Vous êtes sur la page 1sur 42

Project Management by Arul 16:59

Sivagananathan (PIM)

MBA 515 Introduction to


Project Management
Introduction to Project Management

Arul Sivagananathan

The Course
Key Elements:
Introduction to Project Management
Project planning and resourcing
Project financing & costing
Project contracts, Risk, Quality, monitoring & controls
Project (classroom team assignment – Compulsory
attendance)

1
Project Management by Arul 16:59
Sivagananathan (PIM)

Evaluation 

Scheme of Evaluation:

• Classroom project programme ( all groups)

Must have passed all sections to pass final PM course

Reading…. 
Recommended Reading:
• **Project Management by Harvey Maylor – published by Pearson Education

• *Jack R. Meredith and Samuel Mantel JR, Project Management – John Wiley & Sons
• *PMBOK, A Guide to the Project Management Body of Knowledge.4th Edition, The
Project Management Institute, USA.
• Kohil, U. and Chitkara, Project Management Handbook, Tata McGraw – Hill Publishing
Company Ltd
• Gunasekera, P. Mervyn, Managing Projects – Professional Management Handbook
Series, Academy of Management Science, Sri Lanka
• Berkley, T. Bruce, Project Risk Management – Tata McGraw – Hill Publishing Company
Ltd
• Hutching, F. Jonathan, Project Scheduling Handbook – Marcel Dekker Inc

2
Project Management by Arul 16:59
Sivagananathan (PIM)

What is a project

A project is a team of people working together to complete a particular task:

• By a specific TIME

• Within a specific BUDGET

• To a specific STANDARD

Definition of Project

“a management environment that is created for the purpose


of delivering one or more business products according to a
specific business case or requirement”

“a temporary organization that is needed to produce a


unique and pre-defined outcome or result at a
pre-specified time using pre-determined resource”

3
Project Management by Arul 16:59
Sivagananathan (PIM)

Project terms
• Short term – Launch of a products – (< 1year)

• Medium term – Project ICC world cup / Olympics / FIFA Game ( every 3-4 years)

• Long term – Project ‘Star Wars’ (50 years)

Evolution of projects:

Non-Numeric
• The Sacred Cow
• The Operating Necessity
• The Competitive Necessity
• Benefit / Priority Model

Numeric
• Breakeven
• Payback
• RoR (Rate of Return)
• NPV/Discounted Cash flow

4
Project Management by Arul 16:59
Sivagananathan (PIM)

What is project management

Project management is a discipline & a skill and not a profession

Defined as :

“the planning, monitoring, reporting and controlling all aspects of a

project and the motivation of all those involved in it to achieve the

project objectives on time and to the specified cost, quality and

performance”

Who is a project manager

Defined as :
“The person given the authority and responsibility to manage the project
and deliver the end objective”

Characteristics of a Project Manager








5
Project Management by Arul 16:59
Sivagananathan (PIM)

Defining the Scope / Project


S
M
A
R
T
E
R

Defining the Scope / Project


How?
5W&1H -How will it be used
-How long is it required to What?
last -What is the problem
When? -What would be the
-When will it be used impact if not done
-What is the end result
Defining
-What was done before
Who? Project
-Who will use it Scope
-Who will manage it (Charter)
-Who will fund it Why?
-Who will support it -Why is the result required
Where? -Why doesn’t it exist already
-Where will it up used
-Where is it in our list of
priorities

6
Project Management by Arul 16:59
Sivagananathan (PIM)

The measure
Economical

Cost

Scope

Time Quality

Reasonable Acceptable Project Fit for Purpose

Basic Project Planning

Act PLAN

Check
DO

7
Project Management by Arul 16:59
Sivagananathan (PIM)

6 phases of a Project
Identify the problem to be solved or
Initiation
opportunity to be exploited

Specify the scope with an objective, by


Definition
when and with what resource

Detail forecast with specific timelines,


Planning resource, responsibility & communications

Build the tasks, monitor, report &


Control
adjust plans accordingly

Passing what has been created to


Implement the user and helping them to
ation
adjust to any changes
Assess the outcome &
Review look back and learn for
future

Types of Projects

Runners •Regular updates

Repeaters •Regular review

Strangers •Unique / one off

8
Project Management by Arul 16:59
Sivagananathan (PIM)

Functional structure – Adhoc


Functional Projects

CEO

CEO

Dept A Dept B Dept C Dept A Dept B Dept C Project Manager

A B C
A B C
Shared
Resource

Matrix structure

9
Project Management by Arul 16:59
Sivagananathan (PIM)

Project Team

PM

No of
Volume vs Complexity
Projects

Routine
Runners
Functional

Matrix Repeaters
Special

Project Strangers

Complexity

10
Project Management by Arul 16:59
Sivagananathan (PIM)

Choice of Structure
Will depend on:
• Commercial importance
• Amount of involvement required from each team member
• Resource and skill availability
• Project length
• Project type - % of Runner, Repeater or Stranger
• Other parallel projects running
• Cost
• Organization style & culture

Project stakeholders

Stakeholders of a
project

11
Project Management by Arul 16:59
Sivagananathan (PIM)

Stakeholder Analysis
Fully Generally Neutral Generally Totally
Committed Positive Opposed Against
Significant influencer to CEO
project but cannot be
influenced by the PM
Marginal influence but SME
cannot be influenced by
PM
Influence and equal to PM HR
Marginal influence but can Sponsor
be influenced by PM
Significant influence and Public
can be influenced by PM

Project life cycle


No of people,
Cost,
Level of effort

Time

Conceptualization Kick off Implementation Evaluation and Closure

12
Project Management by Arul 16:59
Sivagananathan (PIM)

Multiple Projects
- People
- Cost,
- Effort

Time

Aspects to consider in project


management
Consider the 10-S’s:

1. S
2. S
3. S
4. S
5. S
6. S
7. S
8. S
9. S
10. S

13
Project Management by Arul 16:59
Sivagananathan (PIM)

Key Success factors of a project









MBA 515 Introduction to


Project Management
Session 2 – Project Planning and
Resourcing

14
Project Management by Arul 16:59
Sivagananathan (PIM)

6 phases of Project
Identify the problem to be solved or
Initiation
opportunity to be exploited

Specify the scope with an objective, by


Definition
when and with what resource

Detail forecast with specific timelines,


Planning resource, responsibility & communications

Build the tasks, monitor, report &


Control
adjust plans accordingly

Passing what has been created to


Implement the user and helping them to
ation
adjust to any changes
Assess the outcome &
I.D. Please, Review look back and learn for
Checking In Road future

Activities
Project initiation, team / structure
Initiation
formation, Select PM

Sign off objective, agree resourcing, sign off business


Definition
case, consensus from stakeholders, budget sign off

Project plan, resource plan, quality plan, budget


Planning plan, risk log, project documentation, progress
report, meetings

Monitor & report progress, milestone review


Control
change to scope, budget review, quality review

Implement Testing (UAT), sign off, final review,


ation launch or go-live
Feedback, minor
Review modifications, Project
close & lessons learnt
and sign off

15
Project Management by Arul 16:59
Sivagananathan (PIM)

Project planning techniques


WBS, OBS, RBS, PERT, CPM & Gantt
• WBS – Work Breakdown Structure – Activity of each unit
• OBS – Organisational Breakdown Structure – Roles & Resp of units
• RBS – Risk Breakdown Structure / Resource Breakdown Structure

Launch a
Product

Marketing Production Design Purchasing Finance

Ad agency Market Survey Capacity Material price Delivery


planning Product & stocks schedule Budget
design(s)

Broken down in to Activities

Project planning tools


PERT, CPM (arrow/network diagram), Gantt
• PERT started by US Navy for missile project in 1958 where as CPM was produced by Du Pont
company for R&D
• PERT – Program / Project Evaluation Review Technique
• CPM – Critical Path Method
• Gantt Chart – Project plan with horizontal bars (also referred to as bar chart)
Transport Old
unit and debris
Remove old out
Cupboard & Fix New unit &
appliances appliances

Buy new Unit & Transport


Market New
Survey
appliances unit to Home
Finished
Start
(Kitchen
Refurbishment) Add 2nd coat
Paint the walls
Buy paint & tiles

Delivery
Electrical work Fix tiles
schedule Grout

16
Project Management by Arul 16:59
Sivagananathan (PIM)

Definition and Rules


Key Words
1) Activity – a specific task or sets of tasks required in a project which takes time and
resource to complete
2) Event – The result of completing one or more activities. Usually drawn as nodes at the
start and end of each arc)
3) Network – Combination of all activities (usually drawn as arc)
4) Path – The series of connected activities
5) Critical – Activity or event or path which if delayed will delay the project and cost
money.
6) Critical path – Sequence of critical activities from start to end of a project which is the
total time of the project
7) Non-Critical – Activities which are part of the project but non critical and some delay to
those will not delay the project due to slack time
8) Slack time – Extra time available within a non-critical activity
9) Dummy activity – related but not connected (Shown as dotted lines)

Some Rules:
1) Use straight lines and not curves
2) Lines cannot point backwards
3) All projects must have a start and end node
4) Avoid lines crossing each other.
5) Cannot have two activity lines between two nodes

Definition and Rules

Start End

Critical Path
Activity

Node

17
Project Management by Arul 16:59
Sivagananathan (PIM)

Project planning with cumulative


Timing
1 2 7 8 9 10 15 16 17 18 19
a b c d e f g h i j k

a. Open cupboard & Take Mug – 1 min


b. Fill kettle with water – 1 min
c. Plug & switch on & let it boil– 5 min
d. Once boiled pour in to mug – 1 min
e. Take tea bag & place in mug – 1 min
Total time
f. After 5 mins take tea bag away – 5 min 19 mins
g. Add 2 spoons of sugar & stir– 1 min
h. Add milk & stir – 1 min
i. Strain in to Cup – 1 min
j. Take a tray and place cup on tray – 1 min
k. Serve – 1 min

Project planning tools


Critical Vs Non-Critical
1 6 7 12 13 14 15 16

b c
a
e d f g
h i j k

a. Open cupboard & Take Mug – 1 min


b. Fill kettle with water – 1 min Critical Activity
c. Plug & switch on & let it boil– 5 min
d. Once boiled pour in to mug – 1 min (Cannot delay)
e. Take tea bag & place in mug – 1 min Slack Activity
f. After 5 mins take tea bag away – 5 min
g. Add 2 spoons of sugar & stir– 1 min
(can be delayed)
h. Add milk & stir – 1 min
i. Strain in to Cup – 1 min
j. Take a tray and place cup on tray – 1 min
k. Serve – 1 min

18
Project Management by Arul 16:59
Sivagananathan (PIM)

PERT/CPM/Network Diagram Calculation

2 2
A B
2 2

0 7 3 1
START C D E END
0 7 3 1

6
F
6 KEY
ES Dur EF
Act
LS Dur LF

Project planning tools


Gantt Chart / Bar Chart (all in one)

19
Project Management by Arul 16:59
Sivagananathan (PIM)

Resource Planning / Scheduling


A= 2 weeks, 2 FTE 2

1 C= 5 weeks, 4 FTE 4

B= 3 weeks, 2 FTE
3
FTE
8 Max 8
a
6 6 Optimum
a b
4 c c Min 4

2 c 2 c
b b
1 2 3 4 5 Weeks 1 2 3 4 5 Weeks

Must DO for a successful project delivery


• Project Delivery plan – Business case, Goal, end objective
• Communication plan, key to success to have good comms across all SH
• Risk Plan, balance risk Vs reward. As a PM will have to take some risk
• Resource plan, optimization
• Budget plan, regular reviews and scenario based
• Purchasing plan, eg where possible JIT or outsource to cut time/money
• Delivery plan eg shipment delays, port clearance
• Stakeholder Management, use stakeholder analysis
• MI
• Project update
• Project documentation
• Issue log, maintain up to date logs
• Meeting agenda and Minutes
• Stakeholder updates, proactive updates
• Lessons learnt from previous projects
• Project audit
• Project closure

20
Project Management by Arul 16:59
Sivagananathan (PIM)

Green Projects (balancing the


environmental impacts)
As a modern Project Manager it is important to consider the environmental
and social impact. There are many sustainable green projects and CSR projects which
are all part of the ‘balancing’ process
• Use PESTEL (Political, Economic, Social, Technological, Environmental, Legal)
analysis before embarking on a project
• Most of the projects will have an environmental impact (Example from
construction of a building to manufacturing new products which will carry some
waste back in to earth or atmosphere
• As a project manager find ways to mitigate such action and if unavoidable then
invest in sustainable projects / carbon neutral projects to counter such action
• Cost will be slightly higher than completing a projects without such initiatives
but on the long run it is important that we leave the earth resources for our
children to enjoy as well.

1. Lisa has been engaged at $100 per week as a Project Manager to organize a workshop for
Senior Leadership Team (SLT) of company X. She has listed below the list of activities
she will need to carryout and the time it will take. She has also estimated the cost of each
activity.

No Activity Time Dependency Total


(weeks) Cost ($)
A Design the Workshop & Theme 2 - 800
B Send email to check availability of 4 A 0
all SLT
C Prepare agenda for the workshop 3 A 300
D Search for Venue 2 A 300
E Start the reservation process 2 B 0
F Develop and print workshop 6 C 1100
material
G Book the venue & pay the 50% 1 D 5000
advance
H Send email confirming the date to 2 E,F,G 0
SLT
I Inform CEO the final agenda, cost 1 H 0
& number of SLT attending

a. Lisa has turned to you for help to construct a CPM (network) diagram to work out the
critical path and also to estimate the total cost of the project? Do a forward pass and
backward pass to calculate time of each activity and the total time of the project? (10
marks)

b. Explain what is critical path in a project? Show the critical path of this project and
how Lisa can shorten the time taken in this project if required? (5 marks)

c. Explain the slack time in the activities of this project and how she can reorganize her
schedule without affecting the total time taken? (5 marks)

d. Explain five possible risks associated with this project and how Lisa can mitigate
those risks? (5 marks)

21
Project Management by Arul 16:59
Sivagananathan (PIM)

CPM –Optimistic, Most likely, Pessimistic; Expected

To calculate Expected time (Ex):


Ex = (Op + 4xML + Pe)/6

CPM –Optimistic, Most likely, Pessimistic; Expected


Critical Path

Op ML Ex Pe
Probability

Eg Activity B

0 1 2 3 4 5 6 7 8 9 10 time

22
Project Management by Arul 16:59
Sivagananathan (PIM)

Key Challenges faced by PM











MBA 515 Introduction to


Project Management
Session 3 – Project Finance & costing

23
Project Management by Arul 16:59
Sivagananathan (PIM)

Project Financing
There is no single technique to finance a project. Each project is unique and
financing of each project can be unique as well. Here are few types of
funding (or combination):
• Equity financing – Parent company taking stake in the project, or issue of
new shares
• Loan / lease financing – Banks and lending agents
• Subsidised financing – Government funds
• PPP – Public Private Partnership – toll roads
• Donor funded – NGOs, WB, IMF
• Friendship – BMICH
• Profits, excess cash funded – building a house
• Budget funded – R&D

Project Costing techniques:


There are several techniques used in estimating project costs. Again there is
no single technique in costing a particular type of project. However here are
some tried and tested methods
• Activity based costing - WBS
• Analogous estimation – Using the actual cost of a previous project to estimate the
current cost with inflation added
• Cost plus – All costs as incurred plus an agreed margin (%)
• Zero based budgeting or bottom-up estimate
• Determine resource costing – where factors are constant (per hours rate)
• Parametric estimation – using average rate known – eg construction of a house
• Vendor bid estimate
• Scenario based costing
• YoY budget based – long term projects

24
Project Management by Arul 16:59
Sivagananathan (PIM)

Factors to be considered when costing a project


Key factors
1)
2)
3)
4)
5)
6)
7)
8)
9)
10)

Business case
Considering the key factors, building a business case to get approval for a
project will always be a challenge. Simply because each factor will be
sensitive and a change in the basis point will impact the business case:
To launch a new product (100 units):
- Sales / Marketing cost = $10,000
- Manufacturing / plant cost = $10,000
- Raw material / sourcing cost = $10,000
- Personnel cost = $10,000
Total cost = $40,000
Unit Cost = $40,000/100 unit = $400
Margin = 10%; Selling price of $440; Profits $4,000

25
Project Management by Arul 16:59
Sivagananathan (PIM)

Cash Flow
Value Management
Reserve
Funding required

Cost Estimate

Expected Cash flow

Time

Earned Value (EV)


Current performance is the best indicator of future performance, and
therefore using trend data, it is possible to forecast cost or schedule
overruns at an early stage in a project. The most comprehensive trend
analysis technique is the Earned Value method.

Earned Value is an approach where you monitor the project plan, actual
work, and work-completed value to see if a project is on track. Earned Value
shows how much of the budget and time should have been spent, with
regard to the amount of work done so far.
Planned Value is Budgeted Hours x Budgeted Rate:
PV = BH X BR

Actual Cost is Actual Hours x Actual Rate:


AC = AH X AR

Earned Value is Actual Hours x Budgeted Rate:


EV = AH X BR

To determine scheduled variance and cost variances:


SV = EV - PV
CV = EV - AC

26
Project Management by Arul 16:59
Sivagananathan (PIM)

Performance valuation for Payment


Value Estimated Total
Actual Cost
budget at
(AC)
completion

Funding requirement

Planned Value Now imagine multiple ‘S’ curves


(PV) Example 10 units, 10 weeks @ 100

Earned Value
(EV)

at a given time Date

Types of Analysis
• Payback Analysis – Only considers the cash inflow and outflow
• Eg initial investment is Rs 10M and return is 4M a year then payback period is 2.5 yrs

• IRR (Internal Rate of Return) – Set basic return criteria on time value of money
• (ie the discounted rate for which the NPV=0)

NPV $+
IRR

Discounted rate

NPV $-

• Discounted Cash Flow – Considers the time value of Money


• This is an accurate estimate of a project costs and return on investments.
• Must for a long term project.

27
Project Management by Arul 16:59
Sivagananathan (PIM)

NPV
Net present value (NPV) or net present worth (NPW) is time series of cash
flow, both incoming and outgoing, is defined as the sum of the present
values (PVs) of the individual cash flows.
NPV is simply the PV of future cash flows minus the purchase price.
NPV is a central tool in discounting cash flow (DCF) and is a standard
method using time value of money to appraise long-term projects.

Discount rate is the rate used to discount future cash flows to the present value. It
is the rate of return that could be earned on an investment in the financial markets
with similar risk. It is a key variable in the process (see table).

If NPV is +ve then the project is good to invest in.


If NPV is –ve then the project is not worth investing in.

Fixed cost and sunk costs are not considered in a NPV calculation.

NPV = C n / (1 + i)n
C n is the future value of the investment n years, n = years, i is the discounted rate of return

NPV example
As a PM you have been asked to recommend whether an investment of $6,000 will
provide a payback within 3 years. Assuming running cost of $3,000 in year 1 and
$4,500 from year 2 onwards. Revenue estimated to be $4,000 in year 1 and
thereafter increase by $1000 each year. It is proposed that the company sells the
investment for $5,000 after 3 years. The rate of return is 12%.

Year Outflow Inflow

28
Project Management by Arul 16:59
Sivagananathan (PIM)

Discount Table

Year 3% 4% 5% 6% 7% 8% 9% 10% 11% 12%


0 1 1 1 1 1 1 1 1 1 1
1 0.9709 0.9615 0.9524 0.9434 0.9346 0.9259 0.9174 0.9091 0.9009 0.8929
2 0.9426 0.9246 0.907 0.89 0.8734 0.8573 0.8417 0.8264 0.8116 0.7972
3 0.9151 0.889 0.8638 0.8396 0.8163 0.7938 0.7722 0.7513 0.7312 0.7118
4 0.8885 0.8548 0.8227 0.7921 0.7629 0.735 0.7084 0.683 0.6587 0.6355
5 0.8626 0.8219 0.7835 0.7473 0.713 0.6806 0.6499 0.6209 0.5935 0.5674
6 0.8375 0.7903 0.7462 0.705 0.6663 0.6302 0.5963 0.5645 0.5346 0.5066
7 0.8131 0.7599 0.7107 0.6651 0.6227 0.5835 0.547 0.5132 0.4817 0.4523
8 0.7894 0.7307 0.6768 0.6274 0.582 0.5403 0.5019 0.4665 0.4339 0.4039
9 0.7664 0.7026 0.6446 0.5919 0.5439 0.5002 0.4604 0.4241 0.3909 0.3606
10 0.7441 0.6756 0.6139 0.5584 0.5083 0.4632 0.4224 0.3855 0.3522 0.322
11 0.7224 0.6496 0.5847 0.5268 0.4751 0.4289 0.3875 0.3505 0.3173 0.2875
12 0.7014 0.6246 0.5568 0.497 0.444 0.3971 0.3555 0.3186 0.2858 0.2567
13 0.681 0.6006 0.5303 0.4688 0.415 0.3677 0.3262 0.2897 0.2575 0.2292
14 0.6611 0.5775 0.5051 0.4423 0.3878 0.3405 0.2992 0.2633 0.232 0.2046
15 0.6419 0.5553 0.481 0.4173 0.3624 0.3152 0.2745 0.2394 0.209 0.1827

NPV example
As a PM you have been asked to recommend whether an investment of $6,000 will
provide a payback within 3 years. Assuming running cost of $3,000 in year 1 and
$4,500 from year 2 onwards. Revenue estimated to be $4,000 in year 1 and
thereafter increase by $1000 each year. It is proposed that the company sells the
investment for $5,000 after 3 years. The rate of return is 12%.

Method 2: Discount Table based

Year Outflow Inflow Total 12% PV

29
Project Management by Arul 16:59
Sivagananathan (PIM)

NPV - Example
Co X must decide whether to introduce a new product. The new product will have
startup costs, operational costs, and incoming cash flows over six years. This project
will have an immediate (t=0) cash outflow of $100,000 (which includes machinery,
and employee training costs). Other cash outflows for years 1–6 are expected to be
$5,000 per year. Cash inflows are expected to be $30,000 each for years 1–6. All cash
flows are after-tax, and there are no cash flows expected after year 6. The required
rate of return is 10%. Calculate the present value (PV) for each year and NPV.
Should Co-X invest in the new product?

Years Outflow Inflow Net (I-O) DF 10% PV

Discounted Cash Flow

Net $25,000 YoY

Time value of money

30
Project Management by Arul 16:59
Sivagananathan (PIM)

Cumulative Discounted Cash Flow

Misjudgment

NPV - Calculation
You are the fund manager for company Aquila. The CFO of the company wants you to
evaluate the possibility to buy a business which generates annually (Y1-10) Rs 50,000. The
initial purchase price of the company is Rs 300,000. It also required annual running cost of
Rs 25,000 each year (this incl staff & operating cost). All cash flows are after-tax, and
there are no cash flows expected after year 10 and hence the CFO wants to sell the
business on the 10th year. It is estimated the sale price at that time to be Rs 200,000. The
required rate of return is 10%. Calculate the present value (PV) for each year and NPV.
Advise the CFO?
Years Outflow Inflow Net DF 10% PV

31
Project Management by Arul 16:59
Sivagananathan (PIM)

MBA 515 Introduction to


Project Management
Session 4 - Contract, Controls and
Monitoring

Contract
What is a contract and contract law?

Contract is about 3 ‘R’


• Rules
• Risks
• Relationships

Contract is Bargain
Contract is Risk
Contract is Money

Requirements in a contract Law:


1. Capacity – Of the parties involved
2. Legality – The purpose
3. Certainty – Of the terms of the deal
4. Consideration – The bargain for the risk
5. Offer & acceptance – Proof that the parties agreed the terms and they made the contract

32
Project Management by Arul 16:59
Sivagananathan (PIM)

Project Contracting
In any commercial projects, where there is finance, time and quality
involved, usually a contract is executed.

General Contract
• Offer & Acceptance
• Intension to create legal relationship
• Lawful consideration
• Capacity of parties of competencies
• Free and genuine consent
• Lawful object
• Agreement not declared void
• Certainty and possibility of performance
• Legal formalities

Business Contract
Agreement between 2 or 3 parties in writing , to do, or not to do certain
things. Business contracts are enforceable at law. This will usually involve
monitory transaction. Else it is not a business contract.

• Issue of tender notice in papers or NIT (Notice Inviting Tender)


Enquiry

• Submission of tender document by the bidder


Offer

• Evaluate & Communication in writing by the party accepting the bid


Acceptan and acceptance of the same by the bidder.
ce

• Offer and consideration as acceptance given a legal form and content


Agreeme duly signed by authorized individuals of both authorities
nt

• Contract consists of an agreement on a stamped paper with agreed


Contract variation and the original tender document. This is now a legal form

33
Project Management by Arul 16:59
Sivagananathan (PIM)

Contract Types:
Each project is unique and so is each contract. There are several variations
to the execution of the contract as required by the project:
• BOT
• BTO
• BRT
• BOOT
• BOO
• BOD
• BOL

• You can have several combinations to this by adding other factors:


• FBOT
• DBOT
• Etc etc

Other types of project contracts

1) Turn-key
2) Lump sum
3) Cost+
4) Profit sharing
5) Purchase order
6) Deed
7) Lease
8) HP
9) Insurance\Guarantee
10) LOI – Letter of Intent – Quasi Contract
etc

34
Project Management by Arul 16:59
Sivagananathan (PIM)

Discharge/End of Contract
• Performance
• Breach
• Frustration
• Mutual
• Discharge

Dispute Resolution
Usually arises due to time, cost, quality or resource

• Litigation
• Arbitration
• ADR – Alternative dispute resolution
• Expert resolution
• Negotiation

35
Project Management by Arul 16:59
Sivagananathan (PIM)

Delivery Contracts
Apart from Contract law, there are other factors that needs to be considered
when doing international trade

• Ex-Work
• FAS
• FOB
• C&F
• CIF

Project Monitoring & Control system


Project stages

Monitor & Implement Closure /


Initiate Define Plan
Control / Go-Live Review

Why?
• To track progress against time
• To make payments for work completed
• To check quality
• To update stakeholders on progress’
• Understand issues & risks
• Change requests / changes
• Budget assessment
• Legal requirements
• Environmental impact analysis
• Contract obligations

36
Project Management by Arul 16:59
Sivagananathan (PIM)

Project Monitoring & Control system


Monitor & Implement Closure /
Initiate Define Plan
Control / Go-Live Review

Scope Procurement
Time (Schedule
(definition and (Purchase
control)
progress) control)

Communication Cost Integration Implemen


Planning &
Execution
(Performance (Budget (Integrated tation /
reporting) control) change control) Go-live

Resource Contract
Quality
(Resource (Risk & contract
(Quality Control)
Control) control)

Monitoring & Controls


Monitoring and controlling consists of those processes performed to observe project execution so that
potential problems can be identified in a timely manner and corrective action can be taken, when
necessary, to control the execution of the project. The key benefit is that project performance is
observed and measured regularly to identify variances from the project management plan.

Monitoring and Controlling includes:


• Measuring the ongoing project activities ('where we are');
• Monitoring the project variables (cost, effort, scope, etc.) against the project management plan and
the project performance baseline (where we should be);
• Identify corrective actions to address issues and risks properly (How can we get on track again);
• Influencing the factors that could circumvent integrated change control so only approved changes are
implemented

In multi-phase projects, the monitoring and control process also provides feedback between project
phases, in order to implement corrective or preventive actions to bring the project into compliance with
the project management plan.

Project Maintenance is an ongoing process, and it includes:


• Continuing support post go-live or completion
• Correction of errors and quality compliance
• Update or maintain as per agreed contract over time

When changes are introduced to the project, the viability of the project has to be re-assessed. It is
important not to lose sight of the initial goals and targets of the projects. When the changes accumulate,
the forecasted result incl cost may not justify the original proposed investment in the project.

37
Project Management by Arul 16:59
Sivagananathan (PIM)

Project Risk Assessment Matrix

Activity Relevance Progress Remarks


Low (4-5)

1 1 Activity 1 XX YY

5 3 2 Activity 2 XX YY

3 Activity 3 XX YY
High (1-2) Medium (3-4)

4 Activity 4 XX YY
2
RISK

4 5 Activity 5 XX YY

6 Activity 6 XX YY

6
Key Risks & mitigation:
• Activity 4
• Activity 6
High (4-5) Medium (3-4) Low (1-2) • Activity xx
Critical Path / Progress

Project Risk Log

Type Details Likeli Impact Mitigation Status Owner Alternate


hood (L/M/H) Strategy Plan
(L/M/
H)

38
Project Management by Arul 16:59
Sivagananathan (PIM)

MBA 515 Introduction to


Project Management
Project Quality Management

Quality aspects in Projects


• In Project Management quality control requires the project manager and
the project team to inspect the accomplished work to ensure it's
alignment with the project scope. Fit For Purpose.

• Quality Management - all the activities that are intended to bring about the
desired level of quality (output). – ensure Fit for purpose

• Quality Assurance – Constant review to ensure right end result is delivered

• Quality Audit - the procedural controls that ensure participants are adequately
following the required procedures.

39
Project Management by Arul 16:59
Sivagananathan (PIM)

Quality stages
Define
Monitor & Review &
Quality Implement
Control Audit
scope / Plan

Agree the Implement Monitor Review the


project quality measure and progress and quality and
scope and agree report quality audit output.
define reporting output. Apply Variance to be
measure (CTQ) methods and corrective corrected or
and tolerance measure action where discounted
levels techniques required

Quality Planning
It is good project management practice, as well as a Quality Management process, to identify
in advance all the anticipated deliverables.

For each project, you should identify:

• Nature, description and purpose of the deliverable (ie scope),


• Quality standard (eg discussion draft, final quality, reviewed or tested, measures and
tolerance)
• Dependencies (what must be completed prior and what further deliverables depend upon
this project)
• Date, time, standard required,
• Agree Author/creator/responsibility,
• People who have to review it,
• People who have to approve it,
• People who should receive it for information or use (but who do not get the opportunity
to review or approve)
• Other distribution (eg third parties, auditors, publishing, filing)
• Security/secrecy requirements - ie who can not see or use it
• Audit and sign off documentation

40
Project Management by Arul 16:59
Sivagananathan (PIM)

Quality Planning
Type of content Description Examples
Objectives What are the objectives of Quality •Acceptable levels of functionality
Management? To what extent is quality to achieve
a requirement in preference to •Acceptable levels of security and
timescales, costs, functionality etc? tolerance levels
•Investment in testing & review
Requirements What specific requirements are to be •Review and sign-off of specific
addressed deliverables or work by specified
people
•Types and depth of review
required
•Availability of specified functions
Quality Methods What approaches and methods •Iterative development in
specified stages
•Methodology to be followed
•Peer review of all deliverables
Standards What format and detail should •Output standards
deliverables be in •measure standards
•documentation standards
Procedures Specified procedures for project tasks •documentation control procedure
•issues management procedure
•Closure prcedure

Quality Techniques
• TQM – The Toyota way
• Six Sigma - 3.4 defects per million opportunities
• 5 ‘S’ (More for an office environment)
• SEIRI means Organisation or sorting
• SEITON means straighten or prepare correctly or Straightening
• SEISO means Cleanup or Cleanliness
• SEIKETSU means Standardisation
• SHITSUKE means Discipline or Sustain
• ISO – International Organisation for Standadization
• FMEA – Used is projects where there are processes
• Continuous Improvement
• Fish Bone analysis - used more in projects

41
Project Management by Arul 16:59
Sivagananathan (PIM)

Fish bone analysis for projects


Fish bone analysis will enable you to do an analysis of your current state, your ultimate
goal and therefore all the steps in between. The tool will help you analyse any external
events that may occur between present day and successful goal completion and will
enable project managers to take action to ensure success. Example below;
Man Machine Material
(Management/Pe (Equipment /
ople / Resource) systems/ tools)

Effect /
Issue /
Defect
Reason
(price hike, shipment)

Cause
(delay in delivery)

Money Minute
(cost / funding) (Time)

42

Vous aimerez peut-être aussi