Harga Sat.

Jumlah Harga Jumlah Harga


No. Uraian Jenis Pekerjaan Sat. Koeff. Bahan / Upah Bahan Upah Bahan + Upah
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8

66 1 BUAH PASANGAN LAMPU TL 2 X 36 WATT


Bahan :
Lampu TL 36 Watt + aksesoris bh 1.0000 250,000.00 250,000.00
Trafo bh 1.0000 138,120.00 138,120.00
Alat Bantu set 0.1000 250,000.00 25,000.00
Tenaga Kerja :
Pekerja Oh 0.0300 99,000.00 2,970.00
Tukang Oh 0.3000 105,000.00 31,500.00
Jumlah 34,470.00 413,120.00 447,590.00
Keuntungan maksimal 10%
Jumlah 447,590.00
Dibulatkan 447,590.00
67 1 BUAH PASANGAN LAMPU SL
Bahan :
Lampu SL Philip 25 Watt bh 1.0000 47,000.00 47,000.00
Fitting Lampu bh 1.0000 17,500.00 17,500.00
Alat Bantu set 0.1000 47,000.00 4,700.00
Tenaga Kerja :
Pekerja Oh 0.0010 99,000.00 99.00
Tukang Oh 0.2000 105,000.00 21,000.00
Jumlah 69,200.00 21,099.00 90,299.00
Keuntungan maksimal 10%
Jumlah 90,299.00
Dibulatkan 90,290.00
68 1 BUAH PASANGAN LAMPU DOWNLIGHT 18 WATT
Bahan :
Lampu DL Philip 18 Watt bh 1.0000 75,000.00 75,000.00
Fitting Lampu bh 1.0000 17,500.00 17,500.00
Alat Bantu set 0.1000 47,000.00 4,700.00
Tenaga Kerja :
Pekerja Oh 0.0010 99,000.00 99.00
Tukang Oh 0.0200 105,000.00 2,100.00
Jumlah 97,200.00 2,199.00 99,399.00
Keuntungan maksimal 10% 9,939.90
Jumlah 109,338.90
Dibulatkan 109,330.00
69 1 UNIT PEMASANGAN MCB 2 A
Bahan :
MCB 2 A, 4 A, 6 A 1 PHASA bh 1.0000 58,281.00 58,281.00
Alat Bantu set 0.0500 60,000.00 3,000.00
Tenaga Kerja :
Pekerja Oh 0.0072 99,000.00 712.80
Mekanik/Teknisi Listrik Oh 0.0072 189,000.00 1,360.80
Mandor Oh 0.0072 157,000.00 1,130.40
Jumlah 61,281.00 3,204.00 64,485.00
Keuntungan maksimal 10% 6,448.50
Jumlah 70,933.50
Dibulatkan 70,930.00
69 1 POHON KRIMINIL
Pohon Kriminil Bh 1.0000 1,500.00 1,500.00
Alat Bantu ls 1.0000 300.00 300.00
Upah Tanam 15% ls 1.0000 270.00 270.00
Jumlah 1,800.00 270.00 2,070.00
Keuntungan maksimal 10% 207.00
Jumlah 2,277.00
Dibulatkan 2,277.00
70 1 POHON LIDAH MERTUA
Pohon Lidah Mertua Bh 1.0000 1,750.00 1,750.00
Alat Bantu ls 1.0000 300.00 300.00
Upah Tanam 15% ls 1.0000 307.50 307.50
Jumlah 2,050.00 307.50 2,357.50
Keuntungan maksimal 10% 235.75
Jumlah 2,593.25
Dibulatkan 2,593.00
71 1 POHON BAWANG-BAWANGAN DAN KUCAY MINI
Pohon Bawang-Bawangan dan Kucai Mini Bh 1.0000 1,500.00 1,500.00
Alat Bantu ls 1.0000 300.00 300.00
Upah Tanam 20% ls 1.0000 360.00 360.00
Jumlah 1,800.00 360.00 2,160.00
Keuntungan maksimal 10% 216.00
Jumlah 2,376.00
Dibulatkan 2,376.00
72 1 M2 RUMPUT GAJAH
Rumput Gajah m2 1.1000 15,000.00 16,500.00
Alat Bantu ls 1.0000 300.00 300.00
Upah Tanam 15% ls 1.0000 2,520.00 2,520.00
Jumlah 16,800.00 2,520.00 19,320.00
Keuntungan maksimal 10% 1,932.00
Jumlah 21,252.00
Dibulatkan 21,252.00
Harga Sat. Jumlah Harga Jumlah Harga
No. Uraian Jenis Pekerjaan Sat. Koeff. Bahan / Upah Bahan Upah Bahan + Upah
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8

73 1BH TEH-TEHAN BERBENTUK, T = 40 cm


Pohon Teh-Tehan Bh 1.0000 7,500.00 7,500.00
Alat Bantu ls 1.0000 300.00 300.00
Upah Tanam 15% ls 1.0000 1,170.00 1,170.00
Jumlah 7,800.00 1,170.00 8,970.00
Keuntungan maksimal 10% 897.00
Jumlah 9,867.00
Dibulatkan 9,867.00
Harga Sat. Jumlah Harga Jumlah Harga
No. Uraian Jenis Pekerjaan Sat. Koeff. Bahan / Upah Bahan Upah Bahan + Upah
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8

35 M2 LAPISAN PENETRASI
Bahan :
Batu Pecah 3/5 m³ 1.7800 200,000.00 356,000.00
Batu Pecah 1/2 m³ 0.5600 190,000.00 106,400.00
Abu Batu m³ 0.3000 156,850.00 47,055.00
Aspal kg 180.0000 6,430.00 1,157,400.00
Alat Bantu set 0.3200 75,000.00 24,000.00
Alat Kerja :
Baby Roller 1 Ton/Vibrarator 1.0000 71,420.00 71,420.00
Dump Truck 1.0000 172,060.00 172,060.00
Tenaga Kerja :
Operator Terlatih Oh 0.1500 70,800.00 10,620.00
Pembantu Operator Oh 0.1500 52,000.00 7,800.00
Sopir Truck Oh 0.0750 59,800.00 4,485.00
Pembantu Sopir Oh 0.0750 59,800.00 4,485.00
Buruh Lapangan Tak Terlatih Oh 4.9500 45,400.00 224,730.00
Buruh Lapangan Oh 0.1500 50,200.00 7,530.00
Mandor Lapangan Oh 0.1500 59,800.00 8,970.00
Jumlah 1,934,335.00 268,620.00 2,202,955.00
Keuntungan maksimal 10% 220,295.50
Jumlah 2,423,250.50
Dibulatkan 2,423,250.00

Bandung, ……………….. 2017


Konsultan Perencana
PT. TRI EXNAS

Ir. YUNUS PERWANTO


DIREKTUR UTAMA
DAFTAR HARGA SATUAN BAHAN
TAHUN ANGGARAN : 2017

Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 2 3 4
A BAHAN AGREGAT KASAR & BAHAN PEREKAT.
1 Tanah Urug m3 106,420.00
2 Tanah merah m3 91,180.00
3 Tanah Gembur Lembang m3 125,010.00
1 Pasir urug m3 110,500.00
2 Pasir Batu (Sirtu) Tersaring m3 181,830.00
3 Sirtu m3 206,300.00
2 Pasir pasang m3 149,000.00
3 Pasir beton I / kasar m3 232,000.00
4 Pasir Aspal m3 249,760.00
5 Abu batu m3 173,310.00
4 Batu gosok (apung) kg 20,050.00
5 Batu pecah mesin 1/2-1 m3 190,000.00
6 Batu pecah mesin 1/2 m3 234,000.00
5 Batu pecah mesin 2/3 m3 215,000.00
6 Batu pecah mesin 3/5 m3 200,000.00
7 Batu pecah mesin 5/7 m3 171,000.00
8 Batu pecah mesin 7/10 m3 157,000.00
9 Batu pecah mesin 10/15 m3 124,000.00
10 Batu belah pondasi m3 124,000.00
11 Batu Koral Beton Kali m3 163,650.00
12 Agregat klas C m3 99,000.00
13 Agregat klas A m3 160,220.00
14 Batu Templek Hitam m2 80,220.00
15 Batu Pearlstone Warna kg 9,430.00
16 Batu Granit kg 7,650.00
17 Batu Andesit Uk 20 x 40 x 8 cm m2 198,900.00
18 Serbuk Granit Kg 6,930.00
6 Semen Tiga Roda Kg 1,440.00
7 Semen putih Kg 1,922.60
8 Semen warna kg 11,710.00
9 Semen warna tua kg
10 Semen warna khusus ( biru ) kg 16,463.00
11 Semen Merah, bahan bata merah tumbuk m3 82,870.00
12 AM 100 Kg 55,250.00
13 Semen AM 86 Kg 2,650.00
8 Air Ltr 15.00
9 Sika Top 107 Seal Kg 17,850.00
9 Seal Tape Bh 1,250.00
10 Lem kuning (Aibon) kg 44,200.00
11 Lem putih fox kg 21,270.00
12 Lem Vinil kg 42,540.00
13 Aspal kg 7,691.94
14 HRS Laston ton
B BAHAN PENUTUP DINDING
1 Bata merah bakar kelas I bh 850.00
2 Bata merah bakar kelas II bh 720.00
3 Rooster Beton 20/20 Bh 6,560.00
4 Batako kecil uk. 10 x 20 x 8 bh 1,510.00
5 Batako besar uk. 20 x 30 x 8 bh 2,720.00
6 Con Block Uk.20x40x8 bh 5,460.00
Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 2 3 4
7 Bata Krawang bh 9,110.00
8 I j u k ( 20 kg / m2 ) kg 13,810.00
9 Yumen Board, T. 2 cm lbr 148,000.00
10 Yumen Board, T. 1,5 cm lbr 116,000.00
11 Glass Wall m2 55,000.00
C BAHAN LOGAM
1 Besi baja beton U-32, ulir kg 12,100.00
2 Besi baja beton U-39, ulir kg 12,100.00
3 Besi baja beton U-42, ulir kg 12,100.00
1 Besi baja beton U-24, polos kg 12,100.00
2 Besi baja beton U-32, polos kg 12,100.00
3 Pagar BRC lengkap Tiang (Tanpa Pondasi) m2 230,940.00
2 Kuda-kuda rangka Baja Ringan (Zinkalum) m2 226,980.00
Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 2 3 4
3 Kuda-kuda rangka Baja Ringan (Galvalum) m2 237,630.00
4 Besi profil siku, rata - rata ex DN- SII kg 16,550.00
5 Besi profil siku, rata - rata ex Luar Negeri kg 17,640.00
6 Besi profil IWF, rata - rata ex DN-SII kg 16,550.00
7 Besi profil IWF, rata - rata ex Jepang kg 18,380.00
8 Besi kanal "C" Lip Chanel kg 16,550.00
3 Baja WF, Plat, Siku, C Lips dan INP kg 14,000.00
9 Besi Hollow 4x4 tebal 0,8 mm Bt 149,170.00
10 Besi Hollow 2x4 tebal 0,8 mm Bt 82,870.00
11 Besi CNP 100.50.1,8 m' 52,000.00
12 Tombak Pagar Besi Ø 16 Cobra, T = 20 cm Bh 6,500.00
13 Ongkos Galvanis Besi kg
4 Besi Strip, uk. 3 x 30 mm x 6 m ( 4,21 Kg ) bt 55,250.00
5 Seng BJLS 30, lebar 60 cm ( 1 rol = 50 m' ) m' 46,790.00
6 Seng BJLS 30, lebar 90 cm ( 1 rol = 50 m' ) m' 63,500.00
7 Seng plat BJLS 25 uk. 90 x 180 cm lbr 56,820.00
5 Seng plat BJLS 30 uk. 90 x 180 cm m' 73,530.00
6 Seng gelombang BJLS 25 uk. 0.90 x 1.80 m lbr 56,900.00
7 Seng gelombang BJLS 30 uk. 0.90 x 1.80 m lbr 58,830.00
6 Kawat beton kg 20,520.00
7 Kawat duri ( 1 rol = 80 m' = 10 kg ) m' 5,520.00
8 Kawat Pengikat m' 2,760.00
9 Kawat raam m2 16,190.00
10 Kawat nyamuk hijau m2 30,080.00
11 Kawat Las Kg 31,625.00
12 Plat besi tipis 1 mm kg 17,010.00
13 Plat besi tipis 0,5 mm kg 19,440.00
14 Plat besi tipis 2 mm - 5 mm kg 16,300.00
15 Plat besi tipis 5 mm - 10 mm kg 16,300.00
16 Plat besi tipis 10 mm ke atas kg 16,300.00
17 Allumunium Profil 4" - 4.00 m, ex YKK bt 388,960.00
18 Allumunium Profil 4" - 4.00 m, Warna bt 243,100.00
19 Allumunium Profil 4" - 4.00 m, Warna Sek. Alexindo bt 360,000.00
19 Plat Hitam kg 12,500.00
20 Plat Strip kg 12,500.00
21 Plat Strip 300.03 m' 9,550.00
22 Plat Seng Allmunium Lbr 97,000.00
23 Pintu Alluminium m2 215,000.00
24 Railling tangga besi stainless m' 911,620.00
25 Paku kaca kg 23,750.00
26 Paku eternit kg 21,270.00
27 Paku triplex kg 21,270.00
7 Paku 1 s/d 3 cm kg 21,270.00
8 Paku 4 s/d 7 cm kg 19,010.00
9 Paku uk. 8 s/d 12 cm kg 19,010.00
10 Paku 10" kg
11 Paku Ramset / dina bolt bh 8,970.00
12 Paku anti karat u/ genteng metal ( 35.00 m2 /kg ) kg 27,340.00
13 Paku seng kg 24,970.00
14 Paku beton 10 cm bh 880.00
15 Paku beton 7 cm bh 710.00
16 Paku beton 2 s/d 5 cm bh 440.00
17 Hak kait asbes 7 cm lengkap bh
18 Paku kait lengkap bh 1,320.00
19 Paku cacing kg 60,770.00
Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 2 3 4
20 Besi begel Kuda-kuda kg 21,270.00
21 Duk Angker kg 23,190.00
22 Angker Mur Baut dia. 19 mm panjang 60 cm bh 54,690.00
23 Mur Baut HTB dia. 10 mm s/d 16 mm panjang 5 cm bh 18,230.00
24 Mur Baut biasa dia. 10 mm s/d 16 mm panjang 5 cm bh 11,540.00
25 Piser dia. 12 cm s/d 20 cm bh 9,110.00
26 Paku gipsum anti karat ( 20.00 m2 / kg ) kg 25,130.00
27 Paku sekrup dus 13,530.00
D BAHAN PENGUNCI / PENGGANTUNG DAN KACA
1 Engsel pintu nylon 4" psg 68,000.00
2 Engsel pintu nylon 3" psg 16,500.00
3 Engsel Pintu Allumunium (Floor Hinge), Ex. Dorma bh
4 Engsel Pintu Allumunium (Floor Hinge), Ex .AKN bh
Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 2 3 4
2 Engsel jendela biasa psg 48,000.00
3 Engsel angin psg 35,750.00
4 Grendel jendela ( spring knip ) bh 13,750.00
5 Grendel jendela biasa bh
3 Grendel pintu biasa ( selot ) bh 15,000.00
4 Grendel tanam pintu ganda ( espagnolet ) bh
4 Hak angin stainless bh 40,000.00
5 Hak angin kait biasa bh
6 Door Closer bh 297,000.00
7 Kunci pintu Union/Royal Type besar bh 165,000.00
8 Kunci pintu Union/Royal Type kecil bh
9 Kunci pintu Cap KUDA TERBANG Type besar bh
10 Kunci pintu Cap KUDA TERBANG Type kecil bh 55,000.00
11 Kunci pintu SES Type besar bh
12 Kunci pintu SES Type kecil bh
13 Kunci pintu KM/WC, ALPHA bh 99,000.00
14 Kunci pintu Almunium ALPHA, uk. Pintu standard bh 330,000.00
15 Kunci pintu Almunium AKN, uk. Pintu standard bh
16 Kunci pintu Lemari bh
17 Kaca polos 3 mm m2 104,280.00
5 Kaca polos 5 mm m2 133,700.00
6 Kaca polos 8 mm m2 233,370.00
7 Kaca Buram 12 mm m2 656,370.00
6 Kaca raybend 5 mm m2 212,710.00
7 Kaca raybend 8 mm m2 455,810.00
8 Kaca es 3 mm m2 155,580.00
9 Kaca es 5 mm m2 218,790.00
10 Lapisan Sun Blast m2 214,500.00
11 Glass Block 20 x 20 cm (ex. Luar) Bh 116,990.00
12 Glass Block 20 x 20 cm (ex. DN) Bh 30,600.00
13 Jendela Nako Lengkap Tralis 1 Daun Bh 24,750.00
14 Kaca Cermin 5 mm m2 182,320.00
E BAHAN KAYU / KAYU LAPIS DAN PLAFOND
1 Kayu balok Albasia m3 1,884,020.00
1 Kayu papan Albasia m3 2,005,570.00
2 Kayu Terentang m3 2,206,130.00
3 Kayu balok Rasamala m3 2,655,860.00
4 Kayu kamper Singkil m3 7,033,320.00
2 Kayu balok Borneo super m3 4,922,770.00
3 Kayu papan Borneo super ( Meranti ) uk. 3/20 cm m3 5,687,430.00
4 Kayu papan Borneo super ( Meranti ) uk. 3/30 cm m3 5,687,430.00
5 Kayu balok kamper Medan m3 6,284,130.00
6 Kayu papan kamper Medan, uk. 3/20 cm - 3/30 cm m3 7,033,320.00
7 Kayu balok kamper Banjar m3 6,685,250.00
8 Kayu papan kamper Banjar, uk. 3/20 cm - 3/30 cm m3 7,018,960.00
9 Kayu balok kamper Samarinda m3 9,163,760.00
4 Kayu papan kamper Samarinda, uk. 3/20 cm - 3/30 cm m3 9,964,890.00
5 Kayu papan kamper Samarinda, uk. 3/20 cm m' 9,964,890.00
6 Kayu papan kamper Samarinda, uk. 3/20 cm m' 9,964,890.00
7 Kayu Balok Jati Jateng Tua Lepas Mata Dia. 80 cm keatas m3 28,110,090.00
8 Kayu Balok Jati Jabar Tua Lepas Mata Dia. 80 cm keatas m3 18,870,630.00
9 Kayu Balok Jati Jabar Dia. 40 cm keatas m3 9,644,440.00
10 Kayu kaso Borneo , uk. 5/7 - 4. 00 m' m3 5,687,430.00
11 Dolken dia 5 s/d 7 cm btg 27,590.00
5 Dolken dia 8 s/d 10 cm btg 32,700.00
Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 2 3 4
6 Triplek 3 mm, uk. 1,20 x 2,40 lbr 52,260.00
7 Triplek 4 mm, uk. 1,20 x 2,40 lbr 64,420.00
8 Triplek 4 mm, ukuran pintu lbr 60,770.00
9 Triplex 6 mm, uk. 1,20 x 2,40 lbr 88,730.00
10 Triplek Serat Sungkay lbr 80,000.00
11 Multiplek 9 mm, uk. 1,20 x 2,40 lbr 151,930.00
12 Multiplek 12 mm, uk. 1,20 x 2,40 lbr 194,480.00
13 Multiplek 18 mm, uk. 1,20 x 2,40 lbr 224,860.00
6 Play Wood 9 mm, uk. 1,20 x 2,40 lbr 151,930.00
7 Play Wood 18 mm, uk. 1,20 x 2,40 lbr 357,350.00
8 Teakwood 3 mm, uk. 1,20 x 2,40 lbr 118,510.00
9 Teakwood 4 mm, uk. 1,20 x 2,40 lbr 133,700.00
Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 2 3 4
10 Teakwood 3 mm, ukuran pintu lbr 97,240.00
11 Teakwood 4 mm, ukuran pintu lbr 119,110.00
12 Folding Gate m2 248,620.00
13 Melamin 4 mm, uk. 1,20 x 2,40 lbr 147,070.00
14 Formika putih polos, uk. 1,20 x 2,40 lbr 147,070.00
15 Formika motif, ukuran pintu lbr 143,060.00
16 Reng uk. 2/3 kayu Borneo Super m3 5,687,430.00
17 Reng uk. 3/4 kayu Kamper Banjar m3 7,018,960.00
18 Eternit 4 mm 100 x 100 cm m2 15,470.00
19 Hardflex 5 mm, uk. 120 x 240 cm lbr 102,100.00
20 Eternit hardflex 5 mm, uk. 1.05 x 2.40 lbr 133,700.00
7 Gipsum 120 x 240 cm ex DN lbr 70,860.00
8 Gipsum 120 x 240 cm ex LN lbr 106,350.00
9 Eternit asbes semen, 1.00 x 1.00 x 4,0 mm lbr 16,040.00
10 Eternit asbes semen, 1.00 x 1.00 x 5,0 mm lbr 20,050.00
11 Eternit asbes semen, 1.00 x 1.00 x 6,0 mm lbr 24,860.00
8 GRC lbr 92,980.00
9 List profil kayu kamper 1 cm m' 4,220.00
10 List profil kayu kamper 2 cm m' 4,920.00
11 List profil kayu kamper 4 cm m' 6,280.00
12 List profil kayu kamper 5 cm m' 8,440.00
13 List profil kayu kamper 10 cm m' 24,730.00
10 List Gipsump 7 cm m' 13,370.00
11 List Gipsump 10 cm m' 14,700.00
12 List Gipsump 14 cm m' 20,050.00
F BAHAN PENUTUP ATAP
1 Genteng metal Rainbow lbr
2 Genteng metal Sakura lbr
3 Bubung genteng metal Rainbow bh 91,160.00
4 Bubung genteng metal Sakura bh 115,470.00
5 Genteng palentong pres bakar KW. I, ex Jatiwangi bh 1,760.00
6 Genteng palentong pres Molen Oven KW. I, ex Jatiwangi bh 2,210.00
7 Genteng palentong super / besar natural, ex Jatiwangi bh 3,860.00
8 Genteng palentong super / besar glazuur, ex Jatiwangi bh 2,430.00
9 Genteng bubung segi tiga / bulat, natural bh 1,930.00
10 Genteng bubung palentong besar natural bh 3,030.00
11 Genteng bubung palentong besar glazuur bh 5,520.00
1 Atap genteng asbes, uk. 0.85 x 1.15 lbr 27,620.00
2 Atap Sirap kelas I ( 1 m2 = 80-100 lbr ) lbr 2,760.00
3 Almunium foil, uk. 1.25 x 60.00 m m2 3,860.00
4 Almunium foil, uk. 2.50 x 60.00 m m2 5,240.00
5 Twinlight ( 2.10 x 11.80 ) lbr 2,692,880.00
6 Twinlight m2 120,500.00
G BAHAN PENUTUP LANTAI.
1 Keramik dinding 10/20, 20/20, KW I putih / polos m2 57,340.00
2 Keramik dinding 10/20, corak warna, anti slip m2 63,200.00
3 Keramik dinding 20/20, corak warna, anti slip m2 65,150.00
1 Keramik dinding 20/25, corak warna, m2 63,260.00
2 Keramik 20/20, (KM) warna tua / corak, anti slip m2 53,610.00
3 Keramik 20 x 20 (KM) KW. I DN putih / polos m2 57,340.00
4 Keramik Lantai 20/20, "Roman Denimblue 40504" m2 72,500.00
5 Keramik Lantai 20/20, "KIA FT Amethyis Blue" m2 40,700.00
6 Keramik Lantai 20/40, Roman WT 40206 Twinkle White m2 63,250.00
7 Keramik lantai 30 x30, DN putih polos m2 60,270.00
3 Keramik lantai 30 x30 DN warna /corak, anti slip m2 63,200.00
Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 2 3 4
4 Keramik Lantai 40 x40 DN warna /corak, anti slip m2 75,000.00
5 Granit 40/40, Bianca 200 m2 210,336.40
6 Granito 60/60, "AURORA SILVER MILENIUM" m2 316,850.00
7 Granito 20/60, "AURORA ASTRO GOLD" m2 348,500.00
8 Stairmosing keramik 10 / 20 m' 14,700.00
9 Stairmosing keramik Fiber m2 16,710.00
10 List Keramik 5/40 Lbr 42,000.00
4 Paving block segi ENAM, t = 6 cm, natural m2 111,580.00
5 Paving block segi ENAM, t = 8 cm, natural m2 120,930.00
6 Paving block segi ENAM, t = 6 cm, warna m2 121,550.00
7 Paving block segi ENAM, t = 8 cm, warna m2 131,900.00
8 Grass block 45 x 30 x 8 cm bh 11,420.00
Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 2 3 4
9 Grass block 45 x 30 x 10 cm bh 13,970.00
10 Batu pinggir beton uk. 6 x 15 x 40 cm (Kaansteen) bh 30,380.00
11 Batu pinggir beton uk. 10 x 20 x 35 cm (Kaansteen) bh 35,910.00
12 Batu pinggir beton uk. 15 x 35 x 60 cm (K - 225) bh 42,780.00
13 Kaansteen Pavingblock m' 29,610.00
14 Lantai Parquet m2 139,170.00
15 Karpet ex. Lokal, Wonder (1 = 400 m) m2 200,550.00
16 Under Layer Khusus Parquet m2 22,500.00
17 Under Layer Khusus Karpet m2 65,000.00
H BAHAN FINISHING.
1 Wall Paper Corak Roll 267,410.00
2 Cat dasar Alkali ltr 59,550.00
1 Cat dasar tembok, Indo 9000 Sealer Water Base kg 26,880.00
2 Cat dasar Kayu ltr 16,700.00
3 Cat tembok Sanlex gln 121,550.00
4 Cat tembok Sanlex Wonder kg
3 Cat tembok Vinilex gln 165,750.00
4 Cat tembok Wiratex kg 24,860.00
5 Cat tembok ICI Exterior gln 299,630.00
6 Cat tembok ICI Interior gln 280,780.00
7 Cat kayu / besi Seiv kg 55,250.00
4 Cat kayu / besi Avian kg 55,250.00
5 Cat Duco Kg 200,550.00
5 Meni kayu kg 68,000.00
6 Meni Poxi Kg 42,000.00
7 Soda Coustic kg 22,100.00
8 Cat Zinchromate Bola mas kg 60,430.00
9 Plint coat kg 45,330.00
10 Dempul tembok ( plamuur ) kg 16,570.00
6 Dempul kayu kg 23,840.00
7 Dempul Plitur kg 34,370.00
8 Dempul halus / Impra (Wood Filler) kg 46,790.00
9 Dempul lilin kg 8,680.00
10 Dempul plastik kg 34,560.00
11 Dempul Duco Kg 36,000.00
9 Terpentin ( minyak cat ) ltr 11,760.00
10 Wood Filler Kg 42,350.00
11 Wood Stain Lt 42,000.00
12 Sending Seller Lt 45,000.00
13 Solignem ( 1 blek = 10 liter ) ltr 7,450.00
14 Thiner A ltr 21,720.00
15 Thiner B ltr 36,760.00
16 Thinder Melamik ltr 24,000.00
17 Hardener ltr 17,500.00
18 Glass Bead kg 21,520.00
19 Thermo Plastic kg 21,555.00
20 Kompon kg 51,900.00
21 Oker putih kg 21,270.00
10 Oker warna kg 27,340.00
11 Oten ( pewarna plituran ) bks 9,110.00
12 Melamik kg 46,790.00
12 Sirlak ex India kg 160,220.00
13 Spirtus ltr 10,310.00
14 Plitur jadi DX ltr 46,790.00
15 Plitur jadi Ultran ltr 57,730.00
Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 2 3 4
14 Kuas 3" bh 10,000.00
15 Kuas 4" bh 17,160.00
15 Rol cat bh 27,500.00
16 Kape tembok bh
17 Kape kayu bh
16 Ampelas lbr 4,900.00
17 Teak Oil ltr 27,340.00
18 V e r n i s ltr 36,460.00
17 Minyak Bekisting ltr 18,230.00
18 Plamir Kg 16,570.00
19 Solar (industri) ltr 11,520.00
20 Minyak Pelumas ltr 35,000.00
Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 2 3 4
I BAHAN PERPIPAAN.
1 Pipa pralon PVC. ( AW ) dia 1/2 ", sekulaitas Maspion (Abu-abu) btg 21,910.00
2 Pipa pralon PVC. ( AW ) dia 3/4 ", sekulaitas Maspion (Abu-abu) btg 25,960.00
3 Pipa pralon PVC. ( AW ) dia 1 ", sekulaitas Maspion ( Abu - abu ) btg 32,960.00
4 Pipa pralon PVC. ( AW ) dia 1 1/4 ", sekulaitas Maspion (Abu-abu) btg 45,670.00
5 Pipa pralon PVC. ( AW ) dia 1 1/2 ", sekulaitas Maspion (Abu-abu ) btg 60,130.00
4 Pipa pralon PVC. ( AW ) dia 2 ", sekulaitas Maspion ( Abu - abu ) btg 90,050.00
5 Pipa pralon PVC. ( AW ) dia 2 1/2 ", sekulaitas Maspion (Abu-abu) btg 117,310.00
6 Pipa pralon PVC. ( AW ) dia 3 ", sekulaitas Maspion ( Abu - abu ) btg 165,380.00
7 Pipa pralon PVC. ( AW ) dia 4 ", sekulaitas Maspion ( Abu - abu ) btg 236,100.00
8 Pipa pralon PVC. ( AW ) dia 6 ", sekulaitas Maspion ( Abu - abu ) btg 516,580.00
9 Talang Baja m' 102,120.00
10 Corong Talang bh 79,120.00
11 Talang Sudut Dalam bh 125,120.00
12 Socket bh 37,720.00
13 Bracket bh 30,820.00
8 Grevel beton 1/2 dia 20 cm bh 37,010.00
9 Grevel beton 1/2 dia 30 cm bh 52,060.00
10 Grevel beton 1/2 dia 40 cm bh 69,060.00
J BAHAN / ALAT -ALAT SANITAIR.
1 Kloset jongkok porselen, warna bh 425,420.00
2 Kloset jongkok porselen, putih bh 200,550.00
3 Kloset duduk porselen TOTO, warna standard lengkap bh 1,373,880.00
4 Kloset duduk porselen TOTO, standard lengkap, warna tua bh 2,045,680.00
5 Kloset duduk porselen INA, standard lengkap, warna tua bh 1,203,340.00
6 Kloset jongkok teraso bh 66,850.00
7 Urinoir warna standard lengkap bh 1,430,970.00
8 Penyekat urinoir Porselein lbr 437,580.00
2 Kran Tembok San Ei dia 1/2" Bh 93,590.00
3 Kran Air San Ei Leher Angsa dia 1/2" Bh
4 Wastafel "MIRROR WP 65x56" Unit 3,750,000.00
5 Wastafel lengkap + cermin, ex TOTO type LW 211 CJ Unit 1,470,750.00
6 Kaca Cermin CEA MIRROR 75001 Unit 770,000.00
7 Kaca Cermin Biasa Unit 522,675.00
8 Paper Holder TOTO Unit 372,240.00
9 Bak mandi fibre glass, uk. Kecil bh 276,250.00
10 Bak mandi fibre glass, uk. Besar bh 359,120.00
11 Bak mandi Teraso bh 138,120.00
12 Floor Drain San Ei Bh 218,790.00
13 Floor Drain Lokal Bh 48,620.00

Bandung, ……………….. 2017


Konsultan Perencana
PT. TRI EXNAS

Ir. YUNUS PERWANTO


DIREKTUR UTAMA
DAFTAR HARGA SATUAN UPAH
TAHUN ANGGARAN : 2017
Harga Satuan
No. Jenis Pekerjaan Sat.
( Rp. )
1 2 3 4

1Pekerja Oh 95,000.00
2 Tukang Batu Oh 117,000.00
3 Kepala Tukang batu Oh 157,000.00
4 Tukang Kayu Oh 147,000.00
5 Kepala Tukang Kayu Oh 162,000.00
6 Tukang Besi profil / Tukang Las Oh 147,000.00
7 Kepala Tukang Besi Profil / Tukang Las Oh 162,000.00
8 Tukang Besi Beton Oh 143,000.00
9 Kepala Tukang Besi Beton Oh 161,000.00
10 Tukang Cat Oh 143,000.00
11 Kepala Tukang Cat Oh 129,000.00
12 Tukang Gali Oh 129,000.00
13 Kepala Tukang Gali Oh 157,000.00
14 Tukang Pipa Oh 143,000.00
15 Kepala Tukang Pipa Oh 157,000.00
16 M a n d o r Oh 157,000.00
17 Operator hari 167,000.00
18 Pembantu Operator hari 132,000.00
19 Sopir hari 157,000.00
20 Pembantu Sopir hari 122,000.00
21 Alat bantu ls 123,000.00

Bandung, ……………….. 2017


Konsultan Perencana
PT. TRI EXNAS

Ir. YUNUS PERWANTO


DIREKTUR UTAMA