Renovation of Electro‐Mechanical equipments in a Hotel
ID ITEM Qty Unit
1
Ch 6
4 Sanitary white ware fixtures, test, change if needed 670 pc
5 Washing machines /spare parts/ fixing leakage…cap 1 32 pc
6 Checking all electric devices/ TVs/ sockets/lights/ inte 1200 pc
2
Ch 6
1 Cleaning boilers and testing - cap 250,000 Kcal 9.0 pc 50.0 2.0 35.0 1.0 25.0 1.0
2 Checking /testing/ all radiatots (heating eff, leakin 470.0 pc 50.0 1.0 35.0 0.0 25.0 1.0
3 Checking /testing/ startingl ,Chiller system -cap 4 12.0 pc 50.0 2.0 35.0 1.0 25.0 1.0
3
Ch 6
Day / 1 Day/
Lab No/crew Total cost AV.rate /hr Rate $/unit Hr/day Unit/1 hr Unit/ day Selc crew Lab hr Day Work
crew crews
4.0 160.0 5.0 90.0 9.0 0.06 0.50 1.0 162.0 18.0 4.5 4.5
2.0 75.0 4.7 12.0 9.0 0.39 3.52 5.0 1,203.2 133.7 66.8 13.4
4.0 160.0 5.0 400.0 9.0 0.01 0.11 2.0 960.0 106.7 26.7 13.3
1.0 0.0 0.0 1.0 9.0 1.00 9.00 6.0 670.0 74.4 74.4 12.4
1.0 0.0 0.0 1.0 9.0 0.40 3.60 1.0 80.0 8.9 8.9 8.9
1.0 0.0 0.0 1.0 9.0 1.50 13.50 7.0 800.0 88.9 88.9 12.7
3,875.2 430.6 270.2 65.2