Project Name: CPRL 113MW HFO BASED POWER PLANT PROJECT, RANGPUR

EPC Contractor: REVERIE POWER & AUTOMATION ENGINEERING LTD

Site Visit Date: 20th Febuary, 2019

Serial No Vendor Tasks Discription Work Status Remarks

MV cable laying work finished.


a) MV & LV Power Cable Laying Status LV incomer power cable laying & termination work finished.
Dependency:

Pending Area: STG, Radiator Area & STG Cooling Tower Area.
b) Earthing Job Status Dependency: due to soil excavation, cable damage caused.
Earth Test: Substation Area Completed.

Cable laying work completed for all area.


c) Lighting Work Status Light installation job pending on MV, LV, FTP & WTP Room.

d) Lightning Installation Job

1 Reverie
e) Cable Trench (tank area communication cable route)

f) All Panel Installation & Testing Status

g) RTCC unit secondary drawing finalization

Remote operation check work is contnuing.


h) 132kV Substation Overall Status
Line Feeder operation check done.

i) Overall Material Status

a) GCC & ECC Panel Cable laying

b) EMCC Panel Cable laying & Route Clerance

c) Communiction System via Profinet

d) Rolls Royce Scope Cable Lists (Profibus, TW pair cable)


2 Rolls Royce

e) NGT panel drawing Modifications

f) VFD panel signal lists & Operation schemes

g) RMCC Panel Cable laying

h) Bus Coupling modification Report

a) Cable Trench Update including pipe trench Isuue

b) Control Room Panel General Arrangement Finalization

3 M/s MAN & M/s PIVOT c) Overall cable schedule & cable laying plan

d) Cable & Cable tray site requirement

e) STG building overall status