Vous êtes sur la page 1sur 1

Arcata Levee Repair

Arcata, California

PROJECT HIGHLIGHTS:

• Removal of concrete and


asphalt-concrete debris
• Excavation of the levee slope
within the tidal zone
• Placement of geotextile and
rock armor slope protection
• Installation of turbidity
curtains and others
• BMPs for storm water and
erosion control

Magnus Pacific completed the Arcata Levee repair project the faces of the levees to withstand the erosive forces
in the fall of 2009 for the City of Arcata. The project generated within Humboldt Bay, particularly during storm
involved repairing two levees damaged by strong winds, events.
heavy rain and tidal surges during winter storms in
late 2005 and early 2006. The scope of work included During construction, Magnus Pacific removed the existing
removing concrete and asphalt debris on the faces of concrete and asphalt debris and recycled it off-site or
the levees, excavating unsuitable levee material, and within the project backfill (where suitable), excavated
replacing rock armor slope protection. a toe trench to anchor the RSP on the outer levee face,
installed geotextile fabric between the RSP and finer-
The Arcata levees separate Humboldt Bay from the city’s grained embankment soils, and placed the RSP at a
wastewater treatment ponds and Klopp Lake. Repairs 1.5H:1V maximum slope above the toe trench. The tops
were necessary to ensure the continued operation of of the levees were raised in low-lying areas, to prevent
the wastewater treatment plant and to protect the overtopping during storm events, and widened to allow
community, the lake, and Humboldt Bay from flood. vehicle access for ongoing maintenance and future
construction.
The levees were originally constructed from on-site Bay
Mud. Over the years, concrete and asphalt debris had Funding for all aspects of the project (permitting, design
been used on the levee faces as rock armoring. After and construction) was provided by FEMA and the
reviewing a number of design alternatives for repairing California Office of Emergency Services (OES) following
the slopes, the City’s engineer selected rock slope the storm events of 2005/2006. The project was
protection (RSP) based on its longevity, high reliability, completed on time and within budget, and without a
low maintenance, ease of permitting, and compatibility safety incident.
with the funding criteria. The RSP approach involved
placing various sizes and grades of rock as armor on

Vous aimerez peut-être aussi