Vous êtes sur la page 1sur 2

Project : 4-Laning of Chapra - Hazipur Section of NH - 19 in the state of Bihar (from Km. 143.200 to km.207.

200)

Subject: Status of Geo technical reports for structures on the project road

S. Existing Design Type Span arrangement as Span arrangement Status as on 11.10.2010 Remarks
No. Chainage Chainage per schedules proposed by MELTECH

Chappra
1 145.162 MJB 4 x 20 4 x 20 Particle sizes are to be furnished by Soil consultant For Scour depth calculations
bye pass

Scour calculations are sent to soil consultant for furnishing


2 182.100 183.209 MJB 3 x 25 3 x 25
soil reports

3 203.700 206.436 MJB 46.36+13x60.63+46.36 46.36+13x60.63+46.36 Corrected soil report is submitted on 23-08-2010 Closed

1 204.884 207.768 Flyover 3x25 3x25 Draft Soil report is submitted on 17-08-2010 Meltech to check and revert back
2 206.700 209.530 Flyover 11x20 Draft Soil report is submitted on 27-08-2010 Meltech to check and revert back

1 203.139 205.871 VUP 1x8 1x8 Draft Soil report is submitted on 14-08-2010 Meltech to check and revert back
2 204.150 207.031 VUP 1x8 1x8 Draft Soil report is submitted on 14-08-2010 Meltech to check and revert back
3 206.298 209.050 VUP 1x8 1x8 Draft Soil report is submitted on 14-08-2010 Meltech to check and revert back

Chappra Scour calculations are sent to soil consultant for furnishing


1 143.508 MNB 1x40 4x10
bye pass soil reports
Chappra
2 146.512 MNB 1x10 2x5 Particle sizes are to be furnished by Soil consultant For Scour depth calculations
bye pass
Chappra
3 148.495 MNB 2 x 15 3x10 Particle sizes are to be furnished by Soil consultant For Scour depth calculations
bye pass
Chappra Scour calculations are sent to soil consultant for furnishing
4 152.430 MNB 1 x 10 1 x 10
bye pass soil reports
Chappra Scour calculations are sent to soil consultant for furnishing
5 152.933 MNB 1 x 15 2x7.5
bye pass soil reports
Chappra Scour calculations are sent to soil consultant for furnishing
6 153.210 MNB 1 x 10 1 x 10
bye pass soil reports
Chappra
7 155.365 MNB 1 x 10 1 x 10 Particle sizes are to be furnished by Soil consultant For Scour depth calculations
bye pass
Chappra
8 156.250 MNB 1 x 12 1 x 12 Particle sizes are to be furnished by Soil consultant For Scour depth calculations
bye pass
Chappra Awaiting for final soil report with corrections as per the
9 157.175 MNB 1 x 35 10+15+10 Soil report is submitted on 20-09-2010
bye pass discussions had with soil consultant
Chappra Awaiting for final soil report with corrections as per the
10 157.725 MNB 1 x 20 2x10 Soil report is submitted on 20-09-2010
bye pass discussions had with soil consultant
Chappra Awaiting for final soil report with corrections as per the
11 158.864 MNB 1 x 10 1 x 10 Soil report is submitted on 20-09-2010
bye pass discussions had with soil consultant
Awaiting for final soil report with corrections as per the
12 170.575 172.189 MNB 1x26 3x8.3 Soil report is submitted on 20-09-2010
discussions had with soil consultant
Project : 4-Laning of Chapra - Hazipur Section of NH - 19 in the state of Bihar (from Km. 143.200 to km.207.200)

Subject: Status of Geo technical reports for structures on the project road

S. Existing Design Type Span arrangement as Span arrangement Status as on 11.10.2010 Remarks
No. Chainage Chainage per schedules proposed by MELTECH

Shittalpur Awaiting for final soil report with corrections as per the
13 185.921 MNB 1 x 10 1 x 10 Soil report is submitted on 20-09-2010
byepass discussions had with soil consultant
Shittalpur Awaiting for final soil report with corrections as per the
14 187.037 MNB 1 x 40 4x10 Soil report is submitted on 20-09-2010
byepass discussions had with soil consultant
Shittalpur Awaiting for final soil report with corrections as per the
15 194.718 MNB 1 x 20 2x10 Soil report is submitted on 20-09-2010
byepass discussions had with soil consultant
Soil report for pile foundation system is submitted on 07-09-
16 200.400 203.175 MNB 1x46.67 4x11.2 Soil report is required for raft foundation system
2010
Awaiting for final soil report with corrections as per the
17 201.750 204.535 MNB 1x43.65 8.3+25+8.3 Soil report is submitted on 20-09-2010
discussions had with soil consultant

Chappra
1 143.974 ROB 3x26.230 3x26.230 Soil report is submitted on29-09-2010 Closed
bye pass
Chappra
2 150.984 ROB 13.230+26.230+13.230 13.230+26.230+13.230 Soil report is submitted on29-09-2010 Closed
bye pass
Chappra
3 157.860 ROB 26.23+31.23+26.23 26.23+31.23+26.23 Soil report is submitted on29-09-2010 Closed
bye pass
Digwara
4 177.182 ROB 26.23+31.23+26.23 26.23+31.23+26.23 Soil report is submitted on 07-09-2010 Closed
byepass

Meltech Expressed doubt on Lateral capacity and asked to


5 206.555 209.318 ROB 6x26.230 6x26.230 Soil report is submitted on 14-08-2010
submit revised soil soil report with increased lateral capacity

Vous aimerez peut-être aussi