Vous êtes sur la page 1sur 7

Pir;l.

r: nloor'ur€

,un;,
stainlesssteelventilation stack:\MEp,sellafield
D. A. Bloomer, BEng, MSc, CEng, FIShuctE, MICE
Building & Civil Design Ofhce, British NuclearFuels plc

Synopsis up a shalt throughthree RC floors and a lightweight roof. It is a free_


The paper describes the construction of the ventilation stackfor
standingcantilever,51.7 m high with a 3.9 m diametermultiflue windshield
the Wastes Encapsulation plant at BNFL Seltaftetd, sening
ho*, fitted with helicel scrakesand containing two flues. The thickness of the
the reasons for selecting stainless steel instead'of ,itryooia windshield decreases from 16 mm at is baseto g mm at the top. The wind_
concrete- Detailed aspects of the design and analys;sby tne
shield and both flues irc manufacturcdfrom austenidc stainlesssteel. The
yiydshield andflues are give4 along-with flues arc supportedverticaily by the windshield, at the 17.5 m level, and
fabrication and installation issues. "ontrirnol,
restrainedhorizontallyby accessplatforms above this level. Overall details
In buiding a stack of this size, with the requirement
for a 50- arc shownin Fig l.
year.design life, the current uK standard.foi the desigi
of steet The stackis designedto satisfy r-in-10 00Gyear exrremeenvironmental
stacks (Le. BS a07.6: lgTs) gave insfficiint guidanci in regard performancerequircmenB,i.e. rcsistanceto wind, seismic and extreme
to tle use of stainlss sye! fatigue, hot
flue desiln, the need.fo"r and cold weather-
preloading of the base holding-down bolts, ind the.rrresr
In view of the stack size, and in order to maximise off-site fabricarion,
implications of vonex shedding and wind. ovalisation. an early decision was raken to design the suck such that it would
be
deliveredro site in threefuily prefabricatedtransportablelengthscomplere
rtroduction wiOrflues.
-newasresEncapsulation plant (wEp) projectis BririshNuclearFuels
plc's For constructionreasons,a sLackof theseproportionswould normally be
(BNFL) secondplant at sellafield for the encapsulationof intermediate
located away from its building. However, stack foundations *"uiy
level wastein sealedstainresssteeldrumsfilled with cemenritiousgrours. u
considerableareaon plan, and the amountof available land adjacentto u/Ep
An essentialfeature of the prant is the stainresssteer ventilation stack was extremely limited. The decision was thereforemade to locate the
requiied for the dischargeof the plant's ventilationextracL It is the design, stack
within rhe ServiceBuilding, even rhoughthis made the project much less
fabrication and consrnrctionof the wEp stackwhich forms the basisof this straighdorward.
PaPer.
The stack is located within the service Building of the wEp project, Factors influencing the choice of construction material
emanating from a concretepedestalat the ground-floor revel and p^riing The combined capital cost for the foundations and superstructurefor
a
slipformedreinforcedconcreteor stainlesssteelstack wasbroadty the same.
55.0m lvl. Too of f tues
The stainlesssreeloption was,however,chosenfor the following reasons:
(l) It providedprogrammeadvanragesto the wEp service Building project.
A concretesrackwourdhavehad to be completedbeforc the building'ssteel
Access plotforms frame erectioncould start, whercasthe steel stack altowed the unimpeoeo
constnrctionof the ServiceBuilding in parallel with offsite fabrication
of
the stack.The early presenceof a stackwoutd also have restrictedsteelwork
erection.
Helicol strqkes
(2) The steelsrack,being much righter in weight, could be founded
more
economicallyby using a common raft foundation with the building.
A
concrctestackwould have neededmassconcretedown to rockheadtevel _
35.6m lvl.
I
35.0m lvl. Sitc joint in stock hrst, to avoid any possible'differential settlement under operational
Ioads;secondly,to preventunacceptable levelsof soil-structurcinteraction
3.8m l/ dio-windshicld under seismic loading; and thirdly, to sustain the grcater seismic mass
Eost goblctomoin
h-rilding enlalopc
inertial forcesincurred.
l.5m dio.ftlc nol
(3) The surroundingsitecourd accommodateboth the onsite asembly
of the
0.5m dio. fluc no.l stack from largeprcfabricatedstack sectionsand the large crane neededto
ercct the stack-
\tleothcr hood 2 t . 8 mM . The choice of stainlesssteel rather than carbon steel is to minimise
corrosionand mainrenance(i.e. painting) during the 50-year design life.
16.5m lvl. F.EL :5 m lvt.Fkrc support
plottorm Grade3o4L is uscdinternally,while 3l6L stainlessstccl is providedat all
F-xtroct drrt external locationsto reduce pitting corrosion associatedwith airborne
ond be|lows 5m tvl. chlorides arising from the nearby coastal environment. Both grades of
Sitc roirn stainlesssteelarcreadilyweldablewith high strengrh,exceltentductility and
instocl
subzerotempenrurcproperties,coupledwith good fatigue resistance.

Wind-induced oscillatory phenomenon


Most unlinedlighrweightsteelstackshave a first-mo<Jenaturalfrequency
-O5m lvl.
lessthan l.2Hz(irrespectiveof theirheight),and,having minimal dampinj,
they arc highly susceptibleto osci[ation under wind ioading. As wcll
as
Cornpoctcd hordcorc
designingfor the normalcF[]' qur"i-static wind load, sr^irckiesigners are
T_ adviscd to investigarcthe stressimplications of wind-induced
oscill_
-O.7m lvl.
__^-_r^_1^jT:, r-

-0.9m lvl.
ations- i.e. oscillationsacring 'wirh wind' and perpendicularto the wind
dircction on plan, rhesebeingdue to wind buffeting and vortex shedding,
8cd rock rcspectively.
12.8m 15.5m The 'critical wind spced'is defined as the wincl spccd at which vortcx
sheddingoscillarion@curs and is a function of the srack diamercr
an<l
0m 5m lOm
natumlfrequency. Thisphenomenon @curswhenthc frerlrcncyof sherlding
l r t
*11 *",l"rural frequency. of rlrc.srack,giuiug rise ro
FiC I, North elcwtlion on WI,lP.Scrvire llttil,lino ,l' Venrilttrittn lt,rt ::.::::1-:"f":,.*r
is rninirrutl.
Stlcks ltrc llcttcrllly lrttcd with lrclicalstrakcsto Inrnrmisc hxrthlcvcls.rvlrcreasrbr trrc crnckcdsolutiontherc will lrc a signilicant
vortcx shctldingrcsponscby prornotingrandornratherthan regularpcricxl changein theprsirionof thc ncurralaxis.without prcload.a substantialpart
voricxshcddingbchaviour.Sltoulda stackhavea significantwind oscill- of the stackb:rsering is subjectto downwardtensionfrom thc anchorbolts
ationproblcrn,its life might bc govcrnedby tatigucconsidcrations. and, diametricatlyopposite,concentratedupward comprcssionfrom the
grout.Consequently,the stackbasering hasto carry significant additional
Wind and scismic dynamic analyses stressesto maintainequilibrium. (NB. This effect is morc significant in
Becauseof thepotentialfor aerodynamicosciltatoryproblemsthedesignof stacksbecauseof their light weight and high momentcomparedto stanchion
all nujor steelstacksshouldincludea vibrarionanalysis.Furthermore,the bases,which generallyhavesmallernet tensions.)
structurrlmodelsusedfor a stackvibrationanalysisdueto wind etTectsmay (3) Without prestrcss. a tensileseparationcanoccurat the stack/foundation
needto representthe stack foundations(or supportingstructurcs).This is interfacesuchthat, when the cycle rcverses,the grout would be subjected
beanuse wherefbundationsoffer relatively low rotationalsdftressto rhebase to an impactforceas the crackcloses.This cyclic impact processcanrover
of a stack,foundation'rocking' can occur, which would affect the stack's a period of time, give rise to 'grinding' of the grout lea<lingto the stack
frequencyand rcsponse,thus making a fixed-baseanalysis inappropriate. becomingunstable.
However,in rhecaseof wEp, becauseof is relatively massivefoundation, (4) The effect of preload on rhe bolts substantiallyreduces the range and
it waspossibleto adopta fixed-baseapproachwith considerablec.onfidence magnitudeof the tensile srrcsscyclesexperiencedby the bolts due to stack
for the wind dynamic analysis.This analysisalso assumeda relatively low oscillation and wind fluctuationvchangesin direction. This avoids the
valueof criticaldamping,i.e. 0.5 %. Taking a srrouhalnumbel of 0.2. with possibilityof long-termfatigueof the bola.
the resultingfirst modefrcquency(1.15 Hz), gavea critical wind speedof (5) Therc is the potenrial for the non-prestressedHD bolts progressively to
72m/s,whereasthesecondmode(6.19Hz) gavea criticatwind speedof I l g debonddown to anchor-platelevel and,asa result,inadvertentlyto strctch
m/s.Becausethe lanerwas more than50 % abovethe ESDU, l-in-5Gyear under load within the RC foundation.This would give rise to stack base
'rocking'effects,
meanhourly wind speedat 34 m/s, the secondand higher modeswere not making the dynamicbehaviourvery complex, thus intro-
considercdin rclarionto vortexshedding. ducing considerable uncerrainryconcerningthe validity of a simplified
The scismicperformanceof the wEp stackwas investigated.For this load analysis.
case,higher thannormal stresseswere allowed, which resultedin increased
energy absorption(this being a consequenceof the ductiliry and work- (o) Stroin protika

hardeningeffectsassociatedwith the non-linearstress-strain behaviourof


stainlesssteel),andtherefore1.0 vodampingwasadopted.To takeaccount
of the mannerin which the subsoilmodified the seismicmotion, soil-
E. ond E5 ore Youngs G .E
o
u-,
lloduli fq concrete & O
structureinteraction effects were evaluated.It was found that the stack's steel respectively.
c
(Es = mEc) o
secondmode frcquency had a resonanceeffect with the responseof the t.1
massiveRC foundationto subsoilmovement(modelledas equivalentsoil
CorresparaQ Ec
springsin thedynamicanalysis).This analysiswas,however,conservative moxinwn ,/
as it did not exploit thepotentialfor high levelsof radiationdampingin the cotnr*e -/
surroundingsoil. Norwithstandingthis, it was found thar the l-in-10 000- conprc:dw

t itft,"#j$'o")
strcss f"
year wind performancerequirementgenerallygovemedthe stack'sdesign
andnot theusuallyonerouso.TgZPA seismicqualification.(NB. This has
,T* { *1,.-,j:liil+'
d;"1
twice thedynamicprcssureof the normal I -in-5Gyear wind" sinces3= I .4.) Ncutrol sris
(SeeFig a.)
(b) H0boft |f,os.1,2 & 3 etc
Holdingdown bolt design rith tensiors Tt ,Ir & Tr
Areo h b.ori.rg & individtrct bolt dreos 16
Cyclic loading,dueto wind oscillatoryeffects,conrribures to thedesirability (NB Fc ig thc co.r6pon
cernpneeion - cfingrcsul,ont concntr
of usingpreloadedHD bolts.The wEp stackwasprestressed to its concrete
foundationby preloadingthe HD bolts with a 600 kN tensileholding-down cernprerdon force.)
force in eachof the 24 No- ?:1in diameterborts(8uN rolled threads).
Fig 2(a) showsa typical strainprofile for a stackbaseresultingfrom a (o) Shorr thc stroir profrlc occording to moduhr rotio theory duc to o wind
wind-inducedmoment,wheretlreHD bortshavenot beenpreloaded(i.e. it monrcnt U;1 ;ithout prclood in the H D bolts

behaveslike a 'cracked' RC secrion).Fig 3(b) shows,for the samestack (b) Shorr o plon of thc bssr of-tho corrcrponding stock
in fig 2(o)
base,a typicalbearingstressprofile which would occurif theHD boltshave
beenpreloaded,causingthe interfacebetweenthe baseof the steelstackand ilotc lhc cffcci of thc ctock solf-rcight (nogligiblc) b igrrcrcd in Figs 2 ond 3
the top of the RC foundation to behave rike a prestressed(uncracked) oso thrfthz
interfacein resistingwind moments.Apart from making it very mrrcheasier
to calculatethe bearingstressdisrriburionand bolt forces(seethe equations Fig 2- 'Cracked'basecondition
in Figs 2 and 3, respectively,for t}re cracked and uncrackedconditions), (o)
therc aresignificanrbenefirsin using preloadedtID bolts,which include rhe
following: b - rt;Uot Prudrcss
(l) For a given bendingmomentthe peak bearingsftss on the grout will
be considerablyrcduced.Hence the grout wiil, in general,be much less
liable to crushingfailurc. To illustratethis with rcfercnceto Figs 2 and3,
f min
y=+=,_-_-_f,=
(b)
supposethat (a) M'v1is equal to MwzNrd (b) therc is the limiting prcstrcssed
l*, fr - Ecndhg rtress
conditionwherc/-n. is zero.Then, for the prestressed base,./^,.andp6 will c9mpofr€fit
bc muchlessthantheircrackedbaseequivalen6/" andrl,rcspectively.(The
rcasonfor this can be readily appreciatedif borh solutionsare considered Neutrotoxis
in relationto their sectionmoduli. The sectionmodulusfor the prestressed |.-
(uncracked)sectionwitl be much greaterthan that for the sameconnection
intcrfaccwhenit bchaveslike a conventionalRC crackedsectionbasedon (o)& (b)
modular ratio transformedbolt areasin tension.) shor:. conrprotiw b.orirlg rtrerr dbtrihr&xr lor thc romo ctock bqrc o, h Frg2,
(2) For thc prcstressedcase,thcrc are consistentload parhsat, and above, but ;ith th. odttm ot ycro"d.h h. th. H 0 bon!" rry
{o) *r-,
bcoriDs ilnr dbtribuU<n*rcn thlc b m mornml -J /ril[t"jr"J,
u,"
thc grout interface.This resuls in the transmissionof (a) shear by shear- "o.r,p.r.iii
u," na
comprorrhr b€rng drco r,nder fr. octJonol o rind ,r-fft [j2_"-
friction and (b) tensilebendingstressby a rcductionin the comprcssive
bearingstresson rhe grout.This simplicity of load parhsdoesnot occur in r{o'te-* o"dri -
the cascof the crackedsolution.To appreciatcwhy this is, considerthe # *'*l*ffii'ffiHf;"HdT*"
positionson planof the neutralaxesfor purc bcndingabovethc srackbase ffocr : lnw- - lo + fr t dlorde grwl cornpreriw rtrtsr
ring and at thc grour./stack f rnir - fi - L> 0 (i.r. m rrt tcndh rtrrrr)
baseinterfacefor a given appliedbascmoment.
For the prestressed solurion,the position of the neutralaxis is the sarnear Fig 3. 'Uncracked' base/preloadedHD bolt condirion

29o Tlro structural [ngincer/Volumc 7 " t/ N o 1 6 / 1 7 A r r g u s t 1 9 g 3


[ ) : 1 1 l cB
r :l o o m c r

(6) As wcll as lnlt strcsscycling, a further consequcnce of stack base brium is achievedbetweenthe wind energyimpartcd(i.c. doing thc exciting)
'rocking' is thatit givesriseto anenhanced
top of stacklateraldisplacement and the eneryy dissipatedby the stack's natunl damping. Thc maximum
due to the magnifying levereffectof the stack.This is perhapsa visual rarher nmplitudest which thescarc in equilibrium is a function of thc damping and
than a technicalconsideration,and would be most noticeablewhere very involves solving a transccndentalequation.
long (flexible) HD bols are pnovidedin combinationwirh a rall. slender In thc ESDU analysist,this maximum amplitude is dcrived by making an
stack. initial guessat the amplitude,calculatingthe correspondingvalue of damp
(7) Prestressingthe stackbaseto its foundationresultsin the stackbehaving ing, and tlrcn iterating until the correct damping is obrained. This peak
in a morc linear fashionwhen subjectto dynarnicloading.Consequenrly, amplitude,and its rcspectivemodeshape,is then usedto detcrmine the dis-
the difficulties and uncertaintiesof a non-linearanalysiscan, with con- tribution of maximum moment and she.rroroughout the stack for design
fidence, be avoided. purposcs.
It is suggestedthat theamountof appliedprestressshouldbe designedto ESDIJ6was usedto calculatethe shesscsdue to the effecs of along-wind
avoid the potential for tensile separationof the stack basefrom rhe grour buffeting. This involved evaluatingthe along-wind oscillatory rcsponse
under maximum momentconditions.Although it is desirableto maximise causedby fluctuationsin thc wind specdrelative to is mean value and/or
the amount of inherentdampingwithin a sutck,the prestressing of its base vortices arriving from upwind strucnrrcs.
to the foundationwill tendto reducethe damping,which is a disadvanrage. An alternativc approachto providing helical strakcs for the purpose of
In the caseof WEP, this disadvantagewas considercdto be outweighed by minimising oscillatoryeffecs could have beento incorporatcsome form of
the advantagesas alreadylisted. passivedampingdevicein the stack(i.e. a dynamic vibration absorberT).
For prcloadingto work mosteffectively,relatively long bols arerequircd. Vortex sheddingand along-windbuffeting oscillationswerc each founc.
each fined with paircd sphericalwashersunder the 'lock off nuts. In the significantlyto increasethecantilevermomentsin the windshield.The cor-
caseof the WEP stack,thesebolts were 5.5 m long overall, the need for respondingresultantpeakbasemomens were, resp€ctively,32 % and42 *
which was governed,first, by shearconepull-out requiremensin the RC grcater than the l-in-50-year CP3 pseudo-staticwind momenr. (NB.
foundarion,and, secondly,by practicalconsiderationsassociatedwith the OrttrogonalmomenswerecombinedusingSRSSmethods.)Both the wind-
heightof the RC pedestal.As with conventionalpost-tensioningwork, long induced shearstressesand the self-weight direct stresseswerc found to be
bols provide a flexible stressingup lengthin relationto the axial stiffness very low.
of the elementsundercompression(i.e. the combinedstiffrressof rhe stack
base,grout and concreteshearcones). This flexibility in the bols also has Wind ovalisation efects
the double'benefitof ensuringthat they will be relarively insensitivero Wind aerodynamiceffecs give rise to variationsin pressure/suction around
'lock-off' lossesand,very importantly,
largechangesin the bendingstress the circumferenceof a windshield.This variation in pressurcgenerates
component(i.e."f- in Fig 3 (b)) will not be accompaniedby significant stresseswhich tend to distort the shell slightly into an elliptical shapeon
changesin preloadforcePp,in thebolts.Consequently,theprestress,f will plan-The designpressuredistributionwasdeterminedfrom information by
ftmain reasonablyconstantand,therefore,theextremebearingstresses,/,... Roshko8.The resultingshellstresses wereinvestigared,asw:ls th9 potential
and-f-r^.will be proportionalto moment- for oval oscillation-In this context"the roof plate and accessplatforms
The encastarrchor-platesat tlrc bonom end of the bolts were designedto have provided circumferentialstiffening.
an ultimare pull-out capacityin excessof the ultimate tensilestrengttrof the
bols- The srud-bolts(to BS 4882) werc manufacturedfrom I % chromium- Faigue
molyMenum alloy steel to material specificationBS 150G63G8@LT-75 Basedon theSGyeardesignlife, an assessment wasmadeof thecumulative
and preloadedto 33 Voof their guaranteedminimum yield strength. effect of the total number and range of tensile stresscycles at the crirical
locations.This involvedadaptingZLyear farigueIife equationsto suit 5O.
Design of the windshield year requirementse.Fatiguedid not presenta problem, since the welds had
Openings in the windshield beencarefully laid down, with smoothprofiles,thercbyminimising stress
Wherethe windshieldwaspenetrated by openingsfor the ventilationducrs concentrationeffects-Additionally, as part of the shell design,the tensile
feeding the flues, and the personnelentrancedoor, care was taken to: stressesat critical locationsincorporateda reservemargin to allow for
- avoid sharpcornerswhich could act as fatigueinitiators fatigueconsiderations (seeFig 4).
- restrain the ventilationengineer'senthusiasm(particularly during the
conceptuaidesignphase)for excessivelylarge holesand adjacenthole Installation stresses
provisionsthatstmcrurallywerepotentiallyin the wrong relationshipto The windshieldwas locally stiffenedup to withstandtemporaryreactions
each other appliedby the lifting cradleduring the craneinstallationof the stack.This
- minimisetheeffectof theseopeningsin termsof the resultingreductions involved considerationof the possibility of radial buckling of the shell as
:q j and discontinuitiesin the windshieldshell sectionmodulusand inertia- well as the meridional and circumferential stressesand overall stack
(This requiredengineeringjudgment in the design of shell sriffening deflecrions.
platesaroundthe perimeterof the openingsto sarisfythe generalstabiliry
requiremensof chimneyCodes)

Meridional stressesdue to wind loading


The CP!i' basic wind speed(i.e. l-in-50-year, 3 s gust) for the site was 47 l*-
m/s.Thecantileverbcndingstressesdueto l-in-5Gyear wind werc designed Utirnote copooty boscd
on lhe OOt 0 codc
using the criteria in BS 4076t. This factored strcssCode docs nor provide I
8 rnm s}lcl
permissiblestrcssesfor stainlesssteel.Thesewere computed,thercforc, on I
a pro rata basisfrom the carbonsteel permissiblestresscsand the ratio of
the BS l50l-guaranteed 0.2 Vo proof stress for stainless steel to the E
BS 436Gguaranteedyield stressfor mild steel. For analysispurpos€s,a ;JO
(t
I
meanvalue of Young'smoduluswas used. @
g I l0 nm shell
Helical srakes were provided for the top 17.0 m of the WEP stack. o
D
However;it is not utrcomrnonfor stacksto experienceoscillatoryproblems
z
SJI Shercd
b rird
L_1
cven when fitted with srrakes.The WEP stack,being lightweight and of an .9
a,
clastic design incorporatingweldedconnections(basedon rclatively low !
stressesto minimisc fatigue) and having preloaded HD bolts, was
consideredto havea very low valueof critical damping (OS % assunrcd).
As a rcsult, it wasdecidedthat the srackshouldbc designedagainstpotencial Ito ,r-, ria
aerodynamicoscillationsdueto vortexsheddingand along-windbuffeting.
Vortex sheddingcalculationswere carried out in accordancewith the
0 5000 t0000 t5000 20000 25000
meth<xlscon[ainedin the ESDU Wind EngineeringSubseries]r.When
WhdsficU toagituclirrclBcnding Moment (lNm)
voncx shedclingforccsoccur with a frcquencyctosc to one of the natural
frequcnciesof a stack, large amplitude oscillations can occur. The Fig 4. Comparison of I-in- 10 Ooo-yearwirul and seisnricmoments with
magnitudeof theselbrcesis degrndenton the displacement, until equili- capocity
.4

r - i r l ) ( ) :t t ) l ( ) o u l ( ) l '

cltL*tlltllcrcItti:tl
htrttrvcld.sin c<ln;trrrction
rvrtlrcxtcrn:rlcrrculnlcrcnlial
b:rcking-bnrstbr rhc lrrge llue.

Constnrction
Trial ossemhlyand,specifications
hior ro dispatchof the threesectionsof srackto site, lhey werc fuily
trial
assembled in the fabricationshop to demonstratecomplianccwith the
specifiedtolerancerequirementsfor overall axial straightness, circularity
and 'fit-up' of the siteweld preps.The specificationplaJedrnuchemphasis
on theserequirementsand other related aspecs, incrurJingthe weld
acceptance criteria and the allowable local post-wcldinggeometrical
toleranoes in relationto the propensityof stainlisssteelweldsto give rise
to considerable weld distortion(e.g..peaking').

Windshieldsite joints
The three fabricated sections of stack were sire wercredto form the
completedstack. This was undertakenwith the whole assemblylaid
Fig 5- view insidewindshieUrookingupwards,showingfluesand access horizontaland supportedon rollers.An alternativeform of siteconnection
provisions couldhaveemployeda borteddoubreflangesystem.However,this rype of
joint would have beenvulnerableto significantprying forces.
This could
potentiallyhavegivenriseto fatiguecyclingeffects.It would.nevertheless,
I-in-10 Ooo-yearwindand seismicevenrs
havebeenpossibleto rakeaccountof this in thedesignby usingpreloaded
These'extremeenvironmental'conditionsmay, more correctly,be thcrurir
flangebolts-other problemshad flangesbeenproviJed,lnctude:
of ashavinga probabilityof exceedance of l&o p.a.The associatedrlesisas - theinability of pairedflangefacesto 'mare-up'in
were undertakenusing elasric analyses.The resulting momen,, oile a satisfacrorymanner
due to their being 'out-of-true' (NB srainlesssteel,havinggreaterthan
checkedagainstultimatevaluesbasedon clcINDe. cIcI-ND is an ulrim:ie
normalweld distortion,increasesthis risk) (while gasketsmight appear
limit state code, and hence panial safety factors on load of unirr, ,*.ere
ro be ablero solvethis problem,their characteristiclow stiffness.iour
adoptedfor theseextremeenvironmentalconditions.Fig 4 shou.si:e
acceleratethe processof bolt fatigue)
extremeenvironmentaldesignmomentsasa functionof stackheighr-a.lcng - the need,during rhe fabricationprocess,to ensure
with the ultimatemomentcapacityof the windshield(basedon CICI\D,. that pairedflanges,
whensubsequenrly boltedtogetheron site,providecoaxiajflue holes in
eachof the accessplatforms at eachside of a joint
I-in-lp 0&-year hot and cold weather
Moreover,the bolted constructionalternativeconrrastsvisually with the
A beneficialproperryof stainlesssteetis is excellentductiliry ar sutr_z-o
morecorosion-resistantand aestheticallysuperiorsite-weldedsotution ttrat
temperatures. consequently,the effectof Iow temperatureson the exposed wasprovided.Further,by adoptingappropriateweld acceptance criteria and
areas of the srack (-22"c for l-in-10 Ooo-yearextreme cold u,eet}reo
using relarively low weld design stresses,the potentiil for fatigue was
requiredlittle considerarion.
avoided.However,theoptionof progressivelyerectingthesuck asa series
Although not exposedto oursideweatherconditions,the stackHD bclirs
of lighter secrionswas precluded.
were rcquired to sustaina low temperamrecondition (-12"c). This nc-
essitatedthe selectionof an appropriatequality of steelfor the manur-rcre
Weldfabricarion
of the HD bolts to avoid embrittlement,as well as precaurionsro clrad
The offsire weld fabricationemproyedmainly manual flux-cored metal
againstcorrosion.
inen gas-weldingtechniques.All welds were subjectto l0o zo visual
compliance with the extreme hot weather temperaturerequire:::*::r examinationbetweenruns,followedby 100vo dyepenetration
(43"c) was easily demonstrared as the stack maririal propeniesxrre examination
at cutbackandon completion. Additionatty,themorehighlystressed welds
relatively unaffectedand additionally,becausethermal expansron.ra5 weresubjected to a minimum l0 vox-ray radiography.Th. *. inspection
unrestrained, stressimplicationswereavoided. requirementswere applied to the onsite welds which, owing to practical
limitarions,were laid usingMMA techniques.welding r.n,r-*"r"
Foundation design erected
at siteto prorectagainstadversewearherconditions(Fig 6(b)).
Dividing the maximumstackbasemomentresultingfrom rhe l-in- i 0 olf,r-
All welding proceduresand welder approvalswere in accordancewith
yearwind (i-e.the 'extremewind') by rhesrack'sself-wcightto obrrin
- BS 4870and BS 487l, andinspectionplayeda major role in achievingthe
most onerousvalue of eccentricityfor an equivalentvertica.lload
s:rq 1 final quality standard.Becauseof the potentialfor stresscycling, the welc
value of about 17 m. The severiryof such ovenurning effecrs oa :=e
accepr.ance criteria (i.e. defect size) were consideredin relation to th,
foundation and the needfor preroadin the HD bolrs can be appreciarc<iir
requiredlife of the stack.
this eccentricityis consideredin reladon to the suck diamererof _r-ga-
Furthermore,the service Building 1.0 m-deep RC raft foundadoo uas
'thickened-up' Rolator requirementsduring siteassembly
underthe stack to 3.0 m (Fig l) to provide botr su6ckrr During tlrc siteasscmblyphasethe rhreeprcfabricatedsectionsof
weight locally to resist overturning effects and stiffncss to avoid -, srqckwerc
each supponedon two scts of roLators(fitted with rclatively soft
introduction of unacceptableflexural effects and minirnise .rocl::2. rubber
rollen). The configurarion of theserocatorscompriscd singie{rivc
behaviourin the raft. units
(rotatingin tandem)po,sirionedat rhe top and bonom
endsof the stack with
four setsof idter unis positionedat the rcmaining intermediatesupport
Flue design
poina- The support locations of these rotators and their
The stackhousedtwo fluesof 50o mm and 15@ mm dianrerer.wrrh *arl rcquireo
displacement @paciryneededto ensurethatthey would notdamagethe thin
thicknesses of 4.8mm and6.4 mm, respecrively (Fig 5). Bellou.slse shellof rhewindshieldin termsot
incorporatedin theductsjusr beforetheyenrercdrhewindshicld(sccFg _ - tbcir combinedability ro rorarethe whole
r assemblyas the welding
to allow the stackand flues to move frcely and avoid rhc inrro<Jucumrf
prcr,e*td
significantaxial forcesin the ducs. The flues werc supponed'enicail- g - the requiredcapacityof the rotators
the 17.5m level by rheflue supportplatform,which compnsctla plate:icrr to articulareand thercbyaccom-
modatcoverall site assemblyaxial alignment defecs (i.e. within
on a grillage of steelbeamsdesignedro Bs 5950. The flucs werc tw,i.1
tolcranceccntrelinekjnks), which inevitably would bc prescnt(this
stiffencdat this level and,in the caseof the largerfluc, rhc suppon s.\sdr
might otherwisc have bccn a major probtem oncc thc threc scctions
incorporatedproprieury bearingsto accorr'nodatcroration. Abor.e =rc
bccamca single rigid unit, i.e. whcn the initial circumfcrentialroot
levcl, lateralresrraintto the flueswasprovidedby tlrc inremul laridcr*r:-s
weldswerccompletcdfor rhc two sitcjoints: conscquently,in acting as
platforms.
a whole, tlrc stack was able to rotatc frecly (on all six scu of rorarors)
The flue^design was in accordancewirh rhe ASCE flue cic;er
suchtharall weld runscould bc applieddownhand)
publication'0and was relativelysrraighrforwarrj in rhat ir rlid nor hert a - the largereacion forccsappliedby the rorarorsro rhc windshicldwhich
contendwith explosionsor hot and/orcorrosivegascs.'['lrc site assc=rr.,
might causcbuckling(in vulnerablelocations,this was prcvenrcdby
connectionsinvolvedboltedflangesfor the small flue antl inrcrnallr -an
providinginternalcircumferential stiffencrsin the windshicld)

292 'fhc
Stnrctrrr;rE
l n p i n r , ' r l r / V o l t r r n7o1 l N o 7 6 / 1 7 A r t p t r s t I { ) $ 3
l ' ; r p r : r 'I:! l o o r r r t l r '

pnor to crccrron tor rhc sitc ilsscrnbly(ltig otb)). [;igs (r(c) ilnd 6(d) show
stagcs of thc cranc crccrion. rvhich took placc on 26 octobcr 199o. lrr
setting a trrget stack crccriun darc during the front end planning phase.
consideration was also given to the seasonal variation in wind speed.
A two-phasc grouting rcchnique was provided to the stack basc/
foundation interface at HD bolt lcvel- This involved dividing the stack base
into eight 45' sectors providing manageable grouting arcas around rhc
circumfercnce. Such an approech accommodated setting the stack to tevel
and plumb. and also. by ensunng adequare stability immediarely after
erection. it catered for the risk of early high winds. This techniquc facilirated
the pmgressive removll of all temporary packers. The contract documents
'suggesred
included a work schedule'which gave step-by-step details
concerning how the designers envisaged the installation should be
undertaken, including all the prepamtory work and the sequence of grouting
and prcload application to the HD bols.
Immediately after stack erection. the lightning protection system was
connected to the earth system of the WEP building. Similarly, the stack's
power and light were connected to the supply. These had becn wircd-up
inside the stack prior to erection as part of the stack contract.
After the stack ercction, a rveatherhoodcomprising a number of prefab-
FiS 6(a). Bottom section of stack leaving NEI-ICL Derby ricaed panels, was fitted to the stack to cover the gaps between the roof
opening, which had a perimeterupstand,and the stack as it passed through.
This was then made weathertight by the provision of a flexible flashing
system supplied and installed by the civil contractor (Fig 7). Similarly, ro
maintain fire compartmentation inside the building, flexible fire barriers
were installed around the circumferenceof the stack at each floor level-

Preloading the holding-down bolts


The HD bols were encast ngid (i.e. without sleeves) in ttre foundation
using a template to ensure that the stack base was drilled correctly, Further-
more, and of primary imponance, the encast bolt shanks were debonded
from the foundation concrete, to accommodate elastic stretching of the
entirc shank length of the encast bolts during preloading. Debonding also
avoids the possibility of loss of preload with the passage of time because of
progressive bond failure of the encast bolt shanks.
In practice, the normal methods of torquing up bols (i.e- long rommy-
bars or a torque-multiplier) will introduce a measure of preload. However,
these processes are somewhat imprecise and, where large diameter bolts
and./or high tensile bolts are involved, it will generally be possible to
introduce only a small proportion of the bolt capacity. The 60O kNlbolt
FiS 6(b). Site assembly to the south of WEP using welding tents
preload was applied to WEP's HD bolts using hydraulic bolt tensioners.
These tensionersmade it possibleto introduce high levels of force into the
bolts with considerableaccuracy,the magnitude of which was computed for
Temporary works
each bolt by two independentmethods. First, from measuremenr of the
The contractor was required to design and supply severai irems of tempora-ry
elastic extension (using ultrasonics,i.e. pulse-echo timing techniques) and,
works. These included the lifting cradle (9.5 r weighr) and railing beam,each
secondly, by measurementof hydraulic fluid pressure. Both sets of results
of which was proof load tested prior to dispatch to sire. In order to ensure
uniform support during the lift, the cradle was positioned on rhe windshield
in tlre fabrication shop to serve as a template to guaranteeaccuratefitting
Fig 6(d). View looking wesrduringfinal sragesof stack insrallation ( usinga
of the erecLionshearpadsas they were being welded in place.
lifting cradle and lifting beam)

Installation
A high load route was required for the delivery of the three prefabricared
stack sections to Sellafield. (See Fig 6(a)). The programme allowed 7 weeks

FiS 6 (c). View looking west at lift commencemenl,showing 850 t muin crane
and 180l tailing crane
l)iriltlr:IJloomcr

ensunngthc tchicvcnrcntol'full ccrutlcationprior to invitirrgtcndcrs.


The contrrctorbcganby prorlucingdctailedfabricationdrawings.Thesc
definedall weld locationsnndcorresponding weldingprocedurcsto be usetl
for both offsite fabricationand onsite asscmbly.These drawings, along
with quality plans and method statements.were submittedto BNFL for
commentandapproval.Under the contractQA procedures,xny subsequent
modifications (including variations to the specificarion) rcquircd or
'Concession'forms.
suggestedby the contnctor were submittedon QA
Wherc BNFL grantedtheseconcessions.the contractorwas rcquircd to
'as
modify therelevantfabricationdrawingsaccordingly.Thus,a full setof
built' detaildrawingswas avaihble on contractcompletionfor recordin6/
archivingpurposes.

Contractual approach and considerations


The stackfabricationand installation was provided under a direct contract.
basedon GOWorkVl Conditions of ContracL a traditional, QS prepared,
bill of siteprcliminariescombinedwith a comprchensiveactivity schedule.
An importantfearurcof this activity schedulewas that it was prcpared by
the design engineers,and, when priced by the contractor, it provided a
seriesof lumpsums(i.e. one for eachitem of work both on - and offsite).
Fig 7. View of stack and weatherhood at building roof level This approachmadethe evaluationof interim paymentsrelarivelystraight-
'percentage complete'for eachitem. The con-
forward,i.e. proportionalto
tract was let in November 1989,on the basisof high de{inition tender
showedclose correspondence at all stages,providing confidencethat the drawingsand comprehensivespecificationswhich gave a lump sum
bolts had been successfullydebondedfrom the foundationconcrete.Bolt contract.
tensionersalso avoidedthe dangerof generatingadditionaltorsionalshear The overall programme was extremely tight and, because of the
stressesin the bolts due to the processof torquingthem up. The preloadin procurcmentlead-timesfor stainlesssteelplate,BNFL advanceordera
the HD bolts was appliedprogressivelyover a periodof 4 weeksto suit the bulk of this marcrialfrom British SteelStainlessunder a contractwhich w.s
crushing srrengthof the grout, which was a function of its age. This subsequentlyassignedto the contractor.
approachalso minimised relaxation and creep losses.Furthermore,the The provisionof the cranefor the stackerectionwas included in the stack
'locked off' beforethejacks werereleased(similar to
apptiedpreloadwas contract,togetherwitha requirementthat the stackhad to be fully assembled
the anchoringof prestressing strandsin post-tensioning work). The final 'as on the ground beforc erection. This resulted in a single lift of 95 t. The
lockedoff' bolt forceswere measuredaccuratelyby ultrasonictechniques contractwascompletedby mid-December1990.(Details of theparticipating
and recordedto facilitate the long-termmonitoringof the preloadforce in contractorswith their respectiveinvolvement in the stack procurement
eachof the bolts. procqssarc !o be found in the 'cover story' of The Strucrural Engineer, 16
April 1991.)
Baseconnectiongrout
The grout gap was nominally 70mm. Armorex L2 high flow grout was Project conclusions
used,which combinednon-shrinkand high flow characteristicswith both (l) The introductionof preloadinto the HD bolts provided a number of
rapidearly strengthgain (approx26 N/mm2at 24 h) and,in the longerterm, importantbenefits.Theseincluded,inter alia, a significantreductionin the
high compressivestrength0t = 78.5 N/mm2). potentialfor fatigue in the HD bolts, lower peak grout bearingstrcsses,the
avoidanceof stackbase'rocking' effecs, more reliable stresscalculations
Maintenance requirements for the stack'sHD bolt anchorageassembly,and greaterconfidencein the
To facilitateexternalwindshield maintenance, the roof plate incorporates validity of the lineardynamicanalysison which the designwas based-
an accesshatch and is fitted with steeplejackanchorages.Internally, the (2) BS 4O76:1989 is an improvedadvancement on the 1978editionn,which
windshieldhaspermanentladderswith illuminatedaccessplatformsevery was usedin part for the designof the WEP stack.However,in the author's
7.0 m. opinion,thereremainsomedesignconsiderations which merit clarification,
To enable maintenanceto be undertakenefficiently, a list of safety particularlywith regardto the provisionof a 50-yeardesignlife and/or the
requirementswas preparedfor personnelgoing inside the stack with l4 useof stainlesssteel.
inspectionactivities to be carried out periodically to ensurethe stack's (3) The ESDU methodsof estimatingthe resultantmaximum st
continuing long-term serviceabilityand perforrnance.Following the first momentsat lower wind speedsdue to (a) vortex sheddingsand (b) along-
anniversaryinspection,further inspectionactivitieswerc scheduledto be wind buffetingt gave momentsthat were, respectively,327o and 42 Vo
done at 3-and Gyearly intervals. The schedulegave the rclevant general Ereatarthan for the l-in-SO-yeardesign wind moment based on the
arrangementand fabrication drawing numbersand the criteria to be applied conventionalCP3' approach.Consequently, similar sucks fitted with
for each of the inspectionactivities.Included in this was a table which helical srakes, and possessingminimal damping, may be vulnerable to
'lock off' for eachof
recordedthe 'as built', measuredpreloadforce after oscillatoryproblemsin service.Suchdesignsshould take due cognisance
the HD bolts. This table madeprovisionfor future preloadmeasuremens of thesc phenomena.(The resulting stresseswere checked against the
to be recordedso that any long-termrelaxationtrendscould be monitored. allowablesgiven in BS 4076 1978' which were modified to suit the
propertiesof stainlesssteel.)
Quality assurance (4) Windshieldovalisationeffecs were investigatedin relation to the
Structureson nuclearsites are requiredby the licensingauthority (the circumferential pressuredistributiongiven in ref. 8. The meridionalstresses
Nuclear InstallationsInspectorate(NII)) to bc designedand constructed due to the l-in-10 00Gyear wind were checkedagainstthe criteria in the
underrigorousquaJityassurance(QA) procedures. Prior to commencement CICIND Codee.A fatigue assessment. was also made using CICIND.
of thestructuraldesign,a safetycascdocumentis compiledandagreedwith Finally,ref. lO was uscdfor the designof the flues.
the NII. The designand analysisis thencompletedin accordancewith this (5) The designersspccified someintemal parts from galvaniscdmild stcel,
safetycase.Furtherrnorcrafrcr the designshavebcencheckedand appmved, ratherthan stainlessstecl as pcr the rcmainderof the stack. This approach
they are submitted to an inhousc spccialistscction for an indepcndent providcd linle net benefit owing to thc inconvenienceit causedand the
strucoral assessment. This processinvolves a documentcdappraisalof the precautionsrrcedcdo guardagainstcontActof mild steeland stainlessstccl.
philosophy and selective checking of derail calculations for validity/ (6) The 'suggcstcdwork schedule'for the site installationand thc 'priccd
correctnessand compliance with the saferycasc. activiry schedule', which was a fundamentalcontract document,proved
A n i m p o r t a n tl i c e n s i n gr e q u i r e m e nits t h a t t h e o n s i t ee r e c t i o n / highly succcssfulstmtegies.
constructioncannotcomrnenceuntil theAsscssment Enginccrhasformally (7) All aspectsof thc srackproject werc completcdsatisfactorily(sec Fig
issueda certificateto confirm that he is fully satisfiedwith the dcsign. In 8). The contractor,NEI InternationalCombustionLtd, achievedhigh
the caseof the WEP stack, the aim was to provide firm tenderdrawings standardsof workmanshipin completingthe fabricationand meeting the
suitablcfor a lumpsunl contrxct.Design effort was thereforeput into reguirements of the specification.
'[itV
l)alttrr: Blotlttttlr l ) l r' g r ' : lor'

Paper:Taylor
continuedfrom Pagc 288

Acknowledgement
The author is pleasedto acknowledgethe assistanceof his colleagueJohn
Surtecsfor his gift of historicaland technicalknowledgeesscntialto the
paperand also his now rctired colleagueJohn Snasdellwho taught him
much aboutsleepers.The helpful comentsof Dr D. Cope.of British Rail.
arc also gratefullYacknowledged.

References 'Thedevelopment
l. Barker.R. S. V., lrster, D. R.: andmanufacture of
-75
concrcteunits', Societyof Engineers,May l9a6' ppal
prcstrcssed
discussioncontribution,Henzell.J' S'
2. Srrcssesin railroad tracks- the TalbotReponsI9l8-1940, rcprinted
by American Railway EngineeringAssociation,washington, DC.
1980
'ExperimenSon rcinforcedconcretesleepers"Proc.
3. Johansen,F. C.:
/CE, Railway Division' May 1944,pp3-20
'Experimentson concretesleepers"Proc' /CE, Rail-
4. Thomas,F. G.:
way Division, 1944,PP2l-66
5. 85986 Concrete railway sleepers, London' British Sundards
Institution,first pub. 1941,2nd rev' 1945
'RecentdevelopmenSof prestressedconcreteconstruc-
6. Everine,T. J.:
-
tion with resultingeconomyin the useof steel TechnicalAppendix
by K- W. Mautner', The StructuralEngineer,July l94O'pp62G642
7. First report on prestressedconcrete,f.ondon, IStnrctE, September
1 9 5 1p, P 3 l
8. Cpl I j The structural use of prestressedconcrete in buildings,
London,British StandardsInstitution' 1959
g. Zimmerman,H-: Die MerechnungdesEisenbabnoberbaues (original
pub.c. 1890)W-Ernst& Sons'l94l,3rd ed'
Fig8. Endofproiect 'Fatigueof plain concretewith stress
10. Cornelissenand Reinhardt:
reversals',CEB Bulletin No. /88, lausanne'CEB' 1984

Acknowledgements
on
The authorexpresseshis appreciationto all his colleagues who worked
project- He is panicularly grareful for the suPPort of George
the stack
Maddison(M) (Allott & Lomax).

References
l. BS CP3: Chapter V: Pan 2: Wind loads , London, British Standards
Institution,1972
.Designagainstwind-excitedvibration,'The strucrural
?. Bolton, A:
Engineer,6lA, No- 8, August 1983
Part I :
3. gSbU 82026Strong winds in the armosphericboundary layer:
meanhourlywindspeeds,London,EngineeringSciencesDataUnit'
August 1984
4.Bs40T6Specificationforsteelchimneys,London'BritishStandards
Institution,1978
5.ESDUS503SCircular.cytindricalstruclures:dynamicresponselo
vortex shedding: Part I: Calculation procedures and derivailon,
London, EngineeringSciencesData Unit' May 1986
I :
6. ESDU 86035 Calcitation methodsfor along-wind loading: Pan
Response to
of tine-like structures atmosphericturbulence.[,ondon,
EngineeringSciencesData Unit' December1987
'Control of wind-inducedvibrationsof civil engineering
7. Hirscn, G:
srrucrures"Aachen,4thcolloquiumon IndustrialAerodynamics' June
1980
'Experimen6on the flow pasta circularcylinderat very
8. Roshko,A:
high Reynoldsnumber',Journalof Ftuid Mechanics'May l96l
g. clcIND Model Codefor steelchimneys,Internadonalcommineeon
IndusrrialChimneYs,MaY 1988
of
lO. Designand consrircrion-ofsreelchimneyliners,AmericanSociety
Civil Enginecrs,1975

Vous aimerez peut-être aussi