Name of Project: PRC Warehouse


Location: San Carlos Seminary, Guadalupe, Makati City

ITEM
NO. DESCRIPTION OF WORK QUANTITY UNIT UNIT COST LABOR COST TOTAL AMOUNT

1.0 General Requirements


1.05 Mobilization/Demobilization 1 lot 5,000.00 5,000.00
Sub-total 5,000.00
2.0 Siteworks
2.01 Site Preparation/Clearing/Demolition & Disposal 1 lot 10,000.00 10,000.00
2.04 Excavation 1 lot 5,000.00 5,000.00
Sub-total 15,000.00
3.0 Concrete Footing and Pedestal
Cement 20 bags 240.00 72.00 6,240.00
Crushed Sand 1 load 1,800.00 540.00 2,340.00
Gravel 2 load 3,400.00 1,020.00 8,840.00
10mm dia. Rebar 52 pcs 144.00 43.20 9,734.40
#16 Tie Wire 3 kgs 80.00 24.00 312.00
Sub-total 27,466.40
4.0 CHB Laying and Gravel Bedding
6" CHB 180 pcs 18.00 5.40 4,212.00
Cement 17 bags 240.00 72.00 5,304.00
Crushed Sand 1 load 1,800.00 540.00 2,340.00
10mm dia. Rebar 14 pcs 144.00 43.20 2,620.80
#16 Tie Wire 2 kgs 80.00 24.00 208.00
Gravel 2 load 3,400.00 1,020.00 8,840.00
Sub-total 23,524.80
5.0 Main Structure
2" Dia.GI PIPE (Columns) 9 pcs 2,140.00 642.00 25,038.00
3/4" Dia. Round Bars (Cross Bracing) 14 pcs 673.00 201.90 12,248.60
Roof Sheets 2.4x.7x.6mm Corrugate Roofing (Walls) 50 pcs 550.00 165.00 35,750.00
2"x2" Wire Mesh 8 pcs 500.00 150.00 5,200.00
2" Dia.GI PIPE (Horizontal Support) 25 pcs 2,140.00 642.00 69,550.00
Welding Rod Special 10 kgs 180.00 54.00 2,340.00
200mmx200mmx 6mm Base Plate 14 pcs 350.00 105.00 6,370.00
3"x1/2" dia. Threaded Bolt with nut and washer (G HCS) 56 pcs 48.00 14.40 3,494.40
12x130
10mm dia. Round bars 6 pcs 144.00 43.20 1,123.20
1/2" Thk base plate 14 pcs 280.00 84.00 5,096.00
1/4" Thk base plate 36 pcs 150.00 45.00 7,020.00
Turnbuckle Hook & Hook 56 pcs 240.00 72.00 17,472.00
Industrial Primer (Epoxy) 2 Gals 900.00 270.00 2,340.00
Boysen Enamel Paint 2 Gals 620.00 186.00 1,612.00
Paint Brush 2" 4 pcs 50.00 15.00 260.00
5.01 Cinepa
2"x4" C Purlins x 6m 6 pcs 1,200.00 360.00 9,360.00
2"x3" C Purlins x 6m 13 pcs 950.00 285.00 16,055.00
2" Black Screw 150 pcs 2.00 0.60 390.00
1/2" Hardiflex 5 pcs 1,850.00 555.00 12,025.00
5.02 Roofing
2"x3" C Purlins x 6m 26 pcs 950.00 285.00 32,110.00
Roof Sheets 2.4x.7x.6mm Corrugate Roofing (Roofing) 56 sheets 550.00 165.00 40,040.00
Tek Screw 12mmx65mm w/ washer 1 box 2,000.00 600.00 2,600.00
Sub-total 307,494.20
6.0 Miscellaneous
Contingency 30,000.00 30,000.00
Sub-total 30,000.00
- GRAND TOTAL COST 408,485.40

Notes:
Items in red highlight are items which are of lesser amount from SOLER, while item in black
print are costings from Goldsun

Prepared by: Noted by:

Engr. Jujemar N. Gujelde Engr. Bernard Lasala


Project Engineer EGSD Manager