ROOMWISE PROGRAM FOR MEP SERVICES - CEILING COMPLETION

PROJECT: OMAN ACROSS AGES MUSEUM PACKAGE - 1 (INFRASTRUCTURE )


CLIENT: THE ROYAL COURT AFFAIRS
MAIN CONTRACTOR: SPML - OSCO JV 1/6/2019
MEP CONTRACTOR: INTERNATIONAL ELECTRIC CO- (OMAN) LLC
Clearance date
Sl- No Description of Room Services completion Remarks
to spos
MEP CLEARANCE @ Zone E2 Basement-2 Mechanical Electrical Plumbing
1 Vehical Entry Room 1/15/2019 2/7/2019 1/18/2019 2/7/2019
2 Vehical Movement Area 1/15/2019 2/7/2019 1/18/2019 2/7/2019
3 Gardener Respite 1/15/2019 2/8/2019 1/18/2019 2/8/2019
4 WS Social Space. 1/15/2019 2/8/2019 1/18/2019 2/8/2019
5 WC Room 1/15/2019 2/8/2019 1/18/2019 2/8/2019
6 Toilet or Shower 1/15/2019 2/8/2019 1/18/2019 2/8/2019
7 Cleaner Room 1/15/2019 2/9/2019 1/18/2019 2/9/2019
8 Hazardous Room 1/18/2019 2/10/2019 1/21/2019 2/10/2019 This date are subject to Approved
RCP & Material Delivery of BMS
9 Infected Room 1/18/2019 2/10/2019 1/21/2019 2/10/2019
control valves on 06-01-19 by
10 Garden & Maintenance Store. 1/18/2019 2/10/2019 1/21/2019 2/10/2019 NSC / SPOS
11 WS Clean & Dirty Room 1/18/2019 2/12/2019 1/21/2019 2/12/2019
12 Maintenance workshop 1/18/2019 2/12/2019 1/21/2019 2/12/2019
13 Air Intake Area 1/28/2019 2/14/2019 1/31/2019 2/14/2019
14 Chiller Plant Room / Chiller Yard 1/28/2019 2/14/2019 1/31/2019 2/14/2019
15 STP Room 1/28/2019 2/15/2019 1/31/2019 2/15/2019
16 Long Exit Corridor 1/28/2019 2/16/2019 1/31/2019 2/16/2019
17 Chiller Plant - Front Corridor 1/28/2019 2/16/2019 1/31/2019 2/16/2019
ROOMWISE PROGRAM FOR MEP SERVICES - CEILING COMPLETION
PROJECT: OMAN ACROSS AGES MUSEUM PACKAGE - 1 (INFRASTRUCTURE )
CLIENT: THE ROYAL COURT AFFAIRS
MAIN CONTRACTOR: SPML - OSCO JV 1/6/2019
MEP CONTRACTOR: INTERNATIONAL ELECTRIC CO- (OMAN) LLC
Clearance date
Sl- No Description of Room Services completion Remarks
to spos
MEP CLEARANCE @ Zone E1 Basement-2 Mechanical Electrical Plumbing

1 Chiller Panel Control Room 1/25/2019 1/31/2019 1/28/2019 1/31/2019


2 Secondary Pump Room 1/25/2019 1/31/2019 1/28/2019 1/31/2019
3 RMU Corridor 1/25/2019 1/31/2019 1/28/2019 1/31/2019
4 Transformer / RMU Room-1 1/28/2019 1/31/2019 1/31/2019 1/31/2019
5 Transformer / RMU Room-2 1/28/2019 1/31/2019 1/31/2019 1/31/2019
6 Transformer / RMU Room-3 1/28/2019 1/31/2019 1/31/2019 1/31/2019
7 Transformer / RMU Room-4 1/28/2019 1/31/2019 1/31/2019 1/31/2019
8 Transformer / RMU Room-5 1/28/2019 1/31/2019 1/31/2019 1/31/2019
9 MV Switch gear room 1/28/2019 2/7/2019 1/31/2019 2/7/2019
10 AHU Plant Room 1/28/2019 2/7/2019 1/31/2019 2/7/2019
11 MSB Room 1 1/31/2019 2/7/2019 2/3/2019 2/7/2019
12 MSB Room 2 1/31/2019 2/7/2019 2/3/2019 2/7/2019
13 DRUPS Room 1/31/2019 2/7/2019 2/3/2019 2/7/2019
14 Control Room 1/31/2019 2/7/2019 2/3/2019 2/7/2019
15 Generator Room 1/31/2019 2/7/2019 2/3/2019 2/7/2019