Académique Documents
Professionnel Documents
Culture Documents
TOTAL PRICE
NO. DESCRIPTION
(Rp)
(1) (2) (3)
1 BILL NO 1 : PREPARATORY WORK & BUILDING GIS 150 KV NEW CIKUPA 11,840,759,974
Name of Bidder :
1 of 219
Signature of Bidder:
PEMBANGUNAN GIS 150 KV CIKUPA NEW
DAFTAR DAN KUANTITAS HARGA (BOQ)
DAFTAR 3.3 : DAFTAR DAN KUANTITAS HARGA (BOQ)
BILL NO 1 : PREPARATORY WORK & BUILDING GIS 150 KV NEW CIKUPA
GIS 150 KV NEW CIKUPA
I Preparatory work for Control Building GIS and Site Outdoor Equipment
1 Site Clearing & Grubbing m2 7,500.00 16,000 120,000,000
2 Setting survey & topografi Ls 1.00 Exclude
3 Bowplank m 700.00 48,840 34,188,000
4 Site Office (4m x 5m) m2 20.00 1,228,219 24,564,378
5 Site Storage (4m x 10m) m2 40.00 799,950 31,998,000
6 Soil Investigation for control building and out door equipment :
- Sondir pcs 6.00 Exclude
- Boring and Test Lab (nilai: C,Ø and ɣ ) pcs 4.00 Exclude
- Soil Investigation Report (Sondir & Boring) pcs 3.00 Exclude
7 Design (calculation, detail design and drawing must be economical design) Ls 1.00 Exclude
8 Exit permit, IMB and coordination to instansion Pemda Ls 1.00 Exclude
-
II Control Building For GIS 150 kV -
1 Foundation Building , Basement Work : -
- Excavation of soil (for Pile cap,Tie beam/Sloof and Basement) m3 3,000.00 82,575 247,725,000
- Compacted backfill m3 300.00 36,410 10,923,000
- Compacted sand layer for foundation basement, t : 10 cm m3 144.00 567,900 81,777,600
- Lean Concrete K 125 for Basement & Fondation, t : 10 cm m3 144.00 1,190,655 171,454,320
- Stone Masonry 1 pc : 3 sand m3 103.00 939,940 96,813,820
- Prestressed Spun Pile Ø 60 cm K 600 (Installation with Hydraulic Static Pile Driver) m' 4,320.00 898,440 3,881,260,800
- Pilecap Foundation work (concrete K 225, Fe : 200 kg/m3, formwork) m3 435.00 1,350,274 587,369,383
- Tie Beam/Sloof work (concrete K 225, Fe : 200 kg/m3, formwork) m3 27.00 1,350,274 36,457,410
- Slabs Basement Floor work (concrete K 225, Fe : 150 kg/m3, formwork) m3 223.00 1,190,655 265,516,065
- Basement Wall work (concrete K 225, Fe : 150 kg/m3, formwork) m3 93.00 1,350,274 125,575,523
- Loading Test (compress & uplift) Ls 1.00 -
-
2 Structure Building Work :
- Column work (concrete K 225, Fe : 200 kg/m3, formwork) m3 558.00 1,350,274 753,453,140
- Balk work (concrete K 225, Fe : 200 kg/m3, formwork) m3 27.00 1,350,274 36,457,410
- Slab Floor Work (concrete K 225, Fe : 200 kg/m3, formwork) m3 232.00 1,190,655 276,231,960
- Stair work (concrete K 225, Fe : 150 kg/m3, formwork) m3 12.00 1,350,274 16,203,293
- Column, sloof and ring balk practical work (concrete K 225, Fe :100 kg/m3, formwork) m3 8.00 1,350,274 10,802,196
- Steel Structure WF for entrance stair, complete with connection and accessories kg 9,580.00 21,710 207,981,800
- Checker plate/plat bordess, t = 6 mm kg 1,100.00 15,000 16,500,000
- Hand rail for stairs (Stainless Steel) complete with connection and accesories m' 139.00 1,394,907 193,892,092
- Canopy (concrete K 225, Fe : 150 kg/m3, formwork) m3 25.00 1,350,274 33,756,861
-
3 Roof Work : -
- Steel Structure WF Complete with bolt, plat and connection kg 27,000.00 21,710 586,170,000
- Wind bracing & Tie Rod kg 14,400.00 21,710 312,624,000
- Metal Roof complete Nock with Accessories and connection m2 1,800.00 68,000 122,400,000
- Thermal insulation t=10mm (ram,alumuniumfoil,glasswool,alumiuimfoil,ram) m2 2,000.00 49,000 98,000,000
- Listplank m2 360.00 70,000 25,200,000
- Talang Air m' 200.00 190,000 38,000,000
- Vertical Pipe dia 3" inc clamp,fitting,socket,knee etc sets 50.00 160,000 8,000,000
-
4 Floor Work : -
- Floor Concrete K 125 thickness 12 cm around building GIS m2 137.00 1,190,655 163,119,735
- Ceramic Tile 40 x 40 cm m2 404.00 257,390 103,985,560
- Ceramic Tile 20 x 20 cm m2 49.00 176,740 8,660,260
- Floor Hardener for MV Cell 20 KV and GIS 150 kV m2 1,086.00 51,430 55,852,980
- Raised floor m2 384.00 36,700 14,092,800
- Stepnosing m' 55.00 19,284 1,060,620
-
5 Wall Work : -
- A half brick wall 1pc : 3 sand m2 309.00 115,524 35,696,762
- Plastering & finishing cement wall work 1pc : 3sand, t = 15 mm m2 619.00 78,605 48,656,495
- Ceramic for wall 25 x 20 cm m2 46.00 241,810 11,123,260
- Plint Ceramic m' 182.00 20,963 3,815,310
-
R. Basement
- Downlight fitting inculding installation, wiring , switch and Led 9 watt sets 96.00 210,000 20,160,000
- Spotlight including installation, wiring , switch and Led 30 watt sets 8.00 210,000 1,680,000
- Stop contact including installation, and wiring sets 14.00 165,000 2,310,000
- Emergency lighting including installation, wiring and lamp 30 watt sets 8.00 210,000 1,680,000
- SP including installation, fuse, switch, MCB, wiring pipe indicator lamp and grounding system set 1.00 450,000 450,000
15 Fire Alarm :
1. Alarm bell 6" (150 mm) diameter, break glass & red lamp including installation, and wiring sets 5.00 628,696 3,143,482
2. Smoke detector including installation, and wiring sets 42.00 3,002,042 126,085,755
3. Fixed and rate of rise temperature detector including installation, and wiring sets 42.00 861,544 36,184,866
4. MCFA (Master Control Fire Almr) including indication lamp, battery rectifier and all accessories set 1.00 17,420,000 17,420,000
17 Crane :
- Traveling crane complete with mechanical for crane and accessories
set 1.00 84,000,000 84,000,000
(Steel beam ,roller and installation electrical) capacity 5 ton
I Site Works
1 Plank name GIS & Project Ls 1.00 0
2 Imported Soil Fill include compaction per layer 20cm m3 1,248.00 268,910 335,599,680
3 Road works : 0
- Compacted Onderlaag, Penetration, Sandgravel, Screening, Finishing
m 2
1,600.00 747,430 1,195,888,787
Hotmix
4 Kerb/kansteen 40x25x15 (concrete) m' 600.00 133,291 79,974,495
5 Gate and Fence : 0
- Fence BRC 1.5 m height for trafo 60 MVA & PS, include foundation
m' 88.00 949,203 83,529,861
(concrete K 225, Fe : 50 kg/m3)
- Single Gate BRC 1.5 m height for trafo 60 MVA & PS sets 6.00 460,000 2,760,000
II Steel Structure
1 Galvanized Steel Structure Gantry 150 kV kg 34,150.00 Exclude
2 Galvanized Steel Structure Water Torrent kg 2,150.00 Exclude
III Foundation
1 Post Gantry TW 1 Units 9.00 43,685,862 393,172,754
2 Lightning Arrester Units 24.00 6,761,141 162,267,384
3 Sealingend Units 24.00 6,569,714 157,673,146
4 Transformer 60 MVA Units 1.00 73,996,550 73,996,550
5 Neutral Grounding Resistor Units 2.00 4,652,975 9,305,949
6 Steel structure galvanized support 20 kV kg 700.00 Exclude
7 Transformer PS Units 2.00 13,360,076 26,720,152
8 Entrance stair Set 1.00 5,946,284 5,946,284
I Miscellaneous Works
1 Building Works
- Cable tray for Power cable m 40.00 446,240 17,849,600
- Cable tray for cable control m 40.00 379,280 15,171,200
2 Concrete Works
- Concrete K 225 m3 25.00 1,350,274 33,756,861
- Concrete K 300 m3 50.00 1,404,054 70,202,722
3 Stone masonry 1 pc : 3 ps m3 50.00 939,940 46,997,000
4 Reinforcement Work
- Reinforcement steel work U-24 (BJTP) kg 650.00 11,689 7,597,850
- Reinforcement steel work U-39 (BJTD) kg 2,500.00 11,689 29,222,500
5 Excavation Work
- Excavation of Soil m3 20.00 82,575 1,651,500
6 Filling Work
- Import Soil Fill (include compaction in layer of 20 cm) m3 40.00 268,910 10,756,400
7 Steel structures kg 1,500.00 21,710 32,565,000
8 Bore Pile Ø 60 cm m' 200.00 1,078,185 215,637,000
1 2 3 4 5 6=4x5
1 1 (one) m Bouwplank
- Material :
- Kayu Kelas III 2/20 m3 0.007 1,850,000 12,950
- Kayu Kelas III 5/7 m3 0.007 1,850,000 12,950
- Nail kg 0.020 17,000 340
- Remuneration :
- Carpenter man/day 0.100 85,000 8,500
- Worker man/day 0.100 120,000 12,000
- Worker Chief man/day 0.010 135,000 1,350
- Supervisor man/day 0.005 150,000 750
48,840
2 1 m2 Site Office
- Material :
- Kayu Kelas III m3 0.210 1,850,000 388,500
- Nail kg 0.200 17,000 3,400
- Strip plate kg 1.100 16,000 17,600
- Portland cement kg 5.000 1,050 5,250
- Sand m3 0.200 308,000 61,600
- Split m3 0.150 286,000 42,900
- Red Brick bh 30.000 700 21,000
- Asbes roof sheet 1.200 65,000 78,000
- Window & Door set 0.042 116,400 4,854
- Glass 5 mm m2 0.080 60,500 4,840
- Door lock and hinge bh 0.150 60,500 9,075
- Plywood lbr 0.060 220,000 13,200
- Remuneration : -
- Woker man/day 2.000 85,000 170,000
- Carpenter man/day 2.000 120,000 240,000
- Brick Layer man/day 1.000 120,000 120,000
- Worker chief man/day 0.300 135,000 40,500
- Supervisor man/day 0.050 150,000 7,500
1,228,219
3 1 m2 Site storage
- Material :
- Kayu Kelas III m3 0.180 1,850,000 333,000
- Nail kg 0.300 17,000 5,100
- Portland cement kg 5.000 1,050 5,250
- Sand m3 0.100 308,000 30,800
- Split m3 0.050 286,000 14,300
- Asbes roof lbr 0.800 65,000 52,000
- Renumeration :
- Woker man/day 1.000 85,000 85,000
- Carpenter man/day 2.000 120,000 240,000
- Worker chief man/day 0.200 135,000 27,000
- Supervisor man/day 0.050 150,000 7,500
1 2 3 4 5 6=4x5
799,950
5 1 m3 Excavation of Soil
- Remuneration :
- Worker man/day 0.900 85,000 76,500
- Supervisor man/day 0.045 135,000 6,075
82,575
7 1 m3 Soil Disposal
- Equipment :
- Hoe unit 0.010 450,000 4,500
- Pick Up hour 0.400 250,000 100,000
- Remuneration : -
- Worker man/day 0.330 85,000 28,050
- Supervisor man/day 0.010 135,000 1,350
133,900
1 2 3 4 5 6=4x5
- Supervisor man/day 0.060 135,000 8,100
567,900
1 m2 Compacted Sand layer (tebal 10 cm) 56,790
10 1 m3 Compacted Gravel
- Material :
- Gravel m3 1.000 286,000 286,000
- Equipment : -
- Stamper hour 0.500 350,000 175,000
- Remuneration : -
- Worker man/day 0.500 85,000 42,500
- Supervisor man/day 0.010 135,000 1,350
504,850
1 m2 Compacted Gravel (tebal 20 Cm) 100,970
1 m2 Compacted Gravel (tebal 25 Cm) 126,213
11 1 m2 Half Brick 1 pc : 3 ps
- Material :
- Red brick unit 70.000 700 49,000
- Portland cement (PC) kg 14.370 1,050 15,089
- Sand m3 0.040 264,000 10,560
- Remuneration : -
- Brick layer man/day 0.100 120,000 12,000
- Worker man/day 0.300 85,000 25,500
- Supervisor man/day 0.015 135,000 2,025
- Worker Chief man/day 0.010 135,000 1,350
115,524
13 1 m2 Acian
- Material :
- Portland cement (PC) kg 3.250 1,450 4,713
- Remuneration : -
- Brick layer man/day 0.100 120,000 12,000
- Worker man/day 0.200 85,000 17,000
- Supervisor man/day 0.010 135,000 1,350
- Worker Chief man/day 0.010 135,000 1,350
36,413
1 2 3 4 5 6=4x5
14 1 m Lean Concrete (K125)
3
- Material :
- Portland cement (PC) kg 240.000 1,050 252,000
- Sand m3 0.600 308,000 184,800
- Split m 3
0.570 260,000 148,200
- Equipment : -
- Mollen hour 0.250 400,000 100,000
- Concrete Vibrator hour 1.000 350,000 350,000
- Remuneration : -
- Brick layer man/day 0.189 120,000 22,680
- Worker man/day 1.323 85,000 112,455
- Supervisor man/day 0.132 135,000 17,820
- Worker chief man/day 0.020 135,000 2,700
1,190,655
per m2 , t = 10 cm 119,066
1 2 3 4 5 6=4x5
- Portland cement (PC) kg 202.000 1,050 212,100
- Sand m3 0.485 264,000 128,040
- Remuneration : -
- Brick layer man/day 0.750 120,000 90,000
- Worker man/day 1.500 85,000 127,500
- Supervisor man/day 0.075 135,000 10,125
- Worker chief man/day 0.075 135,000 10,125
- Equipment : -
- Molen Machine hour 0.167 350,000 58,450
939,940
1 2 3 4 5 6=4x5
21 100 kg steel work U 39 or BJTD:
- Material :
- Steel Bar (Reinforcement) U 39 or BJTD kg 105.000 9,300 976,500
- Concrete wire kg 1.500 20,000 30,000
- Remuneration : -
- Steel worker man/day 0.700 120,000 84,000
- Worker man/day 0.700 85,000 59,500
- Supervisor man/day 0.040 135,000 5,400
- Worker chief man/day 0.100 135,000 13,500
1,168,900
Per kg 11,689
1 2 3 4 5 6=4x5
- Tremie Pipa hour 0.200 400,000 80,000
- Mollen hour 0.200 400,000 80,000
- Total Station hour 0.200 150,000 30,000
- Support Equipment : hour 0.200 150,000 30,000
- Mobilisasi alat (per meter pile) ls 1.000 150,000 150,000
- Remuneration : -
- Worker man/day 0.100 85,000 8,500
- Supervisor man/day 0.010 135,000 1,350
- Operator man/day 0.100 175,000 17,500
- Mechanic man/day 0.025 175,000 4,375
- Surveyor man/day 0.020 135,000 2,700
1,078,185
1 2 3 4 5 6=4x5
- Welder man/day 0.200 120,000 24,000
- Supervisor man/day 0.020 135,000 2,700
446,240
1 2 3 4 5 6=4x5
- Reinforced steel plain U24 kg 19.200 9,300 178,560
- Formwork m2 2.200 128,435 282,557
- Galvanis Steel Rack kg 3.200 9,300 29,760
- Dynabolt 10 mm pcs 2.000 2,500 5,000
797,109
35 1 m2 Steel painting
- Material :
- Naturally Meni kg 0.167 90,000 15,030
- Paint steel kg 0.283 19,700 5,575
- Kuas/rol bh 0.050 10,000 500
- Thinner Liter 0.150 28,000 4,200
- Amplas besi sheet 0.400 6,000 2,400
- Remuneration : -
- Worker Paint man/day 0.300 120,000 36,000
- Worker man/day 0.200 85,000 17,000
- Supervisor man/day 0.100 135,000 13,500
- Worker chief man/day 0.030 135,000 4,050
98,255
1 2 3 4 5 6=4x5
- Kuas/rol bh 0.010 25,000 250
- Amplas sheet 0.500 6,000 3,000
- Remuneration : -
- Worker Paint man/day 0.280 120,000 33,600
- Worker man/day 0.160 85,000 13,600
- Supervisor man/day 0.010 135,000 1,350
- Worker chief man/day 0.030 135,000 4,050
74,001
38 1 m2 Waterproofing
- Material
- Waterproofing kg 0.500 20,000 10,000
- Serat Fiber m2 1.000 23,650 23,650
- Remuneration -
- Worker man/day 0.160 85,000 13,600
- Supervisor man/day 0.010 135,000 1,350
48,600
1 2 3 4 5 6=4x5
41 1 m' Fence BRC 1.5 m height
- Excavation of soil m3 0.200 82,575 16,515
- Back Filling m3 0.680 68,135 46,332
- Sand layer t = 0.05 m m3 0.026 308,000 8,008
- Lean Concrete K125 t = 0,05 m m 3
0.026 1,190,655 30,957
- Concrete K-225 m3 0.160 740,000 118,400
- Reinforced steel plain U24 kg 9.600 9,300 89,280
- Formwork m2 0.880 128,435 113,023
- Galvanized Steel pipe dia 2'' inc and clamp m' 1.130 111,833 126,372
- BRC 1,5 m height include instalation m' 1.100 254,833 280,317
- Steel Worker man/day 1.000 120,000 120,000
949,203
1 2 3 4 5 6=4x5
176,740
48 1 m2 Floorhardener
- Material
- Floorhardener kg 5.000 7,760 38,800
- Remuneration -
- Worker man/day 0.120 85,000 10,200
- Supervisor man/day 0.006 135,000 810
- Worker Chief man/day 0.012 135,000 1,620
51,430
1 2 3 4 5 6=4x5
49 1 m2 Raised Floor
- Material
- Raised Floor m2 1.000 -
-Remuneration -
-Worker man/day 0.400 85,000 34,000
-Supervisor man/day 0.020 135,000 2,700
36,700
1 2 3 4 5 6=4x5
54 1 m' Open Drainage (brick) 30/40 cm
- Material :
- Excavation of soil m3 0.351 82,575 28,984
- Back Filling m3 0.105 68,135 7,175
- Sand layer m3
0.060 308,000 18,480
- Plaster cement 1:3 m2 1.100 78,605 86,466
- Acian m2 1.100 36,413 40,054
- Brick 1 pc : 3 ps m2 1.400 939,940 1,315,916
1,497,074
1 2 3 4 5 6=4x5
- Supervisor man/day 0.160 135,000 21,600
- Worker chief man/day 0.010 135,000 1,350
3,201,450
1 2 3 4 5 6=4x5
110,375
1 2 3 4 5 6=4x5
- Galvanized steel angle kg 32.000 14,000 448,000
43,890,740
1 2 3 4 5 6=4x5
- Sand layer m3
0.324 308,000 99,792
- Lean Concrete m3 0.162 1,190,655 192,886
- Concrete K-225 m3 2.400 750,000 1,800,000
- Reinforced steel screw U39 kg 192.000 9,300 1,785,600
- Reinforced steel plain U24 kg 72.000 9,300 669,600
- Formwork m2 9.600 128,435 1,232,976
- Galvanized Steel pipe Ø 2" for earthing cable m' 0.700 111,879 78,315
- PVC Ø 4" for cable trench m' 1.500 81,025 121,538
- Anchor bolt Ø 22 mm pcs 4.000 30,000 120,000
6,569,714
1 2 3 4 5 6=4x5
- Excavation of Soil m 3
3.520 82,575 290,664
- Back Filling m3 1.056 68,135 71,951
- Sand layer m3 0.196 308,000 60,368
- Lean Concrete m3 0.098 1,190,655 116,684
- Concrete K-225 m3 1.440 750,000 1,080,000
- Reinforced steel screw U39 kg 86.400 9,300 803,520
- Reinforced steel plain U24 kg 57.600 9,300 535,680
- Formwork m2 4.800 128,435 616,488
- Anchor bolt pcs 4.000 30,000 120,000
3,695,355
1 2 3 4 5 6=4x5
1 2 3 4 5 6=4x5
- Worker man/day 0.142 -
- Supervisor man/day 0.014 -
Mobilization, -
- Soil compacted for base road m2 1.000 -
-
Per m2 747,430
I MATERIAL :
1 Portland Cemen (PC)
2 Colour Cement
3 Red brick
4 Batu Belah 20-30 cm
5 Split
6 Gravel
7 Sangravel (Sirtu)
8 Sand
9 Soil Imported (tanah urug)
10 BBM / solar
11 Plain reinforced steel U 24 - BJTP
12 Sceew reinforced steel U 39 - BJTD
13 Galvanized steel angle HTS
14 Galvanized steel angle MS
15 Galvanized Steel Plate
16 Galvanis Bolt and Nuts
17 Paint of steel
18 Paint of wooden
19 Paint of wall (Interior)
20 Paint of wall Weathershield (eksterior)
21 Thinner
22 Kuas / Rol
23 Plamur of wall
24 Amplas Besi
25 Amplas Kayu
26 Door closer
27 Hinge/Engsel for door (1 set= 3 pcs)
28 Hinge/Engsel for window (1 set= 2 pcs)
29 Door lock
30 Door
31 Grendel for window (1 set= 2 pcs)
32 Wind hook of window (1 set = 2 pcs)
33 Palm fibre
34 Concrete wire
35 Wire mesh M4
36 Wire mesh M6
37 Wire mesh M8
38 Barbed wire
39 Kayu Kelas I
40 Kayu Kelas II
41 Kayu Kelas III
42 Dolken dia. 6-8 cm, panjang 4 m
43 Floor tile ceramic 200 x 200 mm
44 Ceramic floor tiles 300 x 300 mm
45 Wall tile ceramic 200 x 250 mm
46 Floor tile ceramic 300 x 300 mm
47 Plint tiles 150 x 300 mm
48 Stepnosing 100 x 300 mm
49 Glass 5 mm
50 Naturally paint (Meni)
51 Minyak bekisting
52 Fence BRC height 1,90 m
II REMUNERATION
1 Worker
2 Surveyor
3 Supervisor
4 Operator
5 Brick Layer
6 Steel worker/welder
7 Carpenter
8 Paint worker
9 Instalator
10 Mechanic
11 Asphalt worker
12 Worker Chief
13 Engineer
kg 46,200
kg 13,000
unit 715
m 3
253,000
m 3
286,000
m 3
m3
m3
m3
litre
kg 9,300
kg 9,300
kg
kg
kg
bh
kg
kg
kg
kg
litre
bh
kg
sheet
sheet
unit 709,000
set
set
set
set
set
set
kg
kg
lembar
lembar 379,500
lembar 693,000
m
m2
m2
m2
no
no
m2
kg
litre
m'
kg
m2
m'
m'
bh
ltr
ltr
m2
m2
bh
unit 20,064,206.34
unit 14,321,312.59
unit 1,074,895.23
unit 1,592,335.23
unit 978,337.73
unit 1,277,020.23
m'
m2
m2
m2
set 26,306
set 176,653
set 28,710,000
set 230,000,000
set 14,950,000
set 113,074,000
unit 9,878,700
unit 628,696
unit 3,002,042
unit 861,544
unit 17,420,000
No 1,924,300
No 7,170,800
set
set
set
set
set
man/day
man/day
man/day
man/day
man/day
man/day
man/day
man/day
man/day
man/day
man/day
man/day
man/day
hour
hour
hour
hour
hour
hour
hour
pcs
hour
ls
hour
hour
bh
unit/day
hour
hour
unit/day
hour
unit/day
unit/day
Ls
Sampel
NO. Kebutuha
PEKERJAAN PERSIAPAN
1 1 m² Pekerjaan Pembersihan Lahan
TENAGA KERJA
1 Pekerja
2 Mandor
Bahan:
1
2
Tenaga Kerja:
1
2
3
4
Bahan:
1
2
Tenaga Kerja:
1
2
3
4
Bahan:
1
2
3
4
5
6
Tenaga Kerja:
1
2
3
4
Bahan:
1
2
3
4
5
6
Tenaga Kerja:
1
2
3
4
PEKERJAAN ARSITEKTUR
1 1 m² Memasang dinding bata merah 1/2 bata 1PC:
PERMEN PU 28/PRT/M/2016
Bahan:
1
2
3
Tenaga Kerja:
1
2
3
4
32 1 m² Memasang Wallpapper
Bahan:
1
2
Upah Pasang
PEKERJAAN PLAFOND
1 1 m² Pemasangan plafond gypsum tbl. 9 mm
PERMEN PU 28/PRT/M/2016
Bahan:
1
2
PEKERJAAN SANITARY
1 1 bh Pemasangan kloset duduk lengkap dengan ak
Bahan:
1
2
Tenaga Kerja:
1
2
3
4
10 1 bh Partisi urinoir
Bahan:
1
Upah Pasang dan Material Bantu
11 1 bh Soap holder
Bahan:
1
Upah Pasang dan Material Bantu
12 1 bh Soap desh
Bahan:
1
Upah Pasang dan Material Bantu
13 1 bh Tisue holder
Bahan:
1
Upah Pasang dan Material Bantu
14 1 bh Towel bar
Bahan:
1
Upah Pasang dan Material Bantu
15 1 bh Hand dryer
Bahan:
1
Upah Pasang dan Material Bantu
PEKERJAAN PENGECATAN
1 1 m2 Pengecatan dinding emultion paint
Bahan:
1
2
3
Tenaga Kerja:
1
2
3
4
6 1 m² Pengecatan Duco
PERMEN PU 28/PRT/M/2016
Bahan:
1
2
3
4
5
6
Tenaga Kerja:
1
2
3
4
8 1 m² Pemasangan Kaca Es t = 8 mm
Bahan:
1
2
Tenaga Kerja:
1
2
3
4
Kebutuhan Satuan
RSIAPAN
Pekerjaan Pembersihan Lahan
TENAGA KERJA
Pekerja oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Pengukuran dan pemasangan bowplank
PERMEN PU 28/PRT/M/2016
Kayu 5/7 m³
Paku biasa kg
Kayu papan 3/20 m³
Tenaga Kerja:
Pekerja oh
Tukang kayu oh
Kepala tukang oh
Mandor oh
Total = Jumlah+(Keun
Sewa Pagar sementara dari seng gelombang tinggi 2 meter
Total = Jumlah+(Keun
Pekerjaan Sewa Direksi keet
Dolken btg
Kayu m³
Paku biasa kg
Besi strip kg
semen kg
Pasir pasang m³
Pasir beton m³
Koral beton m³
Bata merah bh
Seng plat lbr
Jendela nako bh
Kaca polos m²
Kunci tanam bh
Plywood 4 mm lbr
Tenaga Kerja:
Pekerja oh
Tukang kayu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Sewa Tower Crane
Sewa Harga Tower Crane bln
Mobilisasi dan demobilisasi Tower Crane ls
Ongkos Operator ls
Asuransi Alat ls
Jumlah ha
Total = Jumlah+(Keun
Total = Jumlah+(Keun
Mengali tanah biasa sedalam 2 meter
PERMEN PU 28/PRT/M/2016
Tenaga Kerja:
Pekerja oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Mengali tanah biasa sedalam 3 meter
PERMEN PU 28/PRT/M/2016
Tenaga Kerja:
Pekerja oh
Mandor oh
escavator jam
dump truck ham
Jumlah ha
Total = Jumlah+(Keun
Mengurug kembali galian
PERMEN PU 28/PRT/M/2016
Tenaga Kerja:
Pekerja oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Memadatkan tanah (per 20 cm)
PERMEN PU 28/PRT/M/2016
Tenaga Kerja:
Pekerja oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Mengurug tanah untuk peninggian lantai bangunan
Dumbtruk jam
Tanah Urug m³
Tenaga Kerja:
Pekerja oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Base Course (Lapisan Agregat Kelas A)
Aggregat Kasar m³
Aggregat halus m³
PERALATAN
Wheel Loader jam
Dump truck jam
Motor Grader jam
Total = Jumlah+(Keun
Sub Base Course (Lapisan Agregat Kelas B)
Aggregat Kasar m³
Aggregat halus m³
PERALATAN
Wheel Loader jam
Dump truck jam
Motor Grader jam
Vibrator Roller jam
Pneumatic Tire Roller jam
Water Tanker jam
TENAGA KERJA
Pekerja jam
Mandor jam
Jumlah ha
Total = Jumlah+(Keun
Pek. Lapisan Resap Pengikat Aspal
Aspal kg
Kerosene ltr
Tenaga Kerja:
Pekerja oh
Mandor oh
Peralatan :
Asphalt Spray jam
Compressor jam
Dump truck 3-4 ton jam
Jumlah ha
Total = Jumlah+(Keun
Pek. Lapisan Permukaan Asphal
Aspal kg
Agregat Kasar m³
Agregat Halus m³
Tenaga Kerja:
Pekerja oh
Mandor oh
Peralatan :
Total = Jumlah+(Keun
Pasangan Kanstein Beton uk. 60/30/15 cm
PERMEN PU 28/PRT/M/2016
Galian Tanah m3
Urugan Pasir m3
Batu Kanstein 10.20 cm bh
Urugan Kembali + Pemadatan m3
Upah Pasang m'
Jumlah ha
Total = Jumlah+(Keun
Membuang Tanah Keluar Site
Dumptruk jam
Alat Bantu ls
Tenaga Kerja:
Pekerja oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Membuang Tanah di Dalam Site Proyek
Dumptruk jam
Alat Bantu ls
Tenaga Kerja:
Pekerja oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Memasang cerucuk dolken kayu 8-10cm/@4m
Err:509 btg
Tenaga Kerja:
Pekerja oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Mengurug pasir urug
PERMEN PU 28/PRT/M/2016
Pasir Urug m³
Tenaga Kerja:
Pekerja oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Memasang Lantai Kerja
PERMEN PU 28/PRT/M/2016
Semen kg
Pasir beton m³
Batu Split 1/2 m³
Air ltr
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Membuat Beton mutu K 175 ,slump ( 12 + 2) cm
PERMEN PU 28/PRT/M/2016
Semen kg
Pasir beton m³
Batu Split 1/2 m³
Air ltr
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Memasang pondasi batu belah campuran 1 PC : 4 PP
PERMEN PU 28/PRT/M/2016
Batu belah bh
Semen kg
Pasir pasang m³
Tenaga Kerja:
Total = Jumlah+(Keun
Memasang besi beton U-24
Jumlah ha
Total = Jumlah+(Keun
Memasang besi beton U-39
Jumlah ha
Total = Jumlah+(Keun
Memasang besi kontruksi
Pipa besi,IWF kg
Sewa Alat jam
Tenaga Kerja:
Pekerja oh
Tukang besi oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Memasang bekisting untuk kolom (2 X Pakai)
Total = Jumlah+(Keun
Memasang bekisting untuk balok (2 X Pakai)
Total = Jumlah+(Keun
Memasang bekisting untuk dinding (2 X Pakai)
Total = Jumlah+(Keun
Total = Jumlah+(Keun
Memasang bekisting untuk tangga
Total = Jumlah+(Keun
Beton Ready mix K 300
Analisa berdasarkan Analisa Lapangan
Total = Jumlah+(Keun
Beton Ready mix K 250
Analisa berdasarkan Analisa Lapangan
Total = Jumlah+(Keun
Memasang Begisting Batako
Batako bh
Semen kg
Pasir pasang m³
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Membuat Screed Beton + kawat ayam
PERMEN PU 28/PRT/M/2016
Semen kg
Pasir pasang m³
Kawat ayam m2
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
AN ARSITEKTUR
Memasang dinding bata merah 1/2 bata 1PC:3PP
PERMEN PU 28/PRT/M/2016
Bata merah bh
Semen kg
Pasir pasang m³
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Total = Jumlah+(Keun
Memasang dinding bata merah 1/2 bata 1PC:5PP
PERMEN PU 28/PRT/M/2016
Bata merah bh
Semen kg
Pasir pasang m³
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Membuat plesteran 1 PC: 3 PP, tebal. 15 mm
PERMEN PU 28/PRT/M/2016
Semen kg
Pasir pasang m³
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Membuat plesteran 1 PC: 4 PP, tebal. 15 mm
PERMEN PU 28/PRT/M/2016
Semen kg
Pasir pasang m³
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Membuat plesteran 1 PC: 5 PP, tebal. 15 mm
PERMEN PU 28/PRT/M/2016
Semen kg
Pasir pasang m³
Total = Jumlah+(Keun
Membuat acian semen
PERMEN PU 28/PRT/M/2016
Semen kg
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Memasang dinding partisi gypsum board tbl. 12 mm
Total = Jumlah+(Keun
Memasang dinding bata ringan 200 x 600 x 100
Total = Jumlah+(Keun
Membuat plesteran semen instan
Total = Jumlah+(Keun
Membuat acian semen instan
Total = Jumlah+(Keun
Pek. Opening Pintu dan Jendela semen instan
Semen kg
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Membuat benang sudut
Semen kg
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Pek. Opening Pintu dan Jendela semen biasa
Total = Jumlah+(Keun
Memasang balok praktis 10/15 cm
Beton mutu K 175 ,slump ( 12 + 2) cm m³
Besi 4d8, d6-150 kg
Memasang bekisting untuk balok 4 kali pakai m²
Jumlah ha
Total = Jumlah+(Keun
Memasang balok 25/15 cm
Beton mutu K 175 ,slump ( 12 + 2) cm m³
Besi 6d10, sengkang d8-200 mm kg
Memasang bekisting untuk balok 4 kali pakai m²
Jumlah ha
Total = Jumlah+(Keun
Memasang balok 15/20 cm
Beton mutu K 175 ,slump ( 12 + 2) cm m³
Besi 6d10, sengkang d8-200 mm kg
Memasang bekisting untuk balok 4 kali pakai m²
Jumlah ha
Total = Jumlah+(Keun
Memasang meja beton tebal 10 cm
Beton mutu K 175 ,slump ( 12 + 2) cm m³
Besi U 24 (d8-150) kg
Memasang bekisting untuk plat lantai 2 kali pakai m²
Jumlah ha
Total = Jumlah+(Keun
Memasang beton plat canopy tebal 10 cm
Beton mutu K 175 ,slump ( 12 + 2) cm m³
Besi U 24 (d8-150) kg
Memasang bekisting untuk plat lantai 2 kali pakai m²
Jumlah ha
Total = Jumlah+(Keun
Memasang dinding keramik 30 x 30 cm
PERMEN PU 28/PRT/M/2016
Keramik uk. 30 x 30 cm bh
Semen kg
Pasir pasang m³
Semen warna kg
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Memasang dinding border homogenius tile 30 x 30 cm
PERMEN PU 28/PRT/M/2016
Total = Jumlah+(Keun
Memasang dinding homogenous tile 30 x 60 cm
homogenius tile 30 x 60 cm bh
Semen kg
Pasir pasang m³
Semen warna kg
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Total = Jumlah+(Keun
Memasang dinding border homogenous tile 30 x 60 cm
Total = Jumlah+(Keun
Memasang plint keramik 10 x 30 cm
Keramik uk. 10 x 30 cm bh
Semen kg
Pasir pasang m³
Semen warna kg
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Memasang homogenius tile 10 x 60 cm cutting size
Total = Jumlah+(Keun
Memasang hospital plint
Non Standar
Hospital plint/skriting bh
Semen kg
Pasir pasang m³
Semen warna kg
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Memasang batu goa fabrikan uk. 20 x 20 cm
Total = Jumlah+(Keun
Memasang dinding batu marmer
batu marmer m²
Semen kg
Semen warna kg
Pasir pasang m³
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Memasang dinding batu granit
Total = Jumlah+(Keun
Memasang Clading Multipleks lapis HPL rangka hollow
Total = Jumlah+(Keun
Memasang Wallpapper
Wallpapper m²
Lem/adhesive ltr
Upah Pasang m²
Jumlah ha
Total = Jumlah+(Keun
Memasang Plint Vinyl curve shape v.s base/ skirting
Non Standar
Vinyl Sheet m¹
Lem/adhesive ltr
Upah Pasang dan Material Bantu m²
Jumlah ha
Total = Jumlah+(Keun
Pengadaan dan pemasangan Signate Stainless steel tebal 0,6 mm
lengkap dengan rangka/ perkuatan dan alat bantu
Total = Jumlah+(Keun
Pengadaan dan pemasangan Lambang Stainless steel tebal 0,6 mm
lengkap dengan rangka/ perkuatan dan alat bantu
Total = Jumlah+(Keun
Memasang Alumunium Composite Panel (ACP), PVDF 0,30 mm alloy 3003
Total = Jumlah+(Keun
Pek. Ornamen GRC Motif Khas Bogor
Total = Jumlah+(Keun
Pemasangan Hospital dan Curtain Rail
Total = Jumlah+(Keun
Pemasangan Roller Blinds Chain System
Sun Control m²
Ongkos Pasang Rail, Jahit Kain, dan Bending m²
Jumlah harg
Total = Jumlah+(Keun
Pemasangan Papan Kayu tebal 5cm lebar 30cm
Total = Jumlah+(Keun
AN PELAPIS LANTAI
Memasang lantai keramik 30 x 30 cm
PERMEN PU 28/PRT/M/2016
Keramik uk. 30 x 30 cm bh
Semen kg
Pasir pasang m³
Semen warna kg
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Memasang lantai homogenius tile 30 x 30 cm (Unpolished)
PERMEN PU 28/PRT/M/2016
Total = Jumlah+(Keun
Memasang lantai homogenius tile 60 x 60 cm (Polished)
PERMEN PU 28/PRT/M/2016
Total = Jumlah+(Keun
Memasang lantai homogenius tile 60 x 60 cm (UnPolished)
PERMEN PU 28/PRT/M/2016
Total = Jumlah+(Keun
Memasang homogenius tile 20 x 60 cm (cutting size)
Total = Jumlah+(Keun
Memasang floor hardener
PERMEN PU 28/PRT/M/2016
Total = Jumlah+(Keun
Total = Jumlah+(Keun
Memasang lantai vinyl sheet
Total = Jumlah+(Keun
Memasang batu granite alam
Total = Jumlah+(Keun
AN PLAFOND
Pemasangan plafond gypsum tbl. 9 mm
PERMEN PU 28/PRT/M/2016
Total = Jumlah+(Keun
Pemasangan plafond GRC board 1200 mm x 2400 mm x 6 mm
PERMEN PU 28/PRT/M/2016
Total = Jumlah+(Keun
Pemasangan plafond Metal Ceiling 150 mm tebal 0,4 mm
Total = Jumlah+(Keun
Pemasangan plafond Metal Ceiling 600 x 1200 x 0,6 mm Pervorated
Total = Jumlah+(Keun
Pemasangan plafond Metal Ceiling 600 x 600 x 0,5 mm Pervorated
Total = Jumlah+(Keun
Pemasangan plafond Drop Ceiling Gypsum board 1200 mm x 2400 mm x 9 mm
Total = Jumlah+(Keun
Pemasangan List plafond gypsum, t = 5 cm
Total = Jumlah+(Keun
Memasang Curtain Box Gypsum Board
Total = Jumlah+(Keun
AN SANITARY
Pemasangan kloset duduk lengkap dengan aksesoris
Total = Jumlah+(Keun
Pemasangan kloset jongkok lengkap dengan aksesoris
Kloset Jongkok bh
Semen kg
Pasir pasang m3
Tenaga Kerja:
Pekerja oh
Tukang batu oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Pemasangan wastafel gantung lengkap dengan aksesoris
Total = Jumlah+(Keun
Pemasangan Wastafel Under Counter lengkap dengan aksesoris
Total = Jumlah+(Keun
Pemasangan urinoir lengkap dengan aksesoris
Total = Jumlah+(Keun
Cove ligth wastafel
Total = Jumlah+(Keun
Pemasangan jet washer
Jet washer bh
Total = Jumlah+(Keun
Pemasangan Kran dinding
Kran dinding bh
Upah Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Kran Air Panas Dingin
Total = Jumlah+(Keun
Partisi urinoir
Partisi Urinoir bh
Upah Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Soap holder
Soap holder bh
Upah Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Soap desh
Soap dish bh
Upah Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Tisue holder
Tisue holder bh
Upah Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Towel bar
Total = Jumlah+(Keun
Hand dryer
Hand dryer bh
Upah Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Hand shower lengkap dengan kran dan aksesoris
Total = Jumlah+(Keun
Zink satu lubang lengkap dengan kran dan aksesories
Total = Jumlah+(Keun
Zink dua lubang lengkap dengan kran dan aksesories
Total = Jumlah+(Keun
Pemasangan Spool hok/sloof zink
Total = Jumlah+(Keun
Pemasangan Curtain Rod
Total = Jumlah+(Keun
Pemasangan floor drain
Floor Drain m2
Upah Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
AN PENGECATAN
Pengecatan dinding emultion paint
Plamir (1 x Lapis) kg
Cat dasar (1 x Lapis) kg
Cat penutup (2 x lapis) kg
Tenaga Kerja:
Pekerja oh
Tukang cat oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Pengecatan dinding weathershield paint
Plamir (1 x Lapis) kg
Cat dasar (1 x Lapis) kg
Cat penutup (2 x lapis) kg
Tenaga Kerja:
Pekerja oh
Tukang cat oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Pengecatan dinding dustproof paint
Plamir (1 x Lapis) kg
Cat dasar (1 x Lapis) kg
Cat penutup (2 x lapis) kg
Tenaga Kerja:
Pekerja oh
Tukang cat oh
Kepala tukang oh
Total = Jumlah+(Keun
Pengecatan plafond emultion paint
Plamir (1 x Lapis) kg
Cat dasar (1 x Lapis) kg
Cat penutup (2 x lapis) kg
Tenaga Kerja:
Pekerja oh
Tukang cat oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Pengecatan plafond weathershield paint
Plamir (1 x Lapis) kg
Cat dasar (1 x Lapis) kg
Cat penutup (2 x lapis) kg
Tenaga Kerja:
Pekerja oh
Tukang cat oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Pengecatan Duco
PERMEN PU 28/PRT/M/2016
Dempul kg
Meni Duco kg
Cat Duco kg
Tiner kg
Amplas lbr
Alat Bantu ls
Tenaga Kerja:
Pekerja oh
Tukang cat oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Pekerjaan Cat Marka Jalan
Total = Jumlah+(Keun
Pengecatan plint Int Semi Gloss
Plamir (1 x Lapis) kg
Cat dasar (1 x Lapis) kg
Cat penutup (2 x lapis) kg
Rol cat bh
Amplas lbr
Kape bh
Tenaga Kerja:
Pekerja oh
Tukang cat oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Pengecatan dinding enamel paint (epoxy)
Plamir (1 x Lapis) kg
Cat dasar (1 x Lapis) kg
Cat penutup (2 x lapis) kg
Tenaga Kerja:
Pekerja oh
Tukang cat oh
Kepala tukang oh
Mandor oh
Jumlah ha
Total = Jumlah+(Keun
Pengecatan plafond enamel paint (epoxy)
Plamir (1 x Lapis) kg
Cat dasar (1 x Lapis) kg
Cat penutup (2 x lapis) kg
Tenaga Kerja:
Total = Jumlah+(Keun
AN KUSEN PINTU DAN JENDELA ALLUMUNIUM
Pemasangan alumunium kusen pintu Powder Coating
Kaca Es t = 8 mm m²
Sealent dengan lakban ex. GE/ Wacker non stain atau setara tube
Tenaga Kerja:
Pekerja oh
Tukang oh
Kepala tukang oh
Mandor oh
Jumlah ha
Pemasangan Kaca Stopsol Super Silver Green 8 mm
Total = Jumlah+(Keun
Pemasangan Pintu D2 Uk. 2 x 900 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
Pemasangan alumunium Frame Daun Pintu Powder Coating m²
Total = Jumlah+(Keun
Pemasangan Pintu Tipe COR Uk. 2 x 900 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
-Daun Pintu
Daun Pintu Frame kayu meranti (Core Honeycomb), Skin HDF Lapis HPL (900 x 2150) bh
+ kaca polos 8 mm (700 x 925 mm) Pabrikasi
-Aksesories & Hardware
Lever Handle set
Floor Hinge set
Top Patch bh
Bottom Patch bh
Top Pivot bh
Mortise Lock set
Cylinder set
Kick plate thickness = 2 mm bh
Kunci tanam Flush Bolt FB 040 S/S 8 + 18 SSS set
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Total = Jumlah+(Keun
Pemasangan Pintu tipe D3 Uk. 900 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
-Daun Pintu
Daun Pintu Frame kayu meranti (Core Honeycomb), Skin HDF Lapis HPL uk. 900 x 2150 bh
+ kaca polos 12 mm (700 x 800 mm) Pabrikasi
-Aksesories & Hardware
Lever Handle set
Cylinder set
Mortise Lock set
Engsel pintu bh
Door closer bh
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu tipe DRW Uk. 400 x 800 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
'-Daun Pintu
Daun Pintu Frame kayu meranti (Core Honeycomb), Skin HDF Lapis HPL ( 400 x 800 x 2150 bh
+ kaca polos 8 mm (200 x 700 mm) Pabrikasi
-Aksesories & Hardware
Lever Handle set
Cylinder set
Mortise Lock set
Engsel pintu bh
Door closer bh
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu tipe DRW-1 Uk. 400 x 800 x 2150 (Interlock)
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
'-Daun Pintu
Daun Pintu Frame kayu meranti (Core Honeycomb), Skin HDF Lapis HPL ( 400 x 800 x 2150 bh
+ kaca polos 8 mm (200 x 700 mm) Pabrikasi
-Aksesories & Hardware
Lever Handle set
Cylinder set
Mortise Lock set
Engsel pintu bh
Door closer bh
Interlock set
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu type PAN Uk. 900 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
-Daun Pintu
Daun Pintu Frame kayu meranti (Core Honeycomb), Skin HDF Lapis HPL uk. 900 x 2150 bh
+ kaca polos 12 mm (700 x 800 mm) Pabrikasi
-Aksesories & Hardware
Lever Handle set
Cylinder set
Mortise Lock set
Engsel pintu bh
Door closer bh
Door closer bh
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu tipe GUD Uk. 900 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
-Daun Pintu
Daun Pintu Frame kayu meranti (Core Honeycomb), Skin HDF Lapis HPL (900 x 2150) bh
-Aksesories & Hardware
Lever Handle set
Cylinder set
Mortise Lock set
Engsel pintu bh
Door closer bh
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu tipe LIN Uk. 700 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
Pemasangan alumunium Frame Daun Pintu Powder Coating m²
Kaca Es t = 8 mm m²
-Aksesories & Hardware
Lever Handle set
Cylinder set
Mortise Lock set
Engsel pintu bh
Door closer bh
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu tipe SPH Uk. 700 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
Pemasangan alumunium Frame Daun Pintu Powder Coating m²
Kaca Es t = 8 mm m²
-Aksesories & Hardware
Lever Handle set
Cylinder set
Mortise Lock set
Engsel pintu bh
Door closer bh
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu tipe JAN Uk. 700 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
Pemasangan alumunium Frame Daun Pintu Powder Coating m²
Kaca Es t = 8 mm m²
-Aksesories & Hardware
Lever Handle set
Cylinder set
Mortise Lock set
Engsel pintu bh
Door closer bh
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu tipe TOI Uk. 700 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
Pemasangan alumunium Frame Daun Pintu Powder Coating m²
Kaca Es t = 8 mm m²
-Aksesories & Hardware
Lever Handle set
Cylinder set
Mortise Lock set
Engsel pintu bh
Door closer bh
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu tipe TOI-1 Uk. 800 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
Pemasangan alumunium Frame Daun Pintu Powder Coating m²
Kaca Es t = 8 mm m²
-Aksesories & Hardware
Lever Handle set
Cylinder set
Mortise Lock set
Engsel pintu bh
Door closer bh
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu tipe TOI-2 Uk. 900 x 2150
-Frame Allumunium
Pemasangan alumunium kusen pintu Powder Coating m
Pemasangan alumunium Frame Daun Pintu Powder Coating m²
Kaca Es t = 8 mm m²
-Aksesories & Hardware
Lever Handle set
Cylinder set
Mortise Lock set
Engsel pintu bh
Door closer bh
-Ongkos Pasang dan Material Bantu ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu Tipe PNL HM uk. 900 x 2150
Pintu Hollow Metal (uk. 900 x 2150)/ Fabrikan ex. Bostinco/ setara unit
Hardware :
Lockcase unit
Cylinder pintu besi unit
Door Handle unit
Door stoper bh
Material bantu dan ongkos pasang ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu Type FS HM uk. 900 x 2150
SINGLE STEEL DOOR + Wired Glass 6 mm ( uk. 900 x 2150 ) Tahan api unit
Hardware :
- Lockcase (tahan api)
- Cylinder (tahan api)
- Bar Handle Corbin (Anti Panic Bar Handle)
- Door closer (tahan api)
Material bantu dan ongkos pasang ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu Type DBS HM uk. 2 x 900 x 2150
Pintu Hollow Metal (uk. 900 x 2150)/ Fabrikan ex. Bostinco/ setara unit
Hardware :
Lockcase unit
Cylinder pintu besi unit
Door Handle unit
Door stoper bh
Material bantu dan ongkos pasang ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu Tipe SHF 1 HM uk. 450 x 1245 mm
Pintu Hollow Metal (uk. 450 x 1245)/ Pabrikan ex. Bostinco/ setara unit
Hardware :
Lockcase unit
Cylinder pintu besi unit
Door Handle unit
Engsel Pintu bh
Material bantu dan ongkos pasang ls
Jumlah ha
Total = Jumlah+(Keun
Pemasangan Pintu Type SHF 2 HM uk. 2 x 450 x 1245
Pintu Hollow Metal (uk. 450 x 1245)/ Pabrikan ex. Bostinco/ setara unit
Total = Jumlah+(Keun
DAN JENDELA GEDUNG RAWAT INAP
RAWAT INAP
Jendela Type W 1
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type W 2
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type W 5
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type W 5A
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type W 6
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type W 4
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type W 2A
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type W 4A
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type W 8
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type BV 2
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type BV 2A
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type BV 3
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type LV 3
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
-Ongkos Pasang dan Material Bantu Aksesories ls
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 4
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
-Ongkos Pasang dan Material Bantu Aksesories ls
Jumlah ha
Total = Jumlah+(Keun
Jendela Type CW 7
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type CW 8
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type CW 9
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type CW 10
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type CW 11
-Allumunium
Total = Jumlah+(Keun
Jendela Type CW 1
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type CW 2
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type CW 3
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type CW 4
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type CW 5
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type CW 6
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
DAN JENDELA BANGUNAN SELASAR DAN RAMP
Jendela Tipe W 2A
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Tipe W 2B
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Tipe W 3
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Tipe W 3B
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Tipe W 3C
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type W 4
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type W 5
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type W 6
-Allumunium
Total = Jumlah+(Keun
Jendela Type LV 1
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 2A
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 2B
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 3
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 3B
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 3C
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 4
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 5
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 6
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
DAN JENDELA BANGUNAN CORE LIFT
Jendela Tipe CW 1
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Tipe W 2
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Tipe W 4
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Pemasangan alumunium Frame Daun Jendela Powder Coating m
Total = Jumlah+(Keun
Jendela Type LV 2
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 4
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 7
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Jendela Type LV 9
-Allumunium
Pemasangan Alumunium Kusen Jendela Powder Coating m
Louvres Alumunium m²
Jumlah ha
Total = Jumlah+(Keun
Rp 17,600.00
0.1000 Rp 85,000.00
Rp 8,500.00
0.1000 Rp 120,000.00
Rp 12,000.00
0.0100 Rp 135,000.00
Rp 1,350.00
0.0050 Rp 150,000.00
Rp 750.00
Jumlah harga persatuan pekerjaan
Rp 46,380.00
Keuntungan+Over head 10% Rp 4,638.00
Total = Jumlah+(Keuntungan+Over head 10%) Rp 51,018.00
Rp 166,239.15
Rp 74,250.00
Rp 313,381.75
Rp 149,939.35
Rp 329,780.00
Rp 76,784.77
Rp 127,041.19
Rp 4,083,238.50
Rp 36,246.40
Rp 183,410.50
Rp 4,619,753.75
Rp 8,138,443.61
Rp 3,947,086.63
Rp 1,368,945.50
Rp 69,652,799.07
D. BAHAN KAYU
1
2
3
4
F. PEKERJAAN ATAP
1
2
3
4
5
6
7
F. SANITAIR
1
2
G. BAHAN FINISHING
1
2
3
4
5
6
7
8
9
10
11
12
13
11
28
29
b.
1
2
10
11
12
12
13
14
15
16
c.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
I. LAIN - LAIN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
HAN KAYU
Dolken kayu dia. 8-10/400 cm
Kayu Kelas I
Balok Kayu Kelas II.
Kayu Kelas III
ERJAAN ATAP
Pekerjaan Konstruksi Atap Baja Ringan tebal 0,8 mm
Atap Sirap Asphal 3 mm
- Multiplek 12 mm
- Anderlayer 3 mm
- Penutup Atap 3 mm
- Flashing
- Reng
- Upah pasang
Nok sirap asphal memanjang
Nok sirap asphal segitiga
Talang air zincalum
Lisplank GRC
Talang air
ITAIR
Kloset duduk lengkap dengan aksesoris
Kloset jongkok lengkap dengan aksesoris
HAN FINISHING
Plamur (1 pail = @ 20 kg)
Cat emultion paint (1 pail = @ 25 kg)
Cat weathershield (1 pail = @ 25 kg)
Cat dusprtproof paint
Cat enamel (epoxy)
Residu
Dempul
Meni Duco
Cat Duco
Thinner
Cat marka thermoplastic
Minyak Cat Nippon Paint - Thinner Melamic ( 1 ltr )
Glass Beet
Allumunium Composite Panel (ACP), PVDF 0,30 mm tebal 4 mm
Daun Pintu
Daun Pintu Frame kayu kamper, Core Honeycomb Frame kayu meranti
Daun Pintu Frame kayu kamper, lapis double multiplek 5mm ( 750 x 2150 )
Daun Pintu Frame kayu meranti (Core Honeycomb), Skin HDF Lapis HPL uk. 900 x 2150
+ kaca polos 12 mm (700 x 800 mm) Pabrikasi
Daun Pintu Frame kayu meranti (Core Honeycomb), Skin HDF Lapis HPL (900 x 2150)
+ kaca polos 8 mm (200 x 700 mm) Pabrikasi
Daun Pintu Frame kayu meranti (Core Honeycomb), Skin HDF Lapis HPL ( 400 x 800 x 2150 )
+ kaca polos 8 mm (200 x 700 mm) Pabrikasi
Daun Pintu Frame kayu meranti (Core Honeycomb), Skin HDF Lapis HPL (900 x 2150)
+ kaca polos 8 mm (700 x 925 mm) Pabrikasi
Daun Pintu Frame kayu kamper, ( 400 x 2150 )
+ kaca polos 8 mm (200 x 700 mm)
Hardware:
Pull Handle
Kunci Swing
Lever Handle
Floor Hinge
Mortise Lock
Cylinder
Door closer
Engsel pintu
Friction Stay Jendela
Friction Stay Bouvenlight
Top Patch
Bottom Patch
Top Pivot
Corner Lock
Pivot hinge
Kunci tanam Flush Bolt FB 040 S/S 8 + 18 SSS
Door stoper
Casement Handle
Lockcase
Cylinder pintu besi
N - LAIN
Air
Paku
Minyak bekisiting
Paku biasa
Kawat beton
Besi strip
asbes
Seng plat
Besi Hollow 40 x 40
Jendela nako
Kaca polos
Kunci tanam
Roll Cat
Amplas
Kape
Kawat beton
Skrup
Paku ramset+misiu
Suspension Rod
Suspension Clip
E' Connector
Jointing Coumpond
Joint Tape @ 75 m
Wall Angle
E'C-Line -0,5x 4,000 mm - Galvalum
Lem/adhesive
Signage room
Signage toilet
Meja Konter
Rangka kamper, plywood,HPL, edging HPL,top counter batu granite
tiang penyangga kaca dia. 50 mm stainless steel, hardware
Lemari Rak
Material: Multiplex 18 mm
Finising : HPL
Timbal tebal 2 mm (25 kg / m2)
U Chanel 75
Rp 85,000 oh
Rp 120,000 oh
Rp 120,000 oh
Rp 120,000 oh
Rp 120,000 oh
Rp 135,000 oh
Rp 150,000 oh
Rp 700 bh
Rp 8,614 bh
Rp 2,750 bh
Rp 286,000 m³
Rp 253,000 m³
Rp 880,000 m³
Rp 858,000 m³
Rp 9,300 kg besi
Rp 9,300 ###
kg
Rp 14,000 ###
kg
Rp 194,000 ###
zak
Rp 362,450 ###
zak
Rp 282,800 sak
Rp 84,660 sak
Rp 58,000 sak
Rp 1,050 ###
kg
Rp 16,000 ###
kg
Rp 308,000 ###
m³
Rp 264,000 m³
Rp 210,000 m³
Rp 203,743 m³
Rp 250,000 m³
Rp 250,000 m³
Rp 250,000 m³
Rp 275,000 m³
Rp 275,000 m³
Rp 160,000 m²
Rp 84,700 m²
Rp 35,000 ltr
Rp 9,900 kg
Rp 12,000 ltr
Rp 110,825 ###
bh
Rp 98,450 ###
bh
Rp 15,125 ###
bh
Rp 44,330 ###
bh
Rp 60,954 ###
bh
Rp 60,954 ###
bh
Rp 4,309 bh
Rp 24,382 ###
bh
Rp 15,125 bh
Rp 9,200 bh
Rp 163,020 m²
###
Rp 440,000 m²
###
Rp 18,471 bh
Rp 65,000 bh
Rp 20,318 bh
Rp 1,100,000 m²
Rp 254,000 m²
Rp 420,000 m²
Rp 900,000 m'
Rp 850,000 m'
Rp 150,000 m'
Rp 140,000 m'
Rp 165,000 m²
Rp 434,500 m²
Rp 291,500 m²
Rp 67,900 m¹
Rp 850,000 ###
m²
Rp 250,000 ###
m²
Rp 25,000 ###
m'
Rp 24,000 btg
Rp 6,250,000 m³
Rp 3,025,000 m³
Rp 1,850,000 m³
Rp 77,100 lbr
Rp 92,200 lbr
Rp 95,000 lbr
Rp 16,000 ###
m
Rp 84,900 m
###
Rp 306,400 pcs
###
Rp 30,800 pcs
###
Rp 10,900 pcs
###
Rp 76,900 pcs
###
Rp 589,000 pcs
###
Rp 301,400 pcs
###
Rp 143,000 pcs
###
Rp 7,500 pcs
###
Rp 5,200 pcs
###
Rp 4,700 pcs
###
Rp 140,000 m²
Rp 550,000 m²
Rp 120,000 m
Rp 95,000 bh
Rp 150,000 m
Rp 11,667 m
Rp 24,000 m
Rp 31,150,000 bh
Rp 3,870,000 bh
Rp 32,000 kg
Rp 53,308 kg
Rp 74,462 kg
Rp 52,308 kg
Rp 65,385 kg
Rp 39,081 ltr
Rp 40,000 kg
Rp 90,000 kg
Rp 120,000 kg
Rp 30,000 ###
ltr
Rp 47,641 kg
Rp 19,700 liter
Rp 28,138 kg
Rp 365,000 m²
Rp 156,000 m
Rp 156,000 m
Rp 120,000 m
Rp 523,900 m2
Rp 850,000 m'
Rp 850,000 Unit
Rp 1,245,000 Unit
Rp 1,050,000 Unit
Rp 1,650,000 Unit
Rp 1,150,000 Unit
Rp 600,000 Unit
Rp 1,350,000 Unit
Rp 1,150,000 Unit
Rp 975,000 Unit
Rp 2,105,000 Unit
Rp 2,650,000 Unit
Rp 7,500,000 Unit
Rp 9,500,000 Unit
Rp 18,500,000 Unit
Rp 712,400 set
Rp 116,200 set
Rp 164,400 set
Rp 1,260,500 set
Rp 186,400 set
Rp 98,600 set
Rp 295,900 set
Rp 59,600 bh
Rp 119,200 bh
Rp 104,100 bh
Rp 371,800 bh
Rp 371,800 bh
Rp 150,000 bh
Rp 770,000 bh
Rp 169,000 set
Rp 197,300 set
Rp 57,000 bh
Rp 38,400 bh
Rp 353,300 unit
Rp 229,900 unit
Rp 600 ltr
Rp 17,000 kg
Rp 10,500 ltr
Rp 17,000 kg
Rp 16,500 kg
Rp 15,000 kg
Rp 65,000 ###
lbr
Rp 195,000 ###
m2
Rp 13,700 ###
m
Rp 116,400 ###
bh
Rp 46,000 ###
m²
Rp 60,500 bh
Rp 39,081 bh
Rp 4,690 lbr
Rp 3,300 bh
Rp 23,449 kg
Rp 200 bh
Rp 1,900 bh
Rp 3,400 bh
Rp 745 bh
Rp 745 bh
Rp 4,300 kg
Rp 30,200 roll
Rp 4,133 m
Rp 6,750 m
Rp 56,500 ltr
Rp 95,000 bh
Rp 137,000 bh
Rp 2,300,000 m¹
Rp 1,500,000 m¹
Rp 1,119,160 m²
Rp 5,600 m¹