APPENDIX-7

(To Para 13.17 of Instructions to the Tenderer)

TIME SCHEDULE

S. items of Commencement Completion


No. Work (No. of Month from (No. of Month from
Effective date of contract) Effective date of contract)

1. Basic Engineering 1 8
2. Detailed Design Engineering 3 21
3. Civil Work 5 22
4. Supply / Delivery of :
i) Foundation Bolts & Inserts 5 22
ii) Building Steel Structures & Sheeting :
a) Imported NA NA
b) Indigenous 5 23
iii) Mechanical Plant & Equipment
including Technological Structures :
a) Imported 12 23
b) Indigenous 7 23
iv) Electrical Plant & Equipment :
a) Imported NA NA
b) Indigenous 11 24
v) Refractories
a) Imported NA NA
b) Indigenous NA NA
vi) Commissioning Spares :
a) Imported NA NA
b) Indigenous 24 26
vii) Special Tools, Tackle
Consumables Oil & Lubricants :
a) Imported NA NA
b) Indigenous 23 26
5. Erection of Building Steel Structures & 7 24
Sheeting:
- For items for which Steel is NA NA
issued by the Employer
- For items for which Steel is 10 24
Procured by the Contractor
6. Erection:
Mechanical Plant & Equipment 8 25
Electrical Plant & Equipment 18 25
7. Erection of Refractories NA NA
8. Time of Completion (Ref. Cl No. 9.5 of GCC)22 26
9. Performance Guarantee Test 26 After Commissioning