Comments Return Form

COMMENTS RETURN FORM

Project: Revamping PLC project CRF No Hold


Document/Drawing Title: SOW
Document/Drawing Number: Hold Review Date: 2 weeks

Sr. Section Comment By Response Action

1.1General: The two points will be


Please add the following: cancelled.
For point 1, the added statement
 EW-Plant at Damietta governorate it’s about 270km far from Cairo is already illustrated in details at
and about 15km from New Damietta city, EW-Plant consist of two system description section.
1 1.1 Haitham
phases (Phase II and Phase III). For point 2,the added statement
 WASCO intends to revamp the control system of its central is the same meaning of existing
one.
processing facilities at EW-plant. This is mainly due to most system
components were obsolete and malfunction of redundant system.

General Scopeof Work: For Point 1: will be


considered.
Please add the followings:
For point 2: cancelled.
2 1.2  Considering that this SOW shall include but not limited to the Haitham
Noted and will be added at
section 6
followings.
 Considering that this project is a EPC project.

PH-III: Will be cancelled


Please add the following: I don't see any difference from
3 2.1.2 Haitham
 The phase III consists of two redundant chassis with 5(Fife) I/Os existing. Please clarify?
chassis (4 Chassis communicated through control net including

Rev. 0 Page 1 of 4
Comments Return Form

Sr. Section Comment By Response Action

prosoft modules for transferring data from flow meters in addition


to fifth chasse which is communicated through Ethernet for MCC.

Warranty: For point 1: already


considered.
Please add the following: For point 2: will be
cancelled.
 The guarantee period shall be which come early of as the following:
1- One year as a guarantee for (S/W and H/W) from prevision
acceptance certificate and clear all puns list items. Will be negotiated with instrument
4 5 Haitham
team.

2- Two years as a guarantee started from receiving material at site in


case of not install due to reasons related to WASCO, in these case
WASCO may ask the contractor to extend the guarantee period by
extra one year in addition to the two years (contractor commercial
offer shall include the price of this item).

For point 1, Will be negotiated For Point 1: will be


General Requirements and Considerations: with instrument team.(but in my cancelled.
Please add the following: opinion there is no alternative For point 2: will be
solution) considered and reflect at
For point 2, For PHII: SOW as following: the
 Contractor shall propose as an optional any other alternative Spare channels will be provided cards at the new panel
solution that will implement the same SOW under Allen are 16 points DI. will be 1 DI, 2 AO and 2
Bradley umbrella if it we applicable in our case. DO.
For PHIII:
5 6  please be advise that no need for new panel as the FF and F&G Haitham Spare channels will be provided
For point 3: will be
considered.
new system shall include anew stand-alone panel and are aprox. 70 AI points and 32 DI
accordingly all the old F&G system shall be transferred from points without 24vDC. For point 4: will be
cancelled.
old panel which mean that it will grantee the needed spar for So, it is an issue to negotiate for
old panel. final decision as the above spare
points will be sufficient or not.
 EL Wastani plant is a brown field your offered shall consider
For Point 3: Noted
implementation of the SOW at minimum S/D period which For Point 4: This period doesn't
determine up till now. So, i can't

Rev. 0 Page 2 of 4
Comments Return Form

Sr. Section Comment By Response Action

will be part of the technical and commercial evaluation. add it.

 please note that the maximum S/D period will be tree days.
For Point 1:please be informed For point 1:Not
that the new processor will be L74 applicable.
From our point of view, I suggest the following: as attached BOM and For point 2: Already
combination for one PLC don't considered.
1- May be we should combine the PLC to become one PLC ( using one applicable for the below reasons:
For Point 3(a):will be
processor L 74( 16MB)) or L 75 (32MB) instead of two PLCs (Phase II and 1-This modification will reduce cancelled.
Phase III). system availability.(as now
For point 3(b):will be
2- For communication we can use ENT2R instead of control net. system will be depend only on
cancelled.
one processor)
3- Also please noting the following:
2- I can't shutdown PHII only.
a- All I/Os racks are still in the same place at phase II and phase III.
3-This modification also will take
b- The existing system consists of two PLCs (one for phase II and the other long time to laying new cables,
6 for phase III, but actually we can’t operate phase II without phase III or vice Haitham and will perform commissioning
Versa. again.
4-Almost used signals at PHII are
In case we apply the aforementioned suggestions this will allow us to save 220V but at PHIII is 24V.
one control panel which include two PLCs system with redundancy system For point 2: This point is already
considered.
with all components.
For Point 3 (a): No change at I/O
list.
If all instrumentation Engineers agree we can hopefully go through with the For Point 3 (b): what is the
new suggestions. purpose of this point. Please
clarify?

Up till now, there isn't clear Will be cancelled


Redundancy problem: reason or evidence for that
Ayman El
7 3.1 1- The Secondary module is disqualified with the primary at PH III due to lower Harony
problem. So, as the system will
processor memory (Application oversize) be replaced, no benefit for list any
reason.
For Redundancy problem: Already considered.
Ayman El Please refer to BOM. This point is
8 4.1.1 Note: It is required to replace the processors with latest series (1756-L7x) with
Harony already considered
higher memory size

Rev. 0 Page 3 of 4
Comments Return Form

Sr. Section Comment By Response Action

Will be considered.
General Requirements and Considerations: Ayman El
9 6 Add new point:Contractor shall be commitment by all WASCO policy The same as point 4 at section 6.
Harony

Will be considered.
I would like to add new item in the SOW as the following replace master switches Ahmed
10 General in latest version fully by contractor Noted
Farag

Rev. 0 Page 4 of 4