Vous êtes sur la page 1sur 38

ANALYSIS OF RATES

STANDARD CALCULATION FOR BRICK WORK AND MORTAR

Assuming a 30 cm brick wall of area 100m2

Vol. of B/W = 100x30/100 = 30m3 (Nominal)

Actual volume = (29/100)x100 = 29 m3

Vol. of one symmetrical brick (i.e. with mortar)

= 0.20x0.10x0.10

= 2000x10-6 m3

(or vol. of one standard or madular brck)

Nos. of bricks in 29m3, volume = 29/2000x10-6 = 14500 nos.

Nos. of bricks for 1 m3 of B/W = 14500/30x1

= 484 nos.

Adding 5% for loose, breakage etc.

For 10m3 of B/W, nos. of bricks = 5000 nos.

9″x4.5″x3″ → traditional brick

22.9 x 11.4 x 7.6 cm → 1984.056 cm3

20x10x10 = 2000 cm3

Cement Mortar

Vol. of cement mortar (set) = 29 – (14500 x 0.19 x 0.09 x 0.09)


= 6.85 m3

Adding 15% extra for filling of frog,

Unevnness of bricks and wastage/looses

Vol. of C.M. reg. = 6.685x1.15

= 7.688 m3

Taking allowances for dry/loose vol. of C.M. as 25%

 Dry/loose vol. of CM = 7.688 x1.25

= 9.609 m3 (for 30m3 of B/W)

 Dry/loose vol. of C.M. for 10m3 B/W

= (9.609/30) x 10

= 3.2 m3

For 100m3 of B/W dry/loose vol. of C.M. = 32m3

Or 32% of B/W
 EARTHWORK IN EXCAVATION IN FOUNDATION INCLUDING

(FILLING) UP TO TRENCH) UNIT -100 CUM.

Take 100m3 (of work)

Particulars Quantity Rate (Rs) Cost (Rs)

Materials

Labours, etc.

Mistri (Mason) ½ No. 380/no/d 190

Mazdoor (Beldar) 44 nos. 200/no./d 8800

Sundries, T&P etc. Lump sum 120 L.S. 120

Total of Material and Labour = 9110

Add 10% contractor’s profit = Rs. 911

Grand total = Rs. 10,021

 Rate per m3 = 10021/100 = Rs. 100.21

 1:5:10 CEMENT CONCRETE BLOCK 9 INCH THICK IN

FOUNDATION

Take – 10 cum.

Taking allowances for dry/loose volume as 52%

Total dry/loose volume = 10+5.2

= 15.2 m3
Cement = 
15.2 
 x1 = 0.95 m3
 1  5  10 

$ No. of bags of cement = 0.95x30

= 28.50 bags

Sand  
15.2 
 x5 = 4.75 m3
 1  5  10 

1st class brick ballast = 


15.2  3
 x10 = 9.50 m
 1  5  10 

Particulars Quantity Rate (Rs) Cost (Rs)

Materials

Cement (0.95m3) 28.5 bags 300/bag 8550

Sand (white) 4.75m3 671/m3 3187.25

1st class brick ballast 9.50 m3 1236/m3 11742

(40mm gauge)

Labour etc

Mistri (Mason) 2 nos. 380/no/d 760

Mazdoor (Beldar) 30 nos. 200/no./d 6000

Sundries, T&P etc. Lump sum 120 L.S. 120

Total of materials and labour = Rs. 30395.25

Adding 10% contractor’s profit = Rs. 3039.52


Adding 1.5% of water charges = Rs.455.93

Grand Total = Rs.33890.7

 Rate per m3 = 33890.7/10 = Rs. 3389


 1ST CLASS BRICK WORK 1:8 CEMENT SAND

MORTAR IN FOUNDATION UP TO PLINTH

Taking 10m3

As the no. of bricks for 1m3 = 500 nos.

No. of bricks for 10m3 of B/W =500x10 = 5000 nos.

Dry/loose volume of cement mortar for 10m3 of B/W = 3.2 m3

Therefore,

Cement 
3 .2 
 x1 = 0.35 m3
1 8 

No. of bags = 0.35x30 = 10.66 bags = 11 bags

White sand = 
3.2 
 x8 = 2.84 m3
1 8 

Particulars Quantity Rate (Rs) Cost (Rs)

Materials

1st Class Brick 5000 nos. 7000/1000 nos. 35000

Cement (0.35m3) 11 bags 300/bag 3300

Sand (white) 2.84 m3 671.08/m3 1905.86

Labour etc

Mistri (Mason) 7½ 380 /no/d 2850

Mazdoor (Beldar) 14 nos. 200/no./d 2800


Sundries, T&P etc. Lump sum 120 L.S. 120

Total of materials and labour = 45975.86

Adding 10% contractor’s profit = Rs.4597.58

Adding 1.5% of water charges = Rs.689.637

Grand Total = Rs.51263.077

 Rate per m3 = 51263.077/10 = Rs. 5126.3077


 EARTHWORK IN FILLING TO RAISE THE LEVEL

OF GROUND UPTO PLINTH – UNIT M 3

Taking 100 cum.

Particulars Quantity Rate (Rs) Cost (Rs)

Materials

Labours, etc.

Mistri (Mason) ½ No. 380/no/d 190

Mazdoor (Beldar) 175 nos. 200/no./d 35000

Sundries, T&P etc. Lump sum 120 L.S. 120

Total of Material and Labour = 35310.00

Add 10% contractor’s profit = Rs. 3531/-

Grand total = Rs. 38841 /-

 Rate per m3 = 38841/100 = Rs. 388.41


 2.5 CM. THICK DPC (DAMP PROOF COURSE)

WITH 1:2:4 CEMENT CONCRETE – UNIT M2

Taking 100 sqm.

Volume of cement concrete =   x100 = 2.50 m3


2 .5
 100 

Adding 10% extra for unevenness of base, wastages etc.

Vol. of cement concrete = 2.50 x 1.1

= 2.75 m3

Dry/loose vol. of cement concrete = 2.75x1.52

(Taking allowances as 52%) = 4.18 m3

Cement 
4.18 
 x1 = 0.59 m3
1 2  4 

No. of cement bags = (0.59x30)

= 17.7 bags = 18 bags

Sand (Mooram) = 
4.18  3
 x 2 = 1.18 m
1 2  4 

Stone ballast (20 mm gague)  


4.18 
 x4 = 2.36 m3
1 2  4 

Cem-seal or impremo = 1kg per bag of cement

= 1x18 = 18 kg
Particulars Quantity Rate (Rs) Cost (Rs)

Materials

Cement (0.59m3) 18 bags 300/bag 5400

Sand (Mooram) 1.18m3 671.08/m3 791.87

Stone ballast (20 mm 2.36m3 1660.04 /m3 3917.69

gauge)

Cem-seal or impermo (1 kg 18 kg 120/kg 2160

per bag of cement)

Labours

Mistri (Mason) 10 ½ nos. 380/no/d 3990

Mazdoor( Beldar) 12 nos. 200/no/d 2400

Forms in sides Lump sum 120 L.S. 120

Sundries, T&P etc. Lump sum 150 L.S. 150

Total materials and Labours = 18929.56

Adding 10% contractor’s profit = Rs. 1892.95

Adding 1.5% water charges = Rs. 283.94

Grand total = Rs. 21106.45

 Rate per m2 = 211.06


 R.C.C. WORK IN COLUMN 1:1½ : 3 - UNIT 1M3

Taking - 10m3

Taking allowances for loose/dry conc. = 52%

Dry loose vol. of conc. = 10x1.52 = 15.2m3

cement =  
1.52
   1  2.76m  2.76  30  83bags
3

 1  1.5  3 

Sand = 
5.2 
  15  4.14m
3

 1  1.5  3 

Stone aggregate = 
5.2 
  3  8.28m
3

 1  1.5  3 

Steel: -

1% steel = 0.1m3

M
f   M   .vol.  78.5q / m 3  0.1m3  7.85q
vol.

So for column taking 2%

2% steel = 15.7 q

15.7  0.2
Binding are = 2% of total steel =  0.0314q
100
Particulars Quantity Rates (Rs.) Cost (Rs.)

Materials:

Cement (2.76m3) 83 bag 2.76m3 300/bag 24900.00

Coarse sand 4.14 777.04/m3 3216.94

Stone ballast 8.28m3 1660/m3 13745.13

M.S bars @ 2/- 15.7q 5000/q 78500

Binding wire 0.0314q 50/kg 157

Total= 120519.07

Labour

Mason 3 nos. 380/no/d 1140.00

Mazdoor 56 nos 200/no/d 11200.00

Sundries L.S. 120 L.S 120.00

Black smith 12 nos. 400/no/d 4800.00

T&P L.S. 150/- 150.00

Carpenter 10 nos. 400/no/d 4000.00

Timber planks and ballies L.S. 600 L.S. 600.00

T&P L.S. 150 L.S. 150.00

Total = 22160

Total of materials and labours = Rs. 142679.07

Adding 1 ½ % water charges = Rs. 2140.18


Adding 10% contractor’s profit = 14267.9

Grand total = Rs. 159087.15

 Rate per m3 = Rs. 15908.715


 1ST CLASS BRICK WORK IN SUPER STRUCTURE

WITH 20X10X10 BRICK WORK 1:6 CEMENT

SAND MORTAR - UNIT 1M3

Taking - 10m3

No. of bricks for 10m3 = 5000 nos.

Dry/loose vol. of cement mortar for 10m3 = 3.2 m3

cement = 
3.2 
   1  0.45m  0.45  30  135bags
3

1 6 

Sand = 
3.2 
  6  2.74m
3

1 6 
Particulars Quantity Rates (Rs.) Cost (Rs.)

Materials:

1st class brick 5000 nos 7000/- 35000.00

Cement (0.45 m3) 13.5 bag 300/bag 4050

Sand coarse 2.74 m3 777.04/m3 2129.08

Total = 41179.08

Labour

Mason 10 nos. 380/no/d 3800.00

Mazdoor 17 nos 200/no/d 3400.00

Scaffolding L.S. 200 L.S 200.00

Sundries T&P L.S. 120 L.S. 120.00

Total = 7520.00

Total of material and labour = Rs. 41179.08

Adding 1 ½ % water charges = Rs. 617.68

Adding 10% contractor’s profit = Rs. 4117.90

Grand total = Rs. 45913.85

 Rate per m3 = Rs. 4591.38.


 WOOD WORK IN CHAUKHAT OR FRAME - UNIT 1M3 (TEAK

WORK)

Taking frame of (210x120) cm door of (18x12)cm section

Particulars Quantity Rates (Rs.) Cost (Rs.)

Materials:

Timber 5.98x0.8x0.12 0.053m3 63576/m3 3369.528

(L=2x2.14+1x1.2=5.48)

Wastage 5% 0.003m3 63576/m3 190.728

Total = 3560.257

Labour

Carpenter 13/16 400/no/d 325

nos.

Helper ½ nos. 200/no/d 100.00

Sundries T&P L.S. 150 L.S. 150.00

Total = 575

Total of material and labour = Rs.4135.257

Adding 10% contractor’s profit = 413.52

Grand total = Rs 4548.77

 Rate per m3 = Rs. 454.87


 12 MM CEMENT PLASTERING IN CEILING 1:3 WITH COARSE

SAND

Taking - 100m3

Taking area = 100m2

t = 12 mm = 0.012 m

Volume = 1.2 m3

Adding 20% extra for unevenness of base joints and wastages, etc.

Vol. of cement mortar reqd. 1.44 m3

 Dry loose vol. of C.M. = 1.44x1.52 = .8m3

(Taking 25% allowance)

= 
1.8 
 Cement   1  0.45m  0.45  30  35bags
3

1  3 

Coarse sand = 
1.8 
  3  1.35m
3

1  3 
Particulars Quantity Rates (Rs.) Cost (Rs.)

Materials:

Cement (0.45m3) 13.5 bag 300/bag 4050

Coarse sand 1.35m3 777.08/m3 1049

Total= 5099

Labour

Mason 12 nos. 380/no/d 4560.00

Mazdoor 15 nos 200/no/d 3000.00

Scaffolding, T&P sundries L.S. 200 L.S. 200.00

etc

Total = 7760.00

Total of material and labour = Rs. 12859

Adding 1 ½ % water charges = Rs. 192.885

Adding 10% contractor’s profit = Rs. 1285.9

Grand total = Rs. 14337.78

 Rate per m2 = Rs. 143.37


 TOR STEEL REINFORCEMENT @ 1% OF R.C.C. WORK UNIT – 1

CU.M.

Taking 10m3

Particulars Quantity Rates (Rs.) Cost (Rs.)

Materials:

Steel , Mild steel bar @ 1%

= 1.0 cum @ 8.5 q/cum

= 7.85 q

Per 10 cum 7.85q 5000/q 39250.00

Binding wire 1.50 kg 50/kg 75.00

Labour

Black smith 8 nos. 400/no/d 3200

Mazdoor 8 nos 200/no/d 1600.00

T&P etc. L.S. 150 L.S. 150.00

Total = 44275

Total of labours and materials or (bending and binding of steel

= Rs. 44275.00

Adding 10% contractor’s profit = 4427.50

Grand total = Rs. 48702.5


 Rate per m3 = Rs. 487.02

 MILD STEEL FRAMES OF DOORS AND WINDOWS OF (35X35X5)

MM ANGLE SECTION:

Taking a frame of (1200x2100) sq.m. door of (35x35x5) mm angle section of mild

steel

Length = [2x(2.1+0.04)+(1x1.2)] = 5.48 m (Taking 4 cm insertion into the ground

Quality = 5.48x2.61 @ kg/m

= 14.3028 kg

Particulars Quantity Rates (Rs.) Cost (Rs.)

Labours:

Black smith 1st class ¾ nos. 400/day 300.00

Helper ½ nos. 200/day 100.00

Sundries T&P etc. L.S. 150/L.S. 150.00

Total= 550

Total of materials and labours = Rs. 550

Adding 10% contractor’s profit = Rs. 55

Grand total = Rs. 605

 Rate per door frame = Rs. 1200

 Rate per quintal = Rs. 6000.00


 R.C.C. work in (M20 GRADE) in beam, slabs and lintels Unit- 1cu.m

Taking - 10m3 grade = M20 (1:1 ½ : 3)

Taking 52% extra dry volume

Thus dry volume = 15.2 cum

Material calculation

Cement = 
152 
 1  2.8cu.m  84bags
 1  1.5  3 

Coarse sand =  
15.2
 1  4.2cu.m
 1  1 . 5  3 

Stone ballast = 
15.2 
  3  8.4m
3

 1  1.5  3 

Particulars Quantity Rates (Rs.) Cost (Rs.)

Materials:

Cement (84 bag) 2.8m3 300/bag 25200.00

Coarse sand 4.2 m3 777.08/m3 3263.73

Stone ballast (20mm gauge) 8.4m3 1660.04/m3 13944.336

Total= 42408.066

Labour

Mason 3 ½ nos. 380/no/d 1330.00

Mazdoor + (Water man) 35+2=37 200/no/d 7400.00

Sundries T&P L.S. 150 L.S 150.00


Timber planks and balies L.S. 200 L.S. 200.00

Carpenter IInd class 10 Nos. 300/- 3000.00

Mazdoor 10 nos. 200/no/d 2000.00

Nails L.S. 300 L.S. 300.00

T&P L.S. 150 L.S. 150.00

Total = 14530

Total of materials, labours & centering and shuttering = Rs. 56938.066

Adding 1 ½ % water charges = Rs. 854.07

Adding 10% contractor’s profit = Rs. 5693.80

Grand total = Rs. 63485.936

 Rate per 1 cum = Rs. 6348.59


 TEAK WOOD WORK IN DOOR AND WINDOWS SHUTTER

GLAZING IN WINDOW SHUTTERS:

Taking a door shutter 1064x2032 mm = 2.162m2

Particular/ details of No. L B/W Thick Quantity Rate Cost

items (m) (m) (m) (Rs.) (Rs)

Materials

Timber:

Style 04 2.032 0.10 0.04 0.0325

Top rail 01 1.064 012 0.04 0.051

Freeze rail 01 1.064 0.12 0.04 0.051

Lock rail 01 1.064 0.18 0.04 0.0077

Bottom rail 01 1.064 015 0.04 0.0064

Pannels total sum of 01 1.534 0.724 0.025 0.0278

length and breadth

L=203.2-(2x12)

(18+15)+(6x1.2)=153.4

= 1.534 m

B=(106.4+1.2)-4x10

+4x1.2=72.4=0.724 m
Insertion = 1.2 cm

Central overlap= 1.2cm

Total 0.0846

Adding 5% for wastage 0.002

Grand total 0.0888 63576 5645.55

cu.m /m3

S.No. Particulars Quantity Rates Cost (Rs.)

(Rs.)

Brass fitting

Tower bolts (30cm) upper 1 no. 30/no. 30.00

Tower bolts (35cm) lower 1 no. 20/no. 20.00

Hinges (10cm) 6 nos. 15/no. 90.00

Brass handle 2 nos. 45/no. 90.00

Wooden cleat 2 nos. 15/no. 30.00

Hinges 2.5 cm (for wooden 2 nos. 15/nos. 30.00

cleat)

Screw (40mm) 20 nos. 1/no. 20.00

Screw (20 mm) 80 nos. 0.50/no. 40.00


Sliding bolt L.S. 60 LS 60.00

Labour

Carpenter I-class 1/15 nos. 400/no/d 26.66

Carpenter II-class 4 nos. 300/no/d 1200.00

Helper 2 nos. 200/no/d 400.00

Putty, glues etc L.S. 150 L.S. 150.00

Sundries T&P L.S. 150 L.S. 150.00

Total = 2336.66

Total of materials, labours & fittings = Rs. 2336.66

Adding 10% contractor’s profit = Rs. 233.66

Grand total = Rs. 2570.32

 Rate per sq.m. (for doors) = Rs. 1188.86

Taking a window shutter 100x150 cm, (area = 1.5 m2)

Particular/ No. L B/W Thick Quantity Rate Cost

details of items (m) (m) (m) (Rs.) (Rs)

Timber:

Style 04 1.5 0.075 0.04 0.018

Top & bottom rail 2 1.0 0.075 0.04 0.006

Sash bars verticals


(15mm insertion)

L=150- 2 1.38 0.04 0.04 0.004

(2x7.5)+(2x1.5)

= 1.38 m

Sash bar

horizontal

(15mm insertion)

L = 50- 6 0.38 0.04 0.04 0.004

(2x7.5)+(3x1.5)

= 38cm = 0.38m

Total 0.032

Add 5% for 0.002

wastage

Grand total 0.034 63576 2161.58

cum /m3
Particulars Quantity Rates (Rs.) Cost (Rs.)

Fittings

Tower bolts (30cm) upper 1 no. 30/no. 30.00

Tower bolt (15cm) lower 1 no. 20/no. 20.00

Hinges (10cm) 4 nos. 15/no. 60.00

Brass handle 1 nos. 50/no. 50.00

Wooden cleat 2 nos. 15/no. 30.00

Hinges 2.5 cm (for wooden cleat) 2 nos. 15/nos. 30.00

Screw (40mm) 20 nos. 1/no. 20.00

Screw (20 mm) 50 nos. .50/no. 25.00

Glass panels 16 nos x 18.5 x 33.75 1.0 2 40/sqft 430.40

cm = 1.0 m2

B=1/2[50-2x7.5-1(2x1.5)]

= 18.5 cm

HT = ¼[150-(2.75)-(3x1)+ (2x1.5)

= 33.75 cm

Putting, glues & nails for fixing L.S. 25.00 25.00

Labours

Carpenter I-class 1/15 400/nos. 26.66

Carpenter II-class 2 nos. 300/no/d 600.00


Helper 1 nos. 200/no/d 200.00

Putty, glues etc

Sundries T&P L.S. 150 L.S. 150.00

Total = 1697.00

Total of materials, labours & fittings = Rs. 3858.58

Adding 10% contractor’s profit = Rs. 385.85

Grand total = Rs. 4244.43

 Rate per m3 = Rs. 2829.62


 PLASTERING ON WALLS WITH 1:5 CEMENT SAND MORTAR

(OUTSIDE & INSIDE) UNIT-1M3

Taking - 100m3

Thickness of plaster = 12 mm

Volume of cement mortar = 100x0.012 = 1.2 m3

Adding 30% extra for filling joints unevenness etc

Volume of cement mortar = 1.2x1.3 = 1.56 m3

Taking allowances for loose/dry vol. of mortar as = 25%

Dry/loose vol. of cement mortar= 1.56x1.52 = 1.95m3

= 2.0 m3

Cement = 
 2.0 
  1  0.33m  10bags
3

1 2  3 

Sand (Fine) = 
2.0 
  3  1.0m  1.0bags
3

1 2  3 

Sand (Coarse) = 
2.0 
  2  0.67
1 2  3 

Particulars Quantity Rates (Rs.) Cost (Rs.)


Materials:

Cement (10 bags) 0.333m3 300/bag 3000.00

Fine sand 1.0 m3 671.08/m3 671.08

Coarse sand 0.67m3 777.04/m3 52.06

Total= 3723.14
Labour

Mason 11 nos. 380/no/d 4180.00

Mazdoor 20 nos 200/no/d 4000.00

Scaffolding L.S. 500 L.S 500.00

Sundries T&P L.S. 150 L.S 150.00

Total = 8830.0
Total of materials and labours = Rs. 12553.14

Adding 1 ½ % water charges = Rs. 188.29

Adding 10% contractor’s profit = 1255.31

Grand total = Rs. 13996.74

 Rate per m3 = Rs. 139.96


 MOSAIC FLOORING OVER BASE CONCRETE 1:2:4 (CEMENT,

COARSE SAND, STONE AGGREGATE)

Taking – 100m2

6 mm thick mosaic layer 1: 1 ½ over 7.5 cm thick cement concrete (1:2:4)

Total dry vol. of materials for cement concrete = 12.4 m3

(with allowances 53% & 10% for voids and unevenness respectively)

Cement = 
 12.4 
  1  1.8m  54bags
3

1  2  4 

Coarse Sand = 
12.4 
  2  3.5m
3

1 2  4 

Sand (Coarse) = 
12.4 
  4  7.1
1 2  4 

Total dry vol. of materials for 6 mm thick mosaic layer

(with allowances 50% & 20% for voids and finishing and cutting respectively) =

1.08 m3

Cement = 
1.08 
 1  0.43m  12.9bags
3

 1  1.4 

Marble chips = 0.43 x 1.5

= 0.65 m5
Particulars Quantity Rates (Rs.) Cost (Rs.)

Materials:

75 mm CC. (1:2:4)

Stone ballast 12 mm gauge 7.1 m3 1660/m3 11786.284

Coarse sand 35m3 777.04/m3 27196.4

Cement (54 bags) 1.8m3 300/bag 16200

6 mm mosaic (1:1 ½ )

Cement (12.9 bags) 0.4 m3 300/bag 3870

Marble chips (3mm gauge) 0.65m3 3000/m3 1950

Marble dust 0.04m3 1500/m3 60

Labours

Mason 21 nos. 380/no/d 7980

Beldar 20 nos 200/no/d 4000.00

Polisher 120 nos. 200/no/d 24000.

Polishing stone L.S. 150 L.S 150.00

(carborndom)

Axalic acid powder L.S. 100/- 100

Side forms L.S. 120/- 120

Sundries T&P etc. L.S. 150/- 150

Total of materials and labours = Rs. 97562.68


Adding 1 ½ % water charges = Rs. 1463.44

Adding 10% contractor’s profit = 9756.26

Grand total = Rs. 108782.38

 Rate per m3 = Rs. 1087.82


 GLAZED TILE WORK IN KITCHEN AND TOILET UPTO DOOR

LEVEL UNIT – 1M2

Taking – 100m2

Glazed tile laid over 12 mm thick cement sand mortar

Total dry vol. of mortar = 2m3

Cement = 2/(1+3) = 0.5 m3 = (15 bags)

Coarse Sand = 0.5x3 = 1.5

Assuming size of tile = 150mm x 150 mm

No. of tiles = 100/0.15x0.15 = 4445 Nos.

Adding 5% extra for breakage and wastage etc.

No. of tiles req. 4445x1.05 = 4667.2 = 4670 Nos.

Particulars Quantity Rates (Rs.) Cost (Rs.)


Glazed tiles:
(15x15)cm (4670 nos.) 100 sqm. 25/piece 116750

Cement (15 bags) 0.50 m3 300/m3 4500

Coarse sand 1.5m3 777.04/m3 1165.56

Cement for tiles and joints 6 bags 300/bag 1800

Labours
Mason 16 nos. 380/no/d 6080

Mazdoor 15 nos 200/no/d 3000


Polisher 120 nos. 200/no/d 24000

Polishing stone L.S. 150 L.S 150.00

Axalic acid L.S. 100/- 100

Sundries T&P L.S. 150/- 150

Total 157695.56
Total of materials and labours = Rs. 157695.56

Adding 1 ½ % water charges = Rs. 2365.43

Adding 10% contractor’s profit = 15769.55

Grand total = Rs. 175821.54


 Rate per m3 = Rs. 1758.21
 WHITE WASHING AND COLOUR WASHING ON WALLS AND

CEILING (3 COATS) UNIT – 1M2

Taking – 100m2

Particulars Quantity Rates (Rs.) Cost (Rs.)

Materials:

1st White lime un slaked 30kg 8/kg 240

Glue powder L.S. 150 L.S. 150

Coloring pigment (10kg/kg) 300q 0.40 L.S. 120

Total = 510.00

Labours

White washer 1 ½ Nos. 300/d 450

Mazdoor 1 ½ Nos. 200/d 350

Sundries T&P L.S. 150 L.S. 150.00

Total = 950.00

Total of material and labour = Rs. 1460

Adding 10% contractor’s profit = 146

Grand total = Rs. 1606.00

 Rate per m2 = Rs. 16.06


 ROOF TERRACING WORK WITH BRICK TILE LAID OVER MUD

PHUSKA UNIT-1M2

Taking - 10m2

Mud phuska roofing 10cm thick below one layer of brick tile with two coat of

bitumen painting below mud phuska and tile one laid 1:3 cement mortar

No. of brick tile = 381 nos. for 10m2

Total dry material for mortar = 0.23 m3

Cement = 
0.23 
  1  0.05m  1.7bags
3

1  3 

Sand = 
0.23 
  3  0.1725m
3

1  3 

Particulars Quantity Rates (Rs.) Cost (Rs.)

Materials:

Brick tiles (23x12x4) 381 nos. 5000/d 1905

Cement (1.7 bags) 0.0575m3 300/bag 510

Sand (coarse) 0.1725m3 777.04/m3 134.039

Earth (loamy soil) 1.0m3 150/m3 150

Bhusa cow dung etc. L.S. 150L.S. 150

Bitumen 20kg 150/kg 3000

Labour
Mason 2 nos. 380/no/d 760

Mazdoor 5 nos 200/no/d 1000

Sundries T&P L.S. 150 L.S 150

Total = 5849.039

Total of materials and labours = Rs. 5849.039

Adding 1 ½ % water charges = Rs. 87.73

Adding 10% contractor’s profit = 584.9

Grand total = Rs. 6521.66

 Rate per m2 = Rs. 65.21

Vous aimerez peut-être aussi