VALORIZACIÓN No.

01
Apr-14

CONTRATO DE EJECUCION DE OBRA A PRECIOS UNITARIOS


DEL PROCESO DE ADJUDICACION DIRECTA PUBLICA
Nº 004- - PRIMERA CONVOCATORIA

OBRA

CONTRATISTA

SUPERVISION

ENTIDAD CONTRATANTE:
VALORIZACIÓN No. 01
Apr-14

OBRA : 0
CONTRATISTA : 0
SUPERVISION : 0
ENTIDAD : 0

PRESUPUESTO BASE S/. 662,683.21 (incl. I.G.V.) Monto S/IGV: S/. 561,595.94
PRESUPUESTO OFERTADO S/. 599,403.09 (incl. I.G.V.) Monto S/IGV: S/. 507,968.72
FECHA DE PRESUPUESTO DICIEMBRE 2013

ADELANTOS: MES DE ABRIL 2014


Adelanto Directo S/. 59,940.31
Adelanto Materiales S/. 239,761.24 ACUMULADO PROGRAMADO = 33.26%
Monto Total Adelantos S/. 299,701.55 ACUMULADO EJECUTADO = 9854.00%
PORCENTAJE = 29627.18%

RESUMEN DE VALORIZACION
CONCEPTO MONTO
S/.

MONTO VALORIZADO EN EL PRESENTE MES 257,735.05

01 0 257,735.05

REAJUSTES 623.75

01 0 623.75

MONTO BRUTO VALORIZACION REAJUSTADA 258,358.80


AMORTIZACION DEL ADELANTEO EN EFECTIVO EN EL PRESENTE MES 25,773.50

AMORTIZACION DEL ADELANTO EN EFECTIVO 25,773.50

AMORTIZACION DEL ADELANTO PARA MATERIALES EN EL PRESENTE MES 0.00

AMORTIZACION DEL ADELANTO PARA MATERIALES 0.00

DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR EL A.D. 0.00

DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR EL A.D. 0.00

DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR EL A. DE MATERIALES 0.00

DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR EL A.DE MATERIALES 0.00


TOTAL DESCUENTOS 25,773.50

I.- MONTO FACTURABLE ( SIN I.G.V) 232,585.30


II.- I.G.V. (18% DE I) 41,865.35
III.- MONTO A FACTURAR ( I + II) 274,450.65

RETENCION 59,940.31
MONTO A PAGAR 214,510.34
#DIV/0!

#DIV/0!
#DIV/0!

#DIV/0!
#DIV/0!
#DIV/0!
VALORIZACIÓN No. 01
41730

OBRA : 0
CONTRATISTA : 0
SUPERVISION : 0
ENTIDAD : 0

AMORTIZACIONES DE ADELANTOS AL MES DE

MONTO DEL CONTRATO S/ 507,968.72 sin IGV


% de Avance valorizado acum. 9854.00%

1 ADELANTO DIRECTO

Otorgado 50,796.87 sin IGV 10.00% del contrato

Amortizado 25,773.50 sin IGV 50.70% del adelanto

Saldo x amortizar 25,023.37 sin IGV 49.3% del adelanto

2 ADELANTO DE MATERIALES

Otorgado 201,480.03 sin IGV 39.7% del contrato

Amortizado #DIV/0! #DIV/0! del adelanto

Saldo x amortizar #DIV/0! sin IGV #DIV/0! del adelanto


VALORIZACIÓN No. 01
41730

OBRA : 0
CONTRATISTA : 0
SUPERVISION : 0
ENTIDAD : 0

AMORTIZACIÓN DEL ADELANTO DIRECTO

ADELANTO OTORGADO: S/. 50,796.87 (SIN IGV)

MONTO CONTRATADO: S/. 507,968.72 (SIN IGV)

VALORIZACION MONTO SALDO AMORTIZACION AMORTIZACION AMORTIZACION SALDO


FECHA
Nº VALORIZACION ANTERIOR TRAMITADA REAL POR REGULARIZAR ACTUAL
(V) AxV/C AxV/C AxV/C
Valorizacion Nº 01 257,735.05 50,796.87 25,773.50
257,735.05 25,773.50 25,773.50 25,023.37
VALORIZACIÓN No. 01
41730

OBRA : 0
CONTARTISTA : 0
ENTIDAD : 0
SUPERVISION : 0

DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR EL ADELANTO EN EFECTIVO

ADELANTO OTORGADO : S/. 50,796.87 (SIN IGV)


MONTO CONTRATADO : S/. 507,968.72 (SIN IGV)

FORMULA 1 : ###
VALORIZACION FECHA MONTO COEFICIENTES DE REAJUSTE REINTEGRO QUE
Nº VALORIZACION MES VALORIZACION MES ADELANTO NO CORRESPONDE
(V) (K) (Ka) D = V x A/C (K/Ka - 1)

1 MARZO 2008 284,944.63 - 1.002 -28,494.46

TOTAL DEDUCCION x A.D. -28,494.46


VALORIZACIÓN No. 01
41730

OBRA : 0
EJECUTA : 0
ENTIDAD : 0
SUPERVISOR : 0

AMORTIZACION ADELANTO DE MATERIALES

MATERIAL : TUBO PVC


INDICE : 72 ADELANTO MONTO
F. PAGO OTORGADO
INCIDENCIA DEL TUBO PVC = 121,753.60 / 200,475.63 = 0.6073 Mar-08 121,753.60
INDICES DEUDA SALDO
MES PARTIDA METR. P.U. MONTO Coefic. MATERIAL AMORTIZ. DE POR
VALORIZ. VALORZ. VALORIZADO Tubo PVC UTILIZADO Io Ia MATERIAL AMORTIZAR
(1) (2) (1)x(2)=(3) (5) (6) (3)x(6)/(5) OTORGADO

Mar-08 05.01.00 163.50 38.22 6,248.97 0.60732 3,795.15 0.00 0.00 #DIV/0! 121,753.60 115,504.63

TOTAL AMORTIZACIONES #DIV/0!

MATERIAL : CEMENTO PORTLAND TIPO I


INDICE : 21 ADELANTO MONTO
F. PAGO OTORGADO
INCIDENCIA DEL CEMENTO PORTLAND TIPO I = 48,372.32 / 200,475.63 = 0.2413 Mar-08 48,372.32
INDICES DEUDA SALDO
MES PART. METR. P.U. MONTO Coefic. MATERIAL AMORTIZ. DE POR
VALORZ. VALORZ. VALORIZADO Cemento UTILIZADO Io Ia MATERIAL AMORTIZAR
(1) (2) (1)x(2)=(3) Portland (5) (6) (3)x(6)/(5) OTORGADO

Mar-08 06.02.00 (1) 59.00 21.20 1,250.80 0.24129 301.80 0.00 0.00 #DIV/0! 48,372.32 #DIV/0!
06,07,00 (1) 59.00 38.70 2,283.30 0.24129 550.93 0.00 0.00 #DIV/0! 48,372.32 #DIV/0!
07,01,06 (1) 215.00 195.93 42,124.95 0.24129 10,164.24 0.00 0.00 #DIV/0! 48,372.32 #DIV/0!
AMORTIZACION ANTERIOR TOTAL AMORTIZACIONES #DIV/0!
MATERIAL : MADERA NACIONAL P/ENCOFRADO Y CARPINTERIA
INDICE : 43
ADELANTO MONTO
F. PAGO OTORGADO
INCIDENCIA DE MADERA NACIONAL P/ENCOF. Y CARP. = 30,349.71 / 200,475.63 = 0.1514 Mar-08 30,349.71
INDICES DEUDA SALDO
MES PART. METR. P.U. MATERIAL Coefic. MATERIAL AMORTIZ. DE POR
VALORZ. VALORZ. UTILIZADO Madera UTILIZADO Io Ia MATERIAL AMORTIZAR
(1) (2) (1)x(2)=(3) Nacional (5) (6) (3)x(6)/(5) OTORGADO

Mar-08 04.12.00 (2) 120.00 26.09 3,130.80 0.15139 473.97 0.00 0.00 #DIV/0! 30,349.71 #DIV/0!
04.13.00 (2) 98.00 35.75 3,503.50 0.15139 530.39 0.00 0.00 #DIV/0! 30,349.71 #DIV/0!

TOTAL AMORTIZACIONES #DIV/0!

RESUMEN

TOTAL AMORTIZACIONES ACUMULADO #DIV/0!


AMORTIZACIONES PAGADAS VAL. ANTERIORES -
TOTAL AMORTIZACION SETIEMBRE #DIV/0!
200,475.63
VALORIZACIÓN No. 01
41730

CONTROL DE LA DEDUCCIÓN DE REAJUSTE QUE NO CORRESPONDE POR EL ADELANTO PARA ADQ. DE MATERIALES
DEDUCCION : Valorizacion x Coef. Incid. x (Ir-Ia)/Io

ADELANTO MONTO MONTO DEFLATADO


MATERIAL : TUBO PVC Nº F. PAGO OTORGADO ADELANTO ACUMULADO
INDICE : 72 01 Mar-08 S/. 121,753.60 #DIV/0! #DIV/0!

MONTO DEL MONOMIO ADEL. I N D I C E S MONTO ADELANTO SALDO


VALORIZACION BRUTO UTILIZ. MAXIMO POR POR DEDUCC.
VALORIZ. INC. % (1)x(2)x(2)'= Io Ia Ir UTILIZABLE UTILIZAR AMORTIZAR "D"
No. MES (1) (2) (2)' (3) (4) (5) (6) ADEL. (8) (8)-(3) (3)x(6-5)/(4)
1 Mar-08 284,944.63 0.305 100.000% 86,908.11 - - - #DIV/0! #DIV/0! #DIV/0! #DIV/0!

ADELANTO MONTO MONTO DEFLATADO


MATERIAL : CEMENTO PORTLAND TIPO I Nº F. PAGO OTORGADO ADELANTO ACUMULADO
INDICE : 21 01 Mar-08 S/. 48,372.32 #DIV/0! #DIV/0!

MONTO DEL MONOMIO ADEL. I N D I C E S MONTO ADELANTO SALDO


VALORIZACION BRUTO UTILIZ. MAXIMO POR POR DEDUCC.
VALORIZ. INC. % (1)x(2)x(2)'= Io Ia Ir UTILIZABLE UTILIZAR AMORTIZAR "D"
No. MES (1) (2) (2)' (3) (4) (5) (6) ADEL (8) (8)-(3) (3)x(6-5)/(4)
1 Mar-08 284,944.63 0.225 100.00% 64,112.54 0.00 0.00 0.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0!

ADELANTO MONTO MONTO DEFLATADO


MATERIAL : MADERA NACIONAL P/ENCOFRADO Y CARPINTERIA Nº F. PAGO OTORGADO ADELANTO ACUMULADO
INDICE : 43 01 Mar-08 S/. 30,349.71 #DIV/0! #DIV/0!

MONTO DEL MONOMIO ADEL. I N D I C E S MONTO ADELANTO SALDO


VALORIZACION BRUTO UTILIZ. MAXIMO POR POR DEDUCC.
VALORIZ. INC. % (1)x(2)x(2)'= Io Ia Ir UTILIZABLE UTILIZAR AMORTIZAR "D"
No. MES (1) (2) (2)' (3) (4) (5) (6) ADEL (8) (8)-(3) (3)x(6-5)/(4)
1 Mar-08 284,944.63 0.096 100.00% 27,354.68 0.00 0.00 0.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0!

TOTAL DEDUCCION QUE NO CORRESPONDE X ADELANTO DE MATERIALES Nº 01 #DIV/0!

TOTAL DEDUCCION QUE NO CORRESPONDE X ADELANTOS DE MATERIALES #DIV/0!


VALORIZACIÓN No. 01
41730

OBRA : 0
CONTRATISTA : 0
SUPERVISOR : 0
ENTIDAD : 0

CALCULO DE LOS REAJUSTES


FORMULA 01 : ###

VALORIZACION FECHA MONTO COEFICIENTE REAJUSTE MENSUAL


Nº VALORIZACION REAJUSTE
(V) K
1 257,735.05 1.002 623.75

TOTAL REAJSUTES MES S/. 623.75


FACTORES DE REAJUSTE

OBRA : 0
CONTRATISTA : 0
ENTIDAD : 0
CONTRATO PRINCIPAL :
FORMULA POLINOMICA : 1 ZONA GEOGRAFICA : 01

K = 0.168 Mr + 0.305 Tr + 0.225 Cr + 0.096 Mr + 0.096 Mr + 0.110 Ir


Mo To Co Mo Mo Io

COEF. PARTICIP. INDICES DE PRECIOS


SIMB. INDICE ELEMENTO INCID. PORCENT. Io Ir
Apr-16 Jul-16

M 47 MANO OBRA (INC. LEYES SOCIALES) 0.168 100.000% 544.120 562.240 0.174

T 72 TUBO PVC 0.305 100.000% 409.290 410.900 0.306

C 21 CEMENTO PORTLAND TIPO I 0.225 100.000% 462.570 459.080 0.223

M 43 MADERA NACIONAL P/ENCOFRADO Y CARPINTERIA 0.096 100.000% 692.290 669.480 0.093

M 49 MAQUINARIA Y EQUIPO IMPORTADO 0.096 100.000% 295.610 295.650 0.096

I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.110 100.000% 427.580 429.420 0.110

1.002

FACTOR DE REAJUSTE "K" 1.000 1.002 0.000 0.000


0.015
VALORIZACION Nº 01 DE AVANCE DE OBRA

AGOSTO 2016

OBRA : 0
CONTRATISTA : 0
SUPERVISOR : 0
ENTIDAD : 0
AREA GEOGRAFICA INEI: 02

INDICE

47 MANO OBRA (INC. LEYES SOCIALES)

72 TUBO PVC

21 CEMENTO PORTLAND TIPO I

43 MADERA NACIONAL P/ENCOFRADO Y CARPINTERIA

49 MAQUINARIA Y EQUIPO IMPORTADO

39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR


FORMULAS POLINOMICAS CONTRACTUALES

OBRA : 0.00
CONTRATISTA : 0.00
ENTIDAD : 0
UBICAC. GEOGRAFICA : PIURA - PIURA - PIURA AREA GEOGRAFICA : 2

FORMULA POLINOMICA N° 01
PRESUPUESTO: ###
MONOM. FACTOR % INCID. SIMBOLO INDICE DESCRIPCION

01 0.168 100.000% M 47 MANO OBRA (INC. LEYES SOCIALES)

02 0.305 100.000% T 72 TUBO PVC

03 0.225 100.000% C 21 CEMENTO PORTLAND TIPO I

04 0.096 100.000% M 43 MADERA NACIONAL P/ENCOFRADO Y CARPINTERIA

05 0.096 100.000% M 49 MAQUINARIA Y EQUIPO IMPORTADO

06 0.110 100.000% I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR

K = 0.168 Mr + 0.305 Tr + 0.225 Cr + 0.096 Mr + 0.096 Mr + 0.110 Ir


Mo To Co Mo Mo Io
VALORIZACION Nº 01 DE AVANCE DE OBRA
AGOSTO 2016
OBRA : 0
EJECUTA : 0
ENTIDAD : 0 ADELANTOS PLAZO DE EJECUCION
FR = 0.90451 Adelanto Directo 10.00% S/. 59,940.31 Inicio Plazo de Ejecucion :
VALOR REFERENCIAL : S/. 662,683.21 Adelanto Materiales 20.00% S/. 119,880.62 Plazo Ejecucion de Obra : 75 dias calendarios
PRESUPUESTO CONTRATADO : S/. 599,403.09 Monto total de adelantos S/. 179,820.93 Vencimiento de Plazo :

PRESUPUESTO AVANCES
Avance
PART. PARTIDA ANTERIOR ACTUAL ACUMULADO SALDO Acumul.
UND CANT. P.U. PARCIAL %
Metrado Monto S/. Metrado Monto S/. Metrado Monto S/. Metrado Monto S/.
00.00.00 REDES DE ALCANTARIILLADO
01.00.00 OBRAS PROVISIONALES
01.01.00 CASETA DE GUARDIANIA Y ALMACEN MES 2.50 350.00 875.00 1.00 350.00 1.50 525.00 2.50 875.00 100.00
01.02.00 CARTEL/PANEL DE IDENTIFICACION DE LA OBRA 1.20 X 2.40 UND 1.00 400.68 400.68 - - 1.00 400.68 1.00 400.68 100.00
01.03.00 SEÑALIZACION,DESVIO DE TRANSITO Y PROTECCION DE OBRA UND 8.00 70.92 567.36 4.00 283.68 4.00 283.68 8.00 567.36 100.00
01.04.00 MOVILIZACION DE EQUIPOS Y MAQUINARIA A LA OBRA GLB 1.00 2,000.00 2,000.00 0.50 1,000.00 0.50 1,000.00 1.00 2,000.00 100.00
02.00.00 TRABAJOS PRELIMINARES
02.01.00 TRAZO Y REPLANTEO ML 2,815.50 0.38 1,069.89 2,175.50 826.69 640.00 243.20 2,815.50 1,069.89 100.00
03.00.00 ROTURA Y REPOSICION DE PAVIMENTO ASF., CONC. Y BLOQUETAS
03.01.00 ROTURA Y REPOSICION DE PAVIMENTO ASFALTICO C/EQUIPO
03.01.01 ROTURA DE PAV. ASFALTICO C/EQUIPO E=5.0 cm M2 1,745.34 3.48 6,073.78 1,029.60 3,583.01 715.74 2,490.78 1,745.34 6,073.78 100.00
03.01.02 SUB BASE AFIRMADO E=0.15 m M2 1,745.34 7.89 13,770.73 - - 1,745.34 13,770.73 1,745.34 13,770.73 100.00
03.01.03 BASE AFIRMADO P/PISTA E=0.20m M2 1,745.34 11.84 20,664.83 - - 1,745.34 20,664.83 1,745.34 20,664.83 100.00
03.01.04 IMPRIMACION ASFALTICA M2 1,745.34 5.68 9,913.53 - - 1,745.34 9,913.53 1,745.34 9,913.53 100.00
03.01.05 CARPETA ASFALTICA CALIENTE E=5 cm M2 1,745.34 21.91 38,240.40 - - 1,745.34 38,240.40 1,745.34 38,240.40 100.00
03.02.00 ROTURA Y REPOSICION DE PAVIMENTO DE CONCRETO
03.02.01 ROTURA DE PAV. CONCRETO C/EQUIPO E=20.00 cm M2 55.71 5.29 294.71 - - 55.71 294.71 55.71 294.71 100.00
03.02.02 SUB BASE AFIRMADO E=0.15 m M2 55.71 7.89 439.55 - - 55.71 439.55 55.71 439.55 100.00
03.02.03 BASE AFIRMADO P/PISTA E=0.20m M2 55.71 11.84 659.61 - - 55.71 659.61 55.71 659.61 100.00
03.02.04 REPOSICION DE PAV. RIGIDO CONCRETO F`c=210kG/cm2 E=0.20m M2 55.71 53.47 2,978.81 - - 55.71 2,978.81 55.71 2,978.81 100.00
03.02.05 JUNTA DILATACION CON TECNOPORT 11/2" C/CR-250 ML 18.00 6.07 109.26 - - 18.00 109.26 18.00 109.26 100.00
03.03.00 ROTURA Y REPOSICION DE BLOQUETAS DE CONCRETO
03.03.01 RETIRO DE BLOQUETAS EXISTENTES M2 138.84 2.12 294.34 - - 138.84 294.34 138.84 294.34 100.00
03.03.02 SUB BASE AFIRMADO E=0.15 m M2 138.84 7.89 1,095.45 - - 138.84 1,095.45 138.84 1,095.45 100.00
03.03.03 BASE AFIRMADO P/PISTA E=0.20m M2 138.84 11.84 1,643.87 - - 138.84 1,643.87 138.84 1,643.87 100.00
03.03.04 BLOQUETAS CONCRETO F`c=380 Kg/cm2 M2 138.84 47.79 6,635.16 - - 138.84 6,635.16 138.84 6,635.16 100.00
03.04.00 REPOSICION DE SARDINEL
03.04.01 SARDINEL CONCRETO F`c=175 Kg/cm2 DE 0.15 X 0.70m M3 0.54 257.71 139.16 - - 0.54 139.16 0.54 139.16 100.00
04.00.00 MOVIMIENTO DE TIERRAS Y ADECUACION DE ZANJAS
04.01.00 EXCAVACION MAQUINA T. NORMAL Y RETIRO TUB. EXIST. H=1.50m ML 898.00 6.69 6,007.62 693.00 4,636.17 205.00 1,371.45 898.00 6,007.62 100.00
04.02.00 EXCAVACION MAQUINA T. NORMAL Y RETIRO TUB. EXIST. H=2.00m ML 831.00 8.41 6,988.71 614.00 5,163.74 217.00 1,824.97 831.00 6,988.71 100.00
04.03.00 EXCAVACION MAQUINA T. NORMAL Y RETIRO TUB. EXIST. H=2.50m ML 613.00 10.50 6,436.50 493.00 5,176.50 120.00 1,260.00 613.00 6,436.50 100.00
04.04.00 EXCAVACION MAQUINA T. NORMAL Y RETIRO TUB. EXIST. H=3.00m ML 473.50 14.03 6,643.21 375.50 5,268.27 98.00 1,374.94 473.50 6,643.21 100.00
04.05.00 REFINE Y NIVELACION FONDO ZANJA P/TUB. 8" ML 2,815.50 0.65 1,830.08 2,175.50 1,414.08 640.00 416.00 2,815.50 1,830.08 100.00
04.06.00 CAMA DE APOYO TUBERIA E=0.10m ML 2,815.50 2.75 7,742.63 2,175.50 5,982.63 640.00 1,760.00 2,815.50 7,742.63 100.00
VALORIZACION Nº 01 DE AVANCE DE OBRA
AGOSTO 2016
OBRA : 0
EJECUTA : 0
ENTIDAD : 0 ADELANTOS PLAZO DE EJECUCION
FR = 0.90451 Adelanto Directo 10.00% S/. 59,940.31 Inicio Plazo de Ejecucion :
VALOR REFERENCIAL : S/. 662,683.21 Adelanto Materiales 20.00% S/. 119,880.62 Plazo Ejecucion de Obra : 75 dias calendarios
PRESUPUESTO CONTRATADO : S/. 599,403.09 Monto total de adelantos S/. 179,820.93 Vencimiento de Plazo :

PRESUPUESTO AVANCES
Avance
PART. PARTIDA ANTERIOR ACTUAL ACUMULADO SALDO Acumul.
UND CANT. P.U. PARCIAL %
Metrado Monto S/. Metrado Monto S/. Metrado Monto S/. Metrado Monto S/.
04.07.00 RELLENO COMPACTADO C/MAT. PROPIO H=1.50m ML 898.00 6.47 5,810.06 693.00 4,483.71 205.00 1,326.35 898.00 5,810.06 100.00
04.08.00 RELLENO COMPACTADO C/MAT. PROPIO H=2.00m ML 831.00 8.18 6,797.58 614.00 5,022.52 217.00 1,775.06 831.00 6,797.58 100.00
04.09.00 RELLENO COMPACTADO C/MAT. PROPIO H=2.50m ML 613.00 11.35 6,957.55 493.00 5,595.55 120.00 1,362.00 613.00 6,957.55 100.00
04.10.00 RELLENO COMPACTADO C/MAT. PROPIO H=3.00m ML 473.50 15.10 7,149.85 375.50 5,670.05 98.00 1,479.80 473.50 7,149.85 100.00
04.11.00 ELIMINACION MAT. EXCEDENTE D=4Km M3 271.73 7.54 2,048.84 - - 271.73 2,048.84 271.73 2,048.84 100.00
04.12.00 ENTIBADO/DESENTIBADO CORRIDO ZANJA HASTA Hp=2.50m ML 613.00 26.09 15,993.17 493.00 12,862.37 120.00 3,130.80 613.00 15,993.17 100.00
04.13.00 ENTIBADO/DESENTIBADO CORRIDO ZANJA HASTA Hp=3.00m ML 473.50 35.75 16,927.63 375.50 13,424.13 98.00 3,503.50 473.50 16,927.63 100.00
04.14.00 TRASVASE AGUAS SERVIDAS MOTOBOMBA 8" HM 360.00 13.06 4,701.60 153.60 2,006.02 206.40 2,695.58 360.00 4,701.60 100.00
05.00.00 SUMINISTRO E INSTALACION DE TUBERIA DE ALCANTARILLADO
05.01.00 SUMINISTRO TUB. PVC 200mm S-20 UF ISO NTP 4435 ML 2,815.50 38.22 107,608.41 2,652.00 101,359.44 163.50 6,248.97 2,815.50 107,608.41 100.00
05.02.00 INSTALACION DE TUBERIA PVC 200mm UF/ISO ML 2,815.50 1.33 3,744.62 2,175.50 2,893.42 640.00 851.20 2,815.50 3,744.62 100.00
05.03.00 PRUEBA HIDR.-ESCORRENT. TUB. 200mm ML 2,815.50 1.41 3,969.86 2,175.50 3,067.46 640.00 902.40 2,815.50 3,969.86 100.00
06.00.00 COSNTRUCCION DE BUZONES Y REHABILITACION
06.01.00 BUZON ESTÁNDAR H=1.50m C/MARCO Y TAPA CONCRETO UND 3.00 1,140.05 3,420.15 - - 3.00 3,420.15 3.00 3,420.15 100.00
06.02.00 TAPON EN BUZON EXISTENTE UND 112.00 21.20 2,374.40 53.00 1,123.60 59.00 1,250.80 112.00 2,374.40 100.00
06.03.00 REHABILITACION BUZON H=1.50m UND 21.00 267.11 5,609.31 - - 21.00 5,609.31 21.00 5,609.31 100.00
06.04.00 REHABILITACION BUZON H=2.00m UND 11.00 287.14 3,158.54 - - 11.00 3,158.54 11.00 3,158.54 100.00
06.05.00 REHABILITACION BUZON H=2.50m UND 8.00 321.83 2,574.64 - - 8.00 2,574.64 8.00 2,574.64 100.00
06.06.00 REHABILITACION BUZON H=3.00m UND 5.00 353.34 1,766.70 - - 5.00 1,766.70 5.00 1,766.70 100.00
06.07.00 DADO CONCRETO Y EMPALME F`c=140Kg/cm2 DE 0.40X0.40X0.40 UND 112.00 38.70 4,334.40 53.00 2,051.10 59.00 2,283.30 112.00 4,334.40 100.00
07.00.00 CONEXIONES DOMICILIARIAS DE DESAGUE Y ROTURA VEREDAS -
07.01.00 CONEXIONES DOMICILIARIAS DE DESAGUE -
07.01.01 EXCAVACION TERRENO A MANO CNEX. DSG. TUB. 6" Hp=1.20m ML 2,002.00 7.16 14,334.32 1,274.00 9,121.84 728.00 5,212.48 2,002.00 14,334.32 100.00
07.01.02 REFINE, NIVEL. ZANJAP/TUB. 160mm INC. CAMA E=10cm ML 2,002.00 2.25 4,504.50 1,274.00 2,866.50 728.00 1,638.00 2,002.00 4,504.50 100.00
07.01.03 RELLENO COMPACTADO C/MATERIAL PROPIO ML 2,002.00 4.67 9,349.34 693.00 3,236.31 1,309.00 6,113.03 2,002.00 9,349.34 100.00
07.01.04 ELIMINACION MAT. EXCEDENTE D=4Km M3 117.39 7.54 885.12 - - 117.39 885.12 117.39 885.12 100.00
07.01.05 PRUEBA HIDR.+ESCORRENT. TUB. 6" (160mm) ZANJA ABIERTA ML 2,002.00 1.11 2,222.22 1,274.00 1,414.14 728.00 808.08 2,002.00 2,222.22 100.00
07.01.06 CONEX. DOMIC. TUB. PVC 160mm X 200mm INC. CAJA Y TAPA UND 286.00 195.93 56,035.98 71.00 13,911.03 215.00 42,124.95 286.00 56,035.98 100.00
07.02.00 ROTURA Y REPOSICION DE VERDAS - -
07.02.01 ROTURA DE VEREDA F`c=140Kg/cm2 H=0.10m M2 457.60 3.84 1,757.18 - - 457.60 1,757.18 457.60 1,757.18 100.00
07.02.02 BASE AFIRMADA P/VEREDA H=0.10m M2 457.60 6.41 2,933.22 - - 457.60 2,933.22 457.60 2,933.22 100.00
07.02.03 REPOSICION DE VEREDA F`c=140 Kg/cm2 H=0.10m M2 457.60 32.00 14,643.20 - - 457.60 14,643.20 457.60 14,643.20 100.00
08.00.00 OTRAS OBRAS - -
08.01.00 PROTECCION LINEA DE AGUA, DESAGUE Y LUZ EXIZTENTE GLB 1.00 55,414.51 55,414.51 0.50 27,707.26 0.50 27,707.26 1.00 55,414.51 100.00

COSTO DIRECTO 510,541.77 251,501.22 259,040.57 510,541.77 -


GASTOS GENERALES 5% 25,527.09 12,575.06 12,952.03 25,527.09 -
UTILIDAD 5% 25,527.09 12,575.06 12,952.03 25,527.09 -
SUB-TOTAL 561,595.95 276,651.34 284,944.63 561,595.95 -
FR 250,233.69 257,735.05 507,968.73
IGV (18%) 101,087.27 47,544.40 46,392.31 91,434.37 -
TOTAL 662,683.22 297,778.09 304,127.36 653,030.32 - 98.54
METRADOS DE OBRA

OBRA : 0 PLAZO DE EJECUCION


CONTRATISTA : 0 Inicio Plazo Ejecucion : 0
ENTIDAD : 0 Plazo Ejecucion Obra : 75 dias calendarios
SUPERVISION : 0 Vencimiento de Plazo : 0

DIMENSIONES
ITEM PARTIDA UND CANT. PARCIAL TOTAL
L A H
00.00.00 REDES DE ALCANTARILLADO
01.00.00 OBRAS PROVISIONALES
01.01.00 CASETA DE GUARDIANIA Y ALMACEN MES 1.00 - - - 1.00 1.00
01.03.00 SEÑALIZACION, DESVIO TRANSITO Y PROTECCION OBRA UND 4.00 - - - 4.00 4.00
01.04.00 MOVILIZACION DE EQUIPOS Y MAQUINARIA A LA OBRA GLB 0.50 - - - 0.50 0.50
02.00.00 TRABAJOS PRELIMINARES
02.01.00 TRAZO Y REPLANTEO ML 2,175.50
Excavacion a Maquina T. Normal H=1.50 m
Bz. 12 - 13 1.00 54.00 - - 54.00
Bz. 8 - 15 1.00 53.00 - - 53.00
Bz. 18 - 19 1.00 62.00 - - 62.00
Bz. 19 - 20 1.00 48.00 - - 48.00
Bz. 20 - 21 1.00 40.00 - - 40.00
Bz. 22 - 23 1.00 40.00 - - 40.00
Bz. 31 - 32 1.00 59.00 - - 59.00
Bz. 37 - 38 1.00 26.00 - - 26.00
Bz. 37 - 39 1.00 61.00 - - 61.00
Bz. 39 - 44 1.00 61.00 - - 61.00
Bz. 45 - 44 1.00 26.00 - - 26.00
Bz. 50 - 51 1.00 50.00 - - 50.00
Bz. 51 - 52 1.00 50.00 - - 50.00
Bz. 52 - 53 1.00 63.00 - - 63.00
Excavacion a Maquina T. Normal H=2.00 m
Bz. 13 - 14 1.00 60.00 - - 60.00
Bz. 14 - 15 1.00 55.00 - - 55.00
Bz. 18 - 17 1.00 62.00 - - 62.00
Bz. 23 - 24 1.00 40.00 - - 40.00
Bz. 32 - 33 1.00 60.00 - - 60.00
Bz. 36 - 37 1.00 77.00 - - 77.00
Bz. 40 - 36 1.00 61.00 - - 61.00
Bz. 43 - 40 1.00 61.00 - - 61.00
Bz. 44 - 43 1.00 77.00 - - 77.00
Bz. 50 - 49 1.00 61.00 - - 61.00
Excavacion a Maquina T. Normal H=2.50 m
Bz. 16 - 17 1.00 62.50 - - 62.50
Bz. 15 - 28 1.00 25.00 - - 25.00
Bz. 25 - 26 1.00 62.00 - - 62.00
Bz. 24 - 25 1.00 61.50 - - 61.50
Bz. 33 - 34 1.00 55.00 - - 55.00
Bz. 36 - 35 1.00 55.50 - - 55.50
Bz. 42 - 41 1.00 61.00 - - 61.00
Bz. 43 - 42 1.00 55.50 - - 55.50
Bz. 49 - 42 1.00 55.00 - - 55.00
Excavacion a Maquina T. Normal H=3.00 m
Bz. 26 - 29 1.00 62.50 - - 62.50
Bz. 16 - 6 1.00 53.00 - - 53.00
Bz. 16 - 29 1.00 56.00 - - 56.00
Bz. 30 - 28 1.00 30.00 - - 30.00
Bz. 34 - 30 1.00 58.00 - - 58.00
Bz. 29 - 35 1.00 55.00 - - 55.00
Bz. 41 - 35 1.00 61.00 - - 61.00
03.00.00 ROTURA Y REPOSICION DE PAV. ASFALTICO, CONC. Y BLOQ.
03.01.00 ROTURA Y REPOSICION DE PAVIMENTO ASFALTICO
03.01.01 ROTURA DE PAVIMENTO ASFALTICO C/EQUIPO E=5.0 cm M2 1,029.60
Rotura de Pavimento de Asfalto (Av. Marcavelica) :
Prolong. Av. Grau y Calle 5 - M. der. 1.00 56.00 1.80 - 100.80
Calles 5 y 4 - M. der. 1.00 56.00 1.80 - 100.80
Calles 4 y 3 - M. der. 1.00 55.00 1.80 - 99.00
Calles 3 y 2 - M. der. 1.00 122.00 1.80 - 219.60
Calles 2 y 1 - M. der. 1.00 55.00 1.80 - 99.00
Calles 1 y Prolong. Av. Sanchez Cerro - M. der. 1.00 61.00 1.80 - 109.80
Prolong. Av. Grau y Calle 5 - M. izq. 1.00 56.00 1.80 - 100.80
METRADOS DE OBRA

OBRA : 0 PLAZO DE EJECUCION


CONTRATISTA : 0 Inicio Plazo Ejecucion : 0
ENTIDAD : 0 Plazo Ejecucion Obra : 75 dias calendarios
SUPERVISION : 0 Vencimiento de Plazo : 0

DIMENSIONES
ITEM PARTIDA UND CANT. PARCIAL TOTAL
L A H
Calles 5 y 4 - M. izq. 1.00 56.00 1.80 - 100.80
Calles 4 y 3 - M. izq. 1.00 55.00 1.80 - 99.00
04.00.00 MOVIMIENTO DE TIERRAS Y ADECUACION DE ZANJAS
04.01.00 EXCAVACION MAQ. T. NORMAL Y RETIRO TUB. EXIST. H=1.50 m ML 693.00
Bz. 12 - 13 1.00 54.00 - - 54.00
Bz. 8 - 15 1.00 53.00 - - 53.00
Bz. 18 - 19 1.00 62.00 - - 62.00
Bz. 19 - 20 1.00 48.00 - - 48.00
Bz. 20 - 21 1.00 40.00 - - 40.00
Bz. 22 - 23 1.00 40.00 - - 40.00
Bz. 31 - 32 1.00 59.00 - - 59.00
Bz. 37 - 38 1.00 26.00 - - 26.00
Bz. 37 - 39 1.00 61.00 - - 61.00
Bz. 39 - 44 1.00 61.00 - - 61.00
Bz. 45 - 44 1.00 26.00 - - 26.00
Bz. 50 - 51 1.00 50.00 - - 50.00
Bz. 51 - 52 1.00 50.00 - - 50.00
Bz. 52 - 53 1.00 63.00 - - 63.00
04.02.00 EXCAVACION MAQ. T. NORMAL Y RETIRO TUB. EXIST. H=2.00 m ML 614.00
Bz. 13 - 14 1.00 60.00 - - 60.00
Bz. 14 - 15 1.00 55.00 - - 55.00
Bz. 18 - 17 1.00 62.00 - - 62.00
Bz. 23 - 24 1.00 40.00 - - 40.00
Bz. 32 - 33 1.00 60.00 - - 60.00
Bz. 36 - 37 1.00 77.00 - - 77.00
Bz. 40 - 36 1.00 61.00 - - 61.00
Bz. 43 - 40 1.00 61.00 - - 61.00
Bz. 44 - 43 1.00 77.00 - - 77.00
Bz. 50 - 49 1.00 61.00 - - 61.00
04.03.00 EXCAVACION MAQ. T. NORMAL Y RETIRO TUB. EXIST. H=2.50 m ML 493.00
Bz. 16 - 17 1.00 62.50 - - 62.50
Bz. 15 - 28 1.00 25.00 - - 25.00
Bz. 25 - 26 1.00 62.00 - - 62.00
Bz. 24 - 25 1.00 61.50 - - 61.50
Bz. 33 - 34 1.00 55.00 - - 55.00
Bz. 36 - 35 1.00 55.50 - - 55.50
Bz. 42 - 41 1.00 61.00 - - 61.00
Bz. 43 - 42 1.00 55.50 - - 55.50
Bz. 49 - 42 1.00 55.00 - - 55.00
04.04.00 EXCAVACION MAQ. T. NORMAL Y RETIRO TUB. EXIST. H=3.00 m ML 375.50
Bz. 26 - 29 1.00 62.50 - - 62.50
Bz. 16 - 6 1.00 53.00 - - 53.00
Bz. 16 - 29 1.00 56.00 - - 56.00
Bz. 30 - 28 1.00 30.00 - - 30.00
Bz. 34 - 30 1.00 58.00 - - 58.00
Bz. 29 - 35 1.00 55.00 - - 55.00
Bz. 41 - 35 1.00 61.00 - - 61.00
04.05.00 REFINE Y NIVELACION FONDO DE ZANJA P/TUB. 8" ML (Sumatoria de partidas 04.01.00, 04.02.00, 04.03.00 y 04.04.00) 2,175.50
04.06.00 CAMA DE APOYO TUBERIA E=0.10m ML (Igual Partida 04.05.00) 2,175.50
04.07.00 RELLENO COMPACTADO C/MATERIAL PROPIO H=1.50 m ML 693.00
Bz. 12 - 13 1.00 54.00 - - 54.00
Bz. 8 - 15 1.00 53.00 - - 53.00
Bz. 18 - 19 1.00 62.00 - - 62.00
Bz. 19 - 20 1.00 48.00 - - 48.00
Bz. 20 - 21 1.00 40.00 - - 40.00
Bz. 22 - 23 1.00 40.00 - - 40.00
Bz. 31 - 32 1.00 59.00 - - 59.00
Bz. 37 - 38 1.00 26.00 - - 26.00
Bz. 37 - 39 1.00 61.00 - - 61.00
Bz. 39 - 44 1.00 61.00 - - 61.00
Bz. 45 - 44 1.00 26.00 - - 26.00
Bz. 50 - 51 1.00 50.00 - - 50.00
METRADOS DE OBRA

OBRA : 0 PLAZO DE EJECUCION


CONTRATISTA : 0 Inicio Plazo Ejecucion : 0
ENTIDAD : 0 Plazo Ejecucion Obra : 75 dias calendarios
SUPERVISION : 0 Vencimiento de Plazo : 0

DIMENSIONES
ITEM PARTIDA UND CANT. PARCIAL TOTAL
L A H
Bz. 51 - 52 1.00 50.00 - - 50.00
Bz. 52 - 53 1.00 63.00 - - 63.00
04.08.00 RELLENO COMPACTADO C/MATERIAL PROPIO H=2.00 m ML 614.00
Bz. 13 - 14 1.00 60.00 - - 60.00
Bz. 14 - 15 1.00 55.00 - - 55.00
Bz. 18 - 17 1.00 62.00 - - 62.00
Bz. 23 - 24 1.00 40.00 - - 40.00
Bz. 32 - 33 1.00 60.00 - - 60.00
Bz. 36 - 37 1.00 77.00 - - 77.00
Bz. 40 - 36 1.00 61.00 - - 61.00
Bz. 43 - 40 1.00 61.00 - - 61.00
Bz. 44 - 43 1.00 77.00 - - 77.00
Bz. 50 - 49 1.00 61.00 - - 61.00
04.09.00 RELLENO COMPACTADO C/MATERIAL PROPIO H=2.50 m ML 493.00
Bz. 16 - 17 1.00 62.50 - - 62.50
Bz. 15 - 28 1.00 25.00 - - 25.00
Bz. 25 - 26 1.00 62.00 - - 62.00
Bz. 24 - 25 1.00 61.50 - - 61.50
Bz. 33 - 34 1.00 55.00 - - 55.00
Bz. 36 - 35 1.00 55.50 - - 55.50
Bz. 42 - 41 1.00 61.00 - - 61.00
Bz. 43 - 42 1.00 55.50 - - 55.50
Bz. 49 - 42 1.00 55.00 - - 55.00
04.10.00 RELLENO COMPACTADO C/MATERIAL PROPIO H=3.00 m ML 375.50
Bz. 26 - 29 1.00 62.50 - - 62.50
Bz. 16 - 6 1.00 53.00 - - 53.00
Bz. 16 - 29 1.00 56.00 - - 56.00
Bz. 30 - 28 1.00 30.00 - - 30.00
Bz. 34 - 30 1.00 58.00 - - 58.00
Bz. 29 - 35 1.00 55.00 - - 55.00
Bz. 41 - 35 1.00 61.00 - - 61.00
04.12.00 ENTIBADO/DESENTIBADO CORRIDO ZANJA HASTA Hp=2.50M ML 493.00
Bz. 16 - 17 1.00 62.50 - - 62.50
Bz. 15 - 28 1.00 25.00 - - 25.00
Bz. 25 - 26 1.00 62.00 - - 62.00
Bz. 24 - 25 1.00 61.50 - - 61.50
Bz. 33 - 34 1.00 55.00 - - 55.00
Bz. 36 - 35 1.00 55.50 - - 55.50
Bz. 42 - 41 1.00 61.00 - - 61.00
Bz. 43 - 42 1.00 55.50 - - 55.50
Bz. 49 - 42 1.00 55.00 - - 55.00
04.13.00 ENTIBADO/DESENTIBADO CORRIDO ZANJA HASTA Hp=3.00M ML 375.50
Bz. 26 - 29 1.00 62.50 - - 62.50
Bz. 16 - 6 1.00 53.00 - - 53.00
Bz. 16 - 29 1.00 56.00 - - 56.00
Bz. 30 - 28 1.00 30.00 - - 30.00
Bz. 34 - 30 1.00 58.00 - - 58.00
Bz. 29 - 35 1.00 55.00 - - 55.00
Bz. 41 - 35 1.00 61.00 - - 61.00
04.14.00 TRASVASE AGUAS SERVIDAS - MOTOBOMBA 8" HM 1.00 - - - 153.60 153.60
32 dias trabajados (Periodo del 29/02 al 31/03/08) ( 32 dias x 4.8 hh/dia ) = 153.60 HM
05.00.00 SUMINISTRO E INSTALACION DE TUB. DE ALCANTARILLADO
05.01.00 SUMINISTRO DE TUB. PVC 200mm S-20 UF ISO NTP4435 ML - - - - - 2,652.00
Guia Remision Nº 005-0003022 - NICOLL PERU S.A. 25.00 6.00 - - 150.00
Guia Remision Nº 005-0003146 - NICOLL PERU S.A. 80.00 6.00 - - 480.00
Guia Remision Nº 005-0003250 - NICOLL PERU S.A. 160.00 6.00 - - 960.00
Guia Remision Nº 005-0003274 - NICOLL PERU S.A. 160.00 6.00 - - 960.00
17.00 6.00 - - 102.00
05.02.00 INSTALACION DE TUBERIA PVC 200mm UF/ISO ML (Igual Partida 04.06.00) 2,175.50
05.03.00 PRUEBA HIDR.+ESCORRENT. TUB. 200mm (8") ML (Igual Partida 05.02.00) 2,175.50
06.00.00 CONSTRUCCION DE BUZONES Y REHABILITACION
06.02.00 TAPON EN BUZON EXISTENTE UND 53.00
METRADOS DE OBRA

OBRA : 0 PLAZO DE EJECUCION


CONTRATISTA : 0 Inicio Plazo Ejecucion : 0
ENTIDAD : 0 Plazo Ejecucion Obra : 75 dias calendarios
SUPERVISION : 0 Vencimiento de Plazo : 0

DIMENSIONES
ITEM PARTIDA UND CANT. PARCIAL TOTAL
L A H
Tapon 01 solo lado = Bz 45,42,35,38,31,34,29,22,12,15,21 11.00 - - - 11.00
Tapon 02 lados = Bz 39,40,32,33,23,24,25,26,13,14,16,17,18,19,20 30.00 - - - 30.00
Tapon 03 lados = Bz 36,37,43,44 12.00 - - - 12.00
06.07.00 DADO CONCRETO Y EMPALME F`c=140 Kg/cm2 UND (Igual Partida 06.02.00) 53.00
07.00.00 CONEXIONES DOMICILIARIAS DESAGUE Y ROTURA VEREDAS
07.01.00 CONEXIONES DOMICILIARIAS DESAGUE
07.01.01 EXCAVACION TERRENO A MANO CONEX. DSG. TUB 6" Hp=1.20m ML 1,274.00
Calle 2 16.00 7.00 - - 112.00
Calle 3 31.00 7.00 - - 217.00
Calle 7 12.00 7.00 - - 84.00
Calle 8 12.00 7.00 - - 84.00
Calle 4 29.00 7.00 - - 203.00
Calle 5 66.00 7.00 - - 462.00
Prolong. Av. Sanchez Cerro 16.00 7.00 - - 112.00
07.01.02 REFINE, NIVELAC. ZANJA P/TUB. 160 mm INC. CAMA e=0.10m ML (Igual Partida 07.01.01) 1,274.00
07.01.03 RELLENO COMPACTADO CON MATERIAL PROPIO ML 693.00
Calle 2 16.00 3.50 - - 56.00
Calle 3 31.00 3.50 - - 108.50
Calle 7 12.00 3.50 - - 42.00
Calle 8 12.00 3.50 - - 42.00
Calle 4 29.00 3.50 - - 101.50
Calle 5 66.00 3.50 - - 231.00
Prolong. Av. Sanchez Cerro 16.00 7.00 - - 112.00
07.01.05 PRUEBA HIDR.+ESCORRENT. TUB. 160mm (6") ZANJA ABIERTA ML 1,274.00
Calle 2 16.00 7.00 - - 112.00
Calle 3 31.00 7.00 - - 217.00
Calle 7 12.00 7.00 - - 84.00
Calle 8 12.00 7.00 - - 84.00
Calle 4 29.00 7.00 - - 203.00
Calle 5 66.00 7.00 - - 462.00
Prolong. Av. Sanchez Cerro 16.00 7.00 - - 112.00
07.01.06 CONEX. DOMIC. TUB. PVC 160mm x 200mm INC. CAJA Y TAPA UND 71.00
Calle 2 16.00 - - - 16.00
Calle 3 31.00 - - - 31.00
Calle 7 12.00 - - - 12.00
Calle 8 12.00 - - - 12.00
08.00.00 OTRAS OBRAS
08.01.00 PROTECCION DE LINEA DE AGUA, DESAGUE Y LUZ EXISTENTE GLB 0.50 - - - 0.50 0.50
VALORIZACIÓN No. 01
41730

OBRA : 0
EJECUTA : 0
ENTIDAD : 0

PRESUPUESTO CONTRATADO : S/. 599,403.09

PLAZO DE EJECUCION : 75 dias calendarios

INICIO DEL PLAZO CONTRACTUAL : 12/30/1899

VENCIMIENTO DEL PLAZO : 12/30/1899

AVANCE FISICO DE LA OBRA : 9854.00%

PROGRAMADO EJECUTADO REAL


FECHA
PARCIAL ACUMULADO % AVANCE PARCIAL ACUMULADO % AVANCE

Mar-08 S/. 198,340.75 S/. 198,340.75 33.26% S/. 304,127.36 S/. 304,127.36 9854.00%

Apr-08

May-08

Jun-08

ESTADO OBRA : OBRA ADELANTADA