Académique Documents
Professionnel Documents
Culture Documents
Project Engineering
User Note:
The requirements of this document are mandatory. Non-compliance shall only be authorised by
the Document Owner or his Delegate through STEP-OUT approval.
A controlled copy of the current version of this document is on PDO's EDMS. Before making
reference to this document, it is the user's responsibility to ensure that any hard copy, or
electronic copy, is current. For assistance, contact the Document Custodian or the Document
Controller.
Users are encouraged to participate in the ongoing improvement of this document by providing
constructive feedback.
1.1 Purpose
This document outlines the minimum requirements for preparation and implementation
of Project Quality Plan (PQP) for all projects within PDO as required by the Project
Engineering Code of Practice CP-117. Reference has been made to the QA requirement
as outlined in the Opportunity and Project Management Guide (OPMG) and DEP
82.00.10.10-Gen. (Project Quality Assurance).
The Quality Plan document shall be kept as compact as possible by briefly summarising
information contained in other documents.
In general, the contents of a typical Project Quality Plan shall consist of the following.
Quality Policy and Objectives
Scope of the Project
Organisation
Quality Assurance of Contracts
Quality Assurance of Design
Document Control
Material Procurement and Control
Construction Quality Assurance
Commissioning and Handover
Change Control and Standards Variance
Audits and Reviews
Page 9 Specification for Project Quality Plan Printed 26/08/06
The controlled version of this CMF Document resides online in LiveLink®. Printed copies are UNCONTROLLED.
Version: 2.0.2
Petroleum Development Oman LLC Effective: Jul-06
3.4 Organisation
The organisation structure and broad organisational responsibilities for quality shall be
illustrated and described. Depending upon the size of the project, the project team shall
be backed up by delegated or corporate QA staff, who shall retain a high degree of
independence and objectivity, reporting directly to the project manager but with a
functional link to the corporate quality organisation.
The organisation shall be designed to ensure that there is single-point accountability, with
clear responsibility / authority, for each activity, and that staff have the required technical
authority and time to complete the work to the required standard.
The PQP shall identify key individuals within the organisation who shall be responsible
for:-
3.8.1 Procurement
The PQP shall include:
the supplier, source of purchase (if different to supplier) for important products,
and the relevant quality assurance requirements that are to be applied
Identification of the specifications that are to be reviewed by the specialist
discipline engineers
methods to be used to select, appraise, evaluate and control Suppliers
requirements for, and reference to, Supplier Quality Plans, where appropriate
methods to be used to satisfy regulatory requirements that apply to purchased
products
means of identifying and ensuring that manufacturer’s ITPs are reviewed and
approved by the Company TA.
II High High Impact on full/part project Key front end Single Loss of <10,000,000
scope (e.g. rotating equipment design document Life >1,000,000
incorrectly specified) errors will have
impact throughout Severe Damage
the project to the
Environment
PEFS/Single line
Diagram
III Moderate Moderate Impact (e.g. control Begins to describe Moderate to <1,000,000
valve ordered with incorrect construction Severe Injury >100,000
flange) method – potential
integrity impact if Minor Damage to
incorrect the Environment
Plot Plan/Piping
Layout
IV Low Low Impact (e.g. Bulk Defines only “how” normally No Injury <100,000
materials incorrectly specified to construct the >10,000
or incorrect quantities on MTO) project Minimum
Damage to the
Isometric or cable Environment
routing drawing
The verification matrix in Appendix 2 shows the default criticality for each deliverable.
The matrix is divided into two parts covering:
the deliverables that have to be reviewed and approved by PDO
and the other deliverables that have been authorised to the design consultant /
contractor for review and approval internally by their discipline engineers.
Approved documents / drawings shall be issued to PDO for information only
according to the discipline areas.
For PDO approved deliverables, the PDO reviewer will be requested to undertake
different levels of review depending on their discipline and the type of deliverable under
review. These actions are described in more detail below, together with their impact on
the overall design process.
For design consultant / contractor internal approved deliverables, discipline engineer
who have been approved for such TA level by PDO will provide input, comments, and
approval as per their discipline area. Other disciplines within the design consultant /
contractor organisation will be copied for either comments or for information. After
internal approval, such documents / drawings will be forwarded to the respective PDO
discipline area, as indicated in the matrix, for information only. However, PDO will
reserve the to alter or reject such deliverables if errors are found or the quality is poor.
Level 1 Corporate Functional Discipline Head. Sets the boundaries wherein the
discipline operates.
Level 2 Experienced Professional. Can handle himself without outside support in
almost all discipline situations.
Level 3 Engineer with specialised but yet incomplete skills in one or more areas of
the discipline.
Refer to SP-2061 – Engineering and Operations technical Authority System for details.
1. Right mouse “Click” on the Matrix above. The following dropdown menu will be
displayed
2. Select “Worksheet Object” and from the following dropdown menu select “Open”
3. The Excel Workbook containing the Design Deliverables Verification Matrix will be
opened.
4. Find the information required:
Find information
Print worksheet or selection
Save Workbook under a different file name for future reference.
Close the Workbook as for any Excel file
CONTRACTOR ETC.)
DESIGN SOURCE
PDO DISCIPLINE
(LDSC, DESIGN
PDO PROJECT
= task = input/output = decision
ENGINEER
ENGINEER
= document
ETL
1 THE DESIGN CONTRACTOR RECEIVES A SCOPE OF WORK FROM 1 1
THE PDO PROJECT ENGINEER AND PREPARES A COST ESTIMATE
WITH FULL DELIVERABLE LISTING AND RETURNS IT TO THE PDO
PROJECT ENGINEER
Note: Refer to SP-1171 – Specification for Quality Assurance of Construction and Engineering
Works for details of similar flowchart for Quality Assurance for procurement, construction, and
commissioning process.
UEV1
Custodian of Document Date: