GENERATOR SET CSTS INSTALLATION STATUS

TOTAL = 36 UNIT

Date : 23-01-2019
Diesel Engine
QTY Installation Plan Schedule Photo Progress 19-8-2017 Photo Progress 07-01-2018 Photo Progress 2-07-2018 Photo Progress 21-09-2018 Photo Progress 22-11-2018 Photo Progress 23-01-2019
No Area Description Rating ( KW )
Plan Actual Started Finished Condition Area Condition Area Condition Area Condition Area Condition Area Condition Area
1 Pioneer Camp LV Generator 3 3 560 kw 01/08/2017 15/10/2017
( Act: 7-10-2017 ) (Comm 26-12-2017)
LV MCC Switchgear 1 1 0,4 kv

2 Early Camp & Subcont Camp-2 LV Generator 12 12 560 kw 01/09/2017 ( Delay ) 30/01/2018( Delay )
LV MCC Switchgear 2 2 0,4 kv ( Act: 21-2-2018 ) ( Act: 2-5-2018 )

3 Subcontractor Camp-1 LV Generator 5 5 560 kw 15/11/2017( Delay ) 30/01/2018( Delay ) NEW


( Act: 19-9-2018 ) ( Act: 20-9-2018 )
LV MCC Switchgear 1 1 0,4 kv 06/11/2018 06/11/2018

NO PROGRESS

4 Company & Contractor Office LV Generator 5 5 560 kw 01/10/2017( Delay ) 15/01/2018( Delay )
( Act: 19-5-2018 ) ( Act: 26-5-2018 )
LV MCC Switchgear 1 1 0,4 kv 08/06/2018 08/06/2018

5 RO & BOF Facility LV Generator 3 3 560 kw 30/10/2017 15/12/2017


(Act :14/11/2017 )
LV MCC Switchgear 1 1 0,4 kv
Dry Type Transformer 1 1 0,4 / 0,69 kv

6 Warehouse LV Generator 2 2 440 kw 01/10/2017( Delay ) 15/11/2017( Delay )


NEW
(Act :10/11/2018 )
LV MCC Switchgear 1 1 0,4 kv

NO PROGRESS

7 Rest Sheed in Train-3 LV Generator 2 2 440 kw 15/09/2017( Delay ) 30/10/2017( Delay )


NEW
LV MCC Switchgear 1 1 0,4 kv
Not yet Install

NO PROGRESS

8 ORF Satelit Office LV Generator 2 2 5 kw 01/09/2017( Delay ) 30/09/2017( Delay )

Not yet Install

NO PROGRESS NO PROGRESS NO PROGRESS NO PROGRESS

9 Jetty Satelit Office LV Generator 2 2 8,4 kw 15/08/2017( Delay ) 15/09/2017( Delay )

Not yet Install

NO PROGRESS NO PROGRESS NO PROGRESS NO PROGRESS

TOTAL : LV GENERATOR 36 30

ADDITIONAL / NEW GENERATOR


1 Company & Contractor Office LV Generator 1 560 kw 04/07/2018 04/08/2018 ADD ADD

2 PIONER CAMP. LV Generator 2 440 kw 14/04/2018 14/04/2018

3 ZONE-A STEENKOL LV Generator 2 440 kw 03/03/2018 03/03/2018

Send to BP NEW ADD


ADD
4 ZONE-B STEENKOL LV Generator 1 440 kw 06/04/2018 06/04/2018

N E W

ADD

ADD

5 ZONE-C MATOA LV Generator 1 440 kw 03/05/2018 03/05/2018


ADD
NEW ADD

6 RO EXISTING COMBO DOCK LV Generator 2 440 kw 11/08/2018 11/08/2018


LV MCC Switchgear 1 0,4 kv

7 FUEL STATION LV Generator 2 125 KVA 11/10/2018 11/10/2018


NEW

8 NEW INCINERATOR LV Generator 2 125 KVA 11/10/2018 11/10/2018


NEW

9 SUBCONT-2 ( KITCHEN / DINNING ) LV Generator 2 800 KVA 22/11/2018 22/11/2018 NEW


LV MCC Switchgear 1 0,4 kv
NEW

10 SUBCONT-1 ( KITCHEN / DINNING ) LV Generator 2 800 KVA


LV MCC Switchgear 1 0,4 kv ADD GENSET
NEW

TOTAL : LV GENERATOR 17 UNIT


LV MCC Switchgear 3 UNIT