Académique Documents
Professionnel Documents
Culture Documents
TABLE OF CONTENTS
1.0 SCOPE...............................................................................................................................7
6.3 Valves...................................................................................................................24
6.3.1 General ..................................................................................................... 24
6.3.2 Accessibility .............................................................................................. 24
6.3.3 Chain Operators ....................................................................................... 25
6.3.4 Handwheel Access................................................................................... 25
6.3.5 Valve Installation, Vertical Handwheel Orientation .................................. 26
6.3.6 Valve Installation, Horizontal Handwheel Orientation.............................. 26
6.3.7 Relative Valve Elevation........................................................................... 27
6.3.8 Valves Below Grade ................................................................................. 27
6.3.9 Valve Body Cavity/Bonnet Pressure Relief.............................................. 27
6.3.10 Globe Type Control Valves....................................................................... 28
6.3.11 Check Valves............................................................................................ 28
6.3.12 Ball Valves ................................................................................................ 28
6.3.13 Safety Relief Valves.................................................................................. 28
6.3.14 Thermal Relief Valves............................................................................... 29
6.3.15 Valve Selection ......................................................................................... 29
6.4 Centrifugal Pumps..............................................................................................29
6.4.1 General ..................................................................................................... 29
6.4.2 Flange Loads ............................................................................................ 30
6.4.3 Piping Reducers ....................................................................................... 30
6.4.4 Restrictions on Elbows in Suction Piping ................................................. 30
6.4.5 Vertical Elbows in Suction Piping ............................................................. 30
6.4.6 Horizontal Elbows in Suction Piping......................................................... 30
6.4.7 Temporary Strainers................................................................................. 30
6.4.8 Vents and Drains ...................................................................................... 30
6.4.9 Pump Selection......................................................................................... 31
6.5 Vent and Drain Systems ...................................................................................31
6.5.1 General ..................................................................................................... 31
6.5.2 Vent and Drain Piping (NPS 2 and smaller)............................................. 31
6.5.3 Equipment Isolation and Drains ............................................................... 31
6.5.4 Pipe Header Termination Drains .............................................................. 31
6.5.5 Vents on Buried Piping ............................................................................. 31
6.5.6 Drain Piping Slopes .................................................................................. 32
6.5.7 Open Drain Header Systems ................................................................... 32
6.5.8 Closed Drain Header Systems ................................................................. 32
6.5.9 Expansion Chambers ............................................................................... 32
7.2 Analysis................................................................................................................33
7.3 Design Criteria ....................................................................................................34
7.4 Routing .................................................................................................................34
7.5 Expansion Joints ................................................................................................35
7.6 Piping Supports ..................................................................................................35
7.6.1 Pipe Support Layout ................................................................................. 35
7.6.2 Anchoring and Guides .............................................................................. 35
7.6.3 Anchor Blocks........................................................................................... 35
7.6.4 Welded Pipe Supports .............................................................................. 36
7.7 Piping Spans .......................................................................................................36
10.0 INSULATION...................................................................................................................42
10.1 Insulation Materials and Application................................................................42
10.1.1 Exterior Piping........................................................................................... 42
10.1.2 Interior Piping............................................................................................ 42
10.1.3 Buried Piping ............................................................................................. 42
10.1.4 Vessels and Tanks.................................................................................... 42
10.1.5 Valves and Equipment.............................................................................. 42
TERASEN PIPELINES (TRANS MOUNTAIN) INC.
ENGINEERING STANDARDS AND PRACTICES
MP1110 Revision 3 January 21, 2000 Page 6 of 44
Title: STATION & TERMINAL PIPING DESIGN
APPENDICES
1.0 SCOPE
This standard is a guide to mandatory design practices for station piping. This
standard shall be limited to systems transporting liquid hydrocarbons including:
crude oil, condensate and liquid petroleum products. This standard shall be
further limited to the design of Low Vapour Pressure (LVP) systems intended for
Category I service.
The scope of this standard includes all pressure pipe, valves, fittings and auxiliary
components used in tank farms, pump stations and terminals. This standard does
not cover the design of Main Line piping systems. The designer is cautioned that
this standard is not a comprehensive design handbook; it does not do away with
the need for the designer or for competent engineering judgement.
The requirements of this standard shall not be applied retroactively to existing
installations, but shall apply to the extension, repair, maintenance, and upgrading
of such installations.
Note: Facilities indicated by heavy lines are within the scope of this standard,
light lines indicate facilities not within the scope.
TERASEN PIPELINES (TRANS MOUNTAIN) INC.
ENGINEERING STANDARDS AND PRACTICES
MP1110 Revision 3 January 21, 2000 Page 8 of 44
Title: STATION & TERMINAL PIPING DESIGN
3.0 DEFINITIONS
3.3 NPS
NPS means Nominal Pipe Size , and the NPS system of nominal size
designation is contained in standards prepared by the American Society of
Mechanical Engineers.
3.4 PN
PN means Pressure Nominal and the PN system of nominal pressure class
designation is contained in standards prepared by the International
Organization for Standardization (ISO). The numerical part of the
designation approximates the maximum cold working pressure rating in bars
(100 kPa).
3.7 SMYS
SMYS means Specified Minimum Yield Strength. This is the minimum
yield strength prescribed by the specification or standard under which the
material is produced.
TERASEN PIPELINES (TRANS MOUNTAIN) INC.
ENGINEERING STANDARDS AND PRACTICES
MP1110 Revision 3 January 21, 2000 Page 10 of 44
Title: STATION & TERMINAL PIPING DESIGN
4.1 General
4.1.4 Materials
The material requirements for pipe, piping components and non-
metallic elements (ie. gaskets, elastomers) shall be in accordance
with the requirements of Appendix A.
4000
Region 3
Short
3500
runs only
Region 4
3000 Avoid applications
in this region
Flow Rate (m 3/hr)
2500
Region 2
2000 Discharge
Piping
1500
1000 Region 1
Suction Piping
500
0
6 8 10 12 14 16 18 20 22 24 26 28 30
Pipe Size (NPS)
5.1 Flanges
5.1.1 General
Raised face, weld neck flanges should be used for permanent
piping. Slip on flanges should be avoided. If slip on flanges are
used, they shall be double welded (welded on the inside and outside
diameter). Except as permitted by clause 5.1.2, the material grade
shall conform to the requirements of Appendix A.
5.2 Fittings
5.2.3 Reducers
Concentric or eccentric reducers joining pipes of different thickness
should be specified for the thicker wall, with end preparation as per
subsection 5.3.5.
5.3.1 General
Typical piping joints are welded, flanged or threaded. Piping systems
should be designed to minimize the number of joints, and should be
welded wherever possible. Joints on piping shall be in accordance
with the requirements of Table 5.3.1.A.
PN 20 = NPS 1½ ? ?
Drain Systems ? ? ?
5.4.1 Elbows
Long radius elbows shall be used in permanent piping for sizes NPS
3 and larger. Because of their poor hydraulic characteristics, short
radius elbows are to be avoided, particularly in pump suction piping
and upstream of valves, flow measuring equipment, and
instrumentation connections. One exception is the use of short
radius elbows in safety relief valve discharge piping to minimize the
moment and forces on the valve.
6.1 General
The overall piping arrangement should be neat, orderly, and economical
based on the following guidelines:
6.1.2 Consistency
Piping layouts at multiple identical pieces of equipment should be
alike for familiarity and ease of operation.
6.1.3 Maintainability
All piping and equipment requiring regular attention by operating and
maintenance personnel should be readily accessible. Adequate,
clear working spaces, of at least 1m, should be provided around
equipment such as pumps and valves. Piping should be self
supporting for ease of equipment removal.
6.1.4 Operability
Piping shall be designed such that operating personnel can perform
their functions in an efficient manner. Not every valve and instrument
can be ideally located, but priorities can be established by
consideration of the frequency of operation and degree of physical
effort required.
6.1.5 Safety
Stairs, ladders, and platforms shall be provided with adequate head
room and lateral clearance. Equipment, valves and other piping
components shall be located such that they do not create hazards.
Special care shall be taken in the placement of valve stems. Every
effort shall be made to keep such projections out of the area between
1400 to 1800 mm (face level) above grade.
6.1.6 Environment
At large integrated manifold systems, overhead cranes complete with
roof systems should be provided to shelter workers and equipment
from the elements and minimize the amount of rainwater runoff to be
TERASEN PIPELINES (TRANS MOUNTAIN) INC.
ENGINEERING STANDARDS AND PRACTICES
MP1110 Revision 3 January 21, 2000 Page 21 of 44
Title: STATION & TERMINAL PIPING DESIGN
6.2 Clearances
6.3 Valves
6.3.1 General
Valves should be installed with their stems oriented between the
vertical upward (preferred) and 45° from vertical positions. Horizontal
valve installations should be avoided. Valves shall not be installed
upside down. The following safety hazards must be avoided when
determining stem orientation: head and knee interference, tripping
hazards, and valve stems at eye level in the horizontal plane. The
valve handwheel size shall not be reduced to accommodate the
piping arrangement.
6.3.2 Accessibility
In determining the location of valves in piping systems, accessibility
for operation and adequate space for maintenance shall be provided.
The use of extended stems should be considered in order to avoid
unnecessary loops or turns in the piping.
TERASEN PIPELINES (TRANS MOUNTAIN) INC.
ENGINEERING STANDARDS AND PRACTICES
MP1110 Revision 3 January 21, 2000 Page 25 of 44
Title: STATION & TERMINAL PIPING DESIGN
VERTICAL HORIZONTAL
TERASEN PIPELINES (TRANS MOUNTAIN) INC.
ENGINEERING STANDARDS AND PRACTICES
MP1110 Revision 3 January 21, 2000 Page 26 of 44
Title: STATION & TERMINAL PIPING DESIGN
6.4.1 General
Piping systems at pump locations shall be designed to allow for
pump removal and maintenance. At locations with multiple pumps,
each pump should have isolation valves and a check valves. The
piping should be designed to minimize flanges loads on the pump
and flexible connections to pumps shall be avoided. Flexible
connections shall not be permitted for pumps with drivers greater
than 3 kw in size.
TERASEN PIPELINES (TRANS MOUNTAIN) INC.
ENGINEERING STANDARDS AND PRACTICES
MP1110 Revision 3 January 21, 2000 Page 30 of 44
Title: STATION & TERMINAL PIPING DESIGN
6.5.1 General
High-point vent and low-point drain connections shall be provided
on all piping systems. These connections provide a means of
flooding and draining piping systems and equipment for hydrostatic
testing and during start-up and shutdown. The recommended design
of vents and drains shall be as shown in Appendix B.
7.1 General
Piping systems shall have sufficient flexibility to prevent thermal expansion or
contraction or movements of piping supports from causing:
7.2 Analysis
Piping stress and flexibility analysis is required for NPS 4 and larger piping
when:
a) it is connected to rotating equipment;
b) it is connected to equipment subject to differential settlement;
c) it forms part of a pressure relieving system;
d) the operating pressures e xceed 7000 kPa; or
e) the operating temperature is outside the shaded area in Figure 7.2.A.
175
-25
2 4 6 8 10 12
7.4 Routing
The following guidelines shall be used to obtain the required flexibility using
the minimum amount of pipe, fittings, and expansion loops:
Note: Spans listed in Table 7.7.A are designed to limit piping deflections to 6.35 mm. Do
not apply where concentrated weights such as heavy valves or heavy fittings exist.
4
TERASEN PIPELINES (TRANS MOUNTAIN) INC.
ENGINEERING STANDARDS AND PRACTICES
MP1110 Revision 3 January 21, 2000 Page 37 of 44
Title: STATION & TERMINAL PIPING DESIGN
8.1.1 General
The mi nimum design wall thickness for buried piping shall be
determined by the following design formula:
8.2.1 General
Wherever possible, buried piping should be located in straight runs
on flat ground. Steep slopes should be avoided. In areas where
steep slopes cannot be avoided, piping should be located such that it
follows the fall line of the slope.
8.4 Backfill
With the exception of bored sections or piping installed in compressible soils
all buried piping should be backfilled in a manner consistent with the cross-
section illustrated in Figure 8.3.3.A. The bedding material should be sand or
fine sand and gravel. If the native soils excavated for the trench are
unsuitable or cannot otherwise be screened, the sand bedding shall be
imported from an appropriate borrow site. Bedding should be placed around
the pipe in a manner to prevent damage to the coating and mechanically
compacted using vibratory equipment to 95% standard Proctor maximum
dry density.
9.2.1 General
All external surfaces of buried, carbon steel piping shall be coated in
accordance with Terasen Pipelines (Trans Mountain) Inc.
Standard GC3102. Alternative coating systems are listed in
Appendix A.
10.0 INSULATION
11.1 Examinations
All nondestructive examinations (visual, radiographic, liquid penetrant and
magnetic particle) shall be in accordance with Terasen Pipelines (Trans
Mountain) Inc. Standard MP3901.
11.2 Testing
All pressure piping and atmospheric drain systems shall be hydrostatically
tested in accordance with Terasen Pipelines (Trans Mountain) Inc.
Standard MP4111. Where pre-tested assemblies are installed, the numbers
of "tie-in" welds not subjected to a pressure test shall be minimized to the
extent possible.