Vous êtes sur la page 1sur 3

Enhancing Offshore Coiled-Tubing

Interventions in Difficult Weather Conditions

A n operator requiring an offshore


coiled-tubing (CT) intervention
offshore Brunei in the South China Sea
compensated gangway. These limita-
tions made safe operation impossible
during monsoon season. Once the oper-
sel to maintain position and remain on
station at a safe distance adjacent to a
platform while performing intervention
encountered challenging monsoon ating rate was deemed limited, stimula- operations. Typically, a DP footprint ex-
weather conditions as well as tion (acidizing) activity was postponed, isted of the distance the vessel operated
limited and aging offshore facilities. thus affecting production results. How- from within a central axis. Each DP ves-
Innovative technologies from various ever, with new concepts of intervention, sel had referencing systems, depend-
applications, including a full-catenary the vessel was able to continue operating ing on the operator or end-user require-
CT system, a dynamic-positioning during rough sea conditions safely and ments. The vessel discussed in this work
(DP) vessel, a knuckle-boom crane, more efficiently. had three referencing systems to pro-
and a heave-compensated gangway, vide a redundancy so that the DP-­system
were combined to provide the New-Concept computer could ascertain the vessel’s
operator with a successful solution for Stimulation Vessel exact location as well as the magnitude
CT-intervention improvement. DP Vessel. The well-intervention/ and direction of environmental forces
stimulation vessel was newly built; it was affecting its position. If changes in posi-
equipped with a DP Class 2 system, which tion were detected by the computer on
Introduction included antiroll tanks and a computer- the basis of the parameters provided by
Operations were performed in the Da- ized ballast-control system. This vessel the referencing system, the DP comput-
russalam offshore waterflood oil field. was designed to operate year-round in er provided automatic command signals
The field’s average sea depth was ap- typical seasonal weather of southeast- to the propulsion systems to increase or
proximately 30 m of water, and the field ern Asian waters. In the coastal waters decrease thrust and direction heading
was approximately 70 km northeast of off Borneo Island, typically in Brunei of the thrusters (in the case of azimuth
Seria. A central field complex had living Darussalam, the significant wave height thrusters) until the desired set location
quarters for approximately 160 person- during the monsoon period from No- or direction was achieved. This was per-
nel, gas lift and compression facilities, vember to February was approximate- formed without operator intervention,
and water-injection facilities. Water- ly 3.5 m. During the remainder of the although a DP operator was fully aware
flooding was a significant factor sup- year, wave height was between 0.5 and of what the system was doing while he or
porting the hydrocarbon-production 2.5 m. However, during the occurrence she monitored the operation.
levels, and, to increase hydrocarbon pro- of storms offshore, the significant wave Another advantage of DP vessels
duction, water-injection improvements height could reach 3.5 to 4.0 m. was that mooring anchors would not
were required. DP vessels were capable of respond- be required to maintain the vessel po-
During monsoon season, the con- ing to dramatically changing weather sition;  this removed the requirement
ventional well-intervention vessel had conditions by helping ensure that the for anchor-handling/towing vessels re-
a limited operating envelope because it DP system interpreted environmental quired to  lay mooring anchors. Gener-
was unable to hold in a rough sea posi- data and allowed the operator to hold ally, DP vessels  were faster and safer
tion and lacked emergency-disconnect or change the vessel’s position accord- when approaching  offshore platforms
CT and hydraulics-hose systems and a ingly. This capability allowed the ves- and well jackets.
The vessel discussed had four DP-
This article, written by JPT Technology Editor Chris Carpenter, contains highlights of referencing systems (each operating on a
paper OTC 24693, “Enhancing the Operational Envelope for Offshore Coiled-Tubing different principle) for helping to ensure
that, should any issues with a particular
Interventions To Be Performed in Monsoon Season,” by Reawat Wattanasuwankorn,
type of referencing system arise, they
Franklin Hammer, and Richard Christieson, Halliburton—Boots & Coots, and
would not negatively affect the rest of
Yan Song and Nick Long, Brunei Shell Petroleum Company, prepared for the 2014 the referencing systems. These systems
Offshore Technology Conference Asia, Kuala Lumpur, 25–28 March. The paper has included a dynamic global-positioning
not been peer reviewed. system, a laser-­scanning system, a high-
precision acoustic-positioning system,
Copyright 2014 Offshore Technology Conference. Reproduced by permission. and a radar-wave location-­determination

The complete paper is available for purchase at OnePetro: www.onepetro.org.

80 JPT • JUNE 2014

CT24693.indd 80 5/15/14 12:35 PM


Fig. 2—ISO lock securing the corner
block to the mounting section, lock
handle, and profile that connects to
the ISO-lock lower mounting section. Fig. 3—The ISO-lock lower mounting
section was welded to the vessel
deck before vessel operation.
Fig. 1—Knuckle-boom crane lifting
CT equipment onto the offshore at all times. The gangway operator then
platform. The knuckle-boom-crane signaled that it was safe for an individ-
design provided better operational ual to cross the gangway. Once all per-
flexibility during the rig-up. sonnel were transferred, the telescop-
ing gangway was retracted and stowed
system. (For detailed descriptions of on the vessel.
each of these systems, please see the Emergency evacuation drills, in-
complete paper.) cluding stretcher cases, were performed
and included in the vessel’s emergency-
Knuckle-Boom Crane. This type of response plans. Fig. 4—ISO lock assembled. ISO
crane was used for lifting the CT equip- blocks were built into all equipment-
ment required on the platform for full- CT and Pumping Unit With Full-­ support frames.
catenary operations (Fig. 1). Catenary System. The stimulation ves-
sel was originally designed to minimize to be positioned between the injector
Auto-Compensated Gangway. This sys- the quantity of CT equipment trans- frame and injector-jacking frame to alle-
tem was a vessel-based, self-­stabilizing ferred onto the production platforms, viate some of the weight from the injec-
platform that actively compensated for allowing work to be performed on small- tor while in transport mode. The lifting
all vessel motion to provide safe off- er platforms with limited deck space, re- frame was removed once the injector was
shore access to the platforms. The sys- ducing rig-up time and lifting hazards, on the platform.
tem helped reduce gangway rig-up time, and avoiding overloading of the platform
eliminate potential hazards from transfer structure. An added safety benefit was Equipment Sea Fastening. On the stim-
by boat, and reduce operating downtime that, because no engine-operated equip- ulation vessel, ISO locks were used to se-
caused by environmental conditions. ment was placed on the platform, a po- cure all equipment to the vessel deck in-
The auto-compensated-gangway tential ignition source was eliminated. stead of using traditional methods such
platform actively compensated wave-­ as chain and boomers or welding equip-
induced motions of the vessel in six de- CT, Nitrogen, and Pumping Equip- ment. Because some of the equipment
grees of freedom by individually actu- ment. A complete set of CT, nitrogen, had the same footprint area, using ISO
ating each of its six hydraulic cylinders. pumping, and acid-blending equipment locks provided more flexibility with re-
Also, a flexible telescoping access bridge was installed on the vessel to provide all spect to equipment placement and chan-
(gangway) was installed on top of the CT with well-intervention capabilities. geout in the event that repairs were re-
auto-compensated gangway platform to To further reduce the number of lifts to quired. The empty raw-acid tanks and
passively compensate for any remaining the platforms, a redesigned lifting frame liquid-nitrogen tanks were easily re-
motion and extend the gangway to the was built that allowed the injector and placed with full tanks between jobs
landing position. injector-jacking frame to be lifted as one using this system. Most of the equip-
To transfer personnel, the gangway unit. The single-lift design saves vessel ment used on the vessel had built-in ISO
was lowered to the vessel deck, and per- deck space. A subbase with International blocks. For equipment without built-in
sonnel were transferred to the gangway Organization for Standardization (ISO) ISO locks, subframes were added. The
platform. The operator then adjusted the locks was added to the injector-jacking ISO lock system consisted of the ISO
gangway platform to the required height frame to secure it to the vessel during blocks, lock, and lower mounting sec-
and pitch and extended the telescoping transport. The subbase ISO locks were tion. The ISO locks worked by installing
gangway to the landing area. The end also the attachment points for the cast- the lock into the lower mounting section
of the telescoping gangway maintained ers used for positioning the injector once welded to the deck. Next, the equipment
a contact force on the landing structure on the platform. A support was designed with ISO blocks was positioned onto the

82 JPT • JUNE 2014

CT24693.indd 82 5/19/14 9:27 AM


lock, and the lever was turned, locking lifted to the platform. Additional flow- control was maintained by means of
the equipment to the deck. The lower- back equipment could be positioned on external barriers, the BOP and Koom-
mounting-section ISO-lock welds  were the platform, depending on the job re- ey system, internal barriers, and the
all magnetic-­particle inspected before quirements. Two video cameras were double-­flapper check valves in the CT
operation of the stimulation vessel. installed on the platform. The display string. Once the conditions allowed the
ISO locks have long been used in the monitor located in the control cabin al- resumption of CT and stimulation activi-
shipping-­container industry and provide lowed the CT operator to observe what ties, the CT could  be rejoined by use of
a safe and secure method of attaching occurred on the platform at all times. An double-ended connectors. All hydraulic
equipment (Figs. 2 through 4). emergency-­disconnect system also ex- hoses could be retrieved and reconnect-
The ISO blocks provided an addi- isted that could be activated if the vessel ed for operations.
tional benefit as an attachment point needed to pull away from the platform
for hydraulic-lift casters when moving during an emergency. Job Results
the lifting frame onto the platform deck. All hoses from the platform were Throughout the 4 months that the
Once the casters were installed, a hy- equipped with recovery slings, which al- vessel was used in the field, 28 acid-­
draulic hand pump was used to raise the lowed quick retrieval so that operation stimulation  and well-intervention
injector-­jacking frame off the deck, al- could be resumed in a short time peri- operations were performed with a
lowing easier movement. od. A Koomey unit was also placed onto 100% operational success rate. The
the platform to operate the safety blow- high-­priority  work on the injection
Full-Catenary System. The system was out preventer (BOP) in the event that wells  helped achieve greater injectivi-
designed so that the CT power pack, an emergency disconnect from the plat- ty than the operator expected. The op-
control cabin, and pumping and mix- form was required. erator has applied the lessons learned
ing equipment remained on the ves- using the enhanced concepts trialed dur-
sel. Only the CT injector, tubing guide, Well Control. Once the CT was cut at ing this work period to a new interven-
and pressure-­control equipment were the reel and the vessel pulled away, well tion vessel. JPT

JPT • JUNE 2014 83

CT24693.indd 83 5/19/14 7:02 AM

Vous aimerez peut-être aussi