 July 2006.
The Test and Evaluation Master plan (TEMP) serves as the master document for outlining the
test and evaluation requirements for the acquisition program. Separate OT programs will be
required for the UH-60M, UH-60M Upgrade, and Block 2 aircraft respectively to evaluate the
operational performance, suitability, and survivability of the overall UH-60 Fleet
Recapitalization/Upgrade Program. The TEMP will only address the planned OT requirements
for the UH-60M aircraft to support a UH-60M FRP DR. Block 2 requirements will be addressed
in revisions of the TEMP to support UH-60M Block 2 Recapitalization/Upgrade Program
milestones.
The Acquisition Strategy follows the guidance provided in DoD Directive 5000.1, 23 OCT 2000,
and DoD Instruction 5000.2, 23 OCT 2000. It incorporates an evolutionary approach and
mirrors the “ORD For Recapitalization of the UH-60 BLACK HAWK Utility Helicopter Fleet.”
The ORD specifies firm requirements for the first block (UH-60M) as well as a firm definition of
full capability of the second (final) block. This Acquisition Strategy describes the strategy for
the UH-60M (Block 1) in terms of capability, funding, development, test, production and
support. Block 2 is described to the extent it can be today. A subsequent Block 2 Program
Acquisition Strategy will address these items in detail when it is written. This UH-60M Program
Acquisition Strategy supports the Milestone decision relevant only to the UH-60M.
The Integrated Master Plan (IMP) signed on 26 June 2001 describes the management approach
for the UH-60M program execution established to comply with the UH-60M Statement of Work,
Schedules, plans and Sikorsky Aircraft System Engineering Process. The objective of the IMP
and its associated schedule, the Integrated Master Schedule (IMS), is to provide both
Government and Contractor program management with real time visibility into the schedule and
the health status of each primary segment of the program. It describes a totally integrated effort
of design engineering, specialty engineering, test engineering, logistics engineering and
production engineering to meet cost, technical performance and schedule objectives. It defines
the management process for the design, development, test and evaluation tasks required to
progress from an operational need to the deployment and operation of the system by the user.
The engineering integration process described by the IMP provides for the timely and
appropriate synergy of the engineering effort and disciplines such as reliability, maintainability
and logistics engineering to enable their influence on the system design.
The UH-60M Specification Tree (Figure 12) was developed in cooperation with the Contractor.
The specification tree provides traceability from the platform ORD, to include multiple other
organizational ORDs (GATM, Force XXI Battle Command Brigade and Below (FBCB2), the
Performance Specification, Segment Specifications, and multiple other layers of documentation.
It has been developed utilizing the format/structure of the WBS, Attachment 3. This provides the
complete traceability of all requirements documents. Any document that provided a Pilot
Vehicle Interface (PVI) was identified within the specification tree. Configuration Management
(CM) of the specification tree is being maintained by the Government and continues to provide
10
UH-60M Systems Engineering Plan
interim updates as the system matures. The top layers, down to and including the Performance
Specification identify the Functional Baseline. The next level, the Segment Specifications and
the Avionics System/Segment Design Document (SSDD), compile what is defined as the
allocated baseline. All documents below this level represent the Product Baseline.
The Baseline UH-60M is nearing the end of the SDD Phase of the program. IOT&E, LFT&E,
and EMV testing have been completed. All eight I/Q aircraft have been delivered, the LRIP
contract has been signed and deliveries of production UH-60M aircraft have started. The third
I/Q aircraft and the first two LRIP aircraft are production representative new build aircraft and
were utilized in the IOT&E. The other 7 IQ aircraft were remanufactured UH-60A or UH-60L
models upgraded to the UH-60M configuration. Close out of all remaining CDRLs is currently
underway, delivery and approval of the outstanding CDRLs will support the Statement of
Airworthiness Qualification, currently scheduled for mid 2007. The full rate production aircraft,
scheduled to start with UH-60M aircraft number 31 and subsequent will be used to support FUE,
2QFY08.
11
UH-60M Systems Engineering Plan
approach with the UH-60M being the first block. This blocked acquisition approach will meet
digitization/situational awareness requirements, allowing the BLACK HAWK fleet to keep pace
with the digitized Army. This strategy also provides a common modernized platform for the
fleet. The UH-60M will comply with the UH-60 Modernization ORD requirements for Block 1.
(Block 2 has its own requirements in the UH-60 Modernization ORD to accomplish leap-ahead
technology through development, integration and qualification of the Improved Turbine Engine
Program (ITEP) propulsion system.)
The UH-60M program is being accomplished in four acquisition phases:
For the UH-60M Modernization Program, the Pre-SDD phase is referred to as Risk Reduction
(RR) and the SDD phase has been referred to as Integration and Qualification (I/Q). Within these
phases the Program has developed and integrated a Risk Management Plan. A summary diagram
of key milestones and events within the UH-60M Modernization Program is depicted in Figure
2.
During the SDD phase of the program, ongoing UH-60 production efforts and existing programs
were leveraged to define innovative and integrated solutions for the UH-60M configuration
baseline and develop key program planning documentation. The SDD phase focused on the
integration and qualification of Block 1 upgrades. The Full Rate Production (FRP) phase or
Production and Deployment Phase will incorporate the Engineering Change Proposal (ECP) into
the existing production line to produce new UH/HH-60M aircraft in preparation for First Unit
Equipped (FUE) in FY08.
12
UH-60M Systems Engineering Plan
NOW
PROGR FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14
AM
UH-60A/A UH-60A-A
(Recap) 22 30 20 20 9 10 10 5 AAO
193
UH-60L
(ACAT IC) 38 32 UH-60
MS C MY VII C/A AAO
LRIP C/A FRP MY VIII CA 1806
UH-60M 5 17 66/59* 39 57 46 19
MEDEVAC MEP 10/5** 10 11 11
(ACAT ID)
DT / Flight Test
OT FUE
13
UH-60M Systems Engineering Plan
To maximize efficiency and reduce risks, the Utility Helicopter Program Office (UH PO)
leverages ongoing UH-60 (UH-60Q and Service Life Assessment Program) efforts to meet Block
1 performance requirements (digital map, flight management system, Control Display Unit
(CDU) rehost, CEFS, WCB Dual Use Application Program (DUAP), Active Vibration Control
(AVC)). Program schedule and cost risk were further reduced through a Risk Reduction (RR)
contract with the contractor to conduct initial design and performance analysis (including trade
studies and the first of three early user demonstrations), initial system requirements definition,
and program planning in support of the I/Q effort.
Key reviews during this phase are the System Requirements Review (SRR), Preliminary Design
Review (PDR), and Critical Design Review (CDR). This phase ends with the successful
demonstration of lift, range, interoperability and reliability and maintainability growth. Detailed
Entrance/Exit criteria for each review can be found in section 2.5.6. Exit criteria for this phase
are shown in Figure 3.
14
UH-60M Systems Engineering Plan
15
UH-60M Systems Engineering Plan
The FUE will be approximately six months after FRP. The unit will receive
aircraft produced during the LRIP contract. In conjunction with fielding the
aircraft, the gaining unit will receive a systems support package, training, and
other support.
• Integrate requirements of the basic aircraft design with materials and manufacturing methods
• Assist in meeting program objectives (ie. technical targets, schedule)
• Conduct trade studies as required to support design/development process
16
UH-60M Systems Engineering Plan
item previously produced or in production. Or, the system, component or item is in low rate
initial production. Ready for full rate production.”
Depending on one’s definition of a “process”, the build of the UH-60M could be seen as a
collection of production processes numbering anywhere from the hundreds to the thousands.
Consequently, decisions as to which processes should be evaluated to determine risks associated
with transitioning to full rate production are very critical. The Defense Acquisition Guidebook
(DAG) (Version 1.0 – 10/17/2004) states that the program manager should tailor the PRR to the
technical scope and risk associated with the system. The UH-60 PO will structure the PRR in
such a manner as to address the criteria associated with an EMRL 4 but will focus on processes
that have been identified either by the Government or the Contractor as processes of concern.
For example, rather than attempting to address all in-house processes at Sikorsky, it may be
more appropriate to concentrate on final assembly, the transmission and main rotor blade
backshops. In addition to addressing the EMRL criteria, the UH-60 PO may chose to assess
other areas of concern. The EMRL 4 criteria are described in Table 1.
17
UH-60M Systems Engineering Plan
Rate projections refined and estimated capacities meet FRP requirements. Any
Industrial Industrial facilities or production line changes are validated. Facilities demonstrated to be
Base/Facilities Base/Facilities adequate in LRIP.
As a starting point, the UH-60 PO will assemble a team of subject matter experts (SME)
covering a spectrum of functional areas from the Project Office, AMRDEC and DCMA-
Sikorsky. The SMEs will be charged with developing a set of questions aimed at addressing the
EMRL 4 criteria. These questions will then be forwarded to the Prime ahead of the scheduled
review as a self assessment. Upon completion, Sikorsky will submit the results of the self-
18
UH-60M Systems Engineering Plan
assessment to the Government. Following a review of the self-assessment, the Government will
conduct fact finding. Fact finding, preferably via a sampling process, will provide the
Government an opportunity to independently verify, validate or further investigate Sikorsky’s
responses.
The next step will be to conduct an on-site review which will consist primarily of Sikorsky
briefing the Government the responses to the self-assessment, reviewing fact-finding results,
joint identification and classification of risks, and joint development of risk mitigation plans.
The risk assessment process to be used will be the same as that currently used on the UH-60M
program and outlined in the UH-60M Risk Management Plan.
Collectively the Product Assurance functions support the system engineering IPT from design
thru qualification and are an integral part of the MS C decision point for the system.
19
UH-60M Systems Engineering Plan
The UH-60M DT Flight Test Program is estimated to consist of approximately 647 flight hours.
A disciplined planning approach is being designed to maximize the use of available flight test
hours. Upon completion of the entire DT/OT flight test program, the threshold requirement for
Mean Time Between Maintenance Action (MTBMA), Mean Time Between Mission Affecting
Failure (MTBMAF), and MTBEMA will be evaluated. Specific
FY 02 FY 03 FY 04 FY 05 FY 06 FY 07 FY 08
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
SDD PHASE PD PHASE FUE
Phases & SYS CDR
MS B MS C FRP DR
Milestones (DAB) FRP SER
LUT in SIL Decision PAE-TEST RPT MSC SER
Flight Test
CTT IR Test
DT Comp/Sub-Sys Qual
Component/
Ground Test Ground Test-
EMI/EMV
SLAP SLAP
EUD
EUD 2
20
UH-60M Systems Engineering Plan
21
UH-60M Systems Engineering Plan
Verification, Validation, and Accreditation (VV&A) process for the candidate models will be
documented in the UH-60 Modernization Simulation Support Plan and adhere to the guidelines
and policies stipulated in DA PAM 5-11 Modeling and Simulation VV&A Process. Modeling
and simulation tools and test beds to be utilized in this phase of the program are identified below.
Separate OT programs will be required for the UH-60M, UH-60M Upgrade and Block 2 aircraft
respectively to evaluate the operational performance, suitability, and survivability of the overall
UH-60 Fleet Upgrade Program. This section only addresses the planned OT requirements for the
UH-60M aircraft to support a UH-60M FRP. A UH-60M System Evaluation Plan, dated
December 2003, was developed to document the detailed evaluation strategy and overall test
effort for the entire development cycle. The System Evaluation Plan defines measures of
performance, evaluation methodology, and concepts for planned events (contractor, DT and OT)
which will provide data to support development of Event Design Plans, Detailed Test Plans, and
the SERs.
The operational testing of the UH-60M will be conducted in two phases. The Limited User Test
(LUT) in the SIL, completed 27 August 2004, was conducted during the SDD phase. The LUT
in the SIL SER supported the MS C/LRIP decision review by providing a limited evaluation of
operational pilot's effectiveness and suitability using the digital cockpit and the status of the
interoperability software. The Initial Operational Test (IOT) for the UH-60M aircraft was
conducted during the PD phase from 16 October – 21 November 2006 and culminated in an
evaluation of the system’s effectiveness, suitability, and survivability as input to a FRP Decision
Review. A follow-on Phase II OT for the HH-60M MEDEVAC was conducted from 24 – 26
January 2007 to evaluate the MEDEVAC specific equipment for effectiveness, suitability, and
survivability. Similarly, a Phase II OT for the JACS/CMWS configuration will be conducted in
March 2007 to investigate the effectiveness, suitability, and survivability of the JACS and
CMWS systems as installed on the UH-60M. Both Phase II OT’s will provide input to the FRP
Decision Review.
22
UH-60M Systems Engineering Plan
During the UH-60M IOT&E, five production representative aircraft (Platoon size element)
accumulated over 248 hours over a 6-week period finishing 6 weeks before originally planned.
The IOT started with a COMEX to verify the aircraft communication systems, perform required
Joint Interoperability Test Command (JITC) certification, and to verify proper establishment of
the Tactical Internet. The test aircraft were operated as an Aviation Platoon from an Assault
Helicopter Company. Portions of the platoon’s parent company leadership and battalion staff,
from the Assault Helicopter Battalion and the Aviation Unit Maintenance (AVUM) Company,
also participated in the test. An Infantry Company and an Artillery Battery acted as the
supported unit. The test location is Fort Hood and the test unit was from the 4/3 ACR.
The UH-60M aircraft has been designated for Live Fire Test and Evaluation (LFT&E) oversight
by the OSD, Director of Operational Test and Evaluation (DOT&E). Based on review of
previous UH-60 data and consideration of cost, a waiver from full up LFT&E has been
approved. In lieu of a full-up UH-60M, system-level test, an alternate test program, outlined in
the UH-60M Aircraft Alternative LFT&E Plan, is being conducted to adequately address
identified ballistic vulnerability data voids. The alternate test program consists of both
static/quasi-static test shots at flight critical components and subsystems as well as system-level
test shots at an operational Ground Test Vehicle. The test results combined with a disciplined
modeling and simulation approach are being used to address survivability of the UH-60M
aircraft.
23
UH-60M Systems Engineering Plan
The approach was to determine the current aircraft’s demonstrated reliability and to project the
aircraft’s future reliability based upon the anticipated corrective actions. Limited DT test results
for the M-unique portion of the system and contractor field data (the measured fielded
performance of the subset of equipment on the UH-60L using data collected through the
Unscheduled Maintenance Sample Data Collection (UMSDC) program) for the legacy portion
were used to estimate the system’s initial MTBEMA (Table 2). The Projection (blue) curve
assumes corrective actions are implemented instantaneously with immediate failure analysis and
corrective actions implemented into the product upon failure occurrence. The AMSAA Maturity
Projection Model (AMPM) was used for reliability projection of the M-unique portion of the
aircraft based on reasonable assumptions regarding fix effectiveness (80%) and management
strategy (fixing 95% of the failure rate) along with the system’s initial MTBEMA and the final
ORD threshold. The projection methodology is based on identification of fixes to failure modes
for which corrective actions are identified, but implementation is delayed. No significant fixes
are identified for the legacy portion that would be manifested through overall system reliability
growth. The demonstrated (pink) curve, derived from the Projection curve, is the demonstrated
path showing the delay for a batch of fixes to be implemented as a step function. Each step
represents a block update of FRACAS corrective actions in a UH-60M production lot. The
calendar time between the Projection curve and the Demonstrated curve is the lead-time
(typically 18 months) to design, manufacture, and implement the corrective actions. This curve
indicates that with current planning and the estimated initial reliability, the ORD MTBEMA
threshold will be achieved during production Lot V.
a. MTBMA => 40 Flt Hours MTBMA => 261.6 Flt Hours (Point Estimate)
b. MTBMAF => 15 Flt Hours MTBMAF => 130.8 Flt Hours (Point Estimate)
c. MTBEMA => 3.7 Flt Hours MTBEMA => 32.7 Flt Hours (Point Estimate)
d. Total MR =< 5.4 MMH/FH Total MR =< 3.7 MMH/FH
e. Unschd MR =< 2.1 MMH/FH Unschd MR =< 0.4 MMH/FH
24
UH-60M Systems Engineering Plan
M I F
S O R
Requirement C P Maturity @ 4,600 FH
T
E Lot V
Point Estimate
Scoring Conf #2 Lot IV
Lot III
Projection
Demonstrate
Lot II (Fixes Implemented)
IOTE &
Lot I
MS C Threshold
value ≥ 2.6
Flight Hours 0 355 505 638 2685 5625 10345 15625 20905
18 month Plus
Engineering &
st
1 Unit Fielded
Manufacturing Mid-
Holding legacy portion at assumed Lead Time Induction
constant MTBEMAlegacy = 4.5 Cycle
Lead Time
Per the UH-60M MTBEMA growth plan, a 4,600 FH test program with a typical lead-time to
design, manufacture, and implement the corrective actions (occurring during production Lot V)
is needed to mature the unique UH-60M equipment. It is anticipated, based on June 2004
program test planning for DT/OT, utilization of aircrafts to get the 4,600 flight hours would be
accrued as shown in Table 3 with the additional “lead-time” flight hours accrued into production
Lot V as shown. LRIP aircraft utilization is based on 20 FH per month utilization post delivery.
25
UH-60M Systems Engineering Plan
support, human factors, training, and safety. Reliability will be measured in mean time between
mission abort (MTBMA), mean time between mission affecting failure (MTBMAF), and mean
time between essential maintenance action (MTBEMA). Maintainability will address the
maintenance requirements associated with the use of the UH-60M. Maintainability will be
measured in maintenance ratio (MR). UH-60M R&M criteria reflect an improvement in the UH-
60A, bringing it to UH-60L standards. IOT RAM values were built on corrective actions
accumulated from the prototype, production, and LRIP aircraft, and these values will be
provided for the FRP DR. Full RAM maturity, to establish ORD threshold requirements, was
projected for 2010. However, as noted in table 2, the IOT RAM values significantly exceeded
the ORD threshold requirements.
With its versatility as a multiple role utility helicopter, BLACK HAWK allows the commander
to conduct overt, covert, and clandestine missions against the enemy's centers of gravity to
destroy key enemy capabilities. Providing precise navigation capability and immediate troop
mobility to the maneuver commander and flown by officers trained in combined arms operations,
BLACK HAWK provides the critical man-in-the-loop capability required for highly flexible
operations in rapidly changing conditions.
The UH-60M joint and combined force digital interconnectivity with other Command, Control,
Communications, Computer, Intelligence, Surveillance and Reconnaissance (C4ISR) systems
provides commanders at all levels the accurate, real time information needed for the
26
UH-60M Systems Engineering Plan
The mission of the UH-60M BLACK HAWK is to support the force commander as a highly
versatile utility platform operating in the extended battlespace increasing the total force
effectiveness throughout the spectrum of conflict and across the range of military distributed
operations. The defining capabilities of the BLACK HAWK, as they relate to the patterns of
operations, are:
Project the Force. The ability of the BLACK HAWK to rapidly deploy to any point on the
globe, using organic, airlift, sealift, or ground assets, supports the total force commander's goal
of quickly gaining and maintaining the initiative. BLACK HAWK can successfully maneuver
worldwide, twenty-four hours a day, in adverse environments to perform its missions. A fully
crashworthy, extended range, fuel management system gives the BLACK HAWK the flexibility
to operate at depth with extended endurance. BLACK HAWK has the capability for extended
intra-theater force projection for the insertion of ground forces in early entry operations.
Gain Information Dominance. Integration of digital communication technology allows the UH-
60M to interface with other Army and Joint C4ISR systems to achieve superior situational
awareness. This capability provides the UH-60 unprecedented battlefield survivability and
effectiveness. In its C2 configuration, BLACK HAWK enhances decision makers' ability to
achieve information superiority by receiving, processing, and displaying an uninterrupted flow
of battlefield situational awareness information. BLACK HAWK interfaces with Army and
Joint C4ISR systems to quickly achieve superior situational awareness.
Shape the Battlespace. BLACK HAWK is part of a decisive force that shapes the battlespace at
the strategic, operational, and tactical levels. The speed, range, mobility, and flexibility of the
BLACK HAWK provide the commander the ability to dominate the expanded multidimensional
battlespace.
Decisive Operations. BLACK HAWK is an integral part of the total force commander's combat
capability to conduct decisive operations. Unmatched situational awareness, rapid
responsiveness, agility, and mobility give the commander the capability to defeat an adversary
by quickly massing effects on the noncontiguous battlefield.
Sustain and Transition the Force. The Upgraded BLACK HAWK has increased combat
capability, maneuverability, and survivability over current utility helicopter systems, while
maintaining a more sustainable logistics profile. Presenting a reduced logistics footprint,
27
UH-60M Systems Engineering Plan
BLACK HAWK can remain mission capable to support the commander under austere
conditions.
Employment. BLACK HAWK sets the worldwide military standard by defining the full
spectrum of utility helicopter operations. Missions are executed during day and night, in NBC
conditions, adverse weather, battlespace obscurants, and extreme environments across the full
range of military operations. BLACK HAWK dominates its battlespace by integrating digital
communications to provide superior situational awareness and to move rapidly to deliver combat
troops and equipment at exactly the right place and time. In its C2 configuration, BLACK
HAWK provides the commander with digital data and voice connectivity to with not only the
other members of the combined arms team, but also joint and coalition forces.
During wartime, BLACK HAWK is the primary means by which the Army conducts air assault
operations across the full spectrum of conflict. Used primarily as an infantry squad carrier, the
BLACK HAWK gives the force commander the capability to dominate and shape the battlespace
through rapid and agile maneuver throughout an expanded and asymmetrical operational area.
During Stability and Support Operations (SASO), the BLACK HAWK supports the JTF
commander in its key role as the primary early entry and rapid reaction force delivery platform.
BLACK HAWK also enhances and extends the capabilities of all commanders to initiate,
conduct, and sustain combat operations by providing internal and external lift of weapon
systems, supplies, and equipment at all echelons. The improved external lift performance of the
UH-60 Block 2 will provide a 9,000 to 10,000 pound capability fulfilling the need for rapid
aerial mobility of emerging weapons systems organic to the future objective force.
BLACK HAWK is the primary platform for airborne C2 providing full joint and combined
interoperability with other C4ISR elements to the commander at echelon above corps, corps,
division, and the ground and air maneuver brigade.
BLACK HAWK is configurable to provide counter-mobility through the Volcano mine delivery
system, medical evacuation with an advance MEDEVAC mission equipment package, and rapid
insertion/extraction with a Fast Rope Insertion/Extraction System (FRIES). As a national asset
the BLACK HAWK performs the role of passenger and equipment movement and is heavily
utilized in disaster relief such as flood and storm recovery operations, medical evacuation, fire
suppression, search and rescue, and VIP transport operations.
28
UH-60M Systems Engineering Plan
2.2.2.4 Survivability
The fourth KPP which the UH-60M must accommodate is Survivability. The aircraft has been
demonstrated to maintain no more than the existing UH-60L Infrared (IR) signature with infrared
suppression systems installed.
Passive countermeasure (CM) systems such as radar and laser warning, along with active CM
warning systems such as IR CM have been integrated into the UH-60M to provide no less
protection than existing (APR-39 and AVR-2) systems.
An active IR missile warning system with automated IR CM activation (Chaff and Flare
Dispensers), crew warning and manual override has been integrated into the UH-60M design.
Internal fuel cells have been qualified to be self-sealing when penetrated by fully tumbled
7.62mm (threshold) and 14.5mm projectiles impacting at 1600 fps.
2.2.2.5 Reliability
Though not a KPP, another key performance enhancing characteristic that is being developed is
improved Reliability, Availability, and Maintainability (RAM). Every opportunity to exploit the
information available through Built-In-Tests (BIT) to reduce the time required for problem
detection and correction. Requirements for an 8000 hr airframe life are flowed to the individual
components. RAM data is being tracked on all UH-60Ms built to date to ascertain if the UH-
60M configuration is of greater reliability than the legacy UH-60L configuration.
29
UH-60M Systems Engineering Plan
30
UH-60M Systems Engineering Plan
upgrades will be incorporated during the UH-60M Upgrade Program. Future improvements will
be initiated at the direction of the UH PO to achieve the objective capabilities outlined in the
ORD.
2.3.3 IPTs
The IPT organization of the UH-60M Baseline Program is shown in Figure 6. The organization
is supplemented by matrix support from other Government as well as Support Contractors filling
critical needs. The UH-60M Baseline Program is managed through an IPT management structure
with an active Government and Sikorsky Aircraft Corporation (SAC) representation on all IPTs.
The UH-60M PM level IPT provides day-to-day functional management of the program. IPT
Leads are responsible for cost, schedule, and performance for their allocations of the Work
Breakdown Structure (WBS). The organization is designed to provide points of contact for the
technical, program management, operations, and specialty functions. Each IPT has weekly
meetings normally through telecons or video teleconferencing (VTC) that includes prime
contractor technical counterparts. Weekly program management reviews (PMR) in the form of
VTCs includes all IPT leads plus the Program Management Working Group (PMWG). This
facilitates the interchange of information between the Government and Contractor, which has
been and remains a vital component of a continuous quality improvement environment. The
Army Systems Acquisition Review Committee (ASARC) provides oversight and review support
to the UH-60M PM and the MDA as the program proceeds through the acquisition life cycle.
Integrated Manufacturing (IM)/Operations, Air Vehicle (AV) and Mission Equipment Packages
(MEP).
31
UH-60M Systems Engineering Plan
Program Managers
Working Group (PMWG)
LTC(P) R. (Chip) Lunn (G)
Bob Mastronardi (S)
UH-60M Baseline
Scott Silies (G)
Robert Frawley (S)
Systems Engineering
Sub-IPT
Eric Martin (G)
Anthony Saccullo (S)
Integrated Manufacturing
Sub-IPT
Dimitri Gerousis (G)
Ray Burke (S)
Mission Equipment
Packages Sub-IPT
Heather Hone (G)
Dave Zavednak (S)
The Program Managers Working Group (PMWG) is comprised of the UH-60M PM and his
Sikorsky Aircraft Corporation counterpart. They are responsible for planning, execution,
integrated product development, design, and life cycle management to deliver a cost effective
and supportable aircraft that meets the user’s requirements on schedule. Subordinate IPTs are
responsible for specific functional areas and report directly to the PMWG. Each IPT is composed
of representatives from other Government agencies and military organizations, industry,
academia, and other sources as appropriate. The UH-60M PM will form Tiger Teams to resolve
specific issues.
32
UH-60M Systems Engineering Plan
Funding and resources for the Government IPTs are managed by the IPT leads though an internal
operating budget (IOB) process whereby the IPT leads allocate funding to support both
Government and support contractor personnel to perform the work of their appropriate IPTs.
The IPT Leads have responsibility for managing their allocated WBS elements (see Attachment
3) to remain within cost and on schedule. In addition, each Government IPT Lead has received
extensive Earned Value Management System (EVMS) Techniques and Tools Training.
Government IPT leads and Sub-IPT leads are required to be Level III certified in their respective
field as defined in the Defense Acquisition Workforce Improvement Act (DAWIA). These
DAIWA certifications involve satisfactory completion of a series of courses taught by the
Defense Acquisition University as well as having served a certain amount of time in that
DAIWA specialty.
The Engineering IPT, Business Management IPT, Logistics Management IPT and the Test
Management IPT are the program’s primary IPTs and are subordinate to the PMWG. Systems
Engineering (SE), Integrated Manufacturing (IM)/Operations, Air Vehicle (AV) and Mission
Equipment Packages (MEP) are subordinate IPTs (sub-IPTs) to the Engineering IPT. Additional
sub-IPTs may be added as required to support any IPT. The Government and the Contractor will
provide IPT co-leads for each IPT. Each IPT derives the authority to make decisions through
empowerment from their respective “chain of command.” Unresolved issues are raised to the
PMWG. Charters for the IPTs and Sub-IPTs are enclosed as Attachment 2.
33
UH-60M Systems Engineering Plan
Doug Shidler
VP BLACK
Bob Mastronardi
UH-60M Project Manager
Tom Kaczyinski
GFE Coordinator
Mathew Lisk
Admin Support
Paul Trompetter George Klein Robert Frawley Judy Serra Ray Burke Len Pinaud
Business Manager ILS Manager UH-60M Chief Engineer Program Plans & Controls Operations Major Subs
Merle Hickok
John P
McLean Assistant ILS Mgr Bob Stewart Tony Saccullo
Rick Brede Bob Piekarz
Paul Rado
Contracts Test System Engineering
Lead Scheduler Scheduler Final Assy Ops
Mike Grant
Dorothy Hardy Attributes Barbara England Rajani Velaparthi Pete Ladyko
Finance
Data Management Scheduling Assistant WPB Hangar Ops
Chris Valentine
Financial Analyst Dave Zavednak Brian Curina Silvia Rodriguez Mike Spears
Avionics Air Vehicle Scheduler Troy Operations
Darlene Ridolfi
Financial Analyst
Dan Cooper Rich Goodrich
Avionics Test Chuck Evanich
Mike Cavallaro Electrical
Material
Financial Analyst
Arnis Buza Mike Petrucci
Systems Integration Airframe
Ira Zoock
Flight Mgmt System
34
UH-60M Systems Engineering Plan
35
UH-60M Systems Engineering Plan
The SE-IPT Lead is the UH-60M program Risk Manager. Risk Management is achieved
through a robust process of tracking each risk and re-evaluating its status on a monthly basis as
documented in the UH-60M Risk Management Plan. The risk management tools consist of a
combination of Microsoft Access and Power Point documents.
36
UH-60M Systems Engineering Plan
37
UH-60M Systems Engineering Plan
• Supporting, developing, and executing the CAIV Plan by providing personnel and cost data
to support decisions.
• Developing, in coordination with the other IPTs, an integrated program schedule. The
schedule will be maintained and will be used as a basis for excursions regarding the impact
of activities progressing at a faster or slower pace than planned.
• Supporting the PMWG as required by maintaining action item data bases, personnel rosters,
meeting minutes and the program library as required.
• Assessing and recommending resource courses of action, including developing and
maintaining baseline cost estimates and other cost documentation and providing inputs to
planning and budgeting processes.
38
UH-60M Systems Engineering Plan
• Supply
• Training
The Government manages the systems engineering processes at the UH-60M System level
through the UH-60M Systems Engineering Sub-IPT. All the UH-60M IPTs have an input to the
39
UH-60M Systems Engineering Plan
Systems engineering processes at the subsystem level are coordinated by the prime contractor’s
system engineer and are imposed through contractual requirements between the prime contractor
and the respective supplier.
Systems
Analysis
Requirements and Control
Analysis
Requirements
Loop
Functional
Analysis
Design
Loop
Synthesis
Verification
2.4.1 Requirements
40
UH-60M Systems Engineering Plan
Inputs to the UH-60M requirements analysis process included customer needs and objectives,
missions, measures of effectiveness/suitability, environments, Mission Needs Statements, ORD
Documents as well as outputs requirements from the previous (higher-level) application of the
system engineering process. The output of the process is a set of functional, interface and
performance requirements. The example below, Figure 9, describes the requirement (mission)
analysis process that was implemented on the UH-60M that translated user requirements into the
UH-60M System Performance Specification, AVNS-PRF-10002.
Requirements
Analysis
Define
Define functional
performance
requirements
requirements
Define technical
Define modes of Define design Define human
performance
operations characteristics factors
measures
Establish requirements
baseline
Mission Analysis is the process of analyzing customer needs, objectives, and requirements in the
context of UH-60M missions, system utilization and environments. Sikorsky performed a
mission analysis during the conceptual phase of the Sikorsky UH-60 Modernization study. The
Sikorsky mission analysis was based upon the UH-60 BLACK HAWK Helicopter Operational
Mode Summary/Mission Profile (OMS/MP). The results of this completed activity combined
with similar US Army analyses are reflected in the ORD and AVNS-PRF-10002. Requirements
in the System Performance Specification have been developed to satisfy US Army needs and
maximize system cost-effectiveness over the system life cycle. System Specification
41
UH-60M Systems Engineering Plan
requirements are based upon Operational Requirements Documents, UH-60 Mission Needs, US
Army UH-60 Analysis of Alternatives and Sikorsky mission and performance analysis.
During the RR and SDD phases of the UH-60M Modernization Program, initial mission
requirements were baselined and continually refined to meet the mission and environment to
fully support overall system definition through the trade study process. Sikorsky conducts
relative worth evaluations to quantify operational effectiveness of trade/design options in terms
of overall mission capability. The operational effectiveness data is combined with peacetime life
cycle costs to identify the trade/design alternative that maximizes system cost effectiveness. The
evaluation method is used for system and segment level trades. Analytical models and man-in-
the-loop simulations are used as appropriate and, based on the tools employed, measures are
developed to quantify mission effectiveness.
At the segment level, sensitivities are generated to evaluate and understand relationships
between performance parameters and operational requirements. These detailed, segment-level
functional and performance analyses are the basis for the characterization of system
requirements in the Prime and Critical Items Development Specifications (CIDS) (hardware),
Sikorsky Engineering Specifications (SES), source control drawings and Software Requirements
Specifications (SRS).
Functional performance allocation decomposes system level requirements until a level is reached
where a specific configuration item can be designed to fulfill the stated requirements. System
performance and design requirements are allocated to each function identified in the functional
analysis. Each function is defined in terms of performance requirements and associated design
constraints. At the completion of this portion of the process, the functional architecture is
established consisting of a set of functions and their corresponding performance requirements. A
“Requirements Loop” is created as requirements developed in the requirements analysis process
are revisited as a result of the Functional Analysis and Allocation process. This is caused by the
emergence of functional issues that require re-examination of higher level requirements.
42
UH-60M Systems Engineering Plan
Functional analysis
Define
Define subfunction
subfunctions states and
modes
Establish functional
architecture
2.4.1.3 Synthesis
Synthesis, Figure 11, is the process of translating functions and constraints developed in the
Functional Analysis and Allocation process into a physical architecture as well as defining the
physical interfaces. The physical architecture is supported by trade studies and effectiveness
analysis. Requirements allocations sheets map the functions and their corresponding functional
and performance requirements to the physical architecture. The objective of design synthesis is
to combine and restructure hardware and software components in such a way as to achieve a
design solution capable of satisfying the stated requirements. During concept development, the
synthesis process defines the basic relationship between sub-systems. During preliminary and
detail design phases, subsystem and component are defined in more detailed as are all interfaces.
The “Design Loop” involves revisiting the functional architecture to verify that the physical
architecture developed is consistent with the functional and performance requirements. The re-
evaluation may result from design issues that arise as the physical architecture is developed and
practical limitations are exceeded. The re-evaluation may result in changes in the requirements,
re-allocation of the functions and/or a re-allocation of the function to physical architecture map.
The digital mockup (DMU) is a tool that Sikorsky uses to assist in this transformation. The
DMU is a central database, which contains the three dimensional geometric designs that has
been generated by the computer aided graphics system, CATIA. The DMU is a tool that
Sikorsky uses to support the spatial integration of the aircraft components and sub-systems. The
43
UH-60M Systems Engineering Plan
DMU allows designers to achieve a sufficient level of spatial integration to control physical
interfaces and to verify mechanical interfaces. The DMU will be utilized on the UH-60M to
reduce the overall cost, risk and schedule time for the program. Sikorsky utilizes complete
DMU designs for new air vehicles. In the case of UH-60M, a hybrid (or partial) DMU approach
will be pursued utilizing CATIA models with sufficient accuracy for wiring harness tools and
Technical Publication illustrations. For the UH-60M, the DMU models that include geometry
suitable for the direct application to the manufacturing of tools, parts or assemblies will be used
for new or modified contractor furnished equipment or components.
Synthesis
Identify
Identify off-the-shelf Identify make or buy
standardization
availability alternatives
opportunities
Final design
Establish design
architecture
44
UH-60M Systems Engineering Plan
Government concurs the specific PUIs are verified, it returns the MFR to the contractor with
concurrence and Sikorsky updates it’s DOORS database accordingly. If the Government deems
the requirement has not been adequately verified by the means stated in the MFR, it returns the
MFR with non-concurrence and an explanation of the deficiency for Sikorsky to resubmit.
This hierarchy of the flowdown of requirements and performance allocations establishes clear
traceability throughout the system from the source (UH-60M System Performance Specification)
to the segment and configuration item (CI) levels. In all cases, each technical performance
requirement is traceable to the applicable higher and lower levels. All lower level “children”
requirements are traceable to a “parent” requirement. When compliance with a performance
requirement calls for more than one subsystem to accomplish the specified functionality, an
interface is identified between the affected subsystems. Interface requirements are developed for
new or unique requirements to specify the role each subsystem has in satisfying the requirement.
The UH-60M System Performance Specification will consist of functional, allocated and
physical baselines defined by AVNS-PRF-10002, Performance Item Specifications (Segment
Specifications) plus SRS and Interface Requirements Specification (IRS) and Product
Specifications (Sikorsky Engineering Specification, Source Control Drawings, Vendor
Specifications), respectively. The specification and levels are illustrated in Figure 12.
45
UH-60M Systems Engineering Plan
FUNCTIONAL AVNS-
Performance
BASELINE 10002E Requirements
UH-60M
Performance
PRODUCT IntraSegment
H H
BASELINE W W
ICD Intermediate
&
Organization
SW SW H H H H
IntraSegmen
ICD
CIs CIs W W W W Lower Level
CI Requirements
Requirements flowdown to the Detail Item Specification level will be performed during the SDD
phase. Detail Items are defined at the fourth or fifth level of the WBS for flowdown. Segment
leads will participate in a flowdown of requirements through the allocation of segment level
requirements to the individual Detail Item Specifications. Physical legacy interfaces will be
defined by installation drawings and wiring diagrams. Legacy Detail Items Specification will use
existing CIDS, SESs, source/specification control drawings and contractor specifications where
applicable. As with segment level interfaces, all unique UH-60M and UH-60M MEDEVAC
unique items will use Interface Control Drawings/Documents (ICD) to define interfaces. UH-
60M unique detail requirements will be documented in CIDS, SESs, source/specification control
drawings and contractor specification where applicable.
46
UH-60M Systems Engineering Plan
independent database that provided a constant capability to verify the Prime Contractor
TM TM
DOORS database. The Core database was utilized on numerous occasions to create
crosswalks between various documents, including the ORD, COICs, OMS/MP, GATM ORD,
TM
multiple FAA and other DoD documents. The Core tool also supported the functional analysis
of the Avionics segment. This analysis created the foundation of the lower level requirements
that resulted in the major portion of the derived requirements for UH-60M cockpit (Situational
Awareness Document). The database was also utilized as a bridge from the Performance
Specification to the Crew Station Working Group (CSWG) effort to develop the final detailed
TM
functionality of the cockpit. The Core tool provided a discrete event simulation capability that
was used to model the operational tasks required during a basic mission and evaluate the
impact/benefit of 4 versus 2 MFDs.
47
UH-60M Systems Engineering Plan
The system engineering process was used to develop an M&S strategy for the UH-60M. The
M&S strategy includes a description of the simulation methodology employed as well as model
metrics and model outputs. The Government does not intend to model all Contractor processes.
Instead, the strategy is to first model aircraft final assembly, the pace of which ultimately
determines how fast the product can be delivered to the customer. Based on what are identified
as the bottleneck processes in final assembly, the plan is to work “back up” the production build
stream and model those processes which are shown to be on the critical path. These models will
also help identify those parts whose availability may be critical in trying to maintain a smooth
production flow.
The simulation software selected for this effort is a commercial off the shelf product named
“WITNESS” by Lanner, Inc. WITNESS is a graphical interactive simulation tool with artificial
intelligence features which enable the non-simulation specialist to quickly build models of
complex operations. WITNESS combines the power of moving color graphics with user
interaction to permit a decision maker or planning team to view a complex factory operation or
business process and interactively use ‘what-if’ techniques to investigate, plan, and implement
changes in the operation and investment of improvement projects. The Government has teamed
with Lanner who is now customizing their product to meet the needs of the UH-60M
Modernization Program. Lanner is developing an executive dashboard, a user-interface and
providing support in data collection and model development. The dashboard will serve as a
dynamic status reporting tool that will display key program metrics.
In July of 2004 UH-60M PMO completed development and validated with the Contractor a
model of the WCB build process. UH-60M PMO plans to complete models of UH-60M and
UH-60L final assembly before the end of calendar year 2004.
48
UH-60M Systems Engineering Plan
will be documented in the UH-60 Modernization Simulation Support Plan and adhere to the
guidelines and policies stipulated in DA PAM 5-11 Modeling and Simulation VV&A Process.
V&V was successfully completed 30 days prior to LUT Operational Test Readiness Review
(OTRR) #2. Modeling and simulation tools and test beds to be utilized in this phase of the
program are identified in the paragraphs below.
The M&S tools identified in the Table 4 represent the M&S tools used to support the design,
test, management, deployment and sustainment of the UH-60M. These M&S tools were used
during preparation for Milestone C and were either developed by the UH-60M Modernization
49
UH-60M Systems Engineering Plan
2.4.2.1.2 EUD-1
Support of the Risk Reduction Trade Studies was accomplished in the Research, Development,
and Engineering Command (RDECOM) Advanced Prototyping and Experimenting (APEX)
Laboratory utilizing the re-configurable common cockpit prototype in order to consider the
widest range of cockpit configurations. The data used for evaluation was collected from a
training period, a series of structured mission scenarios and after action interviews. The APEX
facility records all pilot actions as data and correlates them to mission events.
2.4.2.1.3 EUD-2
Support of the PDR, was accomplished through the use of the RDECOM APEX Laboratory.
The baseline UH-60M cockpit was emulated in the facility. All available tactical hardware and
software was used along with simulations. Data recording and evaluation was similar to EUD-1.
2.4.2.1.4 EUD-3
EUD-3 will use the RDECOM SIL using the cockpit design determined by the CDR. Data
recording and evaluation will be similar to EUD-1 and EUD-2 using audio and video recording.
50
UH-60M Systems Engineering Plan
differences will be presented to the Shipboard Aviation Facilities Certification Manager, Naval
Air Systems Command (NAVAIRSYSCOM), and the Naval Air Warfare Center Aircraft
Division (NAWCAD), Rotary Wing Ship Suitability Branch, for review. UH PMO will use
Electromagnetic/Electronic Environmental Effects (E3)/ Hazards of Electromagnetic Radiation
to Ordinance (HERO) testing and similarity of dynamic/physical interface characteristics of
current certified H-60 in support of Naval shipboard certification.
51
UH-60M Systems Engineering Plan
aviation decontamination solutions and procedures. A V&V effort has been completed. ATEC is
responsible for accreditation.
A series of trade studies were conducted during the risk reduction phase of the UH-60M program
and during the Integration and Qualification contract. The objectives of these trades studies
were performance enhancement to meet KPP requirements, enhancement of RAM, and reduction
of costs.
System Engineering is responsible for definition and implementation of the trade study process.
This document provides an overview of the process including trade organizational structure,
trade procedures, and the approval chain that were utilized during Risk Reduction and
Integration/Qualification phase of the UH-60M Modernization Program in order to accomplish
design optimization.
Trade studies were generally conducted at the system and segment level. System trades
(Attachment 6) are trades affecting the overall system (System Performance Specification
AVNS-PRF-10002) in terms of operational effectiveness/suitability, and cost which involve
elements from more than one of the segments. Segment trades affect only one segment, such as
airframe, avionics, logistics, etc… System and segment trades may address Detail Items in
determining whether their impacts on system attributes such as weight and cost are within stated
tolerances.
The definition of, and the coordination associated with trade studies depends upon the level of
the trade. UH-60M System Engineering has general responsibility of the trade study process and
system level trades. Segment level trades are the responsibility to the primary and supporting
IPTs. IPT leaders are responsible for scheduling trades within the IPT and coordinating activities
to ensure timely and proper completion of all trades. For example, IPT leaders ensure that all
parameters impacted by a trade alternative are identified and evaluated. The System Engineering
52
UH-60M Systems Engineering Plan
IPT assists in coordination of trades to ensure that the trade is conducted according to the trade
process, and the effectiveness evaluation is properly implemented.
53
UH-60M Systems Engineering Plan
complete a trade study are defined. Selection and prioritization of trade study candidates requires
Army involvement at all levels and will be finalized through the IPT process. It is important to
limit alternatives to only those necessary to resolve the trade objective and to minimize
confusion in the understanding of the opportunities provided by the alternatives.
Parameter Metric
Risk
Schedule Qualitative Index (1=Low, 3=Medium, 5=High)
based upon months impact to milestone schedule.
Technical Qualitative Index (1=Low, 3=Medium, 5=High)
based on technology maturity , level of integration
required, and impact to program.
Cost Qualitative Index (1=Low, 3=Medium, 5=High)
based on complexity and anticipated cost.
System Performance
Mission Performance
Flight Performance
Internal Lift Ton nm per mission hr vs. weight empty
External Lift Ton nm per mission hr vs. weight empty
54
UH-60M Systems Engineering Plan
55
UH-60M Systems Engineering Plan
Utility curves are developed to facilitate a sensitivity analysis for the required performance
measures. Utility curves are developed via various techniques, such as modeling and simulation,
to provide an indication of the effect that a change in a performance measure has on system
effectiveness. A few examples of utility curve development for the UH-60M Risk Reduction
effort are described below:
• Mission capability is generally evaluated with modeling and simulation using system
dynamics.
• Reliability and maintainability utility curves are derived from using the standard system
availability equation.
• Subjective categories such as safety and risk will use a qualitative assessment against
specified criteria for that specialty area.
56
UH-60M Systems Engineering Plan
determine the best mix of trade alternatives, Figure 16. This optimization is subject to specific
program constraints and supports the CAIV objectives for the UH-60M.
The system optimization analysis utilizes a mixed integer linear programming technique to
identify the most cost-effective system configuration where multiple KPPs interact. The SE IPT
is responsible for organizing and conducting the system optimization of the trade studies.
2.4.3.9 Results
Utilization of the trade study process detailed herein has resulted in several modifications and
changes to the UH-60M system. During the RR phase, a major trade study effort resulted in
multiple hardware actions being implemented through contract modification or implementation
into the baseline configuration. Attachment 6 contains lists of trades performed during RR and
IQ as well as status of implementation.
UH-60M requirements are documented and tracked at the system and segment level. Overall
technical requirements are contained in the UH-60M Performance Specification, AVNS-PRF-
10002. Changes to the specification are made via a form SCN process where contractor and
57
UH-60M Systems Engineering Plan
government members of the integrated product team have the opportunity to comment on
proposed changes. After a period of comment and revision, the SCNs are boarded at a
Configuration Control Board consisting of Government personnel from the PM and supporting
agencies such as the acquisition center, the user, logistics, and the AMRDEC. After a years
time, a revision is made to the Performance Specification to incorporate all SCNs approved since
the last revision was released.
UH-60M performance specification requirements are further decomposed into the allocated
baseline by means of segment specifications which define in further detail the performance
expected of elements of the UH-60M. Segment specifications have been baselined for Ground
Support Equipment, Dynamic Components, Airframe, and Avionics.
In the UH-60M Modernization Program where the system already exists, all external interfaces
will have to be mapped, changes identified, changes defined, and characteristics listed. The
Contractor will address interface management and integration in the SE portion of the IMP.
Interface control is the coordinated activity necessary to confirm that equipment and software
produced by one party is compatible with that of another party. A technical interface exists
when one of the following occur:
• A subsystem developed item is required to mate with another subsystem’s developed item, or the
converse of this.
• One subsystem is constrained by actions, yet to be completed by another team member at some
specified point in time.
• More than one subsystem/segment must work together to achieve requirement compliance.
58
UH-60M Systems Engineering Plan
59
UH-60M Systems Engineering Plan
hardware, software, and interfaces will be performed before finalizing the product baselines. The
Technical Data Package (TDP) is procured and maintained under the direction of MIL-DTL-
31000C.
60
UH-60M Systems Engineering Plan
In addition, the CM Plan outlines the following configuration change control actions:
61
UH-60M Systems Engineering Plan
• Timing
• Schedule
• Resources
• Inadequate
planning and
preparation
• CM Plan
Configuration • Definition and identification of CI’s
• Mission Need • ABL & PBL established
• Program Initiation • Change control
• System Eng Management • Supplier/Subcontractor change control
Requirements,
•
Functional Analysis Process •
CCB Activity
Disposition of proposed changes
• Logistic & Maintenance
• Status accounting
Plans
• Change audit & verification activity
• Performance
Measurements • Class I baseline change management
• CM process performance measured
• Communication
• Management
Support
• Effective working
IPT & Army IPT Mechanisms/
relationships Facilitators
• Facilities
• Resources
• Training
• Guidance
handbooks, plans
procedures and
standards
62
UH-60M Systems Engineering Plan
63
UH-60M Systems Engineering Plan
Public Law 104-13, The Paperwork Reduction Act of 1995, established the requirement to
replace paper data with digitized data, and to handle, transmit, and store that data by means of an
integrated digital environment. MIL-STD-1840C, DoD Interface Standard, Automated
Interchange of Technical Information, establishes the structure and formats for transfer of digital
information between organizations and systems exchanging digital forms of technical
information throughout the system life cycle.
UH-60M requires on-line access to, or delivery of, the Contractor's programmatic and technical
data in digital form (unless analysis shows that life cycle time or life cycle costs would be
increased) via Contractor Integrated Technical Information Service (CITIS). The UH PMO has
developed a Government concept of operations that spells out Contractor requirements for
functionality (but not the implementation method), user systems interfaces, including the Joint
Engineering Data Management Information and Control System (JEDMICS), data exchange
standards, personnel computer software compatibility, Government network infrastructure,
CITIS accessibility, User training and support, data distribution statement codes, configuration
management, archive document delivery, and video teleconferencing capabilities.
• Transport external load of 4,500 pounds @ 4,000 ft PA, 95 deg F ambient temperature at a
combat radius of 135 km.
• Interoperability requirement to meet 100% of critical top level information exchange
requirements.
All requirements other than KPPs and Design to Unit Production Cost (DTUPC) were subject to
trade studies, allowing the contractor maximum flexibility in developing a CAIV-based solution
in order to satisfy the mission need.
The Prime Contractor monitors the subcontractor’s TPMs within the scope of their subcontracts.
Other IPTs track the significant parameters which pertain to their area of responsibility. The
64
UH-60M Systems Engineering Plan
Test IPT tracks the occurrence and resolution of system level test incident reports (TIRs). The
MEP IPT tracks the resolution of software problem change reports (PCRs).
External Lift Payload (lb.) [>=] KP 5396 450 19.9 ⇑ Projected weight empty decreased
0.8 lb.
Projected weight empty decreased
Self-Deployment (nm.) 1119 105 5.9 ⇑ 0.8 lb.
Sustained Cruise Airspeed OEI (KTAS) [>=] 10 10 6.6 ⇔
Primary Mission Combat Radius (km.) 23 22 4.7 ⇔
CSquared Endurance (hr.) [>=] 4. 4. 4.6 ⇔
Mid. Mission IGE TOGW, OEI (lb.) [>=] 1501 14790 1.5 ⇓ Projected weight empty decreased
0.8 lb.
Sustained Cruise Airspeed (KTAS) [>=] 14 14 0.6 ⇔
MTBMAF 1 1 2.7 ⇔
MTBMA 5 4 37.5 ⇔
MTBEMA 4. 3. 8.1 ⇔
MMH/FH 1. 2. 90.9 ⇔
* Status values are rounded. ** Trend is based on prior months report.
KEY: ⇓ Degrading Trend ⇑ Improving Trend Within Spec Not Within Spec but Mitigation Plan in place Not Within
Spec
65
UH-60M Systems Engineering Plan
Current SW LOC Final SW LOC Faults Memory Load ThroughPut Notes Approach to meet As of:
50% requirement
SLOC % ReUse SLOC % ReUse Total Open Closed Actual At Completion Actual At Completion
FMS 196,623 12% 196,623 12% 430 0 430 24% 24% 50% 50% (1), (6), (8) N/A Dec 5, 2006
(N)
M FDS 123,666 70% 124,848 70% 459 25 434 45% 45% 100% 100% (N) Dec 15, 2006
F TSA 77,923 80% 77,923 80% 247 4 243 12% 12% 60% 75% (N) Dec 15, 2006
D DMS 23,275 77% 23,275 77% 53 8 45 61% 61% 94% 94% (N) Dec 15, 2006
FCC 188,471 0% 188,471 0% 247 10 237 6% 6% 58% 58% (2) Dec 6, 2006
DCU 12,886 60% 12,886 60% 86 0 86 12% 12% 27% 27% (N) Dec 6, 2006
ADC 21,400 90% 21,500 90% 79 16 63 48% 52% 25% 25% (7), (N) Dec 15, 2006
DTS 56,300 76% 56,300 76% 79 9 70 43% 43% 98% 50% (3), (N) Dec 15, 2006
E Net Processor 18,698 60% 18,700 60% 52 0 52 N/A N/A Not Not (4), (N) Dec 15, 2006
S Applicable Applicable
H Mgmt Proc Loader 9,029 90% 9,029 90% 18 0 18 N/A N/A 10% 10% (N) Dec 15, 2006
Mgmt Processor 16,449 30% 16,449 30% 134 0 134 13% 13% 20% 20% (N) Dec 15, 2006
ICS 19,393 79% 19,776 98% 2 0 2 100% 100% 14% 14% (5), (N) Memory reserve Dec 15, 2006
will be met as
part of the Phase
3 ICS
configuration
Total UH-60M 764,113 39% 765,780 40% 1886 72 1814
66
UH-60M Systems Engineering Plan
CIs. This total traceability is resident within the Contractor DOORS@ database and can be
accessed by the Government upon request.
Formal technical reviews are preceded by a series of technical interchange meetings where
issues, problems and concerns are addressed. The formal technical review will not be for
67
UH-60M Systems Engineering Plan
problem solving, but to verify problem solving has been done. Technical reviews reduce
program risk and ease the transition to production by:
Under the terms of the UH-60M Integration and Qualification contract, Sikorsky is given the
responsibility to conduct system level reviews/meetings which are attended by subcontractors
and affected Government agencies to include as a minimum the UH PMO, ATEC, AED, TSM
Lift, and AMCOM Safety. Sikorsky is tasked with identifying and inviting non-Governmental
attendees based on the agenda. With concurrence of the UH PMO Chief Systems Engineer or
Technical Management Division Chief, the UH-60M PM identifies the subject matter experts
from the affected Government agencies based on the agenda, recommendations from the
organizations, and budgetary/space constraints. The contractor program manager and the
Government Project Manager serve as design review co-chairs. These reviews address the
following as a minimum:
• IPT progress
• program status
• CAIV
• trade studies
• cost and schedule goals
• technical performance
• TPMs
• software progress
• risk management
• configuration management
• process validation/producibility
• corrosion prevention
• path ahead to meeting objective requirements
• entrance/exit criteria for each system level review
• recording design decision rationale in the design database
68
UH-60M Systems Engineering Plan
69
UH-60M Systems Engineering Plan
70
UH-60M Systems Engineering Plan
e) Allocation of unit production costs to meet the requirements of paragraph 1.0 to the CI level
f) For computer software –related items, Submittal of the Interface Control Drawings (ICDs)
Documentation List
g) Review of all SRR action items and risk mitigation efforts
h) Updated TMDE requirement
i) Submittal of an initial Software FMECA
j) Submittal of updated Interface Requirements Specifications (IRSs)
k) Submittal of updated Software Requirements specifications (SRSs)
l) Submittal of preliminary top level Software Design Descriptions (SDDs) and Software Test
Plans (STPs)
m) Submittal of an updated JTA-Army compliance matrix that is ready for submittal to the Army
Digitization Office (ADO)
n) Updated software performance budgets (timing, sizing, and throughput)
o) Submittal of updated Depot Partnership Study Technical Report
p) Any additional criteria agreed to at SRR
71
UH-60M Systems Engineering Plan
72
UH-60M Systems Engineering Plan
73
UH-60M Systems Engineering Plan
2.6.1 CAIV
CAIV methodology is utilized by the UH-60M Modernization Program for reducing total
ownership cost and improving system performance through the utilization of aggressive unit
production costs and O&S cost objectives to meet user requirements. The UH-60M
Modernization Program has established a Cost Performance IPT (CP IPT), which includes
representation from each IPT, the Contractor, the User community, the Materiel Developer and
the Combat Developer, to achieve the most optimal outcome. Initially bi-weekly design to unit
cost (DTUC) meetings were utilized to monitor the cost basis throughout all significant design
stages. DTUC remains a tracked requirement within the Performance Specification due to the
fact that Specification changes result in DTUC adjustments. The CP IPT will make
recommendations to the PMWG and report, as a minimum, at all system level reviews. Cost is
considered during the SCN process. Resources are required for investment in the CAIV process
to perform tradeoff analyses, train key personnel, and ensure an overall understanding of CAIV
and its role in the UH-60M Modernization Program.
74
UH-60M Systems Engineering Plan
75
UH-60M Systems Engineering Plan
76
UH-60M Systems Engineering Plan
The Risk Management process, Figure 18, identifies a hierarchy of risks that may potentially
impact the successful achievement of program goals, objectives, thresholds, and/or established
program milestone exit criteria.
Risk
Risk Risk
2.6.2.1 Execution
Risk Management for the UH-60M Modernization Program is accomplished as an integral part
of the program management function. Risk is addressed as a single entity consisting of technical,
cost, schedule, and supportability throughout the entire program life cycle. The elements of the
risk management approach and the general guidelines for each element are described in
subsequent paragraphs.
77
UH-60M Systems Engineering Plan
with a final update for this phase prepared no later than six months prior to MS C. To date, all of
these updates have been accomplished.
2.6.2.1.2.1 Identification
Identification is the first step in the risk assessment process. The basic process involves
searching the UH-60M Modernization Program to determine those critical events that may
prevent the program from achieving its objectives. Risks will be identified by each IPT through
application of knowledge, best judgment and experience, lessons learned from similar programs,
and subject matter experts (SMEs). Following are the general procedures for risk identification:
• Understand the requirements and program performance goals.
• Determine technical/performance risks related to engineering and manufacturing processes.
• Determine technical/performance risks associated with the product in the critical areas.
• Identify cost, schedule, and supportability issues/risks.
2.6.2.1.2.2 Analysis
Risk analysis is an evaluation of the identified risk events to determine the likelihood of the
events occurring and their consequences, to assign a risk rating based on the program criteria,
and to prioritize risks. Each IPT is responsible for analyzing those risk events that they identify.
Techniques to support risk analysis include trade studies, test results, modeling and simulation,
expert opinion, system engineering analysis, risk assessments, or any other accepted analysis
technique. The risk analysis process involves:
• Identification of WBS elements.
• Evaluation of WBS elements using the risk areas (Figure 20) to determine risk events.
• Assignment of likelihood/probability and consequence to each risk event to establish a risk
rating.
• Prioritization of each risk event relative to other risks.
Each IPT will evaluate each risk event in terms of consequence to technical performance,
schedule, cost, or impact to other IPTs and assign a level for the consequence. Figure 19 will be
used when assigning values for likelihood/probability and consequence to risk events.
78
UH-60M Systems Engineering Plan
RISK LEVELS
ASSESSMENT GUIDE
HIGH - Unacceptable Major
e Disruption likely. Different
Likelihood Criteria approach required. Priority
d
Likelihood
management attention
What Is The Likelihood required.
Level
The Risk Will Happen? c
MODERATE - Some
a Remote
disruption. Different approach
b Unlikely b may be required. Additional
c Likely management attention may be
d Highly Likely a needed.
e Near Certainty 1 2 3 4 5
Consequence LOW - Minimum impact.
Minimum oversight needed to
ensure risk remains low.
Consequence Criteria
(Given the Risk is Realized. What is the Magnitude of the Impact?)
Level Technical and/or Schedule and/or Cost and/or Impact on Other Team
Performance
1 Minimal or No Impact Minimal or No Impact Minimal or No Impact None
Risk handling methods will be integrated into program planning and scheduling. IPTs will
develop these actions and events in the context of the WBS elements, establishing links between
79
UH-60M Systems Engineering Plan
them and specific work packages to simplify determinations of impact on cost, schedule,
supportability, and performance.
c
AWR Process S
SE
b
Likelihood
Unscheduled Maintenance C
a Logistics
1 2 3 4 5
Consequence
FIGURE 20. RISK AREAS
80
UH-60M Systems Engineering Plan
properly relates technical, cost and schedule accomplishments; (c) are valid, timely, and able to
be audited; and (d) provides managers with information at a practical level of summarization.
This internal management system is the Sikorsky Planning and Control System (SPACS). It is
utilized to identify variances (cost, schedule, technology, workforce) at the Work Package level.
Through System Engineering processes, the contractors’ work is broken down into measurable
work packages which align with the UH-60M WBS. These work packages are assigned budget
and schedule. Progress in executing these work packages are continuously tracked by the
contractor’s CAMs and reported monthly. These impacts are identified and rolled up to the next
level of WBS management. Eventually these impacts are captured in the IMS and the IMP and
be presented at an Integrated Baseline Review (IBR). EVM focus is one of the four major areas
of the program management process: organizing and staffing, planning, directing and
controlling. EVM is used during SDD Contract and on the LRIP Contract.
2.6.3.2 Planning
Planning is considered the most important of all of the programmatic functions. The UH-60M
plan provides the basis for the development of a meaningful, supportable budget in an effectively
organized and staffed program office. It defines a continuous process of looking to the future. It
evaluates work to be done (scope), the order and time necessary for successful accomplishment
of the work (schedule), and the resources necessary to accomplish the work (cost). Planning will
continue throughout the life of this effort. Since it is an ongoing process, a “baseline” has been
established in order to evaluate performance. The baseline represents a “snapshot” of the plan
(scope, schedule, and cost) at a particular point in time and retained as a tool for performance
evaluation. This baseline allows measuring any changes to the assignment of causes and update
of plans to reflect the changes. The “configuration management” process serves to maintain
scope control. In the UH-60M Modernization Program there is a direct relationship between the
configuration baseline management and scope changes in the earned value management process.
Configuration changes are valid reasons for baseline changes. Scheduling is also an important
aspect of planning. The UH-60M Modernization Program established a master ‘critical path’
program schedule that networks the important program activities and milestones. Schedules
contain current and baseline data sets. The current data continuously reflects progress and
changes to future plans, while the baseline remains stable. The baseline data ties to approved
completion times and events, while the current schedule shows expectations. The baseline has
81
UH-60M Systems Engineering Plan
been changed to reflect approved changes in times or events. The current Estimate At
Completion (EAC) reflects the cost plan. The Budget At Completion (BAC) represents the cost
baseline used for performance evaluation and earned value calculation. The budget ties to the
approved cost for the effort. Budgets were changed as necessary to reflect approved changes in
scope, schedule, or the cost of the effort.
2.6.3.3 Directing
The content of the awarded contracts, as well as changes and modifications to those contracts,
direct and control this Program. In addition, the PM has used other contract vehicles to direct
government organizations in support of the program. Examples of such vehicles include Military
Interdepartmental Purchase Requests, project orders and work requests, Memoranda of
Agreement, and Memoranda of Understanding. Controlling the PM’s discretionary decision
ability is limited and effectively impacts (1) the program scope (what tasks will be done), (2) the
schedule (when and what will be done), and (3) the program funding or budget (the cost of what
will be done when). Upon detection of a deviation from the program plan, a control mechanism
can be be activated to bring the system back into line. The PM’s control mechanisms include
provisions contained in the contract to impact contract performance such as the change clause
(revise, delete scope or requirements), incentives (monetary - on cost, schedule, and technical
performance), award fees (additional fee awarded for excellence in management areas or
reduction of fee awarded for poor performance), and when appropriate, suspension of progress
payments (punitive - resolution of issue required) or possibly termination of the contract
(punitive – failure to perform).
2.6.3.4 Controlling
EVM tasks in the program control phase include obtaining the program management documents
(e.g., SOW, Mission Needs Statement (MNS) and ORD, and Program Acquisition Baseline) and
reviewing and understanding the key features that affect the program. Most important is
obtaining contractor schedules/reports that are provided through the CDRL, comparing the
contractor reports to the program baseline and reviewing and comparing the monthly CDRL
submissions such as the CPR and the quarterly Contractor Flight Safety Release (CFSR) and
being aware of the changes, from month to month, and maintaining an audit trail of those
changes. The Program performs trend analysis on the data and compares the schedule trends to
the CPR trends. The Army will review the program contract and interview functional team
members to determine the program requirements, milestones and specifications as they relate to
schedules. the Army will also conduct on-site visits or teleconferencing to other government
agencies, prime contractor, subcontractor and associate contractors to develop an overall
understanding with all parties of the program requirements and program status. Continuing
analyses of the “critical path” will be performed to determine high-risk areas of the program and
identify and analyze alternate (potential) critical paths. Schedule changes are being documented
for historical purposes. If warranted, lower level schedules will be developed for further
analyses. The UH-60M Modernization Program will evaluate the cost and schedule data using
stochastic methods (i.e., simulation). The key features of the program are addressed with
contractor, subcontractor and customer. The contractor will provide data in electronic transfer
format. Electronic transfer is encouraged to promote information exchange by participating in
team meetings, program reviews, schedule boards, and scheduling side meetings when
82
UH-60M Systems Engineering Plan
warranted. All schedule changes will be documented and an audit trail maintained for the
Program Management Office and to assist in any reviews or audits by appropriate agencies.
Earned value analysis is viewed by the PM as a business management tool that results in an
efficient, optimized, successful program. Similarly, earned value procedures are essential for the
identification of “early warning signs” for problems. These procedures will identify where the
problem is, how much time and money is being used, and provide a prediction for the cost at
completion.
All programmatic tools are similarly mapped to ensure information is available and can be
associated with appropriate outputs from other systems. This ensures that all technical
performance, cost, and schedule issues are included in the different reporting systems used by
the UH-60M PM and the Contractor. Each Integrated Product Team (IPT) applies this data to
the risk elements for proper risk assessment and mitigation. Each IPT develops risk items and
provides periodic inputs in the form of risk charts for ongoing assessments of Program risk. This
process has been documented within the Program and is conducted IAW the Risk Management
Plan.
The information obtained during the analysis process is presented to the appropriate IPT leader
on a monthly basis to augment other technical performance, cost, and schedule reports. Data
developed from the monthly cost account analyses is summarized in text and graphic format for
UH-60M IPT leaders. The data provides technical and business staff with timely information
that is critical in such areas as technical interchange, rationale for decision making, validation of
cost and schedule trends and forecasts, and serves as a basis for potential work-around plans to
mitigate identified risks. Monthly cost management reviews are conducted which include an
overview of program status in terms of cost and schedule trends, life cycle cost, and focus on
program risk elements and other resource drivers, as well as, on required management actions.
The review provides senior management with a summary of monthly-integrated cost analysis for
such activities as cost reporting analysis, risk management assessments, life cycle phase
activities, CAIV program, program funding execution, and review of open action items. Areas
of emphasis for cost account analysis vary throughout the life of the UH-60M Modernization
Program. The process employed within the UH-60M Modernization Program is flexible and
robust enough to accommodate changes in known or potential risk areas.
The EGI being developed by PM AME will be installed on the CH-47 Chinook and the AH-64
Apache Longbow. The UH-60M will use two of these EGIs for redundancy. The H-764G EGI,
integrates the functions of a GPS and an INS into one single line replaceable unit (LRU). The
system is an all-attitude navigation system providing outputs of linear and angular acceleration,
83
UH-60M Systems Engineering Plan
velocity, position attitude (roll, pitch, and platform azimuth), magnetic and true heading, altitude,
body angular rates, time tags and time. The EGIs provide precise positioning information
enabling precise area navigation for both tactical and IFR approaches. The EGIs will replace the
legacy Doppler/GPS Navigation System on the BLACK HAWK UH-60s.
84
UH-60M Systems Engineering Plan
the UH Fleet. The Advanced Symbol Generator (ASG) replaces the Signal Data Converter
(SDC) and provides the bussed interface to the UH-60M.
3.0 Summary
The UH-60M approach to effective system engineering management is threefold. First, it
provides an experienced, system oriented, engineering organization with the direct responsibility
and authority to supervise the conduct of the technical elements of the program. Second, it
implements system engineering through effective planning, analysis, evaluation and
documentation. Third, it provides control through a series of checks and balances that function
as both internal audits and formal program reviews. These system engineering responsibilities
will be coordinated with the SE IPT. System engineering checks and balances are provided by
schedule, cost and technical risk management that identify exceptions to approved work plans.
The process then requires the development of recovery plans for all identified exceptions. With
the integration of test planning activities into the overall system engineering effort, additional
emphasis is placed on high risk areas to ensure program success.
85
UH-60M Systems Engineering Plan
Acronyms
A2C2S Army Aviation Command and Control System
AATD Advanced Aviation Technology Directorate
ADO Army Digitization Office
AED Aviation Engineering Directorate
AES Aviation Electronic Systems
AFCC Advanced Flight Control Computer
AFCS Automatic Flight Control System
ALSE Aviation Life Support Equipment
AMBL Air Maneuver Battle Lab
AMCOM Aviation and Missile Command
AMDF Aviation Master Data File
AMOGS Aviation Medical Oxygen Generating System
AMPM AMSAA Maturity Projection Model
AMPM AMSAA Maturity Projection Model
AMPS/JMPS Army Mission Planning Software/Joint Mission Planning Software
AMRDEC Aviation and Missile Research, Development and Engineering Center
APB Acquisition Program Baseline
APEX Advanced Prototyping and Experimenting
APM Assistant Project Manager
AQ Airworthiness Qualification
AQSOW Airworthiness Qualification Statement of Work
ARI Aviation Restructure Initiative
ARINC Aero Nautical Radio Incorporated
ASARC Army Systems Acquisition Review Committee
ASE Aviation Survival Equipment
AST ATEC System Team
ATCOM Advanced Tactical Combat Model
ATEC Army Test and Evaluation Command
ATTC Aviation Technical Test Center
AUC Average Unit Cost
AV Avionics
AVC Active Vibration Control
Aveh Air Vehicle
AVUM Aviation Unit Maintenance
BAC Budget at Completion
BFT Blue Force Tracker
BHIVE Battlefield Highly Immersive Virtual Environment
BHPS BLACK HAWK Players Station
BIM Blade Integrity Monitoring
BIT Built In Test
C2 Command and Control
C4ISR Command, Control, Communications, Computer, Intelligence,
Surveillance and Reconnaissance
CAAS Common Avionics Architecture System
86
UH-60M Systems Engineering Plan
87
UH-60M Systems Engineering Plan
88
UH-60M Systems Engineering Plan
89
UH-60M Systems Engineering Plan
90
UH-60M Systems Engineering Plan
91
UH-60M Systems Engineering Plan
RR Risk Reduction
RSOI Reception Staging and Onward Integration
SAASM Selective Availability Anti-Spoofing Module
SAFE Stochastic Analysis of Fragmenting Effects
SAS Stabilization Augmentation System
SASO Stability and Support Operations
SATCOM Satellite Communications
SCN Specification Change Notice
SDD System Design Description
SDD System Development and Demonstration
SDP Software Development Plan
SDS Smart Dispenser System
SE Systems Engineering
SEMP System Engineering Master Plan
SEP System Engineering Plan
SER Sikorsky Engineering Report
SER System Evaluation Report
SES Sikorsky Engineering Specifications
SES Sikorsky Engineering Specification
SFR System Functional Review
shp Shaft Horsepower
SIL System Integration Lab
SLAP Service Life Assessment Program
SLS Sea Level Standard
SME Subject Matter Expert
SOA Special Operations Aviation
SoS System of Systems
SOW Statement of Work
SPACS Sikorsky Planning and Control System
SQASH Stochastic Quantitative Analysis of System Hierarchies
SQCR Sequencer
SRR System Requirements Review
SRS Software Requirements Specification
SS&DD Simulation Support and Development Directorate
SSAA System Security Accreditation Agreement
SSDD System/Segment Design Document
SSPP System Safety Program Plan
STD Software Test Description
STEP Simulation, Test, and Evaluation Process
STP Software Test Plan
SW Software
SWCI Software Configuration Item
T&E Test & Evaluation
TACAN Tactical Air Navigation
TAPO Task Force Advanced Programs Office
TDP Technical Data Package
TEMP Test & Evaluation Management Plan
TEPP Test and Evaluation Program Plan
92
UH-60M Systems Engineering Plan
93
Attachment 1. Statutory and Regulatory Information Requirements
STATUTORY INFORMATION REQUIREMENTS
APPLICABLE WHEN
INFORMATION REQUIRED PROGRAM DOCUMENT TITLE
STATUTE REQUIRED
The following information requirements are statutory for both MDAPs and MAIS acquisition programs
Consideration of Technology 10 U.S.C. 2364 Milestone (MS) A UH-60M Technology Maturity
Issues MS B Assessment
MS C
Market Research 10 U.S.C. 2377 Technology N/A, conducted at Milestone B,
15 U.S.C. 644(e)(2) Opportunities information synopsized in the ASR.
User Needs
MS A
MS B
CCA Compliance 40 U.S.C. Subtitle III, MS A (MAIS only) Chief Information Officer
(All IT–including NSS) (See Sec. 8088, Pub.L. 107-248, Program Initiation Assessment
enclosure 4, Table E4.T1.) for Ships
MS B
MS C (if equivalent
to Full-Rate
Production DR)
Full-Rate
Production DR
Post-Deployment Performance 5 U.S.C. 306, reference Full-Rate N/A at Milestone C, will be
Review 40 U.S.C. 11313, Production DR developed for the FRP DR
Registration of mission-critical Sec. 8088(a), Pub.L. 107- Program Initiation Registration Of Mission-Critical
and mission-essential 248, for Ships And Mission-Essential Information
information systems, RCS: DD- Pub.L. 106-398, Section MS B (if Program Systems
C3I(AR)2096 811 Initiation)
MS C (if Program
Initiation or if
equivalent to Full-
Rate Production
DR)
Full-Rate
Production DR
(After initial
registration, shall be
updated quarterly)
Benefit Analysis and 15 U.S.C. 644(e) MS B N/A Conducted at Milestone B
Determination (applicable to MS C (if no MS B)
bundled acquisitions) (part of
acquisition strategy)
Beyond-LRIP Report (OSD 10 U.S.C. 2399 Full-Rate N/A at MS C, will be developed for
OT&E Oversight programs only) Production DR the FRP DR
Programmatic Environment 42 U.S.C. 4321 Program Initiation Programmatic Environment Safety
Safety and Occupational Health for Ships and Occupational Health Evaluation
Evaluation (PESHE) (Including MS B (PESHE)
National Environmental Policy MS C
Act (NEPA) Compliance Full-Rate
Schedule) Production DR
Spectrum Certification 47 U.S.C. 305 MS B Joint Spectrum Center 1494
Compliance (DD Form 1494) Pub. L. 102-538, 104, MS C (if no MS B)
(applicable to all 47 U.S.C. 901-904,
systems/equipment that require DoD Directive 4650.1,
utilization of the electromagnetic OMB Circular A-11, Part 2,
spectrum)
94
APPLICABLE WHEN
INFORMATION REQUIRED PROGRAM DOCUMENT TITLE
STATUTE REQUIRED
The following information requirements are statutory but are not applicable to MAIS acquisition programs
Selected Acquisition Report 10 U.S.C. 2432 Program Initiation SELECTED ACQUISITION
(SAR)— Reports Control for Ships REPORT (RCS: DD-A&T(Q&A)
Symbol (RCS): MS B and annually 823), PROGRAM: UH-60M
DD-AT&L(Q&A)823 (MDAPs thereafter Recap/Upgrade
only) End of quarter
following
MS C
Full-Rate
Production DR
Breach
Unit Cost Report (UCR)— 10 U.S.C. 2433 Quarterly Contained in SAR (see above)
RCS: DD-AT&L(Q&R)1591
(MDAPs only)
Live-Fire Waiver & Alternate 10 U.S.C. 2366 MS B N/A - Prepared at Milestone B –
LFT&E Plan (N/A for AISs) Live Fire Testing on-going
(Covered Systems only)
Industrial Capabilities (part of 10 U.S.C. 2440 MS B UH-60M Industrial Capability
acquisition strategy) MS C Assessment
(N/A for AISs)
LRIP Quantities 10 U.S.C. 2400 MS B Contained in ADM, 31 MAR 05
(N/A for AISs)
Independent Cost Estimate 10 U.S.C. 2434 Program Initiation CAIG ICE performed as part of
(CAIG) and Manpower Estimate for Ships (cost Milestone preparation
(reviewed by OUSD(P&R)) assessment only)
(N/A for AISs) (MDAPs Only) MS B Manpower Estimate Report for
MS C Block 1, UH-60M BLACK HAWK
Full-Rate Utility Helicopter
Production DR
LFT&E Report, 10 U.S.C. 2366 Full-Rate N/A - will be written following
RCS: DD-OT&E(AR)1845 Production DR ending of live fire
(LFT&E-covered programs
only)
Electronic Warfare (EW) T&E Sec. 220 of Pub. L. 103- Annually N/A – UH-60M is not an EW
RCS: DD-AT&L(A)2137 160 as amended by Sec. system
(EW programs on OSD T&E 214 of Pub. L. 103-337
Oversight List)
Core Logistics Analysis/Source 10 U.S.C. 2460, MS B UH-60M Core Depot Logistics
of Repair Analysis (part of 10 U.S.C. 2464, MS C (if no MS B) Analysis
acquisition strategy) 10 U.S.C. 2466
Competition Analysis (Depot- 10.U.S.C. 2469 MS B Conducted at Milestone B, reviewed
level Maintenance $3M rule) MS C (if no MS B) at Milestone C
(part of acquisition strategy)
95
APPLICABLE WHEN
INFORMATION REQUIRED PROGRAM DOCUMENT TITLE
STATUTE REQUIRED
The following information requirements are statutory for MDAPs and
are applicable to MAIS acquisition programs by DODI 5000.2
Technology Development Sec. 803, Pub.L. 107-314 MS A UH-60M Technology Maturity
Strategy (TDS) MS B Assessment
MS C
Acquisition Program Baseline 10 U.S.C. 2435 Program Initiation BLACK HAWK UPGRADE (PNO:
(APB) for Ships 341), dated 31 MAR 05
MS B
MS C (updated, as
necessary)
Full-Rate
Production DR
Program Deviation Report 10 U.S.C. 2435 Immediately upon a N/A
program deviation Previous reports on file
Operational Test Plan 10 U.S.C. 2399 Prior to start of Being developed for IOTE
(DOT&E Oversight Programs operational test and
only) evaluation
Cooperative Opportunities (part 10 U.S.C. 2350a MS B Reviewed and in approved ASR (31
of acquisition strategy) MS C MAR 05)
The following information requirements are statutory for MAIS acquisition programs and
are not applicable to MDAPs
Certification of compliance with Sec. 8088, Pub.L. 107-248 MS A N/A – not a MAIS program
the Clinger-Cohen Act MS B
MS C (if equivalent
to Full-Rate
Production DR)
Full-Rate
Production DR
Certification of compliance with Sec. 8088, Pub.L. 107-248 MS A N/A – not a MAIS program
the Financial Management MS B
Enterprise Architecture MS C (if equivalent
(Financial Management MAIS to Full-Rate
acquisition programs only) Production DR)
Full-Rate
Production DR
96
REGULATORY INFORMATION REQUIREMENTS
WHEN
INFORMATION REQUIRED SOURCE PROGRAM DOCUMENT TITLE
REQUIRED
AoA Plan DODI 5000.2 Concept Decision N/A – Past Concept Decision
ICD CJCSI 3170.01, Concept Decision N/A – ORD developed at Milestone
MS A B
MS B
MS C (if Program
Initiation)
CDD CJCSI 3170.01 Program Initiation N/A – ORD developed at Milestone
for Ships B
MS B
CPD CJCSI 3170.01 MS C The ORD For Recapitalization Of
The UH-60 BLACK HAWK Utility
Helicopter Fleet retained its identity
as an ORD rather than being
reformatted into a Capabilities
Production Document in accordance
with the guidance in the Chairman
of the Joint Chiefs of Staff
Instruction (CJCSI), 3170.01C, 12
March 2004 to support Milestone C.
Acquisition Strategy DODI 5000.2 Program Initiation ACQUISITION STRATEGY
for Ships FOR THE BLOCK 1, UH-60M
MS B BLACK HAWK
MS C MODERNIZATION PROGRAM,
Full-Rate approved 31 MAR 05
Production DR
Analysis of Alternatives (AoA) DODI 5000.2 For MDAPs 2005 Update to the UH-60
- MS A Modernization AoA, TRADOC
- Program Initiation System Manager – Lift, United
for Ships States Army Aviation and
- MS B Warfighting Center, Ft. Rucker,
- MS C (updated as Alabama, 11 February 2005
necessary)
For MAIS
- MS A
- MS B (or
equivalent)
- Full-Rate
Production DR (or
equivalent)
System Threat Assessment DoD Directive 5105.21 Program Initiation UH-60 Systems Threat Assessment
(AIS programs use published for Ships Report
Capstone Information MS B
Operations System Threat MS C
Assessment)
(validated by DIA for ACAT ID
programs)
Technology Readiness DODI 5000.2 Program Initiation UH-60M Technology Maturity
Assessment for Ships Assessment
(preliminary
assessment)
MS B
MS C
Independent Technology DODI 5000.2 MS B N/A – Memo from DUSD (S&T) to
Assessment (ACAT ID only) MS C OIPT and DAB concurring with
(if required by DUSD(S&T)) TMA
97
WHEN
INFORMATION REQUIRED SOURCE PROGRAM DOCUMENT TITLE
REQUIRED
Command, Control, DoD Instruction 4630.8 and Program Initiation UH-60M ISP/C4I Support Plan
Communications, Computers, DoD Directive 4630.5, for Ships
and Intelligence Support Plan MS B
(C4ISP) (also summarized in the MS C
acquisition strategy)
Command, Control, CJCSI 6212.01, Full-Rate N/A at MS C – will be prepared for
Communications, Computers, DODI 5000.2 Production DR FRP DR
and Intelligence (C4I)
Supportability Certification
Interoperability Certification CJCSI 6212.01, DODI Full-Rate N/A at MS C – will be prepared for
5000.2 Production DR FRP DR
Affordability Assessment DODI 5000.2 MS B Conducted as part of Milestone
MS C Decision by Army and OSD PA&E
Economic Analysis (MAIS only) DODI 5000.2 MS A (may be N/A – not a MAIS program
combined with
AoA)
MS B (or
equivalent)
Full-Rate
Production DR (or
equivalent)
Component Cost Analysis DODI 5000.2 For MDAPs Army Cost Position was developed
(mandatory for MAIS; as - Program Initiation as part of Milestone C preparation
requested by CAE for MDAP) for Ships
- MS B
- Full-Rate
Production DR
For MAIS
- Any time an
Economic Analysis
is required—either
by statute or by the
MDA
Cost Analysis Requirements DODI 5000.2 For MDAPs UH-60M Cost Analysis
Description - Program Initiation Requirements Description
(MDAPs and MAIS Acquisition for Ships
Programs only) - MS B
(CARDs shall be prepared - MS C
according to the procedures - Full-Rate
specified in enclosure 6 of this Production DR
Instruction) For MAIS
- Any time an
Economic Analysis
is required—either
by statute or by the
MDA
Test and Evaluation Master Plan DODI 5000.2 MS A (test and Test And Evaluation Master Plan
(TEMP) evaluation strategy For The Recapitalization/ Upgrade
only) Of The UH-60 BLACK HAWK
MS B Utility Helicopter Fleet
MS C (update, if
necessary)
Full-Rate
Production DR
98
WHEN
INFORMATION REQUIRED SOURCE PROGRAM DOCUMENT TITLE
REQUIRED
Operational Test Agency Report DODI 5000.2 MS B System Evaluation Report
of Operational Test and MS C Uh-60m BLACK HAWK
Evaluation Results Full-Rate Utility Helicopter produced by
Production DR U.S. Army Test and Evaluation
Command
Component Live-Fire Test and DODI 5000.2 Completion of Live N/A at MS C, will be completed
Evaluation Report (N/A for Fire Test and after completion of life fire test and
AISs) (Covered Systems Only) Evaluation evaluation
Program Protection Plan (PPP) DoD Directive 5200.39, MS B (based on PPP not created. Analysis found we
(for programs with critical DODI 5000.2 approved had no CPI of our own. Memo to
program information) (includes requirements in AAE written indicating that analysis
Anti-Tamper Annex) (also CDD) had been conducted (6 JAN 05)
summarized in the acquisition MS C
strategy)
Exit Criteria DODI 5000.2 Program Initiation In ADM, 31 MAR 05
for Ships
MS A
MS B
MS C
Each Review
Defense Acquisition Executive DODI 5000.2 Quarterly Defense Acquisition Executive
Summary (DAES) Upon POM or BES Summary (DAES) Report, BLACK
RCS: DD-AT&L(Q)1429 submission HAWK UH-60M (PNO: 341)
Upon unit cost
breach
ADM DODI 5000.2 Program Initiation BLACK HAWK Upgrade (UH-
for Ships 60M) Milestone C acquisition
MS A Decision Memorandum (ADM) 31
MS B MAR 05
MS C
Each Review
Earned Value Management OMB Circular A-11, Part 7, Implement EVMS Monthly reports received from
Systems (EVMS) DODI 5000.2 guidelines in prime contractor, multiple IBRs
ANSI/EIA-748- conducted to date
1998 and conduct
Integrated Baseline
Reviews
(applies to
contracts/agreement
s for RDT&E over
$73 million and
procurement or
O&M over $315
million, both in FY
2000 constant
dollars)
99
Attachment 2. IPT Charters
100
AUTHORITY The PMWG has complete authority to
direct the activities of the program as
well as serve as the final authority to
resolve questions or disputes.
ACCOUNTABILITY The PMWG is accountable to the UHPO
and PEO Aviation for the delivery of the
UH-60M system consistent with funding
and program.
PRODUCTS PMWG Charter
PRODUCTS APPROVAL
______________________ _______
Gov’t UH-60M PM Date
____________________ _______
Contractor UH-60M PM Date
TEAM COMPOSITION The PMWG is comprised of the UH-
60M PM and his/her Sikorsky Aircraft
Corporation counterpart.
101
EXECUTIVE STEERING GROUP CHARTER
PURPOSE This group is responsible for program
oversight, direction, and providing
resources.
SCOPE OF WORK The ESC has the responsibility for
programmatic oversight of the UH-60M
development and production.
INTERFACES Communication between the members of
the Executive Steering Group is
maintained through weekly telecoms.
DESCRIPTION OF TASKS This program integrates multiple
products managed by other Government
agencies and project offices. The UH-60
PM and his staff will continuously focus
their attention on implementing a
program to meet the user’s needs while
incorporating cost reduction initiatives
and work share arrangements as
appropriate.
AUTHORITY The UH-60 PO exercises programmatic,
technical, logistical, and financial control
of the UH-60M Modernization Program.
ACCOUNTABILITY The ESC is accountable to the User
community, the leadership within the
Office of the Secretary of Defense,
and the Department of the Army.
PRODUCTS ESC Charter
PRODUCTS APPROVAL ____________________ _______
PEO Aviation Date
____________________ _______
Sikorsky AC PM Date
____________________ _______
UHPO Date
102
ENGINEERING IPT CHARTER
PURPOSE The Engineering IPT will coordinate the
efforts of the Systems Engineering (SE)
sub-IPT, the Air Vehicle (AV) sub-IPT,
the Mission Equipment Package (MEP)
sub-IPT and the Integrated
Manufacturing (IM) sub-IPT to ensure
that the allocated design achieves a
system solution that meets spec and
schedule requirements of the contract.
SCOPE OF WORK The Engineering IPT will ensure that
aircraft delivered to test are built to
identified standards and are compliant
with product specifications.
The Chief Engineer also budgets the
funding for engineering support from
other government agencies supporting
the UH-60M Modernization Program
technical analyses to include
programmatic contract support.
INTERFACES The Chief Engineer’s counterpart within
the prime contractor’s organization has
similar responsibilities over the prime
contractor’s engineering staff and
provides subcontractors with technical
direction. The UH-60M Chief Engineer
coordinates with the chief engineers of
other government programs which
provide GFE to the UH-60M in order to
coordinate and resolve technical
interface issues and funding as
necessary.
DESCRIPTION OF TASKS • Identify processes and standards for
systems integration.
• Set overall technical objective within
contract requirements, and assist sub-
IPTs in identifying intermediate goals
leading to the objective system.
• Ensure that each sub-IPT is properly
resourced to accomplish its goals.
• Provide timely flow of information to
coordinating and superior IPTs.
103
AUTHORITY The chief engineer interfaces with the
other IPT leads and has the final
approval authority over technical issues
within the UH-60M Modernization
Program .
ACCOUNTABILITY The Engineering IPT is led by the UH-
60M Chief Engineer who reports
directly to the UH-60M Product
Manager and Deputy Product Manager.
PRODUCTS
PRODUCTS APPROVAL Chief Engineer, UH-60M
Deputy PM, UH-60M
PM, UH-60M
TEAM COMPOSITION Chief Engineer, UH-60M
Sub-IPT Leads
AED
User Rep
104
Systems Engineering Sub-IPT Charter
PURPOSE The Systems Engineering sub-IPT
develops and executes an
interdisciplinary program plan to ensure
an integrated and life cycle balanced set
of system product and process solutions
to satisfy the warfighter’s requirements.
SCOPE OF WORK The work breakdown structure will
define which elements fall under the
direct responsibility of the SE IPT. As
listed in the RAM, these WBS elements
address air vehicle level analyses, test,
and integration activities that could not
be allocated or assigned to a specific
team such as Automatic Flight Control
or Fire Control.
INTERFACES The SE Team interfaces with all
program teams, the program
management team, and functional
management within the contractor team,
PM Office and the customer.
DESCRIPTION OF TASKS • Executing and managing a
structured systems engineering
approach that provides a life cycle
balanced set of system product and
process solutions.
• Performing system requirements
analysis, managing changes to the
system requirements within contract
requirements, and tracking
achievement of the system
requirements.
• Facilitating the development and
completion of entrance and exit
criteria for major performance-
related program reviews (e.g. PDR,
CDR) as they relate to technical
issues.
• Conducting, in conjunction with
other IPTs, trade studies and
analyses that consider cost, schedule,
and performance as independent
variables.
• Conducting technical risk
105
assessments, developing mitigation
plans, and tracking technical risk
status
• Maintaining and updating the SEP so
that it remains a living document
that defines the technical aspects of
government and contractor
programmatic activities and
responsibilities. Metric development
evolves from the IPTs.
RESPONSIBILITIES The SE Team will manage coordinating
the delivery of a technically compliant
UH-60M on cost & schedule to the U.S.
Army for Initial Operational Test &
Evaluation.
AUTHORITY Within the contracted SOW, the SE
Team has the authority to affect the
technical decisions which:
1. Can’t reach a consensus within a
given IPT,
2. Affect more than a single IPT,
3. Cross organizational boundaries, or
4. Require air vehicle level trade offs to
be considered. The SE Team is a vehicle
to promote consensus between the
affected IPTs based on a systems level
review of available data. Carry forward
SE IPT decisions to the Project Office
for concurrence.
ACCOUNTABILITY The SE Sub-IPT lead will focus on
his/her respective technical areas and
report directly to the chief engineer.
PRODUCTS System Integration CDRLs, SE Charter
PRODUCTS APPROVAL Govt UH-60M PM
Contractor UH-60M PM
Govt Chief Engineer
Contractor Chief Engineer
SE IPT Lead
TEAM COMPOSITION Core Team Members:
• UH-60M Systems Engineer
• AED representative
• System engineering staff (as req’d)
• Contractor counterparts
106
Business Management (BM) IPT Charter
PURPOSE The BM IPT executes the administration for all
contractual and financial matters for the UH-60M
program.
SCOPE OF WORK The BM IPT will manage the Work Breakdown
Structure, Performance Measurement Baseline,
Earned Value Management System, procurement
management, program analysis and reporting along
with baseline cost estimates.
The BM IPT is also responsible for coordinating
legal matters with appropriate parties.
The BM IPT provides counsel and
recommendations to the OIPT as necessary.
INTERFACES The BM IPT interfaces with the Engineering IPT,
Logistics IPT, and Test IPT.
DESCRIPTION OF The BM IPT will manage the following:
TASKS Management of Milestone Requirements
documentation
Earned Value Management System
Action Items database
Personnel Rosters
Meeting Minutes
Program Library
Baseline Cost Estimates
Budgets
Historical Records of Funding and Program
Changes
Coordination of contract-related matters
Execution of the Integrated Baseline Review
Management of the Performance Measurement
Baseline
107
PRODUCTS CDRLs, Cost Performance Report (CPR), PMB,
CFSR, CARD, BM IPT Charter
PRODUCTS APPROVAL Program Manager
Contractor Program Manager
Govt Contractor
Govt Chief Engineer
Contractor Chief Engineer
SE IPT Lead
TEAM COMPOSITION Core Team Members:
• Business Management IPT Lead
• Contractor Business Management IPT Lead
• Procuring Contracting Officer
• Program Analysts
• Cost Analysts
108
Test IPT Charter
PURPOSE To support the component and
subsystem qualification test effort for
the UH-60M weapons system by
coordinating with all IPTs on test issues;
and to manage the system level test
program.
SCOPE OF WORK Coordinate with segment IPTs on:
- Risk Reduction test
- Component qualification test
- Subsystem qualification test
- Systems bench test
- Live Fire test
Plan, conduct, and report on:
- Combined Test Team operations
- Aircraft flight test
- Government technical and operational
test
The Test IPT has primary responsibility
for the work contained in WBS X.X
INTERFACES The Test IPT interfaces with the system
design IPTs to establish test methods for
component and subsystem testing, and
to:
1. Establish system level test
requirements
2. Prioritize objectives necessary to
support aircraft qualification
3. Obtain feedback from IPTs in order
to evaluate and reprioritize goals to
deliver a safe, qualified aircraft.
109
- Coordinate on component and
subsystem qualification test
requirements for vendor supplied items;
monitor subcontractor qualification
program
- Plan, conduct, and report on
subsystems bench testing
- Plan, conduct, and report on flight test
program
- Coordinate Government test activities
under the Combined Test Team
- Monitor test program status through
the Cost/Schedule Control System
Criteria
RESPONSIBILITIES The Test IPT will manage the conduct of
the system level test program. The
Government Test Coordinator and the
Assistant Product Manager for T&E are
responsible for the Government test
program and Combined Test Team
operations. The IPT will manage the
flight test program and coordinate effort
between the contractor and Government
testers.
AUTHORITY The Test IPT has authority over
resource allocation and scheduling of
flight test activities.
ACCOUNTABILITY The Test IPT is accountable to the
Product Management Overarching IPT
and the Government and company
Program Managers.
PRODUCTS The primary product of the Test IPT is a
fully qualified UH-60M Weapons
System. To this end, the Test IPT
produces system level qualification test
plans and test reports, test schedules and
budgetary reports.
PRODUCTS APPROVAL Govt Program Manager
Contractor Program Manager
Govt IPT Leader
Contractor IPT Leader
110
Logistics IPT Charter
PURPOSE The purpose of this Charter is to
establish and empower a UH-60M
Logistics Integrated Product Team.
SCOPE OF WORK The Logistics IPT will be empowered to
develop and implement a supportability
system which will ensure the UH-60M is
reliable, maintainable, and supportable
throughout its life cycle. The Logistics
IPT will integrate and coordinate with
other government offices and
contractors both vertically and
horizontally. The Logistics IPT will
interact, coordinate, and ensure a
working relation with the other
UH-60M IPTs and government and
contractor office of equal stature.
INTERFACES The Logistics IPT interfaces with all
program IPTs, program management
PMWG, contractor teams, DoD,
and the customer.
DESCRIPTION OF TASKS The Logistics IPT will:
Ensure that aircraft is supportable when
delivered for testing and fielding.
Develop support requirements related to
readiness objectives, to design, and to
each other.
Integrate support considerations
effectively into the system and
equipment design
Identifying the most cost-effective
approach to supporting the system
Ensuring that the required support
structure elements are developed and
acquired.
Provide timely flow of information to
IPTs and the PMWG.
Ensure that the External Lift and Net
Ready KPPs are demonstrated and met.
RESPONSIBILITIES The Logistics IPT will develop,
implement and monitor execution of a
Supportability program to support
the UH-60M Program throughout the
111
life cycle.
A. IPT Leader:
a. Execution of the IPT Charter
b. Formation of the UH-60M-Logistics
IPT
c. Set meeting dates, locations and
milestones
d. Ensuring the IPT fosters an
atmosphere that promotes crossing
organizational boundaries and free flow
dialogue
e. Day to Day management of the IPT
process
f. conduct/host IPT meetings
g. Document decisions in minutes and
distribution of minutes to the
membership
h. Maintain IPT membership
i. Track and keep record of all action
items and assignments
B. IPT Members:
Shall meet as required to help plan,
program, structure, and
document/resolve issues.
a. Identify issues and parameters
b. Develop strategies and program
planning
c. Identify constraints and resources
d. Establish a plan of action and
milestones
e. Propose resolutions
f. Review and provide early input to
documents
g. Help in deciding roadmap/strategy
h. Assume responsibility to obtain
concurrence on issues
i. Provide recommendations to the
WIPT lead
j. Accepting tasking that require
research, writing, and/or briefing
k. Actively participating in the WIPT by
supporting and attending meetings
l. Completing assigned tasks on schedule
and providing results on issues
112
AUTHORITY Within the contracted SOW, the
Logistics Team has the authority to
affect the Logistics decisions which
a. Require resolution of conflicts of IPTs
b. Affect more than a single IPT,
c. Cross organizational boundaries, or
d. Require air vehicle level trade offs to
be considered.
The Logistics Team is a vehicle to
promote consensus between the affected
IPTs based on a systems level review of
available data.
Carry forward Logistics IPT decisions to
the Project Office for concurrence.
ACCOUNTABILITY The Supportability Team is accountable
to the program managers and Senior
Logisticians within the Govt and
contractor organizations
PRODUCTS A supportable system that includes the
following:
A. Maintenance Planning
a. Depot Maintenance Study
b. Level of Repair Analysis
c. Reliability predictions
d. Maintainability predictions
e. Failure Modes, Effects, and Criticality
Analysis
f. Failure Reports
g. Root cause failure analyses
h. Test plans
i. Test Reports
B. Supply Support
a. Provisioning Master Record
b. Authorized Stockage List/Prescribed
Load List
c. Replenishment Spares
d. Maintenance Allocation Chart
e. Government Furnished Equipment
(GFE) requirements list
f. GFE shortage list
C. Interactive Electronic Technical
Manual.
D. Training and Training Support
a. Training Course Program of
Instruction
113
b. Instructor and Key Personnel
Training
E. Training devices
a. T-BOS
b. Maintenance Training Device Suite
F. Computer resources and software
support
a. Maintenance Support Device
b. Diagnostic software
c. Automated Logbook
G. Transportability
a. Transportability Demonstration
b. Transportability kit
c. Component shipping containers
d. Package instructions
H. PBL
a. Core Depot Analysis
b. Business Case Analysis
c. Performance Based Agreements
d. Sources of Support
114
Integrated Manufacturing/Operations Sub-IPT Charter
PURPOSE
SCOPE OF WORK The Operations sub-IPT’s primary
purpose is to ensure that the product
being built is producible at the required
rate, identify production risks and
develop strategies to address risks.
INTERFACES The IM/O IPT interfaces with all
program IPTs, program management,
prime contractor, suppliers, Army
Environmental Center, AMCOM G-4,
Corrosion Prevention Action Team
(CPAT) .
DESCRIPTION OF TASKS • Manage the Process Modeling and
Simulation effort
• Develop and utilize capacity analysis
models
• Identification and management of
critical path production processes
• Identification and management of
parts critical to maintaining a
smooth production flow
• Validate requests for additional
tooling
• Identification and management of
Industrial Base issues
• Develop databases capturing
production costs and other
production data
• Evaluate long lead procurement
requirements
• Develop production cost estimates
• Conduct process proofing
• Conduct production surveillance
• Review hazardous material
management program plan progress
reports
115
• Update the Programmatic
Environmental, Safety and Health
Evaluation (PESHE)
• Develop and implement a Corrosion
Prevention and Control (CPC)
program
RESPONSIBILITIES
AUTHORITY The Integrated
Manufacturing/Operations Sub-IPT is
lead by the UH-60M Integrated
Manufacturing/Operations Lead and
derives the authority to make decisions
through empowerment from the UH-
60M Chief Engineer.
ACCOUNTABILITY The IM/O Team is accountable to the
Engineering IPT and to the program
managers and Chief Engineers within
the Govt and contractor organizations.
PRODUCTS • Updated Programmatic
Environmental, Safety and Health
Evaluation (PESHE)
• Corrosion Prevention and Control
(CPC) program
• Production cost estimates
• Databases capturing production costs
and other production data
• Capacity Models
PRODUCTS APPROVAL Govt Progam Mgmt IPT Lead
Contractor Program Mgmt IPT Lead
Govt Chief Engineer
Contractor Chief Engineer
Govt IM/O IPT
Contractor IM/O IPT Lead
TEAM COMPOSITION UH-60M Integrated
Manufacturing/Operations Lead
Contractor counterparts
116
Air Vehicle Sub-IPT Charter
PURPOSE The Air Vehicle (AV) Sub-IPT will
manage the performance and
operational requirements of the UH-
60M Utility Helicopter. The AV Team’s
purpose is to ensure aircraft subsystems
and components, shown on the WBS,
perform according to stated mission
requirements.
A main effort of the AV Team is to
ensure the Airframe, Propulsion system,
major computer hardware and
software items, and auxiliary systems
are fully capable of accomplishing the
UH-60M mission under the conditions
specified.
SCOPE OF WORK The UH-60M Work Breakdown
Structure lists the elements which fall
under the direct responsibility of the AV
Sub-IPT.
These elements include integration,
management, assembly, test and
checkout of AV subsystems and
components. Since the AV is
predominantly OTS/NDI, the
integration effort and associated testing
will be significant efforts for the IPT.
Hardware and software subject
matter expertise will be required. The
UH-60M Work Breakdown Structure
lists the elements which fall under the
direct responsibility of the AV Sub-IPT.
These elements include integration,
management, assembly, test and
checkout of AV subsystems and
components. Since the AV is
predominantly OTS/NDI, the integration
effort and associated testing will be
significant efforts for the IPT. Hardware
and software subject matter expertise
will be required.
INTERFACES The AV Team interfaces with the SE
IPT, Systems Engineering Team, the
117
program management team, and
functional management within the
contractor team, PM Office, and the
customer.
DESCRIPTION OF TASKS The AV Team will ensure the
accomplishment of the KPPs
including:
• IR Survivability
• HOGE, Endurance and Range
• Net-Ready
Through analysis and participation in
demonstration, testing, production and
operation of the following subsystems
and components:
Airframe
Propulsion
Application and System Software
Communications/Identification Systems
Navigation and Guidance
Central Computer
Fire Control
Data Displays and Controls
Survivability Systems
Reconnaissance
Automatic Flight Control
Central Integrated Checkout
Armament
Weapons Delivery
Auxiliary Equipment
RESPONSIBILITIES • Coordinating the performance and
operational qualification of a mission
capable UH-60M.
• Developing and integrating all
components of the aircraft to include
airframe, mission computers,
avionics, navigation,
communications, mission critical
software, propulsion, and flight
control systems.
• Chairing the Simulation Based
Acquisition Team, evaluating and
recommending alternative design
concepts via in-house simulation and
supporting the SE sub-IPT trade
118
studies.
• Validating the technical baseline
• Developing, in conjunction with
other IPTs, ECPs to support
modifications.
AUTHORITY Within the contracted SOW, the AV
Team has the authority to affect the
technical decisions which relate to
the KPPs and other operational factors.
The Air Vehicle Sub-IPT is lead by UH-
60M Air Vehicle Lead Engineer and
derives the authority to make decisions
through empowerment from the UH-
60M Chief Engineer.
The AV Sub-IPT will carry forward
decisions to the SE IPT for concurrence
and integration.
ACCOUNTABILITY The AV Team is accountable to the
Engineering IPT and to the program
managers and Chief Engineers within
the Govt and contractor organizations.
PRODUCTS Air Vehicle Analyses, Qualification
Reports
PRODUCTS APPROVAL Govt Progam Mgmt IPT Lead
Contractor Program Mgmt IPT Lead
Govt Chief Engineer
Contractor Chief Engineer
Govt AV IPT
Contractor AV IPT Lead
TEAM COMPOSITION Core Team Members:
• Systems Engineering Manager
• Engineering Operations Manager
• Technology managers
• Other IPT leaders
• Business Operations team
representative
• Contracting Representative
Associate Team Members:
• Business Manager (as req’d)
• Technology staff (as req’d)
• System engineering staff (as req’d)
119
Mission Equipment Packages Sub-IPT Charter
PURPOSE Integrate all MEP elements, both
hardware and software, of the mission
equipment package for the UH-60M
Helicopter. Accomplish the Mission
Equipment Package assigned tasks
within the allocated budget and meet
requirements.
SCOPE OF WORK Manage the integration and checkout of
Non Developmental Item MEP to
include the following equipment types:
Communication, Improved Data
Modem, Navigation (EGI, VOR/ILS,
TACAN), Identification Friend or Foe
(IFF), Controls and Displays,
Aircraft Survivability Equipment,
MEP Mission Computers and Data
Busses.
In addition, any MEP software
development, Information
Assurance Strategy efforts, and Net
Ready requirements efforts.
INTERFACES The MEP IPT interfaces with other
IPTs, contractors, TSM, AED, and on-
sight DCMA as needed.
DESCRIPTION OF TASKS Identify, track, resolve risks and areas of
concern. Identify and implement
processes and metrics. Develop and
track MEP schedules. Perform
integration and test of MEP in the
laboratory. Assess MEP performance.
Participate in integration, check-out,
functionals (acceptance tests) and
demonstrations of the MEP when
installed on the aircraft. Status program
management. Coordinate
interoperability risk reduction,
standards conformance, and
certifications (e.g., CTSF and JITC).
RESPONSIBILITIES Covered in other sections of this charter.
AUTHORITY Schedule Control
Risk Management
Interface Management
120
Resolve Technical Disputes
ACCOUNTABILITY Sub-IPT leads focus on their respective
technical areas and report directly to the
chief engineer.
PRODUCTS Integrated MEP hardware and software
AMPS Interface to UH-60M
DATA
PEPS
ICDS
IFMs
PRODUCTS APPROVAL Engineering IPT Lead
TEAM COMPOSITION Leads for Comm/Nav/IFF/C&D/ASE
Logistics
AED
Test/Flight Test *
Contracts*
* As Needed
121
Attachment 3. Work Breakdown Structure
1.0 UH-60M
1.1 AIR VEHICLE AV Sub-IPT
1.1.1 AIRFRAME AV Sub-IPT
1.1.1.1 FUSELAGE AV Sub-IPT
1.1.1.1.1 NOSE SECTION AV Sub-IPT
1.1.1.1.1.1 NOSE SECTION AV Sub-IPT
1.1.1.1.1.2 NOSE SECTION AV Sub-IPT
1.1.1.1.1.3 NOSE SECTION AV Sub-IPT
1.1.1.1.1.4 NOSE SECTION AV Sub-IPT
1.1.1.1.2 MID FUSELAGE AV Sub-IPT
1.1.1.1.3 AFT FUSELAGE (TRANSITION) AV Sub-IPT
1.1.1.4.2 N/A
122
WBS WBS Element Title IPT Responsible
Element#
123
WBS WBS Element Title IPT Responsible
Element#
124
WBS WBS Element Title IPT Responsible
Element#
125
WBS WBS Element Title IPT Responsible
Element#
126
WBS WBS Element Title IPT Responsible
Element#
127
WBS WBS Element Title IPT Responsible
Element#
128
WBS WBS Element Title IPT Responsible
Element#
129
WBS WBS Element Title IPT Responsible
Element#
130
WBS WBS Element Title IPT Responsible
Element#
131
Attachment 4. Critical Technical Parameters (CTP)
Internal Lift Capability (Normal Flight) BMC with 11 combat troops @ 290 lbs. each. CTT
(ORD 4.a.1.a) 4000 feet Pressure Altitude (PA) / 95 degrees F 200 Kilometers combat radius with MS C
Level Flight. With airspeed 145 KTAS using MCP 20 minute fuel reserve at MS C.
500 fpm VROC from HOGE using 95% of
MRP. With Single Engine Inoperative (SEI), 100 225 Kilometers Combat Radius with FRP Decision
KTS and 100 fpm VROC at Intermediate rated 20 minute fuel reserve at FRP Review
power (IPR). Decision Review.
KPP BMC with 4500 lbs. ext. load CTT Combat radius of 135 Kilometers MS C
External Lift Capability: 4000 feet PA / 95 degrees F with 20-minute fuel reserve.
(ORD 4.a.1.c) 200 fpm VROC from HOGE @ 0 Airspeed. FRP Decision
Review
Endurance Flight Time C2 Mission Configuration CTT Fly 4.0 hours, takeoff to landing,
(ORD 4.a.1.b) 2000 feet PA / 70 degrees F with 20 minute fuel reserve @ FRP Decision
200 fpm VROC from HOGE @ 0 Airspeed. Velocity Best Endurance (Vbe). Review
Digital Mission Management – Data AMPS Compatibility CTT Send and Receive 600 Mbytes data FRP Decision
Transfer System Comm/Nav/ASE/MEP Interface for automated at a rate of 1.0 Megahertz. Review
(ORD 4.a.2.c data input.
132
Supported Operational Critical Technical Parameter Development UH-60M Decision
Requirement Stage Event Threshold value Supported
Situational Awareness Tactical digital map capability CTT Digitized moving map IAW MIL- FRP Decision
(ORD 4.a.2.g) PRF-101299. Review
Situational Awareness Mission Information through JVMF messaging CTT Receive, transmit, and display FRP Decision
(ORD 4.a.2.b) JVMF Message Information. Review
Situational Awareness Storm Detection and severe weather avoidance CTT Thunderstorm detection display and FRP Decision
(ORD 4.a.i.2) weather mapping (airborne or Review
ground).
KPP Interoperability growth IAW JTA Army and DoD CTT Open digital architecture IAW JTA MS C
Avionics Army and DOD. Growth to
(ORD 4.b Receive and Transmit Required FRP Decision
JVMF messages. Critical IERs Review
must be met.
Avionics Flight Control handling qualities IAW ADS-33 CTT Level I Handling Qualities IAW FRP Decision
(ORD 4.a.2.i.1) ADS-33 (Non DVE). Review
Avionics Navigate within 10.5m vertical, 8.7m horiz, CTT Accuracy: FRP Decision
(ORD 4.a.2.h) 1.16 mils Directional accuracy Vertical: 10.5 m (5 m CEP). Review
Horiz: 8.7 m (3 m LEP). Dir: 1.
16 mils (0.4 mil LEP).
Mission Equipment Night Vision Compatibility IAW MIL-L-8762A CTT Compliant w/ MIL-L-8762A for FRP Decision
(ORD 4.a..3) Class A. Luminance of 1.0 +/- 0.5 Review
footlamberts.
133
Supported Operational Critical Technical Development UH-60M Decision
Requirement Parameter Stage Event Threshold value Supported
FLIR Performance IAW UH-60Q specifications CTT No degradation from demonstrated FRP Decision
(ORD 4.a.2.c) UH-60Q detection capability. Review
Software Maturity & Quality a. Computer Resource Utilization CTT a. 50 % FRP Decision
(ORD 5.d) b. Requirements Stability b. 75 % Review
c. Design Stability c. 75 %
Survivability Ballistic protection LFT&E Provide Protection to 7.62 mm. FRP Decision
(ORD 4.a.5.c) Review
134
Supported Operational Critical Technical Development UH-60M Decision
Requirement Parameter Stage Event Threshold value Supported
Transportability Meet UH-60L airlift requirements CTT 6 Aircraft in C-5; 3 in C-17. FRP Decision
(ORD 4.a.4) Review
Reliability & Maintainability (ORD 4.a.6) MTBEMA CTT MTBEMA 3.5 Flt Hours (Point MS C
Estimate, See Table II.2)
Reliability & Maintainability a. MTBMA => 40 Flt Hours CTT/IOT MTBMA => 40 Flt Hours (Point
(ORD 4.a.6) b. MTBMAF => 15 Flt Hours Estimate) FRP Decision
c. MTBEMA => 3.7 Flt Hours MTBMAF => 15 Flt Hours (Point Review
d. Total MR =< 5.4 MMH/FH Estimate)
e. Unschd MR =< 2.1 MMH/FH MTBEMA => 3.7 Flt Hours
(Point Estimate)
Total MR =< 5.4 MMH/FH
Unschd MR =< 2.1 MMH/FH
135
Attachment 5. Measures of Effectiveness (MOE)
Operational ORD
Parameter ORD Threshold ORD Objective
Requirement Reference
a) Troop Movement a) Internal Lift at 4,000 feet, 95 degrees F: 11 Combat a) Internal Lift at 4,000 feet, 95 degrees F: 11 ORD 4.a.1.a
Troops @ 290 lbs. each. Combat Radius: 225 km, 20- Combat Troops @ 290 lbs. each. Combat Radius:
min fuel reserve. 500 km, 20-min fuel reserve.
b) External lift b) External Lift (KPP) at 4,000 feet, 95 degrees F: 4500 b) External Lift (KPP) at 4,000 feet, 95 degrees F: ORD 4.a.1.c
lbs. Combat Radius: 135 km (73 nm) plus 20-minute 10000 lbs. Combat Radius: 275 km (148 nm) plus
fuel reserve. (KPP) 20-min fuel reserve.
c) Command and Control c) With a C2 Mission Equipment Package (1800 lbs. c) Same as threshold, except at 4,000 feet, 95 ORD 4.a.1.b
Max GW), five passengers at 245 lbs. each, endurance degrees F: 5.0 hours plus 20 minute fuel reserve.
with ERFS at 2,000 feet, 70 degrees F: 4.0 hours plus
20 minute fuel reserve.
Avionics
a) Architecture a) Open architecture digital avionics system IAW Army a) Same as threshold. ORD 4.a.2.a
and DOD JTA and Global Air Traffic Management
(GATM) Capstone requirements II.
b) Cockpit management system b). Simultaneous digital display of tactical situational b). Integrated digital cockpit management system: ORD 4.a.2.b
awareness and aircraft system status. Receive, display, simultaneous display of primary flight systems:
and transmit JVMF messages and caution advisory aircraft system status and tactical situational
annunciation. awareness. Receive, display, and transmit, JVMF
messages, aircraft systems malfunction analysis
and emergency action procedures.
c) Communications c) Transmit and receive in jam resistant, secure (and c) Same a threshold plus capability to transmit ORD 4.a.2.f
non-secure), and joint service compatible modes of and receive with satellite communications.
communication, voice and data.
- VHF-FM
- UHF-AM
- HF
- VHF-AM (voice only)
d) Situational awareness d) Display of situational awareness picture through a d) Threshold requirement plus voice synthesized ORD 4.a.2.b
digitized, moving map. Support growth for transmit and JVMF messaging.
receive connectivity IAW ABCS requirements.
136
Measures of Effectiveness and Suitability (MOE/S) (continued)
Operational ORD
Parameter ORD Threshold ORD Objective
Requirement Reference
d) Navigation d) Global system with precision accuracy for d) Same as threshold plus distance measuring ORD 4.a.2.h
tactical navigation (land and over-water). Meets system for instrument approaches.
military requirements for operations in civil VFR
and IFR. Secondary Backup independent of
ground or space based components.
e) Flight Handling e) Non-Degraded Visual Environment (DVE), e) Same as threshold. Threshold requirements plus ORD 4.a.2.i.1
flying qualities optimized for minimal pilot in DVE. (Level 1 IAW ADS-33).
workload. (Level 1 IAW ADS-33).
b) Air transportability a) Self deployment to 1,056 nm. b) Same as threshold requirement plus folding ORD 4.a.4.b
components.
b) Air transport of minimum of 6 UH-60M aircraft
c) Sea transportability in one C-5 and 3 per C-17. c) same as threshold. ORD 4.a.4.c
137
Measures of Effectiveness and Suitability (MOE/S) (continued)
ORD
Operational
Parameter ORD Threshold ORD Objective Referenc
Requirement
e
SYSTEM PERFORMANCE System Survivability:
a) Susceptibility Reduction a) Existing UH-60L system of IR signature a) Same as threshold, plus reduced acoustic, and ORD 4.a.5.a
reduction and active/passive CM systems. radar cross section signatures.
b) System Hardening b) Ballistic protection to 7.62 mm. Operate after b) Same as threshold, plus to 14.5 mm. Also ORD 4.a.5.b
encountering NBC contaminates and operable in hardening to high power microwave directed
MOPP IV gear. energy weapons and lasers
c) Self Protection c) Two (7.62 mm) machine guns with laser aiming c) Same as threshold except structural capability ORD 4.a.5.c
device. for 12.7 mm gun.
SYSTEM PERFORMANCE Reliability a) MTBMA =>40 flight hours. a) MTBMA => 56 flight hours. ORD 4.a.6
c) MTBEMA => 3.7 flight hours. c) MTBEMA = > 5.2 flight hours.
INFORMATION EXCHANGE Interoperability Meet 100% of the critical Top Level Information Meet 100% of all Top Level Information Exchange ORD 4.b
Exchange Requirements (KPP) (ORD 4.b). Requirements. (KPP)
138
Measures of Effectiveness and Suitability (MOE/S) (continued)
Operational ORD
Parameter ORD Threshold ORD Objective
Requirement Reference
LOGISTICS & READINESS Logistics Existing Army Maintenance Program with the Same as threshold. ORD 4.c.1
GCSS-A System and Class 1 Interactive
Electronic Technical Manual (IETM).
Maintainability a) Total MR no more than 5.4 Maintenance Man- a) Total MR not more than 4.6 MMH/FH. ORD 4.c.2
hours per flight hour (MMH/FH).
b) Unscheduled MR no more than 2.1 MMH/FH. b) Unscheduled MR not more than 1.3 MMH/FH. ORD 4.c.2
OTHER SYSTEM Shipboard compatibility U.S. Navy surface ship compatibility. Same as threshold. ORD 4.d.2
CHARACTERISTICS Installation of rotor brake. Compatible with
Navy ship refueling capabilities.
CEFS Installation/removal shall not exceed an elapsed Same as threshold, plus: non-pressurized tank with ORD 4.d.1
time of 2 hours. Ballistically tolerant to 7. capability to accept a nitrogen inert system, automatic
62mm. capability to avoid fuel quantity that could exceed
lateral CG limitations. Ballistically tolerant to
14.5mm.
139
Attachment 6. Trade Study Decisions
Risk
Risk Reduction
Reduction Trade
Trade Studies
Implemented
Implemented via
via IQ
IQ Baseline
Baseline
Initial Current
Baseline
Incorporated 4 MFDs
via contract mod
X
Incorporated ESIS
X
Incorporated Fully
Coupled Flight Controller
X
140
Risk
Risk Reduction
Reduction Trade
Trade Studies
Studies
Implemented
Implemented via
via IQ
IQ Baseline
Baseline (cont.)
(cont.)
Initial Current
Baseline
141
Risk
Risk Reduction Trade
Trade Studies
Studies
Implemented
Implemented via IQ
IQ Baseline
Baseline (cont.)
(cont.)
Initial Current
Baseline
Dual 5 amp
SLAB
Incorporated
AVR-2b via contract
mod
Incorporated
X IHIRSS via contract
mod
142
Risk
Risk Reduction
Reduction Trade
Trade Studies
Studies
Implemented via IQ Baseline (cont.)
(cont.)
Initial Current
Baseline
Considering
IVHMS
Incorporating
CEFS
X
Incorporating
Digital ICS
143
Risk
Risk Reduction
Reduction Trade
Trade Studies
Studies
Implemented
Implemented via
via IQ Baseline (cont.)
Initial Current
Baseline
Incorporating
APX-118
X
Folding Composite
Stabliator
X
As req
144
Risk
Risk Reduction
Reduction Trade
Trade Studies
Studies
Implemented
Implemented via IQ Baseline (cont.)
Initial Current
Baseline
145
IQ
IQ Trade
Trade Studies
Studies Evaluated & Implemented
Implemented
Study IQ Implementation
146
Attachment 7. Risk Mitigation Example
Likelihood c
1 2 3 4 5
Consequence
T = Technical Risk
C = Cost Risk
080304 S = Schedule Risk Last Updated: 08/03/04
1
147
Risk Mitigation Example (continued)
The AQSOW identified GFE qualification as Government responsibility. Issues with obtaining the
qualification data for legacy GFE subsystems.
RISK LEVEL: Mod
Technical: Mod to High
Cost: Mod
Schedule: Mod
LIKELIHOOD (of occurrence): e
Restricted AWR or ISAQ until GFE is adequately tested.
-- Some
Some Restrictions are acceptable
acceptable for
for First
First Flight
Flight and
and IOT&E
IOT&E
CONSEQUENCE (if risk materializes): 2
Cannot complete SAQ for full qualification. IFR flight operation restrictions in the OT airworthiness
release and ISAQ
MITIGATION PLAN
Program to perform negotiated ARC-222 EMI testing.
Assess and mitigate the results.
Change to another radio (eg. ARC-231)
POCs:
GOV’T: Roger Olson, Mike Walsh, Greg Kirchhofer
CONT: Tony Sacullo
080304
148
Attachment 8: Technical Review Summary
Govt
Participation
Planned Event Actual Date @ Event
AFCC PDR 19-Dec-2001 N
AFCC CDR 11-Apr-2002 Y
AVC Actuator PDR 31-May-2002 Y
DCU HW PDR 27-Jun-2002 Y
DC 400 Amp Converter PDR 11-Jul-2002 Y
Pitot Heat Sensor PDR 18-Jul-2002 N
ESH PDR 19-Jul-2002 Y
AVC Computer PDR 7-Aug-2002 Y
ADC PDR/CDR 14-Aug-2002 Y
Digital ICS PDR 28-Aug-2002 Y
Pitot Heat Sensor CDR 12-Sep-2002 Y
Crew Seats PDR 17-Sep-2002 Y
DCU HW CDR 17-Sep-2002 Y
DCU SW PDR 18-Sep-2002 Y
FDDCP PDR 19-Sep-2002 Y
Hydraulic Control Logic PDR 25-Sep-2002 N
Squib Test Logic PDR 25-Sep-2002 N
DC 400 Amp Converter CDR 7-Oct-2002 Y
AVR-2B Laser Warning Rcvr PDR 16-Oct-2002 Y
Battery PDR 22-Oct-2002 Y
AVC Actuator CDR 24-Oct-2002 Y
MFD PDR 28-Oct-2002 Y
EGI SRR/PDR 6-Nov-2002 Y
Digital ICS CDR 7-Nov-2002 Y
Fire Ext. Logic PDR#1 5-Dec-2002 Y
AVC Computer CDR 16-Dec-2002 Y
Utility Seats PDR 16-Dec-2002 Y
AVR-2B Laser Warning Rcvr CDR 18-Dec-2002 Y
Hydraulic Logic Module CDR 18-Dec-2002 Y
Squib Test Logic CDR 18-Dec-2002 Y
Battery CDR 7-Jan-2003 Y
Composite Stabilator CDR 9-Jan-2003 Y
Crew Seats CDR 22-Jan-2003 Y
Fire Ext. Logic PDR#2 24-Jan-2003 Y
ESH CDR 28-Jan-2003 Y
Digital Map Kick-off 11-Feb-2003 Y
MFD CDR 12-Feb-2003 Y
FDDCP HW CDR 18-Feb-2003 Y
FMS Hardware CDR 20-Feb-2003 Y
Fire Ext. Logic CDR 6-Mar-2003 Y
EGI CDR/EDR 19-Mar-2003 Y
Reversionary Panel CDR 24-Mar-2003 Y
FDDCP SW CDR 25-Mar-2003 Y
149
Govt
Participation
Planned Event Actual Date @ Event
Data Transfer Unit TIM 16-Apr-2003 N
Data Transfer Unit Kick-off 6-May-2003 Y
Engine Quadrant Warning PDR 15-May-2003 Y
DCU Software CDR 22-May-2003 Y
Digital Maps SRR/PVI#1 3-Jun-2003 Y
FMS Software PDR 17-Jun-2003 Y
MWC Logic Module CDR 22-Jul-2003 Y
Data Transfer Unit PDR 29-Jul-2003 Y
Utility Seats CDR 11-Sep-2003 Y
Digital Maps PDR 21-Oct-2003 Y
Data Transfer Unit TIM 4-Nov-2003 Y
Data Transfer Unit Hardware CDR 13-Nov-2003 Y
Data Transfer Unit Software CDR 3-Dec-2003 Y
Digital Maps CDR 25-Feb-2004 Y
ESIS
FMS Software CDR
IVHMS TIM July 2005 Y
150
Appendix A: UH-60M Upgrade Program Systems Engineering Plan
151