Vous êtes sur la page 1sur 3

FRACTURING & STIMULATION

Open-hole completion system enables multi-stage


fracturing and stimulation along horizontal wellbores
By Rocky Seale, PackersPlus

DRILLING DEEPER AND hori-


zontally has become more viable in many
reservoirs. Successfully completing these
deeper gas reservoirs and horizontal
wells, however, is still a challenge the
industry faces on a daily basis. As drill-
ing technology continues to exploit these
more complex and unconventional res-
ervoirs, completion technology is being
designed and developed to effectively
fracture and stimulate multiple stages
along a horizontal wellbore.

The growth in multi-stage fracturing


has been tremendous over the last four
years due to completion technology that
can effectively place fractures in specific
places in the wellbore. By placing the Figure 1 (above) illustrates the drillability of the FracPort seats, showing that eight seats
fracture in specific places in the horizon- were drilled out in 3.5 hours. Figure 2 (below): A variation of the StackFRAC system
tal wellbore, there is a greater ability to allows the intermediate casing string to be eliminated.
increase the cumulative production in a
shorter time frame. become the field development method of ted or perforated liner. These designs
choice in many cases. However, certain were inflexible in fracturing options,
This article details an
limiting technologies in the completion of and they didn’t address the requirement
open-hole completion
horizontal wells have slowed that growth for mechanical diversion as evidenced
system run as part of
in some reservoir applications. These by microseismic data obtained during
the production liner
have been reservoirs that require specif- horizontal limited-entry treatments
that does not require
ic fracturing treatments at certain inter- conducted in various reservoirs. Thus,
cementing and provides
vals to make them economic to produce. beginning in 2000 and continuing over
mechanical diversion
Vertical stimulation techniques, such two years, various product components
at specified intervals,
as limited entry and bullheading, have and systems were tested and deployed
thus allowing fractur-
proven no more beneficial compared in the field, leading to the StackFRAC
ing operations to be
with vertical wells. Post-production system.
effectively pumped to
analysis on the deliverability of horizon-
their targeted zone. It By developing a system to set in open
tal wells in reservoirs, such as matrix,
effectively eliminates hole, provide mechanical diversion and
heterogeneous and non-conventional
the need for cementing allow multiple fractures to be performed
formations, have shown a direct correla-
the production zone to along the entire horizontal wellbore,
tion to the completion and stimulation
establish mechanical problems with open-hole horizontal com-
methods employed and the subsequent
diversion as desired, pletions to date were addressed, with the
shortcomings when applied to horizontal
which can take weeks to added benefit of cost and time savings
wellbores. Thus, the additional econom-
complete at high costs due to its efficiency.
ics required to drill a horizontal well in
and elevated mechanical
these applications have not been justi- The mechanical open-hole packer system
risks and causing deeper
fied by the equivalent or slightly better is capable of withstanding high differ-
reservoirs to become
production results compared with verti- ential pressures, with fracturing ports
uneconomic to exploit.
cal wells. located between the packers. A series of
DEVELOPMENT Before the development of the these could be run simultaneously in the
StackFRAC system, the only options well on a liner, and the fractures could
Horizontal drilling has be pumped in continuous succession.
advanced significantly for completing an open-hole horizontal
well was either barefoot or using slot- This eliminates the problems encoun-
over the last decade to tered when cementing horizontal liners

112 July/August 2007 D R I L L I N G CONTRACTOR


FRACTURING & STIMULATION

in place. It also eliminates the need for 8 ½-in. open-hole, the standard comple- tions in the liner could be removed,
repeated CT intervention into the well tion is 7 in. or 5 ½ in., so the mechanical allowing full access to the toe of the well-
for setting and removing composite properties of the FracPort were designed bore for standard operations associated
bridge plugs, running perforating guns, to exceed 7-in. 29 ppf and 5 ½ in. 17 with CT, logging, flow testing, etc., to
and the repeated rigging up and down of ppf P-110 liner properties, respectively. be carried out. A design was developed
the fracturing or stimulation equipment. Thus, the flow area of 7-in. 29 ppf liner through investigation of metallurgical
is 30.04 sq in with a tensile strength of properties cross referenced to drillability
By using continuous pumping on all the just over 750,000 lbs and burst and col- with carbide mills.
fractures intervals, the pumping equip- lapse pressures around 10,000 psi. The
ment needs to be rigged up and down 7-in. FracPort has a 25% larger flow area To qualify the various size FracPort
only once, saving time and money and than the liner, while maintaining the ten- seats, prototype equipment was built
reducing the associated HSE hazards. sile strength of over 750,000 and having using the same geometric configurations
a burst and collapse pressure of 10,000 as had been proven with the Standard
SYSTEM DEVELOPMENTS psi. This same design concept holds true FracPort. After function testing, a sur-
for all sizes from 2 3/8-in. to 7-in. tools for face milling test was performed to estab-
After identifying the deficiencies in lish the optimum drilling parameters of
open-hole horizontal completion and hole sizes ranging from 3 ¾ in. to 12 ¼
in., while every component in the system the seat in conjunction with a specified
fracturing options, a development was mill design. The drillability of the seats
initiated to provide a viable solution with is rated to 10,000 psi working pressure.
has been quantified in the field by drill-
the same attributes of a cemented and The next design step was to determine ing out over 500 seats. Through this field
perforated completion using composite the activation process for the FracPort. data, the drilling parameters and opera-
plugs for mechanical isolation. Based on With operational functionality and effi- tions have been optimized. An example
the North American fracturing market, it ciency in mind, it was determined that of the drillability of the seats is dis-
was determined the differential pressure ball activation would be most reliable. played in Figure 1. As shown, eight seats
rating of the open-hole packers needed This would eliminate CT, slickline, wire- were drilled out in 3.5 hours, a perfect
to be 10,000 psi at temperatures up to line and other wellbore interventions example of how most seats are removed
450°F and set in holes enlarged up to to accomplish the desired number of when using CT and motor.
40%, while conforming to hole irregulari- fracs. After dropping the ball, it could be
ties, including ovalities, washouts, etc. pumped down in the flushing fluid of the RE-CLOSABLE FRACPORT
Additionally, it was determined that the previous fracturing interval and land in
a specific seat to activate that FracPort A specific FracPort was designed and
mechanical packers must be hydrauli- built in 2003. This design incorporates
cally actuated and set. Analysis also for the next interval and provide a seal
on the seat to prevent treating the inter- the same design principles as used in
found a dual-element system was opti- both the Standard and Drillable ver-
mal for the higher pressures the packer vals below.
sions. However, it selectively allows the
would see from each direction. Thus, a Development of the ball seats within the FracPorts to be closed and re-opened.
patented redundant seal over a specified FracPort was an engineering challenge. A major limiting issue associated with
length was developed. The packer could The seats would be exposed to high current completion designs in cer-
therefore optimize the mechanical diver- pump rates with various fluids for frac- tain reservoirs is the inability to close
sion within each designed section length turing with high sand concentrations. off a horizontal section due to water
in any open-hole horizontal wellbore Therefore, the seats had to be designed encroachment or the ability to effectively
while being set hydraulically in tension to withstand the high erosional effects of re-stimulate without introducing smaller
or compression, be mechanically locked fracturing proppants. Extensive design tubulars, which in turn increases the
and yet limber enough to navigate higher and testing went into establishing not friction pressure and reduces the rate at
doglegs encountered in short-radius only the geometry of the seat but the which the frac can be pumped.
drilling environments. proprietary material specifications. The
balls and seats were then sized within The Re-Closable FracPort design allows
Equally critical to the system design was any number of sections to be closed to
development of the fluid placement meth- each system to allow the process to be
repeated numerous times on a single job. inhibit production from that zone, or all
od between the packers. The fracturing stages can be closed, leaving only the
system had to be designed to selectively Based on the open-hole diameter and
liner size, up to 18 stages can be pumped last one open, and the well can be re-
open at specific times and, once open, fractured as it was initially, by dropping
withstand the abrasive fracturing fluids into a horizontal wellbore at one time.
balls and pumping specifically designed
for extended periods of time. Initial lay- fracturing treatments for each specific
outs for the fracturing port (FracPort) DRILLABLE FRACPORT section of the horizontal well.
designed for the maximum flow area The next step was to apply the erosion
the system required while retaining
the desired tensile and compressive
resistance technology of the ball seats CASE HISTORIES
into a design that could be easily milled.
strengths as the standard parent liner By using a drillable material, all obstruc- In more than 600 installations of the
for the size in question. For example, in system, more than 3,000 stages have

D R I L L I N G CONTRACTOR July/August 2007 113


FRACTURING & STIMULATION

been fractured, covering more than The stated cost savings do not include
1.2 million ft of horizontal open hole. the benefit of early production. Further
Additionally, more than 200 million lbs to this, systems are increasingly being
of proppant have been pumped through deployed in both horizontal and vertical
StackFRAC systems in hole sizes from wellbores where the intermediate casing
3 ¾ in. to 12 ¼ in. and in various forma- string has been eliminated. This is pos-
tions such as sandstone, shale, lime- sible by using a variation of the system
stone, dolomite, chalk and coal. The that allows the upper portion of the liner
maximum number of stages currently to be cemented in place and leave the
possible is 18. The maximum continu- production interval open hole (Figures
ous pump time has been 26 hrs, and the 2 and 3). This has not only proven more
maximum pumping rate through a sys- efficient but has also saved hundreds of
tem has been 145 BPM. thousands of dollars in tubular costs.

In one eight-stage horizontal well, a Experience in running these systems has


record was set with 3.5 million lbs of Figure 3: Applying StackFRAC to vertical alleviated much of the initial concerns
proppant pumped. These systems are open hole wellbores allows zones to be about getting to TD, even when many
routinely deployed in horizontal wells isolated without cementing and allows have stated that it cannot be accom-
with open-hole sections of more than plished. As a result, many systems now
the long string to be cemented in place
4,000 ft in length, with the maximum hor- run the RockSeal Packers with blank
izontal well run in to date being 7,200 ft. back to surface for upper ground water pipe between to isolate faults, shales or
Recently, the system was deployed in an isolation. Once installed, the system ac- non-productive zones not requiring stim-
extended-reach well where the liner top commodates multiple zone stimulations in ulation. The number of stages incorpo-
was set at 17,100 ft MD and 7,100 ft TVD, a single operation. rated into each assembly also continues
and the shoe was set at 23,000 ft MD to grow, which coincides with the same
and 7,100 ft TVD. These records have allowing for larger ODs while manag- trend for all horizontal multi-stage jobs.
not only proven the system’s durability ing to navigate higher doglegs and then This, in combination with production
but also provided insight to the ability of function properly once on depth. trends from horizontal wells, is further
successfully running completion hard- evidence that mechanical diversion is
Certain aspects of the system vary
ware in the hole. proving effective.
compared with conventional operations.
The broad scope of applications should Fracture initiation pressure is nearly
also be noted: The systems have been always less than cemented and perfo- CONCLUSIONS
run consistently to depths ranging from rated applications due to the associated Horizontal drilling has grown rapidly
1,000 ft TVD to 18,000 ft TVD, and tem- skin, yet higher compared with open-hole over the last decade, but improvements
peratures up to 380˚F, mud weights in bullheading applications. The pressure can still have vast impact on reservoir
excess of 18 ppg as well as in the pres- variation of the system from stage to production and depletion. In 2000,
ence of H2S and CO2. stage has proven invaluable in determin- a technology gap was identified for
ing the effectiveness of the mechanical horizontal wells with open-hole comple-
On a comparative analysis, the deploy- diversion. What has been witnessed in tions, where mechanical diversion was
ment of the system takes 5% to 7% lon- the field is when the horizontal wellbore needed to effectively fracture sections
ger than running a standard liner assem- is partitioned, each compartment has a of the lateral. From these initial system
bly while providing mechanical isolation unique pressure signature for fractur- developments, the StackFRAC system
and the ability to initiate fractures at ing. This unique pressure signature for was spawned. The RockSeal Packer was
desired points along the horizontal well- each stage provides real-time evidence developed specifically to withstand the
bore. The time difference in deploying that the packers are providing the harsh environments encountered in the
the system, however, is more than made mechanical diversion for which they are high-pressure fracturing market. System
up by not having to cement the liner in designed. If the fracture was going past developments also included the FracPort
the well. the packer, then the pressures would be to be placed between the RockSeal
the same for the adjacent interval. The Packers to deliver effective fractures
The RockSeal Packers and FracPorts
exception to this is when the packers are along the horizontal wellbore.
are pre-assembled and tested prior to
run very close to one another in what is
being sent to location, thus expediting More than 600 successful systems have
referred to as a Focus Frac.
the deployment process and providing been deployed in horizontal open-hole
the ability to change the spacing of the For these applications, the fracture ini- wells. The system’s versatility is evident
fractures as required when the well tiation point is dictated by the packer in its application span and the ability
is completed. This allows for optimal placement rather than where the rock is to design the stage length at the rig site
spacing between the packers and the weakest. There has been microseismic and place the components to optimize
deployment of blank sections to isolate run to verify the fracture treatments are the fracture for a particular zone or seg-
sections that do not require fractur- going where intended. regate a nonproductive zone. By pump-
ing, such as a fault. The functionality ing fractures or stimulations in the hori-
is also prevalent in the ability of all the In nearly every field experience, the
zontal wellbore in one day, the well can
components in the system to navigate fractures have been pumped in a single
be placed on production weeks earlier.
high doglegs while maintaining minimal operation, taking less than a day to com-
diametrical clearances. As opposed plete, enabling cost savings of $150,000 This article is based on a presentation at the
and the completion coming on line more DEA Workshop, 19-20 June 2007, Galveston,
to standard open-hole packers, these
Texas.
packers are shorter and more flexible, than a week earlier.

114 July/August 2007 D R I L L I N G CONTRACTOR

Vous aimerez peut-être aussi