Académique Documents
Professionnel Documents
Culture Documents
Client:
Executive Director
Uganda National Roads Authority
(UNRA)
Plot 5 Lourdel Road
P.O. Box 28487
Kampala - UGANDA
October 2011
(Updated September 2012)
TABLE OF CONTENTS
Introduction
Abbreviations and Glossary
0 Quality Assurance
1 Inventory of Existing Road
2 Traffic Forecasting
3 Traffic Loading for Pavement Design
4 Topographic Surveys and Land Acquisition
5 Geometric Design
6 Soils and Materials Investigations
7 Pavement Design
8 Hydrology and Hydraulics Investigations
9 Structures Design
10 Economic Evaluation
11 Standard Bidding Documents
12 Specifications
13 Bills of Quantities
14 Risk Analysis
15 Project Reports (No content in these Guidelines)
16 Suggested Format of Design Review Report
Introduction
The purpose of these Guidelines for Works Contract Review (WCR) is to propose a consistent
and itemised approach to each of the steps covering the pre-construction checking by a
Supervising Consultant (SC) of the engineering road designs commissioned by the Uganda
National Roads Authority (UNRA).
Guidelines exist which are aimed at providing a consistent and simplified checklist for Design
Consultants (DCs) to undertake Detailed Design of a project and for Technical Reviews of that
design to follow the same format. It is intended that the WCR shall be undertaken using a
similar structured layout for the review and report.
Due to the variations in scope of projects, not all of the listed activities will be included in every
project and there are some elements of the Detailed Design that will not be reviewed under the
WCR. Similarly the checklist may exclude some activities that are a necessary part of the
detailed design of other specific projects.
This first edition of the Guidelines does not contain consider the requirements for
environmental, social and land procurement aspects of the design and construction contract.
These Guidelines should not be considered as a Review manual or instruction to the Reviewers
of the SCs and in no way does it reproduce or supersede the Terms of Reference for the
contract being undertaken by the SC. In the case of conflict between this document and the
contents of any part of the Supervision Contracts between the parties, the contract documents
should overrule the contents of this document.
The numbering of chapters and sections in this document are chosen to coincide with the
numbered sections used in the Design and Review Guidelines. To retain consistency between
designs, reviews and reports, all users are asked to retain the same basic numbering system
Where it is considered unnecessary that the SC should review individual subsections of
the design, there will be a lack of continuity in numbering of the Review Report, caused
by such omission.
Where DCs have established a significant scope of works not covered within the Design
Guidelines, an additional sub section will be added by the DC (or the Reviewer) at the end of
the most relevant standard section with a numbered sequence following on from those already
used.
To facilitate the work of reviewing all design reports, DCs were asked to attach at the front of
each report a copy of the relevant sections of these guidelines in which the two boxes (columns
1 and 2 on each sheet) will have been filled showing whether the described item is relevant to
the design and if so, where in the Design documents the relevant information, design data or
discussion can be found. This should assist the SC to locate relevant sections of the design.
UNRA are in the process of developing further standard guide documents which should be used
by the DCs, where possible. Again this should simplify the process of design and review as well
as assist contractors dealing with several different UNRA projects at the same time.
QS = Quantity Surveyor
RAP = Resettlement Action Plan
RDM = Ugandan Roads Design Manual published by Ministry of
Works, Housing and Transport, dated 2010
RFP = Request for Proposals (technical element usually as per final
TOR)
RHS = Right Hand Side
RoW = Right-of-Way (the legally established land reserved for the road
construction)
SE = Supervising Engineer (Consultant)
Services Contract = The contract between the Roads Authority and the Design
Consultants to undertake the design work for particular project
SN = Structural Number
Stakeholder = A person or body that has an interest, material or otherwise, in
the project for which design is being undertaken
Switching Values = The degree to which investment costs can be increased or
project benefits reduced to produce a NPV of zero
ToR = Terms of Reference for the Design Services (see also RFP).
UNRA = Uganda National Roads Authority
UTSS = Uganda Typical Special Specifications
VEF = Vehicle Equivalence (Damage) Factor
Identify and design a methodology to check the Bid Documents and Drawings and
modify any identified elements or details of work contained in the contract that may
result in poor or incomplete workmanship, delays to project completion and increases in
project costs above the contract price,
Determine the areas and level of risk with regard to the completion on time, within
budget and to the required specification
Develop through sensitivity analysis the impact of changes to assumptions made during
design
To quantify the potential extent in terms of quantities and cost of each identified risk
Each risk shall then be identified and classified by the nature of the risk, its sensitivity
analysis and the method of managing or mitigating that risk.
The SC shall implement a Quality Management System for the entire Assignment in accordance
with ISO 9001, either within the framework of their own organisation’s quality management
systems or specifically set up for an individual assignment. This shall contain a Project Quality
Control Plan encompassing all aspects of the assignment to be undertaken by the consultant
with specific reference to the items described in Section 0.1 below which relate only to the WCR
section of the assignment.
The consultant shall submit the Project Quality Control Plan to UNRA for review and approval.
C • Ravelling of asphalt
D • Potholes in asphalt
F • Rutting in asphalt
2. Traffic Forecasting
The SC will not be expected to check in detail all the survey inputs by the DC for Traffic
forecasting but the review shall observe and comment on the following:
4. Topographic Survey
The review and field check of the Topographic Survey undertaken during detailed design is one
of the key elements of the WCR and must be carried out as early as possible in the period
allocated for the WCR. Since agreement has to be reached with the contractor on existing
ground levels throughout, it is recommended that the check field survey is carried out jointly with
the contractor.
All field survey work during the review should be carried out using modern digital instruments
enabling easy transfer of digital field data to the proposed DTM. The DTM shall be compatible
with the road design software MX Roads which is UNRA’s preferred design software. All raw
data captured during the survey should be maintained for scrutiny, particularly important should
there be lack of correlation between design and review surveys.
In addition to the field survey, the SC is to review the procedures and data arising from the survey
undertaken by the DC to ensure that the initial survey, the DTM and the setting out beacons are
correctly referenced for use in the works.
Additional Data files from Initial survey to Section 4.2 describes data files and
4.2
be reviewed if DTMs do not correspond documents that need only be checked if field
A csv data files for detailed survey checks under WCR reveal major errors in
B Summary of Feature Codes used
either setting out beacons or detailed survey
data presented in the DTM
C Rinex files(where GPS measurements were done)
D Traverse Field and computation sheets
Differential Levelling raw data and computation
E
files
F Summary of Control points
Digital Terrain Model (DTM) detail in dxf or dwg
G
format
H Field notes for the survey control network/traverse
Adjustment of the survey control network/traverse
I
and evidence of conformity to TOR
Field notes and reduced observation of field data
J
for creation of models
5. Geometric Design
Guidelines for Detailed Design contain twelve separate sections under Geometric Design, most
of which will not affect the three principle objectives of the WRC which are to ensure that the
project is completed to specification, on time and within budget. Only the sections which may
affect the completion within those objectives are therefore listed below.
As detailed in Section 1 of the WCR, review of the Design Base Statement (DBS) is included
and hence Table 5.1 below and the first table in Annex 5.3 of the Design Guidelines need to be
reviewed.
Note – If the above details are not available in the contract drawings, SC will be expected to
complete the necessary construction drawings in time for use by the contractor
Included in Report Reviewed Comment
5.9 Accommodation of Traffic Design Reference reference (if any)
See UNRA Clarification Note for Design
A Engineers – Issue 0004
Note – If the above details are not available in the contract drawings, SC will be expected to
complete the necessary construction drawings in time for use by the contractor
- where the depth from existing ground level upwards to proposed formation level
exceeds 600mm and where improved subgrade materials will be used, the CBR value
of the subsoil becomes irrelevant to the selection of the soil strength classification.
Note: the above assumes that all topsoil under the proposed or existing embankments will be
removed.
Key areas of concern in Materials Investigation are described below. They include the
following situations for which the SC will need the assistance of the contractor to undertake
exploration, identification, sampling and testing of further samples. The additional tests may be
on either “as dug” samples, or stabilised or modified:
- Lack of guidance from Interpretative Soils Report on use of existing pavement
materials in proposed construction
- Conditions where the haulage distances between suitable borrow areas is excessive
- Limited supply of as dug material suitable for sub base
- Limited number of samples taken per borrow area providing insufficient assurance as
to the depth, extent and consistency of the seam,
- Too few tests have been carried out on materials to be used in stabilised or modified
form with insufficient data on source or quantities of additives used in stabilised
materials
- Lack of proper samples from potential rock quarries with absence of extracted cores
from boreholes.
Table 6.4.1 below contains questionnaire on the conduct and reporting of the Soils
Investigation and the SC should confirm if the investigation was carried out successfully or
whether additional investigation work will be required. Table 6.4.2 below should be used to list
the extra works carried out by the SC and the test data shall be attached in an Appendix.
SC is to list areas of the above investigation, sampling, testing and presentation of results that
is deemed unsatisfactory and where further investigation was necessary under the WCR.
7 Pavement Design
The following guidelines are aimed at reminding the SC of the steps that should have been
considered during the pavement design for new or upgrading of existing roads.
The SC should comment on possible variations to the pavement layer configurations derived
by the DC and offer reasoned recommendations for which alternative configuration could be
adopted.
The DC may have made comparisons of the pavement layers derived under the MOWHC
Pavement Design Manual with those derived from other design codes or methods. If such
alternatives are contained in the Engineering Report, the SC should comment thereon.
Details of hydraulics and hydrology for the bridges on the project do not require a detailed
analytical review at this stage. However the SC Reviewer will be expected to report on all
major water courses, following visits to site, examination of current structures, and basic
hydraulic observations. Such observations can indicate the sufficiency of an existing structure
e.g.
- Is the new bridge soffit level higher than the existing or original?
- Is the new channel opening between abutments as wide or wider than the existing
channel opening?
- What evidence is there of flooding in the area upstream of the bridge
- Are there any high water marks on the face of the abutments and piers that would
indicate adequacy of the existing channel
If all indicators are positive then no specialist check will be required. If the opening of the new
structure is no larger than existing, flood evidence is noticeable and if there is evidence of
scouring or erosion near the bridge, then the SC should call in the services of a
Hydraulics/Hydrology specialist to review the detailed design.
Similar examination should be made for all major cross culverts to ascertain if overtopping of
existing structures has occurred and estimate channel sizes upstream and downstream
together with channel roughness. The condition of all inlet and outlet structures to be retained
or repaired shall be checked, particularly for signs of erosion on the outlet side.
The following elements of design shall be checked to identify and remove any design errors
and to correct any design omissions:
9 Structures Design
The SC shall use the services of an Engineer experienced in bridge design to review the
structural drawings for any box culvert with a span in excess of 4 metres and for any multiple
span bridge or bridge with a single span in excess of 12 metres. However except where
specifically stated, a detailed check of the structural analysis of each element will not be
required under the WCR.
This section of Bridge Review contains a number of check points which serve to remind the
Reviewer of some details that should be addressed by the Designer and checked for inclusion
in the bridge design drawings.
Under the WCR review the following points should be checked in a yes/no method and
answers indicating observance, or otherwise, placed against each item in the notes
Additional Guidance in detailing Bridge Design in which notes are aimed at improving
durability and maintenance through recommended design practice is given in 9.6. below.
Construction Details
- Deck construction sequence should be shown on drawings, especially for continuous
decks.
- Show method of fixing bearings to beams and bearing plinth/installation sequence.
- Allow for pre-cambering concrete and steel beams under loading.
- Review the provision of tapered bearing plates to accommodate camber
- Show details of all chamfers to corners.
Steel Construction Details
- Provide adequate bracing at all supports and in span bracing for steel beam composite
deck erection.
- Details of splice joints cover plates, bolting HSFG, detailing of web stiffeners/bearing
stiffeners especially if deck skewed for access by welding equipment
- Steelwork finishing, metal spray, galvanising, painting etc
Reinforcement Detailing
- Stagger laps for all bars
- All bars to be adjustable across the concrete section unless less than I metre width to
ensure bending tolerances do not result in cover loss
- Review maximum steel percentages
- Bar spacing not exceeding 150mm for thermal cracking considerations
- Construction joints to be shown to ensure they can be constructed properly
- Waterstops and joint detailing in construction joints to be shown
- Review detailing of column seismic plastic hinge zones for conformity with codes
More general detail checks may be carried out using the list in Section 9.8 below.
10 Economic Evaluation
(Note: For the purposes of Works Contract Review by the Supervising
Engineer, this Section 10 need NOT be reviewed)
12 Specifications
12.1 General Specifications
The Standard Bidding Documents prepared by the World Bank and to be used in all UNRA
contracts for new and upgrading works refer to a General Specification and a Special
Specification (also sometimes referred to as Particular Specification). The General Specification
referred to in the contract documents and to be used shall be the following:
Work shall be carried out in accordance with the General Specifications except as supplemented,
modified or revised under the Special Specification to be included in the Contract Documents.
13 Bills of Quantities
13.1 Objectives of Works Contract Review of Bills of Quantities
The format of the Bills of Quantities is based upon the descriptions and measurement items
contained in the General Specification and the Special Specification. The quantities are
prepared by the independent Design Consultant for the project. The objectives of the Works
Contract Review are fivefold:
To check the contract BOQ descriptions against the project drawings and to highlight
any major work items shown on the drawings for which there are no proper
measurement items within the BOQ
To check that the design does not include any construction works that are beyond the
capabilities of the contractors normally bidding for this type of works
To check that the design does not include any materials that are likely to prove difficult
to acquire or to use or that may cause delays to the project
To check and recalculate the quantities of all the items contained in the BOQ that
represent a major proportion of the overall project costs
To provide a revised, priced BOQ that may be considered as a target maximum for the
final construction costs.
The ultimate aim will then be for the SC to supervise through to completion of the contract
works within that targeted maximum cost (subject to variation of price which will be outside the
control of the SC).
Preparation of the revised priced BOQ must be completed within nine months of commencing
the Review unless an alternative time period is contained in the contract agreement between
UNRA and the SC.
The method of measurement used by the SC Quantity Surveyor (QS) will follow that laid down
in the General and Special Specifications. However the particular style of takeoff sheets and
method of recording dimensions and quantities will be at the discretion of the QS. The derived
quantities must be the estimated overall quantity for each item for which the contractor will
receive payment. If any surplus allowance is made on any single item, the SC must clearly
mark this excess and provide justified reason for its inclusion.
The following guide notes are separated into sections corresponding with the Bills of
Quantities and should be used for general guidance only. Particular project conditions may
supersede the suggested method of measurement or quantities.
The suggested methods of estimating the values for certain Provisional Sums are contained in
the following table. If the Prov. Sum values contained in the project BOQ vary considerably
from those in the table below, the higher value shall be used in the revised BOQ.
The SC should consider if the quantities and sizes of housing, offices and vehicles are
appropriate for the project. The table below provides typical examples for a 36 month project
which is approximately 100kms long. They should be adapted to suit the specific project under
design.
A clear note should be included in the Preamble to the BOQ and the Special Specification
regarding ultimate ownership of office, housing and transport as per the following example:
Ownership of Engineers office and housing including all furniture, equipment and
services as well as vehicles and survey equipment provided under Items 14.01 through
14.07 plus Items 14.11 and 14.12 shall revert to the contractor upon completion of the
Contract.
The laboratory and equipment provided under Items 14.08 and 14.09 shall revert to the
Employer.
The intentions for ultimate ownership of the items provided by the contractor shall be checked
with UNRA.
Consider alternatives for corrugated metal pipes as theft has become a problem in some
locations.
Item 22.07 should include concrete haunching to pipes and concrete class 25 is adequate
Item 22.23 PVC service ducts may include 150mm diameter
Lining of drains should be considered carefully particularly in urbanised and trading areas.
Concrete or asphalt berms may be required on curved embankments to prevent erosion and
guide run off to proper chutes.
Stone pitching should be applied on embankments adjacent to bridge abutments and in road
side drains adjacent to culvert inlets and outlets, subject to erosion
Gabions as supporting structures and use in prevention of erosion, Reno mattresses for
resistance to erosion in outfalls
13.3.3 Bill No. 3 - Earthworks and Pavement Layers of Gravel or Crushed Stone
The General Specification and Bills of Quantities sometimes have been misread and hence
UNRA Clarification Note for Design Consultants Issue 0002 has been prepared to cover method
of measurement for the following subjects:
1) Removal haulage and temporary stock piling of top soil, 31.01(b)
2) Removal and haulage to spoil of surplus topsoil, 36.01(a)
3) Retrieving from stock pile, haulage and laying of top soil, 56.03(c)(i)
4) Common Excavation in cut to spoil, 36.01(a)
5) Common Excavation in swamps or wetlands to spoil, 36.01(b)
6) Excavation in rock in cut to spoil, 36.01(c)
7) Fill and improved subgrade layers using G15 or G7 materials, 36.02(a) or 36.02(b)
8) Excavation, preparation, haulage and placing of fill from either cut material or borrow
(same item for both sources but excluding rock), 36.02(c)
9) Breaking out, processing, haulage and placing in embankment of rock either from cut or
quarry (same item for both sources) 36.02(d)
10) Provision of rock as in 7 above either from cut or quarry and placing in pioneer layer,
36.02(h)
This format of billing the earthworks should be followed, using all relevant measured
items as described in the specification.
Clearing and grubbing: suggest measured width should be up to 3.0m outside foot of
embankment or top edge of cut. This should be added to specification (see Clarification Note
002)
Specification should make clear what accommodation works will be required before
commencement of main earthworks
See clarification on topsoil measurement which should be stock piled and reused. Under normal
circumstances no topsoil should go to spoil. Measurement should state clearly how much
outside embankment and cuttings topsoil removal should extend. (see Clarification Note 002)
Estimates of earthworks to spoil shall include any black cotton soils occurring within the
embankment, expansive clays in the Subgrade zone, materials with soaked CBR< 3
If works include removal, storage and re-use of existing pavement layers, measured items
should clarify what tasks are included in the measured item (e.g. planing, crushing, grading,
storing, recovery etc).
Filling material in embankment is measured as one item only, whether it is imported from borrow
areas or excavation from cutting areas on the alignment. (see Clarification Note 002)
Triaxial tests should be carried out on all slopes in deep cutting (except rock) to determine
acceptable grade of slopes. Revised slope grades should be used in re-measurement of
earthworks under the WCR.
Has benching been measured where embankment widened? Are benches wide enough for
excavator to stand?
Are geotextiles required in backfill to swamps? Is type specified in BOQ or specification?
Method of measurement of swamps should be clarified (particularly where soft material is likely
to “flow” from outside intended cutting area. Should this be paid for and should payment be
made for rock fill spread into this area?
Measurement of surcharging in embankment fill and subsequent removal should be included if
so designed. If no surcharge used and embankment settles, extra filling may be required and
should be measured as separate item.
Extra Soil Investigation selected by the SC shall be carried out at start of WCR to clarify quantity
of materials likely to go to spoil, quantity and type of rock excavation (paid or unpaid), quantity
of swamp material to be removed and rock replacement.
Borrow areas and quarries to have weighbridge facilities. These should be detailed in
specification.
Where stabilization or modification of sub base is required, does the BOQ measure this properly
(see Clarification Note 002)
Contractor to assist with preparation of mass haul diagram to ensure haulage distances are
reasonable and selection of borrow areas is appropriate.
Road markings, rumble strips, traffic calming, signs etc need inclusion and re-measurement.
Road sign specification should state whether tubes are filled with sand/cement grout and to
have weakened break off point in case of accident. Specification on plate materials to be
finalised.
Centres of posts for guard rails should be stated. Timber or steel posts should be stated.
Check for special warning signs for curves that are below design standards and at other
dangerous locations.
The Note suggests ways of reducing accidents, delays and nuisance and includes suggested
items for inclusion in the BOQ, items 15.01 and 15.02
The SC should ensure the necessary provisions for Accommodation of Traffic are clearly
demonstrated in the drawings and described in the Special Specification and also in the Bills of
Quantities.
Are the specified details strong enough for the SC to control an uncooperative
contractor? If not, special additional agreements should be put in place early in the
project.
14 Risk Analysis
Objectives of the Risk Analysis
The objectives of the Risk Analysis carried out by the Design Consultant and contained in the
Project Folder were as listed below:
o To develop list of pertinent questions consultants should ask themselves about the
project and develop a measure of risk attached to each
o To identify what design assumptions and related background issues need to be reported
to Supervising Consultant in the Project Folder
o To identify what events or conditions could prevent the project from being completed on
time, to specification and within budget. These events or conditions in effect form the
basis of the risk analysis.
In order that the SC may review thoroughly the risk analysis prepared by the DC, the draft
outline as contained in the Guidelines to Detailed Design and Design Review, (together with
examples), is given below. The SC may reconstruct a separate risk analysis or review and
comment on that prepared by the DC.
Provide answers to each relevant question in table below. As appropriate, DC may delete the suggestions
contained in the table and include only relevant Issues, Risks and Mitigation responses applicable to the
particular project.
14.1.4 Earthworks
DC to develop following and check specifications as noted
From road design software (Rows 1 and 11 below) develop a table in detail that includes
breakdown of cut and fill for each 3km length of the alignment. From results of soil investigation,
and DCs estimates of unusable cut material, swamp excavation, quantities of usable and
unusable rock, estimate the percentage and hence quantities of poor material from cut to be
taken to spoil etc. Derive also the quantities of rock to be excavated in each 3 km section, and
where it will be used. Present quantities all in cubic metres.
o The above table assumes items for removal of top soil outside existing alignment have been
included in software design parameters. If not, the above figures will have to be adjusted to allow
for reduced common cut through removal of topsoil.
o Prepare and include Detailed Quantity Take-off sheets [QTS] to demonstrate precisely how
individual pay item quantities were developed. Details presented in the form of an ‘earthworks’
report to be considered.
Note: In the Factual Soils and Materials report, which does not form part of the contract [but
may be displayed to Bidders for reference purposes] no precise indication of assumed
quantities for “cut-to-fill”, “borrow to fill”, “cut-to-spoil”, “unsuitable” materials, “rock from
cut” or “rock from quarry” are to be shown.
Factual Report
o Present in the Factual Report a table as the example below with just the three items per 3 kms.
Considerable variations between re-measured earthworks quantities and those in the contract
Bill of Quantities occur frequently as a result of incorrect assumptions in design parameters
used in software design and engineering quantity estimates; (e.g safe angles of cut slopes and
embankment slopes and safety zones, percentages of cut material that can be used in
improved sub grade and filling layers, estimated quantities of rock excavation and even
estimates of rock that is unsuitable for use in embankments).
One advantage offered by higher embankments is the reduced need for improved subgrade
where existing subgrade strengths are below selected design levels. However where low or no
embankments are to be constructed, the need for excavating soft subgrade materials to spoil
and replacing with improved subgrade material (usually type G15) can arise.
The following tables may be used to assess the likelihood of such variations occurring during
construction, giving the DC the opportunity to either reconsider the quantities, making some risk
provision, or to reassess the vertical alignment of the proposed road.
Alternatively, some further research, sampling or laboratory triaxial testing may enable cut
slopes to be amended, affecting the overall excavation quantities.
o The DC should provide drawings showing typical cross sections for every construction
scenario likely to be experienced in construction, showing any variations in pavement
layer thickness and cross section dimensions. The drawings should illustrate deep cut
and high fill situations and for any special treatments needed [e.g. at swamps, widening
to accommodate guardrail posts on embankments or for added lane width on curves
etc]. The consultant should include an illustration that shows several typical cases
together with the site investigations to be checked at each.
o DC also to indicate the specific areas - by chainage limits - where special details will be
required such as in Trading Areas, swamps. This data could be presented in tabular
form but details such as boundary fencing/walls, pedestrian and vehicular access
provisions, bus bays and parking areas, pedestrian control barriers etc should be
detailed on drawings.
o More details provided at design stage and measured in the BOQ will reduce the quantity
of extra items to be designed by the SE and included as extras in the overall total cost.
o DC also to indicate proposed treatments for side slopes to resist surface runoff erosion,
ground water ingress etc.
o DC to advise how and where he made additional allowance for runoff from side roads
(can be large volumes) and for its connection to the longitudinal drainage system on the
main route. Forms 8.2.a,b and c in Annex 8 of the Design Guidelines assist in calculating
such runoffs and also the carrying capacity of the receiving drains.
o Where covered drainage ditches and catchpits are used for urban drainage systems,
design must be strong, thorough and appropriate. Standard components to be used
where possible. In addition agree early with UNRA the need (and cost) of such drains.
o DC should note all existing 600 mm dia. Cross culverts are to be replaced.
o DC must have identified borrow areas and aggregate sources in terms of location and
accessibility, potential yield, stabilization needs (e.g. lime, cement, gravel, sand).
o Include plan and borrow area utilisation diagram in the Soils and Materials Report as
illustrated in Figures 6.5 and 6.6 in Annex 6 of the Design Guidelines.
o Haulage costs must be considered carefully, particularly where the distance between
borrow or quarry areas is high. DC should calculate the haulage required on all borrow
materials and materials brought to the site from some distance (e.g. cement). Alternative
pavement designs may need consideration in such circumstances.
o The DC must justify how the traffic loading classification[s] was derived and allowances
made for diverted traffic. Analysis should consider high and low scenarios as well as
look at effects of different over-loading and legislation situations.
o The DC must also explain how the homogenous sections were established [e.g. by
forecast traffic class, by sub-grade strength class derived from test programs etc. or any
other criterion].
Note: the use of a very limited number of homogenous sections may lead to
inappropriate layer thicknesses being used in some sections of the route.
o The adopted design chart from RDM volume must be defined and any alternative design
method[s] used in cases where traffic or sub-grade strength classes are outside the
range of the charts.
Sub-base Type??
Stabilised??
Improved Sub-grade
Grades and Quantity
The DC is to identify any ‘difficulties’ that Contractors will face that could extend the construction
process. These could include:
- access restrictions e.g. from one end of job only;
- access to be provided to other Contractors working in the same area;
- competition for borrow and aggregate sources from other Contractors working in the
area;
- areas subjected to high volume rainfall [say, ?? days / year];
- delays in utility relocations [e.g. due to owners’ work schedules, order times for
materials etc].
See Alternative Table below for analysis and mitigation of risks in earthworks quantities
ANNEX 16
Suggested Format for Report on Works Contract Review
Executive Summary
1. Table of Contents
7. Detailed Review of Design using Checklist and suggested Additional Comment sheets