Vous êtes sur la page 1sur 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/256439080

On Assessment of Existing Offshore Structures

Conference Paper · January 2002

CITATIONS READS
2 479

2 authors:

Gerhard Ersdal Ivar Langen


University of Stavanger (UiS) University of Stavanger (UiS)
37 PUBLICATIONS   207 CITATIONS    34 PUBLICATIONS   105 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Ageing Structures View project

OMAE2011-49959 View project

All content following this page was uploaded by Gerhard Ersdal on 04 July 2014.

The user has requested enhancement of the downloaded file.


On Assessment of Existing Offshore Structures
Gerhard Ersdal
Norwegian Petroleum Directorate and Stavanger University College
Stavanger, Norway

Ivar Langen
Stavanger University College
Stavanger, Norway

assessment procedures are proposed. A few of these will be discussed


ABSTRACT in the following text.

The methods normally used for assessment of existing offshore In order to evaluate the risk of structural failure, it is of importance to
structures are based on design level check, ultimate strength check or analyse the possible structural failure scenarios, and what are the
on a probabilistic approach. There are arguments against all these defences and barriers against these scenarios. This is discussed in
methods. Design level analysis are claimed to be very conservative, as Ersdal (2002), and the main conclusions are given here. The question of
after some years of experience the knowledge of the structure are acceptable low risk is also important, but this is not further discussed in
increased compared with design. Ultimate strength analysis are claimed this paper.
to cover only a small part of the hazards that should be analysed. The
probabilistic approach is claimed to be model dependent and to give In general terms the existing assessment procedures consist of the
inconsistent results between analysis groups, as the subjective choices following steps:
of the analyst are of significant importance. It is also claimed that there - Platform identification (when should assessment be initiated)
is no reasonable target reliability in a reliability approach, but that this - Information review (Design, fabrication, installation and
has to be established in each case dependant on the methods and operation history)
models that are used. The probabilistic approach is tending towards a - Screening (major damages, major changes, deviations from
Risk approach, but is claimed to not fully appreciate all the possible design)
hazards for an offshore structure. - Analysis of the structure (design analysis, ultimate strength
analysis or probabilistic analysis)
This paper describes procedures for safety assessment of existing - Acceptable as is, modification needed or abandonment.
offshore structures as described in ISO 13819-1 (ISO 1995), API The different methods of analysis of the structures are the main purpose
RP2A-WSD (API 2001), ISO/DIS 13822 (ISO 2000) and of this paper, but the other items will also be described.
ISO/CD19902 (ISO 2001). The procedures are presented and discussed
as how they are capable of being measured against a goal of even and The most general accepted standard for offshore structures are the ISO
acceptable risk for the society. 13819-1 “Petroleum and natural gas industries – Offshore Structures –
Part 1: General Requirements”. This standard gives general design
KEY WORDS: Structures, Safety Assessment, Regulations, rules and general rules for assessment of existing structures. The
Standards, Structural analysis, push-over analysis, Reliability analysis. Norwegian regulations (NPD 2001) refer to NORSOK N-001
(NORSOK 2000) for structural design, which again refer to ISO 13819-
INTRODUCTION 1 for assessment of existing structures. However, ISO 13819-1 is a
rather general standard, not very specific on how to perform
Assessment of existing structures is performed in order to extend assessment. The standard gives some indications that Design Code
service life of the facility, as new methods of production and new format, Reserve Strength Ratio format and a probabilistic format is
discoveries may give life extension of fields. Also addition of more acceptable. More details are given in other standards, like API RP2A-
equipment and more personnel, and deterioration and damage of the WSD (API 2001), ISO/DIS 13822 (ISO 2000) and ISO/CD19902 (ISO
structure may lead to a need for assessment. The use of the existing 2001). Procedures are also proposed in different papers and by other
installations will in many cases, even with major upgrading of the organizations, but these will not be reviewed in detail here.
present condition, be preferable from an economic point of view
compared to installing new installations. An assessment of existing Most procedures for assessment of existing fixed offshore structures
installation for possible extension of lifetime should prove that the risk describe a method that is somewhat more relaxed compared to design
of structural failure is acceptable. In order to achieve this, several codes. They typically use deterministic Design Code format (equal to

Paper No. 2002-JSC-379 Ersdal 1


the original requirements or based a reduced load level), probability Table 1: Assessment versus design, Kallaby et al (1994) and Moan and
approach or a Reserve Strength Ratio (RSR) format. Vårdal (2001)
Design criteria Assessment criteria
A reasonable goal could be to have an existing structure of the same Environment Forecast from existing As criteria for “new “
level of safety as a newly designed structure, assuming that a structure data collection platform, with inclusion of
designed according to standards and regulation has the appropriate recent data collection and
safety level. Hence, one could argue that the same design code should use of:
be used in assessment of existing structures. However, there are some - current state of the art
differences in the knowledge about an existing structure and a structure review
in design phase. The knowledge about the structure is increased and the - experience from adjacent
accuracy of the analysis could be improved compared with the design fields
analysis. Also, the life extension time for the structure will in most - hindcasting from actual
cases be less than the initial design life. field sea-states
Loading Conservative Conservative evaluation
The conservatism included in standards and regulation in order to take evaluation from from as-built records and use
care of uncertainties (material selection, fabrication methods, etc) at the proposed use of of recent survey info on:
design stage may be excluded. The regulations also tends to use very structure - marine growth
simplified formulations for utility, capacity etc under the assumption - appurtenances
that the formulas should be easy to use rather than the most exact - removals / additions
formulation. These differences are discussed in Kallaby et al (1994) - topsides weight control
and Moan and Vårdal (2001), and a summary of these discussions is - wind areas
shown in Table 1. Foundation Forecast from site As criteria for “new”
investigation and platform with inclusion of:
Most of these items could be claimed to be up-dated information that laboratory testing of - current state-of-the-art
should normally be included in an assessment situation. If the up-dated soils review
information gives a positive result with regards to the safety of the - experience form adjacent
structure, this should be accounted for. In other situations, the fields
information may indicate a reduced safety of the structure, which - post-drive foundation
should also be accounted for. If this information and updated analyses
calculations result in a structure complying with the design code - scour survey and
standard, it should be accepted as fit for purpose. maintenance
Structural Topology and The structural dimension are
Most procedures claims that a lower acceptance criteria can be used for model dimensions may be fixed and known.
assessment of existing structure compared to design, e.g. lower load changed. In-service inspection may be
factors or Reserve Strength Ratio criteria. Moan and Vårdal (2001) No service inspection applied.
conclude based on Table 1 that in design “High uncertainty requires a available.
large safety margin”, but in an assessment situation “Reduced Conservative
uncertainty and a reduced safety margin may be applied”. This is modelling using global
probably the main assumption for accepting lower design values in an percentages to cover
assessment of an existing structure compared to a new structure. In our not-finalized details
opinion, if lower acceptance criteria should be allowed it must be based and simple geometric
on the reasoning that the epistemic uncertainties are reduced after some assumptions.
years of experience, and that e.g. 10 years of experience prove to some Stress The time for analysis is The quality of the analysis is
extent that the structure is in the “lucky” end of the strength analysis critical. critical. Sufficient time for
distribution. For a structure where the risk of failure is dominated by Strict compliance with model tests, removing of
the fatigue failure modes, the “no detection of a propagating crack” code of practice and conservatism where
after 10 years of service will be a indicator of improved reliability. But regulatory documents. possible, redundancy studies
for a structure that is dominated by other failure modes, this may not be to determine ultimate
the case. For instance a structure that is dominated by failure due to strength of structure and
wave in-deck will not benefit from the same information unless the foundation, sensitivity
structure has experienced severe weather. studies on various
parameters to improve
Other ways of reducing the risk of a structure are to introduce risk confidence levels.
prevention and mitigation procedures, e.g. by inspection and Results Structure has members Structure has some stresses
maintenance program, strengthening of structure or evacuation and joints with up to yield stress, but some
procedures. acceptable utilization. assessment standards allow
for some yielding if the
structure has proven strength
and redundancy.

Paper No. 2002-JSC-379 Ersdal 2


ASSESSMENT PROCESS PROPOSED IN API RP 2A WSD Lateral environmental load may be reduced to 85% of the 100-year
condition for high consequence platforms, and to 50% for low
The API RP 2A WSD is the most commonly used standard for design consequence platforms.
of fixed offshore structures in the United States. The standard is also
used in countries outside US, but is not commonly used in Norway. 2: Ultimate strength analysis
However, the standard is of interest as it is the only one of the generally Ultimate strength analysis is regarded to be a complex and less
used offshore standards that has taken into account assessment of conservative check.
existing structures to a detailed level.
Reserve strength Ratio (RSR) is defined as the ratio of platforms
Application of the API standard ultimate lateral load carrying capacity to its 100-year environmental
The standard is stated to be applicable only for the assessment of condition lateral loading.
platforms, which were designed in accordance with 20th or earlier
editions of the same API standard. Structures designed after the 21st A RSR of 1.6 is required for high consequence platforms, and 0.8 for
edition, should be assessed in accordance with the criteria originally low consequence platforms.
used for the design. By this clause API is limiting the possibility for
using assessment of existing structure to minimize the structural cost by In addition, the following are regarded as acceptable alternative
building a platform intended to have extra modules, but not fully assessment procedures subjected to some limitations:
designed for these additional modules, and then adding them later in an - Assessment of similar platforms by comparison
assessment program under reduced criteria. - Assessment through the use of explicit probabilities of failure
- Assessment based on prior exposure, surviving actual exposure to
The API procedure an event that is known with confidence to have been either as severe or
A flow chart of a general procedure is shown in Figure 1. The API RP more severe than the applicable ultimate strength criteria based on
2A gives two different approaches, on some stages, one for the Gulf of exposure category.
Mexico and another for other US areas. Only the “other US areas” part
of the procedure is included, as this seems to be the most general ASSESSMENT PROCESS PROPOSED IN ISO/CD 19902
approach.
ISO 19902 is also so far only a draft standard, and changes in this
Platform selection / Needs for assessment standard might occur in the final version. Earlier versions of this ISO
API requires an assessment of an existing platform if one of the standard have been based on API. This paper review the draft E, issued
following indicators exists: in June 2001.
- Addition of personnel
- Addition of facility The standard states that it is the owners responsibility to maintain and
- Increased loading demonstrate fitness for purpose of the platform, for its specific site
- Inadequate deck height conditions and operating conditions.
- Damage found during inspection
The goal should be to demonstrate that the probability of a structural
Categorization failure that leads to an unacceptable consequence is acceptably small.
If a platform (structure) is selected for an assessment, it should be The acceptable risk level should be defined by statutory requirements,
categorized with respect to human life safety (manned-non-evacuated, industry practices in the considered region, or by owner’s corporate
manned-evacuated, unmanned) and consequence of failure (high policy, whichever is more onerous.
consequence or low consequence).
Application of the draft ISO 19902 standard
Condition assessment The standard is intended for application to existing jacket platform
When the platform (structure) is identified for assessment, a survey substructures, but could also be used for topside structures.
program should be performed to verify the platforms condition.
Updating of drawings should, if necessary, be performed in this phase. However, so far no regulations are giving reference to this standard, as
it still is a draft standard.
The following questions should be asked:
- Is platform damaged? The ISO 19902 procedure
- Is deck height inadequate? A flow chart of a general procedure is shown in Figure 1.
- Has loading increased?
- Is platform unmanned and with low consequence? Platform assessment indicators triggered / Needs for assessment?
If “No” can be answered to all these questions, the platform (structure) An existing platform should undergo an assessment to demonstrate
can be accepted as it is, and further assessment is not necessary. fitness for purpose if one or more of the following conditions exist:
- Exceedance of intended design life.
Analysis Check - Damage or detoriation of a primary structural component.
There are two potential sequential analysis checks: Minor damage may be accepted, but the cumulative effects of
damage should be documented and accounted for in a global
1: Design level analysis. resistance assessment.
The design level analysis si regarded to be a simpler and more - Changes from the original design or from previous
conservative check. Design level analysis procedures are similar to assessment basis:
those used for new platform design, including the application of all o Addition of personnel or facilities;
safety factors, the use of characteristic rather than mean yield stress, o Modification of facilities;
etc. o More onerous environmental criteria;

Paper No. 2002-JSC-379 Ersdal 3


o More onerous component or foundation resistance height should be checked for potential inundation as this may limit the
criteria; overall structural reliability. The asymmetry of the wave crest versus
o Physical changes to the platform’s design basis, wave height should also be considered. Other loadings should be
e.g. scour or subsidence; considered as for design.
o Inadequate air gap.
Resistance assessment
Screening criteria In general, the assessment of structural components is to be performed
Screening criteria should be developed for the exposure levels of in accordance with the design analysis clauses of the ISO19902
structures being considered, taking into account the remaining service standard, taking into account the current condition or future intended
life, structural condition monitoring records, long term environment, condition, accounting for any damage, repair, scour, modifications, or
degree of confidence in modelling assumptions, sensitivity to analysis other factors that may affect the structural performance or integrity.
assumptions, redundancy and collapse behaviour and structural
deformation (with particular consideration to potential escalation events Two optional methods are offered:
and impairments of lifesaving equipment, escape routes, and temporary - Design level analysis: All appropriate partial action and
refuges). Screening criteria may be developed based on the following resistance factors are to be applied. If all components within
methods: the structure, and foundation, are assessed to have utilization
- Explicitly calculated probabilities of failure less than or equal to unity, the structure is to be considered to
- Risk based structural Reserve Strength Ratios (RSR) be fit for purpose.
- Comparison with similar platforms - Ultimate strength analysis: An ultimate strength analysis can
- Based on prior exposure. be used in order to demonstrate that a platform has adequate
However, fulfilment of the strength criteria’s given in the standard is strength and stability to withstand a significant overload.
the primary recommended method. Local overstress and potential local damages are accepted,
but total collapse or excessive / damaging deformations is to
Platform condition assessment be avoided.
Sufficient information must be collected to allow for an engineering
assessment of the platform’s overall structural integrity. Information of A simplified ultimate strength analysis, called linear elastic redundancy
the platform’s structural condition and facilities, with particular analysis, is also proposed. If a member or joint do not have utilization
attention to data that cannot be explicitly verified (e.g. pile penetration), equal to or lower than unity, this member can be removed from the
should be collected. General inspection of topside, underwater, splash structural model. If it is demonstrated that the load redistribution can be
zone and foundation should be performed, and decision on whether accommodated without causing further components to exceed their
more detailed inspections and possible soil borings is necessary, should maximum utilization, the structure is considered fit for purpose.
be performed based on engineering judgement.
ASSESSMENT PROCESS PROPOSED IN ISO/DIS 13822
The following information should be made available:
- General information (original and current owner, original and ISO 13822 is so far only a draft international standard, and changes in
current platform use and function, location, water depth, this standard might occur in the final version. This paper review the
orientation, platform type (caisson, tripod, 4-6-8 leg, etc), draft issued in 2000. The two standards mentioned previously are both
number of wells and risers, production rate, manning level, mainly based on reserve strength analysis and design analysis, while
performance during past extreme environmental events. this is mainly a pure reliability based assessment standard.
- Original design (design contractor, design date, design
drawings, material specifications, design code used and Application of the ISO 13822 standard
edition, environmental criteria (wind, wave, current, seismic, The standard is intended for application to the assessment of any type
ice, etc), deck clearance elevation, operation criteria (deck of existing structure that was originally designed, analysed and
loading and equipment arrangement), soil data, number, size specified based on accepted engineering principles and/or design rules,
and design penetration of piles and conductors, as well as structures constructed on basis of good workmanship,
appurtenances). historic experience and accepted professional practice.
- Construction (fabrication and installation contractors, date of
installation, as built drawings, fabrication, welding and The ISO 13822 procedure
construction specifications, material traceability records, pile A flow chart of a general procedure is shown in a flow diagram in
and conductor driving records, pile grouting records) Figure 1.
- Platform history (environmental loading history, operation
loading history, accidental loads, survey and maintenance Request / Needs for an assessment
records, repairs (descriptions, analysis drawings and dates), The assessment may be initiated under the following circumstances:
modifications (descriptions, analysis drawings and dates)). - an anticipated change in use or extension of design working
- Present condition (all decks – actual size, location, elevation, life;
loading and equipment arrangement, field measured air gap, - a reliability check as required by authorities, insurance
production and storage inventory, appurtenances – current companies, owners etc.
list, sizes and location, wells – numbers, size and location of - structural detoriation due to time dependent actions (e.g.
existing conductors, recent surveys. corrosion, fatigue)
- structural damage by accidental actions
Action assessment
Metocean data required for assessment is stated to be the same as for Specification of assessment objectives
design, except that the current air gap and allowance for any future The objective of the assessment shall be specified in terms of future
subsidence, within the design life, should be determined. The deck performance required for the structure in an agreement with owner,

Paper No. 2002-JSC-379 Ersdal 4


authorities and the assessing engineer. The required future performance carried out to ensure a target reliability level that represents
shall be specified in the utilisation plan and safety plan. the required level of structural performance.

Scenarios Results of assessment


Scenarios related to a change in structural conditions or actions should - A report form the assessment should be issued, including
be specified in the safety plan in order to identify possible critical scope of assessment, conclusions with regards to the scope,
situations for the structure. sufficient or insufficient reliability, description of structure,
investigations, analysis, verification, discussion of evidence,
Preliminary assessment review of intervention options, conclusions and
Preliminary assessment is described to contain the following activities: recommendations for interventions, inspection and
- Study of documents and other evidence. These documents maintenance plan and documented information.
should be verified with respect to correctness and in - Conceptual design of construction interventions. If the
particular whether documents were updated after previous structural safety or serviceability is shown to be inadequate,
interventions to the structure. Other evidence, such as the the results of the assessment should be used to recommend
occurrence of significant environmental or seismic actions, construction interventions for repair, rehabilitation, or
large actions, change in soil conditions, corrosion, and upgrading of the structure.
misuse of the structure, must be recorded and documented. - Control of risk. An alternative approach to the structure
- Preliminary inspection. Identify the structural system and intervention, which may be appropriate in some
possible damage of the structure by visual observation with circumstances, is to control or modify the risk by imposing
simple tools. load restrictions, altering aspects of the use of the structure,
- Preliminary checks. The preliminary checks should identify and implementing monitoring and control regime.
the critical deficiencies related to the future safety and
serviceability of the structure with a view to focusing Judgement and decision
resources on these aspects in subsequent assessment. Based The client in collaboration with the relevant authority should make the
on these results, it is then judged whether a further final decision on interventions, based on engineering judgement and the
investigation is necessary or not. recommendations in the report and considering all the information
- Decisions on immediate actions. If the preliminary inspection available.
clearly indicates that the structure is in a dangerous condition,
it is necessary to reduce the danger with respect to public Assessment based on satisfactory past performance
safety. ISO 13822 also opens for an assessment based on satisfactory past
- Recommendations for detailed assessment. The preliminary performance, stating that a structure may be considered safe to resist
inspection may clearly show the specific deficiencies of the actions other than accidental actions provided:
structure, or that the structure is reliable for its intended use - careful inspection does not reveal any evidence of significant
over the remaining working life, in which case a detailed damage, distress or detoriation;
assessment is not required. If there is uncertainty in the - the structural system is reviewed, including investigation of
actions, action effects or properties of the structure, a detailed critical details and checking them for stress transfer;
assessment should be recommended. - the structure has demonstrated satisfactory performance for a
sufficiently long period of time for extreme actions due to use
Detailed assessment and environmental effects to have occurred;
Detailed assessment should include the following activities: - there have been no changes for a sufficiently long period of
- Detailed documentary search and review. Drawings, time that could significantly increase the actions on the
specifications, structural calculations, construction records, structure or affect its durability, and no such changes are
inspection and maintenance records, details of modifications, anticipated.
regulations, code of practice which were used for
constructing the structure, topography and subsoil conditions Very few offshore structures have experienced the environmental
should be reviewed. conditions that the current design codes require, so this method is not
- Detailed inspection and material testing. Dimensions of the relevant in most cases, and will be disregarded in the following
structure and characteristic values of material properties discussion.
should be determined from documents of from detailed
inspection and material testing. THE SAFETY OF AN OFFSHORE STRUCTURE
- Determination of actions. Principles for determining actions
should be in accordance with ISO 2394 (ISO 1998) for In order to assess an existing offshore structure it is important to
ultimate limit state and service limit state including fatigue. evaluate failure scenarios and the possible defences against these
- Determination of properties of the structure. Testing on the failure scenarios. Ersdal (2002) have performed a quantitative
structure may be used to measure properties of the structure assessment of the failure paths, defences and barriers (risk contributors)
and/or to predict a load bearing capacity when other for fixed offshore installation. The following defences and barriers
approaches such as detailed structural analysis or inspection influencing the safety of a fixed offshore structure are identified:
alone do not provide clear indication or have failed to - Air gap.
demonstrate adequate structural reliability. - Load capacity versus environmental loading
- Structural analysis. Principles for structural analysis should - Fatigue capacity versus environmental loading
be in accordance with ISO 2394 (ISO 1998). The detoriation - Reserve strength and ductility
of an existing structure should be taken into consideration. - Residual strength and residual fatigue capacity
- Verification. - Evacuation of personnel ahead of storm
Verification of an existing structure should normally be - Environmental loading reducing measures, including wave

Paper No. 2002-JSC-379 Ersdal 5


reducing measures experienced frequency of incidents, and that the gross errors are
- Subsidence monitoring contributing with 80 – 90 % of the errors, or even more for the most
- Inspection methods and intervals including first year serious cases. Also methods and parameters are still based on
inspection subjective choice. Due to the problems with the method, structural
- Maintenance, repair and strengthening reliability analysis will give a bias in the failure probabilities, and it
- Quality in the design, fabrication, installation and operation should not be accepted to use a structural reliability analysis alone to
of the installation, ensured by experience transfer, evaluate the quantitative risk of an offshore structure.
qualification of personnel, quality assurance, verification,
updated regulations and standards, model tests and full scale In order to give an overview, the different standards and methods
tests etc. available can be summarized as follows:
- Corrosion protection (anodes, painting, coating etc.)
- Material selection. API RP 2A WSD (API 2000) allows for:
- Evacuation equipment and efficiency under large tilt - Assessment by design check using reduced lateral loading
- Progressing total collapse should allow for evacuation - Assessment by Reserve Strength Ratio (RSR) check
- Assessment by comparison
The main barriers for a fixed offshore steel structure are in general - Assessment through the use of explicit probabilities of failure
measurable by using results from standard structural calculations. Air - Assessment based on experience (equal or more severe than
gap should be measured after installation, and monitored if the design loading)
installation is exposed to subsidence. Load capacity versus The two first methods seem to be recommended, but all five methods
environmental loading is illustrated by utilization factors in design are given as options.
analysis, and fatigue capacity versus environmental loading can be
illustrated by fatigue damage usually calculated in fatigue design ISO/CD 19902 (ISO 2001) allows for:
analysis. Reserve strength may be modelled by a Reserve Strength - Assessment by design level analysis
Ratio (RSR), and residual strength by a Residual Resistance Factor - Assessment by ultimate strength analysis
(RSR analysis with individual members damaged, often-called RRF ). - Assessment by explicitly calculated probabilities of failure
These factors are also commonly used in probabilistic analysis - Assessment by risk based structural Reserve Strength Ratios
(structural reliability analysis) in order to establish a probability of (RSR)
failure. Also a measure of residual fatigue capacity could be - Assessment by comparison with similar platforms
established, but this is not usually performed by standard methods. - Assessment by prior exposure.

The inspection methods and the interval between inspections and ISO/DIS 13822 (ISO 2000) allows for:
performed maintenance are generally known, but can in some cases be - Assessment by design check
hard to trace back in time. The effect of inspections can be modelled in - Assessment through checking against a target reliability level
a probabilistic analysis, and hence the effect of inspection intervals and - Assessment based on satisfactory past performance.
inspection method (by the POD curve) are quantified by a change in
probability of failure The three regarded standards more or less allows for using most
available methods. Due to this, the different methods are discussed
The rest of the list is not quantifiable in the same manner. The quality rather than the individual standard.
in design, fabrication and installation is probably hard to trace back,
and even if the information is well known, no model for establishing Design Code format
the influence on the structural safety. The safety of a structure is usually regarded to be implicit acceptable in
a structure designed after a recommended design code. This is based on
The manning situation, evacuation equipment and efficiency and the the fact that most design codes are developed over years, and factors of
expected time available for evacuation is consequence related, and will safety have been set to a reasonable level based on the society’s
not be dealt with in detail here. acceptance of risk. Later these load factors have been calibrated
through reliability analysis, but the basis for the reliability target level
DISCUSSION OF THE ASSESSMENT PROCEDURES is the same historic level.

A reasonable goal for regulators on behalf of the society is to create a However, design codes are claimed to be very conservative, as after
regulation that ensures an acceptable and equal level of safety. The some years of experience the knowledge of the structure is increased
generation of a risk target that is consistent from one project to another compared with design. So, according to such an argument , it would be
is in some extent achieved for the operations of an offshore installation, appropriate to ask why this increased knowledge should be disregarded,
including gas leakage, fire, explosions, boat collisions etc. A procedure and why the structure should once again be evaluated as if there were
for assessment of an existing structure should ensure that the no information available about the final product. It might also be
contribution from structural failure to the total risk for an offshore appropriate to ask to what extent you can use this improved knowledge
installation is at an acceptable level. to achieve an improved analysis. The information may make it possible
to perform more accurate analysis, but design analysis could still be the
The most obvious choice for establishing quantitative probabilities of option. The “no detection of propagating cracks” finding, will give
failure is to use a structural reliability analysis, taking into account the reason to update the reliability with regards to fatigue. The same could
variability of the nature, uncertainties in load, uncertainties in be the case for measured foundation behaviour, but other failure modes
capacities and often inspections, maintenance, reserve strength and air- are not equally easy to update.
gap. However, it has been stated in several cases (Melchers 2001,
Kvitrud et al 2001) that the structural reliability analysis does not give a The list of defences and barriers against failure of a offshore structure
value for the probability of failure that is comparable with the given previously, includes quite a few subjects that a design code

Paper No. 2002-JSC-379 Ersdal 6


analysis do not take into account in an assessment situation. Among subjective choices that gives a bias of the failure probability, will also
others the inspection level and results, reserve strength, residual give inconsistent results between analysis groups, as these subjective
strength and gross errors which all may contribute to the total risk of a choices of the analyst are of significant importance. It is also claimed
offshore structure. that there is no general applicable target reliability in a reliability
approach, but this have to be established in each case dependent on the
Design Code format based on a reduced load level methods and models that are used (Moan 1999, p 195).
Standards accepting a reduced load level, accepts lowering the historic
safety level, or believes that an existing structure is more reliable than a ISO/DIS 13822 gives ISO 2394 “General Principles on reliability for
planned structure. The belief in an increased reliability of an existing structures” (ISO 1998) as a reference for procedures on reliability
structure must be based on the experience, and that the structure has analysis and target reliability levels. This ISO standard does not
survived some years. If the structure has been exposed to a load level describe models and methods for the reliability analysis, and target
equal to or more severe than the design load level, this might be a reliability is not necessarily established with methods that are
reasonable idea, but it is questionable whether a structure that has only consistent with the reliability analysis. API (2000) gives very general
been exposed to low loading, compared to design loading, can be guidance on the use of reliability analysis, only stating that the failure
argued to have proven its reliability. After some years of experience, probabilities should be properly derived, and the acceptance criteria
the fatigue failures may be visible, but other weaknesses may not show used should be satisfactorily sustained.
until a high loading is applied to the structure. Especially with regards
to Gross Errors, the history seems to tell us that these errors are not A structural reliability analysis will normally be used in situation where
necessarily exposed in the first few years. As the distribution of the design code analysis check is not satisfied or the code is not
strength has high and low values, some installations must have the low adequate. The purpose of the structural reliability analysis is then to
values. A reasonable question with regards to strength against overload demonstrate that there are some reasonable arguments for a lower
will then be: Could the structure still be in the “unlucky” part of the safety level that is implicit in the design code check. This must again be
strength distribution, even after 10 years of experience? based on a belief that an existing structure is more reliable than a
planned structure. A discussion on this topic is given in the previous
The epistemic uncertainties (statistical and model uncertainties) related “Design code based on a reduced load level” section.
to e.g. shape parameter, wave load on deck, capacity, wave force on
jacket can be reduced based on knowledge acquired through CONCLUSIONS
measurement, operation and inspection.
Different methods for assessment of existing structures have been
Aleatory (inherent) uncertainties, however, related to e.g wave height presented and discussed. A list of defences and barriers to obtain
and current speed, cannot be reduced in an assessment compared to structural safety has been presented. If one accepts this list of defences
design phase. and barriers, existing assessment procedures can be claimed to be
looking at only parts of the problem. E.g. methods based on reserve
With regards to the list of important contributors to the safety of an strength ratio do formally only check the reserve strength of a structure.
offshore structure, the discussion here will be as for design code check. In some cases, but not necessarily all, the method also account for wave
in deck and fatigue. The remaining defences and barriers are usually
Reserve Strength Ratio (RSR) format. not covered in a reasonable manner. Structural reliability methods
A Reserve Strength Ratio analysis alone will not cover possible failure typically account for capacity versus loading, but may also include
modes as fatigue and wave-in-deck. It is reasonable to assume that the inspection, maintenance, reserve strength and air gap. Using standard
RSR values correlates relatively well with the failure probability of a regulation for design of new structures in assessment of existing
structure, when overload due to wind, waves and current are the structures does not better cover gross error, but this method has proven
dominating failure mode. to give safe structures together with rather strict procedures for
inspection, maintenance and repair. However, the results may be
A fundamental requirement in structural analysis is that the calculations unnecessary conservative.
should be on the conservative side. According to the lower bound
theorem of plasticity, an external load in equilibrium with the The problem of gross errors in design, fabrication, installation or
distribution of internal stresses, which nowhere exceeds the acceptable operation is not accounted for in any of these procedures. This failure
plastic stresses in material, is less or equal to the collapse load, if mode is difficult to handle in such procedures, but inspection may give
ductility is acceptable (Chakrabarty, 1987). Normally this is checked by some evidence that the gross errors likely to lead to fatigue damage, is
using a linear elastic analysis, giving statically admissible forces, less likely after some years of operation.
followed by a code check of stresses according to accepted standards,
and the use of ductile material. A method typically used for pushover API (2000) states, “In engineering practise, it is widely recognised that
analysis, including geometric stiffness and plastic hinges, will also give although an existing structure does not meet the present-day design
a solution according to the lower bound theorem. This solution is less standards, the structure may still be adequate or serviceable. Examples
conservative than the linear elastic solution. However, even if this of this not only include fixed offshore structures, but also buildings,
improved solution is acceptable within the lower bound theorem of bridges, dams, and onshore processing plants. The application of
plasticity, it will lower the safety margins towards collapse. The reduced criteria for assessing existing facilities is also recognized in
established safety factors are developed based on linear analysis risk management literature, justified on both cost-benefit and societal
methods, and these safety factors cannot necessarily be adapted to non- grounds”. For a fixed structure where fatigue is the main and most
linear solutions, if the goal is an even level of safety. probable failure mode, the “no propagating crack” finding may give
evidence that the structure is in the “lucky end” of the distribution, and
Probabilistic approach. that the structure may still be adequate or serviceable. For structures
The probabilistic approach, based on structural reliability analysis, is to where other failure modes are dominating the risk picture, this
some extent discussed in the beginning of this section. The same conclusion is harder to accept. The probability of gross error could be

Paper No. 2002-JSC-379 Ersdal 7


claimed to be reduced after some years of successful operation, but it Conference, Sydney, New South Wales, Australia, December 1999, in
could also be claimed that the information on gross errors are not likely “Application of Statistics and probability”, Melchers and Stewart
to be visible until the error occur. What kind of gross errors can we (eds), Balkena, Rotterdam, 2000
expect to be visible in a structure that has been exposed to e.g. a 10 Moan, T. and Vårdal, O.T. (2001). ”Reliability-based requalification of
years storm. Or phrased differently: Does the evidence that a structure existing offshore platforms”, Proceeding of PRADS, 2001, Vol 2, pp
have survived a 10-year storm give evidence on no gross error? 939-945, Balkema, Rotterdam, 2001
NORSOK (2000). ”NORSOK N-001 Structural Design”, Rev.3, NTS,
The most promising method, in the authors view, is a probabilistic Norway, 2000
method based on structural reliability analysis. The standards for ISO (1995) “ISO 13819-1 Petroleum and natural gas industries –
assessing existing structures based on structural reliability methods are Offshore structures – Part 1: General requirements”, ISO 1995
not sufficiently mature at present time, as the reliability approach are ISO (1998) ISO 2394 “General principles on reliability for structures”,
not consistent with the derivation of the reliability target levels. ISO 1998
ISO (2000) “ ISO/DIS 13822 Bases for design of structures –
A procedure for probabilistic assessment of existing structures should Assessment of existing structures”, ISO 2000
give guidance to the methods and models used for the reliability ISO (2001) “ISO/CD 19902 Design of fixed steel jackets”, Draft E,
analysis. These should not necessarily be the best ones, but as long as June 2001
one agree on a set, this makes it more consistent. The reliability
analysis could also be calibrated against a structure with the same
Platform selection
probability distributions as one intends to use for the actual case. The Needs for
calibration structure must be acceptable according to regulations, and assessment
the result of the reliability analysis of this calibration structure should
set the target for the failure probability.
Specification for
Further work is necessary for clarifying a number of issues related to future use
codes for reassessment. Among these are:
- The correlation between RSR and failure probability
Risk categorization
- The dependence of the RSR on wave, wind and current and
condition Screening criteria
- Inclusion of other failure modes as wave in deck, fatigue etc.
- Evaluation of the sensitivity of the reliability analysis to
subjective choices.
- Development of recommended models and parameters in Condition
uncertainty modelling Assessment
- How to deal with Gross error

ACKNOWLEDGEMENTS
Analysis:
The authors would like to thank John Dalsgaard-Sørensen, Sverre - Action assessment
- Resistance assessment Periodical
Haver and Arne Kvitrud for valuable discussions. This work is a part of inspection and
- Design Level analysis
a PhD study financed by Norwegian Petroleum Directorate. - Ultimate strength analysis maintenance
and / or
REFERENCES - Assessment by comparison
- Assessment by probabilities of failure
- Assessment based on prior experience
API RP-2A WSD (2000). “Recommended Practice for Planning, design
and constructing fixed offshore platforms – Working Stress Design”,
API Recommended practice 2A-WSD, Twenty-first edition,
December 2000 Passes
Yes
Chakrabarty, J. (1987). “Theory of Plasticity”, McGraw-Hill Criteria?
International, New York, 1987
Ersdal, G (2002). “Safety of fixed offshore structures, failure paths and
barriers”, OMAE2002-28609, International conference on Offshore No
Mechanics and Arctic Engineering - OMAE 2002, Oslo 2002.
Kallaby, J. and O’Connor P.E. (1994). “An integrated approach for Intervention
underwater survey and damage assessment of offshore Platforms”,
OTC 7487, Offshore Technology Conference Proceedings, Houston,
May 1994
Kvitrud, A, Ersdal, G, Leonardsen R.L. (2001). “On the risk of Construction
Operation
- Repair
structures on the Norwegian continental shelf” Eleventh International - Upgrade
- Monitoring
Offshore and Polar Engineering Conference (ISOPE 2001), - Change in use
- Demolition
Stavanger, Norway, June 17-22, 2001
Melchers, R.E. (2001). “Assessment of existing structures – approaches
and research needs”, Journal of structural engineering, April 2001
Moan, T, Vårdal, O.T. and Johannesen, J.M (1999). “Probabilistic
inspection planning of fixed offshore structures“, ICASP 8 Figure 1: General Assessment procedure

Paper No. 2002-JSC-379 Ersdal 8

View publication stats

Vous aimerez peut-être aussi