TOTAL = 36 UNIT
Date : 23-01-2019
Diesel Engine
QTY Installation Plan Schedule Photo Progress 19-8-2017 Photo Progress 07-01-2018 Photo Progress 2-07-2018 Photo Progress 21-09-2018 Photo Progress 22-11-2018 Photo Progress 23-01-2019
No Area Description Rating ( KW )
Plan Actual Started Finished Condition Area Condition Area Condition Area Condition Area Condition Area Condition Area
1 Pioneer Camp LV Generator 3 3 560 kw 01/08/2017 15/10/2017
( Act: 7-10-2017 ) (Comm 26-12-2017)
LV MCC Switchgear 1 1 0,4 kv
2 Early Camp & Subcont Camp-2 LV Generator 12 12 560 kw 01/09/2017 ( Delay ) 30/01/2018( Delay )
LV MCC Switchgear 2 2 0,4 kv ( Act: 21-2-2018 ) ( Act: 2-5-2018 )
NO PROGRESS
4 Company & Contractor Office LV Generator 5 5 560 kw 01/10/2017( Delay ) 15/01/2018( Delay )
( Act: 19-5-2018 ) ( Act: 26-5-2018 )
LV MCC Switchgear 1 1 0,4 kv 08/06/2018 08/06/2018
NO PROGRESS
NO PROGRESS
TOTAL : LV GENERATOR 36 30
N E W
ADD
ADD