CALENDARIO DE AVANCE DE OBRA VALORIZADO

SEMANAL

OBRA: MEJORAMIENTO DEL SISTEMA VIAL Y PEATONAL


DEL ASENTAMIENTO HUMANO SEÑOR DE LOS
SUPERVISION Y MILAGROS DISTRITO DEPAUCARPATA AQP,
CONSTRUCCION E.I.R.L.
FECHA POR ING. H. H. OVIEDO

DURACION
PLAZO DE EJCUCION EN DIAS 26
7 7 7 5
09- jul 18- @ 16- jul 18- @ 23- jul 18- @ 30- jul 18- @
Item Descripción Parcial (S/.)
15-jul-18 22-jul-19 29-jul-19 03-ago--20
01 JARDINERAS DE CONCRETO 21,811.60 S/.19,099.70 S/.2,711.90
01.01 CONCRETO SIMPLE 18,164.07 S/.15,452.17 S/.2,711.90
01.01.01 + 30% P.G. S/.14,070.17
CONCRETO CILOPEO PARA CIMIENTACION 1:10 14,070.17
01.01.02 JUNTA DE DILATACION e=1/2" 2,711.90 S/.2,711.90
01.01.03 1,382.00
SOLADO PARA ZAPATAS DE 3" - 1:12 (cemento - hormigon) S/.1,382.00
01.02 CONCRETO ARMADO 3,647.53 S/.3,647.53
01.02.01 ACERO CORRUGADO JARDINERA (3/8" promedio) 3,647.53 S/.3,647.53
02 MUROS DE CONTENCION 40,034.51 S/.10,675.62 S/.25,854.19 S/.3,504.70
02.01 CONCRETO ARMADO S/.10,675.62 S/.25,854.19
02.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 4,311.64 S/.4,311.64
02.03 ENCOFRADO MURO DOS CARAS h=1.80 m 14,318.96 S/.6,363.98 S/.7,954.98
02.04 CONCRETO PREMEZCLADO MUROS CONTENCION17,899.21 f'c=175 kg/cm2 S/.17,899.21
02.05 REVESTIMIENTOS 3,504.70 S/.3,504.70
02.05.01 TARRAJEO MUROS EXTERIORES 3,504.70 S/.3,504.70
03 PINTURAS 1,130.35 S/.1,130.35
03.01 PINTURA LATEX EN MUROS EXTERIORES 1,130.35 S/.1,130.35
EXPEDIENTE TÉCNICO DE ADICIONALES N° 01 DE LA OBRA:

MILAGROS DISTRITO DE PAUCARPATA – AREQUIPA-AREQUIPA.”

COSTO DIRECTO S/.62,976.46 S/.29,775.32 S/.25,854.19 S/.6,216.60 S/.1,130.35


GASTOS GENERALES S/.5,038.12 S/.2,382.03 S/.2,068.34 S/.497.33 S/.90.43
“MEJORAMIENTO DEL SISTEMA VIAL Y PEATONAL DEL A. H. SR. DE LOS

UTILIDAD S/.4,408.35 S/.2,084.27 S/.1,809.79 S/.435.16 S/.79.12


SUB TOTAL S/.72,422.93 S/.34,241.62 S/.29,732.32 S/.7,149.09 S/.1,299.90
IGV S/.13,036.13 S/.6,163.49 S/.5,351.82 S/.1,286.84 S/.233.98
TOTAL PRESUPUESTO S/.85,459.06 S/.40,405.11 S/.35,084.14 S/.8,435.93 S/.1,533.88
PORCENTAJE DE AVANCE SEMANAL 47.28% 41.05% 9.87% 1.79%
_________________________________________________________________________________________

PORCENTAJE DE AVANCE SEMANAL ACUMULADO 47.28% 88.33% 98.21% 100.00%

ADICIONALES N° 01