SR NO Description Unit Nos L B D Qty Total Qty.

Rate Amount
Shed

0 Man power for clearance, site preparation, days 2 3 6 300 1800


throwing of spoils etc. (labour) (days)

1.1 Excavation
1.1.1 Earthwork for columns cu.m. 33 0.6 0.6 1.2 14.256
1.1.2 Earthwork for Plinth Area cu.m. 1 8 33 0.5 132
1.1.3 Deduction cu.m. 11 0.6 0.6 0.5 1.98

150 200 30000

1.2 Hand packed stone soling

1.2.1 Columns cu.m. 33 0.6 0.6 0.15 1.782

1.2.2 Plinth Area cu.m. 1 8 33 0.2 52.8

1.2.3 Deduction cu.m. 11 0.6 0.6 0.15 0.594

55 600 33000

1.3 Providing M-20 Grade RCC

1.3.1 Isolated footings cu.m. 33 0.3 0.4 0.93258


1.3.2 Central Columns cu.m. 11 0.15 3.7 0.718864

1.3.3 Peripheral Columns cu.m. 22 0.15 3.5 1.360013

4 6600 26400

1.4 Providing M-15 Grade PCC

1.4.1 Plinth Area cu.m. 1 8 33 0.15 39.6

40 6025 241000

1.5 Reinforcement in columns and foundation kg 135


540 60 32400
(kg/cu.m.)

1.6 U-shaped drain with M15 PCC two sides RM 2 41 82


85 600 51000
1.7 Structural steel

1.7.1 Trusses kg 11 20.8 4.5 1029.6

1.7.2 Purlins kg 5 33 4.5 742.5

1780 70 124600

1.8 Asbestos cement sheet for roofing Sqm 2 35 5 350 360


210 75600

1.9 Half brick Masonry for Manger sqm 4 33 0.25 33 35


800 28000

Total Rs 643800
SR NO Description Unit Nos L B D Qty Total Qty. Rate Amount
labour room

1.1 Excavation
1.1.1 Earthwork for columns cu.m. 4 0.6 0.6 1.5 2.16
1.1.2 Earthwork for Plinth Area cu.m. 1 3 3 0.75 6.75

10 200 2000

1.2 Hand packed stone soling

1.2.1 Columns cu.m. 4 0.6 0.6 0.15 0.216

1.2.2 Plinth Area cu.m. 1 3 3 0.1 0.9

2 600 1200

1.3 Providing M-20 Grade RCC

1.3.1 Isolated footings cu.m. 4 0.3 0.3 0.08478

1.3.2 Columns cu.m. 4 0.2 0.2 3.2 0.512


1 6600 6600

1.4 Black Stone Flooring

1.4.1 Plinth Area cu.m. 1 3 3 9

9 150 1350

1.5 Reinforcement in columns and foundation kg 135


135 60 8100
(kg/cu.m.)

1.8 Asbestos cement sheet for roofing Sqm 1 4.5 4.5 20.25 25
210 5250
1.9 Half brick Masonry sqm 4 3 3 36 40
800 32000

1.10 Plastering sqm 2 40 80


200 16000

Total Rs 72500
SR NO Description Unit Nos L B D Qty Total Qty. Rate Amount
water tank

1.1 Excavation
1.1.1 Earthwork for Plinth Area cu.m. 1 6 8 0.5 24

25 200 5000

1.2 M 15 Grade PCC

1.2.1 Plinth Area cu.m. 1 5 7 0.15 5.25

6 6025 36150

1.3 230mm rubble soling sq.m. 1 5 7 35 35


408 14280

1.4 Full brick Masonry sqm 1 24 2.5 60 60


800 48000
1.5 Plastering sqm 2 60 120
200 24000

Total Rs 127430
Labour Water
SR NO Description Unit Shed Room Tank Total Rate per Unit Rate

0 Man power for clearance, site preparation, days 6 6 300 1800


throwing of spoils etc.

1.1 Excavation cu.m. 150 10 25 185 200 37000

1.2 Hand packed stone soling cu.m. 55 2 0 57 600 34200

1.3 Providing M-20 Grade RCC cu.m. 33000


4 1 0 5 6600

1.4 Providing M-15 Grade PCC cu.m. 277150


40 0 6 46 6025
1.5 Reinforcement in columns and foundation kg 40500
540 135 0 675 60

1.6 U-shaped drain with M15 PCC two sides RM 51000


85 0 0 85 600

1.7 Structural steel kg 124600


1780 1780 70

1.8 Asbestos cement sheet for roofing Sqm 360 80850


25 0 385 210

1.9 Half brick Masonry for Manger sqm 35 60000


40 0 75 800

1.10 Black Stone Flooring sq.m. 0 9 0 9 150 1350

1.11 230mm Rubble soling sq.m. 0 0 35 35 408 14280


1.12 Full brick Masonry sq.m. 60 60 800 48000

1.13 Plastering sqm 40000


80 120 200 200

Total 843730
BILL OF QUANTITIES
SR NO Description Total Cost
A LABOUR COMPONENT

1 Man power for clearance, site preparation, 2000


throwing of spoils etc.
2 Excavation 37000

3 Providing and laying in position - Cement concrete 78000


including compacting curing etc

4 Providing U shape drain including neat cement 10200


polishing, rounding of junctions etc

5 Fitting and fixing of CGI sheet roof with advised 15120


lapping with hooks, bolts and nuts.

Supplying, fabricating, fitting and fixing steel tubular


6 trusses including 24920
cutting, hoisting, fixing in position

7 9700
Laying in position - Stone solling for floor

8 21600
Laying brick masonry with 1:3 cement mortar

9 Carriage and stocking of constructions materials - 25000


15km
B Materials

1 Stone 24840
2 Cement 112000

3 Sand 109000

4 Stone Chips 66000

5 Reinforcement Steel 40500

6 Structural Steel Tubes 124600

7 CGI Sheets 65450

8 Bricks 86000

9 Blackstone 1215

Total 853145