CONTENTS DETAILS
1. Executive Summary
The Limestone lease was granted to Nilesh Pandya over an area of 04.90.00 hectare
at Sur. No100 paiki Village: Bhogat, Tal: Kalyanpur, Dist: Devbhumi Dwarka.
This is a Limestone mining lease
Order of Honourable Supreme Court order-dated 27/02/2012 regarding the mining
projects with lease area more than 5 hectare including projects of minor mineral with
more than 5 hectare required environment clearance.
The mining is Schedule under Category 1 (a) – “B” as per.
Total Mineable reserves from the Limestone mines are estimated as 857500MT.
2. Introduction of the project Background information
i. Identification of project and project proponent. In case of mining project, a copy
of mining lease / letter of intent should be given.
1
Nilesh Pandya
Coordinates
2
Nilesh Pandya
3
Nilesh Pandya
al.
x. Schematic
representations of
the feasibility
drawing which given
in formation of EIA
purpose.
4. Site Analysis
i. Connectivity. Railway Station: Bhatiya (11 km)
Airport: Porbandar (70 km)
ii. Land Form, Land use The mine lease area s p r e a d s i n 04.90.00 h a , which i s
and Land ownership. Private Land. Moreover there will be permanent change
in land use at the end of life of mine, the area will
be converted in to water resourvier, which will
help in ground water recharge of nearby area
iii. Topography (along Layout Map is enclosed as Annexure III and Location Map
with map). as Annexure II and Google Image as Annexure V.
iv. Existing land use The proposed project is Limestone mining which located
pattern (agriculture, in Bhogat. National Park, Forest, Wild Life Sanctuary, Eco
non-agriculture, Sensitive Area is not presented with in10km of the
forest, water bodies project.
(including area
under CRZ), shortest
distances from the
periphery of the
4
Nilesh Pandya
project to periphery
of sanctuary, eco
from the HFL
industrial area, be
given.
v. Existing There is not existing infrastructure in the area.
Infrastructure.
vi. Soil classification The soil found in the study area can be classified alluvial
soil. The topsoil providing thin cover is of light brown
colour.
vii. Climatic data from
secondary sources. Climate data for
Avg. Rainfall 750 mm
Temperature (Max) 40.8˚ C
Temperature (Min) 10.6˚ C
Relative Humidity 65%
Wind Direction SW, W
viii. Social Infrastructure All the social infrastructural facilities like temple ,
available. schools, hospital etc. are available within 5 km of
project site.
5. Planning Brief
i. Planning Concept It is a mine project hence mining of Limestone shall be
(type of industries, carried out. The production of Limestone s h a l l b e
transportation etc.) 8 0 , 0 0 0 MT/Year. Transportation of Limestone shall be
Town and Planning/ done through road by covered dumpers and covered
Development trucks.
authority Other facilities such as power, transportation,
Classification. communication, social infrastructure facilities are locally
available near project site.
ii. Population About 10 persons shall be employed in the mining
Projection project. All the people will be sourced from neighbouring
villages. Thus there will be no increase in population due
to the project.
iii. Land use The land use of the mine lease area will change in to
planning excavated pits; however the pits will be filled with water
( breakup along with at the end of mine life. Plantation will also be carried
along the boundary of lease and fencing will also be
green belt etc).
carried out.
iv. Assessment of The infrastructure facilities like mines office, evacuation
I n f r a s t r u c t u r road, site services will only be required.
e Demand (Physical
& Social).
v. Amenities /Facilities. The following facilities/amenities will be extended by the
5
Nilesh Pandya
mine management:
Direct and in direct Employment, of which most will be
from near by villages.
Arrangements for safe and healthy working conditions.
Provision of Drinking water.
Conducting medical camps for workers and nearby
villagers at regular interval.
6. Proposed Infrastructure
i. Industrial Area The proposed project does not involve any processing
(Processing Area)
ii. Residential Area (Non
All the
Processing
local persons
Area) will be employed, no residential
area/housing is proposed.
iii. Green Belt The area of plantation is proposed a t t h e b o u n d a r y
o f l e a s e a n d n e a r b y v i l l a g e s in consultation with
local authority/Govt. Body.
iv. Social Infrastructure Road facility (existing roads will be maintained regularly)
Public transport system improvement
Direct & Indirect employment opportunity
Social awareness camps,
Increase revenue, sales tax, road tax to state government
v. Connectivity (Traffic Railway station at Bhatiya (11 km)
and Rail /Metro/ & Airport at Porbandar (70 Km)
Waterways etc)
vi. Drinking Water Drinking water will be made available all the times t o
Management w o r k e r s . This will be sourced by local area.
(Source water)
vii. Sewerage System No sewerage system is proposed. However for sanitation
purpose septic tank / soak pit system will be made
available.
viii. Industrial Waste Not applicable
Management
6
Nilesh Pandya