Académique Documents
Professionnel Documents
Culture Documents
1.2 All the tests either on the field or at outside laboratories concerning the execution of the work and supply of
materials by the CONTRACTOR shall be carried out by CONTRACTOR at his cost.
1.3 The work is subject to inspection at all times by the ENGINEER-IN-CHARGE/ ENGINEER. The
CONTRACTOR shall carry out all instructions given during inspection and shall ensure that the work is
being carried out according to the technical specifications of this bidding document, the technical documents
that will be furnished to him during performance of work and the relevant codes of practice.
1.4 Compressed air for carrying out works shall be arranged by the CONTRACTOR at his own cost.
1.5 For material supplied by CUSTOMER/PURCHASER, CONTRACTOR shall carry out the tests, if required by
the ENGINEER-IN-CHARGE/ ENGINEER, and the cost of such tests shall be reimbursed by the
CONTRACTEE at actual to the CONTRACTOR on production of documentary evidence.
1.6 All the tests shall be repeated till all the equipments/machinery satisfy the requirement /obligations of
CONSULTANT/PURCHASER and also the relevant statutory authority.
1.7 During trials/ tests, pre-commissioning/ commissioning, replacing/ changing mechanical / other seals of
equipments like pumps, removal and cleaning / replacing of filters etc. is within the CONTRACTOR’s scope
of work. Replacement spares for this purpose shall be provided by CONSULTANT/PURCHASER.
1.8 All results of inspection and tests will be recorded in the inspection reports, proforma of which will be
approved by the ENGINEER-IN-CHARGE/ ENGINEER. These reports shall form part of the completion
documents. Any work not conforming to execution drawings, specifications or codes shall be rejected and
the CONTRACTOR shall carry out the rectifications at his own cost.
b. Visual Inspection
Inspection of all welds shall be carried out as per the latest editions of the applicable codes and
specifications. All finished welds shall be visually inspected for parallel and axial alignment of the work,
excessive reinforcement, concavity of welds, shrinkage cracks, inadequate penetration, unrepaired burn-
through, under cuts, dimensions of the weld, surface porosity and other surface defects. Undercutting
adjacent to the completed weld shall not exceed the limits specified in the applicable standard/code.
c. Final Inspection
After completion of all tests as per specification the whole work will be subject to a final inspection to ensure
that job has been completed as per requirement. If any defect is noticed, the CONTRACTOR will be notified
by the ENGINEER-IN-CHARGE/ ENGINEER and he shall make good the defects with utmost speed. If
however, the CONTRACTOR fails to attend to these defects within a reasonable time (time period shall be
fixed by the ENGINEER-IN-CHARGE/ ENGINEER) then ENGINEER-IN-CHARGE/ ENGINEER may have
defects rectified at CONTRACTOR cost.
2. SHOP INSPECTION AND TESTS
2.1 GENERAL
2.1.1 The plant and equipment covered by the PURCHASE ORDER/CONTRACT shall be subjected to inspection
and testing. The VENDOR/CONTRACTOR shall provide all services to establish and maintain quality of
workmanship in his works and that of his SUB-VENDOR’s/SUB-CONTRACTOR’s works to ensure the
mechanical accuracy of components, compliance with approved drawings, identification and acceptability of
all materials, parts and equipment.
2.1.2 For supply of systems, the VENDOR/CONTRACTOR shall, at the start of the PURCHASE
ORDER/CONTRACT, furnish a total list of items in his scope of work. This list, giving a brief description of
the item, quantity, names of probable SUB-VENDORS/SUB-CONTRACTORS, and a blank column for
agency for final approval of drawings and documents, shall be submitted for approval by
PURCHASER/CONSULTANT. The blank column shall be filled by PURCHASER/CONSULTANT. The list
shall be submitted within two weeks from the date of Letter of Intent.
2.1.3 For systems and major items such as pressure and load bearing items, machineries etc., the
VENDOR/CONTRACTOR shall furnish quality plan giving details of checks and tests to be conducted by
them on material, process, subassembly and assembly. These shall include requirements as prescribed in
the applicable specifications, codes and statutory requirements. The quality plan shall be reviewed by the
PURCHASER/CONSULTANT and the stages to be witnessed and verified shall be indicated by the
PURCHASER/CONSULTANT in the approved quality plan.
2.1.4 The VENDOR/CONTRACTOR shall give the PURCHASER/CONSULTANT written notice of any material
being ready for testing. The clear notice period shall be seven (7) days for local inspection and fifteen (15)
days for Outstation/International inspection. Such tests shall be to the Vendor’s/CONTRACTOR's account
except for the expenses of the PURCHASER/CONSULTANT. The PURCHASER/CONSULTANT, unless
the inspection of the tests is virtually waived, shall fix a date for inspection with the
VENDOR/CONTRACTOR and attend such tests within fifteen (15) days of the date on which the equipment
is notified as being ready for test and inspection failing which, the VENDOR/CONTRACTOR may proceed
with the tests and shall forthwith forward to the PURCHASER/CONSULTANT duly certified copies of tests.
2.1.5 In all cases where inspection and tests are required whether at the premises or works of the
VENDOR/CONTRACTOR or of any SUB-VENDOR/SUBCONTRACTOR or at laboratory, the
VENDOR/CONTRACTOR, except where otherwise specified, shall provide free of charge all facilities such
as labor, materials, electricity, fuel, water, stores, test bed, apparatus and instruments, laboratory tests etc.
as may be required by the PURCHASER/CONSULTANT to carry out effectively such tests of the equipment
in accordance with the PURCHASE ORDER/CONTRACT and shall give facilities to the
PURCHASER/CONSULTANT to accomplish testing.
2.1.6 The PURCHASER/CONSULTANT shall at all working hours have access to all parts of the
VENDOR’s/CONTRACTOR's and his SUB-VENDOR’s/ SUBCONTRACTOR’s factory where the items of
the plant are being prepared, for carrying out inspection activities as deemed necessary. A set of the
relevant latest approved drawings with approval marking of the PURCHASER/CONSULTANT and drawings
for proprietary items shall be made available by the VENDOR/CONTRACTOR to the
PURCHASER/CONSULTANT, for reference during inspection.
2.1.7 In the case of stage inspection hold points, the VENDOR/CONTRACTOR shall proceed from one stage to
another only after the component is inspected by the PURCHASER/CONSULTANT and written permission
given to proceed further. The same procedure shall be adopted for any rectifications and repairs suggested
by the PURCHASER/CONSULTANT.
2.1.8 The PURCHASER/CONSULTANT shall have the right to inspect any machinery, material, structures,
equipment or workmanship furnished or used by the VENDOR/CONTRACTOR and may reject any which is
defective or unsuitable for the use and purpose intended, or which is not in accordance with the intent of the
PURCHASE ORDER/CONTRACT. The VENDOR/CONTRACTOR, upon demand by the
PURCHASER/CONSULTANT, shall remedy or replace at the VENDOR’s/CONTRACTOR's expense such
defective or unsuitable items of the plant, or the PURCHASER/CONSULTANT may, at the expense of the
VENDOR/CONTRACTOR, remedy or replace such defective or unsuitable items of the Plant.
2.1.9 All principal mill test reports, the VENDOR/CONTRACTOR inspection and tests reports, test certificates and
test curves shall be supplied for all inspection and tests carried out including other records such as stress
relieving charts, radiographic charts and other non-destructive testing records in accordance with the
provisions of the PURCHASE ORDER/CONTRACT, duly certified by the main VENDOR/CONTRACTOR.
The PURCHASER/CONSULTANT shall reserve the right to call for certificates of origin and test certificates
for all raw material and equipment at any stage of manufacture.
2.1.10 The PURCHASER/CONSULTANT shall within fifteen (15) days from the date of inspection as defined
herein give notice in writing to the VENDOR/CONTRACTOR of any non-conformance pertaining to all or
any equipment and workmanship which in his opinion is not in accordance with the
PURCHASEORDER/CONTRACT. The VENDOR/CONTRACTOR shall give due consideration to such
objections and shall either make the modifications that may be necessary to meet the said objections or
shall confirm in writing to the PURCHASER/CONSULTANT giving reasons therein that no modifications are
necessary to comply with the PURCHASE ORDER/CONTRACT.
2.1.11 When the factory tests and documentation have been satisfactorily completed at the
VENDOR’s/CONTRACTOR's or SUB-VENDOR's/CONTRACTOR's works, the
PURCHASER/CONSULTANT shall issue acceptance note or shipping release note or a certificate to this
effect within fifteen (15) days after completion, but if the tests are not witnessed by the
PURCHASER/CONSULTANT, the certificate or comments thereof shall be issued within fifteen(15) days of
the receipt of the VENDOR’s/CONTRACTOR's test certificate by the PURCHASER/CONSULTANT. Failure
of the PURCHASER/ CONSULTANT to take such an action shall not prevent the VENDOR/ CONTRACTOR
from proceeding with the work. The completion of these tests or the issue of the certificates shall not bind
the PURCHASER/ CONSULTANT to accept the equipment, should it, on further tests after erection, be
found not to comply with the PURCHASE ORDER/CONTRACT.
2.1.12 None of the plant and the equipment to be furnished or used in connection with the PURCHASE
ORDER/CONTRACT shall be dispatched until shop inspection; satisfactory to the
PURCHASER/CONSULTANT has been made. However, such shop inspection and/or certification shall not
relieve the VENDOR/CONTRACTOR of his responsibility for furnishing the plant and the equipment
conforming to the requirements of the PURCHASE ORDER/CONTRACT nor prejudice any claim, right or
privilege which the PURCHASER/CONSULTANT may have because of the use of defective or
unsatisfactory items. Should the PURCHASER/CONSULTANT waive the right to inspect anytime, such
waiver shall not relieve the VENDOR/CONTRACTOR in any way from his obligation under the PURCHASE
ORDER/CONTRACT. In the event of the PURCHASER’s/CONSULTANT's inspection revealing poor quality
of goods, the PURCHASER/CONSULTANT shall be at liberty to specify additional inspection procedures, if
required, to ascertain the VENDOR/Contractor’s compliance with the equipment specifications.
3. SUB-ORDERS AND SUB-CONTRACTS
3.1 In order to facilitate the inspection of bought-out materials and plant, the VENDOR/CONTRACTOR shall
submit for approval, three (3) copies of all suborders and sub-contracts placed by him as soon as these are
issued. Copies of any drawings referred to in the sub-order or sub-contracts shall also be submitted, unless
agreed otherwise by the PURCHASER/CONSULTANT.
3.2 The sub-orders, sub-contracts and drawings referred to above shall include all components which are
subjected to electrical and mechanical pressure or stress when the plant is in operation, and also auxiliaries
and spares which are to be directly dispatched to site from the SUB-VENDOR’s/SUB-Contractor’s works.
3.3 All sub-orders and sub-contracts of the main VENDOR/CONTRACTOR shall clearly be marked with the
main VENDOR’s/CONTRACTOR's name and the Purchaser’s/CONSULTANT’s name and the PURCHASE
ORDER/CONTRACT reference. These shall include the following statement: The plant or the equipment
which is the subject of this PURCHASE ORDER/CONTRACT shall comply in every respect with the
requirements of the PURCHASER’s/CONSULTANT's technical specifications and shall be subject to
inspection and tests to the satisfaction of the PURCHASER/CONSULTANT.
3.4 For the purpose of this Para, it is obligatory on the VENDOR/CONTRACTOR that he advises his SUB-
VENDOR/SUB-CONTRACTOR of the pertinent clauses in this specification when ordering bought-out plant,
equipment or materials. In particular, the VENDOR/CONTRACTOR shall advise every SUBVENDOR/SUB-
CONTRACTOR that he is required to supply design calculations, drawings, inspection reports and test
certificates strictly in accordance with this specification and technical information. The SUB-
VENDORS/SUB-CONTRACTORS should also be reminded that they shall include with their offer all tools
and appliances necessary for proper maintenance and all spare parts. Itemized prices of the recommended
spare parts shall be submitted together with the appropriate part numbers and drawings.
4. MATERIAL TESTS
4.1 In the event of the PURCHASER/CONSULTANT being supplied with the certified particulars of tests which
have been carried out for the VENDOR/CONTRACTOR by the supplier of material, the
PURCHASER/CONSULTANT may, at his own discretion, accept the same as proper evidence of
compliance with the requirements of appropriate specifications for the materials.
4.3 Critical materials used in manufacture of the equipment and construction of the plant covered by the
PURCHASE ORDER/CONTRACT may also be subjected to one or more of the Non-Destructive Tests
(NDT) as called for in the enquiry document or as mutually agreed. Salvaging of material due to
unacceptable defect is to be attempted by the VENDOR/CONTRACTOR only after getting specific
concurrence from the PURCHASER/CONSULTANT and according to the approved procedures.
5. INSPECTION AND TESTING OF WELDING
5.1 All welding shall be as per standard specifications. Flanged joints shall also be provided to match the
connecting ends of equipment, valves or where specified. Where specific equipment-piping connection
necessitates several joints, unions shall also be provided. Only qualified welders proficient in welding in the
vertical and overhead positions shall be allowed to weld these pipelines. Preferably welders with proficiency
certificate from Govt. Test House or equivalent recognized authority should be put on the job. It shall be
CONTRACTOR's responsibility to arrange for and bear all costs towards testing of welders.
a. The following steps shall be taken besides controlling quality in general, to make effective control in
carrying out welding:
i) Welding procedure (PQR & WPS) shall be prepared in line with prescribed standard and tests shall
be carried out to qualify the procedures. Number of procedures will depend on variables like
positions of welding, thickness range, etc. Once a welding procedure is qualified, strict adherence
to it shall be made during actual welding.
ii) Welders employed shall be qualified as per prescribed standard. CUSTOMER/PURCHASER will
have the right to check/ witness the certificate(s) / test(s) before and / or during execution of work.
iii) Where applicable, welders shall be tested as detailed in codes specified for pipe welding, vessel
welding and structural welding and appropriate to the corresponding weld position using test pieces
of appropriate parent metal to be used on the job. The PURCHASER/CONSULTANT shall have
the right to have any welder re-tested at any time during the PURCHASE ORDER/CONTRACT.
iv) Makes of welding consumables such as electrodes, filler wires, argon, etc. shall be approved by
CUSTOMER/PURCHASER before using it. Such consumables are, however, subject to qualifying
initial check tests as per ASME codes. These consumables are in the scope of supply of
CONTRACTOR.
v) The CONTRACTOR shall submit batch test certificates, from the electrode manufacturers, giving
details of physical and chemical tests carried out by them, for each batch of electrodes to be used.
vi) Guidelines for acceptance of weld defects detected by radiographic / ultrasonic tests, wherever
applicable, shall be governed by prescribed standard.
b. Radiography and Inspection of welds
i) Radiographic examination shall be carried out by approved agency (having min level 2 certification)
arranged by the CONTRACTOR at his cost.
ii) Weld areas to be radiographed shall be designated by the ENGINEER-IN-CHARGE/ ENGINEER
or his representative. Overall 10% of the joints shall be radiographed. Cost towards radiography of
the pipelines shall be included in the erection cost of pipeline. However, for firefighting hydrant /
foam lines, radiography is not envisaged.
iii) Radiographs of the welds shall be taken as soon as the welding of joint is completed. If repairs are
required they shall be carried out before continuing the other welds.
iv) Repeat radiography due to CONTRACTOR fault or additional radiography necessitated due to poor
performance of CONTRACTOR/welders shall be done at CONTRACTOR cost.
v) Welds found faulty as a result of radiographic, visual or other tests must be chipped off to the
satisfaction of the ENGINEER-IN-CHARGE/ ENGINEER and welded as per specifications and
instructions. The welded portion shall be re-tested as per the instructions of the ENGINEER-IN-
CHARGE/ ENGINEER or his representative. No claims for compensation whatsoever shall be
entertained on this account.
vi) For each weld performed by a welder found unacceptable, two additional checks shall be carried
out on welds performed by the same welder. This operation is iterative and that of the two
additional welds for each weld deemed unsatisfactory shall be continued till such time that two
consecutive welds of satisfactory quality are found for every defective weld.
vii) The CONTRACTOR shall carry out these additional radiographic testing at his own expense. To
avoid the possibility of too many defective welds by a single welder remaining undetected for a
long period to time, the CONTRACTOR shall promptly arrange for radiographic examination so that
there is no accumulation of defective joints.
viii) Hydrotest procedure
Hydrostatic (Hydro) Testing is a process where components such as piping systems, equipment,
and pressure vessels are tested for strength and leaks. Hydro tests are often required before start
up, after shutdowns and repairs in order to validate that equipment will operate under desired
conditions once returned to service.
ix) Recommendations of applicable codes shall be followed for non-destructive tests, wherever
applicable.
5.2 Copies of all welding procedures, procedure qualification records, welders ‘performance qualification
certificates, post-heating and stress relieving records, NDT records and other test results shall be made
available upon request of the PURCHASER/CONSULTANT.
5.3 The PURCHASER shall have free access to inspect welding or any other related operations at any time and
at any stage of fabrication.
5.4 The PURCHASER may require non-destructive testing of any weld for reasons other than those given in the
specification. The responsibility for the cost of such testing shall be mutually decided between the
PURCHASER and the CONTRACTOR.
5.5 The CONTRACTOR shall inform the PURCHASER when the weld preparation and setting up for welding of
various members selected by the PURCHASER is in progress so that the PURCHASER can inspect the
assembly before welding starts.
5.6 Any examination by non-destructive methods on low alloy steels shall be performed after post weld heat
treatment.
5.7 For a welded branch connection, the examination of and any necessary repairs shall be completed before
any reinforcing pad is added.
6. EXAMINATION OF WELD
6.1 Examination refers to the quality control functions performed by the CONTRACTOR during fabrication,
erection and testing.
6.2.1 Materials and components to ensure that these are as per the specification and are free from defects. If
defects are noticed on “free issue” items, these shall be brought to the notice of the PURCHASER without
delay.
6.2.2 Joint preparation and cleanliness
6.2.3 Preheating as applicable
6.2.4 Fit-up, joint clearance, and internal alignment prior to joining
6.2.5 Variables specified by the welding procedure, including filler material, position and electrode
6.2.6 Condition of the root pass after cleaning - external and where accessible, internal
6.2.7 Slag removal and weld condition between passes
6.2.8 Appearance of the finished joint
7. INSPECTION OF EQUIPMENT & COMPONENTS
7.1 The CONTRACTOR shall undertake the inspection of all components to be erected sufficiently in advance,
to check their soundness, conformity to the approved VENDOR’s drawings and their compatibility with the
approved erection procedure.
7.2 All inspection and tests on bought out items shall be made as required by specifications forming part of this
contract. Various stages of inspection and testing shall be identified after receipt of Quality Assurance
Programme from the CONTRACTOR / manufacturer.
7.3 Inspection calls shall be given, as per mutually agreed programme in prescribed proforma, giving details of
equipment and attaching relevant test certificates and internal inspection report of the CONTRACTOR. All
drawings, general arrangement and other contract drawings, specifications, catalogues etc. pertaining to
equipment offered for inspection shall get approved by CUSTOMER/PURCHASER and copies shall be
made available to CUSTOMER/PURCHASER before hand for undertaking inspection.
7.4 All inspections and tests shall be made as required by the specifications forming part of this contract.
CONTRACTOR shall advise CUSTOMER/PURCHASER in writing at least fifteen days in advance of the
date of final inspection / tests. Manufacturer’s inspection or testing certificate for equipment and materials
supplied may be considered for acceptance, at the discretion of ENGINEER-IN-CHARGE/ ENGINEER. All
costs towards related testing at site etc. shall be borne by the CONTRACTOR within their quoted rates.
7.5 The CONTRACTOR shall ensure full and free access to the inspection engineer of
CUSTOMER/PURCHASER at the CONTRACTOR or their sub-contractor’s premises at any time during
contract period to facilitate him to carry out inspection and testing assignments.
7.6 The CONTRACTOR / SUB-CONTRACTOR shall provide all instruments, tools, necessary testing and other
inspection facilities to inspection engineer of CUSTOMER/PURCHASER free of cost for carrying out
inspection.
7.7 Where facilities for testing do not exist in the CONTRACTOR / SUB-CONTRACTOR’s laboratories, samples
and test pieces shall be drawn by the CONTRACTOR / SUB-CONTRACTOR in presence of Inspection
Engineer of CUSTOMER/PURCHASER and duly sealed by the later and sent for tests in Government
approved test house or any other testing laboratories approved by the Inspection Engineer at the
CONTRACTOR cost.
7.8 The CONTRACTOR shall comply with the instructions of the Inspection Engineer fully and with promptitude.
7.9 The CONTRACTOR shall check the Total Indicated Run outs (TIR) on the shafts, mounted couplings and
other rotary elements to be within prescribed limits which may in any case, unless specified otherwise, not
exceed 0.03 mm. The TIR of motor’s shaft concentricity of spigots and perpendicularity or parallelism of
mounting face to shaft axis shall be as specified in contract. In case of motors of speed more than 1000 rpm
‘precision ‘class TIR limits shall be applicable. Any deviations in this regard shall be brought to the notice of
the ENGINEER before the CONTRACTOR undertakes the erection.
7.10 Drive couplings should not be loose with driver and driving equipment. Notice the arrangement and
same shall be attended for proper installation.
7.11 The base/sole plate of the machine shall be checked sufficiently in advance for correctness of mounting
holes with respect to the machine centerlines and anchor bolts provided on foundation, coplanar accuracies
of the mounting pads of the base/sole plate, number and location of jackscrews, vent holes for grouting
purposes in all bulk head section etc. The CONTRACTOR shall check the adequacy and compatibility of
erection procedures with respect to the base/sole plates. The CONTRACTOR shall also check for any
distortion or damage to the mounting reference faces during transit and bring to the notice of the
ENGINEER any defect in order that corrective action could be undertaken in time.
7.12 The CONTRACTOR shall remove any protective coatings and paints on base/sole plates where they are to
be embedded in concrete by approved means. Likewise machine components that shall be cleaned by
approved means before assembly may be received loose with protective coatings and other preservation
measures. The CONTRACTOR shall be responsible for removal of coatings and preparation of such
components for assembly providing all enabling aids as per the MANUFACTURER’s/ENGINEER’s
directions.
7.13 The CONTRACTOR shall ensure that the equipment / assemblies / component of the plant and equipment
required to be inspected are not assembled or dispatched before inspection. In case of, equipment
assembled at site, all components shall be checked for mounting/mating accuracies and run outs before
assembly. The ENGINEER will generally provide the mounting/mating tolerances of such components for
the CONTRACTOR’s guidance where such data is made available by MANUFACTURER.
7.14 VENDOR’s match marks shall be followed precisely during assembly. Extra care shall be exercised while
unpacking and dismantling of dynamically balanced components carefully identifying like coupling halves,
coupling pins, rotor elements, fasteners, keys etc. in order they are used in the appropriate places, so as not
to affect the dynamic balancing carried out by VENDOR. The ENGINEER shall be kept informed of any
discrepancy noticed in this regard.
7.15 On satisfactory completion of final inspection and testing, all accepted plant and equipment shall be
stamped suitably and inspection certificate shall be stamped suitably and inspection certificate shall be
issued in requisite copies for all accepted items. For stage inspection and for rejected items, only inspection
memo shall be issued indicating there in the details of observations and remarks.
7.16 Final Testing and Inspection will be witnessed by Local Authorized Agency / AIA. The arrangement like
special tools, tackles and consumables required carrying out the final testing and inspection, is in the scope
of CONTRACTOR. Any deviations/ defects observed in the free supply by CUSTOMER/PURCHASER will
be rectified by the CONTRACTOR at extra cost. Any deviations/ defects observed during the final inspection
shall be rectified by the CONTRACTOR at his own cost.
8. FABRICATION AND INSPECTION
Fabrication and inspection procedures for vessels, heat exchangers, pipes, tubes and valves etc. shall be in
accordance with procurement specifications, quality plan, applicable codes or any other approved equal.
9.1 All paint materials including primers and thinners shall be procured directly from approved manufacturers by
CONTRACTOR and shall be accompanied by manufacturer’s test certificates. Paint formulations without
certificate shall not be accepted.
9.2 The CONTRACTOR shall provide for the purpose of inspection, thickness measuring instrument (Elcometer
or other approved device), access ladder, lighting, personnel and any other necessary item at no extra cost
to the PURCHASER.
9.3 The PURCHASER may call for batch-wise physical and chemical tests for paint materials. CONTRACTOR
shall arrange to have such tests performed including batch-wise test of wet paints for physical & chemical
analysis as per relevant standard test method. All costs there shall be borne by the CONTRACTOR. The
CONTRACTOR shall produce test reports from manufacturer regarding the quality of the particular batch of
paint supplied. The ENGINEER-IN-CHARGE shall have the right to test wet samples of paint at random for
quality of same. Batch test reports of the manufacturers for each batch of paints supplied shall be made
available by the CONTRACTOR.
9.4 The work involved shall be subject to inspection by the PURCHASER at all times. In particular the following
stage inspections shall be carried out and the CONTRACTOR shall offer the work for inspection and obtain
approval at every stage before proceeding with the next stage. The record of inspection shall be maintained
in the registers. Stages of inspection are as follows:
Surface preparation
Each coat of primer application
Each coat of finish paint application
Any defects noticed during various stages of inspection shall be rectified by the CONTRACTOR to the
satisfaction of the PURCHASER before proceeding further. Irrespective of the inspection, repair and
approval of intermediate stages of work, the CONTRACTOR shall be responsible for making good the
defects found during final inspection and during the guarantee period.. Dry film thickness (D F T)) shall be
checked and recorded after application of each coat and extra coat of paint should be applied to make-up
the DFT specified without any extra cost to CUSTOMER/PURCHASER, the extra coat should have prior
approval of ENGINEER-IN-CHARGE.
9.5 In addition to above, record should include type of shop primer already applied on equipment e.g. Red oxide
zinc chromate or zinc chromate or Red lead primer etc.
9.8 The CONTRACTOR shall provide standard thickness measurement instrument with appropriate range(s) for
measuring.
9.9 Dry film thickness of each coat, surface profile gauge for checking of surface profile in case of sand blasting.
Holiday detectors and pinhole detector and protector whenever required for checking in case of immersion
conditions.
9.10 Prior to application of paints on surfaces of chimneys, the thickness of the individual coat shall be checked
by application of each coat of same paint on M. S. test panel. The thickness of paint on test panels shall be
determined by using gauge such as 'Elkometer'. The thickness of each coat shall be checked as per
provision of this specification. This shall be approved by ENGINEER-IN-CHARGE before application of
paints on surface of chimney.
9.11 At the discretion of ENGINEER-IN-CHARGE, the paint manufacturer must provide the expert technical
service at site as and when required. This service should be free of cost and without any obligation to the
CUSTOMER/PURCHASER, as it would be in the interest of the manufacturer to ensure that both surface
preparation and application are carried out as per their recommendations. The CONTRACTOR is
responsible to arrange the same.
9.12 Final inspection shall include measurement of paint dry film thickness, Adhesion, Holiday detection check of
finish and workmanship. The thickness should be measured at as many points/ locations as decided by
ENGINEER-IN-CHARGE and shall be within + 10% of the dry film thickness, specified in the specifications.
9.13 The CONTRACTOR shall arrange for spot checking of paint materials for Sp.gr., glow time (ford cup) and
spreading rate.
9.14 All results of inspection and tests shall be recorded in the inspection and acceptance reports. These reports
shall be submitted along with completion documents.
9.15 The CONTRACTOR shall arrange expert technical service at site from the paint manufacturer, free of cost,
in case of any problem as and when required by the PURCHASER.
9.16 After completion of work the CONTRACTOR shall check and demonstrate to the PURCHASER that the
DFT measured at least at 20 points on each item painted is not less than the specified thickness.
Inadequate DFT shall necessitate the application of a further coat or coats of paint at no extra cost to the
PURCHASER. The DFT shall be checked by using an Elcometer or other approved device.
10. INSPECTION AND TESTING OF INSTRUMENTS
10.1 Verify that tests required to verify conformance of an item to specified requirements, and to demonstrate
satisfactory performance for service, are planned and executed. Verify that the characteristics to be tested
and test methods to be employed are specified. Verify that test results are documented and their
conformance with acceptance criteria is evaluated.
10.2 Verify that the applicant has established controls for tools, instruments, gauges and other M&TE used for
quality-affecting activities. Verify that M&TE is controlled, calibrated (at specified periods), and adjusted to
maintain accuracy within necessary limits.
10.3 Verify that the applicant has established the requirements to identify the status of inspection and test
activities. Verify that the status is indicated either on the items or in documents traceable to the items, where
it is necessary to assure that required inspections and tests are performed, and to assure that items that
have not passed the required inspections and tests are not inadvertently installed, used, or operated.
Note:
The following equipment shall also receive attention at this stage:
Special high-signal or low-signal selectors calculating relays, etc. shall be adjusted;
The mechanical min/max stop on control valves shall also be adjusted;
The position of limit switches shall be checked and adjusted;
Selector switches shall be checked.
11. INSPECTION FOR ELECTRICAL PANELS
11.1 Gaps or a missing grounding system: The grounding system provides an easy path for electricity to flow to
the earth, should a problem like a short circuit occur. Allowing current to flow in this way helps a circuit
breaker trip, preventing fire and shock. Without a ground path, a person is at risk of becoming the ground,
resulting in electrocution.
11.2 Rust or corrosion: Watch for any rust around the panel, as well as circuit breakers that may not trip in
response to an over current, due to internal corrosion. If breakers have these characteristics, replace them.
If an electrical panel is badly corroded, the entire panel needs to be replaced.
11.3 Evidence of overheating: Watch for signs of melting or burning inside the electrical panel.
11.4 Signs of improper bonding: Look for improper wiring or damaged equipment in general.
12.1 GENERAL
The tests at works shall include electrical, mechanical and hydraulic tests in accordance with the
appropriate clauses of Statutory Regulation, relevant codes and standards and approved drawings and
specifications and in addition any test called for by the PURCHASER/CONSULTANT to ensure that the
plant being supplied fulfils the requirements of the specifications. The VENDOR/CONTRACTOR shall carry
out all the shop tests and inspections as specified in addition to those normally required as per codes and
standards. For items not covered by any code or specifically mentioned in the specifications, the tests are to
be agreed with by the PURCHASER/CONSULTANT. If considered necessary by the
PURCHASER/CONSULTANT, multi-part assemblies shall be fully erected and tested in the works prior to
packing and dispatch to the site.
12.3 CALIBRATION
All instruments used for critical measurement such as pressure gauges for leak tests, instruments for
measuring performance parameters; instruments for precision dimension measurements shall have valid
calibration certificates traceable to national standards. This means that the calibrating agency engaged by
the VENDOR/CONTRACTOR shall use instruments which are intern calibrated by Government approved
agencies and such information shall be recorded in the calibration certificate issued by the calibrating
agency by giving the certificate number, date and date of validity of the certificate given by the Government
approved agency.