ROUTE SURVEY
No Descriptions Unit Quantity Rate Amount
(RM)
1 Preparatory work 1960 10 1960 19 600.00
2 Mobilization and NIL NIL NIL NIL
Demobilization
3 Point Positioning by mark 3 marks 2600 7 800.00
Global Navigation
Satellite System
4 Planimetric control and meter 250 m 50 12 500.00
connection
Built up area
5 Height control and km/party 250 m 3.00 750.00
connection per day
- Ordinary
Built up area
6 Monumenting 4 marks per 3 marks 0.75 1 470.00
- Concreting party day
- Accessible
7 Supply of plans and Per copy 11 copies 30.00 330.00
document
8 Survey of Strip with ha/party per 1.12 ha 1.5 1 463.47
Spot level and Detail day
9 Grid Heighting km/party
per day
10 Setting out of center km/party 0.140 km 4.25 1166.20
line of road per day
11 Longitudinal Profiling km/party 0.140 3.00 823.20
along Established per day
Chainage Pegs
- Built up area
12 Cross Section km/party 0.560 4 274.40
- Built up area per day sections/party
per day
Total RM 46177.27
Grand Total RM 46177.27
Ringgit Malaysia: Empat Puluh Enam Ribu Seratus Tujuh Puluh Tujuh dan Dua Puluh tujuh
Sen Sahaja.
Sekian, terima kasih.
…………………………………..
(MUHAMAD SHAH MIN)
Jurukur Tanah Berlesen
Akta 458 (Pindaan 1991)