Cleaning & Inspection for


Lube oil Heat Exchangers
and Coolers

TECHNICAL PROPOSAL PRP27

Gas Turbine 7FA- Lube oil Compartment


Proposal # Recipient Title Page No.
PRP-135 GE-Power Turbine Aux Scope 1
Table of content

1. Technical Background .......................................................................................................... 4


1.1 Statement of Problem:........................................................................................................................ 4
1.2 Background ......................................................................................................................................... 4
1.2 Objectives: .......................................................................................................................................... 4
1.3 Scope of Work .................................................................................................................................... 5
2. Cost Estimation.................................................................................................................. 7
2.1 Proposed Technical Team ................................................................................................................... 7
2.1 Proposed Quotation............................................................................................................................ 7

Proposal # Recipient Title Page No.


PRP-135 GE-Power Turbine Aux Scope 2
To whom it may concern,

It’s our pleasure for being invited to submit the proposal for the Turbine AUX Scope works at PP-8 for GE
frame 7 Gas Turbine during their Major Inspection

We are submitting a complete proposal for carrying out a Aux works as mentioned by GE ,It is our pleasure
to assure you that NPM holds a team of qualified and experienced Engineers, Supervisors, Technicians,
Fitters, Specialists, EHS Supervisors, Riggers, Crane operators and another necessary crew to deliver the
services within the stipulated timeframe.

Regards

Engr. Hamid Hasan – GM

Proposal # Recipient Title Page No.


PRP-135 GE-Power Turbine Aux Scope 3
1. Technical Background
1.1 Statement of Problem:

A Trunkey Services to carry out the Major Inspection Auxiliary scope during the outage with includes the
Overhauling and Servicing of described systems as per GE / SEC standards.

1.2 Background

National Project Managers (Pvt.) Limited is fully committed for delivering the designated
objectives for their Projects assuring the quality work within all its activities and work
undertaken by the Company. In order to achieve our stated objectives NPM has developed a
framework undermining the following:
National Project Managers (Pvt.) Limited has implemented a management structure that is
based on the quality and commitment of its professional and experienced management and
construction staff. Our management have a specific responsibility for ensuring that the
management structure reflects the quality standard, so that compliance with this Quality Policy
is maintained and improved.
Our approach is to listen to our clients and customers and to openly discuss the individual
requirements of every contract, thus ensuring that our clients remain fully satisfied with our
service delivery. With each project we undertake, a Quality Plan is implemented, encompassing
control measures that ensure the client’s requirements are met, within the specified time, and
in line with the budget. To this end, we endeavour to work as a committed team in a spirit of
co-operation with the client and their customers.
National Project Managers (Pvt.) Limited s' management and supervisory staff has the authority
to make decisions, within the scope of their responsibilities, and is charged with working in
accordance with the documented procedures.ee in staff training to professional level.

1.2 Objectives:

The Immediate objective of this Proposal is to briefly describe the major scope that is required
to carry out the Aux works during the Major Inspection of GT-2 with G.E which includes the
overhauling and Servicing of the Lube/ hydraulic oil system, Washing / cooling water skids and
Aux for Fuel gas system that will be covered during the Outage of GT-2 Major Inspection

Proposal # Recipient Title Page No.


PRP-135 GE-Power Turbine Aux Scope 4
1.3 Scope of Work

All the activities mentioned will be performed as per GE / SEC standards and Approved HSE working
procedures. GE/ SEC will provide us the access for the working personals, tools and equipment’s required
on site. Activities will be mutually coordinated with SEC O&M and GE site personals for related activities
to complete them in designated time frame. Documents (Reports or time sheets) are produced for daily
activity monitoring.
The General Scope will be:

1. Inspect, Overhaul and Test aux. hydraulic pump and Hydraulic oil supply manifold
All the pumps including the Hydraulic system (2 No’s) which needs to be overhauled and
inspected for any major damage or replacements, including the alignment, greasing and bearing
replacement if required.

2. Inspect and Servicing of main lube oil system at Lube oil Compartment
All the Pumps including the 2 AC, 1 DC Lube oil Pumps and 1 AC seal oil Pump which needs to be
services, overhauled and inspected for any damage and replacements required, this also
includes the removal of lube oil, cleaning of the lube oil tank and refilling it back as per GE
standard (Purification to be carried out as per GE request through Oil Purifiers available at site)

3. Clean / Inspect Radiators (coolers) , replace radiator fan bearing and inspect the belts and
replace if necessary
Removing of coolers for detergent / chemical cleaning, inspection of radiator fan bearing and
replacing them if required

4. Inspect lube oil heat exchanger removal ,cleaning and reinstallation of cooler bundles (as
needed) and inspect transfer valves
Removing of tube bundles for cleaning and installing them back , all the transfer valves for the
lube oil system needs to be inspected and cleaned.

5. Cooling water skid servicing /overhauling of cooling water pumps ,servicing of cooling water
fans
Inspection of Cooling water Pumps ( 4 No’s) and 12 (Fin Fans) for replacing of Mechanical seal
and greasing for the pumps , and motor bearing or belt replacement along with its alignment

Proposal # Recipient Title Page No.


PRP-135 GE-Power Turbine Aux Scope 5
6. Inspection , Service and calibration of all valves temperature regulator (VTR) , PRV , Relief
valve ,Orifices , check valve
On site field calibration for all the valves included in the AUX scope for their Packing leakage and
incorrect settings from the fuel gas valve,Pressure regulating valves ,Temperature regulating
valves ,oil flow butterfly valves, Dial gauge indicators and Transmitters needs to be calibrate and
replacing the damaged once as requested by GE

7. Checking and adjustment of alignment for all the Aux pumps


Re-Alignment for all the pumps removed during the Inspection

8. Inspection of Gas control Valves


Servicing of 4 control valves and 2 Stop valves included the removal of the Actuator assembly for
inspections and cleaning only, it may also include some diaphragm and interconnected control
valves which needs to informed by GE during the Inspection and outage phase

9. Servicing and Functional testing of compressor bleed valves


Inspection and Servicing for compressor bleed valves (4 No`s)

10. Visual inspections for expansion joints ,of water , attempter , bleed and cooling, seal air
Inspection of all expansion joints and arresting all leakages for attempters, cooling air, water and
Seal air lines.

11. Hydrogen Coolers


Removal of Generator Hydrogen Coolers (5 Nos) for Cleaning and Inspection

12. Control Devices


Inspection for all the Control devices including Temperature switches and thermostats for their
variations for their dropout and incorrect settings

All activities will be done under the O&M coordination with proper LOTO.

Item Activity Description Supplier


1 LOTO NPM/GE/SEC
2 Supply of Component Material GE
3 Repairing / Leakage arresting NPM
4 Supply of Dial gauge/ Thermostats / Switched GE
5 Valve and gauge Calibration NPM / 3rd Party
6 Lube oil Purification (if requested) NPM
7 Lube oil Purification Skid SEC/GE

Proposal # Recipient Title Page No.


PRP-135 GE-Power Turbine Aux Scope 6
2. Cost Estimation
The Costing of this proposal is based on Activities carried out for the Services against the mentioned activities
during the GT-2 Outage

2.1 Proposed Technical Team

NPM will depute the following crew for this assignment. The Minimum Experience and qualification is
mentioned against each skill. All crew members are highly experienced and possess hands-on
experience of Major assignments

Description Qualification Experience Quantity

Project Manager / Engineer BE Mechanical Engineer 13 Years 01


Mech. Supervisor B-Tech Mechanical 10 Years 01
Mech Technicians DAE Mech 4-8 Years 6
Mech. Helpers SSC/FA/ DAE 4-8 Years 4
Elec/Instr Technicians DAE Electrical and Instrumentation 4-8 Years 2
Scaffolder Qualified/Certified 4-8 Years 2
Rigger Qualified/Certified 4-8 Years 2

2.1 Proposed Quotation

Service Description Unit Qty Unit Price Total


overhauling of Hydraulic Pumps EA 2 4,000.00 8,000
Servicing of Hydraulic oil manifold Lot 1 4,000.00 4,000
Hydraulic Oil
System Lot 1 6,000.00 6,000
Servicing / Cleaning of Hydraulic Valves
Cleaning of Hydraulic Supply Filters EA 2 1,000.00 2,000
Overhauling and Servicing of Lube oil Pumps EA 3 3,000.00 9,000
Overhauling and Servicing of Seal oil Pumps EA 1 3,000.00 3,000
Cleaning and Inspection of Lube oil Tank EA 1 4,000.00 4,000
Lube oil Sampling (Physical Properties, NAS no.) Per 1 800.00 800
sample
Lube Oil Inspection and Cleaning of lube oil Heat
System EA 2 5,000.00 10,000
Exchanger
Inspection and Cleaning of Lube oil Heaters EA 2 4,000.00 8,000
Cleaning of Lube oil Filters EA 4 1,000.00 4,000
Overhauling and Servicing of Mist Eliminator
EA 2 1,000.00 2,000
fans
Inspection of Compartment Vent fans EA 2 1,000.00 2,000

Proposal # Recipient Title Page No.


PRP-135 GE-Power Turbine Aux Scope 7
Overhauling / Servicing of wash water pumps EA 4 3,000.00 12,000
Cooling water Overhauling / Servicing of Cooling fans EA 12 2,500.00 30,000
System Inspection of radiator / coolers EA 2 1,500.00 3,000
Pipe / leakage repairing for Cooling water
Lot 1 3,000.00 3,000
lines(if any)
Relief Valves Per unit 1 1,200.00 1,200
Solenoid Valves Per unit 1 1,500.00 1,500
Servovalves Per unit 1 12,500.00 12,500
Valve Orifices Per unit 1 1,000.00 1,000
Overhauling Check Valves Per unit 1 1,100.00 1,100
and Servicing Manual Butterfly valve Per unit 1 1,200.00 1,200
Calibration of Pressure gauge Per unit 1 450.00 450
Calibration of Temperature gauge Per unit 1 450.00 450
Pneumatic control valves Per unit 1 1,800.00 1,800
Diaphragm Valves Per unit 1 1,500.00 1,500
Pump Shaft
Pump Alignment Per Pump 1 5,000 5,000
Alignment
Gas Control Inspection & Servicing of Gas control valves EA 4 3,000.00 12,000
Valves Inspection & Servicing of Gas Stop valves EA 2 3,500.00 7,000
Hydrogen Removal and Cleaning of Generator
5
Coolers Hydrogen Coolers EA 2,500.00 12,500
Compressor Inspection and Servicing for compressor air
4
Bleed valves bleed valves EA 3,500.00 14,000

Expansion
joints, water inspection and repairing / arresting of all 10,000
bleed leakages for expansion joints , bleed air , Lump sum 1 10,000.00
,cooling and cooling and seal air lines
Sealing air

Note:
1. Valve calibration will be quoted separately as per the type and requirements during the
Inspection
2. Additional items which are not listed above will be quoted separately
3. Motors are not included in this scope
4. Lube oil Purification is not yet confirmed , if requested will be quoted separately
5. Dial gauges will be calibrated from the 3rd party
6. All major components will be by customer / GE
7. Functional Testing will be by GE from Mark IV.

Proposal # Recipient Title Page No.


PRP-135 GE-Power Turbine Aux Scope 8
Proposal # Recipient Title Page No.
PRP-135 GE-Power Turbine Aux Scope 9

Vous aimerez peut-être aussi