1. Earthwork:
[Stratum to be likely hard gravel in top soil and soft rock below 3’
depth]
Earthwork For Columns: [Total depth 3’6” – 4’]
Co =4x4
C1 &C2 = 4”6” X 4’
C3 &c4 = 5’ x 4’6”
2. P.C.C for columns 1:5:10:
For foundation as leveling course, using 40mm blue granite metal
with mix 1:5:10. 6” depth.
For flooring same mix 4” thick
3. Footing and pedestal:[1:2:4]mix
Mat for Co = 3’6” x 3’6” [ 10mm ǿ bars @ 15cm c/c]
C1 & C2 = 4’ x 3’6” [ 10mm ǿ bars @ 15cm c/c]
C3 & C4 = 4’6” x 4’ [ 10mm ǿ bars @ 15cm c/c]
Bed for Mat = 23cm depth
Pedestal = 45cm Height above bed
Column size:
Co = [0.75’ x 0.75’] - 1no (6nos 12mm ǿ bars)
C1 & C2 = [1’0” x 0.75’] -11nos (C1-6nos 12mm ǿ bars)
(C2-4nos 16mm ǿ bars
& 2nos 12mm ǿ bars)
20. The total working cost for the above work is Rs.1110/sq.feet.which
excludes floor finish.
Septic tank of capacity 2500 lits with 0.75 feet brick work with separation
chambers would be provided.
8. Flooring concrete: