ANALISA BIAYA PENGIRIMAN MCB BETON

JAPEK - BALARAJA

Data:

- Volume beton bertulang MCB = 0.2 m3


- Berat MCB = 0.2 m3 x 2400 kg/m3
= 480 kg
- Isi 1 Truck Hiab 3 ton per rit = 24 pcs MCB
- Jarak Japek - Balaraja = 93 km
- Kecepatan rata-rata hiab = 20 km/jam
- 1 Litter Bio Solar = Rp. 9.800,-
- Volume bekisting 1 unit MCB = 2.7 m2

Data Produktivitas Hiab*


Aktivitas Jalan dan Jacking Crane

Data Hari
80-100 km 1 hari
160-180 litter 3 hari
*Data Project Japek

Analisa:

1. Volume
- Jumlah unit angkut MCB 1 rit perjalanan = 24 pcs
- Volume bekisting per unit MCB = 2.7 m2
= 2.7 m2 x 24 pcs
= 64.8 m2
2. Jarak
- 1 rit perjalanan japek – Balaraja = 2 x jarak tempuh
= 2 x 93 km
= 186 km

3. Waktu per rit


- Angkut = 0.5 jam
- 1 Rit perjalanan Japek – Balaraja = Kecepatan hiab x jarak
= 20 km/jam : 186 km
= 9.3 jam
- Turun dan perapihan on site = 0.5 jam
= 10.3 jam

4. Biaya
- Solar
Asumsi ambil data jarak terkecil dan litter solar terbanyak
o Jarak = 80 km per hari
o Vol Solar = 180 litter/3 hari
= 60 litter/hari
o Harga = 60 litter x Rp. 9.800,-
= Rp. 588.000,- per hari
- Etol (PP) – Golongan IV = Rp. 250.000,-
- Uang Jalan dan Parkir = RP. 50.000,-
= Rp. 888.000,-

Kesimpulan:

a. Volume angkut 1 Rit perjalanan Hiab Crane Japek – Balaraja = 64.8 m2


b. Jarak tempuh 1 rit Japek- Balaraja = 186 km
c. Waktu tempuh 1 rit perjalanan Japek- Balaraja= 10.3 jam
d. Biaya tansport perjalanan 1 rit perjalanan Japek-Balaraja = Rp. 888.000,-
e. Total biaya 1 rit perjalanan Japek- Balaraja per m2 = Biaya perjalanan : volume angkut
= Rp. 888.000,- : 64,8 m2
= Rp. 9.074,- per m2