Vous êtes sur la page 1sur 211

CERTIFICATE OF PAYMENT

Certificate of Payments GGC/INF/PSP/3D/08

Godrej Properties Limited, 2nd floor, Rudrapath Complex, above audi s


1 Name of Client /Owner
Rajpath club, S.G.Road, Ahmedabad 380059.
Godrej Garden City Project, B/H Nirma University, Off S G Highway, Ja
2 Name of Project
Village, Ahmedabad.
3 Name of Contractor M/s PSP Projects Pvt. Ltd.
4 Work order No./LOI LOA Dated : 27-July-2015, 4300023780
5 Contract Description Infrastructure Works for Phase 3D at GGC, Ahmedabad
6 Value of Contract Without Cess INR 267,730,270.00 (As per LOA)
7 Amount of Mobilization INR 26,773,027.00
8 Contract Value - 3B Without Cess INR 97,699,621.52 39%
9 Contract Value - 3C Without Cess INR 127,589,407.57 51%
10 Contract Value - 3D Without Cess INR 26,175,079.73 10%
11 Amount of PBG: INR 13,386,513.50
12 Invoice's No's & Date R.A. BILL NO. 08
Sr. Up to Previous Bill This Bill Amount
Description of items
No. Amount (Rs) (Rs)
A Advances :
Mobilization Advance 2,757,217.49 -
Material Advance 1,776,512.00 -
Total of (A) INR.4,533,729.49

B Work Done :
Work Done : 23,084,102.95 200,914.63
Basic Rate Diff. - Steel & Cement 5,768.05 0.00
Total of (B) ### INR.200,914.63
C Additions :
Service Tax @ 5.6% 1,293,032.78 11,251.22
Labour Cess @ 1% 20,358.62 0.00
S B Cess @ 0.2% 42,089.06 401.83
Krishi Kalyan Cess @0.2 % 3,713.00 401.83
Total of (C) INR.1,359,193.46 INR.12,054.88
CERTIFICATE OF PAYMENT

D Recovery Of Mob. Advance


Recovery Of Mob. Advance @ 10.65% (2,757,217) -

Recovery Of Material Advance @ 33.33% (1,776,512) -

Total of (D) (Rs.4,533,729.49) INR.0.00


E HOLD
Hold Amount 0.00 0.00
Total of (E) INR.0.00 INR.0.00
F Debit Note :
Debit :Negative Escalation Of Steel -9,477.95 0.00
Total of (F) -9,477.95 0.00
E Net Total Amount (A+B+C+D+E+F) ### INR.212,969.51
TDS & WCT as Applicable
Net Certified Amount For This Bill (Rs.) INR.212,970.00
Release Parameters :
1 Amount certfied as per Agreed terms & Conditions.

Certification of amount is based on physical progress done & procurement claimed in RA Bill, release of payment is
2 submission of supported essentials (Quality Test Reports & MTC's) for claimed procurement items/amount timely , alo
submission of labour/statutory compliances for the month w.r.t to contract agreement.

Necessary TDS and other statuary taxes if applicable may be checked and deducted by GPL prior to release of any p
3
contractor.
Bank Guarantee :
A) Advance BG No: 0328IGPER013416 against Mob. Adv., Valid up to : 30.09.2016 & Claim Period upto 31.03.2017
4
Bank Guarantee Rs.58,60,000.00
B) Performance BG No: 0328IGPER013516 Valid up to: 31.08.2016 & Claim Period upto 28.02.2017 Value of Bank
5
Rs.1,27,48,262.00. Amendment is in process hence, it will be submitted later on by PSP Projects.
C) Retention BG No: 0328IGPER020515 Valid up to: 31.07.2017 & Claim Period upto 31.01.2018 Value of Bank Gu
6
Rs.1,33,86,514.00
Note :
1 PAN No: AAECP7961L
2 Service Tax Registration No : AAECP7961LST001
3 VAT Registration No : 24073302538
CERTIFICATE OF PAYMENT

4 PF Registration No : GJ/AHD/52371
5 Labour licence no : AMD/792/1/2015 Valid Till 14/7/2016
PF & ESIC Not Applicability Given by Agency. Work is closed hence renewal copy of labour licence is not submitted b
6
Projects.

For , GEM Engserv Pvt. Ltd.

Vaibhav Sawant
Billing Engineer
Godrej Garden City,Ahmedabad
GEM Engserv Pvt. Ltd.
Project - Godrej Garden City,
Ahmedabad, Gujarat.

ENT

Date : 20/09/2016

nd floor, Rudrapath Complex, above audi showroom, Nr


medabad 380059.
B/H Nirma University, Off S G Highway, Jagatpur

300023780
se 3D at GGC, Ahmedabad

INR 10,414,779.66
INR 13,601,030.85
INR 2,757,217.49

Date : 17/09/2016
Cummulative Bill
Remarks
Amount (Rs)

2,757,217.49
1,776,512.00
INR.4,533,729.49

23,285,017.58
5,768.05
###

1,304,284.00
20,358.62
42,490.89
4,114.83
INR.1,371,248.33
GEM Engserv Pvt. Ltd.
Project - Godrej Garden City,
Ahmedabad, Gujarat.

ENT

(2,757,217)

(1,776,512)

(Rs.4,533,729.49)

0.00
INR.0.00

-9,477.95
-9,477.95
###

claimed in RA Bill, release of payment is subjected to


med procurement items/amount timely , alongwith
agreement.

deducted by GPL prior to release of any payment to

.09.2016 & Claim Period upto 31.03.2017 Value of

m Period upto 28.02.2017 Value of Bank Guarantee


er on by PSP Projects.
Period upto 31.01.2018 Value of Bank Guarantee
GEM Engserv Pvt. Ltd.
Project - Godrej Garden City,
Ahmedabad, Gujarat.

ENT

al copy of labour licence is not submitted by PSP

Rejo Joseph
Manager - Contracts & Billing
Godrej Garden City,Ahmedabad
Certificate Of Payment

Certificate of Payments GGC/INF/PSP/3D/02

Godrej Properties Limited, 2nd floor, Rudrapath Complex, above a


1 Name of Client /Owner S.G.Road, Ahmedabad 380059.

2 Name of Project Godrej Garden City Project, B/H Nirma University, Off S G Highway

3 Name of Contractor M/s PSP Projects Pvt. Ltd.

4 Work order No./LOI LOA Dated : 27-July-2015, 4300023780

5 Contract Description Infrastructure Works for Phase 3B at GGC, Ahmedabad

6 Value of Contract Without Cess INR 267,730,270.00 (As per LOA)

7 Amount of Mobilization INR 26,773,027.00

8 Contract Value - 3B Without Cess INR 97,699,621.52 39%

9 Contract Value - 3C Without Cess INR 127,589,407.57 51%

10 Contract Value - 3D Without Cess INR 26,175,079.73 10%

8 Amount of PBG: INR 13,386,513.50

10 Invoice's No's & Date R.A. BILL NO. 02 (Oct. 2015)


Sr. Up to Previous Bill Amount
Description of items This Bill Amount (Rs)
No. (Rs)

A Advances :

Mobilization Advance 2,786,823.61 -

Total of (A) 2,786,823.61 -

B Work Done :

Work Done : 23,084,102.85 200,914.63

Basic Rate Diff. - Cement 0.00 0.00

Basic Rate Diff. - Steel 0.00 0.00

Total of (B) 23,084,102.85 200,914.63

C Additions :

Page 7 of 211
Certificate Of Payment

Certificate of Payments GGC/INF/PSP/3D/02

Service Tax @ 5.6% 1,292,709.76 11,251.22

Labour Cess @ 1% 230,841.03 2,009.15

Total of (C) 1,523,550.79 13,260.37

D Recovery Of Mob. Advance

Recovery Of Mob. Advance @ 10.65% 2,457,731.69 21,391.10

Total of (D) 2,457,731.69 21,391.10

E HOLD

Hold Amount 0.00 0.00

Total of (E) 0.00 0.00

F Debit Note :

Debit : 0.00 0.00

Total of (F) 0.00 0.00

E Net Total Amount (A+B+C-D+E) 24,936,745.56 192,783.90

TDS & WCT as Applicable

Net Certified Amount For This Bill (Rs.) 192,784.00

Release Parameters :

1 Amount certfied as per Agreed terms & Conditions.

Certification of amount is based on physical progress done & procurement claimed in RA Bill, release of payment
2 supported essentials (Quality Test Reports & MTC's) for claimed procurement items/amount timely , alongwith sub
compliances for the month w.r.t to contract agreement.

Page 8 of 211
Certificate Of Payment

Certificate of Payments GGC/INF/PSP/3D/02

3 Necessary TDS and other statuary taxes if applicable may be checked and deducted by GPL prior to release of any

Bank Guarantee :

4 A) Advance BG No: 0328IGPER018315 against Mob. Adv., Valid up to : 29.02.2016 & Claim Period upto 31.08.2016
Rs.2,67,73,027.00

5 B) Performance BG No: 0328IGPER020715 Valid up to: 29.02.2016 & Claim Period upto 31.08.2016 Value of Bank

6 C) Performance BG No: 0328IGPER020615 Valid up to: 31.07.2017 & Claim Period upto 31.01.2018 Value of Bank

7 D) Retntion BG No: 0328IGPER020515 Valid up to: 31.07.2017 & Claim Period upto 31.01.2018 Value of Bank Gua

Note :

1 PAN No: AAECP7961L

2 Service Tax Registration No : AAECP7961LST001

3 VAT Registration No : 24073302538

4 PF Registration No : GJ/AHD/52371

5 Labour licence no : Application dtd. 08.09.2015, Licence Not Received Yet.

6 PF & ESIC Not Applicability Given by Agency.


For , GEM Engserv Pvt. Ltd.

Anant A. Chauhan.
Manager - Contracts & Billing
Godrej Garden City,Ahmedabad

Page 9 of 211
GEM Engserv Pvt. Ltd.
Project - Godrej Garden City,
Ahmedabad, Gujarat.

ate Of Payment

PSP/3D/02 Date: 05.11.2015

perties Limited, 2nd floor, Rudrapath Complex, above audi showroom, Nr Rajpath club,
Ahmedabad 380059.

rden City Project, B/H Nirma University, Off S G Highway, Jagatpur Village, Ahmedabad.

rojects Pvt. Ltd.

: 27-July-2015, 4300023780

ure Works for Phase 3B at GGC, Ahmedabad

INR 10,401,940.13

INR 13,584,263.26

INR 2,786,823.61

NO. 02 (Oct. 2015) Date: 19.10.2015


Cummulative Bill Remarks
Amount (Rs)

2,786,823.61

2,786,823.61

23,285,017.48

0.00

23,285,017.48

Page 10 of 211
GEM Engserv Pvt. Ltd.
Project - Godrej Garden City,
Ahmedabad, Gujarat.

ate Of Payment

PSP/3D/02 Date: 05.11.2015

1,303,960.98

232,850.17

1,536,811.15

2,479,122.78

2,479,122.78

0.00

0.00

0.00

0.00

25,129,529.46

e & procurement claimed in RA Bill, release of payment is subjected to submission of


imed procurement items/amount timely , alongwith submission of labour/statutory

Page 11 of 211
GEM Engserv Pvt. Ltd.
Project - Godrej Garden City,
Ahmedabad, Gujarat.

ate Of Payment

PSP/3D/02 Date: 05.11.2015

e checked and deducted by GPL prior to release of any payment to contractor.

Valid up to : 29.02.2016 & Claim Period upto 31.08.2016 Value of Bank Guarantee

02.2016 & Claim Period upto 31.08.2016 Value of Bank Guarantee Rs.66,93,257.00

07.2017 & Claim Period upto 31.01.2018 Value of Bank Guarantee Rs.66,93,257.00

017 & Claim Period upto 31.01.2018 Value of Bank Guarantee Rs.1,33,86,514.00

ot Received Yet.

For , GEM Engserv Pvt. Ltd.

Manager - Contracts & Billing


Godrej Garden City,Ahmedabad

Page 12 of 211
Certificate Of Payment

Certificate of Payments GGC/INF/PSP/3D/08

Godrej Properties Limited, 2nd floor, Rudrapath Complex, above audi


1 Name of Client /Owner S.G.Road, Ahmedabad 380059.
2 Name of Project Godrej Garden City Project, B/H Nirma University, Off S G Highway, Jag
3 Name of Contractor M/s PSP Projects Pvt. Ltd.

4 Work order No./LOI LOA Dated : 27-July-2015, 4300023780

5 Contract Description Infrastructure Works for Phase 3D at GGC, Ahmedabad

6 Value of Contract Without Cess INR 267,730,270.00 (As per LOA)

7 Amount of Mobilization INR 26,773,027.00

8 Contract Value - 3B Without Cess INR 8,69,79,351.29 39%

9 Contract Value - 3C Without Cess INR 13,45,47,303.70 51%

10 Contract Value - 3D Without Cess INR 3,34,38,584.59 10%

11 Amount of PBG: INR 1,27,48,262.00

12 Invoice's No's & Date R.A. BILL NO. 08


Sr. Up to Previous Bill Amount
Description of items This Bill Amount (Rs)
No. (Rs)
A Advances :
Mobilization Advance 2,757,217.49 -
Material Advance 1,776,512.00 -
Total of (A) 4,533,729.49

B Work Done :
Work Done : 23,084,101.96 1,856,685.53
Basic Rate Diff. - Steel & Cement 5,768.05 0.00
Total of (B) 23,089,870.02 1,856,685.53

C Additions :

Service Tax @ 5.6% 1,293,032.72 103,974.39

Labour Cess @ 1% 20,358.62 0.00

S B Cess @ 0.2% 42,089.06 3,713.37


Certificate Of Payment

Krishi Kalyan Cess @ 0.2% 3,713.37 3,713.37

Total of (C) 1,359,193.77 111,401.13

D Recovery Of Mob. Advance

Recovery Of Mob. Advance @ 10.65% -2,757,217.49 0.00

Recovery Of Material Advance @ 33.33% -1,776,512.00 0.00

Total of (D) -4,533,729.49 0.00

E HOLD

Hold Amount 0.00 0.00

Total of (E) 0.00 0.00

F Debit Note :

Debit :Negative Escalation Of Steel -9,477.95 0.00


Total of (F) -9,477.95 0.00

E Net Total Amount (A+B+C+D+E+F) 24,439,585.84 1,968,086.66


TDS & WCT as Applicable
Net Certified Amount For This Bill (Rs.) 1,968,087.00

Release Parameters :
1 Amount certfied as per Agreed terms & Conditions.

Certification of amount is based on physical progress done & procurement claimed in RA Bill, release of payment is s
2 supported essentials (Quality Test Reports & MTC's) for claimed procurement items/amount timely , alongwith submi
compliances for the month w.r.t to contract agreement.

3 Necessary TDS and other statuary taxes if applicable may be checked and deducted by GPL prior to release of any pay
Bank Guarantee :

4 A) Advance BG No: 0328IGPER013416 against Mob. Adv., Valid up to : 30.09.2016 & Claim Period upto 31.03.2017 Val
Rs.58,60,000.00
Certificate Of Payment

6 B) Performance BG No: 0328IGPER013516 Valid up to: 31.08.2016 & Claim Period upto 28.02.2017 Value of Bank Gu

7 D) Retntion BG No: 0328IGPER020515 Valid up to: 31.07.2017 & Claim Period upto 31.01.2018 Value of Bank Guarant

Note :
1 PAN No: AAECP7961L
2 Service Tax Registration No : AAECP7961LST001
3 VAT Registration No : 24073302538
4 PF Registration No : GJ/AHD/52371
5 Labour licence no : AMD/792/1/2015 Valid Till 14/7/2016
6 PF & ESIC Not Applicability Given by Agency.
GEM Engserv Pvt. Ltd.
Project - Godrej Garden City,
Ahmedabad, Gujarat.

Date: 20.09.2016

path Complex, above audi showroom, Nr Rajpath club,

versity, Off S G Highway, Jagatpur Village, Ahmedabad.

Ahmedabad

INR 25,49,65,239.59 (As Per A1)

INR 10,414,779.66

INR 13,601,030.85

INR 2,757,217.49

Date: 17/09/2016
Cummulative Bill Remarks
Amount (Rs)

2,757,217.49
1,776,512.00
4,533,729.49

24,940,787.49
5,768.05
24,946,555.55

1,397,007.11

20,358.62

45,802.43
GEM Engserv Pvt. Ltd.
Project - Godrej Garden City,
Ahmedabad, Gujarat.

7,426.74

1,470,594.90

-2,757,217.49

-1,776,512.00

-4,533,729.49

0.00

0.00

-9,477.95
-9,477.95

26,407,672.50

Bill, release of payment is subjected to submission of


t timely , alongwith submission of labour/statutory

prior to release of any payment to contractor.

Period upto 31.03.2017 Value of Bank Guarantee


GEM Engserv Pvt. Ltd.
Project - Godrej Garden City,
Ahmedabad, Gujarat.

02.2017 Value of Bank Guarantee Rs.1,27,48,262.00

018 Value of Bank Guarantee Rs.1,33,86,514.00

For , GEM Engserv Pvt. Ltd.

Anant A. Chauhan.
Manager - Contracts & Billing
Godrej Garden City,Ahmedabad
TAX INVOICE
Project: General Devlopment of Ph-3D W.O. No. : 4300023780
Client : Godrej Properties Ltd. W.O. Date : 10/08/2015
2nd Floor Rudra Path Complex, Nr. Rajpath Club, RA Bill NO. : 08
Sarkhej Highway, Ahmedabad Date : 17/09/2016
TENDER + Extra Items - S U M M A R Y
Previous
Cumilative This bill Amount TotalAmount
Cumilative
Sr.No. Description
Amount
Status RA - 07 RA - 08 RA - 08

1 Mob. Advance 2,757,217 2,757,217


Total Workdone Tender Items 23,084,103 200,915 23,285,017
Material Basic Rate Difference -3,710 - -3,710
Material Advvance 1,776,512 1,776,512
A Total Workdone Tender Items 27,614,122 200,915 27,815,037

2 Service Tax @ 5.60% 1,293,033 11,251 1,304,284


Labour Cess @ 1% 20,359 20,359
SWB Tax @ 0.2% 42,089 402 42,491
Krishi Kalyan Cess @0.2% 3,713 402 4,115
B Total Amount in Rs. With Service Tax 28,973,316 212,970 29,186,285

3 DEDUCTION
3.1 Recovery of Material Advance 1,776,512 1,776,512
3.2 [] - -
3.3 2,757,217 - 2,757,217
Total Deduction 4,533,729 - 4,533,729
Net Payable 24,439,587 212,970 24,652,556

PAN No: AAECP7961L


Service Tax Registration No : AAECP7961LST001
VAT Registration No : 24073302538

FOR PSP PROJECTS LTD

AUTHORISED SIGNATORY
Mr. Atit Shah
* Service Tax rate prevailing on date of certification
of RA bill will be Applicable
Project : Godrej Garden city - Infrastructure work - Ahmedabad
Client : Godrej Properties Ltd.
Agency : PSP Projects Pvt.Ltd.,Ahmedabad
Cost Summary for Infra Works - Phase 3 D

Sr No Package Description BOQ Amount Work Done Amount

Up To Previous Bill This Bill Up To Date

1 Hardscape Works 13,542,810 11,505,753 28,026 11,533,779


2 Civil Works 3,740,389 2,477,955 0 2,477,955
3 Electrical Works 6,143,639 3,065,229 55,302 3,120,531
4 PHE Works 8,016,742 4,819,610 14,595 4,834,205
5 Landscape & Irrigation Works 2,009,069 1,215,555 102,991.69 1,318,547
Total 33,452,649 23,084,103 200,915 23,285,018
Escalation for Cement - -
Escalation for Reinforcement
Amount With Escalation 33,452,649 23,084,103 200,915 23,285,018
CEMENT BASIC RRATE DIFFERENCE
GODREJ GARDEN CITY PHASE-3D
Particular Unit Qty. Cement Conent in Bag

Total Executed Qty.up to date for M7.5 Cum 20.99 2.40

Total Executed Qty.up to date for M25 for Pile Cum - 6.00

Total Executed Qty.up to date for M30 for tank Cum 35.33 6.32

15mm thk. Plaster 1:4 Sqm 94.00 0.09

12mm thk. Plastr 1:4 Sqm 144.86 0.08

Brick Work 1:5 Cum 52.70 1.09

Total Cement Consumption i Bag

Basic Rate of Cement

Actual Purchase Rate of Cement

Rate Diference = ( Actual - Basic )

Amount

Total 8,7

Prepared ByAtit Shah 22 of 211


ASIC RRATE DIFFERENCE
GARDEN CITY PHASE-3D
ion of Cement in Bag

50.39

223.29

8.46

11.80

57.45

351.39

220.00

245.00

25.00

8,784.67

8,784.67

Prepared ByAtit Shah 23 of 211


REINFORCEMENT BASIC RATE DIFFERENCE
GODREJ GARDEN CITY PH-3D

Sr No. Date Challan No Party Name 8 MM 10 MM 12 MM Total Qty Unit Rate Bill No Bill Date Amount Vat Bill Amount Fright Certified Amount

1 04/09/2015 N.M. Patel 1.650 1.650 Ton 37650 T-147 04/09/2015 62122.50 3106.13 65228.63 65228.63

2.42 2.420 Ton 36550 T-147 04/09/2015 88451.00 4612.55 93063.55 3800.00 96863.55

2 19/09/2015 Purvi Treading Co. 4.480 11.51 3.06 19.050 Ton T-132 19/09/2015 654112.00 32705.00 686817.00 686817.00

Total Received Steel 6.130 13.930 3.060 23.120 Avrage Rate= 36717.52 Per Ton 848,909.18

Consumed steel up to 19th Sep-2015 in PH-3D 1.200 1.454 0.353 3.007 Basic rate = 40000.00 Per Ton

AMOUNT AS PER BASIC RATE (A)= 120,275.43

AMOUNT AS PER ACTUAL PURCHASE RATE ( B ) = 110,405.41

UP TO DATE ESCALATION AMOUNT = ( B - A ) -9,870.03

Prepared ByAtit Shah 24 of 211


PHASE 3 D - HARDSCAPE WORK BOQ Quantity Amount

Up To
SR.NO PARTICULARS UNIT Qty's RATE Amount This Bill Up To Date Up To Previous Bill This Bill Up To Date
Previous Bill

HARDSCAPING WORKS

Brick work (9" thick) in cement mortar 1:6 mix


using 1st class Brick cost including all material to
1.1 Sqmt 30.703 1264.90 38,836.22 12.03 0.000 12.03 12.03 0.00 0.00 15,220.54 0.00 15,220.54
site, all labour charges and other necessary to
complete (Without Plastering)
Brick work (4" thick) in cement mortar 1:6 mix
using 1st class Brick cost including all material to
1.2 Sqmt 300.002 778.40 233,521.56 300.00 0.000 300.00 304.31 4.31 3,356.46 233,521.56 0.00 233,521.56
site, all labour charges and other necessary to
complete (Without Plastering)
Providing 12mm thick plastering on brickwork with
1.3 Sqmt 621.163 389.20 241,756.64 621.16 0.000 621.16 708.37 87.20 33,939.02 241,756.64 0.00 241,756.64
CM 1:6

Plain Cement Concrete Grade M-15 mix: Supply,


placing, leveling and top smooth finished of pre-
mix/Site mix Cement concrete of grade 15 mix,
1.4 Cum 24.999 5059.60 126,484.94 24.81 0.000 24.81 24.81 0.00 0.00 125,519.29 0.00 125,519.29
cost including all material at site, all machineries
such as vibrating compaction, form work, all
labour charges and other necessary charges.

1.5 PARKING GRASS PAVERS 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Kesarjan grass pavers for parking : Supplying


and laying grass pavers 230mm x 230mm x
65mm thick in natural finish as per given pattern
in vendor specification, cost including all material
Sqm 715.000 1459.50 1,043,542.50 572.05 12.383 584.43 584.43 0.00 0.00 834,906.98 18,072.99 852,979.96
on site all labour charges and all necessary
charges on site. (Grass Paver to be provided at
open parking along the boundary parking with
Basic Rate @ Rs.35/Sqft. )

1.6 DRIVEWAY ROAD ( GREY PAVERS ) 0.000 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Driveway road pavers : Supplying and laying
Pavit make Pavment Tiles 100mm x 100mm x
12mm thick in natural finish as per given pattern
in cement mortar 1:3 with cost including all material Sqm 3600.000 973.00 3,502,800.00 3,399.44 0.000 3,399.44 3,399.44 0.00 0.00 3,307,655.12 0.00 3,307,655.12
on site all labour charges and all necessary
charges on site. (Grey pavers Basic Rate @
Rs.40/Sqft. )
1.7 PCC STRATA BELOW PAVERS 0.000 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Plain Cement Concrete Grade M-15 mix: Supply,
placing, leveling and top smooth finished of pre-
mix/Site mix Cement concrete of grade 15 mix,
cost including all material at site, all machineries Cum 563.804 5059.60 2,852,622.72 556.73 0.000 556.73 556.73 0.00 1.52 2,816,829.94 0.00 2,816,829.94
such as vibrating compaction, form work, all labour
charges and other necessary charges.( Grey
pavers )

Supply and fixing of rough Kota stone as per


drawing. On cement morter 1:3mix.Cost including
1.8 all material at site, all labor charges and other Sqm 214.083 1167.60 249,963.31 214.08 0.000 214.08 222.87 8.79 10,261.45 249,963.78 0.00 249,963.78
necessary charges to complete. The average thick
of kota would be 25 mm.
POLISHED STONES - ( SEAT TOPS) 0.000 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Supply and fixing of 25mm thick. Polished Kota
stone as per drawing on cement mortar 1:3mix for
seat face vertical cladding cost including all
1.9 Sqm 12.004 1362.20 16,351.85 4.05 0.000 4.05 4.05 0.00 0.00 5,516.91 0.00 5,516.91
materials to site, all labor charges and other
necessary charges to complete-( hanging seat-
vertical face )
PERIPHERI WALL COPINGS (RouhghKota) 0.000 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.10 25mm Thick Rough Kota with edge cut finish. Sqm 32.504 1167.60 37,951.67 0.00 0.00 0.00 0.00 0.00
1.11 Painting for Parking Marking Rmt 750.000 145.95 109,462.50 64.24 0.000 64.24 64.24 0.00 0.00 9,375.83 0.00 9,375.83

Providing & laying 150mm dia RCC Hume pipe at


every road crossing 600mm below the WMM Level
1.12 Rmt. 0.000 340.55 0.00 0.000 0.00 0.00 0.00 0.00 0.00
including excavation, PCC Bedding & Encasing all
complete upto 200mm above pipe crest.

Providing & laying Brickbat coba Waterproofing


1.13 above water tank in CM 1:4 (135mm Avg. Thk) Sqm 0.000 778.40 0.00 0.000 0.00 0.00 0.00 0.00 0.00
inclusive of all complete.
Supplying & laying Brick-on-edge for drainage of
1.14 Sqm 0.000 340.55 0.00 0.000 0.00 0.00 0.00 0.00 0.00
rain water below Geotextile fabric.
TOTAL of Tender Item 8,453,293.91 0.00 0.00 7,840,266.58 18,072.99 7,858,339.57
Extra Item 0.00 0.00
Earth fill 0.00 0.00
Backfilling with excavated earth available within
E1 township premises including watering, rolling & cum 1000 97 97,300.00 948.78 0.000 948.78 948.78 0.00 0.00 92,316.29 0.00 92,316.29
compaction to achieve Proctor Density of 95%
Backfilling with earth brought from outside and
E2 watering, rolling, compaction, density (95% cum 2,991.915 462.17 1,382,773.36 1,628.86 0.000 1,628.86 1,628.86 0.00 0.00 752,808.04 0.00 752,808.04
Proctor Density) tests all complete.

Providing, laying, spreading and compacting


graded stone aggregate to wet mix macadam
specification including premixing the Material with
water at OMC in mechanical mix plant carriage of
E3 cum 107.250 2,335.20 250,450.20 91.57 1.982 93.55 93.55 0.00 -0.12 213,831.93 4,628.37 218,460.30
mixed Material by tipper to site, laying in uniform
layers with paver/grader in sub- base / base course
on well prepared surface and compacting with
vibratory roller to achieve the desired density.

Construction of granular sub-base (Grade - III) by


providing coarse graded material, spreading in
uniform layers with motor grader tractor mounted
E4 grader on prepared surface, mixing by mix in place cum 375.870 1,946.00 731,443.02 335.20 0.301 335.50 335.50 0.00 -0.43 652,297.68 585.75 652,883.43
method with rotavator at OMC, and compacting
with vibration to achieve the desired density,
complete as per clause 401

Supply and fixing of M-20 Grade Pre Cast


Concrete Kerbs as per Architectural design &
specification Cost including all materials at site,
necessary machineries, all labour charges and
E5 - 0.00 0.00 0.00 0.00
other necessary charges to complete.
(Rate includes base PCC & benching on both side
with PCC grade 1:4:8 including side shuttering and
nothing extra will be paid)
E6 a) of 300x300x100 mm size rmt 132.000 389.20 51,374.40 129.30 0.000 129.30 129.30 0.00 0.00 50,323.56 0.00 50,323.56
E7 b) of 300x300x150 mm size rmt 132.000 486.50 64,218.00 110.00 0.000 110.00 110.00 0.00 0.00 53,515.00 0.00 53,515.00

Dismantaling of Temporary compound wall


including dismantling of foundation, properly
removal of RCC Post, RCC Panels, Transporting
E8 Rmt 125.000 987.18 123,397.50 115.00 0.000 115.00 115.00 0.00 0.00 113,525.70 0.00 113,525.70
by required means and stacking it properly at
instructed location by client within the site premises
all complete. Nothing extra shall be paid.

Supply, placing, leveling and compaction with


mechanical rammer the Crusher Run for base to
E9 150mm thick cost including all materials at site, all cum 50.159 1,946.00 97,609.41 26.38 0.000 26.38 26.38 0.00 0.00 51,343.98 0.00 51,343.98
labor charges and other necessary charges to
complete
Providing and laying 40 mm dia GI pipe C class in
E10 electrical pole foundation for wiring including Rmt 90.000 457.00 41,130.00 41.80 0.000 41.80 41.80 0.00 0.00 19,102.60 0.00 19,102.60
allignment etc. complete.

Preparation of the road/Embankment surface with


watering rolling & compaction to achieve 95%
E11 Sqmt 4,000.000 63.24 252,960.00 0.00 0.00 0.00 0.00
Proctor
density.

Half Moulding and Polishing of kota stone edge


E12 including all labour, tools and Equipment etc. Rmt 50.000 145.95 7,297.50 23.40 0.000 23.40 23.40 0.00 0.00 3,415.23 0.00 3,415.23
complete

Removal of debrese and dumping it within


E 13 Cum 2,176.062 130.00 282,888.00 626.72 36.452 663.17 663.17 0.00 0.00 81,473.12 4,738.76 86,211.88
township, complete as directed by the Engineer.

Painting of of the kerb with approved paint by the


E14 consultant and GPL team including required Rmt 264.000 97.30 25,687.20 0.00 0.00 0.00 0.00
surface preparation / pimer required all complete.

Midification of Cycle Track - Removal of Existing


Precast Cover, Making necessary offset, Casting of
Precast over with 75mm M25 Grade precase cover
E15 of required size with 8mm dia 200 C/c Nos. 16.000 5,236.00 83,776.00 14.00 0.000 14.00 14.00 0.00 0.00 73,304.00 0.00 73,304.00
reinforcement jali and finish the level with existing
Road complete in all respect as directed by
engineer incharge.

Additinal Charges over item No. 1.6 Phase


3D(Pavit Tile Fixing), for Keeping groove of
required size as directed by engineer incharge in
E16 Sqmt 3,600.000 443.67 1,597,212.00 3,399.44 0.000 3,399.44 3,399.44 0.00 0.00 1,508,229.54 0.00 1,508,229.54
flooring with Pavit tiles, filling the groove with
Laticrete (Un Sanded Grout) and finish the floor to
the satisfaction of engineer incharge.
TOTAL of Extra Item 5,089,516.59 0.00 0.00 3,665,486.69 9,952.87 3,675,439.56
13,542,810.50 0.00 0.00 11,505,753.27 28,025.86 11,533,779.13
0.00 0.00
25 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.

Brick work (9" thick) in cement mortar 1:6 mix using 1st class Brick cost including all material to site, all la
1.1
and other necessary to complete (Without Plastering)

R.A.-04
Seating at Garden Smt 6 1.91 1.050 12.033
Total Brickwork Qty in Sqm 12.03
BOQ Quantity 30.703
Previously Certified Qty 12.03
This Bill Qty. -
Amendment Qty.

Brick work (4" thick) in cement mortar 1:6 mix using 1st class Brick cost including all material to site, all la
1.2
and other necessary to complete (Without Plastering)

R.A.-03
Marked as-1 Smt 1 18.566 0.600 11.140
Marked as-2 Smt 1 42.75 0.600 25.650
Marked as-3 Smt 1 42.76 0.600 25.656
Marked As-4 Smt 1 45.88 0.600 27.528
R.A.-04
Marked as-1 Smt 1 86.42 0.600 51.852
Marked as-2 Smt 1 51.37 0.600 30.822
Marked as-3 Smt 1 50.27 0.600 30.162
Marked as-4 Smt 1 61.047 0.600 36.628
Marked as-5 Smt 1 22.65 0.600 13.590
Marked as-6 Smt 1 18.85 0.600 11.310
Marked as-7 Smt 7 4.5 0.600 18.900
Smt 1 2.85 0.600 1.710
Deduction for R.A.-03 -1 149.956 0.600 -89.974
R.A.-05
Marked as-1 Smt 1 103.53 0.600 62.118
Marked as-2 Smt 1 158.08 0.600 94.848
Deduction of Outer wall Smt -1 2.04 0.600 -1.224
-1 4.02 0.600 -2.412
-1 3.29 0.600 -1.974
Marked as-3 Smt 1 101.41 0.600 60.846
Marked as-4 Smt 1 52.74 0.600 31.644
Deduction of Duplicate Wall Smt -1 11.47 0.600 -6.882
Deduction of pathway wall -1 2.54 0.600 -1.524
Marked as-5 Smt 1 20.99 0.600 12.594
Marked as-6 Smt 1 18.85 0.600 11.310
Marked as-7 Smt 7 4.5 0.600 18.900
Smt 1 4.37 0.600 2.622
Smt -1 1.52 0.600 -0.912
Less Previously certified -1 194.974 -194.974
R.A.-06

26 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
As Per JMR No. 8532 Dated
19/04/2016 Smt 2 17.200 0.600 20.640
Smt 1 6.200 0.600 3.720
Total Brickwork Qty in Sqm 304.31
BOQ Quantity 300.002
Previously Certified Qty 300.00
This Bill Qty. -
Amendment Qty. 4.312

1.3 Providing 12mm thick plastering on brickwork with CM 1:6

R.A.-05
Marked as-1 Smt 2 103.53 0.700 144.942
Marked as-2 Smt 2 158.08 0.650 205.504
Deduction of Outer wall Smt -2 2.04 0.650 -2.652
-2 4.02 0.650 -5.226
-2 3.29 0.650 -4.277
Marked as-3 Smt 2 101.41 0.700 141.974
Marked as-4 Smt 2 52.74 0.700 73.836
Deduction of Duplicate Wall Smt -2 11.47 0.700 -16.058
Deduction of pathway wall -2 2.54 0.650 -3.302
Marked as-5 Smt 2 20.99 0.700 29.386
Marked as-6 Smt 2 18.85 0.650 24.505
Marked as-7 Smt 14 4.5 0.650 40.950
Smt 2 4.37 0.650 5.681
Smt -2 1.52 0.650 -1.976
230mm wall Smt 12 1.91 1.150 26.358
R.A.-06
As Per JMR No. 8532 Dated
19/04/2016 Smt 4 17.200 0.600 41.280
Smt 2 6.200 0.600 7.440
Total Brickwork Qty in Sqm 708.37
BOQ Quantity 621.163
Previously Certified Qty 621.16
This Bill Qty. -
Amendment Qty. 87.202

Plain Cement Concrete Grade M-15 mix: Supply, placing, leveling and top smooth finished of pre-mix/Site
1.4 concrete of grade 15 mix, cost including all material at site, all machineries such as vibrating compaction
labour charges and other necessary charges.

R.A.-03
For Encasing of RCC pipe of
Electrical work Cum 1 41.8 0.25 0.250 2.613
Deduction for Pipe Cum -1 41.8 0.0314159 -1.313
Encasing of DWC Pipe Cum 1 48.3 0.86 0.350 14.538
-2 48.3 0.031 -3.035

27 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
-1 48.3 0.020 -0.971
1 26.1 0.86 0.350 7.856
-2 26.1 0.031 -1.640
-1 26.1 0.020 -0.525
1 23.6 0.78 0.310 5.706
-3 23.6 0.020 -1.424
R.A.-04
Encasing of RCC Pipe 1 35.8 0.25 0.250 2.238
-1 35.8 0.0314159 -1.125
Elecctric Pole Foundation 26 0.35 0.35 0.550 1.752
4 0.25 0.25 0.550 0.138
Total Brickwork Qty in Sqm 24.81
BOQ Quantity 24.999
Previously Certified Qty 24.81
This Bill Qty. -
Amendment Qty.
Kesarjan grass pavers for parking : Supplying and laying grass pavers 230mm x 230mm x 65mm thick i
as per given pattern in vendor specification, cost including all material on site all labour charges and all ne
1.5
charges on site. (Grass Paver to be provided at open parking along the boundary parking with Basic Rate
Rs.35/Sqft. )
R.A.-03
Area behind B Block Smt 1 265.63 265.630
Deduction of Planter Smt -1 19 -19.000
Deduction of Planter Smt -1 7.31 -7.310
R.A.-05
B Block Central area Smt 1 113.98 113.980
D Block Central area Smt 1 128.43 128.430
Smt 1 55.45 55.450
R.A.-06

Near RWh Tank B Block side Smt 1 36.31 36.310


Deduction of Chamber
900 x 900 chamber Cum -1 1.2 1.2 -1.440
R.A.-08
Area behind Bblock Smt 1 251.703 251.703
Central part B block side Smt 1 150.29 150.290
Central part D block side Smt 1 128.43 128.430
D block left side Smt 1 55.45 55.450
Less Previously certified Smt -1 573.490 -573.490
Total Brickwork Qty in Sqm 584.43
BOQ Quantity 715.000
Previously Certified Qty 572.05
This Bill Qty. 12.383
Amendment Qty.

Driveway road pavers : Supplying and laying Pavit make Pavment Tiles 100mm x 100mm x 12mm thick
1.6 finish as per given pattern in cement mortar 1:3 with cost including all material on site all labour charges a
necessary charges on site. (Grey pavers Basic Rate @ Rs.40/Sqft. )

28 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
R.A.-03
At D Block Back side Smt 1 298.64 298.640
Deduction of Planter Smt -1 19.21 -19.210
At Block B Smt 1 796.43 796.430
Deduction of Planter Smt -1 20.5 -20.500
Deduction of Planter Smt -1 38.82 -38.820
R.A.-04
As per Marked On Drawing Smt 1 383.12 383.120
As per Marked On Drawing Smt 1 208.34 208.340
Deduction of RWH Tank -1 20.87 -20.870
R.A.-05
area around building B Smt 1 1878.01 1878.010
area around building D Smt 1 1535.28 1535.280
363.94 363.940

Deduction of Grass Paver aea Smt -1 113.98 -113.980


-1 128.43 -128.430
-1 55.45 -55.450
-1 36.31 -36.310
Deduction of planter 0.000
Deduction of Planter Smt -1 19.21 -19.210
Deduction of Planter Smt -1 20.5 -20.500
Deduction of Planter Smt -1 38.82 -38.820
Deduction of Planter Smt -1 23.74 -23.740
Dedcution of 600 X 600 Smt -17 0.9 0.9 -13.770
Dedcution of 600 X 900 Smt -31 0.9 1.2 -33.480
Dedcution of 900 X 900 Smt -4 1.2 1.2 -5.760
Less Previously certified Smt -1 1587.130 -1587.130
R.A.-06
Pavit Fixing work as per JMR
8529 Dated 17/04/2016 Smt 1 5.100 5 25.500

Pavit tiles fixing to match line as


per JMR Dated 10-02-2016 - NO-
8529A Smt 1 11.000 11.000

Pavit Tiles fixing behind temp.


Compound wall as per attached
Drawing JMR -8537 Smt 1 67.220 67.220
R.A.-07

Asper JMR Dated 26/06/2016 Smt 1 3.700 1.2 4.440

1 1.500 0.7 1.050

1 3.500 0.7 2.450

Total Brickwork Qty in Sqm 3399.44


BOQ Quantity 3,600.00

29 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
Previously Certified Qty 3,399.44
This Bill Qty. -
Amendment Qty. -

PCC STRATA BELOW PAVERS Plain Cement Concrete Grade M-15 mix: Supply, placing, leveling and t
1.7 finished of pre-mix/Site mix Cement concrete of grade 15 mix, cost including all material at site, all mach
vibrating compaction, form work, all labour charges and other necessary charges.( Grey pavers )

R.A.-03
At D Block Back side Cum 1 496.51 0.150 74.477
Deduction of Planter Cum -1 19.21 0.150 -2.882
At Block B Cum 1 1187.19 0.150 178.079
Deduction of Planter Cum -1 20.5 0.150 -3.075
Deduction of Planter Cum -1 38.82 0.150 -5.823
Deduction of RWH Tank Cum -1 18.48 0.150 -2.772
R.A.-04
Pathway PCC of Garden area Cum 1 76.22 0.100 7.622
At D Block and some central porti Cum 1 811.55 0.150 121.733
Deduction of Planter Cum -1 23.74 0.150 -3.561
D Block Cum 1 432.57 0.150 64.886
Balance Area of B Block Cum 1 545.35 0.150 81.803
Dedcution of 600 X 600 Cum -17 0.9 0.9 0.150 -2.066
Dedcution of 600 X 900 Cum -31 0.9 1.2 0.150 -5.022
Dedcution of 900 X 900 Cum -0.3 1.2 1.2 0.150 -0.065
R.A.-05
area around building B Cum 1 1878.01 0.150 281.702
area around building D Cum 1 1535.28 0.150 230.292
Cum 1 363.94 0.150 54.591
Deduction of Grass Paver aea Cum -1 113.98 0.150 -17.097
Cum -1 128.43 0.150 -19.265
Cum -1 55.45 0.150 -8.318
Cum -1 36.31 0.150 -5.447
Deduction of Planter Cum -1 19.21 0.150 -2.882
Deduction of Planter Cum -1 20.5 0.150 -3.075
Deduction of Planter Cum -1 38.82 0.150 -5.823
Deduction of Planter Cum -1 23.74 0.150 -3.561
Dedcution of 600 X 600 Cum -17 0.9 0.9 0.150 -2.066
Dedcution of 600 X 900 Cum -31 0.9 1.2 0.150 -5.022
Dedcution of 900 X 900 Cum -4 1.2 1.2 0.150 -0.864
Pathway PCC of Garden area Cum 1 117.5 0.100 11.750
Less Previously certified Cum -1 503.333 -503.333
Electric pole Cum 8 0.35 0.35 0.550 0.539
Garden wall Cum
Marked as-1 Cum 1 103.53 0.115 0.100 1.191
Marked as-3 Cum 1 101.41 0.115 0.100 1.166
Marked as-4 Cum 1 52.74 0.115 0.100 0.607
Cum -1 11.47 0.115 0.100 -0.132
Cum -1 2.54 0.115 0.100 -0.029
Marked as-5 Cum 1 20.99 0.115 0.100 0.241

30 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
Marked as-6 Smt 1 18.85 0.115 0.100 0.217
Marked as-7 Cum 7 1.5 0.75 0.100 0.788
Cum 1 1.5 0.68 0.100 0.102
Circle Cum 1 28.27 0.100 2.827
Seating Cum 6 1.5 0.45 0.100 0.405
Deduction Cum -6 1.5 0.115 0.100 -0.104
Below Brick wall
Marked as-1 Cum 1 103.53 0.315 0.100 3.261
Marked as-2 Cum 1 158.08 0.315 0.100 4.980
Deduction of Outer wall Cum -1 2.04 0.315 0.100 -0.064
Cum -1 4.02 0.315 0.100 -0.127
Cum -1 3.29 0.315 0.100 -0.104
Marked as-3 Cum 1 101.41 0.315 0.100 3.194
Marked as-4 Cum 1 52.74 0.315 0.100 1.661
Deduction of pathway wall Cum -1 11.47 0.315 0.100 -0.361
-1 2.54 0.315 0.100 -0.080
Marked as-5 Cum 1 20.99 0.315 0.100 0.661
Marked as-6 Cum 1 18.85 0.315 0.100 0.594
Marked as-7 Cum 7 3.87 0.315 0.100 0.853
Cum 1 2.22 0.315 0.100 0.070
230mm brick wall at seating Cum 6 1.51 0.43 0.100 0.390
Ramp PCC to building 12.508 12.508
R.A.-06

As per JMR NO. 8530 Dated


18/04/2016 Below Kota stone Cum 1 17.2 1.5 0.100 2.580

As Per JMR No. 8532 Dated


19/04/2016 Cum 1 6.200 0.115 0.100 0.071

As per JMR Dated 20/04/2016 -


8530A Cum 1 5.1 5 0.150 3.825

Pavit Tiles fixing behind temp.


Compound wall as per attached 67.220
Drawing JMR-8537 Smt 1 0.150 10.083
Total Brickwork Qty in Sqm 556.73
BOQ Quantity 563.80
Previously Certified Qty 556.73
This Bill Qty. 0.00
Amendment Qty.

Supply and fixing of rough Kota stone as per drawing. On cement morter 1:3mix.Cost including all materia
1.8
labor charges and other necessary charges to complete. The average thick of kota would be 25 mm.

R.A.-05
Circle Smt 1 28.27 28.270
Steepping stone Smt 1 1.02 1.020
Smt 7 1.125 7.875
Pathway 117.5 117.500

31 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
Marked as-1 Cum 1 103.53 0.140 14.494
Marked as-3 Cum 1 101.41 0.140 14.197
Marked as-4 Cum 1 52.74 0.140 7.384
Cum -1 11.47 0.140 -1.606
Cum -1 2.54 0.140 -0.356
Marked as-5 Cum 1 20.99 0.140 2.939
Marked as-6 Smt 1 18.85 0.140 2.639
R.A.-06
As per JMR NO. 8530 Dated
18/04/2016 Smt 1 17.2 1.5 25.800
Smt 1 1.8 0.8 1.440
As per JMR NO. 8532 Dated
19/04/2016 Smt 1 6.2 0.115 0.713
R.A.-07

As per JMR Dated 27/06/2016 Smt 1 4.5 0.125 0.563


Total Kotastone flooring Qty in Sqm 222.87
BOQ Quantity 214.083
Previously Certified Qty 214.08
This Bill Qty. -0.000
Amendment Qty. 8.789

Supply and fixing of 25mm thick. Polished Kota stone as per drawing on cement mortar 1:3mix for seat fa
1.9 cladding cost including all materials to site, all labor charges and other necessary charges to complete-(
vertical face )

R.A.-05
Seating Smt 6 0.45 1.500 4.050
Total Kotastone flooring Qty in Sqm 4.05
BOQ Quantity 12.004
Previously Certified Qty 4.05
This Bill Qty. -
Amendment Qty.

1.11 Painting for Parking Marking

R.A.-07
Parking behind B Block Rmt 13 1.62 21.060
Rmt 8 1.62 12.960
Rmt 6 1.62 9.720
Back side as per attached
drawing Rmt 7 0.6 4.200
Center part at B block Rmt 8 0.62 4.960
Behind water tank Rmt 3 0.66 1.980
Centr part of block D Rmt 10 0.63 6.300
At corner Rmt 3 0.76 2.280
Rmt 1 0.78 0.780
Total Kotastone flooring Qty in Sqm 64.24

32 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
BOQ Quantity 750.000
Previously Certified Qty 64.24
This Bill Qty. -
Amendment Qty.
Extra
Backfilling with available earth within township with all leads & lifts
Items -1

earth taken from Ph-3B Cutting 1 948.78 948.780


Total Earth Eork Qty in Sqm 948.78
BOQ Quantity 1,000.00
Previously Certified Qty 948.78
This Bill Qty. -
Amendment Qty.
Extra
Backfilling with earth brought from outside with all leads & lifts
Items -2
R.A.-03
Area Marked As-1 near D block Cum 1 1334.95 0.431 575.777
Central Area Marked As-2 Cum 1 2582.18 0.423 1093.246
Area Marked As-3 Cum 1172.51 0.365 427.519
Debris Removing from D block Cum 0 840.48 0.449 0.000
Debris Removing from B block Cum 0 835.21 0.419 0.000
L & T Water Tank filling work as per attached 0 80.808 0.000
Deduction for RWH Tank from 1 -86.00
Excavation & Back Filling Qty
Deduction for GI Pipe 40mm dia -1 146.40 0.0012566371 -0.184
Deduction for GI Pipe 50mm dia -1 126.34 0.0019634954 -0.248
Deduction for UPVC Pipe 160mm encasing -1 437.19 0.36 0.36 -56.660
Deduction for UPVC Pipe 200mm encasing -1 24.00 0.7 0.7 -11.760
Deduction for 200mm dia Fire Pipe -1 417.39 0.0314159265 -13.113
Deduction for 150mm dia Fire Pipe -1 22.73 0.0176714587 -0.402
Deduction for 80mm dia Fire Pipe -1 65.70 0.0050265482 -0.330
Deduction for DWC Pipe as per encasing -1 48.3 0.86 0.35 -14.538
-1 26.1 0.86 0.35 -7.856
-1 23.6 0.78 0.31 -5.706

Deduction for 600 x 600 -1 1.06 1.06 0.213 -0.239


Chamber D Block for storm water
-1 1.06 1.06 0.276 -0.310
-1 1.06 1.06 0.376 -0.422
-1 1.06 1.06 0.463 -0.520
-1 1.06 1.06 0.401 -0.451
-1 1.06 1.06 0.365 -0.410
-1 1.06 1.06 0.308 -0.346

Deduction for 600 x 600 -1 1.06 1.06 0.743 -0.835


Chamber B Block for storm water
-1 1.06 1.06 0.698 -0.784

33 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
-1 1.06 1.06 0.625 -0.702
-1 1.06 1.06 0.579 -0.651
-1 1.06 1.06 0.533 -0.599
-1 1.06 1.06 0.37 -0.416
-1 1.06 1.06 0.405 -0.455
-1 1.06 1.06 0.224 -0.252
-1 1.06 1.06 0.158 -0.178
Deduction for sewage Chamber -1 1.06 1.36 0.563 -0.812
600 x 900 at D Block
-1 1.06 1.36 0.613 -0.884
-1 1.06 1.36 0.663 -0.956
-1 1.06 1.36 0.713 -1.028
-1 1.06 1.36 0.763 -1.100
-1 1.06 1.36 0.813 -1.172
-1 1.06 1.36 0.863 -1.244
-1 1.06 1.36 0.913 -1.316
-1 1.06 1.36 0.863 -1.244
-1 1.06 1.36 0.813 -1.172
-1 1.06 1.36 0.763 -1.100
-1 1.06 1.36 0.713 -1.028
-1 1.06 1.36 0.663 -0.956
-1 1.06 1.36 0.613 -0.884
-1 1.06 1.36 0.563 -0.812
-1 1.06 1.36 0.563 -0.812
Deduction for sewage Chamber -1 1.06 1.36 0.619 -0.892
600 x 900 at B Block
-1 1.06 1.36 0.669 -0.964
-1 1.06 1.36 0.719 -1.037
-1 1.06 1.36 0.769 -1.109
-1 1.06 1.36 0.819 -1.181
-1 1.06 1.36 0.869 -1.253
-1 1.06 1.36 0.919 -1.325
-1 1.06 1.36 0.969 -1.397
-1 1.06 1.36 0.969 -1.397
-1 1.06 1.36 0.919 -1.325
-1 1.06 1.36 0.819 -1.181
-1 1.06 1.36 0.769 -1.109
-1 1.06 1.36 0.719 -1.037
-1 1.06 1.36 0.669 -0.964
-1 1.06 1.36 0.619 -0.892
Deduction for GI Line chamber -1 1.36 1.36 0.913 -1.689
900 x 900
-1 1.36 1.36 0.913 -1.689
-1 1.36 1.36 0.913 -1.689
-1 1.36 1.36 0.913 -1.689
Deduction for Fire line Chamber -2 1.36 1.36 1.213 -4.487
Deduction for the earth taen from Ph-3B -1 948.78 -948.780
R.A.-04

34 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
Garden pathway earth fill 1 76.22 0.1566 11.936
Debris Removing from D block Cum 1 840.48 0.449 377.281
Debris Removing from B block Cum 1 835.21 0.419 350.254
L & T Water Tank filling work as per attached 1 80.808 80.808
Less certified in civil works -1 90 -90.000
Total Earth Eork Qty in Sqm 1628.86
BOQ Quantity 2,991.92
Previously Certified Qty 1,628.86
This Bill Qty. -
Amendment Qty.
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification
Extra premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to
Item-3 uniform layers with paver/grader in sub- base / base course on well prepared surface and compacting wit
roller to achieve the desired density.
R.A.-03
Area behind B Block Cum 1 265.63 0.15 39.845
Deduction of Planter Cum -1 19 0.15 -2.850
Deduction of Planter Cum -1 7.31 0.15 -1.097
114.26 0.15 17.139
R.A.-04
Area As per attached drawing Cum 1 127.32 0.15 19.098
R.A.-05
Cum 1 55.45 0.15 8.318
Cum 1 36.31 0.15 5.447
Deduction of Chamber
900 x 900 chamber Cum -1 1.2 1.2 0.15 -0.216
R.A.-06
As per JMR No. 8530 Dated
18/04/2016 Cum 1 17.2 1.5 0.15 3.870
As per JMR No. 8528 Dated
16/04/2016 Cum 0.5 11.2 2.4 0.15 2.016
R.A.-08
Area behind Bblock Smt 1 251.703 0.15 37.755
Central part B block side Smt 1 150.29 0.15 22.544
Central part D block side Smt 1 128.43 0.15 19.265
D block left side Smt 1 55.45 0.15 8.318
Less Previously certified Smt -1 85.899 -85.899

Total Brickwork Qty in Cum 93.55


BOQ Quantity 107.25
Previously Certified Qty 91.57
This Bill Qty. 1.982
Amendment Qty.

Construction of granular sub-base (Grade - III) by providing coarse graded material, spreading in uniform
Extra
motor grader tractor mounted grader on prepared surface, mixing by mix in place method with rotavator a
Item-4
compacting with vibration to achieve the desired density, complete as per clause 401

R.A.-03

35 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
At D Block Back side Cum 1 496.51 0.100 49.651
Deduction of Planter Cum -1 19.21 0.100 -1.921
At D Block and some central porti Cum 1 811.55 0.100 81.155
Deduction of Planter Cum -1 23.74 0.100 -2.374
Block B and some central part Cum 1 325.62 0.100 32.570
At B Block Cum 1 784.57 0.099 77.318
R.A.-04
Balance Area of D Block Cum 1 432.57 0.099 43.035
Balance Area of B Block Cum 1 545.35 0.100 54.345
R.A.-05
Deduction of Chamber
Dedcution of 600 X 600 -17 0.9 0.9 0.100 -1.377
Dedcution of 600 X 900 -31 0.9 1.2 0.100 -3.348
Dedcution of 900 X 900 -4 1.2 1.2 0.100 -0.576
R.A.-06

Pavit Tiles fixing behind temp. 67.220 0.100 6.722


Compound wall as per attached
Drawing JMR - 8537 Smt 1
R.A.-08
area around building B Smt 1 1878.01 0.100 187.801
area around building D Smt 1 1535.28 0.100 153.528
363.94 0.100 36.394

Deduction of Grass Paver aea Smt -1 113.98 0.100 -11.398


-1 128.43 0.100 -12.843
-1 55.45 0.100 -5.545
-1 36.31 0.100 -3.631
Deduction of planter 0.000
Deduction of Planter Smt -1 19.21 0.100 -1.921
Deduction of Planter Smt -1 20.5 0.100 -2.050
Deduction of Planter Smt -1 38.82 0.100 -3.882
Deduction of Planter Smt -1 23.74 0.100 -2.374
Dedcution of 600 X 600 Smt -17 0.9 0.9 0.100 -1.377
Dedcution of 600 X 900 Smt -31 0.9 1.2 0.100 -3.348
Dedcution of 900 X 900 Smt -4 1.2 1.2 0.100 -0.576
Less Previously certified -328.477
Total Brickwork Qty in Sqm 335.50
BOQ Quantity 375.87
Previously Certified Qty 335.20
This Bill Qty. 0.301
Amendment Qty.
Extra
150mm thk. Kerbing
Item-7
R.A.-03
Planter at B Block grass paver Rmt 1 12.1 12.100
Planter at B Block grass paver Rmt 1 9.56 9.560

36 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
At B Block Rmt 1 23.99 23.990
Triangle at RWH Tank Rmt 1 24.61 24.610
Triangle at D Block near CompoundRmt 1 20.47 20.470
At D Block Back side Rmt 1 19.27 19.270
Total Brickwork Qty in Sqm 110.00
BOQ Quantity 132.00
Previously Certified Qty 110.00
This Bill Qty. -
Amendment Qty.
Extra
100mm thk. Kerbing
Item-6
R.A.-03
At B Block Rmt 1 57.15 57.150
At D Block Back side Rmt 1 56.65 56.650
R.A.-04
Breaking adn Re-Done as per site Rmt 1 8 8.000
R.A.-07
As per JMR Dated 26/06/2016 Rmt 1 7.5 7.500
Total Brickwork Qty in Sqm 129.30
BOQ Quantity 132.00
Previously Certified Qty 129.30
This Bill Qty. -
Amendment Qty.

Dismantaling of Temporary compound wall including dismantling of foundation, properly removal of RC


Extra
Panels, Transporting by required means and stacking it properly at instructed location by client within the
Items -8
all complete. Nothing extra shall be paid.

R.A.-04
JMR as per Dated 15-12-2015 Rmt 1.000 115.00
115.000
Total Tractor Qty in Hour 115.00
BOQ Quantity 125.00
Previously Certified Qty 115.00
This Bill Qty. -
Amendment Qty.

Extra Supply, placing, leveling and compaction with mechanical rammer the Crusher Run for base to 150mm th
Items -9 including all materials at site, all labor charges and other necessary charges to complete

R.A.-04
Pathway crusher Run of Garden arCum 1 76.22 0.181 13.796
R.A.-05
Cum 1 117.5 0.181 21.268
Less Previously certified Cum -1 76.22 0.181 -13.796
Below Circular Cum 1 28.27 0.181 5.117

TotalCrusher Run Qty in Cum 26.38


BOQ Quantity 50.16

37 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
Previously Certified Qty 26.38
This Bill Qty. -
Amendment Qty.
Extra
Providing and laying 40 mm dia GI pipe C class in electrical pole foundation for wiring including allignmen
Items -10
R.A.-05
Total Electric Pole Foundations Rmt 38 1.1
41.800
TotalGI Pipe Qty in Rmt 41.80
BOQ Quantity 90.00
Previously Certified Qty 41.80

This Bill Qty. -

Amendment Qty.
Half Moulding and Polishing of kota stone edge
Extra
including all labour, tools and Equipment etc.
Items -12
complete
R.A.-05
Seating at Garden Rmt 6 3.9 23.400
TotalGI Pipe Qty in Rmt 23.40
BOQ Quantity 50.00
Previously Certified Qty 23.40
This Bill Qty. -
Amendment Qty.

Additinal Charges over item No. 1.6 Phase 3D(Pavit Tile Fixing), for Keeping groove of required size as d
Extra
engineer incharge in flooring with Pavit tiles, filling the groove with Laticrete (Un Sanded Grout) and finish
Items -16
satisfaction of engineer incharge.

area around building B Smt 1 1878.01 1878.010


area around building D Smt 1 1535.28 1535.280
363.94 363.940
Deduction of Grass Paver aea Smt -1 113.98 -113.980
-1 128.43 -128.430
-1 55.45 -55.450
-1 36.31 -36.310
Deduction of planter 0.000
Deduction of Planter Cum -1 19.21 -19.210
Deduction of Planter Cum -1 20.5 -20.500
Deduction of Planter Cum -1 38.82 -38.820
Deduction of Planter Cum -1 23.74 -23.740
Dedcution of 600 X 600 -17 0.9 0.9 -13.770
Dedcution of 600 X 900 -31 0.9 1.2 -33.480
Dedcution of 900 X 900 -4 1.2 1.2 -5.760
R.A.-06
Pavit Fixing work as per JMR
8529 Dated 17/04/2016 Smt 1 5.100 5 25.500

38 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.

Pavit tiles fixing to match line as


per JMR Dated 10-02-2016 Smt 1 11.000 11.000

Pavit Tiles fixing behind temp.


Compound wall as per attached
Drawing JMR Smt 1 67.220 67.220
R.A.-07
Asper JMR Dated 24/06/2016 Smt 1 3.700 1.2 4.440
1 1.500 0.7 1.050
1 3.500 0.7 2.450
Total Tractor Qty in Hour 3399.44
BOQ Quantity 3,600.00
Previously Certified Qty 3,399.44
This Bill Qty. -
Amendment Qty.

Extra
Hire Charges for JCB including fuel & Operator. Actual running hours shall be paid
Items +

JMR as per Dated 20-10-2015 Hours 1.000 4.00


4.000
JMR as per Dated 21-11-2015 Hours 1.000 7.00
7.000
Area Cleaning at D block 01-
Hours 1.000 2.00
10-2015 2.000
R.A-06
JCB For cleaning 04/04/2016 -
Hours 1.000 3.00
No -8516 3.000

Total JCB Qty in Hour 16.00


Rate 752.00
Amount 12,032.00

Extra
Hire Charges for Tractor including fuel & Operator. Actual running hours shall be paid
Items -

JMR as per Dated 21-10-2015 Hours 1.000 7.00


7.000
JMR as per Dated 20-10-2015 Hours - 4.00
0.000
Area Cleaning at D block 01-
Hours 1.000 2.00
10-2015 2.000
R.A.-07
Eden OPQR Dated 25/02/16 Hours 1.000 4.00
4.000

Total Tractor Qty in Hour 13.00


Rate 173.00
Amount 2,249.00

39 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.

Extra
Supply of UnSkilled Labours with required tools & tackles on Mandays basis for 8 Hours
Items
Excavation Work A & C
Building Mannually Dated 12- Day 5.000 1.125
01-2016 5.625
Excavation Work A & C
Building Mannually For Day 4.000 1.125
Sewage line 11-02-2016 4.500
PCC Breaking Work 31-01-
Day 1.000 0.875
2016 0.875
Pavit Tiles Demolation Work
Day 2.000 1.125
Dated 21-12-2015 2.250

Grass Paver Tiles Demolation


Day 2.000 1.125
Work 23-12-2015
2.250
D Block PCC Breaking work
Day 1.000 1.000
Dated 22-12-2015 1.000
D Block PCC Breaking work
Day 1.000 1.000
Dated 21-12-2015 1.000

GodRej Site Office Shifting


Day 5.000 0.500
Dated 07/10/2015
2.500
RCC Demolatin in Fire line 19-
Day 1.000 0.875
01-2016 0.875
PCC Breaking at D block on
Day 1.000 1.000
Dated 09-01-2016 1.000
PCC Breaking at D block on
Day 1.000 1.000
Dated 08-01-2016 1.000
Mannually Excavation at A & C
Day 5.000 1.125
Building 20-12-2015 5.625
Mannually Excavation at A & C
Day 6.000 1.125
Building 25-12-2015 6.750
R.A.-06
As per JMR No. 8528 Dated
Day 3.000 1.125
16/04/2016 3.375
As per JMR Daed 16/04/2016 Day 15.000 1.125
16.875
As per JMR Daed 15/04/2016 Day 2.000 1.125
2.250
As per JMR Daed 14/04/2016 Day 2.000 1.125
2.250
As per JMR Daed 15/04/2016 Day 5.000 1.125
5.625
As per JMR Daed 04/04/2016
Day 17.000 0.625
- 8516 10.625
As per JMR Daed 03/04/2016 Day 12.000 0.250
3.000
R.A.-07

40 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
EDEN OPQR dated
Day 21.000 1.000
09/03/2016 21.000
Re laying of Brick paver dated
Day 2.000 1.125
28/02/16 2.250
As per JMR Dated 30/10/2015 Day 1.000 0.188
0.188
As per JMR Dated 26/06/2016 Day 4.000 1.125
4.500
R.A.-08
As per JMR Dated 26/07/2016 Day 4.000 1.000
4.000
As per JMR Dated 27/07/2016 Day 4.000 0.750
3.000

Total Un Skilled Labour Qty in Day 114.19


Rate 340.00
Amount 38,823.75

Extra
Supply of Skilled Labours with required tools & tackles on Mandays basis for 8 Hours
Items
R.A.-06
As per JMR No. 8528 Dated
Day 2.000 1.125
16/04/2016 2.250
As per JMR Daed 15/04/2016 Day 1.000 1.125
1.125
Total Un Skilled Labour Qty in Day 3.38
Rate 711.00
Amount 2,399.63

Extra
Hire Charges for Breaker including fuel & Operator. Actual running hours shall be paid
Items
PCC Breaking Work 31-01-
Hour 1.000 7.000
2016 7.000
D Block PCC Breaking work
Hour 1.000 8.000
Dated 23-12-2015 8.000
D Block PCC Breaking work
Hour 1.000 8.000
Dated 22-12-2015 8.000
D Block PCC Breaking work
Hour 1.000 8.000
Dated 21-12-2015 8.000
RCC Demolatin in Fire line 19-
Hour 1.000 7.000
01-2016 7.000
PCC Breaking at D block on
Hour 1.000 8.000
Dated 07-01-2016 8.000
PCC Breaking at D block on
Hour 1.000 8.000
Dated 09-01-2016 8.000
PCC Breaking at D block on
Hour 1.000 8.000
Dated 08-01-2016 8.000

41 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.
R.A.-06
As per JMR No. 8527 Dated
Hour 1.000 19.000
12/04/2016 19.000
As per JMR No. 8525 Dated
Hour 1.000 22.000
10/04/2016 22.000
As per JMR No. 8523 Dated
Hour 1.000 22.000
08/04/2016 22.000
As per JMR No. 8524 Dated
Hour 1.000 22.000
09/04/2016 22.000
As per JMR No. 8526 Dated
Hour 1.000 22.000
11/04/2016 22.000
As per JMR Dated 14/04/2016 Hour 1.000 7.000
7.000
R.A.-07
As per JMR Dated 30/10/2015 Hour 1.000 1.500
1.500
As per JMR Dated 15/09/2015 Hour 2.000 7.000
14.000
As per JMR Dated 16/09/2015 Hour 3.000 8.250
24.750

TotalBreaker Qty in Hour 216.25


Rate 142.00
Amount 30,707.50
Extra items- Removal of debrese and dumping it within township, complete as directed by the Engineer.
13
Total Amount of JCB 12,032.00
Total Amount of Tractor 2,249.00
Total Amount of Unskill Labour 38,823.75
Total Amount of skill Labour 2,399.63
Total Amount of Breakar 30,707.50
Total Amount 86,211.88
Rate of Item 130.00
Qty 663.17
Up yo Previous 626.72
This Bill 36.45

Earthwork excavation from the existing ground level for foundations to required line, level and grades inboth dry
New Extra condition including shoring, strutting, bailing and pumping out water from all sources and dressing of sides,ramm
Item-1 complete, excluding back filling and disposing surplusearth, all labour complete (working space is notconsidered)
Depth

R.A.-06
As per attached JMR Dated
Cmt 1.000 4.600 5.650 1.50
14/04/2016 38.985
Total Qty. 38.99

42 of 211
Measurement Sheet
Belveder Area Hardscape work
Sr No. Particular Unit No. L B H Qty.

New Extra Providing & fixing Heavy duty CI cover over RWH tank slab top
Item-2

R.A.-08
As per attached JMR Dated
Nos. 3.000
14/04/2016 3.000
Total Qty. 3.00

New Extra Providing & Closing DWC pipe holes by spraying PU foam as directed by PMC
Item-2

R.A.-08
As per attached JMR Dated
Nos. 9.000
14/04/2016 9.000
Total Qty. 9.00

43 of 211
Remarks

o site, all labour charges

100% Done

o site, all labour charges

Drawing-6

44 of 211
Remarks

DRG-01

JMR

DRG-01

JMR

pre-mix/Site mix Cement


compaction, form work, all

Drawing-7 & 8

45 of 211
Remarks
Drawing-7 & 8

Copping JMR

mm thick in natural finish


es and all necessary
Basic Rate @

Drawing-9

As per RA-05 WMM


Certification

12mm thick in natural


ur charges and all

46 of 211
Remarks

Drawing- 10 & 11

Drg-02

JMR/8591 / FOR
REWORK IN 3D
JMR/8591 / FOR
REWORK IN 3D
JMR/8591 / FOR
REWORK IN 3D

47 of 211
Remarks

JMR

veling and top smooth


e, all machineries such as
rs )

Drawing- 12 & 13

48 of 211
Remarks

as per JMR

Drg-01

Drg-01

Drg-02

Drg-03

JMR Below Kota

g all material at site, all


25 mm.

49 of 211
Remarks

Drg-01

Drg-01

Drg-01

JMR/8592

JMR

x for seat face vertical


complete-( hanging seat-

100% done

CERTIFICATION TO
CHECK

50 of 211
Remarks

100% done

Alredy Certifed in RA-4


(Civil Work)

JMR

OGL = 49.814

51 of 211
Remarks

Drawing-19
From PH-3B RA 04

52 of 211
Remarks

100% done

pecification including
by tipper to site, laying in
mpacting with vibratory

Drawing-3

Drawing-4

Drg - 01

Drg - 01

JMR

ng in uniform layers with


h rotavator at OMC, and

53 of 211
Remarks

Drawing-1

Deawing-2

Drg -03

Drawing-5

54 of 211
Remarks

Drawing-5

100%

Drawing-5

JMR-

JMR/8591

JMR

moval of RCC Post, RCC


nt within the site premises

o 150mm thick cost

55 of 211
Remarks

JMR

g allignment etc. complete.

Check with electrical

100% done

ed size as directed by
t) and finish the floor to the

Same as Item of Pavit 56 of 211


Remarks

Same as Item of Pavit

JMR/8591
JMR/8591
JMR/8591

JMR

_______A

_______B

57 of 211
Remarks

58 of 211
Remarks

JMR/6092

JMR/6100

JMR/3

JMR/8590

_______C

_______C

59 of 211
Remarks

JMR/3

JMR/1

JMR/2

_______D

Engineer.

______A
______B
______C
______C
______D

es inboth dry and wet


of sides,ramming of bottoms
tconsidered) up to 1mt.

60 of 211
Remarks

61 of 211
PHASE 3 D - CIVIL WORKS BOQ Quantity Amount
Up To
Item Up To Up To Previous
No Items Description Unit Quantity Rate Amount in Rs. Previous This Bill Date Bill This Bill Up To Date
Bill
Design and Build Rain Water Retention tank as per GFC drawings ###
a) Rain Water Retention tank
b) Filter
Chamber along with Architectural Finishes as specified in the drawing.

Earthwork excavation from the existing ground level for foundations to ###
required line, level and grades inboth dry and wet condition including
shoring, strutting, bailing and pumping out water from all sources and
dressing of sides,ramming of bottoms complete, excluding back filling and
disposing surplusearth, all labour complete (working space is
notconsidered)
2.1 a) up to 2.0m depth Cum 98.25 145.95 14,339.00 87.88 0.00 87.88 87.88 0.00 0.00 12,826.16 0.00 12,826.16
2.2 b) from 2.0m to 4.0m depth Cum 35.00 194.60 6,810.03 23.07 0.00 23.07 23.07 0.00 -0.27 4,489.42 - 4,489.42
- 0.00 - 0.00 0.00 0.00 -
Back filling the sides of excavated trenches with earth in layers not
2.3 exceeding 200mmdepth consolidating deposited layer by watering, ramming - 0.00 - 0.00 0.00 0.00 -
, dressing etc., all materials and labour complete.
a) With good excavated earth Cum 33.31 97.30 3,240.97 24.95 0.00 24.95 24.95 0.00 0.00 2,427.82 - 2,427.82
- 0.00 - 0.00 0.00 0.00 -
2.4 Disposal of surplus excavated earth - 0.00 - 0.00 0.00 0.00 -
a) Within the site Cum 100.11 145.95 14,610.47 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
B PLAIN CEMENT CONCRETE (PCC) - 0.00 - 0.00 0.00 0.00 -
Providing and laying PCC 1:4:8 using 40mm gauge and downhard stone
2.5 aggregates, machine mixed, compacted by ramming and cured properly in - 0.00 - 0.00 0.00 0.00 -
levelling course including formwork, if required, all materialsand labour
complete.
a) Below footing and raft/grade slab Cum 2.74 4378.50 11,975.20 2.70 0.00 2.70 2.70 0.00 0.00 11,818.21 - 11,818.21
- 0.00 - 0.00 0.00 0.00 -
Providing and laying at all levels M30 grade RCC using ordinary portland
cement, and 20 mmgauge and down machine crushed hard stone
2.6 aggregates, machine mixed, mechanically vibrated and properly cured, all - 0.00 - 0.00 0.00 0.00 -
materials and labour complete .
M30 grade concrete Cum 38.47 6324.50 243,278.22 35.33 0.00 35.33 35.33 0.00 0.00 223,451.35 - 223,451.35
- 0.00 - 0.00 0.00 0.00 -
Extra item for providing and mixing waterproofing compound Fosroc, Cico
2.7 no.1 or equivalent conforming to IS:2645 by weight of cement as per Cum 37.50 97.30 3,648.75 35.33 0.00 35.33 35.33 0.00 0.00 3,437.71 -0.00 3,437.71
manufacturer’s specification in concrete for sumps
- 0.00 - 0.00 0.00 0.00 -
D FORMWORK - 0.00 - 0.00 0.00 0.00 -

Supplying, fabricating, erecting and fixing in position with boltsand nuts,


nails and ties, etc. centering and shuttering to correctline and levels
including strutting, propping, etc. with necessary bracings in all axes to give
a stable assembly with propping,etc. with necessary bracings in all axes to
2.8 Sqm 187.03 486.50 90,988.15 183.22 0.00 183.22 183.22 0.00 -1.15 89,136.53 - 89,136.53
give a stable assemblywith provision for making the joints in the shuttering
fully leakproof to avoid leakage of cementslurry, dismantling and removing
the aforesaid assembly after the concrete attains sufficient strength to self-
support itself without any cracking and distortion.

- 0.00 - 0.00 0.00 0.00 -


E REINFORCEMENT - 0.00 - 0.00 0.00 0.00 -

Providing and decoiling wherever necessary, cutting,bending, placing and


fixing in position mild steel / high yield strength deformed bars conforming to
IS:1786-2008 with 18 or 16 gauge annealed binding wire of 8 to 10Kg/MT of
reinforcement including cos bending, placing and fixing in position high yield
- 0.00 - 0 0.00 0 0.00 0.00 -
strength deformed bars of HYSD with 18 gauge annealed binding wire at 8
to 10Kg per Mt of reinforcement including cost of cover blocks for all
reinforced concrete items of work at all levels, all materials and labour
complete. (Rate shall include rolling margin of 3% of reinforcement)

2.9 a) Fe500-Labour rate 3.23 24325.00 78,667.05 3.1302972 3.13 3.13 0.00 0.00 76,144.48 - 76,144.48
2.10 b) Fe500 - Basic Rate- supply rate 3.23 40000.00 129,360.00 3.1302972 3.13 3.13 0.00 0.00 125,211.89 - 125,211.89
- 0.00 - 0.00 0.00 0.00 -
F MISCELLANEOUS - 0.00 - 0.00 0.00 0.00 -
Providing and fixing CI manhole covers of Size(600 x 600-medium wt) / DI
2.11 Nos 3.00 4378.50 13,135.50 3 0.00 3.00 3.00 0.00 0.00 13,135.50 - 13,135.50
Manhole Cover of Sample finalised at site.
- 0.00 - 0.00 0.00 0.00 -

Supplying and fixing poly-propelen e rungs of 20mm square bar of size


2.12 260x160mm for access in water retaining structures including anchorage in Nos 22.00 243.25 5,351.50 20 0.00 20.00 20.00 0.00 0.00 4,865.00 - 4,865.00
wall to a minimum depth of 100mm etc. complete and as directed.

- 0.00 - 0.00 0.00 0.00 -

Supplying, providing and fabricating Mild Steel inserts such as Plates, pipes,
puddle flanges, angles, channels, anchor bolts, including MS lugs etc. ,
transporting, erecting and installing the embedded steel parts at all levels,
including surface preparation, setting material in concrete, templates,
furnishing and all handling, welding, bolting, drilling, cutting, jointing, etc. - 0.00 - 0.00 0.00 0.00 -
including applying a coat of red oxide primer or zinc rich epoxy primer
supply of all nuts/lock nuts, washers, bolts, etc. complete with all labour,
materials, tools & tackles, equipment etc. complete as per specifications,
drawings and as directed

2.13 Structural Steel - Basic Rate of Material - SUPPLY Mt - 40000.00 - 0.00 0.00 0.00 -
2.14 Structural Steel - Excluding Basic Rate of - LABOUR Mt - 38920.00 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
Providing and placing PVC water stops for construction joints between two
RCC members and fixed to the reinforcement with binding wire before - 0.00 - 0.00 0.00 0.00 -
pouring concrete, etc. complete.
2.15 a) Serrated with central bulb (230mm wide, 8/6mm thk) Rmt - 486.50 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -

Providing and applying the acrylic polymer based waterproofing treatment


by approved specialised agency underground water retaining structures,
cement grout including preparingthe surfaces, injections to concrete
surfaces bypressure grouting, if required, including providing waterproof
cement plastering average 25mm thick forbottom slab and average 15mm
2.16 - 0.00 - 0.00 0.00 0.00 -
thick for side walls of water tank with CM 1:4 with waterproofing compound
[CICO No.1 or equivalent with 1 Kg. per bag of cement] and continued upto
full height of the side walls including testing the water tightness, furnishing
of ten year's guarantee, etc., all materials and labour complete in all
respects and as directed.

a bottom slab & side walls both Sqm 94.00 827.05 77,742.70 94.00 0.00 94.00 94.00 0.00 0.00 77,742.08 - 77,742.08
- 0.00 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
Providing and constructing 230mm thk brick work with bricks of class
designation 75 below plinth level and above GL in true line level and plumb
2.17 with necessary scaffolding, curing, raking of joints and all materials and Cum 1.63 4865.00 7,915.36 1.626606 1.63 5.44 3.81 18552.19 7,913.44 - 7,913.44
measures to complete the job.
a) In cement mortar 1:5
- 0.00 - 0.00 0.00 0.00 -
PLASTERING - 0.00 - 0.00 0.00 0.00 -
Providing & applying 12mm thick cement plaster including waterproofing
compound with fine sand at all floors and at all heights with necessary
2.18 scaffolding, curing, making grooves, forming pattas etc., all materials and - 0.00 - 0.00 0.00 0.00 -
labour complete.

a)In cement mortar 1:5 Sqm 13.90 437.85 6,086.12 10.8123 0.00 10.81 10.81 0.00 0.00 4,734.17 - 4,734.17
- 0.00 - 0.00 0.00 0.00 -

Providing and fixing uPVC pipes for soil, waste and vent pipes with solvent
joint conforming to IS 13592 - 1992 (Type B) on wall face including fittings
(plain or door) tees,bends, collars, crosses, reducers etc. of approved make
2.19 including erecting necessary temporary scaffolding and make good the Rmt 12.65 389.20 4,923.38 0.00 0.00 0.00 -
walls, making connection with gully trap /inspection chamber etc. complete
including testing of pipelines as per spec.
a) 75mm dia

- 0.00 - 0.00 0.00 0.00 -


Basic Price Variation of Cement - Basic Rate @ Rs.180/Bag Bags - 0.00 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
BOREWELL - 0.00 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
Providing and laying 150mm dia Borewell for Rainwater Harvesting as per
the Consultant's Design/Drawing - 0.00 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
Drilling of Recharge Borewell upto any depth - 300mm dia with Rotary rig &
2.20 Mud circulation method. Rmt. 120.00 1459.50 175,140.00 120.00 0.00 120.00 120.00 0.00 0.00 175,140.00 - 175,140.00
- 0.00 - 0.00 0.00 0.00 -
Providing, laying, jointing, testing & commissioning of 150mm dia MS "C"
2.21 Rmt 120.00 1751.40 210,168.00 119 0.00 119.00 119.00 0.00 0.00 208,416.60 - 208,416.60
Class (Heavy duty) pipe of Jindal Make.
- 0.00 - 0.00 0.00 0.00 -
2.22 Providing & fixing Jhonson V-wire screen of 300mm dia Rmt. 1.41 4865.00 6,874.25 1.413 0.00 1.41 1.50 0.09 423.26 6,874.25 - 6,874.25
- 0.00 - 0.00 0.00 0.00 -
2.23 Extra over item no. (b) for providing slots in MS pipes Rmt 90.00 291.90 26,271.00 90 0.00 90.00 90.00 0.00 0.00 26,271.00 - 26,271.00
- 0.00 - 0.00 0.00 0.00 -
Supply & laying of gravels (natural river material) in the borewell outside
2.24 pipe periphary Cum 8.50 6324.50 53,758.25 6.28 0.00 6.28 6.28 0.00 0.00 39,731.80 - 39,731.80
- 0.00 - 0.00 0.00 0.00 -
Transporation of pipes, loading, unloading, couplings & other misc. fittings
2.25 etc. LS 1.00 24325.00 24,325.00 1.00 0.00 1.00 1.00 0.00 0.00 24,325.00 - 24,325.00
- 0.00 - 0.00 0.00 0.00 -
Collection & disposal of mud outside site premises conforming to the
2.26 Trips 10.00 1459.50 14,595.00 6.00 0.00 6.00 6.00 0.00 0.00 8,757.00 - 8,757.00
requirements of the local authorities.
- 0.00 - 0.00 0.00 0.00 -
2.27 Development Charges of the Recharge well LS 1.00 72975.00 72,975.00 1 0.00 1.00 1.00 0.00 0.00 72,975.00 - 72,975.00
- 0.00 - 0.00 0.00 0.00 -

Providing Water for borewell drilling & testing (To be arranged from the
2.28 existing borewell thru' pipeline or to be brought from Outside in Water Nos. 1.00 97300.00 97,300.00 1 0.00 1.00 1.00 0.00 0.00 97,300.00 - 97,300.00
tankers as per the requirements without any additional cost)
- 0.00 - 0.00 0.00 0.00 -
Earthwork excavation from the existing ground level for foundations to
required line, level and grades inboth dry and wet condition including
shoring, strutting, bailing and pumping out water from all sources and
- 0.00 - 0.00 0.00 0.00 -
dressing of sides,ramming of bottoms complete, excluding back filling and
disposing surplusearth, all labour complete (working space is
notconsidered)
2.29 a) up to 1.0m depth Cum 9.29 145.95 1,355.88 0.00 0.00 0.00 -
2.30 b) from 1.0m to 2.0m depth Cum 9.29 194.60 1,807.83 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
Back filling the sides of excavated trenches with earth in layers not
2.31 exceeding 200mmdepth consolidating deposited layer by watering, ramming - 0.00 - 0.00 0.00 0.00 -
, dressing etc., all materials and labour complete.
a) With good excavated earth Cum 18.58 97.30 1,807.83 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
2.32 Pebbels For Filtermedia 20 to 40mm for filter Media Cum 8.64 4865.00 42,033.60 8.64 8.64 10.52 1.88 9127.17 42,033.60 - 42,033.60
- 0.00 - 0.00 0.00 0.00 -
2.33 Labour for Sloting over Casting in Tank (Manually) for 1.5m height LS 1.00 19460.00 19,460.00 1 0.00 1.00 1.00 0.00 0.00 19,460.00 - 19,460.00
- 0.00 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
MEP RELATED WORKS - 0.00 - 0.00 0.00 0.00 -
I ELECTRICAL(CSS & DG FOUNDATIONS) - 0.00 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
A EARTHWORK - 0.00 - 0.00 0.00 0.00 -
(open excavation) - 0.00 - 0.00 0.00 0.00 -
Earthwork excavation from the existing ground level for foundations to
required line, level and grades inboth dry and wet condition including
shoring, strutting, bailing and pumping out water from all sources and
2.34 - 0.00 - 0.00 0.00 0.00 -
dressing of sides,ramming of bottoms complete, excluding back filling and
disposing surplus earth, all labour complete (working space is not
considered)
a) up to 1.0m depth Cum 83.56 145.95 12,195.58 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
Back filling the sides of excavated trenches with earth in layers not
2.35 exceeding 200mm depth consolidating deposited layer by watering, - 0.00 - 0.00 0.00 0.00 -
ramming , dressing etc., all materials and labour complete.
a) With good excavated earth Cum 41.70 97.30 4,057.41 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
2.36 Disposal of surplus excavated earth - 0.00 - 0.00 0.00 0.00 -
a) Within the site Cum - 145.95 - 0.00 0.00 0.00 -
b) Outside the site by mechanical transport for a lead of 10kms - 0.00 - 0 0.00 0 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
2.37 Sandfilling Cum 52.37 1167.60 61,147.21 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
B PLAIN CEMENT CONCRETE (PCC) - 0.00 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
Providing and laying PCC 1:4:8 using 40mm gauge and downhard stone
aggregates, machine mixed, compacted by ramming and cured properly in
2.38 levelling course including formwork, if required, all materialsand labour - 0.00 - 0.00 0.00 0.00 -
complete.
a) Below footing and grade beams Cum 10.43 4865.00 50,741.95 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
C REINFORCED CEMENT CONCRETE (RCC) - 0.00 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
Providing and laying at all levels M30 grade RCC using ordinary portland
2.39 cement, and 20 mm gauge and down machine crushed hard stone - 0.00 - 0.00 0.00 0.00 -
aggregates, machine mixed, mechanically vibrated and properly cured, all
materials and labour complete .
M30 grade concrete - 0.00 - 0.00 0.00 0.00 -
a) Footing Cum 34.89 6324.50 220,661.81 0 0.00 0 0.00 0.00 -
- 0.00 - 0 0.00 0 0.00 0.00 -
D FORMWORK - 0.00 - 0 0.00 0 0.00 0.00 -

Supplying, fabricating, erecting and fixing in position with boltsand nuts,


nails and ties, etc. centering and shuttering to correctline and levels
including strutting, propping, etc. with necessary bracings in all axes to give
a stable assembly with propping,etc. with necessary bracings in all axes to
2.40 - 0.00 - 0.00 0.00 0.00 -
give a stable assemblywith provision for making the joints in the shuttering
fully leakproof to avoid leakage of cement slurry, dismantling and removing
the aforesaid assembly after the concrete attains sufficient strength to self-
support itself without any cracking and distortion.

a) Footing Sqm 58.64 486.50 28,528.36 0.00 0.00 0.00 -


- 0.00 - 0.00 0.00 0.00 -
E REINFORCEMENT - 0.00 - 0.00 0.00 0.00 -

Providing and decoiling wherever necessary, cutting, bending, placing and


fixing in position mild steel / high yield strength deformed bars conforming to
IS:1786-2008 with 18 or 16 gauge annealed binding wire of 8 to 10Kg/MT of
reinforcement including cos bending, placing and fixing in position high yield
2.41 - 0.00 - 0.00 0.00 0.00 -
strength deformed bars of HYSD with 18 gauge annealed binding wire at 8
to 10Kg per Mt of reinforcement including cost of cover blocks for all
reinforced concrete items of work at all levels, all materials and labour
complete. (Rate shall include rolling margin of 3% of reinforcement)

2.41 Fe500 - LABOUR RATE Mt 2.00 24325.00 48,650.00 0.00 0.00 0.00 -
2.42 Fe500 - Basic Rate - SUPPLY RATE Mt 2.00 40000.00 80,000.00 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
Rmt. Of Wall - 0.00 - 0.00 0.00 0.00 -
- 0.00 - 0.00 0.00 0.00 -
2.43 Piling dia 200mm 3.5Mtrs deep by mechanised equipment / labour with
necessary tolls etc for complete the job Rmt 150.00 486.50 72,975.00 140.00 0.00 140.00 140.00 0.00 0.00 68,110.00 - 68,110.00
2.44 Under reemed Bulb of 600mm dia by necessary tools ete for complete the
job Nos 45.00 486.50 21,892.50 40.00 0.00 40.00 40.00 0.00 0.00 19,460.00 - 19,460.00
2.45 Carrying out excavation in trenches and carting away the excavated
material to the location indicated, up to any lead and level, inclusive of
dewatering if required, shoring, protecting the slopes/sides etc. complete.
Rate shall include backfilling of the excavated pit after construction of
footings or pile caps or space behind the retaining walls, shear walls, walls
of underground structures, buried rafts, foundations etc., including watering,
ramming, compacting, rolling, leveling to required grade etc. complete and Cum 16.00 145.95 2,335.20 9.99 0.00 9.99 9.99 0.00 0.00 1,458.52 - 1,458.52
stacking the excavated material at site or as directed by Project Manager
within site boundary.
Note: Only PCC Area as per Drawing will be considered for measurement.
Provision of working space & slope if required for excavation will not be paid
separately.

2.46 Providing and laying PCC 1:4:8 using 40mm gauge and downhard stone
aggregates, machine mixed, compacted by ramming and cured properly in
levelling course including formwork, if required, all materials and labour Cum 4.00 4865.00 19,460.00 3.38 0.00 3.38 3.38 0.00 18.92 16,424.78 - 16,424.78
complete - FOR RCC BEAM BOTTOM
2.47 Providing and laying PCC 1:4:8 using 40mm gauge and downhard stone
aggregates, machine mixed, compacted by ramming and cured properly in
levelling course including formwork, if required, all materials and labour Cum 3.50 4865.00 17,027.50 2.13118 0.00 2.13 2.13 0.00 0.00 10,368.19 - 10,368.19
complete - FOR COPING
2.48 Providing and laying at all levels M25 grade RCC using ordinary portland
cement, and 20 mm gauge and down machine crushed hard stone
aggregates, machine mixed, mechanically vibrated and properly cured, all
Cum 16.00 5838.00 93,408.00 12.172728 0.00 12.17 12.17 0.00 0.00 71,064.39 - 71,064.39
materials and labour complete. FOR PLINTH BEAM

2.49 Supplying, fabricating, erecting and fixing in position with boltsand nuts,
nails and ties, etc. centering and shuttering to correctline and levels
including strutting,propping, etc. with necessary bracings in all axes to give
a stable assembly with propping,etc. with necessary bracings in all axes to
give a stable assemblywith provision for making the joints in the shuttering
fully leakproof to avoid leakage of cementslurry, dismantling and removing Sqm 91.00 486.50 44,271.50 54.49 0.00 54.49 54.49 0.00 0.00 26,510.16 - 26,510.16
the aforesaidassembly after the concrete attains sufficientstrength to self-
support itself without any cracking and distortion. FOR RCC BEAM &
COPING

2.50 Providing and decoiling wherever necessary, cutting, bending, placing and
fixing in position mild steel / high yield strength deformed bars conforming to
IS:1786-2008 with 18 gauge black annealed binding wire including cost of
bending, placing and fixing in position including cost of cover blocks for all
reinforced concrete items of work at all levels, all materials and labour - 0.00 - 0.00 0.00 0.00 -
complete. (Rate shall include wastage & rolling margin and nothing will be
paid extra) Basic Rate of Reinforcement Steel @ Rs.40,000/MT.

2.50 a) Fe500 - LABOUR RATE Mt 1.24 24325.00 30,211.65 0.00 0.00 0.00 - - -
2.51 b) Fe500 - Basic Rate - SUPPLY RATE Mt 1.24 40000.00 49,680.00 0.00 0.00 0.00 - - -
8A Same as Item no. 6.8 however, reinforcement issued by GPL at GPL's stock
yard on Chargeable basis. Straightening of the reinforcement, internal
transportation, loading & unlaoding shall be done by the Contractor at his - 0.00 - 0.00 0.00 0.00 -
own cost. (Current cost of reinforcement considered = Basic Rate)

2.52 a) Fe500 - LABOUR RATE Mt - 24325.00 - 0.00 0.00 0.00 - - -


2.53 b) Fe500 - Basic Rate - SUPPLY RATE Mt - 40000.00 - 0.00 0.00 0.00 - - -

62 of 211
PHASE 3 D - CIVIL WORKS BOQ Quantity Amount
Item Up To Up To Up To Previous
Items Description Unit Quantity Rate Amount in Rs. Previous This Bill This Bill Up To Date
No Bill Date Bill

Providing and constructing 230mm thk brick work with locally available best
quality bricks below plinth level and above GL in true line level and plumb
with necessary scaffolding, curing, raking of joints and all materials and - 0.00 - 0.00 0.00 0.00 -
measures to complete the job.
a) In cement mortar 1:5
2.54 a) For Pillar Walls (0.8 Mt wide) Sqm 45.00 973.00 43,785.00 39.73 0.00 39.73 39.73 0.00 0.00 38,657.29 - 38,657.29
2.55 b) For Compound Walls (below screen wall level) Sqm 104.65 1264.90 132,371.79 104.65 0.00 104.65 118.93 14.28 18067.63 132,371.79 - 132,371.79
2.56 Providing and constructing 115mm thk brick work with locally available best
quality bricks above GL in true line level and plumb with necessary
scaffolding, curing, raking of joints and all materials and measures to Sqm - 778.40 - 0.00 0.00 0.00 -
complete the job.
a) In cement mortar 1:4
Providing & applying 12 mm thick mala plaster in cement mortar 1:5 with
fine sand at all floors and at all heights with necessary scaffolding, curing,
forming pattas etc., all materials and labour complete. - 0.00 - 0.00 0.00 0.00 -

2.57 For Pillar Walls (0.8 Mt wide) Sqm 90.00 413.53 37,217.25 90 0.00 90.00 122.74 32.74 13539.97 37,217.25 - 37,217.25
2.58 For Compound Walls (below screen wall) Sqm 209.30 413.53 86,550.78 209.3 0.00 209.30 261.56 52.26 21610.68 86,550.78 - 86,550.78
2.59 For the 115 mm thk Wall Sqm - 389.20 - 0.00 0.00 0.00 -
2.60 Charges for making goove of size 15mm with smooth finishing over
plastering RM 244.80 48.65 11,909.52 179.86 0.00 179.86 179.86 0.00 0.00 8,750.19 - 8,750.19
2.61 EXTERIOR ACRYLIC EMULSION PAINT WITHOUT PUTTY: Providing and
applying three coats of Acrylic emulsion paint of approved manufacturer like
Asian,Berger,Nerolac, ICI Dulux or equivalent and of required shade on all
surfaces and all heights to give an even shade including a priming coat with
alkali resistant primer as per manufacturer's specification after thoroughly
brushing the surface free from mortar dropping and other foreign matter, Sqm 344.30 145.95 50,250.59 44.781 0.00 44.78 44.78 0.00 0.00 6,535.79 - 6,535.79
preparing the surface even and sand papered smooth etc. including all
materials and labour complete.

2.62 Providing and applying two coats of ready made putty of approved
manufacturer, applied as per manufacturer's specification after thoroughly
brushing the surface free from mortar dropping and other foreign matter, Sqm 344.30 87.57 30,150.35 0 0.00 - 0.00 0.00 - - -
preparing the surface even and sand papered smooth including all materials
and labour.
2.63 Providing, fabricating, erecting the Barbed Wire & Concertina Wire fencing
above Brick Masonary compound wall as per the Architectural Design
including "Y" angle of 35x35x5 all material, consumables, labour,
scaffolding, civil works , etc. Rmt. - 729.75 - 0.00 0.00 0.00 - - -
Length of Compound wall will be measured (not the individual Barbed
wire length)

Providing, cutting, bending, placing reinforcement in 115mm thk Brick work


after every 3rd course. Rate to include supply, transportation, labour etc. all - 0.00 - 0.00 0.00 0.00 -
complete.
2.64 a) Fe500 - LABOUR RATE MT - 24325.00 - 0.00 0.00 0.00 - - -
2.65 b) Fe500 - Basic Rate - SUPPLY RATE MT - 38920.00 - 0.00 0.00 0.00 - - -
2.66 Backfilling with earth brought from outside with all leads & lifts Cum 90.00 462.18 41,595.75 90 0.00 90.00 90.00 0.00 0.00 41,595.75 - 41,595.75
2.67 Backfilling with available earth within township with all leads & lifts Cum QR 97.30 0.00 0.00 - - -
TOTAl of Tander Item 2,751,018.71 0.00 81,338.40 1,943,692.87 0.00 1,943,692.87
0.00 0.00
Total Carried to Summary 0.00 0.00 0.00 ###
2.68 Cement (per bag) bag 8,349.06 50 417,452.83 1268.8126 0 1268.813 0.00 63,440.63 - 63,440.63
2.69 Reinforcement (per Metric Ton) MT 6.48 5000 32,380.00 -1.40406 0 -1.40406 0.00 -7,020.30 - -7,020.30
2.70 Structural Steel MT 2.50 5000 12,500.00 0 0 0 0.00 - ###
Extra Grass Paver Sqm 715.00 23.4 16,731.00 569.40977 0 569.4098 0.00 13,324.19 - 13,324.19
Extra Pavit Sqm 3,600.00 83.04 298,944.00 3391.5 0 3391.5 0.00 281,630.16 - 281,630.16
TOTAL of Escalation 778,007.83 0.00 351,374.68 - 351,374.68
Extra Item 0.00 0.00
Providing, fabricating and errecting M S Railing (grill) for Compound Wall
consisting of M S Box Section ( 40 mm x 40 mm) Horizontal member at top
and M S Box section ( 25 mm x 25 mm ) vertically placed at 150 mm c/c all
as above panel fixed between two brick piers with M S Straps and bolts and
E1 all as shown in Architect's details inluding oil painting to all M S surfaces as 0.00 0.00
directed by Architect / Owner. (Brick work and brick pier shall be measured
and paid separately)

a Structural Steel - Basic Rate of Material - SUPPLY RATE Mt 2.50 40000.00 100,000.00 2.317383 0 2.32 2.32 0.00 0.00 92,695.32 - 92,695.32
b Structural Steel - Excluding Basic Rate of supply - LABOUR RATE Mt 2.50 38920 97,300.00 2.317383 0 2.32 2.32 0.00 0.00 90,192.55 - 90,192.55
Providing and applying 2 coats of white wash / with white cement on any
surface to give an even shade including thoroughly brooming the Surface to
Extra item
remove all dirt, dust, mortar drops and other foreign mater includig all Sqm 289.06 48.65 14,062.77 - 0.00 289.06 289.06 14062.80 - -
material and measures to complete th job.
TOTAL of Extra Item 211,362.77 14,062.80 182,887.87 - 182,887.87
Total Civil Works 3,740,389.31 95,401.20 2,477,955.41 0.00 2,477,955.41

63 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H
Earthwork excavation from the existing ground level for foundations to required line, level and grades inbot
2.1 including shoring, strutting, bailing and pumping out water from all sources and dressing of sides,ramming
excluding back filling and disposing surplusearth, all labour complete (working space is notconsidered)
a) up to 2.0m depth
R.A.-01
Raft Cmt 1 8.85 4.965 2.000
Total Qty
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.
2.2 b) from 2.0m to 4.0m depth
R.A.-01
Raft Cmt 1 8.85 4.965 0.525
Total Qty
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

Back filling the sides of excavated trenches with earth in layers not exceeding 200mmdepth consolidating d
2.3
ramming , dressing etc., all materials and labour complete.

R.A.-02
Excavation Area Cmt 1 8.85 4.965 2.525
Deduction For Raft Cmt -1 8.85 4.965 0.300
Deduction for Tank Cmt -1 7.95 4.065 2.225
Deduction of side chember Cmt -1 1.19 0.45 1.700
Total Qty
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

Providing and laying PCC 1:4:8 using 40mm gauge and downhard stone aggregates, machine mixed, com
2.5
cured properly in levelling course including formwork, if required, all materialsand labour complete.

R.A.-01
a) Below raft Cmt 1 8.85 4.965 0.05
Cmt -1 2.17 2.17 0.05
Add for 45 degree PCC for sump Cmt 1 4.34 0.64 0.05
Bottom of smp Cmt 1 1.72 1.72 0.05
R.A.-03
Sump Cmt 1 1.42 1.59 0.2
Total Qty
BOQ Quantity

64 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H
Previously Certified Qty
This Bill Qty.
Amendment Qty.

Providing and laying at all levels M30 grade RCC using ordinary portland cement, and 20 mmgauge and d
2.6
stone aggregates, machine mixed, mechanically vibrated and properly cured, all materials and labour comp

R.A.-01
M30 grade concrete for Raft Cmt 1 8.85 4.965 0.25
Cmt -1 2.17 2.17 0.25
Add for 45 degree RCC for sump Cmt 1 4.09 0.64 0.25
Sump Tringle Portion Cmt 0.5 0.45 0.27
Bottom of smp Cmt 1 1.72 1.72 0.25
Total Qty for Raf
Walls ( out to out ) Cmt 2 7.95 0.25 3.00
Walls ( in to in ) Cmt 2 3.565 0.25 3.00
Extra depth for sump Cmt 2 0.895 0.45 0.25
Extra depth for sump Tringle Portion 1 0.45 0.45 0.25
Total Qty for Wall
Slab Cmt 1 7.95 4.065 0.2
Deduction for Manhole Cmt -3 0.283 0.2
Wall of Manhole Cmt 3 1.88 0.15 0.3
Total Qty for Slab
Total Qty
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.
Extra item for providing and mixing waterproofing compound Fosroc, Cico no.1 or equivalent conforming to
2.7
cement as per manufacturer’s specification in concrete for sumps
R.A.-01
M30 grade concrete for Raft Cmt 1 8.85 4.965 0.25
Cmt -1 2.17 2.17 0.25
Add for 45 degree RCC for sump Cmt 1 4.09 0.64 0.25
Sump Tringle Portion Cmt 0.5 0.45 0.27
Bottom of smp Cmt 1 1.72 1.72 0.25
Total Qty for Raf
Walls ( out to out ) Cmt 2 7.95 0.25 3.00
Walls ( in to in ) Cmt 2 3.565 0.25 3.00
Extra depth for sump Cmt 2 0.895 0.45 0.25
Extra depth for sump Tringle Portion 1 0.45 0.45 0.25
Total Qty for Wall
Slab Cmt 1 7.95 4.065 0.2
Deduction for Manhole Cmt -3 0.283 0.2
Wall of Manhole Cmt 3 1.88 0.15 0.3
Total Qty for Slab

65 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H
Total Qty
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

Supplying, fabricating, erecting and fixing in position with boltsand nuts, nails and ties, etc. centering and sh
levels including strutting, propping, etc. with necessary bracings in all axes to give a stable assembly with p
2.8 bracings in all axes to give a stable assemblywith provision for making the joints in the shuttering fully leakp
cementslurry, dismantling and removing the aforesaid assembly after the concrete attains sufficient strengt
without any cracking and distortion.

R.A.-01
Sides of raft Smt 2 8.85 0.25
2 4.965 0.25
Total Qty of Raf
Long Walls ( out to out ) Cmt 2 7.95 3.00
Long Walls ( In side ) 2 7.45 3.00
Short Walls ( Out Side ) Cmt 2 4.065 3.00
Short Walls (in Side ) Cmt 2 3.565 3.00
Extra depth for sump (Outer to Outer) Cmt 2 1.145 0.45
Extra depth for sump (In side) Cmt 2 0.895 0.45
Extra depth for sump Tringle Portion 2 0.45 0.45
Total Qty of Wall
Slab Smt 1 7.45 3.565
Deduction for Manhole Smt -3 0.283
Wall of Manhole Smt 3 1.88 0.5
" Smt 3 2.83 0.3
Sides of slab Smt 2 7.95 0.2
Smt 2 4.07 0.2
Total Qty for Slab
Total Shuttering
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

2.11 Providing and fixing CI manhole covers of Size(600 x 600-medium wt) / DI Manhole Cover of Sample finalis

R.A.-03
Supply and installation of CI manhole covers of Nos. 3 1
RWH Tank
Total Qty of Rungs
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

66 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H
Supplying and fixing poly-propelene rungs of 20mm square bar of size 260x160mm for access in water reta
2.12
anchorage in wall to a minimum depth of 100mm etc. complete and as directed.
R.A.-03
Fixing of Rungs at RWH Tank Nos. 2 10
Total Qty of Rungs
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.
Providing and applying the acrylic polymer based waterproofing treatment by approved specialised agency
retaining structures, cement grout including preparingthe surfaces, injections to concrete surfaces bypressu
including providing waterproof cement plastering average 25mm thick forbottom slab and average 15mm th
2.16
tank with CM 1:4 with waterproofing compound [CICO No.1 or equivalent with 1 Kg. per bag of cement] and
of the side walls including testing the water tightness, furnishing of ten year's guarantee, etc., all materials a
respects and as directed.

R.A.-02
Bottom of Raft Smt 1 7.45 3.565
Sump sides Smt 4 0.45 0.75
Total Qty of Raf
Long Walls ( In side ) Smt 2 7.45 3.00
Short Walls (in Side ) Smt 2 3.565 3.00
Total Qty of Wall
Total Plastering
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.
Providing and constructing 230mm thk brick work with bricks of class designation 75 below plinth level and
2.17 and plumb with necessary scaffolding, curing, raking of joints and all materials and measures to complete t
a) In cement mortar 1:5

R.A.-03
Cmt 2 1.22 0.23 1.65
Sump sides Cmt 2 0.73 0.23 1.65
Deduction for hole Cmt -2 0.0314 0.23
R.A.-07
Inside Tank at filter media Cmt 2 2.65 0.23 1.5
Cmt 2 3.11 0.23 1.5
Total Qty of Brick work
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

67 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H
Providing & applying 12mm thick cement plaster including waterproofing compound with fine sand at all floo
2.18 necessary scaffolding, curing, making grooves, forming pattas etc., all materials and labour complete.
a)In cement mortar 1:5

R.A.-03
Sump sides outer Smt 2 1.22 1.65
Sump sides Smt 1 1.19 1.65
Sump sides inner Smt 2 0.76 1.65
Sump sides Smt 2 0.73 1.65
Deduction for hole Smt -3 0.0314
Total Qty of Plaster work
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

Providing and laying 150mm dia Borewell for Rainwater Harvesting as per the Consultant's

2.20 Drilling of Recharge Borewell upto any depth - 300mm dia with Rotary rig & Mud circulation method.

R.A.-01
Drilling of bore well Rmt 120
Total Qty

2.21 Providing, laying, jointing, testing & commissioning of 150mm dia MS "C" Class (Heavy duty) pipe of Jindal

R.A.-01
Lowering of Pipe with welding Rmt 119
Total Qty

2.22 Providing & fixing Jhonson V-wire screen of 300mm dia

R.A.-07
V-Wire screen Rmt 1.5
Total Qty
2.23 Extra over item no. (b) for providing slots in MS pipes
R.A.-01
Slotting work Rmt 90
Total Qty

2.24 Supply & laying of gravels (natural river material) in the borewell outside pipe periphary

R.A.-01

68 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H

Filling of Gravels Cum 1 0.053 118.5


Total Qty

2.25 Transporation of pipes, loading, unloading, couplings & other misc. fittings etc.

R.A.-01
Loading, Un Loadding and feetings LS 0.5
R.A.-07
Loading, Un Loadding and feetings LS 0.5
Total Qty
BOQ Quantity
Up To previous Qty.
This Bill Qty.
Amendment Qty.

2.26 Collection & disposal of mud outside site premises conforming to the requirements of the local authorities.

R.A.-01
Disposal of Mud Trip 6
Total Qty

2.27 Development Charges of the Recharge well

R.A.-07
Devlopment charges LS 1
Total Qty

Providing Water for borewell drilling & testing (To be arranged from the existing borewell thru' pipeline or to
2.28
Water tankers as per the requirements without any additional cost)

R.A.-07
Providing water Nos. 1
Total Qty

2.32 Pebbels For Filtermedia 20 to 40mm for filter Media

R.A.-07
Pabbels for filter media inside tank Cmt 1 2.65 2.65 1.5
Deduction for pipe Cmt -1 0.0176625
Total Qty
BOQ Quantity
Up To previous Qty.

69 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H
This Bill Qty.
Amendment Qty.

2.33 Labour for Sloting over Casting in Tank (Manually) for 1.5m height

R.A.-07
Labour for slotting Nos. 1
Total Qty

Compound wall
Qty. Calculation for 1 pile
1 Excavation of Pile Rmt 1 3.5
2 Under Reemed Bulb Nos. 1
3 Concreting of pile Cum 1 0.031 3.5

Concreting of bulb Cum 2 0.020 1.257


1 0.05 0.2 1.257

Total Nos of Pile Executed = 40


So Quantity become as per below Qty for
One Pile Nos of pile Qty.
2.43 Excavation of Pile 3.500 40 140.00 20Nos. R.A.-01 & 20 Nos. R.A.-02
2.44 Under Reemed Bulb 1.000 40 40.00 20Nos. R.A.-01 & 20 Nos. R.A.-02

Carrying out excavation in trenches and carting away the excavated material to the location indicated, up t
inclusive of dewatering if required, shoring, protecting the slopes/sides etc. complete. Rate shall include ba
after construction of footings or pile caps or space behind the retaining walls, shear walls, walls of undergro
2.45 foundations etc., including watering, ramming, compacting, rolling, leveling to required grade etc. complete
material at site or as directed by Project Manager within site boundary.
Note: Only PCC Area as per Drawing will be considered for measurement. Provision of working space & slo
excavation will not be paid separately.

R.A.-02
Excavation for compound wall PCC Cum 1 95 0.38 0.222
R.A.-03
Excavation for compound wall PCC Cum 1 23.46 0.38 0.222
Total Qty Excavation in cum
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

70 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H

Providing and laying PCC 1:4:8 using 40mm gauge and downhard stone aggregates, machine mixed, com
2.46
cured properly in levelling course including formwork, if required, all materials and labour complete - FOR R

R.A.-02
PCC Cum 1 95 0.38 0.075
R.A.-03
PCC Cum 1 23.46 0.38 0.075
Cum 1 0.14 0.38 0.075
Total PCC Qty in cum
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

Providing and laying PCC 1:4:8 using 40mm gauge and downhard stone aggregates, machine mixed, com
2.47
cured properly in levelling course including formwork, if required, all materials and labour complete - FOR

R.A.-03
Copping Cum 1 95 0.23 0.1
230mm thk. Brick work above screen Cum -28 0.8 0.23 0.1
Cum -2 0.9 0.23 0.1
R.A.-05
Total length Cum 1 118.46 0.23 0.1
Deduction of brickwork above screen Cum -30 0.8 0.23 0.1
-2 0.9 0.23 0.1
Less Previously certified Cum -1 1.628
Total PCC Qty in cum
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.
Providing and laying at all levels M25 grade RCC using ordinary portland cement, and 20 mm gauge and d
2.48 hard stone aggregates, machine mixed, mechanically vibrated and properly cured, all materials and labour
BEAM
R.A.-02

Pile Concreting 0.148


Cum 40
Plinth Beam Cum 1 95 0.23 0.23
R.A.-03
Plinth Beam Cum 1 23.46 0.23 0.23
Total M-25 Concrete Qty in cum
BOQ Quantity
Previously Certified Qty
This Bill Qty.

71 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H
Amendment Qty.

Providing and laying at all levels M25 grade RCC using ordinary portland cement, and 20 mm gauge and d
2.49 hard stone aggregates, machine mixed, mechanically vibrated and properly cured, all materials and labour
BEAM
R.A.-02
Plinth Beam shuttering Sqm 2 95 0.23
R.A.-03
Plinth Beam shuttering Sqm 2 23.46 0.23
Total Shuttering Qty in Sqm
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

Providing and constructing 230mm thk brick work with locally available best quality bricks below plinth leve
2.54 level and plumb with necessary scaffolding, curing, raking of joints and all materials and measures to comp
a) In cement mortar 1:5 a) For Pillar Walls (0.8 Mt wide)

R.A.-03

230mm thk. Brick work above screen Sqm 28 0.8 1.45

Sqm 2 0.9 1.45

R.A.-05

230mm thk. Brick work above screen Sqm 30 0.8 1.45

Sqm 2 0.9 1.45

Less Previously certified Sqm -1 35.090

R.A.-07

As per JMR Dated 27/06/2016 Sqm 2 0.800 1.45


Total Brickwork Qty in Sqm

72 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

Providing and constructing 230mm thk brick work with locally available best quality bricks below plinth leve
2.55 level and plumb with necessary scaffolding, curing, raking of joints and all materials and measures to comp
a) In cement mortar 1:5 b) For Compound Walls (below screen wall level)

R.A.-02

230mm thk. Brick work below screen Sqm 1 95 1.004

R.A.-05

230mm thk. Brick work below screen Sqm 1 23.46 1.004


Total Brickwork Qty in Sqm
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

Providing & applying 12 mm thick mala plaster in cement mortar 1:5 with fine sand at all floors and at all he
2.57
scaffolding, curing, forming pattas etc., all materials and labour complete. For Pillar Walls (0.8 Mt wide)

R.A.-03
Plaster work above screen Sqm 56 0.8 1.45
Sqm 58 0.23 1.45
Sqm 4 0.9 1.45
R.A.-05
Plaster above screen Sqm 60 0.8 1.45
Sqm 62 0.23 1.45
Sqm 4 0.9 1.45

Top of wall Sqm 1 118.46 0.23


Less Previously certified Sqm -1 89.523
Total Plaster Qty in Sqm
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

73 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H

Providing & applying 12 mm thick mala plaster in cement mortar 1:5 with fine sand at all floors and at all he
2.58
scaffolding, curing, forming pattas etc., all materials and labour complete. For Compound Walls (below scre

R.A.-03

12mm thk. Plaster work below screen Sqm 2 95 1.104


R.A.-05

12mm thk. Plaster work below screen Sqm 2 23.46 1.104


Total Plaster Qty in Sqm
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

2.60 Charges for making goove of size 15mm with smooth finishing over plastering

R.A.-03

Groove work Above screen Rmt 168 0.8

Rmt 58 0.23

Rmt 12 0.9

R.A.-05

Groove work Above screen Rmt 180 0.8

Rmt 62 0.23

Rmt 24 0.9

74 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H

Less Previously certified Rmt -1 158.540


Total Groove Qty in Sqm
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

EXTERIOR ACRYLIC EMULSION PAINT WITHOUT PUTTY: Providing and applying three coats of Acrylic
manufacturer like Asian,Berger,Nerolac, ICI Dulux or equivalent and of required shade on all surfaces and a
2.61 shade including a priming coat with alkali resistant primer as per manufacturer's specification after thoroug
free from mortar dropping and other foreign matter, preparing the surface even and sand papered smooth e
and labour complete.
R.A.-06
Marked as-1 Smt 1 103.53 0.150
Marked as-3 Smt 1 101.41 0.150
R.A.-07
Seating Smt 6 3.9 0.600
Total Plaster Qty in Sqm
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

Providing and applying 2 coats of white wash / with white cement on any surface to give an even shade inc
Extra Item
the Surface to remove all dirt, dust, mortar drops and other foreign mater includig all material and measure

R.A.-07
Plaster above screen Sqm 60 0.8 1.45
Sqm 62 0.23 1.45
Sqm 4 0.9 1.45
Top of wall Sqm 1 118.46 0.23

12mm thk. Plaster work below screen Sqm 1 118.46 1.104

12mm thk. Plaster work below screen Sqm 1 118.46 0.3


Total Plaster Qty in Sqm
BOQ Quantity
Previously Certified Qty
This Bill Qty.
Amendment Qty.

75 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H
2.66
Backfilling with earth brought from outside with all leads & lifts

R.A.-03
Area Marked As-1 near D block Cum 1 1334.95 0.431
Central Area Marked As-2 Cum 1 2582.18 0.423
Area Marked As-3 Cum 1172.51 0.365
Debris Removing from D block Cum 0 840.48 0.449
Debris Removing from B block Cum 0 835.21 0.419
L & T Water Tank filling work as per attached JMR 0 80.808
Deduction for RWH Tank from Excavation & 1
Back Filling Qty
Deduction for GI Pipe 40mm dia -1 146.40 0.0012566371
Deduction for GI Pipe 50mm dia -1 126.34 0.0019634954
Deduction for UPVC Pipe 160mm encasing -1 437.19 0.36 0.36
Deduction for UPVC Pipe 200mm encasing -1 24.00 0.7 0.7
Deduction for 200mm dia Fire Pipe -1 417.39 0.0314159265
Deduction for 150mm dia Fire Pipe -1 25 0.0176714587
Deduction for 80mm dia Fire Pipe -1 65.6 0.0050265482
Deduction for DWC Pipe as per encasing -1 48.3 0.86 0.35
-1 26.1 0.86 0.35
-1 23.6 0.78 0.31
Deduction for 600 x 600 Chamber D Block for -1 1.06 1.06 0.213
storm water
-1 1.06 1.06 0.276
-1 1.06 1.06 0.376
-1 1.06 1.06 0.463
-1 1.06 1.06 0.401
-1 1.06 1.06 0.365
-1 1.06 1.06 0.308
Deduction for 600 x 600 Chamber B Block for -1 1.06 1.06 0.743
storm water
-1 1.06 1.06 0.698
-1 1.06 1.06 0.625
-1 1.06 1.06 0.579
-1 1.06 1.06 0.533
-1 1.06 1.06 0.37
-1 1.06 1.06 0.405
-1 1.06 1.06 0.224
-1 1.06 1.06 0.158
Deduction for sewage Chamber 600 x 900 at D -1 1.06 1.36 0.563
Block
-1 1.06 1.36 0.613
-1 1.06 1.36 0.663
-1 1.06 1.36 0.713
-1 1.06 1.36 0.763

76 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H
-1 1.06 1.36 0.813
-1 1.06 1.36 0.863
-1 1.06 1.36 0.913
-1 1.06 1.36 0.863
-1 1.06 1.36 0.813
-1 1.06 1.36 0.763
-1 1.06 1.36 0.713
-1 1.06 1.36 0.663
-1 1.06 1.36 0.613
-1 1.06 1.36 0.563
Deduction for sewage Chamber 600 x 900 at B -1 1.06 1.36 0.619
Block
-1 1.06 1.36 0.669
-1 1.06 1.36 0.719
-1 1.06 1.36 0.769
-1 1.06 1.36 0.819
-1 1.06 1.36 0.869
-1 1.06 1.36 0.919
-1 1.06 1.36 0.969
-1 1.06 1.36 0.969
-1 1.06 1.36 0.919
-1 1.06 1.36 0.819
-1 1.06 1.36 0.769
-1 1.06 1.36 0.719
-1 1.06 1.36 0.669
-1 1.06 1.36 0.619
Deduction for GI Line chamber 900 x 900 -1 1.36 1.36 0.913
-1 1.36 1.36 0.913
-1 1.36 1.36 0.913
-1 1.36 1.36 0.913
Deduction for Fire line Chamber -2 1.36 1.36 1.213
Deduction for the earth taen from Ph-3B -1 948.78
R.A.-04
Garden pathway earth fill 1 76.22 0.1566
Debris Removing from D block Cum 1 840.48 0.449
Debris Removing from B block Cum 1 835.21 0.419
L & T Water Tank filling work as per attached JMR 1 80.808
Total Earth Eork Qty in Sqm
BOQ Quantity
Previously Certified Qty
This Bill Qty.

Amendment Qty.

77 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H

Extra Item Structural Steel Supply & Installation

R.A.-03
Weight of One Jali MT Nos. L Wight per Rm Total weight
Vertical element of 25x25x2.6 mm MT 8 1.275 1.69 0.017
Vertical element of 25x25x2.6 mm MT 15 1.075 1.69 0.027
Horizontal element of 25x25x2.6 mm MT 2 3 1.69 0.010
Horizontal element of 40x40x3.2 mm MT 1 2.9 3.49 0.010
Base Plate 8mm thk. MT 4 0.030625 62.8 0.008
MS Flat MT 8 0.0046 62.8 0.002
Total Weight of 1 Jali
No. Of Jali Executed 27
R.A.-05
No. Of Jali Executed 4
Total Structural steel used for compound wall
Jali MT

78 of 211
Qty. Remarks
grades inboth dry and wet condition
es,ramming of bottoms complete,
sidered)

87.88
87.88
98.25
87.88
0.00

23.07
23.07
35.00
23.07
-
-

nsolidating deposited layer by watering,

110.95 for Lenth working space considered in calculation have to take decision from GPL
-13.18 Drawing-1
-71.90
-0.91
24.95
33.31
24.95
-
-

mixed, compacted by ramming and


ete.

2.20
-0.24
0.14 (L = 2.17x2)
0.15

0.45 Drawing-14
2.70
2.74

79 of 211
Qty. Remarks
2.70
-

gauge and down machine crushed hard


labour complete .

10.99
-1.18
0.65
0.06
0.74
11.26
11.93
5.35
0.20
0.05
17.52
6.46
-0.17
0.25
6.55
35.33
38.47
35.33
-
-
onforming to IS:2645 by weight of

10.99
-1.18
0.65
0.06
0.74
11.26
11.93
5.35
0.20
0.05
17.52
6.46
-0.17
0.25
6.55

80 of 211
Qty. Remarks
35.33
37.50
35.33
-0.00

tering and shuttering to correctline and


embly with propping,etc. with necessary
ng fully leakproof to avoid leakage of
cient strength to self-support itself

4.43
2.48
6.91
47.70
44.70
24.39
21.39
1.03
0.81
0.41
140.42
26.56
-0.85
2.83
2.54
3.18
1.63
35.89
183.22
187.03
183.22
-
-

Sample finalised at site.

3.00

3.00
3.00
3.00
-
-

81 of 211
Qty. Remarks
in water retaining structures including

20.00 Drawing-15
20.00
22.00
20.00
-

lised agency underground water


ces bypressure grouting, if required,
age 15mm thick for side walls of water
cement] and continued upto full height
all materials and labour complete in all

26.56 Drawing-1
1.35
27.91
44.70
21.39
66.09
94.00
94.00
94.00
-

nth level and above GL in true line level


o complete the job.

0.93
0.55
-0.01 Drawing-14

1.83
2.15
5.44
1.63
1.63
0.00
3.81

82 of 211
Qty. Remarks
and at all floors and at all heights with
mplete.

4.03
1.96
2.51
2.41
-0.09 Drawing-14
10.81
12.65
10.81
-
-

Consultant's Design/Drawing

ethod.

120.00
120.00

ipe of Jindal Make.

119
119

1.50
1.50

90
90

83 of 211
Qty. Remarks
Area = (PI()/4*(0.3^2-
6.28 0.15^2))
6.28

0.50

0.50
1.00
1.00
1.00
0.00
0.00

authorities.

6.00
6.00

1.00
1.00

pipeline or to be brought from Outside in

1.00
1.00

10.53
-0.02
10.52
8.64
0.00

84 of 211
Qty. Remarks
8.64
1.88

1.00
1.00

3.500
1.000
0.110 ( Area = (PI()/4*0.2*0.2)
( Area = ((1/2)*0.2*0.2) L
0.025 = ( PI()*0.4)
0.013
0.148

Nos. R.A.-02
Nos. R.A.-02

dicated, up to any lead and level,


all include backfilling of the excavated pit
s of underground structures, buried rafts,
tc. complete and stacking the excavated

g space & slope if required for

8.014 Drawing-2

1.979
9.99
16.00
9.99
-
-

85 of 211
Qty. Remarks

mixed, compacted by ramming and


plete - FOR RCC BEAM BOTTOM

2.708 Drawing-2

0.669
0.004
3.38
4.00
3.38
0.00
-

mixed, compacted by ramming and


plete - FOR COPING

2.185
-0.515
-0.041 Drawing-16

2.725
-0.552
-0.041
-1.628
2.13
3.50
2.13
-
-
gauge and down machine crushed
s and labour complete. FOR PLINTH

5.906 Drawing-2
5.026 Drawing-2

1.241 Drawing-17
12.17
16.00
12.17
-

86 of 211
Qty. Remarks

gauge and down machine crushed


s and labour complete. FOR PLINTH

43.700 Drawing-2

10.792 Drawing-17
54.49
91.00
54.49
-
-

w plinth level and above GL in true line


ures to complete the job.

32.480

2.610 Drawing-16

34.800

2.610

-35.090

2.320 JMR/8592
39.73

87 of 211
Qty. Remarks
45.00
39.73
-
-

w plinth level and above GL in true line


ures to complete the job.

H =( 50.84-0.1) -
(49.431+.075+0.23)
95.380 Drawing 2 & 3

23.554
118.93
104.65
104.65
-
14.28

and at all heights with necessary


Mt wide)

64.960
19.343 Drawing-16
5.220

69.600
20.677
5.220

27.246
-89.523
122.74
90.00
90.00
-
32.74

88 of 211
Qty. Remarks

and at all heights with necessary


s (below screen wall)

H =( 50.84-0.1) -
(49.431+.075+0.23)
209.760 Drawing 16

H =( 50.84-0.1) -
(49.431+.075+0.23)
51.800 Drawing 16
261.56
209.30
209.30
-
52.26

134.400

13.340

10.800 Drawing-16

144.000

14.260 Drawing-16

21.600

89 of 211
Qty. Remarks

-158.540
179.86
244.80
179.86
-
-

ts of Acrylic emulsion paint of approved


urfaces and all heights to give an even
after thoroughly brushing the surface
red smooth etc. including all materials

15.530 L as per RA-05


15.212 certification in 4'' B/W

14.040
44.78
344.30
44.78
-

en shade including thoroughly brooming


nd measures to complete th job.

69.600
20.677
5.220
27.246

H =( 50.84-0.1) -
(49.431+.075+0.23)
130.780 Drawing 16

H =( 50.84-0.1) -
(49.431+.075+0.23)
35.538 Drawing 16
289.06
-
-
-
289.06

90 of 211
Qty. Remarks

575.777 OGL = 49.814


1093.246
427.519
0.000
0.000
0.000

-86.00

-0.184
-0.248
-56.660
-11.760
-13.113
-0.442
-0.330
-14.538
-7.856
-5.706

-0.239

-0.310
-0.422
-0.520
-0.451
-0.410
-0.346

-0.835

-0.784
-0.702
-0.651
-0.599
-0.416
-0.455
-0.252
-0.178

-0.812

-0.884
-0.956
-1.028
-1.100

91 of 211
Qty. Remarks
-1.172
-1.244
-1.316
-1.244
-1.172
-1.100
-1.028
-0.956
-0.884
-0.812

-0.892

-0.964
-1.037
-1.109
-1.181
-1.253
-1.325
-1.397
-1.397
-1.325
-1.181
-1.109
-1.037
-0.964
-0.892
-1.689
-1.689
-1.689
-1.689
-4.487 Drawing-19
-948.780 From PH-3B RA 04

11.936
377.281
350.254
80.808
1719.63
90.00
90.00
-

- Already Paid in Hardscap


BOQ Extra Item RA-05

92 of 211
Qty. Remarks

weight

Drawing-18

0.075

2.317

93 of 211
OGL For Rain water tank
49.113 49.088 49.069 49.049 49.030
49.265 49.245 49.225 49.206 49.186
49.327 49.338 49.349 49.359 49.343
49.424 49.393 49.404 49.415 49.426
49.544 49.486 49.459 49.470 49.481
Average 49.335 49.310 49.301 49.300 49.293
Total Average 49.308

Bottom Level for Rain water tank


46.785 46.783 46.78 46.787
46.782 46.785 46.783 46.78
Average 46.784 46.784 46.782 46.784
Total Average 46.783

Height Of Excavation = 49.308-46.783 = 2.525 2.525


Seating area bottom
50.22 50.2 50.215 50.225 50.23 50.211
50.213
50.216

Seating area lawn top


50.672 50.675 50.67 50.665 50.65 50.673
50.668
Height of soil filling 0.451
Deduction for kamp 0.15 (Same As Landscap Work Certification by GPL
Depth of soil 0.301

Block D side plantation bottom


50.22 50.23 50.225 50.215 50.203 50.215
50.218

Block D side plantation Top


50.655 50.643 50.647 50.652 50.65 50.657
50.66 50.656 50.65 50.5 50.51 50.505
50.6095
Height of soil filling 0.391
Deduction for kamp 0.15 (Same As Landscap Work Certification by GPL
Depth of soil 0.241
OGL For Compound wall OGL For Strom wat
49.002 48.950 48.898 48.935 49.031 49.137 49.797
49.263 49.365 49.491 49.618 49.744 49.861 49.745
49.867 49.838 49.830 49.935 50.015 50.103 49.742
50.252 50.254 50.250 50.030 49.589 49.656 49.930
49.714 49.694 49.689 49.630 49.578 49.667 49.988
49.7 49.712 49.746 49.787 49.819 49.850 49.840
49.633 49.636 49.651 49.656 49.629 49.712 49.8
49.653
Bottom level of compound wall Bottom level of stro
49.43 49.432 49.431 49.434 49.433 49.431 49.49
49.433 49.430 49.431 49.429 49.428 49.429 49.4
49.431 49.433 49.434 49.431 49.432 49.43
49.429 49.428 49.429 49.431 49.431 49.43
49.43 49.432 49.431 49.434 49.433 49.431
49.431 49.429 49.428 49.43 49.429 49.428
49.43067 49.43067 49.43067 49.4315 49.431 49.42983
49.431

0.222 0.084381 380


0.38
9.956971
760000

118.52 23.52
101.03
Area-1
Top Level of Back filling at D Block for R.A.-03 Top Level of Back
50.26 50.263 50.28 50.285 50.19 50.195 50.21
50.263 50.260 50.282 50.283 50.192 50.193 50.212
50.258 50.263 50.281 50.285 50.191 50.194 50.213
50.259 50.262 50.282 50.285 50.19 50.193 50.214
50.261 50.26 50.283 50.281 50.192 50.19 50.215
50.258 50.263 50.284 50.282 50.195 50.193 50.212
50.261 50.263 50.283 50.281 50.193 50.191 50.214
50.260 50.262 50.282 50.283 50.192 50.193 50.213
50.245

Top Level of GSB filling at D Block for R.A.-03 Top Level of GSB
50.36 50.363 50.38 50.385 50.29 50.295 50.3455 50.31
50.363 50.360 50.382 50.383 50.292 50.293 50.3455 50.312
50.358 50.363 50.381 50.385 50.291 50.294 50.34533 50.313
50.359 50.362 50.382 50.385 50.29 50.293 50.34517 50.314
50.361 50.36 50.383 50.381 50.292 50.29 50.3445 50.315
50.358 50.363 50.384 50.382 50.295 50.293 50.34583 50.312
50.361 50.363 50.383 50.381 50.293 50.291 50.34533 50.314
50.360 50.362 50.382 50.383 50.292 50.293 50.345 50.313
50.345

Top Level of WMM fillin


50.33
50.333
50.331
50.331

OGL For Debri


OGL For Debris Removal for D Building 50.068
49.594 49.478 49.423 49.508 49.473 49.761 49.946
49.555 49.522 49.81 49.602 49.572 49.86 49.953
49.654 49.621 49.909 49.841 49.544 49.671 49.982
49.764 49.503 49.72 49.469 49.733 50.144 49.98
49.907 50.102 49.899 49.982 49.961 50.009 50.002
50.059 49.98 50.034 50.048 50.005 50.034 49.963
50.002 50.02 49.988 49.974 49.925 49.913 49.872
49.844 49.9 49.832 49.845 49.832 49.848 49.816
49.835 49.832 49.822 49.917 49.9 49.854 49.865
49.802 49.721 49.85 49.838 49.835 49.832 49.825
49.861 49.901 49.905 49.84 49.774 49.697 49.855
49.841 49.838 49.835 49.825 49.899 49.883 49.884
49.931 49.847 49.756 49.878 49.756 49.878 49.896
49.97 49.828 49.858 49.9 49.789 49.823 49.923
49.82 49.791 49.801 49.857 49.855 49.852 50.12
49.823 49.816 49.784 49.783 49.778 49.76 50.149
49.861 49.858 49.855 49.853 49.81 49.791 50.176
49.779 49.744 49.76 49.664 49.864 49.861 50.066
49.859 49.856 49.83 49.797 49.766 49.737 49.818
49.754 49.657 49.864 49.864 49.862 49.862 49.537
49.861 49.86 49.859 49.858 49.857 49.855 49.704
49.855 49.853 49.853 49.851 49.851 49.971 49.789
49.934 49.868 49.849 49.849 49.954 49.902 49.799
49.847 49.846 49.8 49.856 49.91 49.867 49.73
49.924 50.04 50.003 49.966 49.904 49.992 49.835
50.035 49.999 49.941 49.913 50.04 50.031 50.097
49.972 50.063 50.032 50.05 50.047 50.073 50.064
50.066 50.01 50.007 49.933 49.948 49.87 50.226
49.944 49.889 49.881 49.871 49.833 49.869 50.164
49.833 49.866 49.799 49.833 49.864 49.811 50.164
49.833 49.821 49.824 49.787 49.851 49.7 50.293
49.819 49.606 49.751 49.852 49.653 49.803 50.14
49.578 49.7 49.503 49.625 49.43 49.551 50.113
49.384 49.476 49.403 49.523 49.364 49.448 50.155
49.826 50.169

D Block level after removal of Debris


49.194 49.078 49.023 49.108 49.073 49.361 49.46 B Block
49.507 49.702 49.499 49.582 49.561 49.609 49.574 49.668
49.447 49.356 49.478 49.356 49.478 49.453 49.41 49.58
49.46 49.459 49.458 49.457 49.455 49.4 49.456 49.425
49.524 49.604 49.403 49.566 49.504 49.592 49.513 49.523
49.433 49.466 49.399 49.433 49.464 49.411 49.471 49.137
48.984 49.078 49.003 49.123 48.964 49.048 49.03 49.764
49.377 49.769

0.449
Block D lawn are bottom
50.217 50.215 50.22 50.25 50.225 50.22 50.213 50.217 50.22

50.2225

Block D lawn area top


50.67 50.707 50.7 50.702 50.7 50.71 50.71 50.706 50.704
50.704875
Height of soil filling 0.482
Work Certification by GPL) Deduction for kamp 0.15 (Same As Landscap Work Certification by GPL)
Depth of soil 0.332

om Block B side plantation bottom


50.213 50.2 50.215 50.22 50.19 50.205
50.18 50.23 50.217 50.215 50.195
50.2073
p Block B side plantation Top
50.653 50.653 50.655 50.672 50.666 50.65 50.657 50.66
50.495 50.665 50.653
50.659
Height of soil filling 0.452
Work Certification by GPL) Deduction for kamp 0.15 (Same As Landscap Work Certification by GPL)
Depth of soil 0.302
OGL For Strom watr trench at D block OGL For Strom watr trench at B block
49.438 49.467 49.655 49.758 50.677 50.656 50.628
49.772 49.766 49.733 49.742 50.568 50.540 50.512
49.709 49.701 49.861 49.98 50.396 50.365 50.301
49.729 49.913 49.924 49.976 50.207 50.176 50.145
50.289 49.952 50.231 50.077 50.071 50.087 50.082
49.787 49.760 49.881 49.907 49.948 49.836 49.784
49.835 50.311 50.277 50.242
50.248
Bottom level of strom water trench at D block wall Bottom level of strom water trench at B block wall
49.495 49.498 49.5 49.505 49.8 49.81 49.816
49.498 49.815

0.337 0.433

49.835 50.248
49.498 49.815

50.515 50.228
Area-3 Area-2
Top Level of Back filling at B Block for R.A.-03 Top Level of Back filling at Central portion for R.A.-03
50.215 50.17 50.19 50.14 50.145 50.21 50.215 50.237
50.214 50.175 50.185 50.142 50.144 50.211 50.214 50.238
50.211 50.177 50.183 50.141 50.143 50.213 50.215 50.237
50.212 50.179 50.18 50.14 50.143 50.21 50.214 50.239
50.21 50.18 50.183 50.142 50.144 50.214 50.215 50.241
50.214 50.184 50.182 50.141 50.143 50.213 50.211 50.24
50.215 50.182 50.177 50.143 50.143 50.21 50.214 50.237
50.213 50.178 50.183 50.141 50.144 50.212 50.214 50.238
50.179 50.237

Top Level of GSB filling at B Block for R.A.-03 Top Level of GSB filling at B Block for R.A.-03
50.315 50.27 50.29 50.24 50.245 50.31 50.315 50.337
50.314 50.275 50.285 50.242 50.244 50.311 50.314 50.338
50.311 50.277 50.283 50.241 50.243 50.313 50.315 50.337
50.312 50.279 50.28 50.24 50.243 50.31 50.314 50.339
50.31 50.28 50.283 50.242 50.244 50.314 50.315 50.341
50.314 50.284 50.282 50.241 50.243 50.313 50.311 50.34
50.314 50.282 50.277 50.243 50.245 50.31 50.314 50.337
50.313 50.278 50.283 50.241 50.244 50.312 50.314 50.338
50.279 50.336

Top Level of WMM filling at Compound wall side B Block Top Level of WMM filling at B Block for R.A.-03 Central p
50.335 50.332 50.334 50.331 50.445 50.45 50.447
50.330 50.333 50.332 50.334 50.446 50.451 50.449
50.333 50.333 50.333 50.332 50.455 50.455 50.446
50.333 50.333 50.333 50.332 50.449 50.452 50.447
50.332 50.450

Top Level of GSB filling at D Block for R.A.-04


50.313 50.315 50.34
50.312 50.314 50.338
50.314 50.31 50.338
50.314 50.315 50.341
50.31 50.313 50.335
50.337

Top Level of GSB filling at B Block for R.A.-04


50.312 50.315 50.337
50.311 50.315 50.339
50.31 50.314 50.338
50.314 50.318 50.338
50.313 50.314 50.337
50.337

0.190 50.142
Top Level of WMM filling at B Block for R.A.-04
50.445 50.455 50.446
50.447 50.454 50.445
50.446 50.451 50.446
50.446 50.453 50.446
50.450

OGL For Debris Removal for B Building Bottom level of soil filled at Garden Pathway
50.003 49.962 49.934 49.991 49.95 50.215 50.21 50.213
49.951 49.955 49.96 49.965 50.012 50.22 50.225 50.21
49.958 49.963 49.968 49.972 49.977 50.21 50.22 50.23
49.992 50.095 49.965 49.97 49.975 50.205 50.2 50.205
49.985 49.989 49.994 50.002 50.012 50.208 50.213 50.205
50.006 50.011 50.022 49.973 49.983 50.213
49.931 49.926 49.899 49.893 49.878
49.858 49.851 49.837 49.845 49.83 Top level of soil filled at Garden Pathway
49.811 49.879 49.824 49.809 49.796 50.37 50.372 50.368
49.803 49.785 49.85 49.782 49.822 50.371 50.375 50.372
49.894 49.824 49.84 49.909 49.823 50.365 50.367 50.375
49.923 49.822 49.869 49.938 49.956 50.371 50.369 50.365
49.952 49.83 49.898 49.862 49.844 50.37 50.368 50.368
49.861 49.859 49.917 49.903 49.861 50.370
49.902 49.94 49.93 49.966 49.945
49.971 50.13 50.14 50.139 50.15
50.159 50.169 50.179 50.189 50.198
50.201 50.165 50.155 50.119 50.109
50.085 50.037 50.007 49.959 49.929
49.832 49.652 49.822 49.666 49.68
49.541 49.459 49.685 49.544 49.486
49.655 49.547 49.544 49.393 49.868
49.71 49.631 49.557 49.548 49.886
49.72 49.641 49.567 49.551 49.809
49.657 49.602 49.746 49.691 49.636
49.726 49.936 49.857 50.005 49.926
49.995 49.916 50.063 49.986 50.132
50.201 50.142 50.22 50.171 50.216
50.198 50.207 50.187 50.197 50.178
50.169 50.177 50.288 50.222 50.189
50.147 50.152 50.158 50.458 50.375
50.222 50.176 50.151 50.13 50.135
50.382 50.3 50.221 50.162 50.137
50.118 50.123 50.839 50.307 50.224
50.313 50.32 50.238 50.245 50.252
50.176 50.094 50.26 50.101 50.178
49.972

B Block level after removal of Debris


49.55 49.56 49.565 49.558 49.611 49.572
49.585 49.589 49.594 49.602 49.612 49.425
49.494 49.424 49.44 49.509 49.423 49.498
49.502 49.54 49.53 49.566 49.545 49.607
49.141 49.059 49.285 49.144 49.086 49.477
49.769 49.777 49.888 49.822 49.789 49.821
49.776 49.694 49.86 49.701 49.778 49.439
49.553
0.419
m watr trench at B block
50.600 50.572
50.458 50.427
50.270 50.239
50.114 50.093
50.077 50.060
49.773 49.763
50.215 50.192
50.248
m water trench at B block wall
49.822 49.825
49.815

Area-2
k filling at Central portion for R.A.-03 50.263
50.242 50.255 50.265
50.242 50.257 50.263
50.243 50.256 50.261
50.24 50.259 50.263
50.24 50.255 50.265
50.241 50.256 50.261
50.243 50.256 50.259
50.242 50.256 50.262
50.237

GSB filling at B Block for R.A.-03


50.342 50.355 50.365
50.324 50.357 50.363
50.343 50.356 50.361
50.34 50.359 50.363
50.34 50.355 50.365
50.341 50.356 50.361
50.3 50.356 50.359
50.333 50.356 50.362
50.336

filling at B Block for R.A.-03 Central part


50.453 50.446
50.453 50.449
50.451 50.448
50.4523333 50.448 50.259
50.450 0.191

GSB filling at D Block for R.A.-04


50.341 50.35 50.363
50.325 50.358 50.364
50.342 50.365 50.361
50.34 50.355 50.365
50.34 50.356 50.359
50.337 0.099

GSB filling at B Block for R.A.-04


50.34 50.355 50.365
50.34 50.356 50.362
50.343 50.353 50.363
50.341 50.352 50.362
50.341 50.352 50.361
50.337 0.100

t B Block for R.A.-04


50.452
50.453
50.455
50.453
50

d at Garden Pathway
50.21
50.213
50.235
50.207
50.207
13

at Garden Pathway
50.37
50.367
50.368
50.37
50.372
70 49
181
PHASE 3 D - ELECTRICAL WORKS
BOQ

ITEM No. ITEM DISCRIPTION UNIT


TOTAL RATE AMOUNT

Electrical works for External Supplying & laying of following 1100 volt grade
XLPE insulated PVC inner sheathed and HR PVC outer sheathed aluminium
conductor armoured cables as per specification in existing trenches, cable
3 trays, ducts, clamped to wall with suitable clamps including, saddles fixing
bolts, connecting testing and commissioning,with necessory cable joints .

3.1 3.1/2 core 240 sq. mm (supply) M 1600 1,026.510 1,642,416.00


3.2 3.1/2 core 240 sq. mm (Installation) M 1600 94.380 151,008.00
3.3 same as above 3.1/2 core 185 sqmm M 100 812.450 81,245.00
3.4 (supply)
same as above 3.1/2 core 185 sqmm M 100 89.510 8,951.00
3.5 (installation)
same as above 3.1/2 core 95 sqmm M 100 442.710 44,271.00
3.6 (supply)
same as above 3.1/2 core 95 sqmm M 100 87.570 8,757.00
3.7 (installation)
Same as above 4 core 25 sqmm M 600 150.810 90,486.00
(supply)
same as above 4 core 25 sqmm
3.8 (installation) M 600 50.590 30,354.00
3.9 same as above 4 core 1.5 sq.mm control cable (supply) M 0 60.320 -
3.10 same as above 4 core 1.5 sq.mm control cable (installation) M 0 35.020 -
Cable end termination of the following
XLPE insulated HR PVC
outer-sheathed aluminium/copper conductor armoured cables of 1100 volt
0
grade-including supplying and fixing of bimettalic crimping lugs,
double-compression glands with earthing.

3.11 same as above 3.1/2 core 240 sq. mm.Aluminium Cable (supply) Nos 16 1,892.480 30,279.68
3.12 same as above 3.1/2 core 240 sqmm.Aluminium Cable (installation) Nos 16 384.330 6,149.28
3.13 same as above 3.1/2 core 185 sq. mm. Aluminium Cable (supply) Nos 16 1,557.770 24,924.32
3.14 same as above 3.1/2 core 185 sq. mm. Aluminium Cable (installation) Nos 16 350.280 5,604.48
3.15 same as above 3.1/2 core 95 sq. mm. Aluminium Cable (supply) Nos 2 997.320 1,994.64
3.16 same as above 3.1/2 core 95sqmm. Aluminium Cable (installation) Nos 2 273.410 546.82
3.17 same as above 4 core 25 sq. mm Nos 10 632.450 6,324.50
3.18 Aluminium
same Cable4 (supply)
as above core 25 sq. mm Nos 10 199.460 1,994.60
3.19 Aluminium Cable4 (installation)
same as above core 1.5 sq.mm control cable (supply) Nos 50 184.870 9,243.50
PHASE 3 D - ELECTRICAL WORKS
BOQ

ITEM No. ITEM DISCRIPTION UNIT


TOTAL RATE AMOUNT

3.20 same as above 4 core 1.5 sq.mm control cable (installation) Nos 50 60.320 3,016.00
Providing, Laying, jointing and testing socketed and spigotted RCC pipes-(NP2
class) for conveying Pipelines across roads conforming to IS:458-collars
jointed with stiff mixture of cement mortar in the proporation-of 1:2 (1 cement :
2 find sand) laid to correct levels below ground in-trenches upto
required depth including excavation in all kind of soil-(hard / soft), dewatering,
refilling, watering, ramming and
removing the-surplus excavated material including curing with all necessary
lead and-lifts as required including testing of joints etc. complete of following-
3.21 sizes. Cost shall be inclusive of providing protection to pipe all-round/ M 50 194.600 9,730.00
haunches as per specification.-same as above 150
mm dia ID (supply)

3.22 same as above 150 mm dia ID (installation) M 50 194.600 9,730.00


3.23 same as above 200 mm dia ID (supply) M 0 291.900 -
same as above 200mm dia ID (installation)Note: Wherever, pipes are laid in Stilt floor,
3.24 providing 75 mm thickcement concrete all around pipe M 0 486.500 -
1:3:6 (1 cement, 3 coarse sand and 6 crushed stone aggregate).
Providing and fixing of the following size medium class GI pipe sleeves.-same as
3.25 above 100 mm. dia (supply) 10 973.000 9,730.00
3.26 same as above 100 mm. dia M 10 486.500 4,865.00
3.27 (installation)
same as above 150 mm. dia (supply) M 0 1,459.500 -
3.28 same as above 150 mm. dia M 0 486.500 -
(installation)
Supply and fixing of perforated type factory fabricated GI cable trays-of the
3.29 following sizes including providing GI suspenders and supports as-per M 15 1,026.510 15,397.65
specifications.-600mm wide (supply)
3.3 same as above 600mm wide M 15 350.280 5,254.20
3.31 (installation)
450mm wide (supply) M 30 671.370 20,141.10
3.32 same as above 450mm wide M 30 324.000 9,720.00
(installation)
PHASE 3 D - ELECTRICAL WORKS
BOQ

ITEM No. ITEM DISCRIPTION UNIT


TOTAL RATE AMOUNT

3.33 same as above 300mm wide (supply) M 30 482.600 14,478.00


3.34 same as above 300mm wide M 30 324.000 9,720.00
3.35 (installation)
same as above 150mm wide (supply) M 45 293.840 13,222.80
3.36 same as above 150mm wide M 45 223.790 10,070.55
(installation)
Plumbing Plant Room Panel, 1 no.80Ampere Manually operated TPN MCB'S, 0-500V
3.37 Digital Volt Meter ,With selector switch to be provied by 2 Amps TP MCCB'S , Nos 0 34,833.400 -
Compartment for UGVCL Metering With Sealing Facility.
3.38 Same as Above (Installation) Nos 0 2,588.180 -
SECTION FEEDER PILLAR TYPE-B (IP-55) TRANSFORMER--Incoming -
630 amps TP Fuse base with 630A HRC fuse with
following-accessories:-,,-i,,Phase indicating lamps.-ii,,18W CFL lamp with holder with
switch-iii,,6A switch socket for maintenance-,,-Bus Bars - 630 amps FP aluminium bus
bars with coloured heat shrinkable-insulated
3.39 sleeve.-,,-Outgoing - 4Nos 200 amps TP Fuse base with 200 amps HRC fuse-100 Nos 2 68,182.970 136,365.94
amps TP Fuse 1Nos base with 100 amps.-All Fuse's shall be of 25 KA breaking
capacity.-SFP-TYPE-B-supply

3.4 same as above (installation) Nos 2 3,484.310 6,968.62


Type-F (for external lighting with
IP-55),,-Incomer: 1no. 63A 4P MCB isolator with 100A 4P insulated copper busbars-
with,,-i.,,Digital energy meter (conzerve # EM 6400 with RS-485 or equivalent)-of
accuracy class-I, with 3
3.41 Nos. 63/5 amps 15VA CTs.1 Nos 0 79,630.320 -
Set--ii.,,VAF digital electronic meter similar to Conzerv ELF- 3259 with-inbuilt selector
switch and 63/5 Amps suitable VA, CL 1 CTs.,,1 Set--iii.,,Phase indicating light shall be
protected by 2 amps MCB’s. 3 Set-supply

same as above (installation)Out going :


2sets each having 6 way TPN DB 6 Nos.
3.42 10 amps SP MCB perphase as outgoing with 3 nos. 40 amps DP RCCB of 30 mA Nos 0 5,477.990 -
leakage currentplus 1 No. 40 amps TP Contactor controlled through 0-24 hour timer
and 1No. 40 amps 4 pole isolator as incomer.
PHASE 3 D - ELECTRICAL WORKS
BOQ

ITEM No. ITEM DISCRIPTION UNIT


TOTAL RATE AMOUNT

Supply and laying of GI pipe under road


3.43 / paved area crossing etc.-including excavation back filling ramming and M 20 389.200 7,784.00
making good.-50 mm dia pipe - supply
3.44 50 mm dia pipe - installation M 20 291.900 5,838.00
3.45 100 mm dia pipe - supply M 15 973.000 14,595.00
3.46 100 mm dia pipe - installation M 15 389.200 5,838.00
3.47 150 mm dia pipe - supply M 0 1,459.500 -
3.48 150 mm dia pipe - installation M 0 486.500 -
Maintenance free earthing electrode/ chemical earthing--Providing and laying of 14.35
mm dia and 3 meter length.copper bonded-earth rod in
150mm dia. in an augured hole in ground , surrounded by-ground enhancement
material as per specification. Inspection chamber-shall be of 400 x 500 mm with
concrete base CI manhole cover with frame-painted with bitumastic paint. 2 Nos. of
50 x 6 mm cross section & 300-mm long copper strip to be clamped with copper
claded rod electrode have-sufficient nos. (But not less than 4 Nos.) of 10 mm dia. GI
3.49 nuts & bolts-for connection to the equipment/ interconnection to the other pits to-form Nos 6 7,467.770 44,806.62
equi-potential bonding .The pH value of ground enhance
material-shall be 6.9 to 7.2 of 1000gm/ lit
@ 20 deg.c.The minimum 30kg of ground-enhancement material shall provided for
each electrode.-supply

3.5 same as above (installation) Nos 6 2,490.880 14,945.28


Supply,Installation,Testing and commissioning of 11/0.433kv Compact Secondary
Sub-Station comprisitng 11kv 630 A 11Kv Non-Ext compactSF6 RMU-2Nos Isolating
Switchs & one Tap off Vacuum circuit Breaker cum-outgoing with metering &
protection 1250 KVA 11 / 0.433 KV Oil cooled-transformer & LT panel consisting of 1
No.2000A (MAX), 3Nos 630A,1Nos of 250A,1Nos of 200A, 2Nos of 63 Amp
3.51 (MAX),3P, 50 kA MCCB with micro-processor based release as outgoing.- All ACB / Nos 0 3,259,939
MCCB shall have Microprocessor based release unit. Package-sub-station shall be
complete as per specification.-supply
PHASE 3 D - ELECTRICAL WORKS
BOQ

ITEM No. ITEM DISCRIPTION UNIT


TOTAL RATE AMOUNT

Supply and fixing in position the best quality Danger Boards of


approved-shape and size as specified by
3.52 Local Electricity Authorities written Nos 4 74.920 299.68
in-English & Local Languages.-supply
3.53 same as above - installation Nos 4 30.160 120.64
Supply and fixing in position 1000 mm wide rubber matting of 11 KV grade-as per
3.54 electricity rules.-supply M 15 925.320 13,879.80
3.55 installation M 15 49.620 744.30
Supply of fire buckets 5 nos. in each set duly filled with fine sand and-fixed on an
angle iron frame as per requirement of local authorities.- Fire buckets shall be painted
3.56 red from outside and white from inside-with additional handle at the bottom.-supply Nos 1 2,490.880 2,490.88

3.57 same as above - installation Nos 1 350.280 350.28


3.58 Supply of first aid box of approved make as per specification.-supply Nos 1 515.690 515.69
3.59 same as above - installation Nos 1 55.460 55.46
Supply of tool kit with 1 pair 11 KV
3.60 rubber hand gloves of approved-make.-supply Nos 1 1,094.620 1,094.62
HT CABLES & LT CONTROL
CABLES-Supplying and laying following size 11 KV grade XLPE aluminium
3.61 conductor-armoured cables laid over MS supports in existing trenches.-3C x M 0 1,396.250 -
240 sqmm 11 KV XLPE cable (supply)

3.32 3C x 240 sqmm 11 KV XLPE cable installation. M 0 84.650 -


Supplying and making cable end terminations for the following size of
11-KV grade, XLPE aluminium conductor armoured cable including termination-
kit complete heat shrinkable sleeve etc.-3 C x 240 sq.mm 11 KV
3.63 Nos 0 10,459.750 -
XLPE cable (indoor) (supply)

3.64 3 C x 240 sq.mm 11 KV XLPE cable Nos 0 1,493.550 -


3.65 (indoor)
3 (installation)
C x 240 sq.mm 11 KV XLPE cable Nos 0 14,434.450 -
3.66 (outdoor) (supply)
same as above (installation) Nos 0 1,994.650 -
3.67 Supplying, laying GI sleeves of following sizes:-150 mm dia (supply) M 0 1,459.500 -
3.68 150 mm dia (installation) M 0 486.500 -
PHASE 3 D - ELECTRICAL WORKS
BOQ

ITEM No. ITEM DISCRIPTION UNIT


TOTAL RATE AMOUNT

EARTHING FOR SUB-STATION EQUIPMENT-Supplying and fixing of following


bare copper/ GI tapes including all-necessary fixing accessories and effecting
3.69 connections.-50 mm x 6 mm thick GI tape (supply) M 0 268.540 -

50 mm x 6 mm thick GI tape
3.70 (installation) M 0 39.890 -
3.71 25 mm x 6 mm thick GI tape M 60 134.270 8,056.20
3.72 (supply)
25 mm x 6 mm thick GI tape M 60 30.160 1,809.60
(installation)
Bracket (750 MM in 32mm Pipe) with 100x 100 mm insert plate & anchor fastner with
3.73 pU paint for BRP 020, 24 W, Green line Smart LED. Nos 31 846.510 26,241.81
3.74 Wall Monted Light Fitting BRP-020 Supply Nos 31 3,634.150 112,658.65
3.75 same as above - installation Nos 31 249.080 7,721.48
3.76 Syntex junction box with 6 Amps MCB & connectors Supply & Installation Nos 31 700.560 21,717.36
Post /Round LED for walkway, 63 W, BGP150 LED with 75 MM dia, 3 Mtr. Pole
3.77 including PU paint. Nos 0 5,474.090 -
3.78 Post /Round LED for walkway, 63 W, BGP150 LED Supply Nos 41 39,917.320 1,636,610.12
3.79 same as above - installation Nos 41 2,490.880 102,126.08
3.80 garden Focus light supply Nos 6 2,490.880 14,945.28
3.81 same as above - installation Nos 6 350.280 2,101.68
3.82 Single Pole MCB 6A to 32A Supply Nos 78 169.300 13,205.40
3.83 63 Amp Four Pole MCB Nos 0 1,343.710 -
3.84 same as above - installation Nos 0 65.190 -
3.85 PVC Pipe 50 mm dia Supply & Installation M 120 146.920 17,630.40
3.86 25mm PVC pipe Supply & Installation M 120 50.590 6,070.80
Making Holes in 200mm thk RCC Walls, cutting reinforcement, inserting the pipe &
3.87 finishing all inclusive (including disposal of dismantled materials) - With Following Nos 5 2,432.500 12,162.50
proper water proffing methodology.
PHASE 3 D - ELECTRICAL WORKS
BOQ

ITEM No. ITEM DISCRIPTION UNIT


TOTAL RATE AMOUNT

Providing and laying of GI "C" Class pipe of 65 mm dia and 3 meter length earth rod
in 150 mm dia. in an augured hole in ground , surrounded by ground coal & salt.
Inspection chamber shall be of 400 x 400 mm with concrete base CI manhole cover
with frame painted with bitumastic paint. 1 Nos. of 50 x 6 mm cross section & 300 mm
3.88 Nos 8 5,176.360 41,410.88
long GI strip to be clamped with GI rod electrode have sufficient nos ( But not less
than 4 Nos.) of 10 mm dia. . 50 Kg coal and 100 Kg salt should be poured
sarrounidng the GI earth electrode.

3.89 same as above - installation Nos 8 1,994.650 15,957.20


EARTHING OF EQUIPMENT / OUTDOOR SWITCHYARD--Supply of Earth station
using 1200 x 1200 x 12 mm. GI plate as per IS-3043/1987 revised upto date complete
3.9 with C.I. Nos 0 9,457.560 -
cover and GI watering-pipe and masonry
work as required.--Supply

3.91 same as above installation Nos 0 3,483.820 -


Supply of 50x10 mm GI earthing strip for earthing of the equipment byconnecting to
earth mat in item 13.2 above, laying under ground orclamped to trench wall using MS
spacers and GI saddles, including makingproper connection to equipment, connecting
one flat with
3.92 M 0 369.740 -
other flatshould be with electric arc welding uniformly done with proper
overlap.Connecting GI strip to earth
electrode will be using GI Bolts.Supply

3.93 same as above installation M 0 124.540 -


3.94 Shock treatment chart English, Hindi, Gujarathi, 900mm x 1200mm. SizeSupply Nos 2 647.040 1,294.08
3.95 Installation Nos 2 74.920 149.84
3.96 CO2 portable Fire Extinguisher (4 litre capacity)Supply Nos 1 6,168.820 6,168.82
3.97 Installation Nos 1 249.080 249.08
3.98 HAND GLOVES 66 kVSupply Nos 0 447.580 -
PHASE 3 D - ELECTRICAL WORKS
BOQ

ITEM No. ITEM DISCRIPTION UNIT


TOTAL RATE AMOUNT

Liaison work with UGVCL/GETCO/Electrical Inspector etc. for 11KV Power


Distribution of Phase 3C (4)- 4 Nos Compact Substation's Network Design,
Installation, Testing & Commisioing's Approval & LT power ehnancement. The
Job includes not limited to;

Power Application collection from CC/FM team. 0 - -


Submission of Application & Test Report with requisite documents to UGVCL.
Organize the Estimates from UGVCL in 2 days.
Submission of Estimate payment to UGVCL.
Logistics management KWM meter from UGVCL & fixing to site with all
accessories in 2 days.

3.99 For flats load Nos 72 1,994.650 143,614.80


3.100 For Common area load Nos 8 2,490.880 19,927.04
For Compact Substation's Network Design, Installation, Testing & Commisioing's
3.101 Approval. Ls 2 124,446.700 248,893.40
3.102 Supply, Installation of common Area meter in meter room. Nos 2 2,490.880 4,981.76
SITC of DP Structure at GETCO Sub-station, as per the detailed Technical
3..103 Specifications. Nos 0 134,371.300 -
D.P. Structure
1. 11 KV AB switch : 1 Set
2. 11 KV D.O. fuse : 1 Set
3. 11 KV Disc insulator : 6 Set
4. 11 KV Pin insulator : 3 Set
5. 5 KV 5 KA L.A. : 1 Set
6. Stay Wire : 1 Set 0 - -
7. Jointing Kit outdoor type: 1set.
8. Steel structure of 9 mtr height I bean
2 nos. Channel, plate, insulator, clamp,
Hardware. Transportation etc

17 CIRCUIT CUM POINT WIRING 0 - -


PHASE 3 D - ELECTRICAL WORKS
BOQ

ITEM No. ITEM DISCRIPTION UNIT


TOTAL RATE AMOUNT

Wiring for 250 volts single phase and neutral 6 amps switched- socket outlet with 2.5
sq.mm PVC insulated copper conductor- 1100 volts grade stranded flexible FR
wires in 25mm dia. 2mm thick-embeded PVC conduit or surface mounted 25 mm dia
16 gauge MS conduit-including providing and
fixing of 6 amps 3 pin switch socket outlet of aprpoved make and design in 1.6 mm
3.104 thick GI box with grid plate and-earthing of third pin of the socket with 2.5 Sq. mm Nos 2 1,717.340 3,434.68
PVC insulated copper conductor stranded flexible FR wire (maximum-eight no. of
switches socket shall be connected on one circuit) Primary Point controlled by one 6
amp switch. (Supply)

3.105 Primary Point controlled by one 6 amp switch. (Installation) Nos 2 124.540 249.08
3.106 25 mm dia 16 guage MS/ 2mm thick M 50 35.020 1,751.00
3.107 PVC
25 mm(Supply)
dia 16 guage MS/ 2mm thick M 50 14.590 729.50
PVC (Installation)
Type E4 way SPN DB, 3 Nos. 10 to 16 amps SP MCB’s &with 1 No DPRCCB’s of 30
3.108 mA leakage current as incomer with neutral link. (Supply) Nos 0 2,777.910 -
Type E4 SPN DB, 3 Nos. 10 to 16 amps SP MCB’s & 1 No.DPRCCB’s of 30 mA
3.109 leakage current as incomer with neutral link. (Installation) Nos 0 398.930 -
3.110 63 amps FP MPCB, 7.5 KW with Nos 1 4,480.660 4,480.66
3.111 Star-Delta
63 amps FP Starter
MPCB, (Supply)
7.5 KW with Nos 1 249.080 249.08
Star-Delta Starter (Installation)
Supply and installation of Double wall corrugated high density polyethylene
pipe with necessary all accessories with excavation and backfilling. 0 - -

3.112 160 mm dia OD M 125 1,167.600 145,950.00


3.113 200 mm dia OD M 200 1,751.400 350,280.00
Construction of Brick Masonary chamber of 900x900 upto 1500 mm depth incluidng
3.114 excavation, backfilling, PCC, 230mm thk Masonary, Inside & outside 12mm thk Nos 4 24,325.000 97,300.00
plaster, SFRC cover etc.
Construction of Brick Masonary chamber of 600x600 upto 1000 mm depth incluidng
3.115 excavation, backfilling, PCC, 230mm thk Masonary, Inside & outside 12mm thk Nos 2 19,460.000 38,920.00
plaster, SFRC cover etc.
TOTAL of Tender Item 5,645,366.19
Extra Item
PHASE 3 D - ELECTRICAL WORKS
BOQ

ITEM No. ITEM DISCRIPTION UNIT


TOTAL RATE AMOUNT

Supplying & laying of following 1100 volt grade XLPE insulated HR PVC outer
sheathed aluminium/copper conductor armoured/unarmored cables laid in ground
excluding the cost of digging upto required depth ( minimum 750 mm) , 150 mm sand
E1 all around the cable, brick protection and back filling,with all necessory piping of
50mm,25mm when require & including connecting, testing and commissioning.

E2 4 core 1.5 sq.mm control Cu cable supply Rmt 2200 91.000 200,200.00
E3 4 core 1.5 sq.mm control Cu cable installation Rmt 2200 20.000 44,000.00
Supply, installation, connection, testing and commissioning of 65x8mm GI Strip with
E4 necessary fixing all complete. Rmt 40 489.000 19,560.00
Supply and installation 3 Mtr. Pole including PU paint, syntex box, required MCB and
E5 connector, all accessories etc. complete Nos 41 5,474.090 224,437.69
Supply, installation, testing and comissioning of 1.5 sqmm 3 core copper flexible cable
E6 Rmt 155 65.000 10,075.00
TOTAL of Extra Item 498,272.69
Total Carried To Summary 6,143,638.88
Quantity Amount
Up To
Up To Previous
Previous This Bill Up To Date This Bill Up To Date
Bill
Bill

1,533.00 - 1,533.00 1,573,639.830 - 1,573,639.830


1,559.00 - 1,559.00 147,138.420 - 147,138.420
- - - - -
- - - - -
- - - - -
- - - - -
570.00 - 570.00 85,961.700 - 85,961.700
570.00 - 570.00 28,836.300 - 28,836.300
- - - - -
- - - - -

- - - - -

16.00 - 16.00 30,279.680 - 30,279.680


16.00 - 16.00 6,149.280 - 6,149.280
4.00 - 4.00 6,231.080 - 6,231.080
4.00 - 4.00 1,401.120 - 1,401.120
- - - - -
- - - - -
8.00 - 8.00 5,059.600 - 5,059.600
8.00 - 8.00 1,595.680 - 1,595.680
- - - - -
Quantity Amount
Up To
Up To Previous
Previous This Bill Up To Date This Bill Up To Date
Bill
Bill
- - - - -

50.00 - 50.00 9,730.000 - 9,730.000

50.00 - 50.00 9,730.000 - 9,730.000


- - - - -

- - - - -

- - - - -
- - - - -
- - - - -
- - - - -

- - - - -

- - - - -
- - - - -
- - - - -
Quantity Amount
Up To
Up To Previous
Previous This Bill Up To Date This Bill Up To Date
Bill
Bill
- - - - -
- - - - -
- - - - -
- - - - -

- - - - -

- - - - -

2.00 - 2.00 136,365.940 - 136,365.940

2.00 - 2.00 6,968.620 - 6,968.620

- - - - -

- - - - -
Quantity Amount
Up To
Up To Previous
Previous This Bill Up To Date This Bill Up To Date
Bill
Bill

- - - - -

- - - - -
- - - - -
- - - - -
- - - - -
- - - - -

- - - - -

- - - - -

- - - - -
Quantity Amount
Up To
Up To Previous
Previous This Bill Up To Date This Bill Up To Date
Bill
Bill

- - - - -

- - - - -
- 4.000 4.00 - 3,701.280 3,701.280
- - - - -

- 1.000 1.00 - 2,490.880 2,490.880

- - - - -
- - - - -
- - - - -
- - - - -

- - - - -

- - - - -

- - - - -

- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
Quantity Amount
Up To
Up To Previous
Previous This Bill Up To Date This Bill Up To Date
Bill
Bill

- - - - -

- - - - -
- - - - -
- - - - -
- 30.000 30.00 - 25,395.300 25,395.300
- - - - -
- 30.000 30.00 - 7,472.400 7,472.400
30.00 - 30.00 21,016.800 - 21,016.800
- - - - -
- - - - -
37.00 - 37.00 92,162.560 - 92,162.560
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
120.00 - 120.00 17,630.400 - 17,630.400
86.61 - 86.61 4,381.600 - 4,381.600

- - - - -
Quantity Amount
Up To
Up To Previous
Previous This Bill Up To Date This Bill Up To Date
Bill
Bill

5.00 - 5.00 25,881.800 - 25,881.800

5.00 - 5.00 9,973.250 - 9,973.250

- - - - -

- - - - -

- - - - -

- - - - -
- - - - -
- - - - -
- 1.000 1.00 - 6,168.820 6,168.820
- - - - -
- - - - -
Quantity Amount
Up To
Up To Previous
Previous This Bill Up To Date This Bill Up To Date
Bill
Bill

- - - - -

- - - - -
- - - - -
- - - - -
- - - - -
- - - - -

- - - - -

- - - - -
Quantity Amount
Up To
Up To Previous
Previous This Bill Up To Date This Bill Up To Date
Bill
Bill

- - - - -

- - - - -
- - - - -
- - - - -
- - - - -

- - - - -
- - - - -
- - - - -

- - - - -

125.00 - 125.00 145,950.000 - 145,950.000


150.00 - 150.00 262,710.000 - 262,710.000

2.00 - 2.00 48,650.000 - 48,650.000

- - - - -

2,677,443.660 45,228.680 2,722,672.340


- - -
Quantity Amount
Up To
Up To Previous
Previous This Bill Up To Date This Bill Up To Date
Bill
Bill

- - - -

1,599.00 - 1,599.00 145,509.000 - 145,509.000


1,599.00 - 1,599.00 31,980.000 - 31,980.000
20.600 20.60 - 10,073.400 10,073.400

37.00 - 37.00 202,541.330 - 202,541.330

119.31 - 119.31 7,755.150 - 7,755.150


387,785.48 10,073.40 397,858.88
3,065,229.14 55,302.08 3,120,531.22
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Electrical works for External Supplying & laying of following 1100 volt grade XLPE insulated PVC
inner sheathed and HR PVC outer sheathed aluminium conductor armoured cables as per
specification in existing trenches, cable trays, ducts, clamped to wall with suitable clamps including,
3.1 saddles fixing bolts, connecting testing and commissioning,with necessory cable joints . 3.1/2 core
240 sq. mm (supply)

R.A.-05

Start End
Belveder Block-B Reading Readding Difference

Drum Number-2X-21651
Block-A CSS to Block-B SFP- Mtr 0 185 185 185.00 DC/540
1 (Cable-1)
Block-A CSS to Block-B SFP- Mtr 185 370 185 185.00 DC/540
1 (Cable-2)
Block-A CSS to Block-B SFP- Mtr 370 555 185 185.00 DC/540
1 (Cable-3)
R.A.-07
Belveder Block-D
Mtr CHL/801/16-
1531RMT CLAIM
978RMT
CSS to Block-D Meter 328.00 328.00 BALANCE -553
516 188.00
Room Cable-1 CLAIM IN 3C

126 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Mtr CHL/801/16-
1531RMT CLAIM
978RMT
CSS to Block-D Meter 325.00 325.00 BALANCE -553
510 185.00
Room Cable-2 CLAIM IN 3C

Mtr CHL/801/16-
1531RMT CLAIM
978RMT
CSS to Block-D Meter 325.00 325.00 BALANCE -553
505 180.00
Room Cable-3 CLAIM IN 3C

Total Qty 1533.00


BOQ Quantity 1,600.00
Previously Certified Qty 1,533.00
This Bill Qty. -
Amendment Qty.
Electrical works for External Supplying & laying of following 1100 volt grade XLPE insulated PVC
inner sheathed and HR PVC outer sheathed aluminium conductor armoured cables as per
specification in existing trenches, cable trays, ducts, clamped to wall with suitable clamps including,
3.2 saddles fixing bolts, connecting testing and commissioning,with necessory cable joints . 3.1/2 core
240 sq. mm (installation)

R.A.-05

Start End
Belveder Block-B Reading Readding Difference

Drum Number-2X-21651

127 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Block-A CSS to Block-B SFP- Mtr 0 185 185 185.00 JMR/588
1 (Cable-1)
Block-A CSS to Block-B SFP- Mtr 185 370 185 185.00 JMR/588
1 (Cable-2)
Block-A CSS to Block-B SFP- Mtr 370 555 185 185.00 JMR/588
1 (Cable-3)
R.A.-07
Belveder Block-D
CSS to Block-D SFP Mtr JMR/4998
516 188.00 328.00 328.00
Cable-1
CSS to Block-D SFP Mtr JMR/4998
510 185.00 325.00 325.00
Cable-2
CSS to Block-D SFP Mtr JMR/4998
505 180.00 325.00 325.00
Cable-3
Belveder Block-D
Mtr JMR/1026. Cable
supply paid in
SFP to Meter Panel-1 12 12.00 Phase 3C

Mtr JMR/1026. Cable


supply paid in
SFP to Meter Panel-2 14 14.00 Phase 3C

Total Qty 1559.00


BOQ Quantity 1,600
Previously Certified Qty 1,559.00
This Bill Qty. -
Amendment Qty.

128 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Electrical works for External Supplying & laying of following 1100 volt grade XLPE insulated PVC
inner sheathed and HR PVC outer sheathed aluminium conductor armoured cables as per
specification in existing trenches, cable trays, ducts, clamped to wall with suitable clamps including,
3.7 saddles fixing bolts, connecting testing and commissioning,with necessory cable joints . same as
above 4 core 25 sqmm
(supply)

R.A.-05

Start End
Belveder Block-B Reading Readding Difference

Drum Number-2X-21088
Block-A CSS to Block-B
Common LT Panel (Cable- Mtr 0 185 185 185.00 DC/540
1)
R.A.-07
Belveder
CHL/830/16
(ATTACH IN
3C)/945 RMT -
CLAIM 385RMT
Block-D Mtr 385 385.00 IN 3D & 560RMT
IN 3C

Total Qty 570.00


BOQ Quantity 600.00
Previously Certified Qty 570.00
This Bill Qty. -
Amendment Qty.

129 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Electrical works for External Supplying & laying of following 1100 volt grade XLPE insulated PVC
inner sheathed and HR PVC outer sheathed aluminium conductor armoured cables as per
specification in existing trenches, cable trays, ducts, clamped to wall with suitable clamps including,
3.8 saddles fixing bolts, connecting testing and commissioning,with necessory cable joints . same as
above 4 core 25 sqmm
(installation)

R.A.-05

Start End
Belveder Block-B Reading Readding Difference

Drum Number-2X-21088
Block-A CSS to Block-B
Common LT Panel (Cable- Mtr 0 185 185 185.00 JMR/588
1)
R.A.-07
Belveder Block-D
Block A AMF to common JMR/5000
area panel 3D(Drum Mtr 385 0 385 385.00
No:- 2x-617)
Total Qty 570.00
BOQ Quantity 600.00
Previously Certified Qty 570.00
This Bill Qty. -
Amendment Qty.
Cable end termination of the following
XLPE insulated HR PVC
outer-sheathed aluminium/copper conductor armoured cables of 1100 volt grade-including supplying
3.11
and fixing of bimettalic crimping lugs,
double-compression glands with earthing. 3.1/2 core 240 sq. mm.Aluminium Cable (supply)

130 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
R.A.-06
Belveder Block-B

CSS to Block-B SFP Panel (2 Nos


3 3.00 JMR/4936
nos of Runs) - 4936

R.A.-07
Belveder
Block-D SFP Panel to Meter JMR/1011
Nos 2 2.00
Panel-1
Block-D SFP Panel to Meter JMR/1011
Nos 2 2.00
Panel-2
CSS to Block-D Side SFP JMR/1010
Nos 2 2.00
Panel
JMR/1010=4NOS
CSS to Block-B Side SFP Nos 3 3.00 ., PAID 1 NOS.
Panel EARLIER
SFP to Meter Panel-1 Nos 2.00 2.00 JMR/1010
SFP to Meter Panel-2 Nos 2.00 2.00 JMR/1010

Total Qty 16.00


BOQ Quantity 16.00
Previously Certified Qty 16.00
This Bill Qty. -
Amendment Qty.

131 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Cable end termination of the following
XLPE insulated HR PVC
outer-sheathed aluminium/copper conductor armoured cables of 1100 volt grade-including supplying
3.12 and fixing of bimettalic crimping lugs,
double-compression glands with earthing. 3.1/2 core 240 sq. mm.Aluminium Cable (Installation)

R.A.-06
Belveder Block-B
CSS to Block-B SFP Panel (2 Nos
3 3.00 JMR/4936
nos of Runs)
R.A.-07
Belveder
Block-D SFP Panel to Meter JMR/1011
Nos 2 2.00
Panel-1
Block-D SFP Panel to Meter JMR/1011
Nos 2 2.00
Panel-2
CSS to Block-D Side SFP JMR/1010
Nos 2 2.00
Panel
JMR/1010=4NOS
CSS to Block-B Side SFP Nos 3 3.00 ., PAID 1 NOS.
Panel EARLIER
SFP to Meter Panel-1 Nos 2.00 2.00 JMR/1010
SFP to Meter Panel-2 Nos 2.00 2.00 JMR/1010

Total Qty 16.00


BOQ Quantity 16.00
Previously Certified Qty 16.00
This Bill Qty. -

132 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Amendment Qty.
3.13 TERMINATION same as above 3.1/2 core 185 sq. mm. Aluminium Cable (supply)
R.A.-07
Belveder
JMR/1010-
CABLE SUPPLY
Block-B SFP Panel to Meter Nos 2 2.00 &
Panel-1 INSTALLATION
PAID IN 3C

JMR/1010-
CABLE SUPPLY
Block-B SFP Panel to Meter Nos 2 2.00 &
Panel-2 INSTALLATION
PAID IN 3C

Total Qty 4.00


BOQ Quantity 16.00
Previously Certified Qty 4.00
This Bill Qty. -
Amendment Qty.
3.14 same as above 3.1/2 core 185 sq. mm. Aluminium Cable (installation)
R.A.-07
Belveder
JMR/1010-
CABLE SUPPLY
Block-B SFP Panel to Meter Nos 2 2.00 &
Panel-1 INSTALLATION
PAID IN 3C

133 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
JMR/1010-
CABLE SUPPLY
Block-B SFP Panel to Meter Nos 2 2.00 &
Panel-2 INSTALLATION
PAID IN 3C

Total Qty 4.00


BOQ Quantity 16.00
Previously Certified Qty 4.00
This Bill Qty. -
Amendment Qty.
3.17 TERMINATION same as above 4 core 25 sq. mm Aluminium Cable (supply)
R.A.-07
Belveder
Block-B SFP Panel to JMR/1011
Nos 2 2.00
Common LT Panel
Block-D SFP Panel to JMR/1011
Nos 2 2.00
Common LT Panel
AMF Panel to Block-B JMR/1011
Nos 1 1.00
Common LT Panel
AMF Panel to Block-D JMR/1011
Nos 1 1.00
Common LT Panel
AMF Panel (Block-A) to JMR/1041
Block-B Common LT Nos 1 1.00
Panel
AMF Panel (Block-A) to JMR/1041
Block-D Common LT Nos 1 1.00
Panel

134 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Total Qty 8.00
BOQ Quantity 10.00
Previously Certified Qty 8.00
This Bill Qty. -
Amendment Qty.
3.18 same as above 4 core 25 sq. mm Aluminium Cable (installation)
R.A.-07
Belveder
Block-B SFP Panel to JMR/1011
Nos 2 2.00
Common LT Panel
Block-D SFP Panel to JMR/1011
Nos 2 2.00
Common LT Panel
AMF Panel to Block-B JMR/1011
Nos 1 1.00
Common LT Panel
AMF Panel to Block-D JMR/1011
Nos 1 1.00
Common LT Panel
AMF Panel (Block-A) to JMR/1041
Block-B Common LT Nos 1 1.00
Panel
AMF Panel (Block-A) to JMR/1041
Block-D Common LT Nos 1 1.00
Panel

Total Qty 8.00


BOQ Quantity 10.00
Previously Certified Qty 8.00
This Bill Qty. -
Amendment Qty.

135 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Providing, Laying, jointing and testing socketed and spigotted RCC pipes-(NP2 class) for conveying
Pipelines across roads conforming to IS:458-collars
jointed with stiff mixture of cement mortar in the proporation-of 1:2 (1 cement : 2 find sand) laid to
correct levels below ground in-trenches upto
required depth including excavation in all kind of soil-(hard / soft), dewatering, refilling, watering,
ramming and
3.21 removing the-surplus excavated material including curing with all necessary lead and-lifts as
required including testing of joints etc. complete of following-sizes. Cost shall be inclusive of
providing protection to pipe all-round/ haunches as per specification.-same as above 150
mm dia ID (supply)

R.A.-03
As per attached JMR DrawinRmt 1 42.2 42.2 JMR-1
R.A.-04
As per attached JMR Rmt 1 35.8 35.8 JMR-1

Total Qty 78.00


BOQ Quantity 50.00
Previously Certified Qty 50.00
This Bill Qty. -
Amendment Qty. 28.00

136 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Providing, Laying, jointing and testing socketed and spigotted RCC pipes-(NP2 class) for conveying
Pipelines across roads conforming to IS:458-collars
jointed with stiff mixture of cement mortar in the proporation-of 1:2 (1 cement : 2 find sand) laid to
correct levels below ground in-trenches upto
required depth including excavation in all kind of soil-(hard / soft), dewatering, refilling, watering,
ramming and
3.22 removing the-surplus excavated material including curing with all necessary lead and-lifts as
required including testing of joints etc. complete of following-sizes. Cost shall be inclusive of
providing protection to pipe all-round/ haunches as per specification.-same as above 150
mm dia ID (installation)

R.A.-03
As per attached JMR DrawinRmt 1 42.2 42.2 JMR-1
R.A.-04
As per attached JMR Rmt 1 35.8 35.8 JMR-1
Total Qty 78.00
BOQ Quantity 50.00
Previously Certified Qty 50.00
This Bill Qty. -
Amendment Qty. 28.00
SECTION FEEDER PILLAR TYPE-B (IP-55) TRANSFORMER--Incoming -
630 amps TP Fuse base with 630A HRC fuse with
following-accessories:-,,-i,,Phase indicating lamps.-ii,,18W CFL lamp with holder with switch-iii,,6A switch
socket for maintenance-,,-Bus Bars - 630 amps FP aluminium bus bars with coloured heat shrinkable-
3.39 insulated
sleeve.-,,-Outgoing - 4Nos 200 amps TP Fuse base with 200 amps HRC fuse-100
amps TP Fuse 1Nos base with 100 amps.-All Fuse's shall be of 25 KA breaking
capacity.-SFP-TYPE-B-supply

R.A.-06

137 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Belveder Block-B
SFP-1 (Block-B, D) Nos 2 2.00 DCN/545

Total Qty 2.00


BOQ Quantity 2.00
Previously Certified Qty 2.00
This Bill Qty. -
Amendment Qty.
SECTION FEEDER PILLAR TYPE-B (IP-55) TRANSFORMER--Incoming -
630 amps TP Fuse base with 630A HRC fuse with
following-accessories:-,,-i,,Phase indicating lamps.-ii,,18W CFL lamp with holder with switch-iii,,6A
switch socket for maintenance-,,-Bus Bars - 630 amps FP aluminium bus bars with coloured heat
shrinkable-insulated
3.40 sleeve.-,,-Outgoing - 4Nos 200 amps TP Fuse base with 200 amps HRC fuse-100
amps TP Fuse 1Nos base with 100 amps.-All Fuse's shall be of 25 KA breaking
capacity.-SFP-TYPE-B-installation

R.A.-06
Belveder Block-B
SFP-1 (Block-B, ) Nos 1 1.00 JMR/4948

R.A.-07
Belveder
Block-D Nos 1 1.00 1.00 JMR/1024

Total Qty 2.00


BOQ Quantity 2.00
Previously Certified Qty 2.00
This Bill Qty. -

138 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Amendment Qty.
8.3 Supply and fixing in position 1000 mm wide rubber matting of 11 KV grade-as per electricity rules.-
supply
R.A.-07
Belveder Mtr 1 4 4.00 DC With 3C

Total Qty 4.00


BOQ Quantity 15.00
Previously Certified Qty -
This Bill Qty. 4.00
Amendment Qty.
8.5 Supply of fire buckets 5 nos. in each set duly filled with fine sand and-fixed on an angle iron frame
as per requirement of local authorities.- Fire buckets shall be painted red from outside and white
R.A.-07
Belveder Mtr 1 1 1.00 DC With 3C

Total Qty 1.00


BOQ Quantity 1.00
Previously Certified Qty -
This Bill Qty. 1.00
Amendment Qty.
11 Bracket (750 MM in 32mm Pipe) with 100x 100 mm insert plate & anchor fastner with pU paint for
BRP 020, 24 W, Green line Smart LED.
R.A.-07
Belveder Nos 1 30 30.00 T-357/16-17

Total Qty 30.00


BOQ Quantity 31.00
Previously Certified Qty -
This Bill Qty. 30.00
Amendment Qty.
11.2 same as above - installation

139 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
R.A.-07
Belveder Block-B
LM-1 Nos 1 1 1.00 JMR/1099
LM-2 Nos 1 1 1.00 JMR/1099
LM-3 Nos 1 1 1.00 JMR/1099
LM-4 Nos 1 1 1.00 JMR/1099
LM-5 Nos 1 1 1.00 JMR/1099
LM-6 Nos 1 1 1.00 JMR/1099
LM-7 Nos 1 1 1.00 JMR/1099
LM-8 Nos 1 1 1.00 JMR/1099
LM-9 Nos 1 1 1.00 JMR/1099
LM-10 Nos 1 1 1.00 JMR/1099
LM-11 Nos 1 1 1.00 JMR/1099
LM-12 Nos 1 1 1.00 JMR/1099
LM-13 Nos 1 1 1.00 JMR/1099
LM-14 Nos 1 1 1.00 JMR/1099
LM-15 Nos 1 1 1.00 JMR/1099
Belveder Block-D
LM-1 Nos 1 1 1.00 JMR/1107
LM-2 Nos 1 1 1.00 JMR/1107
LM-3 Nos 1 1 1.00 JMR/1107
LM-4 Nos 1 1 1.00 JMR/1107
LM-5 Nos 1 1 1.00 JMR/1107
LM-6 Nos 1 1 1.00 JMR/1107
LM-7 Nos 1 1 1.00 JMR/1107
LM-8 Nos 1 1 1.00 JMR/1107
LM-9 Nos 1 1 1.00 JMR/1107
LM-10 Nos 1 1 1.00 JMR/1107
LM-11 Nos 1 1 1.00 JMR/1107

140 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
LM-12 Nos 1 1 1.00 JMR/1107
LM-13 Nos 1 1 1.00 JMR/1107
LM-14 Nos 1 1 1.00 JMR/1107
LM-15 Nos 1 1 1.00 JMR/1107

Total Qty 30.00


BOQ Quantity 31.00
Previously Certified Qty -
This Bill Qty. 30.00
Amendment Qty.
3.76 Syntex junction box with 6 Amps MCB & connectors Supply & Installation
R.A.-07
Belveder-Block-D (In Shaft
LM Light)
LM-16 Nos 1 1 1.00 JMR/4974
LM-17 Nos 1 1 1.00 JMR/4974
LM-18 Nos 1 1 1.00 JMR/4974
LM-19 Nos 1 1 1.00 JMR/4974
LM-20 Nos 1 1 1.00 JMR/4974
LM-21 Nos 1 1 1.00 JMR/4974
LM-22 Nos 1 1 1.00 JMR/4974
LM-23 Nos 1 1 1.00 JMR/4974
LM-24 Nos 1 1 1.00 JMR/4974
LM-25 Nos 1 1 1.00 JMR/4974
LM-26 Nos 1 1 1.00 JMR/4974
LM-27 Nos 1 1 1.00 JMR/4974
LM-28 Nos 1 1 1.00 JMR/4974
LM-29 Nos 1 1 1.00 JMR/4974
LM-30 Nos 1 1 1.00 JMR/4974

141 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Belveder-Block-B (In Shaft
LM Light)
LM-1 Nos 1 1 1.00 JMR/4973
LM-2 Nos 1 1 1.00 JMR/4973
LM-3 Nos 1 1 1.00 JMR/4973
LM-4 Nos 1 1 1.00 JMR/4973
LM-5 Nos 1 1 1.00 JMR/4973
LM-6 Nos 1 1 1.00 JMR/4973
LM-7 Nos 1 1 1.00 JMR/4973
LM-8 Nos 1 1 1.00 JMR/4973
LM-9 Nos 1 1 1.00 JMR/4973
LM-10 Nos 1 1 1.00 JMR/4973
LM-11 Nos 1 1 1.00 JMR/4973
LM-12 Nos 1 1 1.00 JMR/4973
LM-13 Nos 1 1 1.00 JMR/4973
LM-14 Nos 1 1 1.00 JMR/4973
LM-15 Nos 1 1 1.00 JMR/4973

Total Qty 30.00


BOQ Quantity 31.00
Previously Certified Qty 30.00
This Bill Qty. -
Amendment Qty.
Extra Supply and installation 3 Mtr. Pole including PU paint, syntex box, required MCB and connector, all
Item-5 accessories etc. complete
R.A.-05

DC/T-1096/15-16
As per attached Challan Nos. 1 12 12
R.A.-06

142 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks

DC/T-1096/15-16
As per attached Challan Nos. 1 23 23
R.A.-07
Belveder
Nos.
Block-D 1 2.00 2.00 DC/T-1096/15-16

Total Qty 37.00


BOQ Quantity 41.00
Previously Certified Qty 37.00
This Bill Qty. -
Amendment Qty.
3.79 Post /Round LED for walkway, 63 W, BGP150 LED Installation
R.A.-06
As per attached JMR - JMR/4922,4904
4929 Nos. 1 35 35
R.A.-07
Belveder
Block-D Nos 1 2.00 2 JMR/1042

Total Qty 37.00


BOQ Quantity 41.00
Previously Certified Qty 37.00
This Bill Qty. -
Amendment Qty.
PVC Pipe 50 mm dia Supply & Installation
3.85

R.A.-03

143 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Belveder-Block-D
for LM-24 Point Rmt 1 10.00 10 JMR/509
for LM-25 Point Rmt 1 3.80 3.8 JMR/509
for LM-26 Point Rmt 1 10.00 10 JMR/509
for LM-27 Point Rmt 1 10.00 10 JMR/509
for LM-28 Point Rmt 1 3.50 3.5 JMR/509
Belveder-Block-B 0
for LM-14 Point Rmt 1 10.00 10 JMR/508
for LM-1 Point Rmt 1 10.00 10 JMR/508
for LM-2 Point Rmt 1 2.80 2.8 JMR/508
for LM-3 Point Rmt 1 2.60 2.6 JMR/508
for LM-4 Point Rmt 1 4.00 4 JMR/508
for LM-5 Point Rmt 1 10.00 10 JMR/508
for LM-6 Point Rmt 1 10.00 10 JMR/508
LM-11 Rmt 1 3.010 3.01 JMR/526
LM-9 Rmt 1 1.100 1.1 JMR/526
LM-8 Rmt 1 6.000 6 JMR/526
LM-7 Rmt 1 2.150 2.15 JMR/526
LM-6 Rmt 1 3.480 3.48 JMR/526
RA-04
Belveder Block-D
LM-18 Rmt 1 3.200 3.2 JMR/542
LM-17 Rmt 1 1.000 1 JMR/542
LM-16 Rmt 1 0.800 0.8 JMR/542
LM-30 Rmt 1 0.500 0.5 JMR/542
LM-29 Rmt 1 0.600 0.6 JMR/542
Belveder Block-B
LM-15 Rmt 1 0.900 0.9 JMR/542
LM-12 Rmt 1 1.100 1.1 JMR/542

144 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
LM-30 Rmt 1 3.200 3.2 JMR/542
Belveder Block-D
LM-23 Rmt 1 4.500 4.5 JMR/547
LM-22 Rmt 1 1.700 1.7 JMR/547
LM-21 Rmt 1 0.900 0.9 JMR/547
LM-20 Rmt 1 3.400 3.4 JMR/547
LM-18 Rmt 1 0.200 0.2 JMR/547
LM-17 Rmt 1 0.100 0.1 JMR/547
LM-16 Rmt 1 1.200 1.2 JMR/547
Belveder Block-B
LM-9 Rmt 1 3.100 3.1 JMR/547
LM-12 Rmt 1 0.700 0.7 JMR/547
RA-07
Belveder-Block-B (In
Shaft LM Light)
LM-1 Mtr 1 3.400 3.4 JMR/4970
LM-2 Mtr 1 0.000 0 JMR/4970
LM-3 Mtr 1 0.000 0 JMR/4970
LM-4 Mtr 1 0.000 0 JMR/4970
LM-5 Mtr 1 0.340 0.34 JMR/4970
LM-6 Mtr 1 0.000 0 JMR/4970
LM-7 Mtr 1 0.200 0.2 JMR/4970
LM-8 Mtr 1 0.000 0 JMR/4970
LM-9 Mtr 1 3.500 3.5 JMR/4970
LM-10 Mtr 1 0.600 0.6 JMR/4970
LM-11 Mtr 1 0.180 0.18 JMR/4970
LM-12 Mtr 1 1.200 1.2 JMR/4970
LM-13 Mtr 1 4.000 4 JMR/4970
LM-14 Mtr 1 0.000 0 JMR/4970

145 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
LM-15 Mtr 1 0.000 0 JMR/4970
Belveder-Block-D (In
Shaft LM Light)
LM-16 Mtr 1 1.650 1.65 JMR/4962
LM-17 Mtr 1 0.800 0.8 JMR/4962
LM-18 Mtr 1 2.700 2.7 JMR/4962
LM-19 Mtr 1 0.300 0.3 JMR/4962
LM-20 Mtr 1 3.100 3.1 JMR/4962
LM-21 Mtr 1 0.200 0.2 JMR/4962
LM-22 Mtr 1 0.000 0 JMR/4962
LM-23 Mtr 1 3.600 3.6 JMR/4962
LM-24 Mtr 1 0.100 0.1 JMR/4962
LM-25 Mtr 1 0.000 0 JMR/4962
LM-26 Mtr 1 0.800 0.8 JMR/4962
LM-27 Mtr 1 0.200 0.2 JMR/4962
LM-28 Mtr 1 0.400 0.4 JMR/4962
LM-29 Mtr 1 1.950 1.95 JMR/4962
LM-30 Mtr 1 0.500 0.5 JMR/4962

Total Qty 159.26


BOQ Quantity 120.00
Previously Certified Qty 120.00
This Bill Qty. -
Amendment Qty. 39.26
3.86 25mm PVC pipe Supply & Installation
R.A.-07
Belveder-Block-D (In
Shaft LM Light)
LM-16 Mtr 1 2.30 2.3 JMR/4963

146 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
LM-17 Mtr 1 4.00 4 JMR/4963
LM-18 Mtr 1 2.40 2.4 JMR/4963
LM-19 Mtr 1 5.60 5.6 JMR/4963
LM-20 Mtr 1 2.20 2.2 JMR/4963
LM-21 Mtr 1 2.80 2.8 JMR/4963
LM-22 Mtr 1 2.78 2.78 JMR/4963
LM-23 Mtr 1 2.20 2.2 JMR/4963
LM-24 Mtr 1 2.80 2.8 JMR/4963
LM-25 Mtr 1 2.28 2.28 JMR/4963
LM-26 Mtr 1 3.00 3 JMR/4963
LM-27 Mtr 1 3.40 3.4 JMR/4963
LM-28 Mtr 1 2.58 2.58 JMR/4963
LM-29 Mtr 1 4.30 4.3 JMR/4963
LM-30 Mtr 1 2.18 2.18 JMR/4963
Belveder-Block-B (In
Shaft LM Light)
LM-1 Mtr 1 2.30 2.3 JMR/4971
LM-2 Mtr 1 4.10 4.1 JMR/4971
LM-3 Mtr 1 4.60 4.6 JMR/4971
LM-4 Mtr 1 2.30 2.3 JMR/4971
LM-5 Mtr 1 2.70 2.7 JMR/4971
LM-6 Mtr 1 2.30 2.3 JMR/4971
LM-7 Mtr 1 2.35 2.35 JMR/4971
LM-8 Mtr 1 2.55 2.55 JMR/4971
LM-9 Mtr 1 2.34 2.34 JMR/4971
LM-10 Mtr 1 2.45 2.45 JMR/4971
LM-11 Mtr 1 2.32 2.32 JMR/4971
LM-12 Mtr 1 3.00 3 JMR/4971
LM-13 Mtr 1 2.38 2.38 JMR/4971

147 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
LM-14 Mtr 1 3.10 3.1 JMR/4971
LM-15 Mtr 1 3.00 3 JMR/4971

Total Qty 86.61


BOQ Quantity 120.00
Previously Certified Qty 86.61
This Bill Qty. -
Amendment Qty.
3.88 Providing and laying of GI "C" Class pipe of 65 mm dia and 3 meter length earth rod in 150 mm dia.
in an augured hole in ground , surrounded by ground coal & salt. Inspection chamber shall be of 400
R.A.-07
Belveder
For CSS EP-1 (Neutral) Nos JMR/1043
1.00
1
For CSS EP-2 (Body) Nos 1.00 1 JMR/1043
For CSS EP-3 (Body) Nos 1.00 1 JMR/1043
For CSS LT Panel EP-5 Nos JMR/1043
(Body) 1.00
1
For CSS HT Panel EP-6 Nos JMR/1043
1.00
(Body) 1

Total Qty 5.00


BOQ Quantity 8.00
Previously Certified Qty 5.00
This Bill Qty. -
Amendment Qty.
3.89 same as above - installation
R.A.-07
Belveder

148 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
For CSS EP-1 (Neutral) Nos JMR/1043
1.00
1
For CSS EP-2 (Body) Nos 1.00 1 JMR/1043
For CSS EP-3 (Body) Nos 1.00 1 JMR/1043
For CSS LT Panel EP-5 Nos JMR/1043
(Body) 1.00
1
For CSS HT Panel EP-6 Nos JMR/1043
1.00
(Body) 1

Total Qty 5.00


BOQ Quantity 8.00
Previously Certified Qty 5.00
This Bill Qty. -
Amendment Qty.
3.96 CO2 portable Fire Extinguisher (4 litre capacity)Supply
R.A.-07
Belveder Nos 1.00 1 DC With 3C

Total Qty 1.00


BOQ Quantity 1.00
Previously Certified Qty -
This Bill Qty. 1.00
Amendment Qty.
Supply and installation of Double wall corrugated high density polyethylene pipe with necessary all
3.112 accessories with excavation and backfilling. 160 mm dia OD

R.A.-03
As per attached JMR DrawinRmt 1 146.4 146.40 JMR-2
Total Qty 146.40

149 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
BOQ Quantity 125.00
Previously Certified Qty 125.00
This Bill Qty. -
Amendment Qty. 21.40
Supply and installation of Double wall corrugated high density polyethylene pipe with necessary all
3.112 accessories with excavation and backfilling. 200 mm dia OD

R.A.-03
As per attached JMR DrawinRmt 1 150 150.00 JMR-2
Total Qty 150.00
BOQ Quantity 200.00
Previously Certified Qty 150.00
This Bill Qty. -
Amendment Qty.
Construction of Brick Masonary chamber of 900x900 upto 1500 mm depth incluidng excavation,
3.114 backfilling, PCC, 230mm thk Masonary, Inside & outside 12mm thk plaster, SFRC cover etc.

R.A.-06
As per attached JMR DrawinNos. 1 2 2.00 JMR-1
Total Qty 2.00
BOQ Quantity 4.00
Previously Certified Qty 2.00
This Bill Qty. -
Amendment Qty.

150 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks

Supplying & laying of following 1100 volt grade XLPE insulated HR PVC outer sheathed aluminium/copper
conductor armoured/unarmored cables laid in ground excluding the cost of digging upto required depth
( minimum 750 mm) , 150 mm sand all around the cable, brick protection and back filling,with all necessory
piping of 50mm,25mm when require & including connecting, testing and commissioning. 4 core 1.5 sq.mm
control Cu cable supply
Extra
Item-1
R.A.-03

Belveder-Block-B Start End


Reading Readding Difference
LM-1 to LM-2 Rmt 81 64 17 17 JMR/501
LM-2 to LM-3 Rmt 64 40 24 24 JMR/501
LM-3 to LM-4 Rmt 40 24 16 16 JMR/501
LM-4 to LM-5 Rmt 24 1 23 23 JMR/501
LM-1 to LM-14 Rmt 100 81 19 19 JMR/501
LM-14 to LM-13 Rmt 117 100 17 17 JMR/501
LM-13 to LM-12 Rmt 136 117 19 19 JMR/501
LM-3 to External L.T JMR/501
711 554
Panel Rmt 157 157
LM-7 to LM-8 Mtr 1168 1153 15 15 JMR/526
LM-8 to LM-9 Mtr 1153 1136 17 17 JMR/526
LM-9 to LM-10 Mtr 1136 1120 16 16 JMR/526
LM-10 to LM-11 Mtr 1120 1105 15 15 JMR/526
LM-11 to LM-15 Mtr 1083 1061 22 22 JMR/526
LM-15 to LM-12 Mtr 737 712 25 25 JMR/526
LM-12 to LM-13 Mtr 136 118 18 18 JMR/526
LM-6 to LM-14 Mtr 1105 1083 22 22 JMR/526
PL-1 to PL-2 Mtr 1238 1224 14 14 JMR/518

151 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
PL-1 to PL-3 Mtr 1224 1210 14 14 JMR/518
PL-1 to PL-4 Mtr 1210 1196 14 14 JMR/518
PL-1 to PL-5 Mtr 1196 1182 14 14 JMR/518
PL-1 to PL-6 Mtr 1182 1168 14 14 JMR/518
Belveder-Block-D 0 0
LM-23 to LM-24 Rmt 160 137 23 23 JMR/503
LM-24 to LM-25 Rmt 179 160 19 19 JMR/503
LM-25 to LM-26 Rmt 196 179 17 17 JMR/503
LM-26 to LM-27 Rmt 218 196 22 22 JMR/503
LM-27 to LM-28 Rmt 232 218 14 14 JMR/503
LM-28 to LM-29 Rmt 250 232 18 18 JMR/503
LM-26 to External L.T JMR/503
553 312
Panel Rmt 241 241
LM-5 to LM-6 Rmt 288 277 11 11 JMR/514
LM-6 to LM-7 Rmt 310 288 22 22 JMR/514
LM-29 to LM-30 Mtr 831 811 20 20 JMR/535
LM-18 to LM-19 Mtr 811 801 10 10 JMR/535
LM-19 to LM-20 Mtr 801 785 16 16 JMR/535
LM-20 to LM-21 Mtr 785 769 16 16 JMR/535
LM-21 to LM-22 Mtr 769 754 15 15 JMR/535
LM-22 to LM-23 Mtr 754 737 17 17 JMR/535
LM-8 to LM-3 Mtr 847 831 16 16 JMR/535
LM-17 to LM-18 Mtr 870 847 23 23 JMR/535
R.A.-04
Lighting Pole-6 to
Mtr 877 870 JMR/541
Lighting Pole-7 7 7
Lighting Pole-4 to
Mtr 900 877 JMR/541
Lighting Pole-7 23 23

152 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
Lighting Pole-6 to
Mtr 1000 970 JMR/541
Lighting Pole-23 30 30
Belveder
Lighting Pole-39 to
Mtr 906 900 JMR/543
Lighting Pole-40 6 6
Lighting Pole-40 to
Mtr 926 906 JMR/543
Lighting Pole-38 20 20
Lighting Pole-14 to
Mtr 943 926 JMR/543
Lighting Pole-36 17 17
Belveder
LM-30 to LM-16 Mtr 57 41 16 16 JMR/544
LM-16 to LM-17 Mtr 965 943 22 22 JMR/544
Belveder
Lighting Pole-35 to
Mtr 71 57 JMR/546
Lighting Pole-36 14 14
Lighting Pole-36 to
Mtr 85 71 JMR/546
Lighting Pole-37 14 14
Lighting Pole-37 to
Mtr 99 85 JMR/546
Lighting Pole-38 14 14
Belveder-Landscap
Lighting Pole-35 to
Mtr 113 99 JMR/549
Lighting Pole-41 14 14
Lighting Pole-41 to
Mtr 150 113 JMR/549
Lighting Pole-34 37 37
RA-05
Belveder-Block
LP-19 to LP-20 Mtr 330 319 11 11 JMR/567
LP-12 to LP-10 Mtr 300 280 20 20 JMR/567
LP-10 to LP-09 Mtr 319 300 19 19 JMR/567
LP-22 to LP-23 Mtr 341 330 11 11 JMR/567

153 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
LP-20 to LP-22 Mtr 700 691 9 9 JMR/567
LP-21 to LP-24 Mtr 691 675 16 16 JMR/567
Belveder-Block
LP-21 to LP-19 Mtr 264 256 8 8 JMR/556
LP-17 to LP-16 Mtr 229 221 8 8 JMR/556
LP-16 to LP-14 Mtr 256 241 15 15 JMR/556
LP-14 to LP-12 Mtr 280 264 16 16 JMR/556
LP-13 to LP-12 Mtr 241 229 12 12 JMR/556
Belveder-Block
LP-18 to LP-31 Mtr 165 150 15 15 JMR/555
LP-31 to LP-15 Mtr 176 165 11 11 JMR/555
LP-32 to LP-15 Mtr 191 176 15 15 JMR/555
LP-32 to LP-13 Mtr 201 191 10 10 JMR/555
LP-13 to LP-33 Mtr 214 201 13 13 JMR/555
LP-33 to LP-34 Mtr 221 214 7 7 JMR/555
R.A.-06
LP-24 to LP-25 Mtr 655 670 15 15 JMR-599
LP-25 to LP-26 Mtr 645 655 10 10 JMR-599
LP-1 to LP-1A Mtr 580 597 17 17 JMR-599
LP-35 to LP-35A Mtr 597 612 15 15 JMR-599
R.A.-07
LP-28 to LP-26 Mtr 498 528 30 30 JMR/1046
LP-28 to LP-30 Mtr 468 498 30 30 JMR/1046

Total Qty 1599.00


BOQ Quantity 2,200.00
Previously Certified Qty 1,599.00

154 of 211
Measurement Sheet
Belveder Area Electrical Work
Sr No. Particular Unit No. L B H Qty. Remarks
This Bill Qty. -
Amendment Qty.

155 of 211
Quantity Amount
Up To Up To Up To Previous
Previous This Bill This Bill Up To Date
Bill Date Bill
PHASE 3 D - PHE WORKS
S.NO. DESCRIPTION Unit Quantity Rate Amount
1 Plumbing Works for Phase-3A

4.1 Providing, laying, jointing and testing in position the following heavy
class GI pipes for under ground piping conforming to IS:1239 including
all necessary fittings (conforming to IS : 1879) such as elbow, coupler
& tee etc. Cost shall be inclusive of excavation, dewatering, backfilling,
ramming surrounding the pipe alround with minimum 150 mm
thick compacted silver sand and providing thrust block at distance 2 M
C/C. (Pipe shall be provided with anti corrosive protective treatment RM 235 681.10 160,058.50 146.4 0.00 146.40 146.40 0.00 0.00 99,713.04 - 99,713.04
Pypkote / Coatek confirming to AWWA C 203 / IS 10221 standard
complete as per specification). All work complete as per specification
and satisfaction of the Project Manager. 40 mm dia

0 0.00 0.00 0.00 - - -


4.2 50 mm dia RM 235 778.40 182,924.00 126.34 0.00 126.34 126.34 0.00 0.00 98,343.06 - 98,343.06
0 0.00 0.00 0.00 - - -
4.3 65 mm dia RM 30 973.00 29,190.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.4 80 mm dia RM 10 1167.60 11,676.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.5 100 mm dia RM 10 1508.15 15,081.50 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.6 150 mm dia RM 0 2140.60 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.7 125 mm dia RM 0 1751.40 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.8 250 mm dia RM 0 4378.50 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.9 Providing, Laying, jointing and testing socketed and spigotted RCC pipes
(NP2 class) for conveying Pipelines across roads conforming to IS:458
collars jointed with stiff mixture of cement mortar in the proportion of 1:2
(1 cement : 2 find sand) laid to correct levels below ground in trenches
upto required depth including excavation in all kind of soil (hard / soft),
dewatering, refilling, watering, ramming and removing the surplus
excavated material including curing with all necessary lead and lifts as RM 0 1167.60 - 0 0.00 0.00 0.00 - - -
required including testing of joints etc. complete of following sizes. Cost
shall be inclusive of providing protection to pipe all round / haunches as
per specification. 300 mm dia

0 0.00 0 0.00 0.00 0.00 - - -


4.10 450 mm dia RM 20 1751.40 35,028.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.11 600 mm dia RM 0 2140.60 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.12 750 mm dia RM 0 2919.00 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.13 900 mm dia RM 0 3892.00 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.14 1000 mm dia RM 0 4670.40 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.15 1200 mm dia RM 0 5059.60 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.16 Providing & fixing full way lever operated forged brass ball valve of
brass body with forged brass hard chrome plated steel ball tested to a
pressure not less than 15 Kg / sqcm with threaded / flanged joints No. 0 1459.50 - 0 0.00 0.00 0.00 - - -
complete with nuts, bolts, gaskets, washers etc. 32 mm dia

0 0.00 0 0.00 0.00 0.00 - - -


4.17 40 mm dia No. 8 1946.00 15,568.00 7 0.00 7.00 7.00 0.00 0.00 13,622.00 - 13,622.00
0 0.00 0 0.00 0.00 0.00 - - -
4.18 50 mm dia No. 8 2919.00 23,352.00 3 0.00 3.00 3.00 0.00 0.00 8,757.00 - 8,757.00
0 0.00 0 0.00 0.00 0.00 - - -
4.19 Providing & fixing butterfly valve (Body : Grey Cast Iron, Shaft : SS,
Disc : SG Iron (Rilson coated), Liner : HT - EPDM) (upto 150mm dia
with hand lever operation & above with gear box operation). Tested to a
pressure not less than 15 Kg/Sq.cm. Including rubber gasket, flanges, No. 3 3892.00 11,676.00 0 0.00 0.00 0.00 - - -
nuts, bolts, washers & painting complete as required. 65 mm dia

0 0.00 0 0.00 0.00 0.00 - - -


4.20 80 mm dia No. 1 4865.00 4,865.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.21 100 mm dia No. 0 7005.60 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.22 150 mm dia No. 0 9243.50 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.23 200 mm dia No. 0 13427.40 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.24 Providing, fixing , testing and commissioning water meter with direct
reading dial in KL with all necessary fitting such as threaded pieces,
unions, pressure gauge, isolation valve, Non return valve, flange piece
for future removal, flanges / unions complete with all necessary testing
charges and obtaining test certificates from municipal authorities, on
following size pipe lines (1 no. Y strainer shall be provided at inlet and No. 0 7784.00 0 0.00 0.00 0.00 - - -
cost shall be inclusive for the same). The meter shall comply to ISO
4064 standard, feasible for class B or Class A installation. 25 mm dia
(Gun metal)

4.25 40 mm dia (Gun metal) No. 1 11676.00 11,676.00 0 0.00 0.00 0.00 - - -
4.26 50 mm dia (CI) No. 1 14595.00 14,595.00 0 1.00 1.00 1.00 0.00 0.00 - 14,595.00 14,595.00
4.27 65 mm dia (CI) No. 1 19460.00 19,460.00 0 0.00 0.00 0.00 - - -
4.28 80 mm dia (CI) No. 0 24325.00 - 0 0.00 0.00 0.00 - - -
4.29 100 mm dia (CI) No. 0 29190.00 - 0 0.00 0.00 0.00 - - -
4.30 200 mm dia (CI) No. 0 77840.00 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.31 Construction of Water meter chamber with 150 mm best quality bricks of
class 75 as per drawings of the following sizes in cement mortar 1 : 4 (1
cement : 4 find sand) necessary 100 mm thick PCC bed in 1 : 4 : 8.
Inside & outside plastering 12 mm thick with cement mortar 1 : 3 with a
coat of neat cement. Including the RCC top slab for fixing the M.S
grating including necessary excavation, dewatering, refilling, watering,
ramming, removing, the surplus excavated material and making good No. 2 24325.00 48,650.00 0 0.00 0.00 0.00 - - -
the same including curing with all necessary lead and lifts complete as
required. Cost shall be inclusive of providing heavy duty SFRC grating
with frame complete. Internal size of chamber 1200 x 600 - up to 1500
mm deep; heavy duty SF RC cover with frame

0 0.00 0 0.00 0.00 0.00 - - -


4.32 Providing & fixing Auto Air vent for cold water supply transfer lines,
suitable for pressure not less than 15 Kg/Sq.cm. 15 mm dia No. 1 4865.00 4,865.00 0 0.00 0.00 0.00 - - -
0 7297.50 0 0.00 0.00 0.00 - - -
4.33 20 mm dia No. 0 0.00 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.34 Construction of Valve chamber with 230 mm best quality bricks of class
75 as per drawings of the following sizes in cement mortar 1 : 4 (1
cement : 4 find sand) necessary 100 mm thick PCC bed in 1 : 4 : 8.
Inside & outside plastering 12 mm thick with cement mortar 1 : 3 with a
coat of neat cement. Including the RCC top slab for fixing the grating
including necessary excavation, dewatering, refilling, watering, ramming,
removing, the surplus excavated material and making good the same No. 6 19460.00 116,760.00 6 0.00 6.00 6.00 0.00 0.00 116,760.00 - 116,760.00
complete including curing with all necessary lead and lifts as required.
Cost shall be inclusive of providing heavy duty SFRC grating with frame
complete. Internal size 900 x 900 - up to 1500 mm deep; heavy duty
SFRC Cover with frame with frame 900 x 900 mm.

0 0.00 0 0.00 0.00 0.00 - - -


4.35 Internal size 600 x 600 - up to1200 mm deep; heavy duty SFRC Cover
with frame with frame 600 x 600 mm . No. 0 17514.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.36 Internal size 900 x 750- up to 1500 mm deep;heavy duty SFRC Cover
with frame with frame 900 x 750 mm. No. 0 17514.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
Drilling of Bore well of 150 mm dia , 275 m depth. Providing and
Lowering of 150 mm MS tube well casing pipe. Tube well accessories as
required. Filling of 1.6 to 4.8 mm dia Lalkuan Pea Gravel all around Tube
well. Development of Tube well complete. Supplying, installing , testing
4.37 and commissioning Bore well submersible pumps of 15 H.P and 240 m No. 1 973000.00 973,000.00 1.00 - 1.00 1.00 0.00 0.00 973,000.00 - 973,000.00
head including cabling 120 Rmt from Bore well pump to feeder panel,
local contols etc. complete.

0 0.00 0 0.00 0.00 0.00 - - -


Effecting connection from Existing Municipal Water Supply line including
necessary excavation & making good the same including cutting,
boring and tapping the Existing line by providing and installing ferrule /
Tee connections with necessary fittings as required and making good
the same. The rate for this item also includes complete services from
the contractor for liasoning works such as filing necessary applications,
submission of forms for approval to the municipal authorities,
depositing the fees / other amounts as required for getting the
4.38 LS 1 14595.00 14,595.00 0 0.00 0.00 0.00 - - -
premises / installations, inspected and approved and all other
formalities required till the water connection is obtained. All the
expenses incurred in this regard shall be borne by the Contractor
except for the official payments to be made for any security deposit
etc. which will be reimbursed on production of original voucher.

0 0.00 0 0.00 0.00 0.00 - - -


0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.39 Providing, fixing, jointing and testing in position the following UPVC pipes
confirming to IS:4985 of 6 Kg / Sq.cm for Sewerage system cut to
required length. Pipe to be laid below ground level in trenches upto
required depth including excavation in all kind of soil (hard rock),
dewatering, refilling, watering, ramming and removing the surplus
excavated material including curing with all necessary lead and lifts RM 0 681.10 0 0.00 0.00 0.00 - - -
complete as required and making good the same complete as required.
Cost shall be inclusive of providing protection to pipe all round /
haunches as per specification. 110 mm dia

0 0.00 0 0.00 0.00 0.00 - - -


4.40 160 mm dia RM 490 973.00 476,770.00 437.19 0.00 437.19 437.19 0.00 0.00 425,385.87 - 425,385.87
0 0.00 0 0.00 0.00 0.00 - - -
4.41 200 mm dia RM 320 1362.20 435,904.00 48 0.00 48.00 48.00 0.00 0.00 65,385.60 - 65,385.60
0 0.00 0 0.00 0.00 0.00 - - -
4.42 250 mm dia RM 110 2140.60 235,466.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.43 Providing, Laying, jointing and testing socketed and spigotted RCC pipes
(NP2 class) for Sewer and Storm water conforming to IS:458 collars
jointed with stiff mixture of cement mortar in the proportion of 1:2 (1
cement : 2 find sand) laid to correct levels below ground in trenches upto
required depth including excavation in all kind of soil (hard / soft),
dewatering, refilling, watering, ramming and removing the surplus
excavated material including curing with all necessary lead and lifts as RM 140 875.70 122,598.00 0 0.00 0.00 0.00 - - -
required including testing of joints etc. complete of following sizes. Cost
shall be inclusive of providing protection to pipe all round / haunches as
per specification. 150 mm dia

0 0.00 0 0.00 0.00 0.00 - - -


4.44 200 mm dia RM 150 973.00 145,950.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.45 250 mm dia RM 100 1070.30 107,030.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.46 300 mm dia RM 50 1167.60 58,380.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.47 Construction of Storm / sewage Water road gully chamber of the
following sizes in brick work with bricks of class 75 in cement mortar 1 :
5 (1 cement : 5 find sand) necessary foundation concrete (1 : 4 : 8).
Inside & outside plastering 12 mm thick with cement mortar 1 : 3 with a
floating a coat of neat cement. Including the RCC top slab for fixing the
grating including necessary excavation, dewatering, refilling, watering,
ramming, removing, the surplus excavated material and making good No. 14 8757.00 122,598.00 14 0.00 14.00 16.00 2.00 17514.00 122,598.00 - 122,598.00
the same complete as required. Cost shall be inclusive of providing,
Internal size 600 x 600 - upto 1200 mm deep; heavy duty SFRC Grating
with frame 600 x 600 mm.

0 0.00 0 0.00 0.00 0.00 - - -


4.48 Internal size 600 x 600 - upto 1700 mm deep; heavy duty SFRC Grating
with frame 600 x 600 mm. No. 18 11676.00 210,168.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.49 Internal size 600 mm dia - upto 1900 mm deep; heavy duty SFRC
Grating with frame 600 mm dia. No. 0 15568.00 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.50 Internal size 900 x 600 mm dia - upto 1500 mm deep; heavy duty SFRC
Grating with frame dia. No. 31 14595.00 452,445.00 31 0.00 31.00 31.00 0.00 0.00 452,445.00 - 452,445.00
0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.51 Constructing brick masonry circular manhole 1200 mm internal dia at
bottom and 560 mm dia at top in brick work of class 75 in cement mortar
1:4 (1 cement: 4 coarse sand) inside cement plaster 12 mm thick with
cement mortar 1:3 (1 cement: 3 coarse sand) finished with a floating
coat of neat cement, foundation concrete 1:3:6 mix (1 cement :3 coarse
sand: 6 graded stone aggregate 40mm nominal size), benching and
making necessary channel in cement concrete 1:2:4 (1 cement:2 coarse
sand: 4 graded stone aggregate 20mm nominal size ) finished with a
floating coat of neat cement on inside face, proper water proofing to
ensure no ground water seepage in the manhole including necessary
excavation, dewatering, refilling, watering, ramming, removing the
surplus excavated material and making good the same complete No. 5 19460.00 97,300.00 0 0.00 0.00 0.00 - - -
including curing with all necessary lead and lifts as required all complete
as per standard design 1650 mm deep with 600 mm dia, SFRC Heavy
Duty cover and frame, fixed in cement concrete 1:2:4
(1 cement : 2 coarse sand : 4 gradded stone aggregate of 20 mm
nominal size), including centering shuttering all complete.and including
rungs (Foot Rests) as per stanndard specification

0 0.00 0 0.00 0.00 0.00 - - -


4.52 Extra depth for circular type manhole 1200 mm internal dia (at bottom)
with bricks beyond 1650 mm to 2300 mm. RM 0 4865.00 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.53 Providing M.S. foot rests (MS Rungs) including fixing in manholes
with 200 x 200 x 100 mm cement concrete blocks 1:3:6 (1 cement : 3
coarse sand :6 graded stone aggregate 20 mm nominal size) as per Set 5 145.95 729.75 0 0.00 0.00 0.00 - - -
standard design : with 20 x 20 mm square bar.

4.54 Constructing brick masonry circular manhole 1500 mm internal dia at


bottom and 560 mm dia at top with brick work of class 75 in cement
mortar 1:4 (1 cement: 4 coarse sand) inside cement plaster 12 mm thick
with cement mortar 1:3 (1 cement: 3 coarse sand) finished with a
floating coat of neat cement, foundation concrete 1:3:6 mix (1 cement :3
coarse sand: 6 graded stone aggregate 40mm nominal size) benching
and making necessary channel in cement concrete 1:2:4 (1 cement:2
coarse sand: 4 graded stone aggregate 20mm nominal size ) finished
with a floating coat of neat cement on inside face, proper water proofing
to ensure no ground water seepage in the manhole including necessary
excavation, dewatering, refilling, watering, ramming, removing the
surplus excavated material and making good the same complete No. 2 29190.00 58,380.00 0 0.00 0.00 0.00 - - -
including curing with all necessary lead and lifts as required all complete
as per standard design 2300 mm deep with 600 mm dia, Heavy Duty
SFRC cover and frame , fixed in cement concrete 1:2:4
(1cement : 2 coarse sand : 4 gradded stone aggregate of 20 mm
nominal sige)
including centering shuttering all complete.

0 0.00 0 0.00 0.00 0.00 - - -


4.55 Extra depth for circular type manhole 1500 mm internal dia (at bottom)
with brick work of class 75. RM 0 7297.50 - 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.56 Providing M.S. foot rests (MS Rungs) including fixing in manholes
with 200 x 200 x 100 mm cement concrete blocks 1:3:6 (1 cement : 3
coarse sand :6 graded stone aggregate 20 mm nominal size) as per Set 2 145.95 291.90 0 0.00 0.00 0.00 - - -
standard design : with 20 x 20 mm square bar.

0 0.00 0 0.00 0.00 0.00 - - -


0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
Constructing Brick Masonry Open surface drain Covered with RCC Cum
precast grating (medium duty cover suitable for car park park loading) &
with bricks of class designation 75 in cement mortar 1:4 (1 cement : 4
fine sand) including earth excavation, 100 mm thick bed concrete 1:4:8
(1 cement : 4 fine sand : 8 graded stone aggregate 40 mm nominal size)
and 25 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4
graded stone aggregate 12.5 mm nominal size) for filling haunches
including 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) with a
0 0.00 0 0.00 0.00 0.00 - - -
floating coat of neat cement inside the drain, its top and exposed side
including disposal of surplus earth & M.S flat of 5 mm thk off 75 mm wide
@ 75 mm spacing – 6 tier with in storm trench to run electrical cable.
complete as per standard design: Excavation, Backfilling with
compaction and disposal of excess earth

4.57 Providing and fixing over straight or curved drain M.S. CABLE
CLEAT with fixed frame of FLAT 25 mm x 5 mm size fixed to
concrete with Including two Coat of Red Oxide Primer and One Coat of nos 0 145.95 0 0.00 0.00 0.00 - - -
blacl Butumens paints over as required.
4.58 PCC 1:4:8 Cum 12.50 4378.50 54,731.25 12.5 0.00 12.50 18.29 5.79 25357.21 54,731.25 - 54,731.25
0 0.00 0 0.00 0.00 0.00 - - -
4.59 Brick Work 1:5 CM Cum 30 4865.00 145,950.00 25.34987 0.00 25.35 25.35 0.00 0.00 123,327.12 - 123,327.12
0 0.00 0 0.00 0.00 0.00 - - -
4.60 Plaster 12 mm thick CM 1:4 Sqm 160 389.20 62,272.00 144.8564 0.00 144.86 144.86 0.00 0.00 56,378.11 - 56,378.11

156 of 211
Up To Up To Up To Previous
Previous This Bill This Bill Up To Date
Bill Date Bill
PHASE 3 D - PHE WORKS
S.NO. DESCRIPTION Unit Quantity Rate Amount
0 0.00 0 0.00 0.00 0.00 - - -
4.61 Shuttering for PCC Sqm 20 437.85 8,757.00 20 0.00 20.00 62.24 42.24 18494.78 8,757.00 - 8,757.00
0 0.00 0 0.00 0.00 0.00 - - -
4.620 Providing and fixing over straight or curved drain Precast Cover .
300 mm Wide 729.75 40,136.25 0 0.00 0.00 0.00 - - -
Rmt 55
4.630 450 mm Wide Rmt 30 924.35 27,730.50 0 0.00 0.00 0.00 - - -
4.640 600 mm Wide Rmt 300 973.00 291,900.00 55.35 0.00 55.35 55.35 0.00 0.00 53,855.55 - 53,855.55
4.650 750 mm Wide Rmt 25 1167.60 29,190.00 25 0.00 25.00 54.55 29.55 34502.58 29,190.00 - 29,190.00
4.660 900 mm Wide Rmt 32 1459.50 46,704.00 0 0.00 0.00 0.00 - - -
4.670 1000 MM Wide Rmt 5 1946.00 9,730.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
4.680 Providing and fixing over straight or curved drain M.S. CABLE
CLEAT with fixed frame of FLAT 25 mm x 5 mm size fixed to
concrete with Including two Coat of Red Oxide Primer and One Coat of nos 330 145.95 48,163.50 106.00 0.00 106.00 106.00 0.00 0.00 15,470.70 - 15,470.70
blacl Butumens paints over as required.
0 0.00 0 0.00 0.00 0.00 - - -
4.690 Making connection to Municipal sewer / storm water drain including
necessary excavation and breaking the wall of municipal manhole and
making good the same with Cement mortar 1:3, finished with a floating
coat of neat cement and making drains etc. complete. Removing the
excavated surplus material. This also includes the contractor for
liasoning work such as filling necessary applications, submission
of forms for approval to the municipal authorities, depositing and
making channels for the necessary fees and other amounts as
required for getting the premises / installations inspected and Job 1 14595.00 14,595.00 0 0.00 0.00 0.00 - - -
approved and all other formalities required till the sewer / storm
water connection is obtained. All the expenses incurred in this regard
shall be borne by the Contractor, except for the payments to be made
for any security deposits which will be reimbursed on production of
original voucher. For Sewer Connection

0 0.00 0 0.00 0.00 0.00 - - -


4.700 For Storm Water Connection Job 1 14595.00 14,595.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
0 0.00 0 0.00 0.00 0.00 - - -
Fire-Fighting System 0 0.00 0 0.00 0.00 0.00 - - -
Fire Protection System 0 0.00 0 0.00 0.00 0.00 - - -
4.71 0 0.00 0 0.00 0.00 0.00 - - -
Providing, laying, jointing and testing in trenches the following sizes of
MS class `C' (heavy class) pipes conforming to IS:1239 with accessories
like fittings including tees, elbows, reducers, flanges, rubber gaskets,
G.I. nuts, bolts and washers including excavation in all kind of soil,
refilling, ramming, shoring, removing the excavated surplus material,
providing adequate support to the pipe and making good the same RM 155 1313.55 203,600.25 65.7 0.00 65.70 65.70 0.00 0.00 86,300.24 - 86,300.24
complete as required. Rate shall include for dewatering necessary to
execute the work. The pipe shall not be less than 1.5 m below ground
level at any point Thrust bloc to be provided C To C 2 Mtr. 80 mm dia

0 0.00 0 0.00 0.00 0.00 - - -


4.72 100 mm dia RM 0 1800.05 - 0 0.00 0.00 0.00 - - -
0 0.00 - 0 0.00 0.00 0.00 - - -
4.73 150 mm dia RM 110 2627.10 288,981.00 22.725 0.00 22.73 22.73 0.00 0.00 59,700.85 - 59,700.85
0 0.00 - 0 0.00 0.00 0.00 - - -
4.74 200 mm dia (As per IS 3589) RM 430 3405.50 1,464,365.00 417.39 0.00 417.39 417.39 0.00 0.00 1,421,421.65 - 1,421,421.65
0 0.00 - 0 0.00 0.00 0.00 - - -
4.75 Providing protection to embedded MS pipes and fittings by applying
protective primer (@ 100 gm/sqm) thereafter wrapping 4 mm thick
protection coating by thermo fusion process. Overlap shall be
maintained at 15 mm. The application process shall be strictly according
RM 155 272.44 42,228.20 65.7 0.00 65.70 56.70 -9.00 -2451.96 17,899.31 - 17,899.31
to manufacturer’s specification. Thrust block and Sand bedding to be
provided as described in Technical Specification. 80 mm dia

0 0.00 - 0 0.00 0.00 0.00 - - -


4.76 100 mm dia RM 0 389.20 - 0 0.00 0.00 0.00 - - -
0 0.00 - 0 0.00 0.00 0.00 - - -
4.77 150 mm dia RM 110 437.85 48,163.50 22.725 0.00 22.73 22.73 0.00 0.00 9,950.14 - 9,950.14
0 0.00 - 0 0.00 0.00 0.00 - - -
4.78 200 mm dia RM 450 486.50 218,925.00 417.39 0.00 417.39 417.39 0.00 0.00 203,060.24 - 203,060.24
0 0.00 - 0 0.00 0.00 0.00 - - -
4.79 Providing & fixing of butterfly valve (suitable for test pressure of 15 kg /
sqm) with flanges, nut bolts, gaskets and necessary pad locking No. 2 4865.00 9,730.00 0 0.00 0.00 0.00 - - -
arrangement complete required. 80 mm dia
4.80 100 mm dia No. 0 7005.60 - 0 0.00 0.00 0.00 - - -
0 0.00 - 0 0.00 0.00 0.00 - - -
4.81 150 mm dia No. 6 9243.50 55,461.00 2 0.00 2.00 2.00 0.00 0.00 18,487.00 - 18,487.00
0 0.00 - 0 0.00 0.00 0.00 - - -
4.82 200 mm dia No. 4 13427.40 53,709.60 2 0.00 2.00 2.00 0.00 0.00 26,854.80 - 26,854.80
0 0.00 - 0 0.00 0.00 0.00 - - -
4.83 250 mm dia No. 0 17708.60 - 0 0.00 0.00 0.00 - - -
0 0.00 - 0 0.00 0.00 0.00 - - -
0 0.00 - 0 0.00 0.00 0.00 - - -
4.84 Providing and fixing of C.I. wafer type check valve with flanges, Nut,
bolts & washers, painting etc. complete as required. 80 mm dia No. 2 3210.90 6,421.80 0 0.00 0.00 0.00 - - -

0 0.00 - 0 0.00 0.00 0.00 - - -


4.85 100 mm dia No. 0 4865.00 - 0 0.00 0.00 0.00 - - -
0 0.00 - 0 0.00 0.00 0.00 - - -
4.86 150 mm dia No. 4 8075.90 32,303.60 0 0.00 0.00 0.00 - - -
0 0.00 - 0 0.00 0.00 0.00 - - -
4.87 200 mm dia No. 0 15081.50 - 0 0.00 0.00 0.00 - - -
0 0.00 - 0 0.00 0.00 0.00 - - -
4.88 Providing & fixing gun metal External fire hydrant single hydrant
valve with 80 mm N.B. flanged inlet, brass spindle controlled 63 mm
dia female instantaneous outlet type. G.M. coupling, blank cap, chain,
twist release type lug & all accessories Conforming to IS:5290. Including
fixing with anchor fastener and flanged tapping from wet riser and Nos. 12 8075.90 96,910.80 10 0.00 10.00 10.00 0.00 0.00 80,759.00 - 80,759.00
providing pressure gauge with gun metal ball valve complete as
required.

0 0.00 - 0 0.00 0.00 0.00 - - -


4.89 Providing & fixing controlled percolation fire hose pipe (as per
IS:8423) of 63 mm dia and 15 meter length rated for burst pressure of
35.7 Kg/sqcm. The hose shall be tested for flame resistance test in
accordance to IS:8423. Hose shall be complete with ISI marked brass
Nos. 24 4183.90 100,413.60 20 0.00 20.00 20.00 0.00 0.00 83,678.00 - 83,678.00
male & female coupling (IS:903) bound & riveted to hose pipe with
copper rivets & 1.5 mm copper wire (Location : External fire hydrant)

0 0.00 - 0 0.00 0.00 0.00 - - -


4.90 Providing and fixing weather proof lockable cabinet of size not
less than 0.9 x 0.6 x 0.45 mtr made out of MS sheet of 16 gauge
thickness having central opening and 4 mm thick glazed glass doors
(Two nos.) suitably marked on the outside with the letters "FIRE
HOSE" including necessary locking arrangement and shall be painted 12 8854.30 106,251.60 10 0.00 10.00 10.00 0.00 0.00 88,543.00 - 88,543.00
with one coat of primer and two coats of synthetic enamel paint of
approved shade.

0 0.00 - 0 0.00 0.00 0.00 - - -


0.00 - 0 0.00 0.00 0.00 - - -
0 0.00 - 0 0.00 0.00 0.00 - - -
4.91 Providing & fixing gun-metal fire brigade connection (suction
collecting head) consisting of 4 Nos. 63 mm dia instantaneous type male
couplings with built-in check valves, 1 No. 150 mm dia sluice valve, (1
No. 150 mm dia non-return valve) and 150 mm dia flanged outlet set 5 27341.30 136,706.50 0 0.00 0.00 0.00 - - -
complete with bolts, nuts and rubber insertions as required and as per
IS:904-1963.

0 0.00 - 0 0.00 0.00 0.00 - - -


0.00 - 0 0.00 0.00 0.00 - - -
4.92 Providing & fixing gun-metal fire brigade suction hose coupling
(draw-out connection) with nut for female coupling as per IS: 902-1974
complete with 100 mm dia GI suction pipe and 100 mm dia foot valve (to
be connected to static tank). Provision of GI drop pipe and foot valve Set 5 22379.00 111,895.00 0 0.00 0.00 0.00 0.00 - - -
shall be made in all the fire water static storage tanks (4 Nos) (GI
pipe to be paid separately through appropriate item while cost of foot
valve to be included).

0.00 0.00 - - -
Extra Item 0.00 0.00 - - -
Carrying out excavation in trenches and carting away the excavated 145.95
material to the location indicated, up to any lead and level, inclusive of
dewatering if required, shoring, protecting the slopes/sides etc.
complete. Rate shall include backfilling of the excavated pit after
construction of footings or pile caps or space behind the retaining walls,
shear walls, walls of underground structures, buried rafts, foundations
etc., including watering, ramming, compacting, rolling, leveling to
E1 required grade etc. complete and stacking the excavated material at site Cum 200.00 29,190.00 35.876871 0.00 35.88 35.88 0.00 0.00 5,236.23 - 5,236.23
or as directed by Project Manager within site boundary.
Note: Only PCC Area as per Drawing will be considered for
measurement. Provision of working space & slope if required for
excavation will not be paid separately.

Total 0 8,016,741.60 93,416.61 4,819,609.74 14,595.00 4,834,204.74

157 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks

Providing, laying, jointing and testing in position the following heavy class GI pipes for under ground piping conforming to IS:1239
including all necessary fittings (conforming to IS : 1879) such as elbow, coupler & tee etc. Cost shall be inclusive of excavation,
dewatering, backfilling, ramming surrounding the pipe alround with minimum 150 mm thick compacted silver sand and
4.1
providing thrust block at distance 2 M C/C. (Pipe shall be provided with anti corrosive protective treatment Pypkote / Coatek
confirming to AWWA C 203 / IS 10221 standard complete as per specification). All work complete as per specification and
satisfaction of the Project Manager. 40 mm dia

R.A.-03

Connecting line to B & D block Rmt 65 65.00


1 JMR-12

40mm pipe at D Block Rmt 22.6 22.60


1 JMR-11

40mm pipe at B Block Rmt 48.6 48.60


1 JMR-11

R.A.-04

Block B to C Rmt 10.2 10.20


1 JMR-11
Total Qty 146.40
BOQ Quantity 235.00
Previously Certified Qty 146.40
This Bill Qty. -
Amendment Qty. -

158 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks

Providing, laying, jointing and testing in position the following heavy class GI pipes for under ground piping conforming to IS:1239
including all necessary fittings (conforming to IS : 1879) such as elbow, coupler & tee etc. Cost shall be inclusive of excavation,
dewatering, backfilling, ramming surrounding the pipe alround with minimum 150 mm thick compacted silver sand and
4.2
providing thrust block at distance 2 M C/C. (Pipe shall be provided with anti corrosive protective treatment Pypkote / Coatek
confirming to AWWA C 203 / IS 10221 standard complete as per specification). All work complete as per specification and
satisfaction of the Project Manager. 50 mm dia

R.A.-03

At D Block 50mm dia Rmt 26.54 26.54


1 JMR-13

Connecting line to B & D block Rmt 65 65.00


1 JMR-12

At D Block 50mm dia Rmt 22.7 22.70


1 JMR-11

R.A.-04

Block B to C Rmt 12.1 12.10


1 JMR-11
Total Qty 126.34
BOQ Quantity 235.00
Previously Certified Qty 126.34
This Bill Qty. -
Amendment Qty. -

159 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks

Providing & fixing full way lever operated forged brass ball valve of brass body with forged brass hard chrome plated steel ball
4.17 tested to a pressure not less than 15 Kg / sqcm with threaded / flanged joints complete with nuts, bolts, gaskets, washers etc. 40
mm dia

R.A.-06
40mm dia ball valve as per attached
Nos. 7.00
JMR & Drawing 7 JMR-2
Total Qty 7.00
BOQ Quantity 8.00
Previously Certified Qty 7.00
This Bill Qty. -
Amendment Qty. -

Providing & fixing full way lever operated forged brass ball valve of brass body with forged brass hard chrome plated steel ball
4.18 tested to a pressure not less than 15 Kg / sqcm with threaded / flanged joints complete with nuts, bolts, gaskets, washers etc. 50
mm dia

R.A.-06
50mm dia ball valve as per attached
Nos. 3.00
JMR & Drawing 3 JMR-2
Total Qty 3.00
BOQ Quantity 8.00
Previously Certified Qty 3.00
This Bill Qty. -

160 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
Amendment Qty. -

Providing, fixing , testing and commissioning water meter with direct reading dial in KL with all necessary fitting such as
threaded pieces, unions, pressure gauge, isolation valve, Non return valve, flange piece for future removal, flanges / unions
4.26 complete with all necessary testing charges and obtaining test certificates from municipal authorities, on following size pipe lines
(1 no. Y strainer shall be provided at inlet and cost shall be inclusive for the same). The meter shall comply to ISO 4064 standard,
feasible for class B or Class A installation.50 mm dia (CI)

R.A.-08

Tube Well Chamber Nos. 1.00


1 JMR-14
Total Qty 1.00
BOQ Quantity 1.00
Previously Certified Qty -
This Bill Qty. 1.00
Amendment Qty. -

Construction of Valve chamber with 230 mm best quality bricks of class 75 as per drawings of the following sizes in cement mortar
1 : 4 (1 cement : 4 find sand) necessary 100 mm thick PCC bed in 1 : 4 : 8. Inside & outside plastering 12 mm thick with cement
mortar 1 : 3 with a coat of neat cement. Including the RCC top slab for fixing the grating including necessary excavation,
4.34
dewatering, refilling, watering, ramming, removing, the surplus excavated material and making good the same complete including
curing with all necessary lead and lifts as required. Cost shall be inclusive of providing heavy duty SFRC grating with frame
complete. Internal size 900 x 900 - up to 1500 mm deep; heavy duty SFRC Cover with frame with frame 900 x 900 mm.

R.A.-03

Valve Chamber at D Block Nos. 2.00


2 JMR-14

R.A.-05

161 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks

FWS & DWS Chamber Nos. 2.00


2

Fire Chamber Nos. 2.00


2
Total Qty 6.00
BOQ Quantity 6.00
Previously Certified Qty 6.00
This Bill Qty. -
Amendment Qty. -

Drilling of Bore well of 150 mm dia , 275 m depth. Providing and Lowering of 150 mm MS tube well casing pipe. Tube well
accessories as required. Filling of 1.6 to 4.8 mm dia Lalkuan Pea Gravel all around Tube well. Development of Tube well complete.
4.37
Supplying, installing , testing and commissioning Bore well submersible pumps of 15 H.P and 240 m head including cabling 120
Rmt from Bore well pump to feeder panel, local contols etc. complete.

Drilling of Bore well Nos. 0.5 0.50


1 As per Site JMR Check list

R.A.-03 0.00

Drilling of Bore well 0.5 0.50

Total Qty 1.00


BOQ Quantity 1.00
Previously Certified Qty 1.00
This Bill Qty. -
Amendment Qty. -

162 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks

Providing, fixing, jointing and testing in position the following UPVC pipes confirming to IS:4985 of 6 Kg / Sq.cm for Sewerage
system cut to required length. Pipe to be laid below ground level in trenches upto required depth including excavation in all kind of
4.40 soil (hard rock), dewatering, refilling, watering, ramming and removing the surplus excavated material including curing with all
necessary lead and lifts complete as required and making good the same complete as required. Cost shall be inclusive of
providing protection to pipe all round / haunches as per specification. 160 mm dia

R.A.-03
UPVC 160mm dia at D Block for
Rmt 41.3 41.30
Sewage 1 JMR-19
UPVC 160mm dia at D & B Block for
Rmt 44.9 44.90
storm 1 JMR-18

UPVC 160mm dia for storm water Rmt 112.8 112.80


1 JMR-17

UPVC 160mm dia for Sewage Rmt 117.24 117.24


1 JMR-16
UPVC 160mm dia sewage line for
Rmt 23.7 23.70
connecting B & D Building 1 JMR-15
UPVC 160mm dia storm water line
Rmt 35.6 35.60
for connecting B & D Building 1 JMR-15

R.A.-04

UPVC 160mm dia sewage line for


Rmt 11.95 11.95
D Building 1
UPVC 160mm dia sewage line for B
Rmt 12.3 12.30
Building 1

163 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
UPVC 160mm dia storm water line
Rmt 17.9 17.90
for D Building 1
UPVC 160mm dia sewage line for B
Rmt 19.5 19.50
Building to old connection 1

Total Qty 437.19


BOQ Quantity 490.00
Previously Certified Qty 437.19
This Bill Qty. -
Amendment Qty.

Providing, fixing, jointing and testing in position the following UPVC pipes confirming to IS:4985 of 6 Kg / Sq.cm for Sewerage
system cut to required length. Pipe to be laid below ground level in trenches upto required depth including excavation in all kind of
4.41 soil (hard rock), dewatering, refilling, watering, ramming and removing the surplus excavated material including curing with all
necessary lead and lifts complete as required and making good the same complete as required. Cost shall be inclusive of
providing protection to pipe all round / haunches as per specification. 200 mm dia

R.A.-03

UPVC 200mm dia at kiosk Rmt 12 48.00


4 JMR-20
Total Qty 48.00
BOQ Quantity 320.00
Previously Certified Qty 48.00
This Bill Qty. -
Amendment Qty. -

164 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks

Construction of Storm / sewage Water road gully chamber of the following sizes in brick work with bricks of class 75 in cement
mortar 1 : 5 (1 cement : 5 find sand) necessary foundation concrete (1 : 4 : 8). Inside & outside plastering 12 mm thick with
cement mortar 1 : 3 with a floating a coat of neat cement. Including the RCC top slab for fixing the grating including necessary
4.47
excavation, dewatering, refilling, watering, ramming, removing, the surplus excavated material and making good the same
complete as required. Cost shall be inclusive of providing, Internal size 600 x 600 - upto 1200 mm deep; heavy duty SFRC
Grating with frame 600 x 600 mm.

R.A.-03

Storm water Chamber at B block Nos. 6.00


6 JMR-22

Storm water Chamber at D block Nos. 3.00


3 JMR-21

R.A.-04

Storm water Chamber at D block 1.00


1

R.A.-06

Storm water trench 6.00


6 JMR-03
Total Qty 16.00
BOQ Quantity 14.00
Previously Certified Qty 14.00
This Bill Qty. -
Amendment Qty. 2.00

165 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks

Construction of Storm / sewage Water road gully chamber of the following sizes in brick work with bricks of class 75 in cement
mortar 1 : 5 (1 cement : 5 find sand) necessary foundation concrete (1 : 4 : 8). Inside & outside plastering 12 mm thick with
cement mortar 1 : 3 with a floating a coat of neat cement. Including the RCC top slab for fixing the grating including necessary
4.50
excavation, dewatering, refilling, watering, ramming, removing, the surplus excavated material and making good the same
complete as required. Cost shall be inclusive of providing, Internal size 600 x 900 - upto 1500 mm deep; heavy duty SFRC
Grating with frame 600 x 900 mm.

R.A.-03

Sewage Line at B block Nos. 14.00


14 JMR-23

Sewage Line at D block Nos. 13.00


13 JMR-24

R.A.-04

Sewage Line at D block Nos. 3.00


3

Sewage Line at B block Nos. 1.00


1
Total Qty 31.00
BOQ Quantity 31.00
Previously Certified Qty 31.00
This Bill Qty. -
Amendment Qty. -
4.58 PCC 1:4:8 for strom water trench
Up to RA-2
PCC at B block Cum 1 48.4 1.35 0.100 6.53 Drawing 4 & 5 and JMR-1
PCC at D block Cum 1 21.3 1.5 0.100 3.20 Drawing 6 & 7 and JMR-2
R.A.-04

166 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
PCC at B block Cum 1 8.1 1.35 0.100 1.09
Copping at B Block Cum 2 48.4 0.35 0.150 5.08
Copping at D Block Cum 2 21.3 0.35 0.150 2.24
Copping at B Block Cum 2 8.1 0.35 0.150 0.85
Dedcution for Cover Cum -2 77.8 0.075 0.060 -0.70
Total Qty 18.29
BOQ Quantity 12.50
Previously Certified Qty 12.50
This Bill Qty. -
Amendment Qty. 5.79
4.59 Brick Work 1:5 CM for strom water trench
Up to RA-2
Brick work at B block Cum 2 48.4 0.35 0.365 12.37 Drawing 4 & 5 and JMR-1
Brick work at D block Cum 2 21.3 0.35 0.732 10.91 Drawing 6 & 7 and JMR-2
R.A.-04
Brick Work at B block Cum 2 8.1 0.35 0.365 2.07
Total Qty 25.35
BOQ Quantity 30.00
Previously Certified Qty 25.35
This Bill Qty. -
Amendment Qty. -
4.60 Plaster 12 mm thick CM 1:4
Up to RA-2
Plaster work at B block Smt 4 48.4 0.365 70.66 Drawing 4 & 5 and JMR-1
Plaster work at D block Smt 4 21.3 0.732 62.37 Drawing 6 & 7 and JMR-2
R.A.-04
Plaster Work at B block Cum 4 8.1 0.365 11.83
Total Qty 144.86
BOQ Quantity 160.00

167 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
Previously Certified Qty 144.86
This Bill Qty. -
Amendment Qty. -
4.61 Shuttering for PCC
Up to RA-2
PCC work at B block Cum 2 48.4 0.100 9.68 Drawing 4 & 5 and JMR-1
PCC work at D block Cum 2 21.3 0.100 4.26 Drawing 6 & 7 and JMR-2
R.A.-04
PCC Work at B block Cum 2 8.1 0.100 1.62
Copping at B Block Cum 4 48.4 0.150 29.04
Copping at D Block Cum 4 21.3 0.150 12.78
Copping at B Block Cum 4 8.1 0.150 4.86
Total Qty 62.24
BOQ Quantity 20.00
Previously Certified Qty 20.00
This Bill Qty. -
Amendment Qty. 42.24

Providing and fixing over straight or curved drain M.S. CABLE CLEAT with fixed frame of FLAT 25 mm x 5 mm size fixed to
4.680
concrete with Including two Coat of Red Oxide Primer and One Coat of blacl Butumens paints over as required.

Up to RA-2
Cleat for electric cable in strom
Nos. 73 73.00
water trench at B block 1 Drawing 4 & 5 and JMR-1
Cleat for electric cable in strom
Nos. 33 33.00
water trench at D block 1 Drawing 6 & 7 and JMR-2
Total Qty 106.00

168 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
BOQ Quantity 330.00
Previously Certified Qty 106.00
This Bill Qty. -
Amendment Qty. -
4.640 Providing and fixing over straight or curved drain Precast Cover . 600 mm Wide

R.A-05
Kesarjan Drain cover work at B
Rmt 55.35 55.35
block 1
Total Qty 55.35
BOQ Quantity 300.00
Previously Certified Qty 55.35
This Bill Qty. -
Amendment Qty. -

4.650 Providing and fixing over straight or curved drain Precast Cover . 750 mm Wide

R.A-05
Kesarjan Drain cover work at D
Rmt 22.65 22.65
block 1
R.A-06
Kesarjan Drain cover work at D
Rmt 31.9 31.90
block 1
Total Qty 54.55
BOQ Quantity 25.00

169 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
Previously Certified Qty 25.00
This Bill Qty. -
Amendment Qty. 29.55

Providing, laying, jointing and testing in trenches the following sizes of MS class `C' (heavy class) pipes conforming to IS:1239 with
accessories like fittings including tees, elbows, reducers, flanges, rubber gaskets, G.I. nuts, bolts and washers including
4.710 excavation in all kind of soil, refilling, ramming, shoring, removing the excavated surplus material, providing adequate support to
the pipe and making good the same complete as required. Rate shall include for dewatering necessary to execute the work. The
pipe shall not be less than 1.5 m below ground level at any point Thrust bloc to be provided C To C 2 Mtr. 80 mm dia

R.A.-04
Fire line80 mm dia MS pipe Rmt 1 65.7 65.70
Total Qty 65.70
BOQ Quantity 155.00
Previously Certified Qty 65.70
This Bill Qty. -
Amendment Qty. -

Providing, laying, jointing and testing in trenches the following sizes of MS class `C' (heavy class) pipes conforming to IS:1239 with
accessories like fittings including tees, elbows, reducers, flanges, rubber gaskets, G.I. nuts, bolts and washers including
4.73 excavation in all kind of soil, refilling, ramming, shoring, removing the excavated surplus material, providing adequate support to
the pipe and making good the same complete as required. Rate shall include for dewatering necessary to execute the work. The
pipe shall not be less than 1.5 m below ground level at any point Thrust bloc to be provided C To C 2 Mtr. 150 mm dia

R.A.-04
Fire line150 mm dia MS pipe Rmt 1 22.725 22.73
Total Qty 22.73
BOQ Quantity 110.00

170 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
Previously Certified Qty 22.73
This Bill Qty. -
Amendment Qty. -

Providing, laying, jointing and testing in trenches the following sizes of MS class `C' (heavy class) pipes conforming to IS:1239 with
accessories like fittings including tees, elbows, reducers, flanges, rubber gaskets, G.I. nuts, bolts and washers including
4.740 excavation in all kind of soil, refilling, ramming, shoring, removing the excavated surplus material, providing adequate support to
the pipe and making good the same complete as required. Rate shall include for dewatering necessary to execute the work. The
pipe shall not be less than 1.5 m below ground level at any point Thrust bloc to be provided C To C 2 Mtr. 200 mm dia

R.A.-02
Fire line 200mm dia MS pipe Rmt 1 128.14 128.14 JMR 3, 4 and Drawing -8
R.A-03
Fire line 200mm dia MS pipe at D
Rmt 125.66
Block 1 125.66 JMR-25
Rmt 1 45.17 45.17 JMR-26
Fire line at B block Rmt 1 44.24 44.24 JMR-27
Connecting to B & D Block Rmt 1 24.63 24.63 JMR-28
From B block tooutside compound
Rmt 20.95
wall 1 20.95 JMR-29
R.A.-04
Fire line200 mm dia MS pipe Rmt 1 28.6 28.60
Total Qty 417.39
BOQ Quantity 430.00
Previously Certified Qty 417.39
This Bill Qty. -
Amendment Qty.

171 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks

Providing protection to embedded MS pipes and fittings by applying protective primer (@ 100 gm/sqm) thereafter wrapping 4 mm
thick protection coating by thermo fusion process. Overlap shall be maintained at 15 mm. The application process shall be strictly
4.750
according to manufacturer’s specification. Thrust block and Sand bedding to be provided as described in Technical Specification.
80 mm dia

R.A.-04
Fire line80 mm dia MS pipe Rmt 1 65.7 65.70
R.A.-08
Fire Line 80mm dia MS pipe Rmt -10 0.9 -9.00

Total Qty 56.70


BOQ Quantity 155.00
Previously Certified Qty 65.70
This Bill Qty. -9.00
Amendment Qty. -

Providing protection to embedded MS pipes and fittings by applying protective primer (@ 100 gm/sqm) thereafter wrapping 4 mm
thick protection coating by thermo fusion process. Overlap shall be maintained at 15 mm. The application process shall be strictly
4.77
according to manufacturer’s specification. Thrust block and Sand bedding to be provided as described in Technical Specification.
150 mm dia

R.A.-04
Fire line150 mm dia MS pipe Rmt 1 22.725 22.73
Total Qty 22.73
BOQ Quantity 110.00

172 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
Previously Certified Qty 22.73
This Bill Qty. -
Amendment Qty. -
thick protection coating by thermo fusion process. Overlap shall be maintained at 15 mm. The application process shall be strictly
4.780
according to manufacturer’s specification. Thrust block and Sand bedding to be provided as described in Technical Specification.

R.A-03
Fire line 200mm dia MS pipe Rmt 1 128.14 128.14 JMR 3, 4 and Drawing -8
Fire line 200mm dia MS pipe at D
Rmt 125.66
Block 1 125.66 JMR-25
Rmt 1 45.17 45.17 JMR-26
Fire line at B block Rmt 1 44.24 44.24 JMR-27
Connecting to B & D Block Rmt 1 24.63 24.63 JMR-28
From B block tooutside compound
Rmt 20.95
wall 1 20.95 JMR-29
R.A.-04
Fire line200 mm dia MS pipe Rmt 1 28.6 28.60
Total Qty 417.39
BOQ Quantity 450.00
Previously Certified Qty 417.39
This Bill Qty. -
Amendment Qty.
Providing & fixing of butterfly valve (suitable for test pressure of 15 kg / sqm) with flanges, nut bolts, gaskets and necessary pad
4.81
locking arrangement complete required. 150 mm dia
R.A.-06
150mm dia Fire butterfly valve as
Nos. 2.00
per attached JMR & Drawing 2 JMR-05
Total Qty 2.00
BOQ Quantity 6.00
Previously Certified Qty 2.00

173 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
This Bill Qty. -
Amendment Qty. -

Providing & fixing of butterfly valve (suitable for test pressure of 15 kg / sqm) with flanges, nut bolts, gaskets and necessary pad
4.82
locking arrangement complete required. 200 mm dia

R.A.-06
200mm dia Fire butterfly valve as
Nos. 2.00
per attached JMR & Drawing 2 JMR-05
Total Qty 2.00
BOQ Quantity 4.00
Previously Certified Qty 2.00
This Bill Qty. -
Amendment Qty. -

Providing & fixing gun metal External fire hydrant single hydrant valve with 80 mm N.B. flanged inlet, brass spindle controlled
63 mm dia female instantaneous outlet type. G.M. coupling, blank cap, chain, twist release type lug & all accessories
4.88
Conforming to IS:5290. Including fixing with anchor fastener and flanged tapping from wet riser and providing pressure gauge
with gun metal ball valve complete as required.

R.A.-06
80mm dia Fire Hydrant valve as per
Nos. 10.00
attached JMR & Drawing 10 JMR-14
Total Qty 10.00
BOQ Quantity 12.00

174 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
Previously Certified Qty 10.00
This Bill Qty. -
Amendment Qty. -

Providing & fixing controlled percolation fire hose pipe (as per IS:8423) of 63 mm dia and 15 meter length rated for burst pressure
of 35.7 Kg/sqcm. The hose shall be tested for flame resistance test in accordance to IS:8423. Hose shall be complete with ISI
4.89
marked brass male & female coupling (IS:903) bound & riveted to hose pipe with copper rivets & 1.5 mm copper wire (Location :
External fire hydrant)

R.A.-07

Hose Pipe Nos. 20.00


20 JMR-14
Total Qty 20.00
BOQ Quantity 24.00
Previously Certified Qty 20.00
This Bill Qty. -
Amendment Qty. -

Providing and fixing weather proof lockable cabinet of size not less than 0.9 x 0.6 x 0.45 mtr made out of MS sheet of 16
gauge thickness having central opening and 4 mm thick glazed glass doors (Two nos.) suitably marked on the outside with
4.9
the letters "FIRE HOSE" including necessary locking arrangement and shall be painted with one coat of primer and two coats of
synthetic enamel paint of approved shade.

R.A.-07

Cabinet Nos. 10.00


10 JMR-14
Total Qty 10.00

175 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
BOQ Quantity 12.00
Previously Certified Qty 10.00
This Bill Qty. -
Amendment Qty. -

Extra item Excavation for strom water trench

Up to RA-2
Excavation work at B block Cum 1 48.4 1.35 0.337 22.05 Drawing 4 & 5 and JMR-1
Excavation work at D block Cum 1 21.3 1.5 0.433 13.83 Drawing 6 & 7 and JMR-2
Total Qty 35.88
BOQ Quantity 200.00
Previously Certified Qty 35.88
This Bill Qty. -
Amendment Qty. -

Providing, Laying, jointing and testing socketed and spigotted RCC pipes (NP2 class) for conveying Pipelines across roads
conforming to IS:458 collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 find sand) laid to
Extra Item correct levels below ground in trenches upto required depth including excavation in all kind of soil (hard / soft), dewatering, refilling,
-2 watering, ramming and removing the surplus excavated material including curing with all necessary lead and lifts as required
including testing of joints etc. complete of following sizes. Cost shall be inclusive of providing protection to pipe all round /
haunches as per specification. 150 mm dia

R.A.-05
Asper attached JMR Rmt 1 71 71

Total Qty 71.00


BOQ Quantity -
Previously Certified Qty -

176 of 211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks
This Bill Qty. -
Amendment Qty. 71.00

177 of 211
PHASE 3 D - LANDSCAPE & IRRIGATION WORKS 3D Quantity

Up To Previous
Sr. No. PARTICULARS UNIT Quantity Rate Amount This Bill
Bill

AREA STATEMENT SQ.M 1950 -


1 Softscape in ground floor
Area avilable for softscape SQ.M -

A Earth work-stripping/Excavation/Filing
5.1 By removal of clods, building debbris, dirt etc. and carting of
debris out of the site, to provide a clean surface to dump soil for cum 390 291.90 113,841.00 390.000 -
grading works etc. complete
5.2 Excavation and filling of good earth to the required depth from I
km vicinity of the site to reach formation levels and planting
areas, including lead and lift,spreading ,leveling etc, complete. cum 878 340.55 298,832.63 236.826 -

5.3 Supply of soil Mix (Soil to brought from site itself) measurment
by clients and contractor's reprsentative ) Soil Mix A consist of
Black Cotton Soil 60% (Existing on site) Sand 10%,Manure cum 585 535.15 313,062.75 228.712 -
20%,neem cake 10%.sample to be submitted for lanscape
Architect's approval.
Soil mix contain pipe, geo fabric linning, brick bat, sand, garden poyta
SQ.M -
soil & manure
-
Sub total- Earth work- Stripping/Excavation/Filling -
NOTE: -
The quantity of red earth for filling shall be a separete item as
indicated ebove, and the value for the same shall not be
repeated in the rate of the trees, specimen shrubs, small and -
medium shrubs, ground cover, climbers amd lawn.
-
About 20% of the soil filling quantity shall be deducted towards
narural compaction of soil within planters and planting beds- for -
the purpose of bill certification.
178 of 211
PHASE 3 D - LANDSCAPE & IRRIGATION WORKS 3D Quantity

Up To Previous
Sr. No. PARTICULARS UNIT Quantity Rate Amount This Bill
Bill

-
B Lawn (including planting media) -
Garden soil is to be spread on garden upto a depth of 75mm
and mixed with manure to attain a total depth of 100mm to form
the final garden surface. Surface preparation is by raking and
mixing to attain a smooth finished surface and planted with
rooted slips of the specified grass spices. Rate to include
supply of grass species, labour charges for mixing soil media in
the desired proportion,planting of grass and maitaince for a
period of 6 months from the date of planting.Rate shall include
-
supply of neem cakes and all other additives as mentioned
praportion and supply of material for top dressing (seived soil
and manure to achive the final finish) (Diblling with american
blue lawn c-c 3" & two top dressing to achive the final finished )

5.4 AMERICAN BLUE LAWN SQ.M 200 145.95 29,190.00 200.000 -


5.5 KORIAN CARPET LAWN SQ.M 285 194.60 55,461.00
-
Supply and planting of trees of the specified ht. and crown
-

C Common trees -
Pits of size 900x900x900mm filled with 50% of mother earth
and balance 50% filled with a mixture of garden soil and
manure in the ratio of 3:1:1 Rate to include supply of healthy
trees as per the specs,labour charges for pitting mixing soil
media,filing the pits with soil media,planting the tree and
maintaince for a period of 6 months from the date of -
planting.Rate does not includes (supply of garden soil has been
covered under item no A3 and shall not be repeated here)

-
179 of 211
PHASE 3 D - LANDSCAPE & IRRIGATION WORKS 3D Quantity

Up To Previous
Sr. No. PARTICULARS UNIT Quantity Rate Amount This Bill
Bill

NAMES- TREES (8 ft height bushy 4-5 branches,3" girth)


-

5.6 BAUHINIA PURPUREA(10' BUSHY) nos 2 1,751.40 3,502.80 2.000 -


5.7 ALSTONIA SCHOLARIS(10' BUSHY) nos 29 1,751.40 50,790.60 11.000 -
5.8 CASSIA FISTULA nos 14 1,946.00 27,244.00 14.000 -
5.9 CHRISTMAS TREE nos 1 1,946.00 1,946.00 1.000 -
5.1 PLUMERIA RUBRA DWARF nos 52 1,946.00 101,192.00 52.000 -
5.11 TABEBUIA ROSEA nos 17 1,508.15 25,638.55 17.000 -
5.12 PLUMERIA CARACASANA nos 12 1,751.40 21,016.80 9.000 -
5.13 PLUMERIA ALBA nos 4 1,751.40 7,005.60 0.000 -
LAGESTROMEA FLOSREGINEA -
TOTAL NO. OF TREES nos 131 - -
-
NAMES- CLIMBERS AND CREEPERS -
1 IPOMEA HORSEAFOLLIAE THUNBERGIA ALBA/ LAURIFOLIA nos -
2 CURTAIN CREEPER nos -
-
Sub Total for all climbers & creepers -
-
NAMES- CLIMBERS AND CREEPERS -
5.14 Bougainvillea nos 52 145.95 7,589.40 0.000 -
-
-
Supply and planting of tall shrubs -

180 of 211
PHASE 3 D - LANDSCAPE & IRRIGATION WORKS 3D Quantity

Up To Previous
Sr. No. PARTICULARS UNIT Quantity Rate Amount This Bill
Bill

D Pits of size 450x450x450mm filled with 50% of mother earth


and balance 50% filled with a mixture of garden soil and
manure in the ratio of 3:1:1 Rate to include supply of healthy
shrub species min 3'0" - 4'0"high, labour charges for pitting
mixing soil media,filing the pits with soil media,planting the
sapling and maintaince for a period of 3 months from -
planting.Rate does not includes (Supply of garden soil has been
covered under item no A3 and shall not be repeated here)

-
5.15 THEVETIA NERIFOLIUM (6-8 ft height BUSHY) nos 71 145.95 10,362.45 71.000 -
-
Sub Total for tall shrubs nos 71 - -
-
Medium Shrubs and Small shrubs -
E Pits of size 375x375x375mm filled with 50% of mother earth
and balance 50% filled with a mixture of garden soil and
manure in the ratio of 3:1:1 Rate to include supply of healthy
shrub species min 1'-6" high, labour charges for pitting mixing
soil media,filing the pits with soil media,planting the sapling and
maintaince for a period of 3 months from planting.Rate does not -
includes (Supply of garden soil has been covered under item no
A3 and shall not be repeated here)

-
E.a Supply and planting of common Medium and Small shrubs
(1-2 ft height) -

5.16 LANTANA WHITE( 6" HEIGHT) nos 487 58.38 28,431.06 448.000 -
5.17 LANTANA MAUVE(9" BUSHY) nos 626 58.38 36,545.88 446.000 -
5.18 MINI HAMELIA PATENS nos 220 68.11 14,984.20 220.000 -
5.19 MINI ALLAMANDA NERIFOLIA nos 829 68.11 56,463.19 741.000 -
5.2 ASPARAGUS SPRINGERI nos 1960 58.38 114,424.80 1491.000 -
181 of 211
PHASE 3 D - LANDSCAPE & IRRIGATION WORKS 3D Quantity

Up To Previous
Sr. No. PARTICULARS UNIT Quantity Rate Amount This Bill
Bill

5.21 MINI NERIUM OLEANDER(2' BUSHY) nos 1430 58.38 83,483.40 1430.000 -
5.22 MINI BOUGAINVILLEA nos 123 82.70 10,172.10 123.000 -
5.23 VARIGATED CANNA nos 287 68.11 19,547.57 287.000 -
5.24 TAGAR nos 102 82.70 8,435.40 0.000 30.000
5.25 GALPHIMIA GLAUCA(3' BUSHY) nos 834 68.11 56,803.74 247.000 -
5.26 MINI TAGAR nos 466 82.70 38,538.20 452.000 14.000
5.27 RHOEO nos 243 82.70 20,096.10 243.000 -
5.28 MINI HIBISCUS nos 176 68.11 11,987.36 99.000 -
5.29 FICUS BLAKIYANA nos 6 97.30 583.80 0.000 -
5.3 VARIGATED FICUS nos 134 160.54 21,512.36 0.000 -
5.31 RAPHIS PALM nos 28 267.57 7,491.96 0.000 28.000
5.32 ARECA PALM nos 20 214.06 4,281.20 0.000 12.000
5.33 DRACENA MAHATMA nos 66 160.54 10,595.64 0.000 -
5.34 VARIGATED TAGAR nos 88 87.57 7,706.16 0.000 -
5.35 DWARF HELICONIA nos 88 87.57 7,706.16 0.000 88.000
5.36 RUSSELIA RED nos 46 68.11 3,133.06 0.000 -
6 ASPARAGUS MEYERII nos -
8 WEDELIA TRILOBATA nos 38.92 -
SPIDER LILY nos -
TABERNAEMONTANA CORONAREA nos -
HYBRID HIBISCUS nos -
PLUMBAGO nos -
ALPINIA nos -
CUPHEA PINK nos -
GOLDEN BAMBOO nos -
GOLDEN FICUS nos -
MINI ALAMANDA nos -
MURRAYA EXOTICA nos -
LAGESTROMIA INDICA nos -
IXORA nos -
VARIGATED LANTANA nos -
RED CANNA nos -
182 of 211
PHASE 3 D - LANDSCAPE & IRRIGATION WORKS 3D Quantity

Up To Previous
Sr. No. PARTICULARS UNIT Quantity Rate Amount This Bill
Bill

CYCAS PALM nos -


RAPHIS PALM nos -
-
Sub-total nos 8259 - -
-
-
-
5.37 Irrigation System for phase 3D design and build as per approval
from the project manager LS 1 379,470.00 379,470.00 0.700 0.215

TOTAL 2,009,068.92

2,009,068.92

208,027.40

183 of 211
ity Amount

Up To
Up To Date This Bill Up To Date Amendm Amendment
Previous Bill
ent Qty Amount Final Amount

390.00 113,841.00 - 113,841.00


337.53 98,526.31 212,367.31 -

236.83 80,650.99 - 80,650.99


-0.00 -0.53 80,650.46 -640.67

228.71 122,394.97 - 122,394.97

0.00 0.50 122,395.47 -356.29


- -
- - - -
- - - - - -
- - - - - -
- - - - - -

- -
- - - -
- - - - - -

- -
- - - -
184 of 211
ity Amount

Up To
Up To Date This Bill Up To Date Amendm Amendment
Previous Bill
ent Qty Amount Final Amount
- - - - - -
- - - - - -

- -

- - - -
200.00 29,190.00 - 29,190.00 277.48 40,497.59 69,687.59 -
- - - - - -285.00
- - - - - -

- -
- - - -
- - - - - -

- -

- - - -
- - - - - -
185 of 211
ity Amount

Up To
Up To Date This Bill Up To Date Amendm Amendment
Previous Bill
ent Qty Amount Final Amount

- -
- - - -
2.00 3,502.80 - 3,502.80 - - 3,502.80 -
11.00 19,265.40 - 19,265.40 - - 19,265.40 -18.00
14.00 27,244.00 - 27,244.00 - - 27,244.00 -
1.00 1,946.00 - 1,946.00 1.00 1,946.00 3,892.00 -
52.00 101,192.00 - 101,192.00 3.00 5,838.00 107,030.00 -
17.00 25,638.55 - 25,638.55 - - 25,638.55 -
9.00 15,762.60 - 15,762.60 - - 15,762.60 -3.00
- - - - - - - -4.00
- - - - - -
- - - - - -131.00
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - - -52.00
- - - - - -
- - - - - -
- - - - - -

186 of 211
ity Amount

Up To
Up To Date This Bill Up To Date Amendm Amendment
Previous Bill
ent Qty Amount Final Amount

- -

- - - -
- - - - - -
71.00 10,362.45 - 10,362.45 - - 10,362.45 -
- - - - - -
- - - - - -71.00
- - - - - -
- - - - - -

- -

- - - -
- - - - - -

- -
- - - -
448.00 26,154.24 - 26,154.24 - - 26,154.24 -39.00
446.00 26,037.48 - 26,037.48 - - 26,037.48 -180.00
220.00 14,984.20 - 14,984.20 50.00 3,405.50 18,389.70 -
741.00 50,469.51 - 50,469.51 - - 50,469.51 -88.00
1,491.00 87,044.58 - 87,044.58 - - 87,044.58 -469.00
187 of 211
ity Amount

Up To
Up To Date This Bill Up To Date Amendm Amendment
Previous Bill
ent Qty Amount Final Amount
1,430.00 83,483.40 - 83,483.40 341.00 19,907.58 103,390.98 -
123.00 10,172.10 - 10,172.10 394.00 32,583.80 42,755.90 -
287.00 19,547.57 - 19,547.57 159.00 10,829.49 30,377.06 -
30.00 - 2,481.00 2,481.00 - - 2,481.00 -72.00
247.00 16,823.17 - 16,823.17 - - 16,823.17 -587.00
466.00 37,380.40 1,157.80 38,538.20 144.00 11,908.80 50,447.00 -
243.00 20,096.10 - 20,096.10 181.00 14,968.70 35,064.80 -
99.00 6,742.89 - 6,742.89 - - 6,742.89 -77.00
- - - - - - - -6.00
- - - - - - - -134.00
28.00 - 7,491.96 7,491.96 112.00 29,967.84 37,459.80 -
12.00 - 2,568.72 2,568.72 - - 2,568.72 -8.00
- - - - - - - -66.00
- - - - - - - -88.00
88.00 - 7,706.16 7,706.16 411.00 35,991.27 43,697.43 -
- - - - - - - -46.00
- - - - - -
- - - 593.00 23,079.56 23,079.56 -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
188 of 211
ity Amount

Up To
Up To Date This Bill Up To Date Amendm Amendment
Previous Bill
ent Qty Amount Final Amount
- - - - - - -
- - - - - - -
- - - - - -
- - - - -
- - - - - -
- - - - - -
- - - - - -
0.92 265,629.00 81,586.05 347,215.05
0.00 155.68 347,370.73 -0.08

1,215,555.40 102,991.69 1,318,547.09 329,606.10 1,648,153.19


1139268.74953
76,286.65 -
21,405.64
5199.36
1702.81 7427
29190 2227.64
233520

189 of 211
Client : PSP Projects Ltd.

PROJECT - GODREJ GARDEN CITY


Contractor Name-Green Gold Garden & Agro Consultancy

Sub : Belvador (Phase-3D) Summery sheet for plantat

BILLABLE To be
SR.NO PARTICULARS Unit QUANTI Total Claime
RA-05 Qty,
TY Ra-
Total 2+3+4+ d in
Qty. this bill
5 RA-5
NAMES- TREES (8 ft height bushy 4-5
branches,3" girth) BBi BY BW BL1 BM1 BV1 BW1 BX2 BY2
1 BAUHINIA PURPUREA(10' BUSHY) nos 2 0 2 0
2 ALSTONIA SCHOLARIS(10' BUSHY) nos 29 1 1 11 1
3 CASSIA FISTULA nos 14 4 4 8 14 8
4 CHRISTMAS TREE nos 1 1 1 2 1
5 PLUMERIA RUBRA DWARF nos 52 0 55 0
6 TABEBUIA ROSEA nos 17 0 17 0
7 PLUMERIA CARACASANA nos 12 0 9 0
8 PLUMERIA ALBA nos 4 0 0 0
0 0 0
NAMES- CLIMBERS AND CREEPERS 0 0 0
1 Bougainvillea nos 52 0 0 0
0 0 0
Supply and planting of tall shrubs 0 0 0
D Pits of size 450x450x450mm filled with 0 0 0
50% of mother earth and balance 50%
filled with a mixture of garden soil and 0 0 0
1 THEVETIA
manure in NERIFOLIUM (6-8 Rate
the ratio of 3:1:1 ft height
to include nos 71 9 9 71 9
BUSHY)
supply of healthy shrub species min 3'0" -
4'0"high, labour charges for pitting mixing 0 0 0
Medium
soil Shrubs the
media,filing andpits
Small shrubs
with soil 0 0 0
E media,planting the sapling and
Pits of size 375x375x375mm filled maintaince
with
for 0 0 0
50%a of
period of 3earth
mother monthsandfrom planting.Rate
balance 50%
does not includes (Supply of garden
filled with a mixture of garden soil and soil has 0 0 0
been
manure covered
in theunder item
ratio of noRate
3:1:1 A3 and shall
to include
not be repeated here)
supply of healthy shrub species min 1'-6"
high, labour charges for pitting mixing soil 190 of211
media,filing the pits with soil
media,planting the sapling and maintaince
for a period of 3 months from planting.Rate
Client : PSP Projects Ltd.

PROJECT - GODREJ GARDEN CITY


Contractor Name-Green Gold Garden & Agro Consultancy

Sub : Belvador (Phase-3D) Summery sheet for plantat

BILLABLE To be
SR.NO PARTICULARS Unit QUANTI Total Claime
RA-05 Qty,
TY Ra-
Total 2+3+4+ d in
Qty. this bill
5 RA-5
NAMES- TREES (8 ft height bushy 4-5
branches,3" girth) BBi BY BW BL1 BM1 BV1 BW1 BX2 BY2
E.a Supply and planting of common Medium 0 0 0
1 and SmallWHITE(
LANTANA shrubs (1-2 f height)
6" HEIGHT) nos 487 25 77 51 153 448 153
2 LANTANA MAUVE(9" BUSHY) nos 626 25 77 50 152 446 152
3 MINI HAMELIA PATENS nos 220 143 143 270 93
4 MINI ALLAMANDA NERIFOLIA nos 829 0 741 0
5 ASPARAGUS SPRINGERI nos 1,960 26 26 1491 26
6 MINI NERIUM OLEANDER(2' BUSHY) nos 1,430 164 62 119 108 453 1771 112
7 MINI BOUGAINVILLEA nos 123 12 12 517 0
8 VARIGATED CANNA nos 287 75 219 294 446 91
9 TAGAR nos 102 0 0 0
10 GALPHIMIA GLAUCA(3' BUSHY) nos 834 0 247 0
11 MINI TAGAR nos 466 0 452 0
12 RHOEO nos 243 202 202 424 21
13 MINI HIBISCUS nos 176 0 99 0
14 FICUS BLAKIYANA nos 6 0 0 0
15 VARIGATED FICUS nos 134 0 0 0
16 RAPHIS PALM nos 28 0 0 0
17 ARECA PALM nos 20 0 0 0
18 DRACENA MAHATMA nos 66 0 0 0

191 of211
Client : PSP Projects Ltd.

PROJECT - GODREJ GARDEN CITY


Contractor Name-Green Gold Garden & Agro Consultancy

Sub : Belvador (Phase-3D) Summery sheet for plantat

BILLABLE To be
SR.NO PARTICULARS Unit QUANTI Total Claime
RA-05 Qty,
TY Ra-
Total 2+3+4+ d in
Qty. this bill
5 RA-5
NAMES- TREES (8 ft height bushy 4-5
branches,3" girth) BBi BY BW BL1 BM1 BV1 BW1 BX2 BY2
19 VARIGATED TAGAR nos 88 0 0 0
20 DWARF HELICONIA nos 88 0 0 0
21 RUSSELIA RED nos 46 0 0 0
8,259 1454 7533 667
Total 8513.00 71 26 5 164 62 119 187 373 447 1454

192 of211
Measurement Sheet
Belveder Area Civil Work
Sr No. Particular Unit No. L B H Qty. Remarks

By removal of clods, building debbris, dirt etc. and carting of debris out of the site, to provide a clean surface
5.1
to dump soil for grading works etc. complete

R.A.-04

Debris Removing from D block Cum 1 840.48 0.449 377.281

Debris Removing from B block Cum 1 835.21 0.419 350.254


Total Qty 727.53
BOQ Quantity 390.00
Previously Certified Qty 390.00
This Bill Qty.
Amendment Qty. 337.53
Phase-D Belvador
PROJECT - GODREJ GARDEN CITY

Sub : Black Cottan Soil Qty sheet for belvador area (Phase-3D)

Sr. No. Area Code Area Sq. Mt. Av. Hight (m) Qty.(M3)
1 BB 28.60 0.527 15.07
2 BF2 10.45 1.043 10.90
R.A.-06
BY,BA1,BG1,BJ1 112.12 0.301 33.75
BM1,BL1,BV1,BW1 331.35 0.245 81.18
BK1 201.21 0.338 68.01
BO1,BP1,BQ1,BR1 92.74 0.301 27.91
BA,BC,BF,BE1,BN1,B
Z1 168.84 0.00
Total 236.82
BOQ 878
Up to Previous 25.97
This Bill Qty. 210.85
Client : PSP Projects pvt. Ltd.
Phase-D Belvador
PROJECT - GODREJ GARDEN CITY
Contractor Name-Green Gold Garden & Agro Consultancy

Sub : Soil Mix Qty sheet for belvador area (Phase-3D)

Sr. No. Area Code Area Sq. Mt. Av. Hight (m) Qty.(M3)
1 BB 28.60 0.15 4.29
2 BD 22.66 0.39 8.84
3 BE 7.91 0.39 3.08
4 BG 18.49 0.382 7.06
5 BI1 35.12 0.38 13.35
6 BE2 23.68 0.388 9.19
7 BF2 10.45 0.15 1.57
8 BN2 16.28 0.272 4.43
R.A.-05
BY,BA1,BG1,BJ1 112.12 0.15 16.82
BM1,BL1,BV1,BW1 331.35 0.15 49.70
BK1 201.21 0.15 30.18
BO1,BP1,BQ1,BR1 92.74 0.15 13.91
BA,BC,BF,BE1,BN1,BZ1 168.84 0.15 25.33
R.A.-06
BW 33.46 0.15 5.02
BF2 3.10 0.48 1.49
BY1 grass paver 11.46 0.15 1.72
R.A.-07
BBi 6.96 0.15 1.04
BX2 38.92 0.15 5.84
BY2 34.57 0.15 5.19
BH 2.74 0.15 0.41
BI 0.30 0.15 0.05
BJ 1.10 0.15 0.17
BK 0.54 0.15 0.08
BL 1.88 0.15 0.28
BM 3.57 0.15 0.54
BN 0.54 0.15 0.08
BO 1.10 0.15 0.17
BP 0.30 0.15 0.05
BQ 2.74 0.15 0.41
BR 0.30 0.15 0.05
BS 0.30 0.15 0.05
BT 21.24 0.15 3.19
BU 0.54 0.15 0.08
BV 1.10 0.15 0.17
BX 0.30 0.15 0.05
BZ 2.74 0.15 0.41
BB1 0.30 0.15 0.05
BC1 0.58 0.15 0.09
BD1 12.59 0.15 1.89
BF1 0.57 0.15 0.09
BH1 0.30 0.15 0.05
BS1 0.30 0.15 0.05
BT1 0.57 0.15 0.09
BU1 12.61 0.15 1.89
BA2 21.24 0.15 3.19
BB2 0.57 0.15 0.09
BC2 0.30 0.15 0.05
BD2 2.74 0.15 0.41
BG2 0.30 0.15 0.05
BH2 1.10 0.15 0.17
BI2 0.54 0.15 0.08
BJ2 3.57 0.15 0.54
BK2 1.88 0.15 0.28
BL2 0.54 0.15 0.08
BM2 1.10 0.15 0.17
BO2 0.30 0.15 0.05
BP2 2.74 0.15 0.41
BQ2 0.57 0.15 0.09
BR2 0.30 0.15 0.05
BS2 2.74 0.15 0.41
BT2 0.30 0.15 0.05
BU2 1.10 0.15 0.17
BV2 0.54 0.15 0.08
BZ2, Bwi,Bwii 26.22 0.15 3.93

Total 228.71
BOQ 585.00
Up to Previous 228.71
This Bill Qty 0.00
Client : PSP Projects pvt. Ltd.
Date: 14/04/2016
PROJECT - GODREJ GARDEN CITY
Contractor Name-Green Gold Garden & Agro Consultancy

Sub : Measurmentsheet for American Blue Lawn at Belvador Site.

Sr. No. Description Area Code Area Sq. Mt.


1 BK1 201.21
2 BO1 46.7
3 BP1 23.05
4 GRASS PAVER BA,BC,BF,BE1,BN1,BZ1 168.84
R.A.-06
GRASS PAVER BY1 11.46
R.A.-08
Bz2 BZ2 23.85
BWI 16.24
Bwii 44.50
84.59
26.22
Total 477.48
BOQ 200.000
Up to Previous 200.000
this bill 0.000
Cumulative Qty 200.000
Amendment 277.476
877.5
51.8

210.8572
Client : PSP Projects pvt. Ltd.

PROJECT - GODREJ GARDEN CITY


Contractor Name-Green Gold Garden & Agro Consultancy

Sub : Belvador (Phase-3D) Summery sheet for

BILLABLE
SR.NO PARTICULARS Unit QUANTI RA-02 Bill Plantation Qty. RA-03 Bill Plantation Qty.
TY

NAMES- TREES (8 ft height bushy 4-5


branches,3" girth) BB BD BE BG BI1 BE2 BF2 BN2 BY+BA1 BG1 BJ1 BK1
1 BAUHINIA PURPUREA(10' BUSHY) nos 2 2
2 ALSTONIA SCHOLARIS(10' BUSHY) nos 29 5 2
3 CASSIA FISTULA nos 14
4 CHRISTMAS TREE nos 1 1
5 PLUMERIA RUBRA DWARF nos 52
6 TABEBUIA ROSEA nos 17 9
7 PLUMERIA CARACASANA nos 12 9
8 PLUMERIA ALBA nos 4

NAMES- CLIMBERS AND CREEPERS


1 Bougainvillea nos 52

Supply and planting of tall shrubs


D Pits of size 450x450x450mm filled with
50% of mother earth and balance 50%
filled with a mixture of garden soil and
1 THEVETIA
manure in NERIFOLIUM (6-8 Rate
the ratio of 3:1:1 ft height
to include nos 71 62
BUSHY)
supply of healthy shrub species min 3'0" -
4'0"high, labour charges for pitting mixing
Medium
soil Shrubs the
media,filing andpits
Small shrubs
with soil
E media,planting the sapling and
Pits of size 375x375x375mm filled maintaince
with
for
50%a of
period of 3earth
mother monthsandfrom planting.Rate
balance 50%
does not includes (Supply of garden
filled with a mixture of garden soil and soil has
been
manure covered
in theunder item
ratio of noRate
3:1:1 A3 and shall
to include
not be repeated here)
supply of healthy shrub species min 1'-6"
high, labour charges for pitting mixing soil
media,filing the pits with soil
media,planting the sapling and maintaince
for a period of 3 months from planting.Rate
E.a Supply and planting of common Medium
and SmallWHITE(
shrubs (1-2 f height)
1 LANTANA 6" HEIGHT) nos 487 99 20 15 51 42
2 LANTANA MAUVE(9" BUSHY) nos 626 99 20 15 51 42
3 MINI HAMELIA PATENS 127
nos 220
4 MINI ALLAMANDA NERIFOLIA nos 829 454 102 101
5 ASPARAGUS SPRINGERI nos 1,960 144 112 435 61
6 MINI NERIUM OLEANDER(2' BUSHY) nos 1,430 57
7 MINI BOUGAINVILLEA nos 123 124 26
8 VARIGATED CANNA nos 287 96 56
9 TAGAR nos 102
10 GALPHIMIA GLAUCA(3' BUSHY) nos 834 81 113
11 MINI TAGAR nos 466 127 74
12 RHOEO nos 243 222
13 MINI HIBISCUS nos 176 44 55
14 FICUS BLAKIYANA nos 6
15
VARIGATED FICUS nos 134
16 RAPHIS PALM
nos 28
17 ARECA PALM
nos 20
18 DRACENA MAHATMA
nos 66
19 VARIGATED TAGAR
nos 88
20 DWARF HELICONIA/Spider Lilly
nos 88
21 RUSSELIA RED
nos 46
22 WEDELIA TRILOBATA
nos -
8,259
Total 8513.00 384 167 56 240 286 307 113 223 898 234 238 9
RA-03 Bill Plantation Qty. RA-04 Bill Plantation Qty. RA-05 Bill Plantation Qty.

BL1+BM BQ1 BR1 BV1 BW BW1 BF2i BBi BY BW BL1 BM1 BV1 BW1 BX2 BY2 BH BI BJ BK BL BM
1

3 1
3 3 4 4
1
30 15 10
7 1

9
68 25 77 51
67 25 77 50
143
84
432 213 68 26
710 39 391 121 164 62 119 108
355 12
75 219
5 10
53
90 22 68 38 33 5 9
202

9
1

15 15

31 5 18 10

1275 62 152 622 528 232 53 71 26 5 164 62 119 187 373 447 40 5 19 10 25 34
RA-06 Bill Plantation Qty. K & L Biulding

BN BO BP BQ BR BS BT BU BV BX BZ BB1 BC1 BD1 BF1 BH1 BS1 BT1 BU1 BQ2 BR2 BS2 BT2 BU2 BV2 BA2 BB2 BC2 BD2
48 17 17 48

9 20 9 23 23 9 20 9
1 1 1 1 1 1 1 1 1

112 74 74 74 112

10 18 5 31 5 6 47 10 24 5 31 5 6 21 6 5 5 6 21 6 6 31 5 18 10 47 6 5 31

10 19 5 40 5 7 227 10 25 5 40 5 7 135 7 5 5 7 135 81 6 40 5 19 10 227 7 5 40


Total
Qty.
Privious
Up to Qty.
R.A.-
09
BG2 BH2 BI2 BJ2 BK2 BL2 BM2 BO2 BP2 This Bill Amendment Up Todate Qty for this bill after deducting amendment
Qty.
2 2 0 0 2 2
11 11 0 11 11
14 14 0 0 14 14
2 2 0 1 1 1
55 55 0 3 52 52
17 17 0 0 17 17
9 9 0 9 9
0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
71 71 0 0 71 71
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
448 448 0 448 448
446 446 0 446 446
270 270 0 50 220 170
741 741 0 741 741
1491 1491 0 1491 1491
1771 1771 0 341 1430 1089
517 517 0 394 123 -271
446 446 0 159 287 128
10 5 30 0 30 30 30
247 247 0 247 247
9 5 610 452 158 144 466 322
424 424 0 181 243 62
99 99 0 99 99
0 0 0 0 0
0 0 0 0 0
9 140 0 140 112 28 -84
1 1 12 0 12 12 12
0 0 0 0 0
0 0 0 0 0
15 8 499 0 499 411 88 -323
0 0 0 0 0
5 18 10 10 18 5 31 593 0 593 593 0 -593
8965 7533 1432
5 19 10 34 18 10 19 5 40 8965
Client : PSP Projects pvt. Ltd. Date: 14/04/2016
Phase-3D-Belvador
PROJECT - GODREJ GARDEN CITY
Contractor Name-Green Gold Garden & Agro Consultancy

Sub : Total Paver Block Area Measurmentsheet of Soil Mix

Sr. No. Description Area Code Area Sq. Mt.


1 BA 69.17
2 BC 87.43
3 BF 86.21
4 BE1 113.80
5 BN1 126.20
6 BZ1 61.82
R.A.-06
BY1 36.96
Total Paver Block area (A) 581.59
Soil Mix Filling area @ 31% of (A) (M2) 180.29
Area
5 Shrub bed At Block B (BG) Smt 18.49 18.49
32 Shrubbed Near RWH Tank (BI1) Smt 35.12 35.12
56 Shrubbed Near D Block ( BN2) Smt 16.28 16.28
47 Shrubbed near Borewell (BE2) Smt 23.68 23.68
BB Smt 28.6 28.6
BD Smt 22.66 22.66
BE Smt 7.91 7.91
Bei Smt 4.52 4.52
BH Smt 2.74 2.74
B1 Smt 0.3 0.3
BJ Smt 1.1 1.1
BK Smt 0.54 0.54
BL Smt 1.88 1.88
BM Smt 3.57 3.57
BN Smt 0.54 0.54
BO Smt 1.1 1.1
BP Smt 0.3 0.3
BQ Smt 2.74 2.74
BR Smt 0.3 0.3
BS Smt 0.3 0.3
BT Smt 21.74 21.74
BU Smt 0.54 0.54
BV Smt 1.1 1.1
BW Smt 33.46 33.46
BX Smt 0.3 0.3
BY Smt 12.73 12.73
BZ Smt 2.74 2.74
BA1 Smt 56.41 56.41
BB1 Smt 0.3 0.3
BC1 Smt 0.58 0.58
BD1 Smt 12.59 12.59
BF1 Smt 0.57 0.57
BG1 Smt 25.41 25.41
BH1 Smt 0.3 0.3
BJ1 Smt 17.46 17.46
BK1 Smt 201.21 201.21
BL1 Smt 111.5 111.5
BM1 Smt 75.36 75.36
BQ1 Smt 6.28 6.28
BR1 Smt 8.2 8.2
BS1 Smt 0.3 0.3
BT1 Smt 0.57 0.57
BU1 Smt 12.61 12.61
BV1 Smt 96.5 96.5
BA2 Smt 21.24 21.24
BB2 Smt 0.57 0.57
BC2 Smt 0.3 0.3
BD2 Smt 2.74 2.74
BF2 Smt 13.55 13.55
BG2 Smt 0.3 0.3
BH2 Smt 0.1 0.1
BI2 Smt 0.54 0.54
BJ2 Smt 3.57 3.57
BK2 Smt 1.88 1.88
BL2 Smt 0.54 0.54
BM2 Smt 1.1 1.1
BO2 Smt 0.3 0.3
BP2 Smt 2.74 2.74
Grassing Area BK1 Smt 201.21 201.21
Grassing Area BO1 Smt 46.7 46.7
Grassing Area BP1 Smt 23.05 23.05
Grassing Area BX1 Smt 11.6 11.6
Grass Paver Area
Area behind B Block Smt 581.59 180.2929
1785.05 1383.753

BOQ Area 1950


0.915
0.215 0.91541
379470
347370.7
0.709617
379470
269278.3
Belvedare Ramp JMR
Block B Block D
Sr No. L B H Qty. Sr No. L B H Qty.
1 2.58 0.94 0.075 0.18189 1 2.44 0.9 0.075 0.1647
2 2.45 0.94 0.075 0.172725 2 2.9 0.9 0.075 0.19575
3 2.1 1.36 0.075 0.2142 3 3.45 1.56 0.075 0.40365
4 2.66 1.36 0.075 0.27132 4 2.83 1.56 0.075 0.33111
5 2.66 1.3 0.075 0.25935 5 2.7 1.3 0.075 0.26325
6 2.2 1.3 0.075 0.2145 6 2.1 1.3 0.075 0.20475
7 2.4 1 0.075 0.18 7 2.47 1.875 0.075 0.347344
8 2.6 1 0.075 0.195 8 2.94 1.875 0.075 0.413438
9 3.4 1.5 0.075 0.3825 9 3.42 1.55 0.075 0.397575
10 2.8 1.5 0.075 0.315 10 2.86 1.55 0.075 0.332475
11 3.3 2.6 0.075 0.6435 11 3.4 2.8 0.075 0.714
12 3.4 2.6 0.075 0.663 12 2.35 2.7 0.075 0.475875
13 2.8 1.5 0.075 0.315 13 2.9 1.55 0.075 0.337125
14 3.5 1.5 0.075 0.39375 14 1.4 1.55 0.075 0.16275
15 2.6 1 0.075 0.195 15 2.95 1 0.075 0.22125
16 2.44 1 0.075 0.183 16 2.47 1 0.075 0.18525
17 2.1 1.3 0.075 0.20475 17 2 1.3 0.075 0.195
18 2.65 1.5 0.075 0.298125 18 2.65 1.3 0.075 0.258375
19 2.4 2.4 0.075 0.432 19 2.65 1.4 0.075 0.27825
20 2.8 1.5 0.075 0.315 20 2.1 1.4 0.075 0.2205
21 3.35 1.5 0.075 0.376875 6.102416
6.406485

Total Concrete = 12.5089

Vous aimerez peut-être aussi